ARGYLL AND BUTE COUNCIL     POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD         15th February 2024 
CLIMATE CHANGE BOARD UPDATE & DECARBONISATION TRACKER 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council continues to address climate change themes through
its established Climate Change Board, and to take action informed by the
Decarbonisation Plan 2022-25 which is underpinned by the Decarbonisation
Tracker. 
1.2 Recent severe weather events in Argyll and Bute have confirmed the need to
focus upon adaptation to the unavoidable impacts of climate change. Use of
Adaptation Scotland resources and toolkits, and taking up membership of the
Public Sector Climate Adaptation Network, will support progress in
developing climate change adaptation plans. 
1.3 The annual Public Bodies Climate Change Duties Report for 2022/23 has
been submitted by Argyll and Bute Council. Headline data confirms that Argyll
and Bute Council’s carbon emissions for the reporting period has reduced to
26,512 tonnes of carbon dioxide equivalent, continuing the downwards trend
from 2015/16 baseline reporting year. 
1.4 The purpose of this report is to summarise and highlight some of the main
activities of the Climate Change Board over the previous quarter. 
2.0  RECOMMENDATIONS 
2.1 The Policy and Resources Committee are asked to note and consider the
updates contained at Section 5 of the report and full Decarbonisation Tracker
update attached at Appendix A.

Page 2

ARGYLL AND BUTE COUNCIL      POLICY & RESOURCES COMMITTEE 
CLIMATE CHANGE BOARD         15th February 2024 
CLIMATE CHANGE BOARD UPDATE & DECARBONISATION TRACKER 
3.0 INTRODUCTION 
3.1 The Climate Change Board reports progress to the Policy and Resources
Committee on a regular basis. This report outlines overarching activities of the
Climate Change Board to the Council and is useful to provide an update of key
contributors to the Council’s climate actions. The Council’s Decarbonisation Plan
2022-25 aligns with the Council’s main emissions sources, and maps out
actions required to achieve net zero by 2045. 
4.0 RECOMMENDATIONS 
4.1 The Policy and Resources Committee are asked to note and consider the updates
contained at Section 5 of the report and the full Decarbonisation Tracker update
contained within Appendix A. 
5.0 SUMMARY UPDATES OF CLIMATE CHANGE BOARD 
A - Climate Change Adaptation
5.1 Severe rainfall experienced across Argyll and Bute in October 2023 has
highlighted the seriousness of impacts and risks associated with climate
change. The region experienced a number of landslips, and significant surface
flooding impacting the road network, communities, business and access to
essential services. 
5.2 Adaptation to the unavoidable impacts of climate change is critical to ensuring
resilience to the projected changes in our weather. Climate projections for the
West of Scotland confirm that we are likely to experience:
• Warmer and drier summers
• Milder wetter winters, with less snow and frost

Page 3

• More severe rainfall events
• More variable weather
• Increasing sea levels
This creates challenges in safeguarding our buildings, assets, transport
infrastructure and ensuring the Council can continue to deliver essential
services when and where these are needed. In recognition of this, Argyll and
Bute Council identified climate change adaptation as one of the six themes
within its Decarbonisation Plan 2022 - 2025. 
5.3 In October 2023, Argyll and Bute Council was accepted to join the Public Sector
Climate Adaptation Network, facilitated by Adaptation Scotland. Through
participation with the Network, the Council will benefit from:
• Training and skills development covering topics such as risk
assessment, public engagement and project planning
• Advice and support on using the Adaptation Scotland Capability
Framework and Benchmarking Tool
• Opportunities to network and receive peer support 
• Space to reflect on learning and share experience with others
5.4 Argyll & Bute Council’s Climate Change Officer continues to progress work on
the Adaptation Scotland Starter Pack and Benchmarking Tool to review and
assess the Council’s climate change adaptation capabilities. Participation in the
Public Sector Climate Adaptation Network will support this process. 
B - Public Bodies Climate Change Duties Report
5.5 Public sector bodies play a key role in meeting Scotland’s climate change
legislation that sets out a key target date for net zero emissions for all
greenhouse gases by 2045. Public bodies are required to report annually on
compliance with climate change duties established under the Climate Change
(Scotland) Act 2009. Mandatory reporting commenced in 2015/16.
5.6 Argyll and Bute Council has completed and submitted the annual Public Bodies
Climate Change Duties Report for 2022/23. This was completed with data and
narrative input from cross-Council services and submitted to the Sustainable
Scotland Network ahead of deadline in November 2023. Headline data confirms
that the Council’s total carbon emissions for the year 2022/23 is 26,512 tonnes
of carbon dioxide equivalent (tCO2e). This represents a reduction of 1,705
tCO2e compared to 2021/22 total emissions (28,217 tCO2e). Further analysis
of the Council’s emissions data will be provided in a future Policy and
Resource’s Committee report.
5.7 Sustainable Scotland Network is currently completing a quality assurance
process across all Public Bodies Climate Change Duties Reports. An Analysis
Report identifying key trends and examples of good practice will be published
by Sustainable Scotland Network in Spring 2024.

Page 4

5.8 With regards to continuous improvement, the Council has shared its 2022/23
Public Bodies Climate Change Duties Report with North Ayrshire Council as
continuation of a reciprocal peer review process established last year.
Feedback from last year’s peer review process has informed this year’s
submission. 
C – Local Heat and Energy Efficiency Strategy (LHEES)
5.9 The Local Heat and Energy Efficiency Strategy (LHEES) aims to decarbonise
heat in buildings and improve energy efficiency across the local authority area.
The process involves local authorities identifying how each segment of the
building stock needs to change to meet national objectives, including achieving
zero greenhouse gas emissions in the building sector and removing poor
energy efficiency as a driver of fuel poverty. In addition, strategic
decarbonisation zones must be identified, and the necessary measures for
reducing building emissions within each zone must be outlined. Finally, the
LHEES must prioritise areas for delivery based on national and local policies.
The LHEES also provides a strategic plan for directing government funding and
private investment towards decarbonising heat. 
5.10 The process includes several stages, starting broadly and becoming more
focused and action-oriented. Please refer to Figure 1.
Figure 1: The LHEES process 
Due to tight timelines for the LHEES, the Council is collaborating with northern
Scottish councils through the HUB North network to attempt to reduce the time
required for each stage. 
5.11 The Council has completed the first three stages of the LHEES, namely the
Policy and Strategy Review, the creation of a Data and Tools Library, and the
identification of Strategic Zones and Pathways. Two additional stages, the

Page 5

Generation of Initial Delivery Areas and the Building Level Assessment, are
partially complete and the remainder is expected to be concluded by mid-
January. Stage 6 is currently in the planning phase, and stakeholder workshops
will take place in February, these workshops will assist us to finalise the delivery
areas. The final two stages are anticipated to be completed late /spring early
summer. 
D - Scottish Government Energy Efficient Scotland: Area Based Scheme
5.12 To date, since 1st July 2023, Argyll and Bute Council has spent £870,000 of a
£1,979,827 budget awarded by the Scottish Government Energy Efficient
Scotland – Area Based Scheme (ABS), insulating privately owned and privately
rented properties in mainland and island addresses.  
5.13 Non-means tested grants of between £9,000 and £21,000 are available to all
eligible households for the application of insulation, significantly reducing
household consumption of energy on a “Fabric First” basis and contributing
towards the Scottish Government carbon reduction targets.   Additionally, a
joint project in conjunction with Argyll Community Housing Association in Bute
and Tarbert was awarded a grant of £633,600. 
E - Carbon Neutral Islands Programme
5.14  The Scottish Government Carbon Neutral Islands project aims to support six
islands to become carbon neutral by 2040. The six islands participating in the
programme are Islay, Barra, Great Cumbrae, Hoy, Raasay and Yell. Each
island has completed carbon audits, developed community climate change
action plans and climate change investment strategies which will identify
learning and good practice that can be shared with other Scottish islands. 
5.15  Argyll and Bute Council will sit on the newly formed Local Authority Advisory
Group with the aim of supporting implementation of the Carbon Neutral Island’s
project, ensuring alignment and co-ordination with wider Local Authority
activity, and reciprocal sharing of information. 
F - 20 Minute Neighbourhoods
5.16 The Scottish Government defines the concept of 20 Minute Neighbourhoods
as: ‘where people can meet their needs within a 20 minute walk from their house
– enabling people to live better, healthier lives and supporting our net zero
ambitions.’
5.17 In support of both local businesses and the 20 Minute Neighbourhood concept,
the Council has continued to support the Argyll and Bute Gift Card. In the pre-
Christmas period, the Council ran a competition to design the next batch of
cards and promoted the Argyll & Bute Gift Card online.

Page 6

G – Argyll and the Isles Coast and Countryside Trust (ACT) Climate Change
Projects Update
5.18 Argyll and the Isles Coast and Countryside Trust (ACT) has established two
new projects complementing ongoing work on climate change:
• Argyll and Bute Climate Action – Community Planning Partnership
Climate Change Strategy 
• ABCAN (Argyll & Bute Climate Action Network) Hub, funded by the
Scottish Government
5.19 The purpose of the Argyll and Bute Climate Action – Community Planning
Partnership Climate Change Strategy project is to undertake a climate risk
assessment for Argyll & Bute as a region and to develop a Climate Change
Strategy and Action Plan comprising an integrated set of adaptation, mitigation
and engagement actions. Argyll & Bute Council with other Community Planning
Partnership partners have provided funding for a Project Manager for two years,
with a Steering Group drawn from the Climate Change Working Group of the
Community Planning Partnership. The Project Manager is employed by Argyll
and the Isles Coast and Countryside Trust (ACT), and started in post on 30
October 2023.
5.20 The emphasis of early phase activity has been to learn from existing initiatives
to inform development of a methodology appropriate to the specific needs of
Argyll and Bute and the timescale for the exercise. This will build upon and add
value to existing climate-related work and duties across the region rather than
replicate or replace activity. Next steps include an engagement programme,
continuation of audit and gap analysis, mitigation and adaptation risk and
opportunity methodology development. This project will continue to report in
detail to the Argyll and Bute Community Planning Partnership.
5.21 The new ABCAN Hub project will give a voice to community-led climate action,
help to co-ordinate activities and support communities in progressing towards
a net zero Argyll and Bute. Additionally, it will raise awareness of carbon
impacts, and mitigate key climate themes. With Scottish Government funding,
the ABCAN Hub project will establish a network of hubs based in each locality,
providing staff resource to co-ordinate and build on current climate activities,
deliver carbon literacy training, facilitate climate conversations, provide seed
funding for climate mitigation, engage with hard-to-reach groups and identify
opportunities for partnership working. The project is overseen by a collaboration
between ACT, Argyll & Bute Third Sector Interface and Time for Change Argyll
& Bute, and is part of ACT’s ongoing ACT Now project. The ABCAN Hub project
will ensure that Argyll & Bute has a cohesive approach to tackling climate
change in its communities.

Page 7

5.22 The ABCAN Hub project is ideally placed to support the Argyll and Bute
Community Planning Partnership Climate Action project with grassroots
engagement, alongside other Climate Action Hubs in Scotland. 
6.0 CONCLUSION
6.1 This report provides various updates in relation to the Council’s activities in
relation to Climate Change. 
7.0 IMPLICATIONS
7.1 Policy – Meeting obligations and commitment to Climate Change.
7.2 Financial – No direct linkage in this paper.
7.3  Legal – Meeting requirements of the Climate Change (Scotland) Act 2009, and  
the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019.
7.4  HR – None.
7.5  Fairer Scotland Duty: 
7.5.1   Equalities - protected characteristics – None. 
7.5.2   Socio-economic Duty – None. 
7.5.3  Islands – None.
7.6 Climate Change – Direct link updating activities of the Climate Change Board
and projects that will address climate change. 
7.7 Risk – Not addressing impacts or causes of climate change can lead to  
increased cost or censure if targets are not met.
7.8  Customer Service – None. 
Douglas Hendry, Executive Director with responsibility for Commercial
Services 
Policy Lead Climate Change & Environment, Councillor Ross Moreland 
15 January 2024                                                  
For Further Information:-
Ross McLaughlin, Head of Commercial Services 
Helensburgh and Lomond Civic Centre
ross.mclaughlin@argyll-bute.gov.uk

Page 8

APPENDICES
Appendix A – Climate Change Decarbonisation Tracker – February 2024

Page 9

Appendix A – Climate Change Tracker
ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
W1 –Develop and Implement Waste
Strategy 
(L) Roads and
Amenity Services,
Community,
commercial
customers
Implementation of
the Waste Strategy
transitioning to
Landfill ban
compliant Residual
Waste Recovery
solutions by 2025.
External funding and support being
sought from the Scottish Government
Please see Environment,
Development & Infrastructure
Reports – links below:
WASTE PPP UPDATE.pdf (argyll-
bute.gov.uk)     Waste Update – EDI
committee 1/6/2023
WASTE PPP UPDATE.pdf (argyll-
bute.gov.uk)    Waste Update – EDI
committee 31/8/2023
WASTE UPDATE - EDI Nov
2023.pdf (argyll-
bute.gov.uk)    Waste Update – EDI
committee 30/11/2023
W2 – Promote the Waste Hierarchy
through community Education 
(L) Roads and
Amenity Services
Evidence of
community
Education
Not secured New Web content and Education
materials for Primary and Secondary
Schools were developed and
delivered to online Education
Environment Summit October 21 and
the COP 26 Event on the 6th
November 21. Advised that this
action has paused/stopped.
W3 – Reduce Council use of disposable
and single use plastics across all
departments and settings 
(L) Procurement
and Commercial
Services, all
Council Services 
Adoption of new
working practices
and procurement
No specific funding in place, research
required to impact on operation
costs 
A report on Single Use Plastic went to
the Policy and Resources Committee
on 9 December 2021, and the
following recommendations were
approved:
• Note and consider that the
various Services that
currently purchase SUP
products consider whether
these products are essential

Page 10

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
or if there is a potential
alternative that would meet
the Service requirements,
prior to orders being placed
via PECOS or contacting the
Procurement, Commercial
and Contract Management
Team (PCCMT) for a
procurement process to be
carried out.
• Note and consider that the
Sustainable Procurement
Policy will be updated to
reflect the Climate Change
Board desire to limit SUP
where possible –wording
has been included in the
Annual Review 2023/2024
version of the Procurement
Strategy 2022/2025 as
follows: “To provide
procurement support to any
strategic decisions taken by
the Council in relation to the
usage of Single Use Plastic
products and their
recyclability.” 
• Note and consider that the
Commodity Sourcing
Strategy templates used for
Regulated Procurements
have been updated to
include a question regarding
SUP.

Page 11

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
Changes in legislation were brought
into force by the Scottish
Government on the 1st June 2022
restricting single-use plastic cutlery,
plates, straws, drink stirrers and
balloon sticks, expanded polystyrene
food containers and expanded
polystyrene cups and other beverage
containers, as well as all products
made of oxo-degradable plastic.  
Some products already changed and
others under review. 
W4 – Extend and explore pre-ordering
for school food to reduce food waste 
(L) Commercial
Services and 
Education 
Evidence of
extension of pre-
ordering & food
waste reduction
Project funded and solution procured Full implementation of Cashless
Catering and Pre-ordering system is
completed.
E1 – Deliver Renewable Sourcing
Strategy 2 
(L) Commercial
Services 
Adoption of
Strategy
RSS2 consultancy work funding to be
confirmed; expectation is that project
implementation will be through
combinations of prudential
borrowing (subject to business case
approvals) and/or external funding. 
RSS2 next stage development work
includes specification development
and preparation of invitation to
tender for specialist consultancy
support. Current work in progress;
intended to be market tested early
2024.
E2 – Delivery of Non-domestic Energy
Efficiency Framework (NDEEF) Projects 
(L) Commercial
Services 
Evidence of delivery
of projects
Project development work is funded
by combinations of the Scottish
Government and the procured
provider (costs absorbed within the
tender process). 
Funding for project implementation
will come from Council approved
capital allocations:
• Climate Change 20/21 -
£500K
Non Domestic Energy Efficiency Fund
(NDEEF1) Energy Performance
Contract was signed on 16 July 2021
(circa £1.25m investment with 10
year payback). The originally
intended mini project list has been
fully delivered. Following on from the
P&R Committee report in May 2023:
May PR - Climate Change -NDEEF
Progress update.pdf (argyll-
bute.gov.uk), four final mini projects,

Page 12

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
• Climate Change 21/22 -
£600K
• Asset Sustainability –  £175K
which were added as contract
variations, remained to be
implemented. Tarbert School LED
lighting was installed in the 2023
school summer recess; Kilmory
Nursery solar pv was installed in
September 2023; the intended low
carbon heating solution and pv
installation at Cardross PS have been
intentionally delayed whilst we try to
access a recently launched funding
scheme: Scotland’s Public Sector
Heat Decarbonisation Fund | Salix
Finance.  A bid was submitted by the
5/12/23 fund deadline (value £460K
with the Council needing to
contribute 20% of that). Bid
outcomes will be communicated
February 2024. 
In addition to the above, the
procurement sourcing strategy for
the next batch of sites, using
designation NDEEF2, is under way.  A
spend to save investment of
£2Million is being targeted.
E3 – Delivery of additional solar
installations at Council assets 
(L) Commercial
Services 
Evidence of delivery
of projects
Consultancy work funding to be
confirmed; expectation is that project
implementation will be through
combinations of prudential
borrowing (subject to business case
approvals) and/or external funding.
Best solar pv opportunities are being
delivered within NDEEF (Ref item E2)
and advantage is also being taken to
install solar pv solutions within the
asset sustainability capital
programme where possible  e.g. as a
component of roof upgrades.

Page 13

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
The potential for a large solar pv
ground array at the Kilmory Estate is
currently being limited due to electric
grid constraints – engagement with
SSEN is ongoing to try to identify
solutions. 
The Council now has 27no solar pv
installations in operation amounting
to over 1.3MW capacity.
E4 – Delivery of Water Efficiency Audits
across our Estate 
(L) Commercial
Services 
Evidence of delivery
of projects
Works items are generally small scale
and are being funded through
existing approved budgets where
possible; otherwise costs will be met
from savings generated.
Significant Council wide asset
verification exercise and ensuring
water use minimised. 
The asset verification element of this
project is substantially complete and
substantial savings have been
identified and recovered. A case
study is being prepared to
demonstrate the range of tasks
undertaken and to convey the scale
of savings made and refunds
received. The final stage of work
involves an exercise to reduce water
consumption (with carbon emissions
reduction) over a number of sites and
is underway.
E5– Delivery of Energy Efficiency
Scotland Programme 
(L) Housing
Services,
Registered Social
Landlords 
Evidence of delivery
of projects
Funding amounts are determined by
localised factors and is paid as a 
proportion of the Scottish
Governments’ Heat In Buildings
Strategy 
To date since 1st July 2023 Argyll and
Bute Council has spent £870,000 of a
£1,979,827 budget awarded by the
Scottish Governments Energy
Efficient Scotland – Area Based
Scheme (ABS), insulating privately
owned and privately rented
properties in mainland and island
addresses.  Non-means tested grants

Page 14

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
of between £9,000 and £21,000 are
available to all eligible households
for the application of insulation,
significantly reducing household
consumption of energy on a “Fabric
First” basis contributing towards
both the Councils and Scottish
Governments carbon reduction
targets.   Additionally, a joint project
in conjunction with Argyll
Community Housing Association in
Bute and Tarbert was awarded a
grant of £633,600. 
E6 – Complete LED streetlight
replacement programme 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects
Fully funded through prudential
borrowing
Contractors have now commenced
works  in the Lorn Area to progress
the last installation phase of the
project.  Works have gone well
though there is still approx.230
Luminaires to be upgraded to LED in
the Lorn Area – The Luminaires are
on order – Works should be
completed early 2024. The Council
has 14442 streetlights in total so
carbon emissions have already been
greatly reduced by the LED Upgrade
Project.
2022/23 figures were CO2 totals 673
tonnes, this has been reducing year
on year, back in 2015/16 figures were
CO2 Totals 3140 tonnes.
2023/24emissions are forecast to be
reduced again. YTD (End Of October –
Carbon Totals 334)

Page 15

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
E7 – Continue support of ABRA and
review Renewable Energy Strategy
annually 
(L) Economic
Development
Evidence of delivery
of projects 
Officer resource to support currently
funded
Work to support ABRA ongoing, the
next meeting is planned for March
2024.  Current ongoing project by SSE
Networks for renewal of powerlines
between Inveraray and Crossaig,
further works to follow to increase
capacity to 275kv.  The outline
business case for Islay Energy System
work through the Rural Growth Deal
has been submitted to Government. 
The Islay Carbon Neutral Islands
project has produced an action plan
and we are awaiting further
information from the Scottish
Government to understand how this
is expected to be taken forward.
E8 – Continue support for offshore
development of renewables 
(L) Economic
Development
Evidence of delivery
of projects
(expected late
2020s/early 2030s)
Officer resource to support currently
funded
Scottish Power Renewables are
progressing the Islay site (Machair
Wind) project , expected to seek
consent during the mid 2020s. The
Crown Estate Scotland Innovation
and Targeted Oil and Gas (INTOG)
leasing has identified a site off Islay
for a 100MW innovation project.
T1 – Develop a Fleet Replacement
Strategy supportive of fuel efficient,
electric and hybrid vehicles 
(L) Roads and
Infrastructure
Services
Adoption of
Strategy
Part for current financial year The Fleet Replacement Strategy is
complete but is subject to on-going
change in line with legislative
changes as it is an operational
document.
T2 – Develop a vehicle routing system
that will reduce road miles for
operations 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects
Part for current financial year  There is a further report on this going
to EDI in March. The project has
slipped against the original project
timeline due to the project manager
being away on a short-term

Page 16

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
secondment and staff time having
been taken up with the October
weather event and the RIS service
review. The project manager is now
back in post and looking to restart
progress meetings etc and revise the
project plan. The data gathering
around our routes and the cleansing
and verification of the data is proving
more onerous than originally thought
but this is a key step to provide the
system with the correct foundations.
The work to cleanse the data with the
support of the contracted supplier is
ongoing, and the second workstream
to bring in the hardware for RCVs is
about to begin. 
T3 – Develop an electric vehicle
infrastructure strategy 
(L) Roads and
Infrastructure
Services
Evidence of delivery
of projects 
Part for current financial year 
The development of the EV network
is funded by external grant monies
from Transport Scotland, and the
costs of developing the strategy in
terms of staff time are covered via
existing budgets
Ultimately the cost recovery model 
The strategy and expansion plan is in
place – we cannot move forward with
a delivery programme until such time
as our funding from SG is confirmed.
The national EVIF programme is
seeing some delays and changes in
guidance and application process. All
Councils are in the same position and
we are in discussions with TS/SG on
how the programme will operate
going forward and when we are likely
to see a funding award. 
We have, through a separate fund
accessed via HiTRANS, progressed
the installation of 8 new rapid

Page 17

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
chargers across the area in the last
quarter of 2023 and these are
coming on stream which brings our
network up to 37 chargers. 
We are also continuing to progress
installs at Council hub offices with the
next sites being {Union St Rothesay
and Kintyre House Campbeltown 
T4 – Support Digital by Default theme
Service Review & Recovery Plan to
reduce need to travel
All Council
Departments
Evidence of delivery
of projects
Part for current financial year Council is adopting ‘Our Modern
Workspace’ programme and  Digital
First approach as services change and
evolve post pandemic.  
T5 – Develop new active travel plans for
Council buildings and our towns 
(L) Economic
Development
Evidence of delivery
of projects
No active travel funding is provided
by Council.   
External competitive challenge funds
are time consuming to secure and
projects have to be shaped to fit with
external funders’ aspirations and
requirements by the 1.7FTE Active
Travel staff in the Strategic
Transportation Team. However, at
present these are the only available
source(s) of potential funding to
deliver active travel improvements. 
2022/23 Progress 
The 1.7FTE Active Travel Team
secured £3.03M external challenge
funding in 22/23 for development
and delivery of 32 active travel
projects across Argyll and Bute,
The purpose of active travel is to
make it as easy as possible and help
to encourage individuals, businesses
and visitors to choose to walk, wheel
or cycle for local journeys.  Increasing
activity and reducing sedentary
behaviour has significant health
benefits and can increase accessibility
to essential services, education,
employment, retail and
leisure.  Walking and cycling are
lower cost travel modes and, if they
are a viable option, can help
households reduce their reliance on
private cars, particularly multiple car
households.
No Council funding is currently
expended on Active Travel work, with
all costs, including internal staff costs
(1.7FTE), having to be funded via
successfully securing external

Page 18

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
requiring 22 separate competitive
challenge funding applications to 8
separate funds. 
Projects funded via the active travel
team within Strategic Transportation
in 2022/23 included:
• First two sections of high-quality
segregated cycleway in Argyll and
Bute constructed at Helensburgh
Waterfront and Ralston Road,
Campbeltown in 2022/23.
• Significant upgrade to path
network in Castle Gardens,
Dunoon.
• New cycle and scooter storage and
access at Castlehill School,
Campbeltown.
• New cycle parking at the
community owned Port Ellen
Playing Fields Community
Development, Islay.
• Funded Cycling UK to run the
Dunoon Cycle Bothy
• Funded ACT to upcycle 65 bikes to
return to the local Mid-Argyll
Community and to assist children
of refugees in Oban to have
opportunity to cycle.
• Funded ACT to deliver Carbon
Literacy training to over 30 people.
• Creation of new Smartphone Apps
for Tobermory and Bowmore
(adding to the existing popular
challenge funds. As all active travel
work is currently reliant on securing
external funding, therefore the
projects which are progressed are
those which can successfully secure
external challenge funding. 
Argyll and Bute Active Travel
Strategy: Officers are working to
develop an Argyll and Bute Active
Travel Strategy and present it for
Council by summer 2024.  The Active
Travel Strategy would provide the
overarching context for the Council
to support and promote active travel
across the Council area. Having an
adopted and current Active Travel
Strategy is increasingly becoming a
pre-requirement to access Scottish
Government derived active travel
funding. 
Active Travel Delivery Plan:
Following approval of Active Travel
Strategy, an Active Travel Delivery
Plan will be developed to create a
prioritised list of active travel projects
for the whole of Argyll and Bute. 
Active Travel Projects: The majority
of external funding available is
provided by the Scottish Government
via a number of third sector
organisations who are paid to

Page 19

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
apps for Campbeltown, Dunoon,
Helensburgh, Oban and Rothesay)
• Printed Active Travel Map
Helensburgh
• Design work progressed for
ambitious walking and cycling
projects including:
- Dunoon, Town Centre to Hunters
Quay Active Travel route.
- Helensburgh: Helensburgh –
Cardross – Dumbarton Cyclepath
and Helensburgh – Garelochhead
Cycleway.
- Islay, Bowmore to Bridgend Path
(with Islay Community Access
Group).
- Jura, Craighouse to Corran Sands
Active Travel Improvements.
- Lochgilphead: Front Green to
Crinan Canal and Town Centre to
Joint Campus Active Travel
Routes.
- Rothesay, Town Centre to Joint
Campus Active Travel
Improvements.
- Oban, Oban to Ganavan Sands
Active Travel Improvements and
Community engagement to
identify desire for future active
travel improvements in Oban.
administer these funds.  The focus for
Scottish Government Active Travel
funding is to develop and deliver
infrastructure projects and associated
behaviour change.  As such, the focus
for the very limited staff capacity in
the Active Travel Team has been to
develop and deliver infrastructure
projects across Argyll and Bute with a
focus on our main towns and
locations with strong community
support. 
Active Travel Plans for Towns: There
are Active Travel Plans in place for
the main towns in Argyll and Bute,
albeit some are now quite
historic.  The town Active Travel Plans
focus on identifying potential active
travel route networks for key
towns.  These provide a framework
for the development of new active
travel routes, which will enable and
encourage residents, businesses and
visitors to choose to travel more
actively.  No funding is currently
secured to enable the Active Travel
Plans for towns to be updated. 
Council Staff Travel Plan: At present it
is not proposed to progress with
development of a Council Staff Travel
Plan.  This is due to (a) requirement
to make best use of limited internal

Page 20

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
staff capacity; and, (b) the ongoing
uncertainty of longer-term staff
profiles and bases.  Staff Travel Plans
focus on measures to make it easier
and preferable for staff to choose to
walk, cycle, use public transport or
car share to commute to work or for
work journeys, or use economical
pool vehicles for work journeys.   A
travel plan should encourage staff to
choose the most economical and
least environmentally damaging
travel mode.  Engagement will be
required with services which manage
staff in buildings and/or council
buildings as this is essential to
creating deliverable and effective
travel plans for staff.  This includes
Estates, HR, SMT and building
users.  It is recommended that work
on the Council Staff Travel Plan is
commenced after a decision has
been made on future staff working
patterns and office rationalisation as
these will have a significant impact on
the Council Staff and their
travel.  There is currently no funding
secured to enable this work to be
progressed.   
PA1 – Review Council Flooding & Coastal
Protection Policy 
(L) Roads and
Infrastructure
Services
Review of policy No specific funding in place, research
required to impact on operation
costs
Reviews are in process.

Page 21

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
PA2 – Review Council Sustainable
Procurement Policy 
(L) Procurement  Review of policy  No specific funding in place, research
required to impact on operation
costs
This policy is reviewed on an annual
basis. 
OFF1 – Develop opportunities for
environmental sustainability projects
with ACT and partners 
(L) Climate
Change Board,
ACT and partners
Delivery of projects  Limited funding via ACT for existing
projects
SSEN compensatory planting – Phase
1 and 2 complete at Kilmory. 
ACT has completed habitat surveys in
the Glenan Wood area in Cowal for a
biodiversity net gain project
supported by SSEN.  This project
would see 50 hectares of Rainforest
cleared of invasive rhododendrons
and form part of the landscape scale
rainforest restoration project in West
Cowal.  The other Argyll landscape
scale project ACT is involved with is
Knapdale.  These are 2 of the 7 focus
rainforest projects in Scotland
supported by  the Alliance for
Scotland’s Rainforest.
https://savingscotlandsrainforest.
org.uk/projects 
ACT has entered agreement with
Mastercard’s Priceless Planet
Coalition to plant 100,000 native
trees in West Cowal over the coming
5 years.  Sites are confirmed and
legal agreements being finalised. This
planting will offer opportunities for
carbon credits for landowners.

Page 22

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
ACT is hosting the Community
Planning Partnership’s Climate
Action Manager who will be
developing a Climate Action Strategy
and Action Plan over the next 2
years.  In addition, ACT has
partnered with the Third Sector
Interface and Time for Change to
become the ABCAN (Argyll and Bute
Climate Action Network) Hub.  The
Hub team will engage with
communities and organisations to
encourage and support activity and
engage with the strategic work of
CPP supported post.   
ACT undertaking peatland
restoration on Islay, Jura and
extending into mainland Argyll,
supported by ScotGov’s Peatland
Action and Esmee Fairbairn
Foundation.  In addition to the 2 Islay
based jobs, we will be offering a 1-
year trainee position in 2024. 
Carbon Literacy Training – Cooler
Futures schools programme and ACT
Outdoors STEM subject delivery
offered with the  ACTNow project. 
ACT keen to support Argyll and Bute
Council in achieving Carbon Literate
Organisation silver accreditation.

Page 23

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
ACT delivering Bikes Back to the
Community with the support of
Smarter Choices, Smarter Places
funding.  
ACT has two electric bikes available
for groups and businesses and
Councillors/Council officers to trial. 
ACT is the lead partner in a successful
Alliance for Scotland’s Rainforest bid
to the Facility for Investment Ready
Nature in Scotland fund– to facilitate
private finance investment into
habitat restoration.  Contracts to
research Project Standards and
Integrity Charter, an Enterprise
Model and apply to a pilot area
within Argyll are underway. 
Concludes March 2025. 
ACT is preparing a proposal to Argyll
and Bute Council to establish a
Woodland Enterprise Hub at Kilmory
(adjacent to MAKI Pups site) which
will be the base and training site for
ACT Rainforest Squad who can offer
woodland management services. 
This project has been supported by
an award from the National Heritage
Lottery Fund, and DRAX who has
supported ACT to establish a Tree
Nursery as part of the proposal.

Page 24

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
COMM1- Develop and deliver
Communications Plan to support
Decarbonisation Plan 
(L) Climate Change
Board and
Communications
Team
Delivery of
Communications
Plan
Part of Communications Support  External communications
We continue to promote actions the
council is taking, and actions that
others can take, to develop climate-
friendly Argyll and Bute. For example:
• Promoting easier recycling
on Coll and Tiree
• HMPA SG consultation
response 
• Council calls for ban on
single use disposable vapes
• Council and ATC nomination
for Planning Awards for
Argyll rainforest project
• Council achieves bronze
carbon literate award
• Council calls for clarity on
deposit return scheme 
• Promotion of home
efficiency projects –
insulated over 160
households to date
• Landfill ban – request
meeting with SG Minister
• Food waste service
campaign to encourage
more Helensburgh and
Lomond residents to use
their caddies – ‘Bucket Load
of Good’
• Promotion of ongoing
Campbeltown Flood
Prevention Scheme
• Free active travel apps

Page 25

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
• Hermitage Park green flag
status
• Funding for additional EV
charging points
• Increased funding
announcement for Energy
Efficiency Scheme 
• Green Summer campaign –
series of posts encouraging
people to adopt small
changes 
- School uniform recycling
scheme
- Plastic free picnics
- International plastic
free bag day
- Shop Local
- Reduce fast fashion
- Active travel maps
- National Marine Week
- World Conservation Day
• New Campbeltown cycle
path
• Dunoon active travel route
consultation
• Helensburgh active travel
route consultation 
• Supporting Communities
Fund.
• Highlighted Corporate Plan
including climate action
• Built environment Planning
Awards

Page 26

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
• Transport Scotland funding
for cleaner, greener council
fleet
• Lochgilphead Active Travel
consultation and reminders
• Installation of solar panels at
council offices
• Net zero target
commitments 
• Improvements at household
waste recycling centres
• Council agrees projects to
address biodiversity loss
• Better journeys campaign –
to encourage more people
to mix and match journeys -
teasers before official launch
in January 2024
• Christmas recycling tips
• Cascade – have a greener
Christmas
• Cascade – tips for leftovers 
COMM2 - Engage with community and
partners and deliver Climate Change
Directory for our region 
(L) Community
Planning and
Development
Team
Delivery of
engagement map 
In place until end of financial year The CPP Climate Change signposting
page is  live 
https://www.argyll-bute.gov.uk/cpp-
climate-change   with further entries
added as they are received. 
The dedicated Climate Change
funding opportunities search,
available through the signposting

Page 27

ACTION LEAD (L) AND
PARTNERS
TARGET or
MILESTONE
FUNDING COMMENTS 
page, is conducted and an updated
document produced on a regular
basis. 
The Community Planning team
established the CPP Climate Change
Working Group which has developed
a collaborative funding package and
work to deliver a Climate Change
Plan for the area. (see update on ACT
and partners within this report)
COMM3 - Monitor the delivery of actions
in the Climate Change Action Plan and
review in 2024
(L) Climate Change
Board 
Review of this plan
by December 2024 
Monitored through Tracker to be
submitted quarterly to Policy &
Resources Committee. 
Completed – next review Dec 2024