ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 15 FEBRUARY 2024
FINANCIAL REPORTS MONITORING PACK – 31 DECEMBER 2023  
1. INTRODUCTION 
1.1 This report provides a summary of the financial monitoring reports as at the end of
December 2023. There are five detailed reports, setting out the position as at 31
December 2023, which are summarised in this Executive Summary: 
• Revenue Budget Monitoring Report 
• Monitoring of Financial Risks 
• Capital Plan Monitoring Report 
• Treasury Monitoring Report 
• Reserves and Balances 
2. DETAIL 
2.1 Revenue Budget Monitoring Report 
2.1.1 This report provides a summary of the current revenue budget monitoring position to
ensure net expenditure is contained within budget.  It provides corporate and
departmental information with comparisons on a forecast outturn and a year to date
basis. 
2.1.2  There is a forecast overspend of £0.091m as at the end of December 2023.  The key
variances are:
- Within Roads, numerous variances accumulating to a £1.257m overspend –
this is arising from an under-recovery of income in Piers & Harbours as a
result of a reduced number of berthings, in Public Conveniences due to
delayed installation of turnstiles, and on Traffic Regulation Orders (TROs) in
Roads. This is combined with overspends on Pupil Transport driver/escort
costs, Street Lighting Maintenance, staff costs in Amenities due to high
sickness and turnover and an unachievable saving in relation to Depot
Rationalisation.  These are partially offset by an underspend in Public
Transport payments to operators. 
- Within Development and Economic Growth, numerous variances
accumulating to a £0.306m overspend.  These include Homeless B&B costs,
a reduction in income for fish export certificates following Brexit, reduction in
building warrant income and legal costs within Environmental Health. 
- Within Executive Director Kirsty Flanagan there is an over-recovery of
vacancy savings and increased ferry grant income amounting to a favourable
projection of £0.612m. 
- Within Treasury Management, there is a forecast underspend of £0.294m in
relation to a discount received on the early repayment of three loans. 
- Within Council Tax income, an over-recovery of £0.187m is projected based
on current collection rates.

Page 2

- Within NDR, an underspend of £0.180m as costs have come through lower
than budget.  
- Within Legal and Regulatory Support, there is a favourable variance of
£0.168m resulting from historic water refunds.
- Within Education, there is slippage on Scottish Government 100 day Promise
funding due to delays in recruitment which is partially offset by an overspend
from Schools Residential placements due to a higher than budgeted demand
for this service resulting in an overall £0.020m underspend.
- Within Customer and Support Services, a net underspend of £0.011m arising
from an underspend on software licenses within ICT and on the Argyll and
Bute Manager training program partially offset the under-recovery of income
in the print and mail room due to increased digitalisation, 
2.1.3  There is a year to date overspend of £6.724m.  More focus is on the forecast outturn
position, hence why sometimes the year to date position is not updated.  The year to
date variances mainly relate to the timing of income and expenditure and recharging
of costs to capital. 
2.1.4 With regard to the ongoing financial impact of COVID-19, there are £5.512m of
reserves committed to manage the impact of the pandemic. The detail behind these
commitments is contained within Appendix 2 of the Reserves and Balances report. 
2.1.5 Total policy savings relevant to 2023-24 financial year amount to £6.953m.  The
table below outlines their progress as at 31 December 2023.   
Category No. of
Options
2023-24
£000
2023-
24
FTE
2024-25
£000
2024-
25
FTE
Future
Years
£000
Future
Years
FTE
Delivered 10 5,843.5 (0.7) 5,891.0 (0.7) 6,058.0 (0.7)
On Track to be
Delivered 4 656.0 2.5 629.0 11.9 560.0 12.4
Still to be
Implemented 1 0.5 0.0 0.5 0.0 0.5 0.0
Being Developed 0 0.0 0.0 0.0 0.0 0.0 0.0
Will not be achieved 2 248.5 0.0 248.5 0.0 248.5 0.0
Potential Shortfall 2 180.0 0.0 180.0 0.0 180.0 0.0
Delayed 1 24.0 0.0 24.0 0.0 24.0 0.0
TOTAL 20 6,952.5 1.8 6,973.0 11.2 7,071.0 11.7 
2.1.6 There are two savings marked as not going to be achieved. A cost pressure has
been recognised in 2024-25 for one of these and the other will be met by
underspends within the Service which will remove these savings targets.  Two
further savings are categorised as having a shortfall and one is currently delayed.   
Health and Social Care Partnership (HSCP) – Financial Update

Page 3

2.1.7 The forecast outturn position at the end of December is an estimated overspend of
£0.443m for 2023-24 (forecast to come in on budget for Social Work and overspend
of £0.443m for Health). The HSCP’s financial position will continue to be monitored
and Financial Services staff will engage with the HSCP Chief Financial Officer to
ensure that mitigation actions are in place to address the deficit and ensure that no
additional funding is required from the Council. 
2.2 Monitoring of Financial Risks 
2.2.1  This report outlines the process and approach developed in carrying out a financial
risks analysis and provides an update on the current assessment of financial risks.   
2.2.2 There are 5 Council wide revenue risks identified for 2023-24 currently amounting to
£2.835m.   
2.2.3 There are currently 39 departmental risks totalling £5.265m.  Of the 39 departmental
risks, 6 are categorised as likely.  These will continue to be monitored and action
taken to mitigate or manage these risks.   
2.2.4 The current top three risks in terms of the financial impact are noted in the table
below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads
Maintenance -
Bridges, Culverts
& Sea Defences
Extreme localised weather may
result in loss of bridge, culvert,
road or sea defence.
3 750
Roads and
Infrastructure
Services
Waste PPP -
Indexation
Historical payments made
towards Waste PPP based on
indexation rates have been
challenged by Renewi resulting
in a potential cost to the council.
3 586
Roads and
Infrastructure
Services
Winter
Maintenance
Adverse weather conditions
which require greater than
budgeted number of gritting
runs.
4 365 
2.2.5 
2.2.6
There have been no changes to the departmental risks since the report as presented
to the Policy and Resources Committee on 7 December 2023.   
There is a risk that there are revenue costs of circa £0.900m incurred as a result of
significant rainfall in Autumn 2023 will not be fully covered by the Bellwin
scheme.  This issue and three other potential risks relating to funded childcare for 1
and 2 year olds, the proposed new school campus on Mull and digital access for
learners are covered in section 3.6 of the Financial Risks report.

Page 4

2.3 Capital Plan Monitoring Report 
2.3.1 
2.3.2
This report provides a summary of the current capital plan monitoring position. 
Information is provided in terms of monitoring year to date budget, current full year
budget, future years total budget and funding and non-financial in terms of project
performance. 
In recent years, the Council has agreed additional funding for the capital programme
totalling £10.803m to address specific costs related to dealing with COVID,
inflationary pressures arising as a consequence of the factors detailed in paragraph
2.3.3 below and other cost pressures on the capital plan. To date, £8.1m has been
allocated to projects leaving a balance of £2.703m available for allocation as
required. 
2.3.3  The impact of the pandemic along with the UK exit from the European Union, the
Russian invasion of Ukraine and sanctions on Russian owned entities has seen
significant price increases as well as disruptions to the supply chain and longer lead
in times. The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all have an effect on the overall contract price and
make it extremely challenging to manage expenditure and the availability of supply.
As a result of this it should be noted that there are likely to be other significant
financial impacts which are not quantifiable at this stage. 
2.3.4 Actual net expenditure to date is £24.334m compared to a budget for the year to
date of £24.309m giving rise to an overspend for the year to date of £0.025m
(0.10%).  
2.3.5 The forecast outturn for 2023-24 is a forecast net expenditure of £34.239m
compared to an annual budget of £41.791m giving rise to a forecast underspend for
the year of £7.552m (18.07%). 
2.3.6 The forecast total net projects costs on the capital plan are £216.052m compared to
a total budget for all projects of £216.975m giving rise to a forecast overspend for
the overall capital plan of £0.910m (0.42%).  
2.3.7 In respect of total project performance, there are 157 projects within the capital plan,
140 are complete or on target, 2 are off target and recoverable and 15 projects are
off track.  
2.4 Treasury Monitoring Report 
2.4.1 This report provides information on the current levels and recent transactions in
relation to the capital financing limit, total borrowing, temporary borrowing and long
term borrowing and investments.   
2.4.2 The net movement in external borrowing for the period 1 November 2023 to 31
December 2023 was a decrease of £3m.

Page 5

2.4.3 Borrowing is below the Capital Financing Requirement for the period to 31
December 2023, at this stage in the financial year capital expenditure is below
target. 
2.4.4 The levels of investments were £56.929m at 31 December 2023. The average rate
of return achieved was 5.054% which is below the target SONIA (Sterling Overnight
Index Average) rate for the same period of 5.187%. 
2.5 Reserves and Balances 
2.5.1 This report summarises the overall level of reserves and balances and monitors the
spending of the earmarked reserves, providing detailed information on the unspent
budget earmarked balances.   
2.5.2 The Council has a total of £666.354m unusable reserves that are not backed with
resources.  They are required purely for accounting purposes. 
2.5.3 At 31 March 2023, the Council had a total of £93.828m of usable reserves.  Of this: 
• £2.916m relates to the Repairs and Renewals Fund
• £4.503m relates to Capital Funds
• £86.409m was held in the General Fund, with £79.466m of this balance
earmarked for specific purposes. 
2.5.4  During 2023-24, the amount of £4.776m which was previously agreed to be utilised
from the one-off reprofiling gain from the Loans Fund Review was drawn down into
Earmarked Reserves to be used to fund the Capital Programme as detailed in
paragraph 3.5.1 of the reserves report. This results in the total earmarked balance
increasing to £84.242m. 
2.5.5 Of the earmarked balance of £84.242m:
• £41.505m is invested or committed for major initiatives/capital projects 
• £6.032m has already been drawn down
• £13.087m is still to be drawn down in 2023-24
• £23.618m is planned to be spent in future years 
2.5.6 The table below summarises the position of the unallocated General Fund balance. 
Further explanation of the figures can be found at Section 3.4 of the Reserves and
Balances report.  
Heading Detail £000
Unallocated General Fund
as at 31 March 2023 
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£5.6911
1,252

Page 6

Budgeted allocation to
General Fund for 2023-24
Budget
Per the Budget Motion at Council on
23 February 2023
19
Earmarked Balances no
longer required
Per paragraph 3.3.3 – amount
previously earmarked that can be
released back to the general fund
104
Current Forecast Outturn
for 2023-24 as at 31
December 2023
Per paragraph 3.4.2.  (91)
Social Work outturn
adjustment
Per paragraph 3.4.3 - Social Work
would expect to transfer any surplus
to internal IJB reserves
0
Allocation from unallocated
general fund balance
Per paragraph 3.4.4 (8)
Estimated Unallocated
balance as at 31 March
2024 
1,276 
2.5.6 It can be seen that, after taking into consideration the budgeted allocation to the
General Fund agreed by Council on 23 February 2023, the earmarked balances no
longer required, the current forecast outturn position for 2023-24 and the proposed
allocation for floral displays the Council is forecast to have a £1.276m surplus over
contingency. 
2.6 VIREMENTS OVER £0.200m (Revenue) 
2.6.1 Virement is the process of transferring budget between cost centres, services or
departments or between capital projects.  The Council’s constitution notes that
virements over £0.200m require approval by Council.  This section of the report will
be used to outline revenue virements in the period that require approval.   Capital
virements are included within the capital monitoring report. 
2.6.2 For the period November and December, there is one virement requiring
authorisation: 
- £0.900m of funding recognised for Discretionary Housing payments.  This is
Scottish Government funding via Circular 03/2023.   
3.  RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee:

Page 7

a) Consider the revenue budget monitoring report as at 31 December 2023. 
b) Note the financial risks for 2023-24. 
c) Note the capital plan monitoring report as at 31 December 2023 and approve the
proposed changes to the capital plan outlined in Appendix 4 of that report. 
d) Note the treasury monitoring report as at 31 December 2023. 
e) Consider the reserves and balances report as at 31 December 2023.  
f) Recommend to Council that the revenue virements over £0.200m during
November and December 2023 are approved. 
4. IMPLICATIONS 
4.1 Policy – None.
4.2 Financial -  Outlines the revenue and capital monitoring
for 2023-24 as at 31 December 2023
4.3 Legal -  None.
4.4 HR -  None.
4.5 Fairer Scotland Duty -   None.
4.5.1 Equalities – protected
characteristics - 
None.
4.5.2 Socio-economic Duty -  None.
4.5.3 Islands -  None.
4.6 Climate Change - None.
4.7 Risk -  Risks are included in financial risks report. 
4.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director /Section 95 Officer
12 January 2024 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 8

REVENUE BUDGET MONITORING REPORT AS AT 31 DECEMBER 2023 POLICY AND RESOURCES COMMITTEE
15 FEBRUARY 2024 
2023-24 Overall Position:
There is a forecast overspend of £0.091m as at the end of December 2023.  Within Executive Director Douglas Hendry, there is a forecast
underspend of £0.188m due to slippage in the utilisation of 100 day promise funding and historic water refunds offset by an overspend within
Residential Schools due to a higher than budgeted demand for this service.  Within Executive Director Kirsty Flanagan, there is a forecast
overspend of £0.940m due to an under-recovery of income in Piers & Harbours due to a reduction in the number of berthings, in Public
Conveniences due to the delayed installation of turnstiles, Print & Mail Room due to a shift to digital communication channels resulting in a
reduction in printing activity, a reduction in Building Warrant and Fish Export Certificate income and on Traffic Regulation Orders (TROs) in
Roads. This reduction in income is combined with overspends on Pupil Transport driver/escort costs, Temporary Accommodation for Housing
Homeless, Legal costs in Environmental Health, Street Lighting Maintenance, staff costs in Amenities due to high sickness and turnover and
an unachievable saving in relation to Depot Rationalisation.  These are partially offset by an over-recovery of vacancy savings, an underspend
in Public Transport payments to operators, underspend in IT software licences and an underspend in training for Argyll & Bute Manager
courses.  Social Work is currently forecasting to break even at the end of the financial year.  This is due to a combination of the over-recovery
of vacancy savings, income from fees, charges and recharges and the use of non-recurring reserves to offset cost pressures arising from a
high demand for services and the use of agency staff to fill staffing recruitment and retention gaps across adult services.  There are forecast
underspends within Treasury Management of £0.294m in relation to a discount received on the early repayment of three loans and within
NDR of £0.180m due to actual costs being less than the available budget.  There is also a projected over-recovery of £0.187m within Council
Tax. 
There is a year to date overspend of £6.724m.  The year to date variances within the departments tend to relate to the timing of income and
expenditure and costs to capital not recharged yet. 
Key Highlights as at December 2023:  
• Council services are projecting an overspend of £0.301m as at 31 December 2023.  
• During November 2023, the 2023-24 pay settlement was agreed for Chief Officers and non teaching staff. As a result of this the Payroll
Team implemented the first stage of the new relevant pay rates and processed the related back pay during the month of November.
The final stage of the uplift will be implemented in two steps with the new rates being applied from the December pay run onwards and
any arrears due to staff over the period 1st April 2023 to 15th November 2023 being calculated and paid by the end of February 2024.
• As the pay settlement has now been received the budgets require to be adjusted to reflect the new employee costs and the
corresponding Scottish Government funding will offset costs.  It is hoped this will be completed in the January period and preliminary
workings indicate that there should be no cost pressure as a result of the settlement. 
Key Financial Successes:
Performance against budget for 2022-23 was an overall net favourable position of £3.326m underspend after adjusting for year-end
earmarking.  This breaks down as:
• £0.347m net underspend in relation to Council service departmental expenditure

Page 9

• £6.937m net underspend in relation to other central costs largely due to a one-off treasury gain as a result of a discount on the early
repayment of loans
• £0.652m over-recovery of Council Tax income
• £4.610m of unspent budget earmarkings 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Addressing the long-term impact of the COVID pandemic on service
demand and the increasing challenges facing departments across the
Council in relation to the recruitment and retention of suitably qualified
and experienced staff.
Engagement and monitoring of both issues with departments to
assess how these challenges are affecting service capacity and
capability, staff attendance, utilisation of agency staff and costs.
Collaboration with services and other back-office teams to consider
and develop mitigating actions.
Achieving a favourable year-end position and achieving savings targets
in light of council wide risks to expenditure. 
Robust monitoring of the financial position and delivery of savings to
ensure budget issues inform the budget monitoring process.
Monitoring Social Work expenditure and more widely the IJB position as
any overspend will transfer back to partner bodies in the first instance.  
Continue to work closely with the CFO of the IJB to ensure that early
indication of any potential adverse financial outturn is identified and
corrective action is agreed as appropriate to reduce the risk to the
Council. 
Identifying further savings and delivering services more efficiently with
less resources, as whilst a balanced 2023-24 budget was agreed in
February 2023 there are still budget gaps in future years.
The Council will continue to progress savings options identified,
refine options that require further development and seek to identify
further savings through themed reviews and business process
reviews.
Maintaining or improving the level of service income recovered, for
example planning, building standards and car parking.  
Actively monitor income recovery and ensure Council fees and
charges policies are regularly reviewed. 
Managing spend in service areas which are demand led and, to some
extent, outwith service control, for example Winter Maintenance. 
Use a risk-based approach to budget monitoring to focus additional
attention on these areas.
Ongoing requirement to fund unavoidable inflationary increases in areas
like utility costs, fuel, food etc. This is impacted further by the availability
of supply because of the COVID-19 pandemic, UK exit from the European
Union, Russia’s invasion of Ukraine and sanctions on Russian owned
entities, to name a few influencing factors.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes. 
Cost of living crisis impacting on pay inflation negotiations which could
result in pay awards above what is deemed affordable.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.

Page 10

Forecast Outturn Position
There is a forecast underspend of £0.301m for 2023-24 as at 31 December 2023.
Department
Annual
Budget   
£'000
Forecast
Outturn   
£'000
Current
Forecast
Variance
£'000
Previous
Forecast
Variance
£000
Change
£000 Explanation
Chief Executive's Unit 1,177 1,177 0 0 0
Executive Director (Douglas Hendry) 133,044 132,856 188 188 0
The projected underspend is due to slippage in the utilisation of Scottish
Government 100 day promise funding and historic water refunds, offset by an
overspend within Residential School Budgets due to a higher than budgeted
demand for this service.
Executive Director (Kirsty Flanagan) 56,363 57,303 (940) (1,005) 65
The projected variance is due to an under-recovery of income in Piers &
Harbours as a result of a reduced number of berthings, in Public Conveniences
due to the delayed installation of turnstiles, Print & Mail Room due to a shift to
digital communication channels resulting in a reduction in printing activity,
reduction in Building Warrant and Fish Export Certificate income and on TROs
in Roads. This is combined with overspends on Pupil Transport driver/escort
costs, Temporary Accommodation for Housing Homeless, Legal costs in
Environmental Health, Street Lighting Maintenance, staff costs in Amenities due
to high sickness and turnover and an unachievable saving in relation to Depot
Rationalisation. These are partially offset by an over-recovery of vacancy
savings, an underspend in Public Transport payments to operators, underspend
in ICT software licences and an underspend in training for A&B Manager
courses.
Social Work 76,117 76,117 0 0 0
The projected break even position is due to a combination of the over-recovery of
vacancy savings, income from fees, charges and recharges and the use of non-
recurring reserves to offset cost pressures due to high demand for services and
the use of agency staff to fill staffing recruitment and retention gaps across Adult
Services.
Central Budgets 27,178 26,704 474 294 180 The projected underspend results from recognition of a discount received on the
early repayment of loans £0.294m and a projected underspend on NDR £0.180m
Financed By (293,879) (294,066) 187 0 187 Projected over-recovery of Council tax income
Total 0 91 (91) (523) 432

Page 11

Further information on the departmental forecast variances is included later on in the report. 
(1,200)
(700)
(200)
300
800
April
May
June
July
August
September
October
November
December
January
February
£ 000
Forecast outturn position for each Department from the start of the financial year
Chief Executive's Unit
Executive Director (Douglas Hendry)
Executive Director (Kirsty Flanagan)
Social Work
Central Budgets
Financed By
Underspend
Overspend

Page 12

Year to Date Position
The year to date position as at 31 December 2023 is an overspend of £6.724m and the main variances are noted below. 
Department
YTD
Actual
£'000
YTD
Budget
£'000
YTD
Variance   
£'000
Explanation
Chief Executive's Unit 897 938 41 The year to date underspend can be attributed to profiling issues
Executive Director (Douglas Hendry) 99,074 98,955 (119) The year to date overspend is due to overspends within the Residential School
Budget, under recovery of commercial income and various budget profiles that
require to be refined. These overspends are partially offset by slippage in 100 day
promise funding and historic water refunds.
Executive Director (Kirsty Flanagan) 48,197 42,028 (6,169) The year to date variance is mainly due an under-recovery of berthing income in
Piers and Harbours, delay in the processing of recharges to capital within Roads,
Housing expenditure incurred in advance of grants being received as well as an
overspend in Fleet due to a timing difference between expenditure occurring and
recharging services.
Social Work 46,703 46,658 (45) The year to date overspend is mainly due to the use of agency staff across
Homecare and Older People Residential Units in Adult Services.
Central Budgets 6,765 6,333 (432) The year to date overspend can be attributed to profiling issues.
Funding (196,006) (196,006) 0
Total Net Expenditure 5,630 (1,094) (6,724)

Page 13

Further information on the departmental year to date variances is included later on in the report. 
0%
25%
50%
75%
100%
Chief Executive's Unit
Executive Director (Kirsty Flanagan)
Executive Director (Douglas Hendry)
Social W
ork
Central Budgets
TOTAL
Expenditure to date against the remaining budget for each Department
YTD Actual £000 Remaining Budget £000

Page 14

OBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 DECEMBER 2023
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual Budget Forecast
Outturn
Forecast
Variance
Variance
£'000 £'000 £'000 % £'000 £'000 £'000 %
Departmental Budgets
Chief Executive's Unit 897 938 41 4.4% 1,177 1,177 0 0.0%
Executive Director (Douglas Hendry) 99,074 98,955 (119) (0.1%) 133,044 132,856 188 0.1%
Executive Director (Kirsty Flanagan) 48,197 42,028 (6,169) (14.7%) 56,363 57,303 (940) (1.7%)
Social Work 46,703 46,658 (45) (0.1%) 76,117 76,117 0 0.0%
Total Departmental Budgets 194,871 188,579 (6,292) (3.3%) 266,701 267,453 (752) (0.3%)
Central Budgets
Other Operating Income and Expenditure (1,060) (1,436) (376) 26.2% 3,874 3,874 0 0.0%
Joint Boards 1,015 993 (22) (2.2%) 1,396 1,396 0 0.0%
Non-Controllable Costs 6,810 6,776 (34) (0.5%) 21,908 21,434 474 2.2%
Total Central Budgets 6,765 6,333 (432) (6.8%) 27,178 26,704 474 1.7%
TOTAL NET EXPENDITURE 201,636 194,912 (6,724) (3.5%) 293,879 294,157 (278) (0.1%)
Financed By
Aggregate External Finance (142,863) (142,863) 0 0.0% (227,021) (227,021) 0 0.0%
Local Tax Requirement (53,143) (53,143) 0 0.0% (59,301) (59,488) 187 (0.3%)
Contributions to General Fund 0 0 0 0.0% (1,525) (1,525) 0 0.0%
Earmarked Reserves 0 0 0 0.0% (6,032) (6,032) 0 0.0%
Total Funding (196,006) (196,006) 0 0.0% (293,879) (294,066) 187 (0.1%)
(Deficit)/Surplus for Period 5,630 (1,094) (6,724) 0 91 (91)
CURRENT PROJECTED FINAL OUTTURNYEAR TO DATE POSITION

Page 15

SUBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 DECEMBER 2023
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual
Budget
Forecast
Outturn
Forecast
Variance
Variance
£'000 £'000 £'000 % £'000 £'000 £'000 %
Subjective Category
Employee Expenses 137,133 135,936 (1,197) (0.9%) 190,431 190,885 (454) (0.2%)
Premises Related Expenditure 14,818 13,987 (831) (5.9%) 20,612 20,568 44 0.2%
Supplies and Services 19,679 18,209 (1,470) (8.1%) 25,504 26,131 (627) (2.5%)
Transport Related Expenditure 10,119 9,225 (894) (9.7%) 17,792 17,678 114 0.6%
Third Party Payments 120,664 117,558 (3,106) (2.6%) 173,251 174,179 (928) (0.5%)
Capital Financing 3,314 0 (3,314) 15,208 15,428 (220) (1.5%)
TOTAL EXPENDITURE 305,727 294,915 (10,812) (3.7%) 442,798 444,869 (2,071) (0.5%)
Income (300,097) (296,009) 4,088 (1.4%) (442,798) (444,778) 1,980 (0.5%)
(Deficit)/Surplus for Period 5,630 (1,094) (6,724) 0 91 (91)
YEAR TO DATE POSITION CURRENT PROJECTED FINAL OUTTURN
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.

Page 16

CHIEF EXECUTIVE’S UNIT – AS AT 31 DECEMBER 2023 
The department is currently forecasting spend in line with budget. 
The department has a year to date underspend of £0.041m (4.4%) which can be attributed to profiling issues. 
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Chief Executive 1,177 1,177 0 0 0
Totals 1,177 1,177 0 0 0
Year to Date Position 
Key Financial Successes:
• All savings options have been delivered.  
• The department’s 2022-23 outturn position was an underspend of £0.017m. This resulted from an overall underspend of £0.087m offset
by earmarking of £0.070m due to auto-carry forwards including unspent grants and third party contributions.   
Key Financial Challenges: Proposed Actions to address Financial Challenges:
To continue to deliver a high-quality service to support community
engagement and participation.
Regular monitoring, reflection and improvement cycle on service
provision to ensure most efficient use of staffing and financial
resources to meet national and local policy requirements for quality
engagement.
0%
25%
50%
75%
100%
Chief Executive
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 17

To continue to deliver a high quality support service function to community
organisations and community planning partners during a time of challenge
arising from continuing reductions in funding.
Seek to work in partnership with third sector organisations such as
the TSI in Argyll and Bute to efficiently deliver full package of support
to community organisations. Within the partnership working of the
CPP we seek to establish working groups and collate resources
within this to deliver high quality solutions to identified needs.
Demands for funding from community applications to the Supporting
Communities Fund higher than available annual funds by about 40%.
Continue to monitor fund criteria adapting this to align with priority
outcomes for Argyll & Bute and continue to support groups to seek
alternative sources of funding from our database of funding
providers.

Page 18

CHIEF EXECUTIVE’S UNIT – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2023 
Service Area YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Executive 307 304 (3) (1.0%) 421 421 0 0.0% Outwith Reporting Criteria
Community Planning
& Development 590 634 44 6.9% 756 756 0 0.0% Outwith Reporting Criteria  
897 938 41 4.4% 1,177 1,177 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 19

CHIEF EXECUTIVE’S UNIT – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2023
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 667 666 (1) (0.2%) 924 924 0 0.0% Outwith Reporting Criteria
Supplies and
Services 8 9 1 11.1% 12 12 0 0.0% Accumulation of underspends across a range of
account codes
Transport 6 11 5 45.5% 14 14 0 0.0% Underspend on staff travel budgets
Third Party 278 289 11 3.8% 294 294 0 0.0% Outwith Reporting Criteria
Income (62) (37) 25 (67.6%) (67) (67) 0 0.0%
Unbudgeted income received from Bord Na
Gaidhlig to fund a new post within Gaelic
Development.  The budgets will be adjusted in
January period to recognise the income /
expenditure for the post. 
Totals 897 938 41 4.4% 1,177 1,177 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 20

CHIEF EXECUTIVE’S UNIT – RED VARIANCES AS AT 31 DECEMBER 2023
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation      
0 0.0%   
A red variance is a forecast variance which is greater than +/- £50,000.

Page 21

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 DECEMBER 2023  
The department is currently forecasting an under spend of £0.188m (0.1%) which is due to slippage in the utilisation of Scottish Government
100 day promise funding and historic water refunds, offset by an overspend within Residential School Budgets due to a higher than budgeted
demand for the service. 
The department has a year to date (YTD) overspend of £0.119m (0.1%). The YTD position is due to overspends within the Residential School
Budget, under recovery of commercial income and various budget profiles that require to be refined.  These overspends are partially offset by
slippage in 100 day promise funding and historic water refunds.                           
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Executive Director
(Douglas Hendry) 452 452 0 0 0
Head of Commercial
Services 11,654 11,654 0 0 0
Head of Education 105,006 104,986 20 91 (71)
Head of Legal and
Regulatory Support 15,932 15,764 168 0 168
Totals 133,044 132,856 188 91 97 
Year to Date Position 
Key Financial Successes:
The 2022-23 year-end consolidated outturn position was an under spend of £2.202m after adjusting for automatic earmarking. Contributing
factors included:
• Effective contract management of NPDO and Hub School contracts, including a lower-than-expected insurance premium as a result of
the annual renegotiation of insurance costs. 
0%
25%
50%
75%
100%
Executive Director
(Douglas Hendry)
Head of
Commercial
Services
Head of Education Head of Legal and
Regulatory Support
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 22

• Successful negotiations with utility suppliers achieved both historic water charge refunds and ongoing reductions to water rates.
• Implementation of NDEEF project resulting in recurring annual saving in utilities and a significant contribution to meeting Net Zero
targets.
• Income generation within Early Years.
• Increased rental income within One Council Property. 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
The legacy impact of COVID-19 on our young learners has led to an
increased demand on the additional support need functions of the
Education Service in response to the growing health and wellbeing
needs of our young people and their families.
Analysis and review of delivery models, robust costings of any
service redesign required and continual monitoring of associated
budgets
Impact of the current cost of living crisis on the cost of the school day for
learners and their families.
Work with schools to ensure effective use of PEF to close the
poverty related attainment gap and identify other funding sources
to ensure equity of experience for all children.
Impact of the current cost of living crisis on uptake in demand led service
areas like catering, design services and licensing.
Continually refine/develop systems to accurately forecast outturns
and the impact on the future financial outlook. Strategies in place
to redesign services in line with future demand.
Ensure that Catering and Cleaning Services remain efficient and
effective given the requirement to increase free school meal provision for
P6/7 and Early Years, the impact of high inflation on produce and a
requirement to adhere to the Statutory Guidance supporting Nutritional
Requirements for Food and Drink in Schools (Scotland) Regulations
2020.
Support a longer-term service re-design project, including
collaborative working with partners and cross department support
with implementation of revised service delivery models. Continual
monitoring and review of costs and budgets, ensuring that any
efficiencies and savings are secured for the Council
Manage delivery of legislative/policy requirements that may not be fully
funded by Scottish Government therefore placing additional burdens on
the Council, for example, expansion of Universal Free School Meals for
P6 and 7s.
Analysis of new obligations and whether they incur additional costs
not met through increased funding allocations. Work will be
designed and implemented in the most effective way within
resource availability.
The Council has a requirement to deliver 1140 hours of Early Learning
and Childcare (ELC). The ring-fenced grant was reduced in 2022-23 and
again this year, reducing funding by £1.478m. 
Robust service costings, financial monitoring and timely reporting
to ensure the service can be delivered within the financial
resources available. Medium term forecasting on population to
shape ongoing service redesign. Analysis of potential to extend
income generation using “spare” capacity to trial paid care for
under 2’s
Impact of high inflationary uplifts within the NPDO/HUB School contracts. Ensuring continued effective contract management of NPDO/HUB
Schools to minimise the impact of high inflationary uplifts.

Page 23

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2023  
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director (Douglas
Hendry)
Central/Management
Costs
290 291 1 0.3% 452 452 0 0.0% Outwith Reporting Criteria    
290 291 1 0.3% 452 452 0 0.0%  
Head of
Commercial
Services
Catering 846 747 (99) (13.3%) 1,265 1,265 0 0.0% The YTD overspend is due to the
timing of income and
expenditure.
Head of
Commercial
Services
Central/Management
Costs
1,133 1,060 (73) (6.9%) 1,728 1,728 0 0.0% The YTD overspend is due to the
timing of income and
expenditure.
Head of
Commercial
Services
CHORD 110 75 (35) (46.7%) 63 63 0 0.0% The YTD overspend is due to the
timing of recharges to capital.
Head of
Commercial
Services
Cleaning 45 258 213 82.6% 481 481 0 0.0% The YTD underspend is due to
the timing of recharges for
cleaning and the reduced use of
bank staff. 
Head of
Commercial
Services
Culture, Heritage,
Recreation & Sport
4,541 4,391 (150) (3.4%) 5,980 5,980 0 0.0% The YTD overspend is due to the
profiling of utilities and CRA
budgets. 
Head of
Commercial
Services
Events &
Commercial
Catering
294 7 (287) (4100.0%) 3 3 0 0.0% The YTD overspend is due to an
under recovery of income and
high staff costs within
Commercial Cafés and Events.
The new senior manager is
currently working with finance
reviewing the current business
model.
Head of
Commercial
Services
Property Portfolio (185) (124) 61 (49.2%) (191) (191) 0 0.0% The YTD underspend is due to
the timing of One Council
Property income.
Head of
Commercial
Services
Property Services 188 766 578 75.5% 817 817 0 0.0% The YTD underspend is due to
the receipt of historic water
charge refunds and the profile of
property fee income. 
Head of
Commercial
Services
Shared Offices 900 850 (50) (5.9%) 1,508 1,508 0 0.0% The YTD overspend is due to the
profiling of refuse collection
recharges.

Page 24

7,872 8,030 158 2.0% 11,654 11,654 0 0.0%  
Head of
Education
Additional Support
for Learning
8,304 8,212 (92) (1.1%) 11,625 11,625 0 0.0% The main contributing factor to
the YTD overspend is the budget
profile relating to the pay award
costs for ASN Assistants.
Head of
Education
Central/Management
Costs
1,797 1,720 (77) (4.5%) 2,325 2,325 0 0.0% The YTD position is due to
overspends in Licence fees,
profiling that requires refining,
partially offset by a number of
small underspends elsewhere
within the service. 
Head of
Education
Community Learning
& Development
5 3 (2) (66.7%) 13 13 0 0.0% The YTD overspend is within the
Central Repairs Account (CRA)
which is managed across the
Service and is profile related. 
Head of
Education
COVID 109 112 3 2.7% 136 136 0 0.0% Outwith Reporting Criteria
Head of
Education
Early Learning &
Childcare
5,273 5,353 80 1.5% 9,993 9,993 0 0.0% The main contributing factor for
the YTD underspend is due to
delays in recruitment within ELC
settings.  This is partially offset
by a YTD overspend in the 1140
Hours budget which will be
rectified through a drawdown
from Earmarked Reserves.
Head of
Education
Primary Education 29,057 28,699 (358) (1.3%) 38,133 38,133 0 0.0% The YTD position is due to
overspends in the school
adaptations and maintenance
budget due to a higher level of
minor repairs than budget allows,
some of which will be covered
from earmarkings and the
remainder offset by underspends
elsewhere. Additionally, profiling
of cleaning and grounds
maintenance recharges requires
refining. There is also a YTD
under-recovery in school meal
income and YTD overspend in
teacher cover costs for which
journals require to be processed.
These overspends are partially
offset by a YTD underspend in
PEF.

Page 25

Head of
Education
Pupil Support 1,881 1,778 (103) (5.8%) 2,636 3,016 (380) (14.4%) The YTD overspend in the
Schools Residential Budget is
due to a higher demand for
service than budget allows.  A
forecast variance of £380k has
been recorded through the
ledger reflecting this position. 
The YTD overspend is partially
offset by an underspend in
Psychological Services which is
profile-related.
Head of
Education
Schools - Central
Services
1,372 1,364 (8) (0.6%) 2,393 1,993 400 16.7% Outwith Reporting Criteria
Head of
Education
Secondary
Education
28,370 28,196 (174) (0.6%) 37,752 37,752 0 0.0% The YTD position is due to
overspends in the school
adaptations and maintenance
budget due to a higher level of
minor repairs than budget allows,
some of which will be covered
from earmarkings and the
remainder offset by underspends
elsewhere. Additionally, profiling
of cleaning and grounds
maintenance recharges requires
refining. There is also a YTD
under-recovery in Education
Maintenance Allowance and
school meal income for which
journals require to be processed.
These overspends are partially
offset by a YTD underspend in
PEF. 
76,168 75,437 (731) (1.0%) 105,006 104,986 20 0.0%  
Head of Legal &
Regulatory
Support
Central/Management
Costs
193 184 (9) (4.9%) 271 271 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Community Safety 131 126 (5) (4.0%) 185 185 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Elections 42 9 (33) (366.7%) 37 37 0 0.0% The YTD overspend is due to the
current budget profile.

Page 26

Head of Legal &
Regulatory
Support
Governance 552 438 (114) (26.0%) 726 726 0 0.0% The YTD overspend is due to
spend on Council Chambers ICT
Equipment for which earmarked
reserves are to be drawn down.  
Head of Legal &
Regulatory
Support
Governance, Risk &
Safety
414 412 (2) (0.5%) 581 581 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Legal Services 359 399 40 10.0% 749 749 0 0.0% The YTD underspend is due to
delays in recruitment and the
over-recovery of licencing
income. 
Head of Legal &
Regulatory
Support
NPDO and Hub
Schools
11,824 12,316 492 4.0% 11,481 11,313 168 1.5% The YTD underspend is partially
due to the receipt of historic
water charge refunds and a
forecast variance has been
processed for £168k to reflect
this. The remaining underspend
is due to the timing of income
and expenditure.
Head of Legal &
Regulatory
Support
Procurement,
Commercial and
Contract
Management
766 827 61 7.4% 1,218 1,218 0 0.0% The YTD underspend is due to
delays in recruitment. 
Head of Legal &
Regulatory
Support
Trading Standards &
Advice Services
463 486 23 4.7% 684 684 0 0.0% Outwith Reporting Criteria    
14,744 15,197 453 3.0% 15,932 15,764 168 1.1%      
99,074 98,955 (119) (0.1%) 133,044 132,856 188 0.1%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 27

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2023  
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 76,419 76,746 327 0.4% 106,222 105,822 400 0.4% Non-Education: The YTD underspend of £42k is due to
delays in recruitment. 
Education:  The £285k YTD underspend is mainly within
staffing budgets in ELC settings, Secondary Schools and
Learning Centres. Under the Scheme of Devolved School
Management (DSM) schools are permitted flexibility at year
end, therefore no forecast variance will be processed in
relation to any remaining underspend.
Premises 6,540 5,835 (705) (12.1%) 8,467 8,299 168 2.0% Non-Education: The YTD underspend of £107k is largely
due to historic water charge refunds.
Education: The £812k overspend is mainly due to repairs
and maintenance costs within schools and capital costs
relating to 1140 Hours expansion - £200k from earmarked
reserves will be drawn down to cover a proportion of this.
£131k is due to Utilities profiling and £120k is due to
profiling of cleaning, grounds maintenance and CRA
budgets. The remainder is offset by underspends
elsewhere.
Supplies and
Services
9,264 9,730 466 4.8% 13,497 13,497 0 0.0% Non-Education: The YTD overspend is £193k. Earmarked
reserves to be drawn down for costs of Council Chambers
ICT Equipment. 
Education: The £659k underspend is mainly due to
underspends in PEF due to profiling and school budgets.
Under the Scheme of Devolved School Management (DSM)
schools are permitted flexibility at year end, therefore no
forecast variance has been processed in relation to this. 
Transport 297 293 (4) (1.4%) 397 397 0 0.0% Non-Education: Outwith Reporting Criteria.
Education: Outwith Reporting Criteria. 
Third Party 31,524 31,666 142 0.5% 41,797 42,177 (380) (0.9%) Non-Education: The YTD underspend of £260k is largely
due to the timing of large payments in respect of NPDO/Hub
contracts and the timing of recharges.
Education: The YTD overspend of £118k is due to
increased demand within Schools Residential
Accommodation.

Page 28

Income (24,970) (25,315) (345) 1.4% (37,336) (37,336) 0 0.0% Non-Education: The YTD over-recovery of income of
£411k is due to the timing of school catering recharges and
Property Fee income.   
Education: The under-recovery of income of £756k is due
to the profile of income for Education Maintenance
Allowances and school meals. Journals at year end are
required to reduce this variance. 
Totals 99,074 98,955 (119) (0.1%) 133,044 132,856 188 0.1%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 29

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – RED VARIANCES AS AT 31 DECEMBER 2023
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Education - Pupil Support 2,636 3,016 (380) (14.4%) Higher than budgeted demand for placements within
Residential Schools.
Education - Schools Central Services 2,393 1,993 400 16.7% Slippage in the use of 100 day promise funding for additional
teachers and support staff that will be fully utilised in 2024-25.
Legal and Regulatory Support - NPDO and Hub
Schools 11,484 11,316 168 1.5% Historic water charges refund paid to NPDO Schools 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 30

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 DECEMBER 2023 
The department has a forecast overspend of £0.940m (1.7%). This is due to an under-recovery of income in Piers & Harbours as a result of a
reduced number of berthings, in Public Conveniences due to the delayed installation of turnstiles, Print & Mail Room due to a shift to digital
communication channels resulting in a reduction in printing activity, reduction in Building Warrant and Fish Export Certificate income and on
TROs in Roads. This is combined with overspends on Pupil Transport driver/escort costs, Temporary Accommodation for Housing Homeless,
Legal costs in Environmental Health, Street Lighting Maintenance, staff costs in Amenities due to high sickness and turnover levels and an
unachievable saving in relation to Depot Rationalisation.  These are partially offset by an over-recovery of vacancy savings, an underspend in
Public Transport payments to operators, underspend in ICT software licences and an underspend in training for A&B Manager courses. 
The department has a year to date overspend of £6.169m (14.7%).  This is mainly due an under-recovery of berthing income in Piers and
Harbours, delays in the processing of recharges to capital within Roads, Housing expenditure incurred in advance of grants being received 
and an overspend in Fleet due to a timing difference between expenditure occurring and recharging services.  
Forecast Outturn Position  Year to Date Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Executive Director (Kirsty
Flanagan) 524 (88) 612 601 11
Head of Customer Support
Services 9,061 9,050 11 11 0
Head of Development and
Economic Growth 8,370 8,676 (306) (150) (156)
Head of Financial Services 6,682 6,682 0 (210) 210
Head of Roads and
Infrastructure Services 31,726 32,983 (1,257) (1,257) 0
Totals 56,363 57,303 (940) (1,005) 65 0%
25%
50%
75%
100%
Executive
Director (Kirsty
Flanagan)
Head of
Customer
Support
Services
Head of
Development
and Economic
Growth
Head of
Financial
Services
Head of Roads
and
Infrastructure
Services
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 31

Key Financial Successes:
During 2022-23 the department had an over-recovery of Planning Fee and Building Warrant income, an over-recovery of NDR commission
due to a successful debt recovery campaign during the year (which focussed on high level debts) plus an over recovery of vacancy savings. 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Ensuring that services spend to budget and do not overspend after the
department had an overspend of £1.5m after automatic earmarkings in
2022-23.
Detailed monitoring in the key areas overspent in 2022-23 to flag up
concerns early and mitigate before becoming an overspend. 
Department / Service ongoing ability to meet future savings / efficiency
requirements.
Monitoring of trends / expenditure levels / service configuration and
the Service Packages Policy Options savings process.
Rising cost of materials, software and consultancy services across the
service will result in a reduction in activity or overspends.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as soon as known.
Financial Services to continue to deliver a high-quality support service
function during a time of substantial uncertainty and challenge arising from
continuing reductions in funding whilst costs are increasing due to ongoing
high levels of inflation and service demand caused by world events.
Ensure the team is operating as efficiently and effectively as
possible by building resilience across the team and working
collaboratively with other services of the Council to support
evidence-based decision making. 
Carry out the improvements identified during the Revenue and
Benefits Business Process Review to maximise income generation
and deliver efficiencies in service provision.
Winter Maintenance costs are difficult to estimate as they are very much
dependant on the weather.  
Close monitoring of Winter Maintenance activity and reporting of the
financial implications through the budget monitoring process. The
Council agreed the winter policy, setting out the intervention level
and locations to be treated.  The number of treatments is determined
by weather conditions. The current budget provision provides for 58
full equivalent runs. There is a sophisticated weather monitoring
system in place consisting of several weather stations, this is
supported by a forecasting and meteorological service which is
collaboratively procured by West of Scotland local authorities.
Dangerous buildings costs as there is no budget for this expenditure and
the council has no control over the demand for the service.
Building Standards, Legal Services and Financial Services are
working closely to manage debt recovery and to consider other
options to minimise corporate risk exposure.

Page 32

Due to the nature of the various components of Waste Management there
are ongoing challenges with:
• The introduction of the Deposit Return Scheme
• Uncertainty with recycling income/ gate fee costs due to the           
volatility of the market
• Challenges in the legislative changes around the disposal of      
Biodegradable Municipal Waste 
To closely monitor all service components of Waste Management
and review the Waste Strategy in conjunction with our contractual
partner Renewi (previously Shanks).

Page 33

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2023
Service
Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director (Kirsty
Flanagan)
Central/Management
Costs
245 143 (102) (71.3%) 524 (88) 612 116.8% Based on the YTD vacancy
savings recovered, it is currently
anticipated that an over recovery
is likely to be achieved in the
region of £400K. There is also a
forecast underspend due to the
receipt of funding for ferries
previously funded internally of
£212k.    
245 143 (102) (71.3%) 524 (88) 612 116.8%  
Head of
Customer
Support Services
Central/Management
Costs
113 129 16 12.4% 174 174 0 0.0% Underspend on payments to
other bodies due to the timing of
payments.
Head of
Customer
Support Services
Communications 192 233 41 17.6% 324 324 0 0.0% Underspend in employee costs
due to vacancies which will be
used to cover future consultancy
costs.
Head of
Customer
Support Services
Customer Service
Centres
1,112 1,056 (56) (5.3%) 1,522 1,585 (63) (4.1%) Under-recovery of income for
recharges for Print and Mail
Room. Shift to digital
communication channels
resulting in reduction in mail and
printing activity but same
recharge model being applied.
Cost pressure to be added for
future years to accommodate
these changes.
Head of
Customer
Support Services
HR 1,958 2,008 50 2.5% 2,678 2,648 30 1.1% Underspend due to pausing
Argyll and Bute Manager
programme and not having to
purchase training modules
Head of
Customer
Support Services
ICT 3,024 2,936 (88) (3.0%) 4,307 4,263 44 1.0% Underspend projected for
software licence purchases.
Head of
Customer
Support Services
Registrars 28 28 0 0.0% 56 56 0 0.0% Outwith Reporting Criteria.    
6,427 6,390 (37) (0.6%) 9,061 9,050 11 0.1%

Page 34

Head of
Development &
Economic Growth
Airports 954 922 (32) (3.5%) 1,210 1,210 0 0.0% Outwith Reporting Criteria.
Head of
Development &
Economic Growth
Building Control (140) (157) (17) 10.8% (144) (94) (50) 34.7% Under-recovery of building
warrant income.
Head of
Development &
Economic Growth
Central/Management
Costs
422 399 (23) (5.8%) 579 579 0 0.0% Outwith Reporting Criteria.
Head of
Development &
Economic Growth
Culture & Heritage 117 162 45 27.8% 228 228 0 0.0% Underspend due to Rothesay
Pavilion not being open - budget
will be earmarked for future
costs once operational.
Head of
Development &
Economic Growth
Development
Management
119 168 49 29.2% 315 315 0 0.0% Over-recovery of planning fee
income due to one-off high value
planning applications.
Head of
Development &
Economic Growth
Development Policy 290 281 (9) (3.2%) 392 392 0 0.0% Outwith Reporting Criteria.
Head of
Development &
Economic Growth
Economic
Development
827 1,270 443 34.9% 1,150 1,150 0 0.0% Underspend is due to grant
income received in advance of
expenditure which is partially
offset against expenditure that
requires draw down from
earmarked reserves.
Head of
Development &
Economic Growth
Environmental
Health
903 777 (126) (16.2%) 1,188 1,294 (106) (8.9%) Overspend due to reduction in
Fish Export Certificate income
Head of
Development &
Economic Growth
Environmental
Initiatives
88 86 (2) (2.3%) 120 120 0 0.0% Outwith Reporting Criteria.
Head of
Development &
Economic Growth
Housing 3,887 3,362 (525) (15.6%) 3,096 3,246 (150) (4.8%) Overspend reflects demand for
the provision of homeless
accommodation which is being
met using Bed and Breakfast
establishments. 
Head of
Development &
Economic Growth
Private Landlords (314) 0 314 0.0% 0 0 0 0.0% Underspend is due to income for
Private Landlord Registration
fees received against a zero
budget.
Head of
Development &
Economic Growth
Transportation
Policy
372 169 (203) (120.1%) 236 236 0 0.0% Overspend is due to expenditure
for SUSTRANS and CWSR

Page 35

incurred in advance of grant
claim.    
7,525 7,439 (86) (1.2%) 8,370 8,676 (306) (3.7%)  
Head of Financial
Services
Accounting &
Budgeting
1,901 1,921 20 1.0% 2,672 2,672 0 0.0% Outwith Reporting Criteria.
Head of Financial
Services
Internal Audit &
Fraud
242 249 7 2.8% 338 338 0 0.0% Outwith Reporting Criteria.
Head of Financial
Services
Revenues & Benefits 2,288 2,410 122 5.1% 3,023 3,023 0 0.0% Underspend is due to Benefits
Admin Government Grants
received ahead of profile & over-
recovery of Council Tax Water
and sewage collection income
due to a new billing order
bringing in more income than
budget.  
Head of Financial
Services
Scottish Welfare
Fund
602 624 22 3.5% 649 649 0 0.0% Outwith Reporting Criteria.    
5,033 5,204 171 3.3% 6,682 6,682 0 0.0%  
Head of Roads &
Infrastructure
Services
Amenity 3,021 2,728 (293) (10.7%) 3,248 3,367 (119) (3.7%) Forecast variance relates to
overspend across amenities for
use of roads staff to cover
vacancies and sickness (£85K),
under-recovery of hire of
facilities income (£28K) and
public convenience income due
to delay with fitting of door
charging mechanism (£40K).  
There is also a high risk of a
CRA overspend in Parks CRA,
no forecast variance entered to
date pending proposed CRA
spend across RIS. At this stage
there is an anticipated over-
recovery of crematorium income
of £34K.  YTD variance higher
than Forecast Variance mainly
due to budget profile out of
alignment with actuals
particularly with Cemeteries and
Crematoria income which is
difficult to profile due to the
nature of the service. Also
payroll variance as pay award

Page 36

exceeds payroll budget
allocated.
Head of Roads &
Infrastructure
Services
Car Parking (292) (456) (164) 36.0% (582) (582) 0 0.0% Overspend due to timing of
income for Electric Vehicle
Chargers where electricity is
paid in advance of receiving the
income which should be rectified
over the financial year.
Head of Roads &
Infrastructure
Services
Central/Management
Costs
2,606 2,384 (222) (9.3%) 3,013 3,013 0 0.0% Overspend is due to the profile
of the income budget which will
be rectified by the end of the
year as well as costs for the RIS
Review Consultants which will
be met from a drawdown from
earmarked reserves.
Head of Roads &
Infrastructure
Services
Depots 303 241 (62) (25.7%) (429) (321) (108) 25.2% Delay in rental income and
timing of expenditure causing
small overspend which will be
rectified over the financial year.
Forecast variance due to saving
for Depot Rationalisation no
longer being achievable in year.
Head of Roads &
Infrastructure
Services
Fleet & Transport 7,008 6,320 (688) (10.9%) 8,624 8,666 (42) (0.5%) Overspend due to the timing of
Fleet recharges to other
services.  Forecast variance for
overspend for additional Pupil
Transport costs which is partially
offset against an underspend in
Public Transport due to a
reduction in payments to
operators.
Head of Roads &
Infrastructure
Services
Infrastructure 286 539 253 46.9% 763 763 0 0.0% Underspend due to the timing of
Flood and Coastal Protection
works which will be rectified over
the financial year.

Page 37

Head of Roads &
Infrastructure
Services
Marine (3,309) (5,125) (1,816) 35.4% (4,350) (3,500) (850) 19.5% YTD variance higher than
projection due to timing of cash
flow in comparison to profiling of
budget and delay in receiving
grant from Transport Scotland.
Forecast overspend due to the
under-recovery of income from
Berthing charges and additional
employee costs to cover
absence.
Head of Roads &
Infrastructure
Services
Network & Traffic
Management
180 66 (114) (172.7%) 129 179 (50) (38.8%) Forecast overspend due to the
under recovery of TRO income
based on current shortfalls in
income to date and prior years'
total income.
Head of Roads &
Infrastructure
Services
Road Safety 82 92 10 10.9% 88 88 0 0.0% Small underspend due to the
timing of PPE purchases.
Head of Roads &
Infrastructure
Services
Roads & Lighting 10,361 7,422 (2,939) (39.6%) 7,092 7,180 (88) (1.2%) YTD overspend due to the
timing of income in comparison
to the profiling of the budget,
mainly due to a delay in
recharges for capital funded
activity which will be rectified
over the financial year. Forecast
variance for overspend in Street
Lighting due to increased levels
of maintenance required to meet
the service's responsibilities. 
Head of Roads &
Infrastructure
Services
Waste 8,721 8,641 (80) (0.9%) 14,130 14,130 0 0.0% YTD variance mainly relates to
private contractor costs,
including co-mingled gate fee
and H&L residual waste, partly
due to profiling of budget and
anticipated tonnages reductions
over winter months. Also payroll
variance partly due to pay award
exceeding payroll budget
allocated (including overtime
arrears).    
28,967 22,852 (6,115) (26.8%) 31,726 32,983 (1,257) (4.0%)      
48,197 42,028 (6,169) (14.7%) 56,363 57,303 (940) (1.7%)

Page 38

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 39

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2023
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 31,566 31,142 (424) (1.4%) 44,179 43,935 244 0.6% YTD overspend in Development Management due to
additional staff whose costs will be offset against additional
Planning income that will be received this financial year and
additional costs in Marine to cover absences, Private
Landlords which will be offset against income and within
Pupil Transport.
The forecast underspend relates to an over-recovery of
vacancy savings, underspend on Staff Training Course Fees
and additional funding received for ferries all partially offset
by overspends in Marine, Pupil Transport and Depot costs
due to a saving not being achieved in year. 
Premises 2,175 2,222 47 2.1% 3,447 3,447 0 0.0% Outwith Reporting Criteria.
Supplies
and
Services
7,813 6,428 (1,385) (21.6%) 8,931 8,887 44 0.5% YTD overspend relates to Economic Development for
expenditure that is funded from grant income; Purchase of
Car Parking Machines that will be offset against budget
sitting in Third Party Payments; costs for the new HR and
Payroll system (covered from an earmarked reserve which
will be drawn down later in the year) and materials in Roads
that is offset against additional income for recharges to
capital.
Forecast variance for an underspend in ICT software
licences.
Transport 9,336 8,365 (971) (11.6%) 16,328 16,328 0 0.0% YTD overspend for vehicle repairs and maintenance in Fleet,
which will be offset against additional income for recharges to
the services and External Hires in Roads that will be offset
against additional income for recharges to capital.
Third Party 47,629 44,324 (3,305) (7.5%) 64,472 64,677 (205) (0.3%) YTD overspend within Economic Development,
Transportation and Housing for expenditure that is funded
from grant income.  Additional external contractor costs in
Roads that will be offset against additional income for
recharges to capital.  These overspends are partially offset
against an underspend in Benefit Payments.
Forecast variance relates to overspends in Street Lighting for
maintenance costs, additional employee costs to cover
absence and vacancies within Amenities and Housing
Temporary Accommodation. These are partially offset by
underspends in Public Transport payments to Bus Operators.

Page 40

Capital
Financing
0 0 0 0.0% 2,398 2,398 0 0.0% Outwith Reporting Criteria.
Income (50,322) (50,453) (131) 0.3% (83,392) (82,369) (1,023) 1.2% YTD under-recovery of income from Berthing charges in
Piers and Harbours and Housing Benefit Income within
Revenues & Benefits which is mainly offset against un-
budgeted income in Economic Development and Housing,
which will fund expenditure throughout the year. 
Forecast variance relates to the under-recovery of income in
Piers and Harbour for Berthing, under-recovery of income
from door entry systems within Public Conveniences and
under-recovery of income from TROs, Building Warrants and
Fish Export Certificates.
Totals 48,197 42,028 (6,169) (14.7%) 56,363 57,303 (940) (1.7%)   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 41

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – RED VARIANCES AS AT 31 DECEMBER 2023 
Service Area
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Vacancy Savings (251) (651) 400 (159.4%) Over-recovery of vacancy savings.
Public Transport 5,266 5,118 148 2.8% Underspend in Operator Payments.
Pupil Transport 1,020 1,210 (190) (18.6%) Overspend in transport costs for drivers/escorts.
Piers & Harbours (2,655) (1,905) (750) 28.2% Under-recovery of income from Berthing charges.
Street Lighting 262 350 (88) (33.6%) Overspend on maintenance costs.
Traffic Regulation Orders (110) (60) (50) 45.5% Under-recovery of income from Traffic Regulation Orders.
Depots (108) 0 (108) 100.0% Proposed saving for Depot Rationalisation no longer being
achievable in year.
Central Management Costs 48 (153) 201 418.8% Underspend due to receipt of funding for ferries previously
funded internally.
Piers & Harbours 408 508 (100) (24.5%) Overspend in employee costs to cover absences.
Housing 27 102 (75) (277.8%) Overspend for Temporary Accommodation costs in
Homelessness.
Environmental Health (128) (38) (90) 70.3% Reduction in Fish Export Cetificate income as a
consequence of the UK leaving the EU. 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 42

SOCIAL WORK – AS AT 31 DECEMBER 2023 
The department is currently forecasting to break even at the end of the financial year. This is due to a combination of the over-recovery of
vacancy savings, income from fees, charges and recharges and the use of non-recurring reserves to offset cost pressures due to high demand
for services and the use of agency staff to fill staffing recruitment and retention gaps across Adult Services.   
The department has a year to date overspend of £0.045m (0.1%) which is mainly due to the use of agency staff across Homecare and Older
People Residential Units in Adult Services. 
Forecast Outturn Position 
Service Annual
Budget
£000
Forecast
Outturn
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change
£000
Chief Officer Integration 278 (183) 461 461 0
Head of Strategic Planning
and Performance 480 472 8 8 0
Head of Health and
Community Care 39,125 40,727 (1,602) (1,602) 0
Head of Acute and
Complex Care 19,812 19,321 491 491 0
Head of Children and
Families 16,422 15,780 642 642 0
Totals 76,117 76,117 0 0 0
Year to Date Position 
Key Financial Successes: 
Delivered an underspend of £3.556m at the end of 2022/23 after automatic earmarkings of £1.078m. The total underspend of £4.634m has
been transferred to IJB reserves and should allow for future investment and transformation across Social Work. 
-60%
-35%
-10%
15%
40%
65%
90%
115%
Chief Officer
Integration
Head of Adult
Services
Head of Children
and Families
Head of Strategic
Planning and
Performance
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 43

Key Financial Challenges: Proposed Actions to address Financial Challenges:
Deliver the outstanding savings total for 2023/24 of £0.621m (as at
December 2023).
Maintain a close working relationship with the HSCP Service
Improvement Team to quickly and efficiently identify and assess
options for delivering the outstanding savings. 
Development and delivery of future service redesigns which will be
necessary to contain service expenditure within the allocated resource,
noting that in year savings still need to be identified for 23/24 to address
the 23/24 budget gap, as well as budget gaps in future years. 
Support from finance to assist strategic managers to develop and
identify further savings and to look beyond the short term to identify
and plan the changes which will be needed to address the expected
ongoing budget challenges over the current, and future, years.
Use of agency staff to support service delivery across Social Work, but
particularly in Older People services, due to recruitment and retention
challenges within the service. Year to date spend at December 2023 of
£2.288m. 
Close working relationship with the HSCP to support the costing of
a plan to stabilise the service and ensure it is operationally and
financially sustainable. This includes an exit plan from the reliance
on agency staff. 
Cost of living crisis affecting pay inflation negotiations and financial
sustainability of service providers, which could affect affordability and
sustainability of service delivery. 
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.

Page 44

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 DECEMBER 2023
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Officer
Integration
Integration
Headquarters
241 409 168 41.1% 569 577 (8) (1.4%) The YTD variance is as a result of timing
differences on planned payments to NHS. The
forecast variance is outwith reporting criteria.
Chief Officer
Integration
Social Work
Central
Support
(856) (579) 277 (47.8%) (291) (760) 469 (161.2%) The YTD variance is due to over-recovery on
vacancy savings combined with underspends
on centrally held funding.  The forecast
underspend is due to an over-recovery on
vacancy savings (£248k) combined with
underspends on centrally held funds, printing
& stationery and postages. 
(615) (170) 445 (6.8%) 278 (183) 461 (162.6%)  
Head of
Strategic
Planning &
Performance
Management
& Central
Costs
314 312 (2) (0.6%) 446 447 (1) (0.2%) Outwith reporting criteria.
Head of
Strategic
Planning &
Performance
Service
Development
23 31 8 25.8% 34 25 9 26.5% The YTD and forecast variances are due to
staff vacancies resulting in both a payroll
underspend and an under-recovery on
Charges to Health Boards.    
337 343 6 25.2% 480 472 8 26.2%  
Head of
Health and
Community
Care
Management
& Central
Costs
422 896 474 52.9% 1,303 552 751 57.6% The YTD variance is mainly due to
underspends on centrally held funds.  The
forecast underspend is mainly due to
underspends on centrally held funds and staff
vacancies. 
Head of
Health and
Community
Care
Older People 25,015 23,235 (1,780) (7.7%) 37,822 40,175 (2,353) (6.2%) The YTD variance reflects demand within the
care home placement and homecare budgets
and overspends on employee costs due to the
use of agency staff in residential units and
homecare. The forecast overspend reflects
demand driven overspends within the care
home placement budgets (£1.1m) and
homecare (£1.6m). High staff costs across
HSCP residential units due to agency cover
are also contributing to forecast overspend.
These overspends are partially offset by
staffing underspends across ACM teams and

Page 45

underspends on payments to other services
from the delayed discharge budgets. 
25,437 24,131 (1,306) (5.4%) 39,125 40,727 (1,602) (4.1%)  
Head of
Acute and
Complex
Care
Learning
Disabilities
7,014 7,447 433 5.8% 14,174 13,592 582 4.1% The YTD variance reflects demand for
residential placements partially offset by
demand for supported living.  The forecast
underspend reflects known demand for
Residential Placements partially offset by
overspends on Supported Living and Respite
due to demand. 
Head of
Acute and
Complex
Care
Management
& Central
Costs
63 95 32 33.7% 130 102 28 21.5% Both the YTD and forecast variances are due
to underspends in areas such as printing and
stationary, travel and payments to other
bodies.
Head of
Acute and
Complex
Care
Mental Health 1,560 1,520 (40) (2.6%) 2,720 2,761 (41) (1.5%) Outwith reporting criteria.
Head of
Acute and
Complex
Care
Physical
Disability
1,800 1,746 (54) (3.1%) 2,788 2,866 (78) (2.8%) The YTD variance reflects demand for service
within the supported living budgets and
overspends on purchases within the IES store.
This is partially offset by underspends in the
residential budget.  The forecast overspend
reflects higher than budgeted demand for
Supported Living and higher than budgeted
equipment purchasing in the Integrated
Equipment Service. These are offset slightly
by a forecast underspends in the Residential
Care budgets. 
10,437 10,808 371 33.8% 19,812 19,321 491 21.3%  
Head of
Children &
Families
Child
Protection
2,326 2,507 181 7.2% 3,674 3,393 281 7.6% The YTD variance is as a result of payroll
underspends due to vacancies as well as
underspends on travel and subsistence
combined with demand for services across
contact & welfare. The forecast underspend is
as a result of demand for contact and welfare
services as well as forecast underspends in
the Area Teams on payroll costs, payments to
other bodies, travel and subsistence.
Head of
Children &
Families
Children with
a Disability
681 648 (33) (5.1%) 983 1,026 (43) (4.4%) Outwith reporting criteria.

Page 46

Head of
Children &
Families
Criminal
Justice
192 193 1 0.5% 224 172 52 23.2% The YTD variance is outwith reporting criteria.
The forecast underspend is due to vacancies
within the Criminal Justice team. 
Head of
Children &
Families
Looked After
Children
5,596 5,830 234 4.0% 7,832 7,507 325 4.1% The YTD variance is as a result of demand for
fostering, kinship and adoption placements as
well as YTD over-recovery of income for
provision of nursery meals. This is combined
with payroll underspends due to vacancies
and long term absence.  The forecast
underspend is as a result of demand for
fostering, kinship and adoption placements as
well as on supporting young people leaving
care. There is also an over-recovery on
income from the Home Office for
unaccompanied asylum seeking children. This
is all partially offset by demand for external
residential placements and payroll overspends
in the children's houses. 
Head of
Children &
Families
Management
& Central
Costs
2,312 2,368 56 2.4% 3,709 3,682 27 0.7% The YTD variance is as a result of the receipt
of grant income in advance of budget profile.
The forecast variance is outwith reporting
criteria.    
11,107 11,546 439 3.8% 16,422 15,780 642 3.9%  
GRAND
TOTAL   46,703 46,658 (45) (0.1%) 76,117 76,117 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 47

SOCIAL WORK – SUBJECTIVE SUMMARY AS AT 31 DECEMBER 2023 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 26,109 25,010 (1,099) (4.4%) 34,990 36,089 (1,099) (3.1%) The YTD overspend is due to the use of
agency staff across the HSCP (£2.2m YTD
variance; £2.8m forecast), partially offset by
over-recovery on vacancy savings and
payroll underspends due to vacancies. The
forecast underspend is mainly due to
forecast payroll underspends and over-
recovery of vacancy savings offset by
agency costs. 
Premises 1,187 834 (353) (42.3%) 1,544 1,848 (304) (19.7%) The YTD overspend is mainly due to
overspends on utilities, central repairs and
property maintenance. The forecast
overspend is due to anticipated overspends
on utilities due to current market conditions
as well as on central repairs and property
maintenance. Some of the utility overspend
is offset by an over-recovery on income for
recharges to other bodies for shared costs. 
Supplies &
Services
1,567 1,091 (476) (43.6%) 1,439 2,110 (671) (46.6%) The YTD and forecast overspend is mainly
due to forecast slippage on agreed savings
targets within C&F and homecare in addition
to higher than budgeted purchase of
equipment in the integrated equipment store
and telecare.
Transport 443 504 61 12.1% 683 569 114 16.7% The YTD and forecast underspend is due to
various travel underspends across the whole
department following changes to working
practices post Covid-19 and the number of
staff vacancies.
Third Party 39,699 39,819 120 0.3% 61,895 62,238 (343) (0.6%) The YTD underspend is largely due to
budget profiling and timing of payments to
third parties across purchased care services.
The forecast overspend is as a result of
demand for purchased care services across
Adult Services and residential care with
C&F. This is partially offset by underspends
in Fostering and Adoption as well as
underspends on unallocated centrally held
funds.

Page 48

Income (22,302) (20,600) 1,702 (8.3%) (24,434) (26,737) 2,303 (9.4%) The YTD and forecast over recovery of
income is mainly due to increased income
from fees, charges and recharges.
Totals 46,703 46,658 (45) (0.1%) 76,117 76,117 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.  
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 49

SOCIAL WORK – RED VARIANCES AS AT 31 DECEMBER 2023
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Social Work Central
Support (320) (789) 469 (146.6%)
The forecast underspend is due to an over-recovery on vacancy savings (£248k)
combined with underspends on centrally held funds, printing & stationery and
postages. 
Management & Central
Costs 1,303 552 751 57.6% The forecast underspend is mainly due to underspends on centrally held funds and
staff vacancies. 
Older People 37,829 40,182 (2,353) (6.2%)
The forecast overspend reflects demand driven overspends within the care home
placement budgets (£1.1m) and homecare (£1.6m). High staff costs across HSCP
residential units due to agency cover are also contributing to the forecast overspend.
These overspends are partially offset by staffing underspends across ACM teams
and underspends on payments to other services from the delayed discharge budgets. 
Learning Disability 14,189 13,607 582 4.1% The forecast underspend reflects known demand for Residential Placements partially
offset by overspends on Supported Living and Respite due to demand. 
Physical Disability 2,792 2,870 (78) (2.8%)
The forecast overspend reflects higher than budgeted demand for Supported Living
and higher than budgeted equipment purchasing in the Integrated Equipment
Service. This is offset slightly by a forecast underspend in the Residential Care
budgets. 
Child Protection 3,674 3,393 281 7.6%
The forecast underspend is as a result of demand for contact and welfare services as
well as forecast underspends in the Area Teams on payroll costs, payments to other
bodies, travel and subsistence.
Criminal Justice 224 172 52 23.2% The forecast underspend is due to vacancies within the Criminal Justice team. 
Looked After Children 7,832 7,507 325 4.1%
The forecast underspend is as a result of demand for fostering, kinship and adoption
placements as well as on supporting young people leaving care. There is also an
over-recovery on income from the Home Office for unaccompanied asylum seeking
children. This is all partially offset by demand for external residential placements and
payroll overspends in the children's houses. 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 50

MONITORING OF SAVINGS – AS AT 31 DECEMBER 2023
New policy savings were identified for the three year period 2023-24 to 2025-26 and these were agreed by Council in February 2023.  Council
agreed to policy savings of £6.145m in 2023-24 rising to £6.260m by 2025-26. 
The position of historical policy saving options is as follows:
- 2022/23 – those not delivered or that have further increases in value in 2023-24 onwards total £0.187m
- 2021/22 – those not delivered or that have further increase in value in 2023-24 onwards total £0.195m
- 2020/21 – those not delivered total £0.050m
- 2019/20 – all delivered
- 2018/19 - those not delivered total £0.376m
The 2023-24 savings have been removed from departmental budgets, however, it is important to monitor whether the saving has actually been
delivered to ensure that costs are not continuing resulting in an overspend by the end of the year.  It is also important to ensure that any
preparatory work required to deliver savings in future years is on track. 
There are two savings where the department has indicated they will not be achieved, two are categorised as having a potential shortfall and one
is currently delayed as summarised below: 
Saving Saving
Agreed
Status Detail Shortfall/
Delayed
Value
TB07 – Depots  Feb-18 Will not be achieved  Savings to date via the Oban project, tidying up NDR costs form
previous disposals and removing security costs. 
The remainder of the outstanding saving is based on removing the
smallest depot budget from each town but cannot do this without the
capital investment to create fit for purpose single depot facilities.   
Working through possible alternative delivery model and updated
business case for Lochgilphead – there is a shortfall between
possible capital costs and likely income from vacated sites. 
This saving will not be achieved and a cost pressure has been put
through for this for 2024-25.  Work will be ongoing on the depot
rationalisation across the area and future savings will be brought
once known. 
£107,500

Page 51

R&I17 - Public transport
fare scale increase
Feb-21 Will not be achieved   Fare increase did not offset the saving advised by the Stantec review. 
This saving will not be achieved and shortfall has been absorbed by
underspends elsewhere in the service.
£29,000
TB13b Roads and
Amenity Services
charging (non-statutory
services)
Feb-18 Potential Shortfall -
there is a risk that the
original saving will not
be achieved in full.  
The original proposal was to introduce charges for providing lighting
design and increase charges by 20% for road construction consents,
skips, scaffolds, hoarding, permits and licences. Whilst some
additional income has been generated through third party works,
opportunities are expected to be limited over the foreseeable future
due to staff shortages and other competing demands.
£150,000
TB12b Stadiums Feb-18 Potential Shortfall -
there is a risk that the
original saving will not
be achieved in full.  
Discussions had stalled with partners in the Oban and Lorn area with
regard to Mossfield stadium to create a sports Hub, attract external
funding to improve facilities and therefore attract additional events to
the arena.  The users group has now reconvened and will be
reporting to the steering group. It should be noted there is generally a
downturn in usage of pitches partly due to more clubs booking all
weather pitches at high schools and the loss of a well established
club disbanding which will result in the loss of income. The Mossfield
Sport Group have highlighted that certain clubs along with the Shinty
Associations have expressed concerns with regards to the condition
of the Pavilion and changing facilities and this is likely to impact on
income.  East King Street bookings have reduced due to the
condition of the changing facilities and clubs having to play their
fixtures elsewhere.
£30,000
TB09 – Public
Conveniences
Feb-18 Delayed - The full
saving will not be
achieved in line with
the original estimated
timescale.  
Door access control project has an indicative start date of November
for installs.   This delay has missed the busy summer months and
October holidays so expected income over winter will be minimal. We
have no way to accurately predict income levels but the system
allows for regular reporting and itemisation so we will quickly be in a
position to profile future income.
£24,000 
All policy saving options previously agreed are noted in the table below for information.

Page 52

2023-24 2023-24
£000 FTE
Executive Director Douglas Hendry
CS01 Feb-22 Commercial
Services
Climate Change & Resource Efficiency 63.0 0.00 On Track to be Delivered
CS03 Feb-22 Commercial
Services
Stretch Targets for One Council Income &
Events
20.0 0.00 Delivered
EDU2324-001 Feb-23 Education Estimated saving due to change in pupil
numbers
700.00 0.0 Delivered
EDU2324-002 Feb-23 Education Removal of non-statutory Cultural
Coordinator post.
15.00 0.8 Delivered
Executive Director Kirsty Flanagan
DEG05(a) Feb-20 Development
and Economic
Growth
Raise additional fees by adopting the
current Building Cost Information Service
(BCIS) guide for the cost of building work.
Regular service users have been
informed of this change.
50.00 0.0 Delivered
DEG07 Feb-21 Development
and Economic
Growth
Additional income through fees and
charges for s64 Non-Material Amendment
Submissions, non e-planning application
submissions and property history
searches
28.00 0.0 Delivered
DEG01 Feb-22 Development
and Economic
Growth
Crown Estate Administration Contribution
to Project Delivery
104.0 0.00 Delivered
DEG2324-002 Feb-23 Development
and Economic
Growth
Reduce discretionary budget to minimum.
Retain budget to pay memberships to
SCDI, SLAED & HOPS but remove
remainder of discretionary budget.
21.50 0.0 Delivered
DEG2324-001 Feb-23 Development
and Economic
Growth
Long-term vacant 0.5FTE building
standards surveyors post that arose
through an employee reducing their
working hours is no longer requires in
structure.
24.00 0.5 Delivered
FIS2324-001 Feb-23 Financial
Services
Service Concessions - Alteration to
accounting treatment to align the
repayment of borrowing relating to new
schools over their asset life.  Guidance
from Scottish Government now permits
this change of accounting treatment. 
Further detail will be provided to Council in
due course.
4,831.00 0.0 Delivered
FIS2324-002 Feb-23 Financial
Services
The Service has identified savings
through rightsizing of budgets, an
organisational restructure with investment
in modern apprenticeships and temporary
staff designed to boost income from the
billing of additional local taxes and the
recovery of associated debt. In addition
efficiency savings from increased
productivity, increased levels of process
automation and moving more customers
to transact with the service over the
internet will allow previously outsourced
review works to be carried out internally.
493.00 0.0 On Track to be Delivered
TB07 Feb-18 Roads and
Infrastructure
Services
Create one main depot in key areas to
reduce costs
172.50 0.0 Will not be achieved
TB13b Feb-18 Roads and
Infrastructure
Services
Roads & Amenity Services charging (non-
statutory services)
150.0 0.00 Potential Shortfall
TB12b Feb-18 Roads and
Infrastructure
Services
Review charges for stadiums to enable
improvement work
30.00 0.0 Potential Shortfall
TB09 Feb-18 Roads and
Infrastructure
Services
Public Conveniences - Progress
sustainable models including turnstiles
and franchising; establish simpler asset
transfer process
24.00 0.0 Delayed
R&I17 Feb-21 Roads and
Infrastructure
Services
Public transport fare scale increase 76.00 0.0 Will not be achieved
R&I05 Feb-21 Roads and
Infrastructure
Services
Design service fees - bringing in line with
industry standards and reduce cost of
consultancy. Two posts created as a
spend to save
50.00 -2.0 Delivered
R&I09 Feb-21 Roads and
Infrastructure
Services
Road inspections find and fix -  reduce
reactive work by proactivity. Moving to AI
technology as technology develops
40.00 1.0 On Track to be Delivered
R&I15 Feb-21 Roads and
Infrastructure
Services
Emergency services support and fuel
provision from our fuel supplies
0.50 0.0 Still to be Implemented
RIS2324-001 Feb-23 Roads and
Infrastructure
Services
Support Communities to move to different
approaches to delivering School Crossing
Patrols through engagement with Parent
Council and Communities.
60.00 1.5 On Track to be Delivered
TOTAL 6,952.5 1.8
Template Ref Saving
Agreed
Service Savings Option Status of Implementation

Page 53

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE 
15 FEBRUARY 2024
FINANCIAL RISKS ANALYSIS 2023-24  
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to provide a summary of the key financial risks
facing the Council.   
1.2  A number of Council wide risks, both revenue and capital, have been identified
along with risks for each department and service of the Council.  For each
departmental risk the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix. 
1.3 There are 5 Council wide revenue risks identified for 2023-24 currently amounting
to £2.835m. 
1.4 There are currently 39 departmental risks totalling £5.265m.  Of the 39
departmental risks, 6 are categorised as likely.   
1.5 The financial risks are monitored routinely and actions put in place to continue to
mitigate the risks.

Page 54

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE 
15 FEBRUARY 2024
FINANCIAL RISKS ANALYSIS 2023-24  
2. INTRODUCTION 
2.1 This report outlines the process and approach developed in carrying out a
financial risks analysis and provides a note of the current assessment of financial
risks for 2023-24. 
3 DETAIL 
3.1 Introduction 
3.1.1 The Council is currently in a period of significant financial challenge.  In
developing its budget to address both restricted resources and cost and demand
pressures there are a number of financial risks the Council needs to consider and
manage. 
3.1.2 There are a number of risks that affect the income or expenditure across the
whole council and these have been identified.  Financial risks have been
considered by each department and service of the Council.   
3.1.3 For each risk, the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix as follows: 
1 – Remote
2 – Unlikely
3 – Possible
4 – Likely
5 – Almost Certain 
3.1.4 The Argyll and Bute Integrated Joint Board (IJB) with responsibility for Social
Work and a range of Health services was established and came into effect on 1
April 2016.  The IJB is responsible for financial and strategic oversight of these
services.  It is the responsibility of the IJB to consider the individual financial risks
associated with Integration Services and they are therefore not contained within
this report.  A Council wide risk has been included in respect of the IJB being
unable to deliver the social care service within the budget allocated. 
3.2 Council Wide Risks 
Revenue  
3.2.1 Utility costs remain a volatile area and it is difficult to accurately predict how the
prices could vary.  The outturn in respect of utilities for 2022-23 was an overspend
of £0.597m which was due to the unprecedented inflationary uplifts within the

Page 55

energy market although forward purchasing sheltered the Council from the full
impact.  During 2023-24 the Council re-contracted for its energy needs and was
exposed to significantly higher market rates creating an in year cost pressure of
£0.936m with a proposal to fund this from the £1.4m contingency set aside for
inflationary increases as part of the 2023-24 budget setting process. With the
volatility of utilities pricing it is very difficult to predict the impact going forward but
a financial risk based on a 20% variation based on the original utilities budget
amounts to £0.827m. 
3.2.2 The SJC pay award for 2023-24 is now settled and the budgets will be updated in
the January period to reflect the additional staff costs and offsetting associated
Scottish Government income.  Initial workings have indicated that the funding will
offset the additional costs and there will be no in-year pressure resulting from the
pay award.   
3.2.3 At the budget meeting on 24 February 2023, the Council agreed 6 new policy
savings options that would deliver savings over the period 2023-24 to 2025-26. 
The savings to be delivered in 2023-24 amount to £6.145m.  Whilst the Council
have a good track record in delivering savings, a 10% shortfall on this savings
target would amount to £0.615m. 
3.2.4 The estimated level of council tax income is based on current and forecast Band
D equivalents and non-payment rates.  This reflects our most recent experience in
terms of the council tax base and likely collection rates.  A 1% variation in council
tax income amounts to approximately £0.593m.  
3.2.5 In respect of the Health and Social Care Partnership, it is the responsibility of the
Chief Officer and Chief Financial Officer to manage the HSCP financial position. 
If an overspend is forecast, a budget recovery plan will be prepared and
submitted to the IJB, the Council and NHS Highland.  Where recovery plans are
unsuccessful and an overspend occurs at the financial year end, and the HSCP
has insufficient reserves to meet the overspend, then the partners will be required
to make additional payments to the HSCP.  Whilst any additional payments by the
Council and NHS Highland will be deducted from future years funding, there is still
a financial risk that the Council may have to pay out additional monies in year.  As
at 31 December 2023, the net HSCP outturn in 2023-24 is estimated to be a
£0.443m overspend (Social Work forecasting a breakeven position and an
overspend of £0.443m from Health).  As Social Work are currently projecting a
breakeven position and the IJB holds significant financial reserves, there is a nil
value on the risk.   
3.2.6 There is an ongoing requirement to fund unavoidable inflationary cost increases in
areas like fuel, food etc. This has been predominantly caused by the lack of
availability of supply of labour and materials as a result of the COVID-19
pandemic, the UK exit from the European Union, Russia’s invasion of Ukraine and
sanctions on Russian owned entities and ongoing events in the Middle East. 
Inflation has been falling and the Bank of England estimates that it should
continue to fall this year.  We will continue to closely monitor the situation and
update our financial forecasts using the best information available to us. A 1%
general inflation increase has been included with a financial impact of £0.800m.

Page 56

3.2.7  The Council wide risks are noted within the table below.   
Description Likelihood Assessed
Financial Impact
£000
Energy costs increase by 20% greater
than anticipated
3 827
10% shortfall on Savings Options 2 615
1% variation in Council Tax Income 2 593
IJB refer to Council for additional
funding to deliver social work services
1 0
1% variation of General Inflation Risk  4 800
Total  2,835 
Capital  
3.2.8 The finance settlement announcement on 20 December 2022 provided details of
the Local Government funding for 2023-24 and there is therefore certainty as to
what our funding is in respect of the General Capital Grant and the specific capital
grants already distributed. 
3.2.9  The capital plan for 2023-24 includes an estimate of £1.195m in respect of capital
receipts.   This is based on an assessment provided by the Special Projects Team
in January 2023.  A 10% variation equates to £0.120m and this would require to
be managed across the capital programme.   
3.2.10  General feedback from Scotland Excel and the Project Managers indicates that
price increases and uncertainty continue to be experienced as well as disruptions
to the supply chain and longer lead times, particularly in relation to the
construction sector and material availability. This can be attributed to a number of
factors such as the drag on markets and supplies of the COVID-19 pandemic, UK
exit from the European Union, Russia’s invasion of Ukraine and sanctions on
Russian owned entities and ongoing events in the Middle East, to name a few.
3.2.11  The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all have an effect on the overall contract price
and make it extremely challenging to manage expenditure and the availability of
supply. 
3.2.12 While it has been possible to estimate the impact of these pressures on some
projects, and therefore either include those projections within the capital
monitoring report or adjust the capital programme accordingly, for others it is
more difficult and no forecast has been projected at this stage but there are likely
to be further significant financial impacts not yet reported. 
3.2.13 Surveys have been completed in the Councils Learning Estates in relation to
Reinforced Autoclaved Aerated Concrete (RAAC) with only 1 building confirmed
as having it present with steps underway for its removal. This will include a decant

Page 57

of the students for approximately 9 months plus total removal and replacement of
the roof during 2024. The estimated costs associated with this are £3m which will
require additional funding. The Council is also currently undertaking both desktop
and on-site assessments to establish if RAAC is elsewhere in the Estate in over
650 buildings with priority being given to categories of building where there is high
and sustained footfall. No RAAC has been confirmed in these categories of
building thus far.  
3.3  Departmental/Service Risks 
3.3.1 The detail of each departmental financial risk is included within Appendix 1.  The
following table provides a summary of the number of risks within each department
and likelihood category with the financial impact. 
Department 1 - Remote 2 - Unlikely 3 - Possible 4 - Likely 5 - Almost
Certain Total
No £000 No £000 No £000 No £000 No £000 No £000
Chief Executive's
Unit 0 0 0 0 0 0 0 0 0 0 0 0
Executive Director
Douglas Hendry 2 20 6 560 7 600 5 565 0 0 20 1,745
Executive Director
Kirsty Flanagan 5 335 2 230 11 2,590 1 365 0 0 19 3,520
Total 7 355 8 790 18 3,190 6 930 0 0 39 5,265 
3.3.2 The current top three risks in terms of the financial impact are noted in the table
below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads
Maintenance -
Bridges, Culverts
& Sea Defences
Extreme localised weather may
result in loss of bridge, culvert,
road or sea defence.
3 750
Roads and
Infrastructure
Services
Waste PPP -
Indexation
Historical payments made
towards Waste PPP based on
indexation rates have been
challenged by Renewi resulting
in a potential cost to the council.
3 586
Roads and
Infrastructure
Services
Winter
Maintenance
Adverse weather conditions
which require greater than
budgeted number of gritting
runs.
4 365

Page 58

3.3.3 The risks which are likely, but not included above, are noted below: 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Council Wide -
Commercial
Services
Council Wide
Central Repairs
Increased demands on central
repair budgets (CRA) due to a
decrease in Capital funding,
increase in statutory and
emergency repairs and
increases in supplier/contractor
charges.  This impacts on all
departments of the Council with
a Central Repairs Budget.
4 300
Legal and
Regulatory
Support
Contract RPI for
NPDO and Hub
Schools
Increase in RPI would result in
higher costs.
4 100
Legal and
Regulatory
Support
NPDO -
Reduction in
insurance
savings within
NPDO Schools
Increase in insurance costs as a
result of the long-term effects
of Covid-19 on the insurance
market and flood claims.
4 75
Legal and
Regulatory
Support
Elections More than 1 by-election
required outwith standard
election cycle.
4 60
Legal and
Regulatory
Support
Licensing Reduced numbers of licensing
applications leading to reduced
income.
4 30     
3.4  Changes to Financial Risks since last report 
3.4.1 There have been no changes to the departmental risks since the financial risks
report was presented to the Policy and Resources Committee on 7 December
2023.  
3.5 Monitoring of Financial Risks 
3.5.1  Financial risks will be reviewed and monitored on a two monthly basis and will be
included in the pack of financial reports submitted to Policy and Resources
Committee.

Page 59

3.5.2  During the 2023-24 budget setting process a contingency of £1.4m was agreed
which was circa 0.5% of the Councils budget at that time. This was included due
to the volatility in prices, the increases in inflation together with continuing
increased demand. The risk associated with Winter Maintenance will be
monitored closely over the coming months and should it materialise it is
recommended that this contingency is used to offset the pressure.  
3.6 Potential Future Risks 
3.6.1 Scottish Government are, over the next 2 years, proposing to extend funded
childcare to all 1 and 2 year olds across Scotland. This brings significant financial
and qualitative risks to the service. The needs and legislative requirements for this
age range would mean significant capital work across our estate and in many
settings there is not the space so extensions would be required. Having this age
range in the same play space as 3/4 year olds seriously impacts on the ability of
practitioners to effectively support age appropriate learning and play. It is
uncertain when this risk will arise. 
3.6.2 The Council’s bid to the Scottish Governments Learning Estate Investment
Programme (LEIP) for funding for a new school campus on Mull was successful.
While this is good news and will provide welcome investment in the school estate
it does come with a financial pressure that is required to be funded if the project is
to proceed. The Scottish Government will fund up to 50% of eligible costs leaving
the Council to fund circa £20m therefore Council need to consider full affordability
options before agreeing to progress with this project. There are £9m in earmarked
reserves set aside for this purpose with funding required for the remaining
balance. A paper outlining possible funding options will be presented to Council in
due course. 
3.6.3  As a result of significant rainfall Argyll and Bute Council activated the Bellwin
scheme in relation to the recovery of costs associated with the incident. The
funding from this scheme is welcomed however eligibility criteria of costs are
restrictive. Primarily the first £0.529m has to be covered by the Local Authority of
which £0.398m has been identified from Crown Estates funding with the
possibility this could be topped up further once the Crown Estate full year
allocation of funding is confirmed. Secondly, capital expenditure does not qualify
therefore any long term replacements to infrastructure such as bridges cannot be
claimed through the scheme therefore if not already part of the capital programme
will require funding. Estimated costs were submitted to the Scottish Government
on 5 December 2023 along with a request to extend the scheme by ten months to
allow for all works to be completed.  The Scottish Government have subsequently
rejected this request and will only extend the claim by two months. The revenue
costs are being finalised but there is a risk that costs of circa £0.900m in revenue
could extend beyond the claim period and therefore may not be eligible for the
scheme.   
3.6.4 In its present configuration, Argyll and Bute Council’s digital network does not
have the capacity to accommodate the requirements of the Scottish
Government’s vision for digital access over the next four years, including a device

Page 60

for every learner, which would entail a large increase in the number of devices
accessing the network. The network requires to be redesigned to allow digital
access on the scale proposed by the Scottish Government. In addition to
investment in bandwidth, device management and protection, there is a
requirement to replace existing network hardware in all schools. Following an
independent consultation on the network by Insight, IT and Education have co-
authored a paper “Resourcing Educations Digital Aspirations” that identifies the
work required to meet the Scottish Governments expectations. COSLA have
raised this issue with the Scottish Government and there is an expectation that
this will be fully funded as it is a Scottish Government commitment but there
remains a risk associated with this. 
4 CONCLUSION 
4.1 This report summarises the key financial risks facing the Council.  There are 5
Council wide risks and 39 departmental risks identified with 6 categorised as
likely.  The financial risks are monitored routinely and actions put in place to
continue to mitigate the risks.   
5 IMPLICATIONS 
5.1 Policy - None.
5.2 Financial -  The financial value of each risk is included within the
appendix.   
5.3 Legal -  None.
5.4 HR -  None.
5.5 Fairer Scotland Duty - None.
5.5.1 Equalities – protected
characteristics - 
None.
5.5.2 Socio-economic Duty -  None.
5.5.3 Islands -  None.
5.6 Climate Change - None.
5.7 Risk -  Financial risks are detailed within the appendix.
5.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
12 January 2024 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
APPENDICES
Appendix 1 – Detail of Department/Service financial risks 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 61

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 DECEMBER 2023
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Commercial Services Catering Costs - Provision of
Meals to Early Years Children
The Children and Young People (Scotland) Act placed duties
on Councils to provide meals in an Early Years setting to
entitled children where sessions span over lunch time.  The
total quantum of grant funding is reducing and may not be
sufficient to fund the additional costs depending on uptake
and the additional costs to support the meal provision in
partner provider settings.
Joint strategy with procurement colleagues to reduce
potential impact of supplier charges.  Control food
wastage/portion controls.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Catering Purchases Increased supplier charges and higher than average inflation
on food costs.  In addition to this the Scottish Government
reviewed the regulations that govern the food and drinks
provided in schools and implemented revised regulations. 
The revised standards focus on reducing sugar, reducing red
processed meat and increasing fibre. Thus far, there has
been an increase in costs in produce and a reduction in
demand for school meals.
Joint strategy with procurement colleagues to reduce
potential impact of supplier charges.  Control food
wastage/portion controls; introduction of online ordering to
help manage food waste. Analysis and regular review of
menu choices.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Catering - Implementation of
Universal Free School Meals in
Primary Schools for P6 and P7
pupils
The Scottish Government may not give the local authority
adequate funds to support the policy to expand free school
meals in primary schools to include P6 and P7 pupils (the
scheme has already been implemented for P1 to P5 pupils).
Although expansion paused for full implementation for
P6&7, FSM expanded through entitlement to Scottish Child
Payment.
Senior manager connected into the National Operational
Delivery Group.  This enables the Council's viewpoint to be
considered.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Rental Income from Properties Due to current economic climate, there may be reduced
ability to recover rental income from leased properties or
place suitable tenants in properties as leases come to an
end.
Management of leasehold properties by Estates team, any
issues with debt recovery being dealt with in line with
Council debt recovery policy.
2 60 2 60
Executive Director
Douglas Hendry
Commercial Services Surplus Properties Ongoing market difficulties lead to increased numbers of
surplus properties, in addition, as Our Modern Workspace
Project gains traction more properties will become surplus
to operational requirements. There are residual running
costs associated with all surplus properties.
One Council property team in place who will monitor market
conditions and work with prospective tenants/ purchasers to
let/sell surplus properties.
3 50 3 50
Executive Director
Douglas Hendry
Commercial Services Leisure Service Level
Agreements
Increase in RPI and/or other running costs (eg utilities,
payroll etc) resulting in requests for additional funding.
Monitoring annual alteration to contract RPI rate,
communication with service providers and mitigation
through financial forecasting and review of existing budget.
3 50 3 50
Executive Director
Douglas Hendry
Council Wide -
Commercial Services
Council Wide Central Repairs Increased demands on central repair budgets (CRA) due to a
decrease in Capital funding, increase in statutory and
emergency repairs and increases in supplier/contractor
charges.  This impacts on all departments of the Council with
a Central Repairs Budget.
Joint strategy with procurement colleagues to reduce
potential impact of supplier/contractor charges. Close
monitoring of central repairs budgets and commitments and
instructing only statutory tests/inspections and essential
repairs.
4 300 4 300
As at 31 October 2023 As at 31 December 2023

Page 62

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Education ASN Support Demand for ASN support continues to increase. Scottish
Government statistics suggest a 3% year on year increase,
resulting in an additional resource requirement. Particularly
where gaps in our enhanced provision exist. The medium-
term detriments on the development of young children
which occurred as a consequence of service closures during
the COVID pandemic have increased demands on the service
as children require additional support to catch up.  The
Additional Support for Learning National Implementation
plan continues to inform our strategic direction in line with
the Angela Morgan Review.
Service is currently looking at alternative options for service
delivery to mitigate the inescapable pressures. Continuing to
ensure robust assessment of needs, monthly monitoring of
budget, any delays in recruitment factored into projections
to enable informed decision making on allocation of funding
for new/amended /additional support packages. Following a
full ASN review, the service are currently investing in the
development of four new learning centres in order to
provide greater equity in meeting the more complex needs
of some learners as well as considering plans to develop
enhanced wellbeing resources across our learning estate in
future.  This aims to reduce the frequency of children having
to be educated in high cost out of area placements.
3 200 3 200
Executive Director
Douglas Hendry
Education Pre-Five Units - retention of
partner providers
Failure in the commissioning or retention of pre-five partner
provider units to deliver 1140 hours would result in an
increased pressure on the Council to deliver the service.
Annual financial appraisal; Support network; Short-term cash
injections.
3 100 3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Children and Young People
(Scotland) Act - ELC 1140 hours
The Council has been required to deliver 1140 hours of Early
Learning and Childcare since August 2021. The Scottish
Government has committed to funding this and the Council
has revised its service model to align it to the Scottish
Government's reduced funding profile.  A risk remains that
actual costs of delivery exceed the Government Grant in any
given year.  For example, if child numbers are higher than
estimated, this may require additional staffing which has not
been included in the staffing model funded by Scottish
Government. Scottish Government has included plans to
further expand on eligibility for 1140 hours to all 2 year olds
and some one year olds within the current Parliamentary
session. As yet there has been no funding commitment.
However this will place unknown cost pressures on both our
capital and revenue budgets
Continuous monitoring and review of the service model,
usage and resources.
3 100 3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Education (Scotland) Act
The Education (Scotland) Act 2000 requires Councils to
undertake assessments of the need for the provision of
Gaelic Medium Primary Education (GMPE) and the duty to
support and promote Gaelic Education. This may lead to
additional staffing requirements depending upon the
demand for Gaelic from parents.
Continuous monitoring and review of the service model and
resources available within budget.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Hub DBDA/DBFM Schools  -
Litigation
Increased risk of the requirement to litigate to conclude final
capital contract payments due.
Monitoring claims and mitigation through robust challenge
of any additional claims.
2 150 2 150
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Contract RPI for NPDO and Hub
Schools
Increase in RPI would result in higher costs. Monitoring annual alteration to contract RPI rate and
mitigation through financial forecasting and review of
existing budget.
4 100 4 100

Page 63

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO - Reduction in insurance
savings within NPDO Schools
Increase in insurance costs as a result of the long-term
effects of Covid-19 on the insurance market and flood
claims.
Monitoring annual alteration to contract insurance rate and
mitigation through financial forecasting and review of
existing budget.
4 75 4 75
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services - Litigation Increased number of litigation cases. Ensure Legal Services are gateway to access all legal advice
and that advice is sought at earliest opportunity.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO/Hub DBFM contract
management efficiencies
Reduction in ability to generate contract management
efficiencies.
Monitoring annual efficiencies generated and mitigation
through robust contract management and application of
contract specifications/requirements.
2 50 2 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Elections More than 1 by-election required outwith standard election
cycle.
Outwith direct management control. 4 60 4 60
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Licensing Reduced numbers of licensing applications leading to
reduced income.
Monitoring of trends and reporting the financial impact in
the budget monitoring.
4 30 4 30
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Children's Panel Increased number of referrals increasing costs through
increases in the running costs.
Maximise the use of council facilities/resources for panel
session in the first instance.
1 10 1 10
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services Failure to minimise Council wide use of external legal advice. Ensure legal services are gateway to access all legal advice. 1 10 1 10
Executive Director
Kirsty Flanagan
Customer Support
Services
Software Licences Potential risk of being under licensed for software which will
be identified via software audits which would incur
additional costs.
ICT security and compliance officer in post and duties include
review of systems to ensure fully licenced. 
2 100 2 100
Executive Director
Kirsty Flanagan
Customer Support
Services
Additional Bandwidth for
Education
Additional costs required to be incurred in relation to
additional bandwidth required to deliver the Education
Digital Strategy due to a more digitalised learning
curriculum.
Work closely with Education on Digital Devices for All
strategy to ensure necessary IT is in place.
3 50 3 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Environmental Health- export
certificates
Downturn in requests for export certificates as a result of UK
withdrawal from EU, changes to international trading
agreements or business economy. Reduction in demand
creates a budget pressure on environmental health budget.
Monitor income and resources required for export health
certificates / attestations required to support the export
market. Continue with food safety regulation activities
associated and support at 3rd country audits.  Pursue debt
rigorously with key customers through seeking regular
payments.
2 130 2 130
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Dangerous Buildings
interventions
Building Standards having to deal with an increasing level of
dangerous building work which has significant financial
implications for Council.
Monitor activity and seek to recover costs from the owner. 3 100 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fees reduced by
Scottish Government
Potential that the Scottish Government may reduce planning
fees due to poor performance by the Planning Authority.
The Scottish Government has recently appointed a national
Planning Performance Champion however the detail of how
this role intends to incentivise improvement/penalise poor
performance at a local authority level remains unclear at
this time
Maintain high levels of performance as articulated by
performance markers detailed in Planning Performance
Framework annual report.
1 100 1 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fee shortfalls Due to downturn in economic / building activity, in
particular renewable energy development and other major
developments could lead to planning fee income shortfalls
leading to revenue budget pressures.
Current income levels are looking more positive, however,
we are dependent on some high value applications coming
in which, if they don't materialise, will impact the overall
position.  Will continue to monitor Development
Management income and expenditure tightly and investigate
further income generation streams.
1 50 1 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Building Warrant fee shortfalls Due to loss of commercial income and downturn in
economic / building activity, building warrant fee income
shortfalls leading to revenue budget pressures.
Continue to monitor Building Standards income and
expenditure tightly and investigate further income
generation streams.
1 50 1 50

Page 64

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Homelessness Temporary
Accommodation Income
Unpredictable number of Homeless applications. Inability to
recover rent.  Increase costs of property maintenance and
tenancy change over.
Provision of Housing Options information and advice service
to minimise number of applicants proceeding to full
homeless application. Implementation of Rapid Rehousing
Plan.
3 50 3 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Animal Health Carrying out livestock seizure to protect welfare of the
animals
Monitor activity and seek to recover costs from the disposal
of the animals.
1 10 1 10
Executive Director
Kirsty Flanagan
Financial Services Council Tax Debt Collection
Recovery
Recovery of debt becomes more difficult to pursue in the
current economic climate.  This is in relation to historical
debt that has accumulated over many years therefore any
adverse collection rates will impact on the year end debt
provision as opposed to the in-year financial position, hence
no forecast variance has been reported within the current
year.
Robust monitoring of arrangements with debt collection
agency and performance against target collection rates.
3 345 3 345
Executive Director
Kirsty Flanagan
Financial Services Housing Benefit Subsidy Loss of Housing Benefit Subsidy due to exceeding LA error
threshold.
Processes in place for handling of claims accurately and
efficiently.
1 125 1 125
Executive Director
Kirsty Flanagan
Financial Services Sundry Debt Recovery Recovery of debt becomes more difficult to pursue in the
current economic climate. 
Additional staff are being put in place in the Sundry Debt
Team who will work jointly with Legal Services to enhance
the robustness of the Council's debt recovery processes.
3 85 3 85
Executive Director
Kirsty Flanagan
Financial Services Non-Domestic Rates Relief Risk of demand changing due to legislative changes outwith
our control for charitable relief for Arms Length External
Organisations (ALEO).
Outwith direct management control. 3 30 3 30
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Waste PPP - Indexation Historical payments made towards Waste PPP based on
indexation rates have been challenged by Renewi resulting
in a potential cost to the council.
Conversations are in place between Council and Renewi with
the aim of minimising the potential impact.
3 586 3 586
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Waste - Compost Like Output
(CLO)
Compost Like Output is an element of waste that has been
heat treated and can only be used for landfill site
restoration. Renewi are currently producing more CLO than
we need and it is building up in our landfill sites - this has
been flagged up as a concern by SEPA and will need to be
removed.
Discussions ongoing with Renewi and the Council on steps
forward and what element the council is responsible for.
3 164 3 164
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Roads Maintenance - Bridges,
Culverts & Sea Defences
Extreme localised weather may result in loss of bridge,
culvert, road or sea defence.
Routine inspections to deal with potential weak areas -
based on a stitch in time repair regime.
3 750 3 750
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Winter Maintenance Adverse weather conditions which require greater than
budgeted number of gritting runs.
Monitor weather conditions and apply gritting policy to
minimise costs.
4 365 4 365
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Roads Maintenance - Roads
Network
Adverse weather conditions result in deterioration of the
road network necessitating greater spend on repair of
defects.
Manage maintenance budgets to ensure that spend is
prioritised to deal with safety defects.
3 230 3 230
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Car Parking Income Reduced number of visitors to the area and use of council
owned car parks resulting in a reduction in income.
Closely monitor income levels throughout the year,
especially in high visitor seasons.
3 200 3 200
39 5,265 39 5,265

Page 65

ARGYLL AND BUTE COUNCIL  POLICY & RESOURCES COMMITTEE  
FINANCIAL SERVICES 15 FEBRUARY 2024 
CAPITAL BUDGET MONITORING REPORT – 31 DECEMBER 2023 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the position of the capital budget as at 31
December 2023. The report provides information on the financial position in respect
of the capital plan and the performance in terms of delivery of capital plan projects. 
1.2  Financial Position: 
 Current Year to Date – actual net expenditure to date is £24,334k
compared to a budget for the year to date of £24,309k resulting in an
overspend for the year to date of £25k (0.10%).
 Forecast Outturn for 2023-24 – forecast net expenditure for the full
financial year is £34,239k compared to an annual budget of £41,791k giving
rise to a forecast underspend for the year of £7,552k (18.07%).    
 Total Capital Plan – forecast total net project costs on the total capital plan
are £216,885k compared to a total budget for all projects of £216,065k giving
rise to a forecast overspend for the overall capital plan of £820k (0.38%). 
1.3 Project Delivery: 
 Asset Sustainability – Out of 85 projects there are 70 projects (82%) on
track, 2 projects (3%) off track but recoverable and 13 projects off track (15%).
 Service Development - Out of 42 projects there are 41 projects (98%) on
track, 0 projects (0%) off track but recoverable and 1 projects (2%) off track.
 Strategic Change – Out of 30 projects there are 29 projects (97%) on track,
0 projects (0%) are off track but recoverable and 1 projects (3%) off track.  
1.4 
1.5 
The Capital Programme is funded by various income streams as detailed in
Appendix 5. Additional funding has been allocated from revenue to clear small
overspends across a number of projects. 
Originally the Council was projecting £1,195k of capital receipts this financial year. 
However, the revised forecast for the financial year is now £484k, of which £160k
have been received. This is as a result of delays in assets sales rather than a
permanent reduction and over the life of the programme there is no overall impact. 
The estimated level of receipts will be kept under review as market conditions
change, as will values following due diligence undertaken by prospective purchasers
on the condition of asset.

Page 66

ARGYLL AND BUTE COUNCIL  POLICY & RESOURCES COMMITTEE  
FINANCIAL SERVICES 15 FEBRUARY 2024 
CAPITAL BUDGET MONITORING REPORT – 31 December 2023 
2.0  INTRODUCTION 
2.1 
2.2 
2.3 
2.4 
2.5 
2.6 
2.7 
This report provides an update on the position of the capital budget as at 31 December
2023. The report provides information on the financial position in respect of the capital
plan and the performance in terms of delivery of capital plan projects. 
Following the decision at Policy and Resources Committee on 9 December 2021, the
Rothesay Pavilion project was put on pause whilst potential funding options were
being considered. At the budget meeting in February 2023 additional funding was
allocated to this project which will allow the project to progress towards success by
supporting completion of certain work stages. The financial information included within
this report now includes amounts relating to Phase 1 of the Rothesay Pavilion project. 
Campbeltown Flood Scheme has seen compensation events raised by the contractor
which has resulted in a forecasted overspend of £0.710m. These are currently being
discussed with the consultant and cost saving approaches are being sought to bring
the project in on budget though at this stage the current forecasted overspends have
been included within the figures and the project is marked as off track. 
Surveys have been completed in the Councils Learning Estates in relation to
RAAC with only 1 building confirmed as having it present with steps underway for its
removal. This will include a decant of the students for approximately 9 months plus
total removal and replacement of the roof during 2024. The estimated costs associated
with this are £3m which will require additional funding and will be considered as part of
the 2024-25 budget setting process. 
The Councils bid to the Scottish Governments Learning Estate Investment Programme
(LEIP) for funding for a new school campus on Mull was successful. While this is good
news and will provide welcome investment in the school estate it does come with a
financial pressure that is required to be funded if the project is to proceed. The
Scottish Government will fund up to 50% of eligible costs therefore the Council will be
required to fund circa £20m. 
As a result of significant rainfall Argyll and Bute Council activated the Bellwin scheme
in relation to the recovery costs associated with the incident. The funding from this
scheme is welcomed however eligibility criteria of costs are restrictive. Capital
expenditure does not qualify therefore any long term replacements to infrastructure
such as bridges cannot be claimed through the scheme therefore if not already part of
the capital programme will require funding. Works to the value of £1.8m have been
carried out already with future anticipated works costing circa £2.5m being identified,
both which will require capital funding allocated. 
New Waste legislation has been introduced on the disposal of Persistent Organic
Pollutants (POPs).  POPs are organic chemical substances which pose a risk to
human health and the environment due to their persistence in the environment,
bioaccumulation through the food chain and long-range environmental transport
across a wide geographical range.  These items of waste will need to be stored
separately from general waste at landfill sites before being disposed of which will incur
additional capital expenditure.  A forecast of £110k has been reported in the capital
monitoring which is currently shown as an overspend and will require additional
funding to be identified.

Page 67

2.8 
2.9 
2.10 
A £1m cost pressure was identified during 2021-22 in relation to repairs to the A884
Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea wall on
Bute. Emergency works were carried out and a permanent solution is currently being
developed. Additional funding of £1m was allocated for this purpose at the Council
meeting on 24 February 2022 however there remains a risk that costs will exceed this.
Feasibility report underway to progress the permanent works and estimated costs. 
The impact of the pandemic along with the UK exit from the European Union, the
Russian invasion of Ukraine and sanctions on Russian owned entities has seen
significant price increases as well as disruptions to the supply chain and longer lead in
times. The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all have an effect on the overall contract price and
make it extremely challenging to manage expenditure and the availability of supply. 
As a result of this it should be noted that there are likely to be other significant financial
impacts which are not quantifiable at this stage, as follows: 
 Rothesay Pavilion – despite additional funding being awarded there remains a
funding gap to allow full completion of the original intended works. 
 Harbour Investment Programme – likely to be contractual cost increases in
future years (expected to be funded from increased fees and charges).
 Universal Free School Meals – delayed roll out to P6 and P7 and uncertain
capital funding levels available from the Scottish Government. Distributions of
2023-24 funding have not yet been announced. 
 Bridges Fund - A scheme of bridge capital works was developed and 80%
funded through the Local Bridge Maintenance Fund with £5.450m of funding
approved. Increased capital contract costs from when the scheme was
developed to now, has the schemes costing approximately £12m. Discussions
are in place to request the original funding be approved to cover a smaller
scheme with less bridges. 
 In general, capital contracts across the programme are seeing significant price
increases. 
Although the direct impact of COVID on most local services has reduced or even
ceased altogether over the last 12 months, COVID-19 in conjunction with the UK exit
from the European Union and the Russian invasion of Ukraine, continues to affect
worldwide supply chains. 
In recent years additional funding of £10.803m has been allocated to the capital
programme for this purpose which has mitigated the impact to date however, as
detailed in the table below, only £2.703m remains unallocated to projects facing
inflationary pressures. 
Funding for Capital Inflationary Pressures £m
COVID-19 Funding 0.257
February 2021 Budget Meeting - Capital Cost Pressures 4.646
February 2022 Budget Meeting - Capital Cost Pressures 3.900
February 2023 Budget Meeting – Capital Projects Inflation Pressures 2.000
Total Additional Funding Allocated to Capital 10.803
Allocated to Projects within Capital Programme (5.779)
Committed for future years (2.321)
Balance Remaining 2.703 
3.0  RECOMMENDATIONS 
3.1 Note the contents of this report and the financial summaries as detailed in Appendix 8
and approve the proposed changes to the capital plan detailed in Appendix 4.

Page 68

4.0 CURRENT YEAR TO DATE FINANCIAL POSITION 
4.1 
4.2
Overall Position 
Actual net expenditure to date is £24,334k compared to a budget for the year to date
of £24,309k resulting in an overspend for the year to date of £25k (0.10%). 
Project/Department Position 
The table below shows the year to date net expenditure against the year to date
budget by project type and service: 
Project Type:
Year to
Date
Budget    
£'000
Year to
Date
Actual    
£'000
Variance       
£'000
Asset Sustainability 10,679 10,704 (25)
Service Development 2,477 2,477 0
Strategic Change 11,153 11,153 0
Total  24,309 24,334 (25)
Service:      
ICT 869 869 0
Education 4,069 4,069 0
Live Argyll 562 562 0
Health & Social Care Partnership 613 613 0
Shared Offices 781 782 (1)
Roads & Infrastructure 12,980 13,004 (24)
Development & Economic Growth 754 754 0
CHORD 3,681 3,681 0
Total 24,309 24,334 (25) 
Material variances are explained in Appendix 1 and there are a number of small
variances contributing to the year to date overspend.

Page 69

5.0  FORECAST OUTTURN 2023-24 
5.1  Overall Position 
Forecast net expenditure for the full financial year is £34,239k compared to an annual
budget of £41,791k giving rise to a forecast underspend for the year of £7,552k (18.07%). 
5.2 Project/Department Position 
The table below shows the forecast expenditure and budget for the year by project type
and service. 
Project Type:
Annual
Budget            
£'000
Forecast
Outturn        
£'000 
Forecast
Variance     
£'000
Asset Sustainability 24,786 18,380 6,406
Service Development 201 (45) 246
Strategic Change 16,804 15,904 900
Total  41,791 34,239 7,552
Service:      
ICT 1,428 1,428 0
Education 6,917 5,940 977
Live Argyll 1,084 1,084 0
Health & Social Care Partnership 2,201 944 1,257
Shared Offices 1,906 1,907 (1)
Roads & Infrastructure 23,496 18,177 5,319
Development & Economic Growth (931) (931) 0
CHORD 5,690 5,690 0
Total 41,791 34,239 7,552 
Material variances are explained in Appendix 2 and there are a number of smaller
variances contributing to the forecast underspend.

Page 70

6.0  TOTAL PROJECT COSTS 
6.1 Overall Position 
Forecast total net project costs on the total capital plan are £216,885k compared to a
total budget for all projects of £216,065k giving rise to a forecast overspend for the
overall capital plan of £910k (0.38%). 
6.2  Project/Department Position 
The table below shows the forecast expenditure and budget for the total capital plan by
project type and service. 
Project Type:
Capital
Plan
Budget           
£'000
Forecast
Project
Costs        
£'000 
Total
Capital
Plan
Variance         
£'000
Asset Sustainability 59,393 59,503 (110)
Service Development 22,358 22,358 0
Strategic Change 134,314 135,024 (710)
Total  216,065 216,885 (820)
Service:      
ICT 6,380 6,380 0
Education 45,636 45,636 0
Live Argyll 2,971 2,971 0
Health & Social Care Partnership 4,752 4,752 0
Shared Offices 23,539 23,539 0
Roads & Infrastructure 59,281 60,101 (820)
Development & Economic Growth 5,307 5,307 0
CHORD 68,199 68,199 0
Total 216,065 216,885 (820) 
Material variances are explained in Appendix 3 and there are a number of smaller
variances leading to the forecast overspend.

Page 71

7.0  TOTAL PROJECT PERFORMANCE 
7.1  Overall Position 
There are 157 projects within the Capital Plan, 140 are Complete or On Target, 2 are
Off Target and Recoverable and 15 are Off Track.
7.2  Project Position 
The table below shows the Performance Status of the Projects in the Capital Plan. 
Project Type:
Complete/
On Target
Off Target/
Recoverable
Off
Target/
Problem Total
Asset Sustainability 70 2 13 85
Service Development 41 0 1 42
Strategic Change 29 0 1 30
Total 140 2 15 157
Service:        
ICT 7 0 0 7
Education 30 0 1 31
Live Argyll 19 0 0 19
Health & Social Care
Partnership 16 0 1 17
Shared Offices 23 1 0 24
Roads & Infrastructure 22 1 13 36
Development & Economic
Growth 17 0 0 17
CHORD 6 0 0 6
Total 140 2 15 157

Page 72

7.3  Chart of Performance Status 
The graph provides a view of the Performance Status of the Projects included in the
Capital Plan: 
0
10
20
30
40
50
60
70
80
90
Asset Sustainability Service Development Strategic Change
Off Target/
Problem
Off Target/
Recoverable
Complete/ On
Target

Page 73

8.0 OFF TRACK PROJECTS 
8.1  The Off-Track projects are noted in the table below and variance reports are included in
Appendix 6. 
Project Type Project What is Off
Track?
Explanation
RIS - Service
Development
Fleet
Management
Current Year
Expenditure
Slippage into future years.
Delays in the delivery of
orders has led to this
slippage. A number of
vehicles (£800k) are
forecast for delivery in
March 2024, if these
vehicles face any delays
further slippage will occur
before the year end.  
RIS - Asset
Sustainability
Environmental
Projects
Current Year
Expenditure
Slippage into future years.
Planning applications and
associated works are
ongoing for the Cemeteries
where works are still to
commence. No further
capital expenditure forecast
for 2023-24 now that
Tobermory Cemetery works
are complete.
RIS - Asset
Sustainability
Play Park
Renewal
Current Year
Expenditure
Slippage into future years.
Engagement with Local
Communities is taking
place to determine the
works which will go ahead,
as these discussions are
still taking place no
expenditure is forecast to
occur within 2023-24.
RIS - Asset
Sustainability
Footway
Improvements
Current Year
Expenditure
Slippage into future years.
The full footways
programme for 2023-24
was not delivered within the
year due to adverse
weather, sickness within
the team and other
commitments. These works
are forecasted to be carried
out in 2024-25 alongside
the 2024-25 programme.
RIS - Asset
Sustainability
Active Travel Current Year
Expenditure
Slippage into future years.
The full footways
programme for 2023-24
was not delivered within the
year due to adverse
weather, sickness within
the team and other
commitments. These works
are forecasted to be carried

Page 74

out in 2024-25 alongside
the 2024-25 programme.
RIS - Asset
Sustainability
Flood Prevention Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. There were also
unsuccessful tender processes
due to excessive costs being
quoted on returns which
required retendering.
RIS - Asset
Sustainability
Coastal
Protection
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. 
RIS - Asset
Sustainability
Coastal Change
Adaptation
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. 
RIS - Asset
Sustainability
Bute Seawall
Repairs
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. 
RIS - Asset
Sustainability
Helensburgh
Flood Mitigation
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. There were also
unsuccessful tender processes

Page 75

due to excessive costs being
quoted on returns which
required retendering.
RIS - Asset
Sustainability
Bridge
Strengthening
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. 
RIS - Asset
Sustainability
Local Bridge
Maintenance
Fund
Current Year
Expenditure
Slippage into future years.
Resources were reallocated to
the numerous emergencies
which arose from the October
2023
weather incident. Resources
were reallocated accordingly
hence delays in existing
projects. 
RIS - Strategic
Change
Campbeltown
Flood Scheme
Current Year
Expenditure
& Total
Project
Expenditure
Slippage into future years
due to revised cash flow
forecasts provided from
Consultant and Contractor.
As we approach the year
end the financial position
becomes clearer and total
Project Expenditure is
reporting an overspend due
to an overspend on the
Burnside Square project
and compensation events
that have been raised by
the Contractor. 
PropEdu-Asset
Sustainability
Secondary
Schools
Current Year
Expenditure
Slippage into future years
due to delays to the roof
works at Islay High School.
Works had been
programmed to start in
2023-24 however delays
due to weather conditions,
tender returns exceeding
project budget and
redesigns of the scope of
works has led to a slippage
being reported.
PropNonEdu-
Asset
Sustainability
Tigh an Rudha Current Year
Expenditure
Slippage into future years.
The project is delayed due
to tender returns for Tigh
An Rudha exceeding the
anticipated costs of the
project. HSCP projects are
on pause while future of the
Tigh an Rudha is
determined.

Page 76

9.0 
9.1 
RIS - Asset
Sustainability
POPs Waste Total Project
Expenditure
Project is currently showing
an overspend as the
funding for the essential
works of separating POPs
waste has still to be
identified. 
STRATEGIC CHANGE PROJECTS 
Appendix 7 gives detailed information in respect of the Strategic Change Projects within
the Capital Plan. The appendix gives details of the forecast cost of each project against
the approved budget, the start and anticipated completion date of the project and an
assessment of the risks of the project and, if these are not green, gives an explanation
of the problem.

Page 77

10.0 
10.1 
CHANGES TO CAPITAL PLAN 
The table below shows proposed changes to the Capital Plan at summary level which
include slippages, accelerations and virements. Explanations relating to the specific
projects involved can be seen in Appendix 4. 
The updated gross expenditure capital plan incorporating these proposed changes can
be found in Appendix 9. 
Department
Prev.
Agreed
Changes 
2023-24
2023-24 2024-25 2025-26 Future
Years
Total
Capital
Plan
£’000 £’000 £’000 £’000 £’000 £’000
Asset
Sustainability (1,595) (6,430) 6,430 0 0 0
Service
Development 34 (246) 246 0 0 0
Strategic Change (8,222) (900) (2,990) (11,000) 14,890 0
Total (9,783) (7,576) 3,686 (11,000) 14,890 0              
Service:            
ICT 154 0 0 0 0 0
Education (903) (977) 977 0 0 0
Live Argyll (207) 0 0 0 0 0
Health & Social
Care Partnership 6 (1,257) 1,257 0 0 0
Shared Offices (364) 1 (1) 0 0 0
Roads &
Infrastructure (7,424) (5,343) 1,453 (11,000) 14,890 0
Development &
Economic Growth (523) 0 0 0 0 0
Major Projects (522) 0 0 0 0 0
Total (9,783) (7,576) 3,686 (11,000) 14,890 0 
11.0          FUNDING 
11.1  The Capital Programme is funded by various income streams as detailed in Appendix 5.
Additional funding has been allocated from revenue to clear small overspends across a
number of projects.

Page 78

12.0 
12.1 
12.2 
12.3 
12.4 
12.5 
12.6 
12.7 
12.8 
IMPLICATIONS 
Policy – Monitors progress against the capital plan. 
Financial – Monitors funding and commitments of the capital plan. 
Legal – Available funding may not address all Statutory and Regulatory requirements in
relation to Health and Safety. 
HR – Available funding may have an impact on the sustainability of the Property Design
Team and Infrastructure Design Team. 
Fairer Scotland Duty – None. 
12.5.1     Equalities – protected characteristics – None. 
12.5.2     Socio-economic Duty – None. 
12.5.3     Islands – None. 
Climate Change – The Council is committed to addressing climate change via projects
within the capital plan. 
Risk – There are risks around increasing capital contract costs and the level and timing
of capital receipts. 
Customer Service – None.   
Kirsty Flanagan 
Executive Director / Section 95 Officer 
12 January 2024                                                  
Policy Lead for Finance and Commercial Services – Councillor Gary
Mulvaney 
APPENDICES
- Appendix 1 – Year To Date finance variance explanations
- Appendix 2 – Forecast Outturn variance explanations
- Appendix 3 – Total Project finance variance explanations
- Appendix 4 – Changes to Capital Plan and Financial Impact
- Appendix 5 – Capital Funding
- Appendix 6 - Off Track project variance reports
- Appendix 7 - Cumulative spend, completion dates and risks relating                         
to significant capital projects. 
- Appendix 8 - Financial Summary – Overall
- Financial Summary – Executive Director Kirsty Flanagan
- Financial Summary – Executive Director Douglas Hendry
- Appendix 9 - Updated/Revised Capital Plan
For further information contact: Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 79

APPENDIX 1 – Year to Date Financial Variance Explanations
Listed below are the projects where the variance is +/- £50k.
Project
YTD
Budget
£’000
YTD
Actual
£’000
(Over)/
Under
Variance       
£’000
Explanation
Other variances under £50k   (25)          Total value of non-material variances less than +/-£50k
Total   (25)

Page 80

APPENDIX 2 – Outturn Variance Explanations
Listed below are the projects where the current year variance is +/- £50k. 
Project 
Annual
Budget
£’000
Outturn
£’000
Total
(Over)/
Under
Forecast
Variance         
£’000
Explanation
Fleet Management
2,512 2,266 246
Slippage into future years. Delays in the delivery of orders has led to this
slippage. A number of vehicles (£800k) are forecast for delivery in March 2024, if
these vehicles face any delays further slippage will occur before the year end.  
Environmental Projects
650 200 450
Slippage into future years. Planning applications and associated works are
ongoing for the Cemeteries where works are still to commence. No further
capital expenditure forecast for 2023-24 now that Tobermory Cemetery works
are complete.
Play Park Renewal
312 0 312
Slippage into future years. Engagement with Local Communities is taking place
to determine the works which will go ahead, as these discussions are still taking
place no expenditure is forecast to occur within 2023-24.
Footway Improvements
750 450 300
Slippage into future years. The full footways programme for 2023-24 was not
delivered within the year due to adverse weather, sickness within the team and
other commitments. These works are forecasted to be carried out in 2024-25
alongside the 2024-25 programme.
Active Travel
389 189 200
Slippage into future years. The full footways programme for 2023-24 was not
delivered within the year due to adverse weather, sickness within the team and
other commitments. These works are forecasted to be carried out in 2024-25
alongside the 2024-25 programme.
Flood Prevention
807 340 467
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects. There were also
unsuccessful tender processes due to excessive costs being quoted on returns
which require retendering.
Coastal Protection
99 6 93
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects.
Coastal Change Adaptation
158 41 117
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects. 
Helensburgh Flood Mitigation
428 1 427
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects. There were also

Page 81

unsuccessful tender processes due to excessive costs being quoted on returns
which require retendering.
Bridge Strengthening
1,336 373 963
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects. 
Local Bridge Maintenance Fund
1,000 173 827
Slippage into future years. Resources were reallocated to the numerous
emergencies which arose from the October 2023 weather incident. Resources were
reallocated accordingly hence delays within existing projects. 
Campbeltown Flood Scheme
9,702 8,802 900
Slippage into future years due to revised cash flow forecasts provided from
Consultant and Contractor. As we approach the year end the financial position
becomes clearer and total project expenditure is reporting an overspend due to
an overspend on the Burnside Square project and compensation events that
have been raised by the Contractor.
Secondary Schools
1,129 852 277
Slippage into future years due to delays to the roof works at Islay High School.
Works had been programmed to start in 2023-24 though delays due to weather
conditions, tender returns exceeding project budget and redesigns of the scope
of works has led to a slippage being reported.
Block Allocation - Education 916 216 700 Unallocated Education Block Allocation was kept aside to cover any of the
RAAC costs which may have accelerated into 2023-24. Block allocation not
required in 2023-24 has now been slipped into 2024-25.
Tigh an Rudha
600 109 491
Slippage into future years. The project is delayed due to tender returns for Tigh
An Rudha exceeding the anticipated costs of the project. HSCP projects are on
pause while future of the Tigh an Rudha is determined.
Block Allocation - HSCP
766 0 766
Slippage into future years. HSCP Block Allocation had not fully been allocated in
2023-24 as programme of works was in limbo while decision on Tigh an Rudha
was being made. Above mentioned delays to the Tigh an Rudha has resulted in
the HSCP Block Allocation slipping into 2024-25 along with the funding already
allocated to Tigh an Rudha.
Other variances under £50k   16 Total value of non-material variances less than +/-£50k.
Total  7,552 
APPENDIX 3 – Total Project Finance Variances
Listed below are the projects where the total project variance is +/- £50k.

Page 82

Project 
Capital
Plan
Budget
£’000
Forecast
Project
Costs
£’000
Total (Over)/
Under
Forecast
Variance         
£’000
Explanation
Campbeltown Flood Scheme 15,215 16,925 (710)
Total Project Expenditure is reporting an overspend due to an overspend on the
Burnside Square project and compensation events that have been raised by the
Contractor. 
POPs Waste 0 110 (110) Total Project Expenditure is reporting an overspend due to the funding still to be identified
for the essential works to separate and store POPs Waste items. 
Other variances under £50k   (0)
Total value of non-material variances less than +/-£50k. Project Managers are working to
reduce these small individual overspends by identifying underspends elsewhere within the
capital plan.
Total  (820)

Page 83

APPENDIX 4 – Changes to Capital Plan and Financial Impact
OVERALL COST CHANGES
Project
2023-
24
£’000
2024-
25
£’000
2025-
26
£’000
Future
Years
£’000
Total
Capital
Plan
£’000
Recommendation Explanation
Lochgilphead Depot
Rationalisation
25 0 0 0 25
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Demolition of unsafe buildings required prior
to advancing project.
Town Centre Funds -
Dunoon Castle Gardens
10 0 0 0 10
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Overspend carried forward from prior year.
Oban Depot Development
Project
5 0 0 0 5
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Small overspend due to late engineer 
fees incurred.
Glengorm - Cell and
Transfer Station
4 0 0 0 4
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Small overspend due to additional materials
found during project.
Riverside Leisure Centre
Refurbishment
1 0 0 0 1
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Small overspend due to water ingress issues.
Tobermory Top Flat
6 0 0 0 6
Transfer budget from the
Capital Grant Area Control
Accounts to cover the
projected overspend in the
project.
Small overspend due to late property 
fees incurred. 
Capital Fund – Area
Control Accounts (51) 0 0 0 (51)
Utilise budget from the Area
control accounts to cover
overspends detailed above. 
Total Cost Changes 0 0 0 0 0

Page 84

SLIPPAGES AND ACCELERATIONS
Project
2023-
24
£’000
2024-
25
£’000
2025-26
£’000
Future
Years
£’000
Total
Capital
Plan 
£’000
Recommendation Explanation
Harbour
Investment
Programme 
(3,890) (11,000) 14,890 0 Reprofile future
years expenditure Earlier in 2023-24,
Burnett Building 1 (1)   0 Accelerate from
2024-25
Works scheduled for 2024-25, accelerate from 2024-25 to cover
building survey costs.
Fleet
Management (246) 246   0 Slip budget from
2023-24
Slippage into future years. Delays in the delivery of orders has led
to this slippage. A number of vehicles (£800k) are forecast for
delivery in March 2024, if these vehicles face any delays further
slippage will occur before the year end.  
Environmental
Projects
(450) 450   0 Slip budget from
2023-24
Slippage into future years. Planning applications and
associated works are ongoing for the Cemeteries where works
are still to commence. No further capital expenditure forecast
for 2023-24 now that Tobermory Cemetery works are
complete.
Play Park
Renewal (312) 312   0 Slip budget from
2023-24
Slippage into future years. Engagement with Local Communities
is taking place to determine the works which will go ahead, as
these discussions are still taking place no expenditure is forecast
to occur within 2023-24.
Footway
Improvements
(300) 300   0 Slip budget from
2023-24
Slippage into future years. The full footways programme for 2023-
24 was not delivered within the year due to adverse weather,
sickness within the team and other commitments. These works
are forecasted to be carried out in 2024-25 alongside the 2024-25
programme.
Active Travel
(200) 200   0 Slip budget from
2023-24
Slippage into future years. The full footways programme for 2023-
24 was not delivered within the year due to adverse weather,
sickness within the team and other commitments. These works
are forecasted to be carried out in 2024-25 alongside the 2024-25
programme.
Flood Prevention
(467) 467   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects. There were also unsuccessful tender
processes due to excessive costs being quoted on returns which
require retendering.

Page 85

Coastal
Protection (93) 93   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects.
Coastal Change
Adaptation (117) 117   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects.
Bute Seawall
Repairs (41) 41   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects.
Helensburgh
Flood Mitigation
(427) 427   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects. There were also unsuccessful tender
processes due to excessive costs being quoted on returns which
require retendering.
Bridge
Strengthening (963) 963   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects.
Local Bridge
Maintenance
Fund (827) 827   0 Slip budget from
2023-24
Slippage into future years. Resources were reallocated to the
numerous emergencies which arose from the October 2023
weather incident. Resources were reallocated accordingly hence
delays within existing projects.
Campbeltown
Flood Scheme (900) 900   0 Slip budget from
2023-24
Slippage into future years due to revised cash flow forecasts
provided from Consultant and Contractor. As we approach the
year end the financial position becomes clearer.
Secondary
Schools
(277) 277   0 Slip budget from
2023-24
Slippage into future years due to delays to the roof works at Islay
High School. Works had been programmed to start in 2023-24
though delays due to weather conditions, tender returns
exceeding project budget and redesigns of the scope of works
has led to a slippage being reported.
Block Allocation -
Education (700) 700   0 Slip budget from
2023-24
Unallocated Education Block Allocation was kept aside to cover
any of the RAAC costs which may have accelerated into 2023-24.
Block allocation not required in 2023-24 has now been slipped
into 2024-25.
Tigh an Rudha (491) 491   0 Slip budget from
2023-24
Slippage into future years. The project is delayed due to tender
returns for Tigh An Rudha exceeding the anticipated costs of the

Page 86

project. HSCP projects are on pause while future of the Tigh an
Rudha is determined. 
Block Allocation -
HSCP
(766) 766   0 Slip budget from
2023-24
HSCP Block Allocation had not fully been allocated in 2023-24 as
programme of works was in limbo while decision on Tigh an
Rudha was being made. Above mentioned delays to the Tigh an
Rudha has resulted in the HSCP Block Allocation slipping into
2024-25 along with the funding already allocated to Tigh an
Rudha.
Total Slippages
and
Accelerations
(7,576) 3,686 (11,000) 14,890 0  
Net Impact of
Changes (7,576) 3,686 (11,000) 14,890 0

Page 87

CAPITAL PROGRAMME FUNDING Appendix 5
Estimated
Capital Funding
Carry Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 22-23
Slippage /
Acceleration
Additional
Funding
Updated
Capital
Funding
Available
General Capital Grant 11,900 222 -222 0 11,900 9,851 -276 0 129 9,704 10,007 54 0 0 10,061
Capital Grant - Area Control Accounts 0 0 0 51 51 0 0 0 0 0 0 0 0 0 0
Transfer to Revenue for Private Sector Housing Grant (PSHG) -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033
Capital Receipts 1,195 -60 -651 0 484 350 0 651 0 1,001 400 0 0 0 400
Flooding Allocation 155 0 0 0 155 155 0 0 0 155 155 0 0 0 155
Ring Fenced Capital Grant 5,800 0 14 0 5,814 304 0 314 400 1,018 0 0 -324 0 -324
Restricted Funding 1,613 0 -522 1,394 2,485 0 0 488 2,065 2,553 0 0 34 50 84
Funded by Reserves 11,909 6,533 0 243 18,685 8,187 289 0 186 8,662 1,175 -155 0 0 1,020
Additional Funding from Revenue 25 0 0 117 142 0 0 0 0 0 0 0 0 0 0
Insurance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Harbour Investment Programme 22,235 -13,035 -6,000 0 3,200 27,025 -5,025 2,110 0 24,110 29,700 20,300 -11,000 0 39,000
Prudential Borrowing 20,718 -6,510 -10,889 74 3,393 27 6,434 11,106 0 17,567 0 1,388 5 0 1,393
Loans Fund Review 0 2,694 651 0 3,345 1,331 0 -651 0 680 0 0 0 0 0
COVID Funding 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
74,517 -10,156 -17,619 1,879 48,621 46,197 1,422 14,018 2,780 64,417 40,404 21,587 -11,285 50 50,756
BREAKDOWN OF ADDITIONAL FUNDING
Additional Funding 2023-24 2024-25 2025-26 Reported Source
Tobermory Top Flat - SHF 30 Jan-23 Revenue Funding
Dunoon STEM Hub 50 Jan-23 Revenue Funding
Dunoon STEM Hub 150 Jan-23 Grant Funding
Dunoon Cycle Bothy 145 Jan-23 Grant Funding
Gartbreck - Capping 118 Mar-23 Reserves
Dunoon Cycle Bothy 74 Mar-23 Scottish Government
Tigh Na Rhuda 400 50 Mar-23 Scottish Government
Helensburgh and Rosneath Cycleways 290 Jun-23 SPT
SPT - Bus Infrastructure 25 Jun-23 SPT
Dunoon STEM Hub 1,750 Jun-23 Rural Growth Deal
Rural Growth Deal planning stages 132 Jun-23 Rural Growth Deal
Public Conveniences Upgrade - Coastal Communities Fund 200 Jul-23 Coasal Communities Fund
Tobermory Harbour Wall and Railings, Phase 2 100 Jul-23 Coasal Communities Fund
Tobermory Harbour Wall and Railings, Phase 2 250 Jul-23 Scottish Government
Server Sustainability 95 Jul-23 Earmarked Reserves
Oban Depot Development 67 Aug-23 Revenue Funding
Roads Recon - STTS Funding 347 Aug-23 STTS
Roads Recon - STTS Funding 40 Sep-23 STTS
Coastal Change Adaptation 129 Sep-23 Scottish Government
Telecomms Network 236 Oct-23 Earmarked Reserves
Clean Energy - NDEEF1 -50 Oct-23 Earmarked Reserves
Rural Growth Deal  - Clyde Engineering 25 Oct-23 Earmarked Reserves
Capital Grant - Area Control Accounts 51 Dec-23 Control accounts
Rural Growth Deal 5 Dec-23 Rural Growth Deal
Total 1,879 2,780 50
2025-262024-252023-24

Page 88

OFF TRACK PROJECT  Appendix 6
Project Name:  Fleet Management Project Manager:  John Blake Risk: Low
Initial Start Date:  On-going Proposed End Date:  On-Going 
How was this project initially funded?  
Prudential Borrowing 
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why is the project classified as off target?
Project is off target due to current year forecasted expenditure slipping out with 2023-24. 
What has caused the issue outlined above?  
The above issue has been caused due to procurement delays, continuation of delays caused by superconductor shortages in the vehicle manufacturing
industry.
What action will be taken to rectify this issue?
Forecasts have been updated to reflect the updated anticipated delivery dates of ordered vehicles.
What are the implications of the action proposed?
Proposed actions will result in slippages being reported for 2023-24 and future year’s forecasts changing to reflect the above mentioned delays. A number of
deliveries are currently forecasted for March 2024, any delays to these deliveries will result in further slippages out with 2024 before the year end.

Page 89

OFF TRACK PROJECT  Appendix 6
Project Name:  Environmental Projects Project Manager: Hugh O’Neill   Risk: Low
Initial Start Date:  
On-going
Proposed End Date:
N/A  
How was this project initially funded? 
Scottish Government General Capital Grant Allocation 
Please detail any additional funding. 
Coastal Community Funding 
Previously Reported Committee and Date:  
N/A - First off track report
Next Reported Committee and Date: 
Why is the project classified as off target?
Forecasted expenditure slipping out with 2023-24
What has caused the issue outlined above?  
Works at Tobermory Cemetery were completed in July 2023. Planning applications and associated prep work are ongoing for the cemetery works in
Campbeltown, Strachur, Sandbank, Lismore and Calgary. Slippage occurred due to initial profiling inaccuracy. No further capital expenditure is due on these
cemeteries in 2023-24, therefore the profile requires amendment.
What action will be taken to rectify this issue?
Forecasts have been updated to reflect the forecasted expenditure on the planned cemetery works.  
What are the implications of the action proposed?
Proposed actions will result in slippages being reported for 2023-24. No further implications associated with this slippage, the original forecast for 2023-24 was
overstated as not enough planning time was considered when setting the capital profile.

Page 90

OFF TRACK PROJECT  Appendix 6
Project Name:  Play Park Renewal Project Manager:  Hugh O’Neill Risk: Low
Initial Start Date:  2021-22 - 1st year of funding Proposed End Date:  2025-26 - final year of funding (estimate) 
How was this project initially funded?  
Scottish Government Specific Capital Grant
Please detail any additional funding.  
Previously Reported Committee and Date: N/A - first time reported as
off track 
Next Reported Committee and Date: 
Why is the project classified as off target?
Forecasted expenditure slipping out with 2023-24
What has caused the issue outlined above?  
A full engagement process for the consideration of the improvement of 28 play parks across the area was completed in July 2023. Area committees have been
updated with the reported findings and are now engaging with the local community councils. Due to the timing of these discussions, spend in 2023-24 is no
longer forecast to occur. Slippage was caused by the original profile not allowing for as much planning and engagement time as was required.
What action will be taken to rectify this issue?
Forecasts have been updated to reflect that no expenditure is expected to occur in 2023-24.
What are the implications of the action proposed?
Proposed actions will result in slippages being reported for 2023-24.

Page 91

OFF TRACK PROJECT  Appendix 6
Project Name:  Footway Improvements                           
Active Travel - works part of Footway Capital Scheme
Project Manager:  Hugh O’Neill Risk: Low 
Initial Start Date:  On-going Proposed End Date:  
N/A
How was this project initially funded?  
Scottish Government General Capital Grant Allocation 
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why is the project classified as off target?
Forecast expenditure slipping out with 2023-24
What has caused the issue outlined above?  
Due to adverse weather, sickness within the team and other commitments the full footway works scheduled for 2023-24 were not completed within the year.  
What action will be taken to rectify this issue?
Forecast expenditure for the remaining schemes has been slipped into 2024-25 as this is when the schemes will be carried out.
What are the implications of the action proposed?
Remaining 2023-24 schemes will now be completed during 2024-25 programme of works.

Page 92

OFF TRACK PROJECT  Appendix 6
Project Name: 
Flood Prevention
Coastal Protection
Coastal Change Adaptation
Bute Seawall Repairs
Helensburgh Flood Mitigation
Bridge Strengthening
Local Bridge Maintenance Fund
Project Manager:  Elsa Simoes Risk: Low
Initial Start Date:  N/A Proposed End Date: N/A   
How were these project initially funded?  
Scottish Government General Capital Grant Allocation
Scottish Government Specific Capital Grant Allocation - Coastal Change
Adaptations 
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why are the projects classified as off target?
Forecasted expenditure has slipped out with 2023-24 for the above Asset Sustainability projects.
What has caused the issue outlined above?  
The team tasked with delivering these projects were tasked with allocating resources to the numerous emergencies which arose from the October 2023
flooding. Resources were reallocated accordingly from the Capital Plan – this resulted in those schemes being reprogrammed. Resources were not available to
reach the anticipated forecasted expenditure for 2023-24.
Unsuccessful tender processes due to excessive costs being quoted on returns also required retendering and further consumed resources.
What action will be taken to rectify this issue?
Forecasted expenditure has been slipped outwith 2023-24. Feasibility of achieving the current 2024-25 levels of work will be considered during year end
discussions.
What are the implications of the action proposed?
Works previously programmed for 2023-24 have been pushed back to 2024-25 as tender processes continue to be progressed.

Page 93

OFF TRACK PROJECT  Appendix 6
Project Name:  Campbeltown Flood Scheme Project Manager: Jamie Salmon  Risk: High
Initial Start Date:  01/08/2016
Works Contract commenced - 27/05/2022
Proposed End Date:  
Q1 2024-25 with defect period running to February 2026
How was this project initially funded?  
Scottish Government
Prudential Borrowings 
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why is the project classified as off target?
Current year forecast expenditure slipping out with 2023-24 and total project forecasting an overspend. 
What has caused the issue outlined above?  
Current year slippage has been caused by the live nature of the Construction and Services Contracts. Budget is updated on a Monthly basis considering the
monthly revised cashflow predictions from AECOM (the consultant) and Dawson Wam (the contractor). The cause for forecasted expenditure to slip out with
2023-24 was due to additional works being required at Dalaruan Street Culvert. These works were compensation events involving Scottish Gas and Scottish
Water to carry out diversions and enabling works. These works delayed the progress on Dalaruan Street culvert and as such the slippage reflects this. 
Overspend is forecasted due to the following:
£500k of compensation events which have been raised by the Contractor
£300k overspend on the Burnside Square Services and Works project within the scheme 
What action will be taken to rectify this issue?
Profile has been updated to reflect the up-to-date cashflow predictions from AECOM and Dawson Wam, Estates, Public Utilities and Infrastructure
Design. Compensation events have been monitored closely to ensure these have been managed in accordance with the condition of contract (Works
Contract) – this is ongoing as with all contracts managed by Infrastructure Design.
What are the implications of the action proposed?
The project is now forecasted to be overspent.

Page 94

OFF TRACK PROJECT  Appendix 6
Project Name:  Secondary Schools Project Manager:  Rhona Mitchell Risk: Low 
Initial Start Date:  N/A Proposed End Date:  N/A 
How was this project initially funded?  
Block allocation
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why is the project classified as off target?
Forecasted expenditure has slipped out with 2023-24.
What has caused the issue outlined above?  
Delays to the works on the roof at Islay High School has caused forecasted expenditure for 2023-24 to slip into 2024-25. Works had been programmed to start
in 2023-24 though delays due to weather conditions, tender returns exceeding project budget and redesigns of the scope of works has led to a slippage being
reported.
What action will be taken to rectify this issue?
Capital monitoring has been updated to reflect the delay in the project commencing, works are ongoing to bring project scope in line with budgetary
constraints after previous tender returns exceeding this.
What are the implications of the action proposed?
Works are now scheduled to commence in 2024-25.

Page 95

OFF TRACK PROJECT Appendix 6
Project Name:  Tigh An Rhuda Project Manager:  Rhona Mitchell Risk: Med
Initial Start Date: Proposed End Date:
How was this project initially funded? Scottish Government
Capital Grant Block allocation
Please detail any additional funding.
SG Island Funding 
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Forecasted expenditure has slipped out with 2023-24.
What has caused the issue outlined above?
The project is delayed due to tender returns for Tigh An Rudha exceeding the anticipated costs of the project. HSCP projects are on pause while future of the Tigh an
Rudha scope of works is determined.
What action will be taken to rectify this issue?
Forecasted expenditure has been slipped to reflect that Tigh An Rudha will not commence until at least 2024-25.
What are the implications of the action proposed?
Scope of project is still to be fully determined, as such no expenditure is expected for the remainder of 2023-24.

Page 96

OFF TRACK PROJECT  Appendix 6
Project Name: POPs Waste   Project Manager: A Millar   Risk: Med
Initial Start Date:  November 2023 Proposed End Date:  TBC 
How was this project initially funded?  
TBC
Please detail any additional funding.  
Previously Reported Committee and Date:    Next Reported Committee and Date: 
Why is the project classified as off target?
Project is currently reporting a forecasted overspend.
What has caused the issue outlined above?  
New Waste legislation has been introduced on the disposal of Persistent Organic Pollutants (POPs).  POPs are organic chemical substances which pose a risk
to human health and the environment due to their persistence in the environment, bioaccumulation through the food chain and long-range environmental
transport across a wide geographical range.  These items of waste will need to be stored separately from general waste at landfill sites before being disposed
of which will incur additional capital expenditure.  A forecast of £110k has been reported in the capital monitoring which is currently shown as an overspend and
will require additional funding to be identified.
What action will be taken to rectify this issue?
Funding will be identified during the budget setting process. Once identified the forecasted overspend will be eliminated.
What are the implications of the action proposed?
No further implications.

Page 97

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 7
Strategic Change Projects
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Estimated
Completion
Date
Project
Risks
Identified Explanation
Campbeltown Flood Scheme 4,992 8,802 15,925 15,215 01/08/2016 02/05/2024 Red Contractor's updated programming of work moved Public Utility works from 22/23 to 23/24
Street Lighting LED Replacement 3,226 61 3,900 3,900 01/08/2016 31/12/2024 Green Tender for final package of works still to be awarded.
Helensburgh Waterfront Development 23,415 977 24,392 24,392 01/04/2017 31/03/2024 Green Physically complete, retentions outstanding
CHORD Oban 7,279 626 7,905 7,905 27/10/2016 31/03/2022 Green Issues with contract close out impacting on timescales.
TIF - Halfway House Roundabout 66 56 640 640 tbc tbc Green Scope of project still to be determined - budget to be reprofiled.
CHORD Rothesay 15,231 6,737 24,012 24,012 tbc tbc Green Project recommenced.
Harbour Investment Programme 7,397 3,243 91,335 91,335 01/04/2017 31/03/2028 Green Budget slipped into future years.
Dunoon Primary 10,635 234 10,869 10,869 18/12/2014 30/04/2020 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Kirn Primary School 10,085 34 10,119 10,119 24/04/2014 31/10/2017 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Replacement of Oban High 2,844 406 3,250 3,250 24/04/2014 31/01/2019 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Helensburgh Office Rationalisation 11,538 300 11,838 11,838 25/04/2013 31/12/2022 Green Project subject to legal dispute.
CHORD Dunoon 12,495 27 12,522 12,522 03/02/2012 09/03/2018 Green
Main contract complete and retentions paid. Landscaping and remediation works ongoing but
issues with water ingress may require works in 22-23.
Kilmory Business Park Phase 2AA 47 560 1,129 1,129 01/02/2022 01/09/2024 Green Development Agreement still to be concluded.
Carbon Management - Non Education 29 21 50 50 01/04/2015 31/12/2024 Green Projects being determined.
Dunoon Pier OBC 2,844 0 2,844 2,844 03/02/2012 26/02/2016 Green Project complete.
Campbeltown Office Rationalisation 595 1 596 596 01/02/2015 31/03/2019 Green Complete.
TIF - Oban Airport Business Park 489 56 590 590 22/01/2015 31/12/2025 Green
Campbeltown Schools Redevelopment 2,092 38 2,130 2,130 16/02/2012 30/11/2018 Green Physically complete - negotiations with contractor delaying payment of financial sums outstanding.
CHORD - Helensburgh 6,529 28 6,557 6,557 29/09/2011 30/04/2015 Green Main contract complete. Art project proposed for 23-24.
TIF - North Pier Extension 214 0 214 214 06/12/2017 06/12/2021 Green Complete.
TIF - Lorn/Kirk Road 2,169 1 2,170 2,170 22/01/2015 31/03/2021 Green Complete.
Carbon Management Fuel Conversions 107 0 107 107 01/02/2014 31/03/2019 Green Complete.
Kilmory Biomass  Carbon Management 956 0 956 956 20/09/2012 31/03/2019 Green Complete.
Clean Energy - NDEEF1 964 224 1,331 1,331 tbc 31/03/2024 Green
Clean Energy - NDEEF2 0 50 1,140 1,140 tbc tbc Green
Net Zero 0 0 366 366 tbc tbc Green
Strategic Change Total 129,739 22,482 240,388 239,678
Project Risk Classifications:
Green - Risks can be managed and are viewed as stable or reducing.
Amber - Risks are increasing but are still manageable.
Red - Risks are increasing or have increased to such an extent they may affect delivery of the project.
Capital Expenditure Dates Risks

Page 98

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL Appendix 8
FINANCIAL SUMMARY - NET EXPENDITURE
Current Financial Year To Date
Budget Actual
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Executive Director Douglas Hendry 5,557 5,558 (1) 10,402 8,169 2,233 23,042 23,042 0
Executive Director Kirsty Flanagan 5,552 5,576 (24) 15,609 11,436 4,173 38,026 38,136 (110)
Asset Sustainability Total 11,109 11,134 (25) 26,011 19,605 6,406 61,068 61,178 (110)
Service Development Projects
Executive Director Douglas Hendry 321 321 0 526 526 0 16,438 16,438 0
Executive Director Kirsty Flanagan 2,264 2,264 0 6,244 5,998 246 38,354 38,354 0
Service Development Total 2,585 2,585 0 6,770 6,524 246 54,792 54,792 0
Strategic Change Projects
Campbeltown Schools Redevelopment 0 0 0 38 38 0 2,130 2,130 0
Dunoon Primary 2 2 0 234 234 0 10,869 10,869 0
Replacement of Oban High 0 0 0 406 406 0 3,250 3,250 0
Kirn Primary School 0 0 0 34 34 0 10,119 10,119 0
Carbon Management - Non Education 0 0 0 21 21 0 50 50 0
Carbon Management Business Cases 0 0 0 0 0 0 201 201 0
NPDO Schools Solar PV Panel Installations 0 0 0 0 0 0 761 761 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 0 0 0 400 400 0
Carbon Management Fuel Conversions 0 0 0 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 0 0 0 19 19 0
Carbon Management - Group Heating Conversion Project 0 0 0 0 0 0 1,938 1,938 0
Kilmory Biomass  Carbon Management 0 0 0 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 0 0 0 182 182 0
Campbeltown Office Rationalisation 0 0 0 1 1 0 596 596 0
Helensburgh Office Rationalisation 0 0 0 300 300 0 11,838 11,838 0
Clean Energy - NDEEF1 145 145 0 224 224 0 1,331 1,331 0
Clean Energy - NDEEF2 0 0 0 50 50 0 1,140 1,140 0
Net Zero 0 0 0 0 0 0 366 366 0
Campbeltown Flood Scheme 7,293 7,293 0 9,702 8,802 900 15,215 15,925 (710)
Street Lighting LED Replacement 31 31 0 61 61 0 3,900 3,900 0
Harbour Investment Programme 1,131 1,131 0 3,200 3,200 0 91,292 91,292 0
Harbour Investment Programme Non - PB 0 0 0 43 43 0 43 43 0
TIF - Lorn/Kirk Road 0 0 0 1 1 0 2,170 2,170 0
TIF - North Pier Extension 0 0 0 0 0 0 214 214 0
TIF - Oban Airport Business Park 1 1 0 56 56 0 590 590 0
TIF - Halfway House Roundabout 0 0 0 56 56 0 640 640 0
CHORD - Helensburgh 0 0 0 28 28 0 6,557 6,557 0
CHORD Dunoon 0 0 0 27 27 0 12,522 12,522 0
CHORD Oban 0 0 0 626 626 0 7,905 7,905 0
CHORD Rothesay 3,605 3,605 0 6,737 6,737 0 24,012 24,012 0
Helensburgh Waterfront Development 76 76 0 977 977 0 24,392 24,392 0
HWD - FFE (Funded by LA) 0 0 0 34 34 0 350 350 0
Kilmory Business Park Phase 2AA 0 0 0 560 560 0 1,129 1,129 0
Dunoon Pier OBC 0 0 0 0 0 0 2,844 2,844 0
Strategic Change Total 12,284 12,284 0 23,416 22,516 900 240,028 240,738 (710)
Total Expenditure 25,978 26,003 (25) 56,197 48,645 7,552 355,888 356,708 (820)
INCOME
Asset Sustainability
Executive Director Douglas Hendry 0 0 0 (128) (128) 0 (578) (578) 0
Executive Director Kirsty Flanagan (430) (430) 0 (1,097) (1,097) 0 (1,097) (1,097) 0
Asset Sustainability Total (430) (430) 0 (1,225) (1,225) 0 (1,675) (1,675) 0
Service Development Projects
Executive Director Douglas Hendry 0 0 0 0 0 0 (7,771) (7,771) 0
Executive Director Kirsty Flanagan (108) (108) 0 (6,569) (6,569) 0 (24,663) (24,663) 0
Service Development Total (108) (108) 0 (6,569) (6,569) 0 (32,434) (32,434) 0
Strategic Change Projects
Helensburgh Office Rationalisation 0 0 0 0 0 0 (349) (349) 0
Dunoon Primary 0 0 0 0 0 0 (137) (137) 0
Campbeltown Flood 0 0 0 0 0 0 (270) (270) 0
Harbour PB (1,131) (1,131) 0 (3,200) (3,200) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road 0 0 0 (113) (113) 0 (2,154) (2,154) 0
H'burgh CHORD Public Realm Imprv 0 0 0 0 0 0 (570) (570) 0
Helensburgh Waterfront Development 0 0 0 (2,320) (2,320) 0 (7,979) (7,979) 0
Kilmory Business Park Phase 2AA 0 0 0 (979) (979) 0 (979) (979) 0
CHORD - Dunoon Waterfront 0 0 0 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 0 0 0 (1,624) (1,624) 0
Strategic Change Total (1,131) (1,131) 0 (6,612) (6,612) 0 (105,714) (105,714) 0
Total Income (1,669) (1,669) 0 (14,406) (14,406) 0 (139,823) (139,823) 0
Net Total 24,309 24,334 (25) 41,791 34,239 7,552 216,065 216,885 (820)
Full Year This Financial Year Total Project Costs
31 December 2023

Page 99

MONITORING REPORT
Budget Actual Variance Budget Forecast Variance Budget Forecast Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability
Education 3,747 3,747 0 5,859 4,882 977 13,409 13,409 0
Live Argyll 561 561 0 1,062 1,062 0 2,125 2,125 0
Health and Social Care Partnership 613 613 0 2,147 890 1,257 3,452 3,452 0
Shared Offices 636 637 (1) 1,334 1,335 (1) 4,056 4,056 0
Asset Sustainability Total 5,557 5,558 (1) 10,402 8,169 2,233 23,042 23,042 0
Service Development Projects
Ardrishaig Primary Pre 5 Unit 0 0 0 0 0 0 2 2 0
Bowmore Primary School - Pre 5 Unit 0 0 0 0 0 0 149 149 0
Clyde Cottage - 600 hour provision 0 0 0 0 0 0 556 556 0
Craignish Primary School - Pre 5 Extension 0 0 0 0 0 0 400 400 0
Iona Primary School - Pre 5 Unit 0 0 0 0 0 0 490 490 0
Islay High and Rosneath Primary School Pitches 0 0 0 0 0 0 719 719 0
Lochgoilhead Primary School - Pre 5 Unit 0 0 0 0 0 0 391 391 0
Park Primary Extension/Pre Fives Unit 0 0 0 0 0 0 341 341 0
Tarbert High School - Biomass enabling work 0 0 0 0 0 0 0 0 0
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 491 491 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 0 0 0 120 120 0
Early Learning and Childcare 0 0 0 0 0 0 850 850 0
Early Learning and Childcare - 1140 Hours 320 320 0 320 320 0 7,774 7,774 0
CO2 Monitoring - Covid Mitigation in Schools 0 0 0 113 113 0 192 192 0
Early Learning and Childcare - 1140 Hours - CFCR 0 0 0 0 0 0 1,379 1,379 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 38 38 0 38 38 0
Riverside Leisure Centre Refurbishment 1 1 0 1 1 0 1,246 1,246 0
Dunclutha Childrens Home 0 0 0 54 54 0 1,300 1,300 0
Service Development Total 321 321 0 526 526 0 16,438 16,438 0
Strategic Change Projects
Campbeltown Schools Redevelopment 0 0 0 38 38 0 2,130 2,130 0
Dunoon Primary 2 2 0 234 234 0 10,869 10,869 0
NPDO Schools Solar PV Panel Installations 0 0 0 0 0 0 761 761 0
Non NPDO Schools Solar PV Panel Installations 0 0 0 0 0 0 400 400 0
Carbon Management Fuel Conversions 0 0 0 0 0 0 107 107 0
Carbon Management Capital Property Works 2016/17 0 0 0 0 0 0 19 19 0
Carbon Management - Group Heating Conversion Project 0 0 0 0 0 0 1,938 1,938 0
Kilmory Biomass  Carbon Management 0 0 0 0 0 0 956 956 0
Oil to Gas Heating Conversions 0 0 0 0 0 0 182 182 0
Campbeltown Office Rationalisation 0 0 0 1 1 0 596 596 0
Helensburgh Office Rationalisation 0 0 0 300 300 0 11,838 11,838 0
Clean Energy - NDEEF1 145 145 0 224 224 0 1,331 1,331 0
Clean Energy - NDEEF2 0 0 0 50 50 0 1,140 1,140 0
Net Zero 0 0 0 0 0 0 366 366 0
CHORD Oban 0 0 0 626 626 0 7,905 7,905 0
CHORD Rothesay 3,605 3,605 0 6,737 6,737 0 24,012 24,012 0
CHORD - Helensburgh 0 0 0 28 28 0 6,557 6,557 0
CHORD Dunoon 0 0 0 27 27 0 12,522 12,522 0
Helensburgh Waterfront Deveopment 76 76 0 977 977 0 24,392 24,392 0
HWD - FFE (Funded by LA) 0 0 0 34 34 0 350 350 0
Kilmory Business Park Phase 2AA 0 0 0 560 560 0 1,129 1,129 0
Dunoon Pier OBC 0 0 0 0 0 0 2,844 2,844 0
Strategic Change Total 3,828 3,828 0 10,297 10,297 0 125,964 125,964 0
Total Expenditure 9,706 9,707 (1) 21,225 18,992 2,233 165,444 165,444 0
INCOME
Asset Sustainability
Education 0 0 0 (125) (125) 0 (125) (125) 0
Shared Offices 0 0 0 (3) (3) 0 (3) (3) 0
Asset Sustainability Total 0 0 0 (128) (128) 0 (578) (578) 0
Service Development Projects
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 (485) (485) 0
Bunessan Primary School - Gaelic Medium Improvements 0 0 0 0 0 0 (30) (30) 0
Early Learning and Childcare 0 0 0 0 0 0 (918) (918) 0
Early Years 1140 Hours 0 0 0 0 0 0 (6,300) (6,300) 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 0 0 0 (38) (38) 0
Service Development Total 0 0 0 0 0 0 (7,771) (7,771) 0
Strategic Change
Helensburgh Office Rationalisation 0 0 0 0 0 0 (349) (349) 0
Dunoon Primary School 0 0 0 0 0 0 (137) (137) 0
H'burgh CHORD Public Realm Imprv 0 0 0 0 0 0 (570) (570) 0
Helensburgh Waterfront Development 0 0 0 (2,320) (2,320) 0 (7,979) (7,979) 0
HWD - FFE (Funded by LA) 0 0 0 0 0 0 (350) (350) 0
CHORD - Oban 0 0 0 0 0 0 (1,624) (1,624) 0
Net Departmental Total 9,706 9,707 (1) 17,798 15,565 2,233 145,097 145,097 0
31 December 2023
Total Project CostsFull Year This Financial YearCurrent Financial Year To Date
Appendix 8
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR DOUGLAS HENDRY

Page 100

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT
Current Financial Year To Date
Budget Actual
(Over)/Under
Variance Budget
Year End
Forecast
(Over)/Under
Variance Budget Forecast
(Over)/Under
Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE
Asset Sustainability Projects
Flood Prevention 101 101 0 807 340 467 1,305 1,305 0
Coastal Protection 2 2 0 99 6 93 199 199 0
Coastal Change Adaptation 30 30 0 158 41 117 287 287 0
Bute Sea Wall Repairs 46 46 0 100 59 41 680 680 0
Helensburgh Flood Mitigation 1 1 0 428 1 427 428 428 0
Bridge Strengthening 240 240 0 1,336 373 963 1,686 1,686 0
Local Bridge Maintenance Fund 123 123 0 1,000 173 827 5,203 5,203 0
Roads Reconstruction 3,619 3,619 0 7,419 7,419 0 15,419 15,419 0
Roads Reconstruction - Helensburgh CHORD 0 0 0 47 47 0 47 47 0
Roads Reconstruction - Oban CHORD 0 0 0 3 3 0 3 3 0
Helensburgh CHORD - Signage etc 0 0 0 10 10 0 10 10 0
Lighting 0 0 0 440 440 0 1,040 1,040 0
Environmental Projects 191 191 0 650 200 450 1,021 1,021 0
Play Park Refurbishment 0 0 0 312 0 312 938 938 0
Public Convenience Upgrades 54 54 0 282 282 0 282 282 0
Footway Improvements 381 381 0 750 450 300 750 750 0
Glengorm - Capping 0 0 0 0 0 0 0 0 0
Glengorm - Cell and Transfer Station (PB) 89 89 0 89 89 0 89 89 0
Gartbreck - Capping 6 6 0 6 6 0 200 200 0
POPs Waste 0 24 (24) 0 24 (24) 0 110 (110)
EV Quick Chargers 0 0 0 62 62 0 62 62 0
Tobermory Car Park 0 0 0 96 96 0 96 96 0
Active Travel 0 0 0 389 189 200 389 389 0
Block Allocation - RIS 0 0 0 0 0 0 4,268 4,268 0
Server Sustainability 120 120 0 352 352 0 1,177 1,177 0
PC Replacement 306 306 0 518 518 0 1,835 1,835 0
Telecomms Network 243 243 0 256 256 0 480 480 0
Asset Sustainability Total 5,552 5,576 (24) 15,609 11,436 4,173 38,026 38,136 (110)
Service Development Projects
Preliminary design for  Regional Transport projects 0 0 0 16 16 0 221 221 0
Campbeltown Old Quay 0 0 0 0 0 0 1,381 1,381 0
Fleet Management - Prudential Borrowing 1,188 1,188 0 2,187 2,187 0 4,861 4,861 0
Fleet Management 0 0 0 325 79 246 4,538 4,538 0
Lismore Ferry 0 0 0 15 15 0 672 672 0
Oban Depot Development Project 9 9 0 9 9 0 2,189 2,189 0
Lochgilphead Depot Rationalisation 33 33 0 33 33 0 62 62 0
Jackson's Quarry Refurbishment 0 0 0 0 0 0 285 285 0
Witchburn Road Demolition 0 0 0 0 0 0 158 158 0
Safe Streets, Walking and Cycling (CWSS) 0 0 0 370 370 0 3,383 3,383 0
SPT - bus infrastructure 0 0 0 0 0 0 1,430 1,430 0
Cycleways - H&L (FSPT) 7 7 0 300 300 0 3,402 3,402 0
Helensburgh Public Realm - Arts Strategy Fund 0 0 0 50 50 0 53 53 0
Town Centre Funds 341 341 0 718 718 0 4,329 4,329 0
Rural Growth Deal 160 160 0 162 162 0 212 212 0
Dunoon Cycle Bothy 220 220 0 292 292 0 563 563 0
Dunoon STEM Hub 19 19 0 713 713 0 2,558 2,558 0
Ardrishaig North Active Travel 75 75 0 112 112 0 880 880 0
Nature Restoration Fund 0 0 0 346 346 0 346 346 0
Gibraltar Street Public Realm Improvements 12 12 0 222 222 0 250 250 0
Hermitage Park 0 0 0 26 26 0 3,388 3,388 0
West Coast UAV Innovation Logistics and Training Hub 0 0 0 0 0 0 0 0 0
Applications Projects 200 200 0 348 348 0 3,193 3,193 0
Service Development Total 2,264 2,264 0 6,244 5,998 246 38,354 38,354 0
Strategic Change Projects
Campbeltown Flood Scheme 7,293 7,293 0 9,702 8,802 900 15,215 15,925 (710)
Street Lighting LED Replacement 31 31 0 61 61 0 3,900 3,900 0
Harbour Investment Programme 1,131 1,131 0 3,200 3,200 0 91,292 91,292 0
Harbour Investment Programme - Non PB 0 0 0 43 43 0 43 43 0
TIF - Lorn/Kirk Road 0 0 0 1 1 0 2,170 2,170 0
TIF - Oban Airport Business Park 1 1 0 56 56 0 590 590 0
TIF - Halfway House Roundabout 0 0 0 56 56 0 640 640 0
Strategic Change Total 8,456 8,456 0 13,119 12,219 900 114,064 114,774 (710)
Total Expenditure 16,272 16,296 (24) 34,972 29,653 5,319 190,444 191,264 (820)
INCOME
Asset Sustainability
EV Quick Chargers 0 0 0 (27) (27) 0 (27) (27) 0
Roads Reconstruction (430) (430) 0 (470) (470) 0 (470) (470) 0
Tobermory Car Park 0 0 0 (400) (400) 0 (400) (400) 0
Asset Sustainability Total (430) (430) 0 (1,097) (1,097) 0 (1,097) (1,097) 0
Service Development Projects
Applications Projects 0 0 0 (46) (46) 0 (437) (437) 0
Safe Streets, Walking and Cycling 0 0 0 (376) (376) 0 (2,988) (2,988) 0
SPfT 0 0 0 (25) (25) 0 (1,268) (1,268) 0
Cycleways - H&L (FSPT) 0 0 0 (590) (590) 0 (3,502) (3,502) 0
Town Centre Funds 0 0 0 (625) (625) 0 (2,237) (2,237) 0
Rural Growth Deal (81) (81) 0 (182) (182) 0 (212) (212) 0
Dunoon STEM Hub 0 0 0 (2,050) (2,050) 0 (2,558) (2,558) 0
Ardrishaig North Active Travel 0 0 0 0 0 0 (50) (50) 0
Dunoon Cycle Bothy 0 0 0 (394) (394) 0 (563) (563) 0
Gibraltar Street Public Realm Improvements 0 0 0 0 0 0 (250) (250) 0
Hermitage Park 0 0 0 0 0 0 (3,319) (3,319) 0
Fleet Management - PB 0 0 0 (2,187) (2,187) 0 (4,861) (4,861) 0
Fleet Management (27) (27) 0 (27) (27) 0 (27) (27) 0
Lochgilphead Depot Rationalisation 0 0 0 0 0 0 0 0 0
Millpark Depot Demolition Insurance 0 0 0 0 0 0 (53) (53) 0
Oban Depot - Mill Park Insurance Claim 0 0 0 0 0 0 (1,681) (1,681) 0
Oban Depot - Appin Depot Sale 0 0 0 0 0 0 0 0 0
Oban Depot - Revenue Contribution 0 0 0 (67) (67) 0 0 0 0
Lismore Ferry 0 0 0 0 0 0 (500) (500) 0
Witchburn Road Demolition 0 0 0 0 0 0 (157) (157) 0
Service Development Total (108) (108) 0 (6,569) (6,569) 0 (24,663) (24,663) 0
Strategic Change Projects
Campbeltown Flood 0 0 0 0 0 0 (270) (270) 0
Harbour PB (1,131) (1,131) 0 (3,200) (3,200) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road 0 0 0 (113) (113) 0 (2,154) (2,154) 0
Strategic Change Total (1,131) (1,131) 0 (3,313) (3,313) 0 (93,716) (93,716) 0
Total Income (1,669) (1,669) 0 (10,979) (10,979) 0 (119,476) (119,476) 0
Net Departmental Total 14,603 14,627 (24) 23,993 18,674 5,319 70,968 71,788 (820)
31 December 2023
Full Year This Financial Year Total Project Costs
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR KIRSTY FLANAGAN
Appendix 8

Page 101

CAPITAL PLAN 2023-24 APPENDIX 9
Overall Summary
Service
Previous Years
£000's
2023-24                                           
£000s
2024-25                 
£000s
2025-26                
£000s
2026-27                 
£000s
2027-28                
£000s Total
Education 39,077 6,037 5,006 3,521 0 0 53,641
Shared Offices 17,661 1,910 3,343 977 0 0 23,891
ICT 2,529 1,474 1,593 1,221 0 0 6,817
RIS 26,197 24,731 46,640 44,028 17,623 0 159,219
DEG 18,331 3,424 2,653 0 0 0 24,408
HSCP 1,246 972 2,085 477 0 0 4,780
Live Argyll 1,274 1,084 636 427 0 0 3,421
CHORD 68,156 8,989 2,461 105 0 0 79,711
Overall Total 174,471 48,621 64,417 50,756 17,623 0 355,888

Page 102

CAPITAL PLAN 2023-24 APPENDIX 9
Education
Category Service Project
Previous
Years
£000's
2023-24                     
£000s
2024-25                 
£000s 2025-26                 £000s
2026-27            
£000s
2027-28            
£000s
Total
£000s
Asset Sustainability Education Asbestos Control/Removal Works 0 7 0 0 0 0 7
Block Allocation - Education 0 216 866 520 0 0 1,602
Digital Inclusion 20-21 0 9 0 0 0 0 9
Free School Meals 0 379 900 1,495 0 0 2,774
Homeless Houses - Housing Quality Standard 0 1 0 0 0 0 1
Internal Refurbishment Budget 0 7 0 0 0 0 7
Lochgilphead Primary School Demolition 0 0 0 0 0 0 0
Pre-5's/Nurseries 0 0 0 0 0 0 0
Primary Schools 0 3,370 2,420 1,280 0 0 7,070
School Houses - Housing Quality Standard 0 13 0 0 0 0 13
Secondary Schools 0 852 820 226 0 0 1,898
Asset Sustainability Total 0 4,854 5,006 3,521 0 0 13,381
Service Development Education Ardrishaig Primar School - Pre Five Extension 2 0 0 0 0 0 2
Bowmore Primary School - Gaelic Medium Grant 0 38 0 0 0 0 38
Bowmore Primary School - Pre Five Unit 149 0 0 0 0 0 149
Bunessan Primary School - Gaelic Medium Improvements 120 0 0 0 0 0 120
Clyde Cottage - 600 hours provision 556 0 0 0 0 0 556
CO2 Monitoring - Covid Mitigation in Schools 79 113 0 0 0 0 192
Craignish Primary School - Pre Five Extension (600 hours funding) 400 0 0 0 0 0 400
Early Learning and Childcare 850 0 0 0 0 0 850
Early Learning and Childcare - 1140 Hours 7,454 320 0 0 0 0 7,774
Early Learning and Childcare - 1140 Hours - CFCR 1,379 0 0 0 0 0 1,379
Iona Primary School - Pre Five Unit (600 hours funding) 490 0 0 0 0 0 490
Islay High & Rosneath PS Pitches 719 0 0 0 0 0 719
Lochgoilhead Primary School - Pre Five Unit (600 hours funding) 391 0 0 0 0 0 391
Park Primary Extension and Pre Fives Unit 341 0 0 0 0 0 341
Sandbank Gaelic Pre Five Unit 491 0 0 0 0 0 491
Service Development Total 13,421 471 0 0 0 0 13,892
Strategic Change Education Campbeltown Schools Redevelopment 2,092 38 0 0 0 0 2,130
Dunoon Primary School 10,635 234 0 0 0 0 10,869
Kirn Primary School 10,085 34 0 0 0 0 10,119
Replacement of Oban High School 2,844 406 0 0 0 0 3,250
Strategic Change Total 25,656 712 0 0 0 0 26,368
Overall Total 39,077 6,037 5,006 3,521 0 0 53,641

Page 103

CAPITAL PLAN 2023-24 APPENDIX 9
Shared Office
Category Service Project
Previous
Years
£000's
2023-24     
£000s
2024-25      
£000s
2025-26      
£000s
2026-27        
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability Shared Offices 5-7 East Clyde Street - Coastal Communities Fund 0 0 0 0 0 0 0
Argyll House, Dunoon 0 9 0 0 0 0 9
Asbestos Capital Property Works 0 51 0 0 0 0 51
Block Allocation 0 152 298 427 0 0 877
Bowmore Area Office 0 76 0 0 0 0 76
Burnett Building 0 3 107 0 0 0 110
Capital Property Works 0 38 0 0 0 0 38
Fire Risk Assessment Works 0 14 0 0 0 0 14
Helensburgh and Lomond Civic Centre - Emergency Heating Pipework 0 130 0 0 0 0 130
Hill Street Dunoon Rewire 0 33 0 0 0 0 33
Kilmory Castle 0 0 1,409 0 0 0 1,409
Legionella Control Works 0 144 0 0 0 0 144
Manse Brae District Office 0 0 0 0 0 0 0
Manse Brae Roads Office 0 2 0 0 0 0 2
Our Modern Workspace 0 683 480 0 0 0 1,163
Asset Sustainability Total 0 1,335 2,294 427 0 0 4,056
Strategic Change Shared Offices Campbeltown Office Rationalisation 595 1 0 0 0 0 596
Carbon Management - Group Heating Conversion Project (Prudential Borrowing)1,938 0 0 0 0 0 1,938
Carbon Management Business Cases (FPB) 201 0 0 0 0 0 201
Carbon Management Capital Property Works 16/17 19 0 0 0 0 0 19
Carbon Management Fuel Conversions (FPB) 107 0 0 0 0 0 107
Clean Energy - NDEEF1 964 224 143 0 0 0 1,331
Clean Energy - NDEEF2 0 50 540 550 0 0 1,140
Helensburgh Office Rationalisation  (FPB,REC) 11,538 300 0 0 0 0 11,838
Kilmory Biomass Project OBC (FPB,REV) 956 0 0 0 0 0 956
Net Zero 0 0 366 0 0 0 366
Non-NPDO Schools PV Panel Installations 400 0 0 0 0 0 400
NPDO Schools Solar PV Panel Installations 761 0 0 0 0 0 761
Oil to Gas Heating Conversions (FPB) 182 0 0 0 0 0 182
Strategic Change Total 17,661 575 1,049 550 0 0 19,835
Overall Total 17,661 1,910 3,343 977 0 0 23,891

Page 104

CAPITAL PLAN 2023-24 APPENDIX 9
Major Projects
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25    
£000s
2025-26     
£000s
2026-27          
£000s
2027-28     
£000s
Total
£000s
Strategic Change CHORD CHORD - Dunoon 12,495 27 0 0 0 0 12,522
CHORD - Helensburgh -Public Realm Imprv 6,529 28 0 0 0 0 6,557
CHORD - Oban 7,279 626 0 0 0 0 7,905
CHORD - Rothesay 15,231 6,737 1,973 71 0 0 24,012
Helensburgh Waterfront Development 23,415 977 0 0 0 0 24,392
HWD - FFE 316 34 0 0 0 0 350
Kilmory Business Park Phase 2AA 47 560 488 34 0 0 1,129
OBC for Dunoon Pier 2,844 0 0 0 0 0 2,844
Strategic Change Total 68,156 8,989 2,461 105 0 0 79,711
Overall Total 68,156 8,989 2,461 105 0 0 79,711

Page 105

CAPITAL PLAN 2023-24 APPENDIX 9
ICT
Category Service Project
Previous
Years
£000's
2023-24      
£000s
2024-25      
£000s
2025-26      
£000s
2026-27     
£000s
2027-28       
£000s
Total
£000s
Asset Sustainability ICT Block Allocation - ICT 0 0 132 0 0 0 132
PC Replacement 0 518 648 669 0 0 1,835
Server Sustainability 0 352 425 400 0 0 1,177
Telecomms Network 0 256 72 152 0 0 480
Asset Sustainability Total 0 1,126 1,277 1,221 0 0 3,624
Service Development ICT Applications Projects 2,529 348 316 0 0 0 3,193
Service Development Total 2,529 348 316 0 0 0 3,193
Overall Total 2,529 1,474 1,593 1,221 0 0 6,817

Page 106

CAPITAL PLAN 2023-24 APPENDIX 9
Roads and Infrastructure Services
Category Service Project
Previous
Years
£000's
2023-24     
£000s
2024-25    
£000s
2025-26   
£000s
2026-27    
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability RIS Block Allocation 0 0 0 4,268 0 0 4,268
Bridge Strengthening 0 373 1,313 0 0 0 1,686
Bute Sea Wall Repairs 0 59 621 0 0 0 680
Coastal Change Adaptation 0 41 246 0 0 0 287
Coastal Protection 0 6 193 0 0 0 199
Environmental Projects 0 200 821 0 0 0 1,021
EV Quick Chargers 0 62 0 0 0 0 62
Flood Prevention 0 340 772 155 38 0 1,305
Footway Improvements 0 450 300 0 0 0 750
Glengorm - Capping 0 0 0 0 0 0 0
Glengorm - Cell and Transfer Station (PB) 0 89 0 0 0 0 89
Helensburgh CHORD - Signage etc 0 10 0 0 0 0 10
Helensburgh Flood Mitigation 0 1 427 0 0 0 428
Investment in Active Travel 0 189 200 0 0 0 389
Lighting 0 440 600 0 0 0 1,040
Local Bridge Maintenance Fund 0 173 4,827 203 0 0 5,203
Plant and Machinery 0 0 0 0 0 0 0
Public Convenience Upgrades 0 282 0 0 0 0 282
Roads Reconstruction 0 7,419 8,000 0 0 0 15,419
Roads Reconstruction - Helensburgh CHORD 0 47 0 0 0 0 47
Roads Reconstruction - Oban CHORD 0 3 0 0 0 0 3
Tobermory Car Park 0 96 0 0 0 0 96
Asset Sustainability Total 0 10,280 18,867 5,017 38 0 34,202
Service Development RIS Campbeltown Old Quay 1,381 0 0 0 0 0 1,381
Depot Rationalisation 0 0 0 0 0 0 0
Fleet Management - Prudential Borrowing 2,674 1,941 246 0 0 0 4,861
Jackson's Quarry Refurbishment 285 0 0 0 0 0 285
Lismore Ferry Replacement 637 15 20 0 0 0 672
Lochgilphead Depot Rationalisation 29 33 0 0 0 0 62
Oban Depot Development 2,180 9 0 0 0 0 2,189
Preliminary design for  Regional Transport projects (tif) 205 16 0 0 0 0 221
Witchburn Road Demolition 158 0 0 0 0 0 158
Service Development Total 10,582 2,339 1,446 0 0 0 14,367
Strategic Change RIS Campbeltown Flood Scheme 4,992 8,802 1,410 11 0 0 15,215
Harbour Investment Programme PB 7,397 3,200 24,110 39,000 17,585 0 91,292
Street Lighting LED Replacement 3,226 61 613 0 0 0 3,900
Strategic Change Total 15,615 12,063 26,133 39,011 17,585 0 110,407
Overall Total 26,197 24,682 46,446 44,028 17,623 0 158,976

Page 107

CAPITAL PLAN 2023-24 APPENDIX 9
Development and Economic Growth
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25   
£000s
2025-26    
£000s
2026-27     
£000s
2027-28     
£000s
Total
£000s
Service Development DEG Ardrishaig North Active Travel 755 112 13 0 0 0 880
Cycleways - H&L (FSPT) 2,812 300 290 0 0 0 3,402
Dunoon Cycle Bothy 259 292 12 0 0 0 563
Dunoon STEM Hub 95 713 1,750 0 0 0 2,558
Gibraltar Street Public Realm Improvements 28 222 0 0 0 0 250
Helensburgh Public Realm - Arts Strategy Fund 3 50 0 0 0 0 53
Hermitage Park 3,362 26 0 0 0 0 3,388
Nature Restoration Fund 0 346 0 0 0 0 346
Rural Growth Deal 50 162 0 0 0 0 212
Safe Streets, Walking and Cycling (CWSS) 3,013 370 0 0 0 0 3,383
SPT - bus infrastructure 1,405 0 25 0 0 0 1,430
Town Centre Funds 3,611 718 0 0 0 0 4,329
Service Development Total 15,393 3,311 2,090 0 0 0 20,794
Strategic Change DEG 01 TIF - Lorn/Kirk Road 2,169 1 0 0 0 0 2,170
05 TIF - North Pier Extension 214 0 0 0 0 0 214
09 TIF - Oban Airport Business Park 489 56 45 0 0 0 590
TIF - Halfway House Roundabout 66 56 518 0 0 0 640
Strategic Change Total 2,938 113 563 0 0 0 3,614
Overall Total 18,331 3,424 2,653 0 0 0 24,408

Page 108

CAPITAL PLAN 2023-24 APPENDIX 9
Health & Social Care Partnership
Category Service Project
Previous
Years
£000's
2023-24   
£000s
2024-25   
£000s
2025-26   
£000s
2026-27    
£000s
2027-28    
£000s
Total
£000s
Asset Sustainability HSCP Ardfenaig 0 27 0 0 0 0 27
Block Allocation 0 0 1,058 184 0 0 1,242
Capital Property Works 0 79 0 0 0 0 79
Digitalising telecare 0 100 0 0 0 0 100
Dunoon Hostel 0 0 0 0 0 0 0
Eadar Glinn 0 0 0 0 0 0 0
East King Street Childrens Home 0 58 0 0 0 0 58
Glencruitten Hostel 0 81 36 143 0 0 260
Gortonvogie 0 1 0 0 0 0 1
Greenwood/Woodlands 0 216 0 0 0 0 216
Lochgilphead Resource Centre 0 16 0 0 0 0 16
Rothesay Community Education Centre 0 0 0 0 0 0 0
Shellach View 0 144 0 0 0 0 144
Thomson Home Rothesay 0 0 0 0 0 0 0
Tigh An Rudha HFE 0 109 991 150 0 0 1,250
Tobermory Top Flat 0 28 0 0 0 0 28
Asset Sustainability Total 0 918 2,085 477 0 0 3,480
Service Development HSCP Dunclutha Childrens Home 1,246 54 0 0 0 0 1,300
Service Development Total 1,246 54 0 0 0 0 1,300
Overall Total 1,246 972 2,085 477 0 0 4,780

Page 109

CAPITAL PLAN 2023-24 APPENDIX 9
Live Argyll
Category Service Project
Previous
Years
£000's
2023-24    
£000s
2024-25    
£000s
2025-26    
£000s
2026-27   
£000s
2027-28 
£000s
Total
£000s
Asset Sustainability Live Argyll Aqualibrium 0 343 48 40 0 0 431
Corran Halls Gaelic Centre 0 113 46 84 0 0 243
Inveraray CARS 0 0 0 0 0 0 0
Kintyre Community Education Centre - Lift Shaft Refurbishment 0 2 0 0 0 0 2
LA - Indoor Cycles 0 0 0 0 0 0 0
Lochgilphead Library Relocation 0 14 0 0 0 0 14
Moat Centre (Roofing) 0 0 0 0 0 0 0
Queen's Hall - Partition Wall 0 0 0 0 0 0 0
Riverside Leisure Centre - Health Suite Upgrade 0 204 0 0 0 0 204
Rothesay Swimming Pool 0 40 25 50 0 0 115
The Moat Centre - Gym Store 0 0 0 0 0 0 0
The Moat Centre - Heating Upgrade 0 0 0 0 0 0 0
The Moat Centre - Window Upgrade 0 0 0 0 0 0 0
Victoria Halls, Helensburgh 0 78 0 0 0 0 78
Asset Sustainability Total 0 1,062 636 427 0 0 2,125
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1,245 1 0 0 0 0 1,246
Service Development Total 1,245 1 0 0 0 0 1,246
Strategic Change Live Argyll Carbon Management 29 21 0 0 0 0 50
Strategic Change Total 29 21 0 0 0 0 50
Overall Total 1,274 1,084 636 427 0 0 3,421

Page 110

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES                                15 FEBRUARY 2024 
TREASURY MANAGEMENT MONITORING REPORT – 31 DECEMBER 2023 
1.0.  EXECUTIVE SUMMARY 
1.1. This report sets out the Council’s treasury management position for the period 1
November 2023 to 31 December 2023 and includes information on: 
 Overall borrowing position
 Borrowing activity
 Investment activity
 Economic background
 Interest rate forecast
 Prudential Indicators 
1.2. Estimated borrowing is below the Capital Financing Requirement for the period to 31
December 2023, at this stage in the financial year capital expenditure is below target. 
1.3. The net movement in external borrowing in the period 1 November 2023 to 31 December
2023 was £3m. 
1.4. The levels of investments were £56.929m at 31 December 2023. The rate of return
achieved was 5.054% compared to the target SONIA rate which was 5.187%. 
1.5. The Council has significant cash balances which are invested in accordance with its
Annual Treasury Management Strategy on the basis of security first, liquidity second and
then return.

Page 111

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES                                15 FEBRUARY 2024 
TREASURY MANAGEMENT MONITORING REPORT – 31 DECEMBER 2023 
2.0. INTRODUCTION 
2.1. This report sets out the Council’s treasury management position for the period 1
November 2023 to 31 December 2023 and includes information on: 
 Overall borrowing position
 Borrowing activity
 Investment activity
 Economic background
 Interest rate forecast
 Prudential Indicators 
3.0. DETAIL
Overall Borrowing Position 
3.1. The table below details the estimated capital financing requirement (CFR) and compares
this with the estimated level of external debt at 31 March 2023. The CFR represents the
underlying need for the Council to borrow to fund its fixed assets and accumulated capital
expenditure. 
Forecast Forecast Forecast
2023/24 2024/25 2025/26
£000 £000 £000
CFR at 1 April 291,782 286,645 316,648
Net Capital Expenditure 6,593 42,195 40,911
Less Loans Fund Principal Repayments (5,950) (6,254) (6,573)
Less: NPDO Repayment (5,780) (5,938) (6,235)
Estimated CFR 31 March 286,645 316,648 344,751
Less Funded by NPDO (111,564) (105,784) (105,846)
Estimated Net CFR 31 March 175,081 210,864 238,905
Estimated External Borrowing at 31 March 142,534 170,835 189,152
Gap 32,547 40,029 49,753 
3.2. Borrowing is below the Capital Financing Requirement for the period to 31 December
2023. Whilst borrowing rates are still comparatively low, the Council has delayed
taking out any new long term borrowing, as rates are expected to drop towards the
end of 2024 plus the Council has significant cash balances which reduces the need
to borrow in the short term. 
3.3. The Council’s Treasury Management Strategy states that any decision to borrow in
advance will be within forward approved Capital Financing Requirement estimates.

Page 112

3.4. The Council’s estimated net capital financing requirement at 31 December 2023 is
£175.081m. The table below shows how this has been financed. £109.377m is
funded by loans and there are substantial internal balances of £122.633m of which
£56.929m are currently invested, as detailed in section 3.7, leaving a net internal
balance of £65.704m. 
Position at
31/10/23
Position at
31/12/23
£000 £000
Loans 112 109
Net Internal Balances 72 66
Total CFR 184 175 
3.5. During the period from 1 November 2023 to 31 December 2023, £24m of loans were
repaid and was replaced with new borrowing of £21m.  The analysis of the movement
in borrowing is shown in the table below: 
Actual
£m
(24)
21
Net Movement in External Borrowing (3)
External Loans Repaid 1st November 2023 to 31st
December 2023
Borrowing undertaken 1st November 2023 to 31st
December 2023
3.6. The table below summarises the movement in the level and rate of temporary
borrowing at the start and end of the period. 
£000 % Rate
Temp borrowing at 31st October 2023 328 4.40%
Temp borrowing at 31st December 2023 222 4.40%

Page 113

Investment Activity
3.7.     The average rate of return achieved in the Council’s investments to 31 December 2023
was 5.054% compared to the SONIA (Sterling Overnight Index Average) rate for the same period
of 5.187%. The Council’s rate of return is marginally less than SONIA due to the rapid rise
in interest rates which increased SONIA faster than the Council was able to redeem its
existing lower rated investments. At 31 December 2023 the Council had £56.929m of short
term investments at an average rate of 5.054%. The table below details the counterparties
that the investments were placed with, the maturity date, the interest rate and the credit
rating applicable for each counterparty. 
Counterparty Maturity Amount £000 Interest
Rate
Rating  S&P
Clydesdale Bank Instant 2,779 5.15% Short Term A-2, Long
Cambridgeshire County Council 22/01/2024 5,000 1.00% AA
London Borough of Croydon 10/10/2024 5,000 4.10% AA
National Bank of Kuwait 09/04/2024 7,500 5.13% Short Term A-1, Long
First Abu Dhabi Bank 09/05/2024 5,000 5.27% Short Term A-1+,
London Borough of Croydon 10/06/2024 5,000 5.30% AA
Close Brothers 31/01/2024 2,500 5.87% Short Term A-1, Long
First Abu Dhabi Bank 01/02/2024 5,000 5.93% Short Term A-1+,
First Abu Dhabi Bank 09/08/2024 5,000 6.16% Short Term A-1+,
Goldman Sachs 16/02/2024 5,000 5.93% Short Term A-1, Long
Australia and New Zealand Banking Group 16/02/2024 5,000 5.92% Short Term A-1+,
MMF- Federated Call 1,600 0.00% AAA
MMF - Legal and General Call 2,550 0.00% AAA
Total 56,929 
3.8. All investments and deposits are in accordance with the Council’s approved list of
counterparties and within the limits and parameters defined in the Treasury Management
Practices. The counterparty list is constructed based on assessments by leading credit
reference agencies adjusted for additional market information available in respect of
counterparties. 
3.9. The Council has significant cash balances which are invested in accordance with its
Annual Treasury Management Strategy. These cash balances are in excess of what is
required for normal operating purposes but the economic environment for investments
has improved over the last few months with an increase in interest rates, making investing
these monies easier than in previous years.
Economic and Interest Rate Forecasts 
3.10. The latest economic background is shown in Appendix 1 with the interest rate forecast in
Appendix 2. 
Prudential Indicators 
3.11. The prudential indicators for 2023-24 are attached in Appendix 3.

Page 114

4.0. CONCLUSION 
4.1 In the period from 1 November 2023 to 31 December 2023, the Council’s borrowing remained
unchanged, and is currently below the Capital Financing Requirement. There are substantial
internal balances, of which £56.929m is currently invested. The investment returns were
5.054%. 
5.0. IMPLICATIONS 
5.1. Policy        None   
5.2. Financial       Complies with Annual Treasury Strategy 
5.3.  Legal        None 
5.4. HR        None 
5.5. Fairer Duty Scotland:       
5.5.1  Equalities – protected characteristics  None
5.5.2  Socio-economic Duty    None
5.5.3  Islands       None 
5.6.  Climate Change       None 
5.7. Risk        None 
5.8. Customer Service     None 
Kirsty Flanagan
Section 95 Officer
4 January 2024 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
Appendix 1 – Economic Background
Appendix 2 – Interest Rate Forecast
Appendix 3 – Prudential Indicators 
For further information contact Anne Blue, Head of Financial Services 
anne.blue@argyll-bute.gov.uk

Page 115

Appendix 1 – Economics Update 
 The third quarter of 2023/24 saw: 
- A 0.3% m/m decline in real GDP in October, potentially partly due to unseasonably
wet weather, but also due to the ongoing drag from higher interest rates.  Growth
for the second quarter, ending 30th September, was revised downwards to -0.1%
and growth on an annual basis was also revised downwards, to 0.3%; 
- A sharp fall in wage growth, with the headline 3myy rate declining from 8.0% in
September to 7.2% in October, although the ONS “experimental” rate of
unemployment has remained low at 4.2%;
- CPI inflation continuing on its downward trajectory, from 8.7% in April to 4.6% in
October, then again to 3.9% in November;
- Core CPI inflation decreasing from April and May’s 31 years’ high of 7.1% to 5.1%
in November, the lowest rate since January 2022;
- The Bank of England holding Bank Rate at 5.25% in November and December;
- A steady fall in 10-year gilt yields as investors revised their interest rate
expectations lower.
 The revision of GDP data in Q2 to a 0.1% q/q fall may mean the mildest of mild
recessions has begun. Indeed, real GDP in October fell 0.3% m/m which does suggest
that the economy may stagnate again in Q3. The weakness in October may partly be
due to the unseasonably wet weather. That said, as the weakness was broad based it
may also be the case that the ongoing drag from higher interest rates is more than
offsetting any boost from the rise in real wages.
 However, the rise in the flash composite activity Purchasing Managers Index, from
50.7 in November to 51.7 in December, did increase the chances of the economy
avoiding a contraction in Q3. The improvement was entirely driven by the increase in
the services activity balance from 50.9 to 52.7. (Scores above 50 point to expansion
in the economy, although only tepid in this instance.)  The press release noted that
this was primarily driven by a revival in consumer demand in the technological and
financial services sectors. This chimes with the further improvement in the GfK
measure of consumer confidence in December, from -24 to -22. The services PMI is
now consistent with non-retail services output growing by 0.5% q/q in Q3, but this is in
stark contrast to the manufacturing sector where the output balance slumped from
49.2 to 45.9 and, at face value, the output balance is consistent with a 1.5% q/q fall in
manufacturing output in Q3.
 The 0.3% m/m fall in retail sales volumes in October means that after contracting by
1.0% q/q (which was downwardly revised from -0.8% q/q) in Q2, retail activity remained
weak at the start of Q3. That suggests higher interest rates are taking a bigger toll on
real consumer spending. 
 Higher interest rates have filtered through the financial channels and weakened the
housing market but, overall, it remains surprisingly resilient with the Halifax house price
index recently pointing to a 1.7% year on year increase whilst Nationwide’s December
data pointed to a -1.8% year on year decrease.  However, the full weakness in real
consumer spending and real business investment has yet to come as currently it is
estimated that around two thirds to a half of the impact of higher interest rates on
household interest payments has yet to be felt.

Page 116

 Overall, we expect real GDP growth to remain subdued throughout 2024 as the drag
from higher interest rates is protracted but a fading of the cost-of-living crisis and
interest rate cuts in the second half of 2024 will support a recovery in GDP growth in
2025.
 The labour market remains tight by historical standards, but the sharp fall in wage
growth seen in October will reinforce the growing belief in markets that interest rates
will be cut mid-2024. Wage growth eased in October much faster than the consensus
expected. Total earnings fell by 1.6% m/m, which meant the headline 3myy rate eased
from 8.0% in September to 7.2% in October. This news will be welcomed by the Bank
of England. Indeed, the timelier three-month annualised rate of average earnings
growth fell from +2.4% to -1.2%. Excluding bonuses, it fell from 5.3% to 2.0%.
Furthermore, one of the Bank’s key barometers of inflation persistence, regular private
sector pay growth, dropped from 7.9% 3myy to 7.3%, which leaves it comfortably on
track to fall to 7.2% by December, as predicted by the Bank in November. 
 The fall in wage growth occurred despite labour demand being stronger in October
than expected. The three-month change in employment eased only a touch from
+52,000 in September to +50,000 in October. But resilient labour demand was offset
by a further 63,000 rise in the supply of workers in the three months to October. That
meant labour supply exceeded its pre-pandemic level for the first time, and the
unemployment rate remained at 4.2% in October. In the three months to November,
the number of job vacancies fell for the 17th month in a row, from around 959,000 in
October to around 949,000. That has reduced the vacancy to unemployment ratio as
demand for labour eases relative to supply, which may support a further easing in
wage growth in the coming months.
 CPI inflation fell from 6.7% in September to 4.6% in October, and then again to 3.9%
in November. Both these falls were bigger than expected and there are clear signs of
easing in domestic inflationary pressures. The fall in core CPI inflation from 5.7% to
5.1% in November was bigger than expected (consensus forecast 5.6%). That’s the
lowest rate since January 2022. Some of the decline in core inflation was due to the
global influence of core goods inflation, which slowed from 4.3% to 3.3%. But some of
it was due to services inflation falling from 6.6% to 6.3%. The Bank views the latter as
a key barometer of the persistence of inflation and it came in further below the Bank’s
forecast of 6.9% in its November Monetary Policy Report. This will give the Bank more
confidence that services inflation is now on a firmly downward path. 
 The Bank of England sprung no surprises with its December monetary policy
committee (MPC) meeting, leaving interest rates at 5.25% for the third time in a row
and pushing back against the prospect of near-term interest rate cuts. The Bank
continued to sound hawkish, with the MPC maintaining its tightening bias saying that
“further tightening in monetary policy would be required if there were evidence of more
persistent inflationary pressures”. And it stuck to the familiar script, saying that policy
will be “sufficiently restrictive for sufficiently long” and that “monetary policy is likely to
need to be restrictive for an extended period of time”. In other words, the message is
that the MPC is not yet willing to endorse investors’ expectations that rates will be cut
as soon as May 2024.
 Looking ahead, our colleagues at Capital Economics forecast that the recent
downward trends in CPI and core inflation will stall over the next few months before

Page 117

starting to decline more decisively again in February. That explains why we think the
Bank of England won’t feel comfortable cutting interest rates until H2 2024. 
 The fall in UK market interest rate expectations in December has driven most of the
decline in 10-year gilt yields, which have fallen in line with 10-year US Treasury and
euro-zone yields. 10-year gilt yields have fallen from 4.68% in October 2023 to around
3.70% in early January, with further declines likely if the falling inflation story is
maintained.
 Investors’ growing expectations that the Fed will cut interest rates soon has led to an
improvement in risk sentiment, which has boosted the pound and other risky assets.
In addition, the rise in the pound, from $1.21 in November to $1.27 now, has also been
supported by the recent relative decline in UK wholesale gas prices. 
 The further fall in 10-year real gilt yields in December has supported the recent rise in
the FTSE 100. That said, the index remains 5% below its record high in February 2023.
This modest rise in equities appears to have been mostly driven by strong
performances in the industrials and rate-sensitive technology sectors. But UK equities
have continued to underperform US and euro-zone equities. The FTSE 100 has risen
by 2.2% in December, while the S&P 500 has risen by 3.8%. This is partly due to lower
energy prices, which have been a relatively bigger drag on the FTSE 100, due to the
index’s high concentration of energy companies. 
In the chart below, the rise in gilt yields across the curve in the first half of 2023/24, and
therein PWLB rates, is clear to see, prior to the end of year rally based on a mix of
supportive domestic and international factors. 
3.00%
3.40%
3.80%
4.20%
4.60%
5.00%
5.40%
5.80%
6.20%
6.60%
7.00%
PWLB Rates 3.4.23 - 29.12.23
1 Year 5 Year 10 Year 25 Year 50 Year 50 year target %

Page 118

MPC meetings 2nd November and 14th December 2023
 On 2nd November, the Bank of England’s Monetary Policy Committee (MPC) voted to keep
Bank Rate on hold at 5.25%, and on 14th December reiterated that view.  Both increases
reflected a split vote, the latter by 6 votes to 3, with the minority grouping voting for an increase
of 0.25% as concerns about “sticky” inflation remained in place.  
 Nonetheless, with UK CPI inflation now at 3.9%, and core inflating beginning to moderate
(5.1%), markets are voicing a view that rate cuts should begin in Q1 2024/25, some way ahead
of the indications from MPC members.  Of course, the data will be the ultimate determinant, so
upcoming publications of employment, wages and inflation numbers will be of particular
importance, and on-going volatility in Bank Rate expectations and the gilt yield curve can be
expected.
 In addition, what happens outside of the UK is also critical to movement in gilt yields.  The US
FOMC has kept short-term rates in the range of 5.25%-5.50%, whilst the ECB has moved its
Deposit rate to a probable peak of 4%.  Markets currently expect both central banks to start
cutting rates in 2024.

Page 119

Appendix 2 – Interest Rate Forecast 
The Council has appointed Link Group as its treasury advisors and part of their service is to assist the
Council to formulate a view on interest rates. The PWLB rate forecasts below are based on the Certainty
Rate (the standard rate minus 20 bps) which has been accessible to most authorities since 1st
November 2012. 
Link provided the following forecasts on 08 January 2024.  These are forecasts for Bank Rate, average
earnings and PWLB certainty rates, gilt yields plus 80 bps.   
 The Link forecast for average earnings are averages i.e., rates offered by individual banks may
differ significantly from these averages, reflecting their different needs for borrowing short-term cash
at any one point in time.
Additional notes by Link on this forecast table: -
 Our central forecast for interest rates was previously updated on 7 November and reflected a
view that the MPC would be keen to further demonstrate its anti-inflation credentials by keeping
Bank Rate at 5.25% until at least H2 2024.  We expect rate cuts to start when both the CPI
inflation and wage/employment data are supportive of such a move, and when there is a
likelihood of the overall economy enduring at least a slowdown or mild recession over the coming
months (although most recent GDP releases have surprised with their on-going robustness). 
 Naturally, timing on this matter will remain one of fine judgment: cut too soon, and inflationary
pressures may well build up further; cut too late and any downturn or recession may be
prolonged.  
 In the upcoming months, our forecasts will be guided not only by economic data releases and
clarifications from the MPC over its monetary policies and the Government over its fiscal policies,
but also international factors such as policy development in the US and Europe, the provision of
fresh support packages to support the faltering recovery in China as well as the on-going conflict
between Russia and Ukraine, and Gaza and Israel. 
A SUMMARY OVERVIEW OF THE FUTURE PATH OF BANK RATE
 Our central forecast for interest rates was previously updated on 7th November and reflected a view
that the MPC would be keen to underpin its anti-inflation credentials by keeping Bank Rate at 5.25%
until at least H2 2024.  We expect rate cuts to start when both the CPI inflation and
wage/employment data are unequivocally supportive of such a move, and that there is a strong
likelihood of the overall economy enduring tepid growth (at best) or a mild recession (at worst) over
the coming months. 
 Naturally, timing on this matter will remain one of fine judgment: cut too soon, and inflationary
pressures may well build up further; cut too late and any downturn or recession may be prolonged.   
Link Group Interest Rate View 08.01.24
Mar-24 Jun-24 Sep-24 Dec-24 Mar-25 Jun-25 Sep-25 Dec-25 Mar-26 Jun-26 Sep-26 Dec-26 Mar-27
BANK RATE 5.25 5.25 4.75 4.25 3.75 3.25 3.00 3.00 3.00 3.00 3.00 3.00 3.00
3 month ave earnings 5.30 5.30 4.80 4.30 3.80 3.30 3.00 3.00 3.00 3.00 3.00 3.00 3.00
6 month ave earnings 5.20 5.10 4.60 4.10 3.70 3.30 3.10 3.10 3.10 3.10 3.10 3.10 3.10
12 month ave earnings 5.00 4.90 4.40 3.90 3.60 3.20 3.10 3.10 3.10 3.10 3.10 3.20 3.20
5 yr   PWLB 4.50 4.40 4.30 4.20 4.10 4.00 3.80 3.70 3.60 3.60 3.50 3.50 3.50
10 yr PWLB 4.70 4.50 4.40 4.30 4.20 4.10 4.00 3.90 3.80 3.70 3.70 3.70 3.70
25 yr PWLB 5.20 5.10 4.90 4.80 4.60 4.40 4.30 4.20 4.20 4.10 4.10 4.10 4.10
50 yr PWLB 5.00 4.90 4.70 4.60 4.40 4.20 4.10 4.00 4.00 3.90 3.90 3.90 3.90

Page 120

 In the upcoming months, our forecasts will be guided not only by economic data releases and
clarifications from the MPC over its monetary policies and the Government over its fiscal policies,
but also international factors such as policy development in the US and Europe, the provision of
fresh support packages to support the faltering recovery in China as well as the on-going conflict
between Russia and Ukraine, and Gaza and Israel. 
 On the positive side, consumers are still anticipated to be sitting on some excess savings left over
from the pandemic, which could cushion some of the impact of the above challenges and may be
the reason why the economy is performing a little better at this stage of the economic cycle than
may have been expected. Nonetheless, with approximately 400,000 households per quarter facing
a mortgage interest reset at higher levels than their current rate, the economy will face on-going
headwinds from that source, in addition to lower income households having to spend
disproportionately on essentials such as food, energy and rent payments. 
PWLB RATES
 The short and medium part of the gilt curve has rallied since the start of November as markets
price in a quicker reduction in Bank Rate through 2024 and 2025 than held sway back then. 
This reflects market confidence in inflation falling back in a similar manner to that already seen
in the US and the Euro-zone.  At the time of writing there is c70 basis points difference between
the 5 and 50 year parts of the curve. 
The balance of risks to the UK economy: -
 The overall balance of risks to economic growth in the UK is even. 
Downside risks to current forecasts for UK gilt yields and PWLB rates include: -
 Labour and supply shortages prove more enduring and disruptive and depress economic activity
(accepting that in the near-term this is also an upside risk to inflation and, thus, could keep gilt yields high
for longer). 
 The Bank of England has increased Bank Rate too fast and too far over recent months, and
subsequently brings about a deeper and longer UK recession than we currently anticipate. 
 Geopolitical risks, for example in Ukraine/Russia, the Middle East, China/Taiwan/US, Iran and
North Korea, which could lead to increasing safe-haven flows. 
Upside risks to current forecasts for UK gilt yields and PWLB rates: -
 Despite the recent tightening to 5.25%, the Bank of England allows inflationary pressures to
remain elevated for a long period within the UK economy, which then necessitates Bank Rate
staying higher for longer than we currently project.
 
 The pound weakens because of a lack of confidence in the UK Government’s pre-election fiscal
policies, resulting in investors pricing in a risk premium for holding UK sovereign debt. 
 Projected gilt issuance, inclusive of natural maturities and Quantitative Tightening (QT), could
be too much for the markets to comfortably digest without higher yields compensating.

Page 121

Appendix 3 – Prudential Indicators 
PRUDENTIAL INDICATOR 2023-24 2023-24 2024-25 2025-26
(1).  EXTRACT FROM BUDGET
Forecast
Outturn
Original
Estimate
Forecast
Outturn
Forecast
Outturn
Capital Expenditure £'000 £'000 £'000 £'000
Non - HRA 6,593 43,110 42,195 40,911
TOTAL 6,593 43,110 42,195 40,911
Ratio of financing costs to net revenue stream
Non - HRA 4.25% 4.37% 4.40% 4.43%
Net borrowing requirement
brought forward 1 April * 291,782 304,498 286,645 316,648
carried forward 31 March * 286,645 372,359 316,648 344,751
in year borrowing requirement (5,137) 67,861 30,003 28,103
In year Capital Financing Requirement
Non - HRA (5,137) 67,861 30,003 28,103
TOTAL (5,137) 67,861 30,003 28,103
Capital Financing Requirement as at 31 March    
Non - HRA 286,645 372,359 316,648 344,751
TOTAL 286,645 372,359 316,648 344,751

Page 122

PRUDENTIAL INDICATOR 2023-24 2024-25 2025-26
(2).  TREASURY MANAGEMENT PRUDENTIAL INDICATORS £'M £'M £'M
Authorised limit for external debt -    
borrowing 268 283 305
other long term liabilities 112 113 108
TOTAL 380 396 413
Operational boundary for external debt -     
borrowing 263 278 300
other long term liabilities 109 110 105
TOTAL 372 388 405
Upper limit for fixed interest rate exposure
Principal re fixed rate borrowing 190% 190% 190%
Upper limit for variable rate exposure
Principal re variable rate borrowing 60% 60% 60%
Upper limit for total principal sums invested for over 364 days £20m £20m £20m
(per maturity date)
Maturity structure of new fixed rate borrowing during 2023/24upper limit lower limit
under 12 months 30% 0%
12 months and within 24 months 30% 0%
24 months and within 5 years 30% 0%
5 years and within 10 years 40% 0%
10 years and above 100% 0%

Page 123

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 15 FEBRUARY 2024
RESERVES AND BALANCES – UPDATE AS AT 31 DECEMBER 2023 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to advise Members of the overall level of
reserves held by the Council as well as providing detail on the monitoring of the
earmarked balances held within the General Fund. 
1.2 The Council has a total of £666.354m unusable reserves that are not backed with
resources. They are required purely for accounting purposes. 
1.3 At 31 March 2023 the Council had a total of £93.828m of usable reserves. Of this:
• £2.916m relates to the Repairs and Renewals Fund
• £4.503m relates to Capital Funds
• £86.409m was held in the General Fund, with £79.466m of this balance
earmarked for specific purposes.
1.4  During 2023-24, the amount of £4.776m which was previously agreed to be utilised
from the one-off reprofiling gain from the Loans Fund Review was drawn down into
Earmarked Reserves to be used to fund the Capital Programme as detailed in
paragraph 3.5.1. This results in the total earmarked balance increasing to
£84.242m. 
1.5 Of the earmarked balance of £84.242m: 
• £41.505m is invested or committed for major initiatives/capital projects 
• £6.032m has already been drawn down
• £13.087m is still to be drawn down in 2023-24
• £23.618m is planned to be spent in future years 
1.6 The Council’s General Fund contingency level is set at 2% of net expenditure for
2023-24 which equates to £5.691m.  At the beginning of the financial year there
was £1.252m of unallocated General Fund Balance (over and above contingency). 
After taking into consideration the budgeted allocation to the General Fund agreed
by Council on 23 February 2023, the earmarked balances no longer required, the
current forecast outturn position for 2023-24 and the proposed allocation for floral
displays the Council is forecast to have a £1.276m surplus over contingency.

Page 124

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 15 FEBRUARY 2024
RESERVES AND BALANCES - UPDATE AS AT 31 DECEMBER 2023 
2. INTRODUCTION 
2.1 This report outlines current balances on the Council’s reserves, both usable and
unusable. It also provides detail on the monitoring of the earmarked balances
within the General Fund.   
3. DETAIL 
3.1 Types of Reserves 
3.1.1 Usable Reserves - Councils have powers to establish certain resource backed
reserves which can be used to fund expenditure.  The powers of councils to
establish reserves are laid out in Schedule 3 of the Local Government
(Scotland) Act 1975.  These allow councils to establish a Renewal and Repairs
Fund, Insurance Fund and Capital Fund. Councils can also establish a Useable
Capital Receipts Reserve.  The Council must also maintain a General Fund and
can earmark balances for specific purposes within the General Fund. 
3.1.2 Unusable Reserves – Councils are also required to establish certain reserves
that are not backed by resources. They are required purely for accounting
purposes and do not represent resources available for councils to utilise. The
Pensions Reserve, Revaluation Reserve, Capital Adjustment Account, Financial
Instruments Adjustment Account and Accumulated Absences Account are
examples of unusable reserves. 
3.2 Reserve Balances at 31 March 2023 
3.2.1 The balances on each type of reserve at 31 March 2023 are set out in the two
tables below, per the Unaudited Accounts for 2022-23. 
Unusable Reserves £000
Revaluation Reserve 174,952
Capital Adjustment Account 268,788
Financial Instruments Adjustment Account (1,871)
Pensions Reserve 232,073
Accumulated Absences Account (7,588)
Total Unusable Reserves 666,354 
Usable Reserves £000
Repairs and Renewals Fund 2,916
Capital Fund and Usable Capital Receipts Reserve 4,503                                                                                                                
General Fund  86,409
Total Usable Reserves  93,828
Total Reserves  760,182

Page 125

3.2.2 The Revaluation Reserve represents the unrealised gains in the valuation of
fixed assets. The Capital Adjustment Account represents the difference
between depreciation based on proper accounting practice and statutory
charges for financing capital expenditure. The Financial Instruments Adjustment
Account represents the difference between gains and losses on borrowing and
statutory capital financing charges. The Pensions Reserve represents the
difference between pension costs based on proper accounting practice and
payments made for pension costs. The Accumulated Absences Account
represents the costed difference between holiday pay entitlement and actual
holidays taken at 31 March. 
3.2.3 The Repairs and Renewals Fund was established to support funding of renewal
and replacement of school equipment.  Schools can only draw on the Repairs
and Renewals Fund to the extent they have previously paid into the Fund and
contributions must be contained within schools devolved budgets. 
3.2.4 The Capital Fund was established to receive all capital receipts generated by
the Council and can be used to support the capital plan or meet the principal
repayments on loan charges. The Council decides as part of the budget
process each year how it wishes to draw funding from the Capital Fund. 
3.2.5 The Usable Capital Receipts Reserve relates to the accumulated unspent
capital receipts from sale of council houses prior to transfer of the housing
stock. The reserve forms part of the Council’s Strategic Housing Fund and can
only be used for investment in social housing. The reserve will be used in
accordance with the approach to investing in housing agreed by the Council in
August 2012. 
3.3 General Fund 
3.3.1 The General Fund balance at 31 March 2023 can be analysed as follows: 
Balance
31/03/23
£000
Balance on General Fund as at 31 March 2022 96,081
Decrease to General Fund balance at end of 2022-23 (9,672)
Earmarked Balances (79,466)
Contingency allowance at 2% of net expenditure (5,691)
Unallocated balance as at 31 March 2023 1,252 
3.3.2 The General Fund includes balances that the Council has agreed to earmark for
specific purposes. Some of these earmarked balances will be spent during the
current financial year and some of them will be held over and spent in later
years. The table below shows the balance at 31 March 2023, the new amount
earmarked from the Loans Fund gain (see section 3.5.1), the amounts that are
currently invested or set aside for major initiatives, the amount already spent
and planned to be spent in the current year, the amount to be spent in future
years and any sums no longer required to be earmarked. Appendix 1 provides
further details on the breakdown of unspent budget earmarkings.  Officers have

Page 126

reviewed and updated the spending profiles. Appendix 2 provides further details
on the breakdown of COVID reserves. 
3.3.3 Investment in Affordable Housing £0.104m – this earmarked balance provides
cash backed reserves for the loans to registered social landlords.  It is
estimated that as at 31 March 2024, the balance on the remaining loans will be
£3.059m, therefore £0.104m can be released back to the general fund. 
3.4 Unallocated General Fund Balance
Earmarking
Category
Balance
31/03/2023 -
per year
end
published
report
New
Earmarkings
in year
Invested or
committed
for major
initiatives
/capital
projects
Drawn-
down to
2023-24
Budget as
at 31/12/23
Still to be
drawn-
down in
2023-24
Planned
Spend
Future
Years
Released to
General
Fund
£000 £000 £000 £000 £000 £000 £000
Strategic Housing
Fund 7,247 6,847 400
Investment in
Affordable
Housing
3,163 3,059 104
Capital Projects 16,059 4,776 20,835
Lochgilphead and
Tarbert
Regeneration
1,460 1,460
Support for Rural
Growth Deal 756 756
Asset
Management
Investment
2,098 2,070 28
Piers and
Harbours
Investment Fund
2,789 2,789
Scottish
Government
Initiatives
2,834 383 152 2,299
CHORD 378 150 228
DMR Schools 1,394 669 692 33
Energy Efficiency
Fund 218 218
Existing Legal
Commitments 476 476
Unspent Grant 13,179 489 1,811 4,684 6,195
Unspent Third
Party Contribution 265 31 97 137
Previous Council
Decision - Other 3,808 1,699 225 424 1,460
Redundancy
Provision 1,578 500 1,078
Supporting
Organisational
Change
1,426 111 89 1,226
One Council
Property Team 566 189 377
Fleet - Timing
Delay 658 174 484
Hermitage Park 19 5 14
Electric Vehicle
Chargers 17 0 17
COVID-19 5,512 257 592 3,347 1,316
Unspent Budget 13,566 1,140 1,782 2,666 7,978
Totals 79,466 4,776 41,401 6,032 13,387 23,318 104

Page 127

3.4.1  The Council’s General Fund contingency is set at 2% of net expenditure for
2023-24 and amounts to £5.691m.  At the beginning of the financial year there
was £1.252m of unallocated General Fund Balance (over and above
contingency).   After taking into consideration the budgeted allocation to the
General Fund agreed by Council on 23 February 2023, the earmarked balances
no longer required, the current forecast outturn position for 2023-24 and the
proposed allocation for floral displays the Council is forecast to have a £1.276m
surplus over contingency. 
3.4.2 The revenue budget position as at 31 December 2023 was estimated to be a
£0.091m overspend. 
3.4.3 Social Work, as a part of the Integrated Joint Board (IJB), are able to hold any
surplus within reserves therefore it is expected that any underspend that
materialises would be transferred to the IJB reserves and the General Fund of
the Council would not be impacted.  Note that as at 31 December, Social Work
was projecting a breakeven position.  
3.4.4 The Environment, Development and Infrastructure Committee on 31 August
2023 agreed to pursue a blended model of options for the provision of floral
displays and recommended the additional revenue cost for 2023-24 of £0.008m
be funded from the unallocated General Fund and built into the budget outlook
estimates for future years.  
3.4.5  The table below summarises the position of the unallocated General Fund
balance taking into consideration the points noted above. 
Heading Detail £000
Unallocated General Fund
as at 31 March 2023
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£5.691m
1,252
Budgeted allocation to
General Fund for 2023-24
Budget
Per the Budget Motion at Council on
23 February 2023
19
Earmarked Balances no
longer required
Per paragraph 3.3.3 – amount
previously earmarked that can be
released back to the general fund
104
Current Forecast Outturn
for 2023-24 as at 31
December 2023
Per paragraph 3.4.2.  (91)
Social Work outturn
adjustment
Per paragraph 3.4.3 - Social Work
would expect to transfer any surplus
to internal IJB reserves
0
Allocation from
unallocated general fund
balance
Per paragraph 3.4.4 (8)
Estimated Unallocated
balance as at 31 March
2024 
1,276

Page 128

3.5 Loans Fund Review 
3.5.1 At the Council meeting on 27 February 2020, it was agreed that the one-off re-
profiling gain of £20.561m generated by the loans fund review should be used
partly to create a provision for the increasing principal repayments over the next
10 years (£7.649m) with the remainder of the gain (£12.912m) used to fund
known liabilities/cost pressures. The table below shows what has been drawn
down against the one-off gain and the remaining balance. 
Agreed
Allocation
Transferred
to
Earmarked
Reserves in
previous
years
Transferred
to
Earmarked
Reserves
23-24 
Balance
Remaining 
£000 £000 £000 £000
Provision for increasing
principal repayments 7,649   7,649
Funding Gap in Capital
Programme 2,619  (2,619) 0
Significant Strategic Change
Projects  5,013 (2,856) (2,157) 0
Completed Projects  5,280 (5,280)  0 
20,561 (8,136) (4,776) 7,649 
4. CONCLUSION 
4.1 The report outlines the overall reserves and balances for the Council covering
the purpose and level of each reserve.  It also provides detail as to expenditure
against earmarked balances held within the General Fund.   
4.2 As at 31 December 2023 the estimated unallocated General Fund, after taking
into consideration the budget motion, the current forecast outturn for 2023-24
and the proposed allocation for floral displays, the Council is estimated to have
a £1.276m surplus over contingency. 
5. IMPLICATIONS 
5.1 Policy - Earmarked funds and funds set aside for delivery of
Single Outcome Agreement are available to support
Council Policy.
5.2 Financial -  Outlines the balances held with the Council’s usable
and unusable reserves.     
5.3 Legal -  None.
5.4 HR -  None.
5.5 Fairer Scotland Duty- None.
5.5.1 Equalities – protected
characteristics - 
None.
5.5.2 Socio-economic Duty -  None.
5.5.3 Islands -  None.
5.6 Climate Change - None.
5.7 Risk -  A contingency of £5.691m (equivalent to 2% of net
expenditure) has been set aside as part of the

Page 129

general fund.  This has been subject to a risk
assessment. 
5.8 Customer Service -  None. 
Kirsty Flanagan
Executive Director/Section 95 Officer 
12 January 2024 
Policy Lead for Finance and Commercial Services - Councillor Gary Mulvaney 
APPENDICES
Appendix 1 – Earmarked Reserves breakdown of unspent budget
Appendix 2 – Earmarked Reserves breakdown of COVID earmarkings 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 130

APPENDIX 1
Earmarked Reserves - Unspent Budget
As at 31 December 2023
Ref Department Service Description Opening Balance Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
001 Chief Executive's Unit Community Planning Communities and Partnership
Team
8,855 0 8,855 0 8,855 The funds have originated from externally sourced income due to an employee being seconded to the
Scottish Community Development Centre (SCDC).  The funds will be used to support the team in
relation to meeting its priorities of Building Back Better (Communities), Climate Change and the review
of the Argyll and Bute Outcome Improvement Plan.
0 8,855
002 Executive Director
(Douglas Hendry)
Across Services /
Education
Digital Projects (Supply Staff
Booking System)
25,100 9,900 15,200 0 15,200 To deliver a number of Digital Service Transformation Projects with a commitment of £0.035m towards
a Supply Staff Booking system.  Phase 1 of the project is nearing completion.
9,900 15,200
003 Executive Director
(Douglas Hendry)
Commercial Services Rothesay Academy - Demolition
and Waste Disposal
953,875 73,655 880,220 0 880,220 Since Rothesay Academy was vacated over 15 years ago no site clearance has taken place and there are
potential Health and Safety and insurance cover implications due to deterioration of the building.
£55,000 earmarking has allowed clearance of remaining materials and debris.
Also £840,000 to fund estimated future costs of demolition (subject to removal of listed status) to be
added to an existing earmarking . There are potential Health and Safety and insurance cover
implications due to deterioration of the building.
73,655 880,220 0
004 Executive Director
(Douglas Hendry)
Commercial Services Rothesay Pavilion Charity 750,000 0 750,000 0 750,000 Agreed at Council meeting February 2020, £750k additional revenue support subject to conditions
which seek to minimise the risk to the Council as far as is reasonably practicable including requirement
for adequate business and financial management and regular reporting by RPC.
0 750,000
005 Executive Director
(Douglas Hendry)
Commercial Services Rothesay Pavilion Essential
repairs
306,400 0 306,400 0 306,400 Essential repairs to deal with potential health and safety risks and to avoid further deterioration. 
Budget provision was approved by the Policy and Resources Committee on 21 August 2014. 
0 306,400
006 Executive Director
(Douglas Hendry)
Commercial Services Estates - NDR Revaluation
Appeals
84,688 24,750 59,938 59,938 0
The Council agreed to make provision to meet the cost of appealing Non Domestic Rates (NDR)
revaluations which were imposed from April 2017. The remaining funds were carried forward to the
2023/24 revaluation cycle however a recent change in position by the Scottish Government may restrict
the appeals which can be made. This is still under discussion and Gerald Eve Surveyors have been
appointed as specialist advisers on this matter. In the event that appeals are limited there may be an
opportunity to utilise Gerald Eve for more general valuation advice subject to Procurement approval.
84,688 0
007 Executive Director
(Douglas Hendry)
Commercial Services Demolition of former
Lochgilphead Primary and
Rothesay Secondary School
0 0 0 0 0 To fund the demolition of the former Lochgilphead Primary School and former Rothesay Academy
(subject to the removal of the listing). Lochgilphead Primary complete and remainder of funds to be
used to commence Rothesay Project. This project now completed.
0 0
008 Executive Director
(Douglas Hendry)
Commercial Services Mid Argyll Community Pool 30,000 30,000 0 0 0 At the Council Budget meeting on 23 February 2023, the Council committed to a one-off investment of
£0.030m to Mid Argyll Community Pool in response to an external funding request. Paid.
30,000 0
009 Executive Director
(Douglas Hendry)
Commercial Services MacTaggart Leisure Islay 30,000 30,000 0 0 0 At the Council Budget meeting on 23 February 2023, the Council committed to a one-off investment of
£0.030m to MacTaggart Leisure, Islay in response to an external funding request. Paid.
30,000 0
010 Executive Director
(Douglas Hendry)
Commercial Services Site Investigation Works 21,013 0 21,013 21,013 0 For Site Investigation works in relation to Tweeddale Street Car Park and Oban Airport Business Park,
exploring commercial opportunities to develop the sites and raise revenue income for Argyll and Bute
Council. HUB North were instructed to procure contractors to undertake the site investigations these
are now complete. The remainder of the budget is intended to be utilised for other site investigation
and pre-development works to further develop commercial opportunities across the council area.
21,013 0
011 Non Departmental /
Executive Director
(Douglas Hendry)
Across Services /
Commercial Services
Information Management
(Estates Survey Work)
12,697 0 12,697 12,697 0 To support a number of initiatives in respect of improving the Council's information management in line
with the transformation agenda and increasing the pace of change as outlined in the BV Review.  The
planned initiatives include: Estates Survey work £122k, Digitalisation of Title Deeds £92k, document
management and workflow system for Planning, Building Standards and Environmental Health £77k and
a balance of funding to explore information management solutions in a strategic and coherent way
£209k
12,697 0
012 Executive Director
(Douglas Hendry)
Commercial Services (2023 Contract Inflation
Adjustments) MAKI/Islay Pools
SLA - inflationary increase
9,523 9,523 0 0 0 Additional pressure resulting from the February 2023 inflation rate being higher than the assumptions
built into the non-pay inflation calculation which went to Council at budget setting and reflects the
difference between what was in the budget and what will need to be paid under the SLAs. The February
inflation figure wasn't known until the middle of March, after the budget was set, and the recent trend
in inflation reductions turned around in February with an increase.
9,523 0 0
013 Executive Director
(Douglas Hendry)
Education ASN Review 1,255,000 0 1,255,000 0 1,255,000 To fund capital costs of ASN adaptations as part of ASN Review to increase equity of provision across
Argyll and Bute.  This will be subject to a business case as part of the wider ASN review. Update:
Business case now approved and working group set up with quotes for works being carried out Jan
2024.
0 1,255,000 0
014 Executive Director
(Douglas Hendry)
Education Reduced Teacher Staffing Costs -
Strike Action
800,000 0 800,000 0 800,000 To fund one off savings in 2024-25 from the underspend in staffing from strike action. 0 800,000 0
015 Executive Director
(Douglas Hendry)
Education (2023 Digital Projects) School Wi-
Fi Upgrades
200,000 33,076 166,924 116,924 50,000 To extend Wi-Fi coverage within school settings through the purchase of additional hardware such as
access points, switches and other networking hardware. This will result in more flexible learning spaces
and support the growing number of devices within schools. 
150,000 50,000 0

Page 131

Ref Department Service Description Opening Balance Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
016 Executive Director
(Douglas Hendry)
Education Education Transformation Fund 146,579 1,942 144,637 144,637 0 At the Council meeting on 27 February 2020, it was agreed to input £400k into Education Digital
Learning.  The additional funds have been spent in 20/21, 21/22 and 22/23 as part of the ongoing
transformation work in the Education service, focussing on digital and virtual learning technology and
the development of learning clusters.  This will continue into 2023/24.
146,579 0
017 Executive Director
(Douglas Hendry)
Education MCR Pathways Pilot 80,000 40,872 39,128 0 39,128 Funding to support implementation of MCR Pathways mentoring programme within three secondary
schools for 2023-24 academic year. Funding will allow the employment of a dedicated Co-ordinator
within each setting to develop and implement the programme which is designed to benefit care
experienced and other disadvantaged pupils through targeted mentoring support.
40,872 39,128 0
018 Executive Director
(Douglas Hendry)
Education Gaelic Specific Grant 30,000 0 30,000 0 30,000 Proposal to fund the continuation of the Principal Teacher Languages (Gaelic focus) post for the 2023-
24 academic year to promote and develop Gaelic Medium Education across Argyll and Bute. This
earmarking refers to the Council contribution towards the Gaelic grant for 22-23.
0 30,000 0
019 Executive Director
(Douglas Hendry)
Education (2023 Digital Projects) Cashless
Catering
30,000 0 30,000 5,000 25,000 To support the ongoing implementation of the new cashless catering system during the testing and roll
out phase.
5,000 25,000 0
020 Executive Director
(Douglas Hendry)
Education Skype for Business for Education
/ Digital Projects (Skype for
Business)
10,000 0 10,000 10,000 0 To fund the initial capital costs for the implementation of Skype for Business for Education.  This will
bring the Education service in line with other council departments and will improve staff collaboration
and modernise school telephony to deliver the  service more efficiently and cost effectively.
A balance was released back to the general fund in 2021-22 because the rollout project was almost
complete with only £0.01m expected spend in 23/24.
10,000 0
021 Executive Director
(Douglas Hendry)
Education Education Learning Estate
Condition Surveys
1,815 0 1,815 1,815 0 To fund the delivery of School Core Facts (SCF) compliant Condition Surveys for prioritised School
Buildings.
1,815 0
022 Executive Director
(Douglas Hendry)
Legal and Regulatory
Services
Education Purchasing Officers 210,000 37,000 173,000 0 173,000 The earmarked funds will be used to fund an education purchasing team within the Procurement
Service for two years.  The team will embed good procurement practice, train headteachers on current
procurement process requirements, develop spend plans that evidence best value.
37,000 173,000
023 Non Departmental /
Executive Director
(Douglas Hendry)
Across Services / Legal
and Regulatory
Services
Information Management
(Digitalisation of Title Deeds)
92,000 0 92,000 0 92,000 To support a number of initiatives in respect of improving the Council's information management in line
with the transformation agenda and increasing the pace of change as outlined in the BV Review.  The
planned initiatives include: Estates Survey work £122k, Digitalisation of Title Deeds £92k (delay on
spending due to COVID-19), document management and workflow system for Planning, Building
Standards and Environmental Health £77k and a balance of funding to explore information
management solutions in a strategic and coherent way £209k
0 92,000
024 Executive Director
(Douglas Hendry)
Legal and Regulatory
Services
Councillor IT Equipment 44,557 0 44,557 0 44,557 There is currently no budget for the provision and renewal of IT equipment for members. the
earmarking identifies a resource to utilise spend for that purpose to ensure that members have
continued support in maintaining and replacing vital IT equipment.
0 44,557
025 Executive Director
(Douglas Hendry)
Legal and Regulatory
Services
Digital Projects: Hybrid Council
meetings
43,302 0 43,302 0 43,302 The funding will be used to maintain the ICT equipment used to support the provision of on-line and
hybrid Council meetings.
0 43,302
026 Executive Director
(Douglas Hendry)
Legal and Regulatory
Services
Debt Counselling & Welfare
Rights
21,452 0 21,452 0 21,452 To meet the cost of a Debt Counselling and Welfare Rights Management System. 0 21,452
027 Executive Director
(Douglas Hendry)
Legal and Regulatory
Support
(2023 Contract Inflation
Adjustments) NPDO and DBFM
School Contracts – inflationary
increase
350,000 350,000 0 0 0 Additional pressure resulting from the February 2023 inflation rate being higher than the assumptions
built into the non-pay inflation calculation which went to Council at budget setting and reflects the
difference between what was in the budget and what will need to be paid under the NPDO/Hub DBFM
Schools contracts. The February inflation figure wasn't known until the middle of March, after the
budget was set, and the recent trend in inflation reductions turned around in February with an
increase.
350,000 0 0
028 Executive Director
(Douglas Hendry)
Legal and Regulatory
Support
(2023 Digital Projects)
Replacement of Council
Chambers Online Meeting
Equipment
130,000 0 130,000 130,000 0 Current online meeting system  is less than resilient and has failed on a number of occasions, leading to
issues at strategic committees. A condition assessment by the incumbent maintenance contractor has
highlighted that the current equipment is now at end of life and unsupportable due to the 
obsolescence of the system. Discussions with ICT have taken place to identify a simpler more robust
solution to be procured.
130,000 0 0
029 Executive Director
(Kirsty Flanagan)
Customer Support
Services
(2023 Digital Projects) iTrent
Project
332,000 0 332,000 147,000 185,000 Combination of parallel running of the new iTrent system alongside the legacy systems for up to 18
months whilst iTrent is implemented and additional staffing resource to implement iTrent in late June
2024 and support staff for the first 3 months of operation through summer 2024. Total includes £73k
from Financial services for funding additional staffing resource to implement the payroll components of
the iTrent HR and Payroll System by the end of June 2024 and support staff for the first 3 months of
operation during summer 2024.
147,000 185,000 0
030 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Security Operations Centre
Subscription
113,594 0 113,594 53,594 60,000 There is a requirement to pay for a 3-year subscription at £60,000 per annum with a cost pressure being
added to the ICT revenue budget to cover the costs from year 4 onwards.  There is unallocated funding
of £103,545 from the earmarking (172) created at 2020/21 year end for 'Digital Projects' combined with
this earmarking to cover these costs for 3 years.
53,594 60,000
031 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Growing our Own and Modern
Apprentices
109,150 0 109,150 95,790 13,360 Funding earmarked to support trainee development and modern apprenticeship opportunities based
on priority workforce risk areas. These areas have been identified and proposals developed. £95,790 to
be spent in 23/24 and £13,360 to be spent in 24/25 to fund a graduate trainee and 3 apprentices to
deliver trainee development and modern apprenticeship opportunities
95,790 13,360
032 Non Departmental /
Executive Director
(Kirsty Flanagan)
Across Services /
Customer Support
Services
Digital Projects (Increase in
Schools Bandwidth)
63,455 0 63,455 63,455 0 To complete one of a number of Digital Service Transformation projects with a commitment of £0.064m
to increase Schools Bandwidth. 
63,455 0
033 Executive Director
(Kirsty Flanagan)
Customer Support
Services
(2023 Digital Projects) Resilient
Website Project
60,000 0 60,000 60,000 0 Cybersecurity action to move to a cloud based website platform that would improve resilience and
enable service continuity in the event of a cyber attack.  Procurement in progress for resilient website
solution and Scotgov Cloud Services Project providing input. Contract Award expected by end 2023.
60,000 0 0

Page 132

Ref Department Service Description Opening Balance Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
034 Executive Director
(Kirsty Flanagan)
Customer Support
Services
(2023 Digital Projects) Digital
Project Officer
60,000 0 60,000 60,000 0 Employ a temporary Digital Project Officer as part of OD changes. 60,000 0 0
035 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Implementation of Gaelic
Language Plan
30,000 0 30,000 30,000 0 Agreed at Council Meeting February 2021.  Provision of funding for delivery and implementation of the
council’s Gaelic Language Plan in recognition of the contribution that Gaelic makes to economic growth
and to the tourism sector, and to enable delivery of key activities within the plan which currently
receive no revenue funding.
30,000 0
036 Executive Director
(Kirsty Flanagan)
Customer Support
Services
(2023 Digital Projects) Digital
Engagement Services Developer
28,000 7,242 20,758 4,388 16,370 To fund 50% of a new temporary LGE10 post.  The post is a Digital Engagement Services Developer that
will provide capacity to deliver service efficiencies through the use of the new CREATE/RPA software. 
The other 50% of the post can be funded from a current vacancy.  New temporary Digital Developer
took up post on 18/09 and funds will be used for salary across the rest of the year – to be drawn down
in FQ4.
11,630 16,370 0
037 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Business Development Training 27,601 288 27,313 27,313 0 This budget is funding ongoing leadership development, coaching, action learning sets and
commissioned training including Priority Management.
27,601 0
038 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Learning and Development 19,436 0 19,436 19,436 0 In order to maximise the opportunities and efficiencies of digital learning, this funding will be used to
support the extension of digital learning in order to deliver the Digital Learning Strategy, which was
approved in FQ4 20/21.
19,436 0
039 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Establishing HR Service Centre 13,824 0 13,824 13,824 0 To facilitate the implementation of technical efficiency improvements and new processes 13,824 0
040 Non Departmental /
Executive Director
(Kirsty Flanagan)
Across Services /
Customer Support
Services
Digital Projects (Replacement
Learning Management System)
11,470 0 11,470 11,470 0 To deliver a number of Digital Service Transformation Projects with an original commitment of £0.030m
towards a replacement Learning Management System £0.030m.
11,470 0
041 Executive Director
(Kirsty Flanagan)
Development &
Economic Growth
Planning Income (Saving 23-24) 340,000 340,000 0 0 0 To fund one off operational saving MGT5 agreed for the 2023/24 budget 340,000 0 0
042 Executive Director
(Kirsty Flanagan)
Development &
Economic Growth
Planning Income 60,000 0 60,000 60,000 0 To fund additional resources to support and develop the Council's planning service. 60,000 0 0
043 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Oban TIF (Tax Incremental
Financing)
385,193 0 385,193 116,000 269,193 Will be used to fund the TIF Programme office for a further 3 years as well as the programme office for
Rural Growth Deal beyond the funding that was agreed at Council for this in February 2021.
116,000 269,193
044 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Strategic Events & Festivals 80,664 0 80,664 40,946 39,718 At the Council meeting on 25 February 21, a decision was taken to agree £90k funding for Events and
Festivals for 22/23, in order that the application process can commence during 21/22 and that this
agreed figure be augmented by any underspend remaining from the 20/21 financial year.  At 24
February 22, decision made to agree £90k for 23/24, in order that the application process can
commence during 22/23 and that this agreed figure be augmented by any underspend remaining from
the 21/22 financial year.  Applications have been received and payments will be made in 2023-2024.
40,946 39,718
045 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Island Post 50,461 0 50,461 50,461 0 To fund a temporary post at LGE11 to assist with the National Islands Plan Implementation Route Map
2020-2025.
50,461 0
046 Non Departmental /
Executive Director
(Kirsty Flanagan)
Across Services /
Development and
Economic Growth
Information Management
(Document Management and
Workflow for Planning, Building
Standards and Environmental
Health)
21,177 0 21,177 21,177 0 To support a number of initiatives in respect of improving the Council's information management in line
with the transformation agenda and increasing the pace of change as outlined in the BV Review.  The
planned initiatives include: Estates Survey work £122k, Digitalisation of Title Deeds £92k, document
management and workflow system for Planning, Building Standards and Environmental Health £77k and
a balance of funding to explore information management solutions in a strategic and coherent way
£209k Hoping to implement the replacement for IDOX in March 2024 but there have been severe
issues/delays with the new programme
21,177 0
047 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Royal National Mod 20,000 0 20,000 20,000 0 One off funding allocation for the Royal National Mod agreed as part of the budget setting process for
2019/20. Grant contract issued. Proposed payment of £20k per annum starting 2020/21  (2023/24 final
payment of £20k)
20,000 0
048 Executive Director
(Kirsty Flanagan)
Financial Services Financial Systems 33,748 0 33,748 33,748 0 To fund the completion of the implementation of the Oracle Fusion Financial Management System, a
software update for cash receipting to ensure card payments can still be taken and the procurement
and implementation of a new system to manage the requirements of the IFRS16 Leases accounting
standard.
33,748 0
049 Executive Director
(Kirsty Flanagan)
Financial Services Accounting and Budgeting Team
Resilience
30,664 0 30,664 16,664 14,000 To fund the implementation of a new staffing structure in 2022/23 as agreed at ELT on 12 April 2022
which has been implemented.  The residual funding is being used to meet the costs of ongoing
professional accountancy  training over the period 2022/23 to 2026/27
16,664 14,000
050 Executive Director
(Kirsty Flanagan)
Financial Services CIPFA 24,040 1,835 22,205 4,165 18,040 CIPFA Training - To fund the professional training costs for staff undertaking the CIPFA professional
accountancy qualification.
6,000 18,040
051 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure Waste Variation Monies 1,967,056 3,344 1,963,712 716,540 1,247,172 This will be used to fund/part-fund various waste infrastructure projects that will support the council’s
compliance with the 2025 ban on the Landfill of Biodegradable Municipal Waste. This will include
scoping work for the creation of a waste transfer station at Helensburgh and landfill cell construction
works at Gartbreck  (£640k for Capital works on Gartbreck completed in 2022/23, reserve will be drawn
down for this in 2023/24).
719,884 410,000 837,172
052 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure 3G pitches / Tarbert Sports
Pitches
375,022 76,749 298,273 3,251 295,022 In November 2018, the Council agreed to a maintenance funding package to be progressed for a
number of 3G pitches including Tarbert. This funding will provide an estimated 6.5 years’ worth of
ongoing maintenance up to 2025-26. 
80,000 80,000 215,022
053 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure Green Transport Initiatives 140,000 0 140,000 0 140,000 At the Council meeting on 27 February 2020, it was agreed to input £400k in Green transport,
investment in footway and cycle path maintenance supporting the healthy wellbeing and green agenda. 
Spend has been delayed due to COVID and this will be taken forward in 23/24. £260k Footways
Reconstruction programme now spent and will be drawn down against capital programme during
23/24. £140k Ardrishaig North Project spent in 22/23 and drawn down in 24/25.
0 140,000

Page 133

Ref Department Service Description Opening Balance Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
054 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure Climate Change 81,884 0 81,884 81,884 0 At the Council meeting on 27 February 2020, it was agreed to input £500k budget to mitigate the
impacts of weather related damage and climate change with specific emphasis on gully cleaning and
drainage improvements.  Spend has been delayed due to COVID and the intention is to spend the funds
on 2 Gully Motors plus staff over next 2 years. Vehicles have been received and budget will be drawn
down to cover their cost. The remaining budget will be used towards running the vehicles.
81,884 0
055 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure Amenity Services introduction of
management information
system
28,099 0 28,099 0 28,099 Delay with introduction of amenity time recording system due to increased costs.  Discussions ongoing
to find alternative cheaper solution.  The software/system being introduced by HR/Payroll during 2023-
24 offers a time-recording facility.  Although not included in the current HR/Payroll spec, once the new
system is up and running, the proposal would be to investigate the time-recording system to see if
viable for amenity time recording purposes.
0 28,099
056 Executive Director
(Kirsty Flanagan)
Roads & Infrastructure
Services
(2023 Contract Inflation
Adjustments) Waste PPP
255,000 0 255,000 150,000 105,000 Adjustment to inflation included in the budget based on updated RPIX figures at February 2023.  Based
on the current forecast it is anticipated the full earmarking will not be required and is unlikely to 
exceed £150K.  For the purposes of balancing this spreadsheet I have entered £150K against 2023-24
and the balance against 2024-25 at this stage.  Will be monitored monthly.
150,000 105,000 0
057 Non Departmental Non Departmental Underwriting development of
Rothesay Pavilion
1,000,000 0 1,000,000 0 1,000,000 Funding to meet additional costs identified as necessary for the refurbishment of Rothesay Pavilion. 0 1,000,000
058 Non Departmental Non Departmental Oban TIF (Tax Incremental
Financing - Excess NDR)
875,651 0 875,651 0 875,651 This is the surplus NDR after paying all Loans Charges in respect of TIF infrastructure projects.  This fund
will be used in the future as TIF projects are delivered.
0 0 875,651
059 Non Departmental Non Departmental Loans Fund 385,279 385,279 0 0 0 At the Council Budget meeting on 24 February 2022, Saving FS01, a Loans Fund
Management/Operational saving for 22/23 budget of £0.500m was agreed with at least £0.200m to
come from underspends in 21/22.  The underspend position for 21/22 is £0.385m and this earmarking is
being released as a saving to help bridge the 2023/24 budget gap.
385,279 0
060 Non Departmental Non Departmental Loans Fund 300,000 300,000 0 0 0 To fund one off operational saving MGT3 agreed for the 2023/24 budget 300,000 0 0
061 Non Departmental Non Departmental Information Management
(Balance of Funding)
209,844 9,375 200,469 0 200,469 To support a number of initiatives in respect of improving the Council's information management in line
with the transformation agenda and increasing the pace of change as outlined in the BV Review.  The
planned initiatives include: Estates Survey work £122k, Digitalisation of Title Deeds £92k, document
management and workflow system for Planning, Building Standards and Environmental Health £77k and
a balance of funding to explore information management solutions in a strategic and coherent way
£209k
9,375 200,469
062 Non Departmental Non Departmental Spend to Save Route
Optimisation Software
100,000 17,225 82,775 82,775 0 One-off re-profiling gain as a result of the loans fund review to fund known liabilities/cost pressures as
agreed at budget setting meeting in February 2020 -  Spend to save route optimisation (£0.100m) which
will be spent over  2023/24.
100,000 0
063 Non Departmental /
Social Work
Non Departmental Engagement with Hub North re
provision of services for olders
adults and vulnerable people
across Argyll and Bute
100,000 0 100,000 100,000 0 At the Council budget meeting February 23, an allocation of £0.1m from the Unallocated General Fund
balance for the Health and Social Care Partnership to engage, in partnership with the Council, with Hub
North to develop a strategic business case in relation to the provision of services for older adults and
other vulnerable people across Argyll and Bute.
100,000 0
064 Non Departmental Non Departmental CHARTS 80,000 0 80,000 80,000 0 As agreed at Council on 24 February 2022, investment in CHARTS £0.075m.  To support the organisation
in delivering targeted support, in communities, to the culture, arts and heritage sector as part of its
plans to contribute to overall economic recovery.
At the Council Budget meeting on 23 February 2023, the Council committed to £0.075m one-off
investment in CHARTS in response to an external funding request will be spent in 23-24
80,000
065 Non Departmental Non Departmental Community Resilience Fund 76,447 0 76,447 0 76,447 Fund established in 2012/13 to be spent over more than one year. Fund reduced at the Council meeting
on 11 February 2016
0 76,447
13,565,615 1,782,055 0 11,783,560 2,665,905 9,117,655 4,447,960 7,189,810 1,927,845

Page 134

APPENDIX 2
COVID
As at 31 December 2023
Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General
Fund
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
001 Chief Executive's Unit Community Planning Community Planning - temp post
to support communities
55,000 0 55,000 55,000 0 Post supporting year 1 of supporting communities fund 55,000 0
002 Chief Executive's Unit Community Planning Covid impacts – support to
communities’
49,147 47,926 1,221 1,221 0 Funding provided in relation to the Local Self-Isolation Assistance Service.  The Community Planning and
Development Team will work with community groups to support their community response and
resiliency to Test and Protect and the longer term impacts of COVID-19 on local community
organisations.
49,147 0
003 Executive Director
(Douglas Hendry)
Education Logistics Funding - Safe Opening
of Schools
699,036 0 699,036 50,000 649,036 Scottish Government funding to ensure the safe opening and operation of schools. Includes transport,
PPE, cleaning, ventilation and expansion of estate. It is likely that any unused balances would have to be
returned to the Scottish Government. Window replacement programme in schools with windows that do
not open, this will improve ventilation.  £500k to fund one off savings 2024-25.
50,000 649,036
004 Executive Director
(Douglas Hendry)
Education Additional Teaching/Support in
Schools/Digital Devices/Family
Home Learning Support Fund -
£45m Grant
421,198 69,832 351,366 311,366 40,000 Continuation of funding for additional staffing, teachers, support staff, additional devices for pupils and
additional family/home learning programmes.
381,198 40,000
005 Executive Director
(Douglas Hendry)
Education Education to Support Young
People
191,042 160,560 30,482 0 30,482 As agreed at the Council Meeting on 25 February 2021 with an original allocation of £0.600m.  Agreed to
fund a package of measures to boost the wellbeing and build back the resilience of young people, in
particular those most vulnerable, following the Covid-19 pandemic, including counselling and increased
provision of childcare for children under three. Notes that the Scottish Government is yet to confirm
details of funding for similar initiatives and, should our investment in children’s wellbeing qualify for this
funding, the balance will be re-allocated to the Recovery and Renewal Fund. 
160,560 30,482
006 Executive Director
(Douglas Hendry)
Education Recruitment of Additional
Teachers and Support Staff in
Schools
51,371 51,371 0 0 0 Fund additional teachers and support staff. Complete. 51,371 0
007 Executive Director
(Douglas Hendry)
Legal and Regulatory
Services
Welfare Rights Support 131,634 64,906 66,728 0 66,728 As agreed at the Council Meeting on 25 February 2021 - an allocation of £0.172m.  As part of our focus
on Improving Opportunities for People and Communities, agrees to provide additional resources to
proactively support people experiencing poverty and hardship, by investing in two additional Welfare
Rights support staff for two years.
64,906 66,728
008 Executive Director
(Kirsty Flanagan)
Customer Support
Services
Self Isolated Support / Self
Isolated Support Grant (HR)
65,250 49,750 15,500 0 15,500 These were monies that were provided by Scotgov to fund additional overtime and resources for
Shielding/Caring for People and Test and Protect activities.
The funds are being used for a number of Customer Service and Business efficiency related projects
including a system and consultancy of RPA (robotic process automation) and application development.  A
full corporate website upgrade and renewal using specialist web resources and the Digital Reception
Project.  Year 2 of Create/RPA low code and robotics system due for payment in October - £49k to be
drawn down. Procurement underway for Digital Registration Platform with contract award due FQ3.
49,750 15,500
009 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Staycation and Marketing Argyll
and Bute
389,992 0 389,992 300,000 89,992 As agreed at the Council Meeting on 25 February 2021 with an original allocation of £0.800m.   This will
include provision of additional waste disposal facilities and other facilities that will be informed by the
Motorhome and Informal Camping Survey.
As agreed at Council on 24 February 2022, Staycation investment £0.100m.  Augments the 2021/22
£0.5m staycation initiative with an additional investment of £100k, including support for community
groups and partners in the provision of facilities which can support increasing staycation visitor numbers
during the 2022/23 and 2023/24 seasons.
300,000 89,992
010 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Tackling Digital Exclusion Top-Up
Fund
217,600 0 217,600 217,600 0 As agreed at the Council Meeting on 25 February 2021.  Establishes the Tackling Digital Exclusion Top Up
Fund to support communities and in some cases individuals that are missing out on national
programmes due to logistics and economies of scale.  While vouchers are available from the UK and
Scottish Governments in some cases these do not cover the full cost of infrastructure builds. 
Expenditure should be incurred during 23-24 to draw down against.
217,600 0
011 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
LACER Funding (Sector Support
Grant)
95,398 0 95,398 95,398 0 Local Authority COVID Economic Recovery Fund grant.  This will provide funding, either part of the small 
business development grant or standalone, to help micros and small business to implement projects that
contribute to the sector as well as benefitting the business, for example: Tourism and hospitality, food
and drink or retail.  With option to provide additional business support to hard hit areas including Bute
and Kintyre where unemployment remains higher than average - support via specialist advice, locally
tailored grants to meet local priorities and targeted marketing activity. to be split £115,000 for Shop
fronts and £35,000  Business support via Business Gateway (as at 25/10/23 Shop fronts have £84,248
remaining and Bus support have £11,150 should all be spent in 23/24
95,398 0
012 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
Economic Development - temp
post to support economic
recovery
55,000 0 55,000 55,000 0 As agreed at Policy & Resources committee on 9 December 2021, allocation of £0.055m to a post to
support the economic and social recovery together with the building back stronger themes.  To be used
to fund Settlement Project Support Officer during 23-24.
55,000 0
013 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
EH Covid Posts 37,775 0 37,775 37,775 0 Funding initially for 2 posts for 2 years.  Posts were initially recruited to with one leaving and the other
going on maternity leave resulting in delays in expenditure.  One employee is now back from maternity
leave and earmarked reserve will be drawn down to cover their costs in 23-24.
37,775 0
014 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
LACER Funding (New Enterprise
Support Grant)
31,159 0 31,159 31,159 0 Local Authority COVID Economic Recovery Fund grant.  This funding would provide £3,000 grants to help
new businesses start up and establish.  Fund fully committed, there was a delay in getting all payments
made and remainder will be made in 23-24.
31,159 0
015 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
LACER Funding (Shop Local) 26,793 0 26,793 26,793 0 Local Authority COVID Economic Recovery Fund grant.  This funding would provide funding to continue
the Shop Local scheme into 2022/23 and 2023/24, buying additional cards and allow the cards to gather
momentum and support local businesses.
26,793 0
016 Executive Director
(Kirsty Flanagan)
Development and
Economic Growth
LACER Funding (Small Business
Development Grant)
24,988 0 24,988 24,988 0 Local Authority COVID Economic Recovery Fund grant.  This funding will provide funding of between
£500 and £5,000 to help existing micro and small businesses to improve their resilience or growth via
projects to implement green initiatives, implement digital development, implement marketing
improvements and improve efficiency/innovation.  Fully committed with final payments due in 2023-
2024.
24,988 0

Page 135

Ref Department Service Description Opening Balance Budget
Drawdown
Released
back to
General
Fund
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in 23-
24
Planned to
spend in future
years
Plans for Use Amount
Planned to be
Spent in 2023-
24
Amount
Planned to be
Spent in 2024-
25
Amount
Planned to be
Spent from
2025/26
onwards
017 Executive Director
(Kirsty Flanagan)
Financial Services Housing Benefits Private 321,524 35,640 285,884 285,884 0 Specific funding allocation for Housing Benefit including DHP. Funds will be used to continue to support
vulnerable people initially financially affected by the COVID-19 outbreak but now facing the cost of living
crisis to sustain their tenancies.  This earmarking will help offset potential overspends in the DHP/
Scottish Welfare Fund budget going forward.
321,524 0
018 Executive Director
(Kirsty Flanagan)
Financial Services Flexible Food Fund 194,156 107,620 86,536 86,536 0 Financial Insecurity funding from Scottish Government routed into the Argyll and Bute Flexible Food and
Fuel Fund (ABFFFF) is aimed at tackling financial insecurity for adults and families across Argyll and Bute. 
Working in partnership with the Community Food Forum, Bute Advice Centre and ALIenergy, households
with low incomes and no access to cash savings can apply for immediate financial support.  The Fund
helps support daily living expenses.   In the period from 10 January 2021 to 30 November 2022  client
gain in extra benefits income for families was £2.25 million with 1,550 families had been supported. The
project has been extended to 31 March 2025 with funding coming from the UK Shared Prosperity Fund
and this earmarking to support it. It is proposed that underspends from the Flexible Funding for
Supporting People at tier 4 COVID will be used to support this project over the next two years to cover a
funding gap of £50,000. The Scottish Government have provided this funding and have endorsed this
award winning project promoting it as part of the solution to end the need for foodbanks nationally.
194,156 0
019 Executive Director
(Kirsty Flanagan)
Financial Services Flexible Funding for Supporting
People while at Tier 4 COVID
76,357 4,666 71,691 71,691 0 Funding from SG to strengthen local authority responses to meet emerging needs and support people in
their communities struggling with the restrictions and guidance at all protection levels re COVID,
particularly those at risk through health and social inequalities. This support could cover the same types
of support.  In June 2021 the Council agreed to support 20 projects led by a range of Council officers,
officers from the HSCP and members of the third sector to deliver wide ranging support across our
region.  A report will be presented to members in due course.
76,357 0
020 Executive Director
(Kirsty Flanagan)
Financial Services Self Isolated Support Grant 5,316 0 5,316 0 5,316 Unspent admin funding for processing Self isolation Support Grants. 0 5,316
021 Non Departmental Non Departmental Recovery and Renewal Fund 1,547,000 0 1,547,000 1,547,000 0 As agreed at Council on 24 February 2022, Recovery and Renewal Fund £1.547m.  This is provision for
future recovery, regeneration and renewal, as well as any future pressures which may arise following the
Covid-19 pandemic through a dedicated Recovery and Renewal Fund.  Commitments have been made
against this fund as follows: Levelling up bid costs £0.150m, Scotland Loves Local overspend £0.037m and
Rothesay Pavilion £1.360m.
1,547,000 0
022 Non Departmental Non Departmental COVID Funding 418,337 0 418,337 0 418,337 Net balance on COVID cost centres at year end 2022/23 with proposals on use to be developed. 0 0 418,337
023 Non Departmental Non Departmental Capital pressure 257,000 0 257,000 0 257,000 Pressure identified on the 20/21 COSLA COVID costs spreadsheets - requires to be earmarked to be
drawn down when required against the Capital Plan.  To be incurred during 23-24 and drawn down in 24-
25.
0 257,000
024 Non Departmental Non Departmental Levelling up Fund bids per P&R
February 22
150,000 0 150,000 150,000 0 As agreed at Policy & Resources committee on 17 February 2022, an allocation of  up to £0.150m to
support Levelling Up Fund bids
150,000 0
5,512,073 592,271 0 0 4,919,802 3,347,411 1,572,391 3,939,682 1,154,054 418,337