ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES
COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
15 AUGUST 2024 
OCTOBER 2023 WEATHER EVENT – UPDATE 
1.0 INTRODUCTION
1.1 This is a follow up to the report presented to Council on 25 April 2024 in
respect of the October 2023 weather event.  A number of projects have
become increasingly more complex as the full extent of the damage,
underlying ground conditions and a number of other factors have emerged. 
This report provides a detailed update on the various flood sites, provides
information relating to the estimated overspends within the various projects
and also proposes a range of measures for Members to consider which could
be used to cover the estimated overspends.   
2.0 RECOMMENDATIONS
2.1 It is recommended that the Policy and Resources Committee:- 
a. Note the updates on the works undertaken and completed and those that
are ongoing.
b. Notes the revised forecast overspend of £3.853m that is currently
unfunded. 
c. Approves that options 1, 2 and 3 as detailed in the table at paragraph
3.10 are used to fund the overspend and defer consideration of the
remainder of the overspend once the Crown Estate Funding and Place
Based Investment funding is confirmed for 2024-25.   
3.0 DETAIL
3.1 Following a period of unprecedented wet weather where there was a level of
rainfall that left ground conditions very wet and in many cases saturated, over a
months’ worth of rain fell over a 36 hour period starting Friday 6 October 2023
and running into Saturday 7 October 2023.  This was the wettest 2-day period on
record for Scotland since 1891 (MET Office report). Argyll and Bute was the worst
affected area as shown in the chart below:

Page 2

3.2 The works carried out following the rain event were extensive with dozens of
locations requiring attention from simple cleansing of a small drain to significant
landslides and bridge replacements. 
3.3 A significant amount of work has been undertaken and completed thus far. 
Some examples include: 
• Various bridges – Tree and debris clearance to minimise flood risk at Bridgend
Bridge, Upper Stronafian Bridge and Victoria Bridge (Cowal) and Glenmallon
Bridge and Lindowan Burn Bridge (Helensburgh & Lomond).  Confined space
inspections and clearance was also completed to reduce the flood risk at
structures in Helensburgh. 
• B828 Glenmore Bridge (Cowal) – Repairs to damaged parapets and training
walls caused landslide.  Works undertaken by internal Structures Maintenance
Team 
• B839 Lochgoilhead Bridge (Cowal) – Repairs to the scoured and exposed
bridge abutments and central pier foundations, reinstatement of erosion
protection along the riverbank and riverbed. Working with Ross MacArthur
Contractors to ensure bridge remained open to public and local community was
not shut off, especially given the closure of the nearby B828 road due to
landslips. 
• B828 Glenmore Road (Cowal) – Rock anchor repairs to rebuild eroded and
missing road edges and verges, damaged road culverts and road restrain

Page 3

systems caused by landslip and rockfall. Working with Geo-Rope to completion,
the road was reopened following separate remedial works by Forestry and Land
Scotland to remove further risk of rockfall to users. 
• Ri Cruin Bridge – bridge abutment repair, scour protection works and invert
pitching repairs carried out in conjunction with DA MacDonald and the Council’s
Bridge Squad team. 
• A815 Landslip clearance to reopen the road in conjunction with the reopening
of the A83 as a vital route to and from Cowal.  This site is immediately adjacent
to the “Dunoon Road End Straights” section of the A83 beside the Rest and Be
Thankful and ongoing monitoring of this site continues. 
3.4 The following table summarises locations where works are still outstanding. 
The most significant area of work relates to the A816, Kintraw, Ardfern landslide
and further information on this is also provided within Appendix A.  Further
information relating to the financial estimates is included within the table at
paragraph 3.6. 
LOCATION ONGOING WORKS SCHEDULED
COMPLETION
A816-110
Cuilfail Hotel
Bridge,
Kilmelford  
Following severe damage, this bridge was
immediately closed to traffic, demolished, a
new structure installed and reopened to traffic
in under two weeks. 
Hydrological, Bathymetric & Ecological
Studies are now nearing completion alongside
consultations with SEPA. 
Ongoing designs of rock armour, bridge
parapet, bridge training walls and narrow
footway on the upstream side of the bridge. 
Contract award for the above described
Phase 2 works was made after the Council’s
Bellwin claim in February 2024 and are higher
than the figure which was included in the
claim.    
Site works due to re-
start mid August
2024 aiming to be
complete before
winter. 
B844-010
Kilninver
Bridge 
Phase 1 emergency works to protect the
bridge and the B844 road completed
November 2023. 
Previously proposed Phase 2 designs and
works (scour protection) now being
incorporated into Local Bridge Maintenance
Fund scheme.  Designs being carried out in-
house with a view to works being tendered
mid 2025.  Any risks incurred from the delays
to the Phase 2 works are being monitored and
controlled to ensure the road network remains
safe.  
Late Summer 2026

Page 4

C30 Ford to
Malevich  
Works completed and road fully reopened.  
As the emergency works progressed, rock
was found to be much deeper than
anticipated, costs to secure engineering
solution to rock were therefore higher than
previous estimates.    
July 2024 
B836-060
Balliemore
Bridge, Glen
Lean 
Following severe damage to and partial
collapse of existing bridge, a temporary bridge
and associated road alignment was installed
in under 2 months, with the alternative route
opening on 1st December 2023. 
Next steps are construction of a new,
permanent bridge and removal of the
temporary structure. 
The Council’s attempts to seek engagement
from OpenReach to remove their apparatus
from within the bridge to allow the bridge to be
demolished are ongoing.  At this stage it
appears that OpenReach will charge the
Council circa £230k for this and their works
will take around 2 months.  This will also
require an extended hire period for the
temporary bridge.    
Late 2024 / Early
2025 
A816 Bealach
Mor, Kintraw,
Ardfern catch
pits at base of
unstable
slope  
Licence To Occupy discussions are still
ongoing between the Council and the
Landowner. 
Works along the toe of the slope have been
reviewed and at this time further landslip and
rockfall events are within a predictable
pattern, however, further significant landslides
could occur at this location.
We are now studying the option of installing
rockfall protection barriers within the road
corridor, which would no longer require catch
pits and fencing as previously proposed. 
Further information (including budget costs) is
described in more detail in Appendix A.  
See Appendix A for
timescales  
A816 Bealach
Mor, Kintraw,
Ardfern convoy
system ‘v’ fixed
traffic lights 
Road Safety Audit has been progressed and
identified some amendments to the road
layout, these have been incorporated into the
proposed works detailed later in this report.  
Hard wired traffic lights being designed for
installation in due course. 
Further information (including budget costs) is
described in more detail in Appendix A.  
End of September
2024 
A816 Bealach
Mor, Kintraw,
Ardfern –
permanent
diversion onto
Archaeologist has carried out further
investigative works and have given positive
feedback. The next stage is further design
work including ground investigation,
environmental impact assessment and
3 – 5 years

Page 5

a widened
alignment of
the emergency
route   
additional archaeological matters which will
allow for permissions to be sought and a final
design progressed for a permanent solution. 
A new, separate contract is being progressed
for this element of permanent works as a
scope for these will be able to be developed
and prepared by the Council in advance. 
Cost options are being worked up, further
information will be included in the next
update.   
Update to the Financial Estimates 
3.5 The report to Council in April advised that the estimated costs related to the
weather incident amounted to £10.543m.  A claim amounting to £5.494m of
revenue costs was submitted to Scottish Government at the end of the 4
month period and after deducting our threshold of £0.529m this results in a
net claim of £4.965m – £4.353m of this has been received with the final
£0.612m outstanding from Scottish Government whilst final checks are being
made.  The Council secured a further £2.3m of funding as part of the budget
negotiations and the remainder was funded by either Council reserves or
borrowing as part of the budget agreed in February 2024.   
3.6 A number of projects have become increasingly more complex as the full
extent of the damage, underlying ground conditions and a number of other
factors have emerged and as a result costs have increased to those
estimated in the report to Council in April 2024.   The table below details the
revised estimates and the increase in cost that is not currently budgeted for
along with reasons for the increase. 
Scheme  Feb 2024 
Estimate 
£000 
Movement
Between
Interim
and Final
Bellwin
Claim
£000
Total
Funded
Position
£000
July 2024
Updated
Estimate
£000
Increase
from
Funded
Position
£000
Reasons for Increase
B836-060
Balliemore
Bridge (Glen
Lean) –
Revenue 
752  (57) 695 1,150 455  Due to the nature of the extreme
weather event damage to
Balliemore Bridge, and following
consultation with other Scottish
Councils, it was anticipated that
notifying OpenReach that the bridge
was damaged beyond repair that
they would divert their apparatus at
their own cost to protect their
infrastructure.  OpenReach have not
been in agreement with this and
have insisted that the Council pay to
divert and reinstate the apparatus in
accordance with regular NRSWA

Page 6

Legislation processes.  Current legal
advice is to progress this route. 
Feb 24 estimate did not include
diversion of OpenReach apparatus
(£230k) and associated costs for
delays to phase 2 works due to
OpenReach diversion including
extended hire of temporary bridge
(at a higher weekly rate, circa
£100k), traffic management,
inspections and management (circa
£125k) until new, permanent bridge
is constructed late 24 / early 25. 
B836-060
Balliemore
Bridge (Glen
Lean) –
Capital 
1,448  0 1,448 1,448 0 n/a
A816
Bealach Mor
(Ardfern /
Kintraw)
Landslip –
Revenue 
2,809 94  2,903 5,155 2,252 Previously proposed Catchpit &
Bund, estimated at a cost of
£1.35m, was not included in Bellwin
Claim in Feb 2024. 
Land access delays have incurred
additional costs for traffic
management, project management,
maintenance & ongoing stabilisation
of current works, standing time. 
Roads Safety Audit has now been
concluded and recommends
additional safety measures which
will allow the removal of the traffic
management convoy arrangement
to reduce long term costs. 
Installation of these measures along
with the traffic light system will incur
additional costs in the short term. 
A816
Bealach Mor
(Ardfern /
Kintraw)
Landslip –
Capital
scheme for
long term,
permanent
realignment 
1,100 0  1,100 1,100 0 n/a
C030
Kilmaha
Landslip -
Revenue 
315  83  398 864 466 Rock head found much deeper than
anticipated - requiring redesigns for
longer and additional anchors,
support beams and higher spec
mesh. 
Weather and material delivery
delays.

Page 7

Higher tonnage of rock armour from
earlier scheme on site than reported
/ estimated. 
Vehicle Barriers now included due
to the significant difference in level
exposed by the new arrangement. 
U014
Scammadale
Landslip -
Revenue 
454  (83)  371 838 467 Rock head found much deeper than
anticipated - requiring redesigns for
longer and additional anchors,
support beams and higher spec
mesh. 
Weather and material delivery
delays. 
Assistance to residents and
businesses as this lifeline cul-de-sac
road could not be fully closed. 
Vehicle Barriers now included due
to the significant difference in level
exposed by the new arrangement. 
A816-110
Cuilfail Hotel
Bridge,
Kilmelford –
Revenue
Emergency
Response 
200  0  200 200 0 n/a
A816-110
Cuilfail Hotel
Bridge,
Kilmelford –
Permanent
Capital 
1,800 0 1,800 2,086 286 Contract cost for Phase 2 works
confirmed after Bellwin claim.  This
also now include rock armour to
protect upstream and downstream
embankment protection. 
These capital works were not
eligible for Bellwin scheme. 
Other
Revenue
Schemes 
1,665 102 1,767  1,694 (73)  This line captures the following: 
Bridge Debris Clearances 
Lochgoilhead Bridge Repairs 
Roads Workers time and materials
for all repairs and flood works they
carried out 
Costs came in lower thanks to
emergency response works at Ri
Cruin Bridge being suffice and
removing the need for further works
during the summer as was initially
forecast.
Revenue
Totals 
6,195 139  6,334  9,901  3,567

Page 8

Capital
Totals 
4,348  0  4,348 4,634 286 
Overall
Weather
Event
Totals 
10,543 139 10,682 14,535  3,853 
Next Steps 
3.7 Our current focus is to complete the various works still outstanding and to
continue to monitor slopes where debris flows may affect the road network.
Current status, options and associated cost estimates (including
substantiation of costs which have gone over the original estimates made at
the time of the Council’s Bellwin claim) for the ongoing schemes.   
3.8 Climate change is a significant challenge to the Council for a number of
reasons but not least it is a challenge for the road and transport infrastructure.
This report highlights the challenges from the October weather incident and
the report in April highlighted some of the challenges faced over the last
decade or so.  The road and wider transport system provides the economic
backbone for our communities. We need to have infrastructure which is fit for
purpose and sufficiently resilient to withstand the increasing weather
challenges we are experiencing which are linked closely to climate change.
The building of a bypass on the A816, strengthening bridges, and modifying
roadside ditches are all adaptations being progressed to better accommodate
some of the climate changes we are seeing. However, more will be needed
and whilst the works mentioned above will increase our infrastructure
resilience to future weather events, the network overall is fragile and unable to
cope with significant weather events.   
3.9 It will be necessary to see more infrastructure investment put in place to
enable climate change adaptations to be made. The level of investment will
be significant, and the Council will need to consider how its funding can be
assembled and what lobbying can be progressed with Scottish and UK
Governments. 
Options to be considered to fund overspend 
3.10 The revised estimates give rise to a £3.853m overspend that will require to be
funded.  The Council’s current unallocated General Fund Balance (not taking
into account other overspends that are reported in the budget monitoring
pack) is £2.259m.  This overspend would therefore mean the Council would
have to use the General Fund contingency and a recovery plan would require
to be put in place to bring the General Fund out of contingency.  A number of
options have been outlined below that could fund the forecast overspend.   
No. Options Amount
£000
Comment/Implications
1 Pause previously
approved Roads
2,029 This will impact on the
condition of the road network

Page 9

Reconstruction Schemes
(see detail in Appendix B)
and with much reduced
capital block for next year
there is no guarantee that the
previously programmed
schemes will be able to be
progressed.  Unclear as to the
impact of Roads Condition
Index (RCI) but likely not to
be positive.  
2 Use £50k revenue within
loans fund street lighting
improvements for
prudential borrowing, this
could raise £750k of
funding.
780 Will reduce the number of
column replacements and
lighting cable repairs
impacting on the resilience of
the lighting network.
3 Utilise some of the
unallocated capital
funding for street lighting
cable and column
replacements
100 Will reduce the number of
column replacements and
lighting cable repairs
impacting on the resilience of
the lighting network. 
Sub-Total 2,909 
Balance from one of the
following:  
4 Use Crown Estate and
Place Based Investment
Funding to fund the
remaining balance
944 
OR
This would limit the
opportunities to use this
funding for other projects
across the Council area. 
Funding has not been
confirmed for either schemes
for 2024-25 yet. 
5 Use Unallocated General
Fund Reserves
944 
OR
This would reduce the level of
unallocated General Fund
reserves significantly and
based on the other
overspends currently being
reported (see separate
budget pack report) this would
reduce the unallocated
General Fund to £0.214m.  
6 Reallocate capital funding
set aside for the waste
transfer station and use
prudential borrowing to
fund waste transfer
station (this would have a
revenue implication
944 This will cost £0.061m in
recurring revenue expenditure
that will need to be added to
the loans fund. 
3.11 It is recommended that the Policy and Resources Committee agree to Options
1-3 in the table above that will fund £2.909m of the overspend.  The remainder
of the overspend could be considered later in the financial year once the Crown

Page 10

Estate Funding and Place Based Investment funding is confirmed for 2024-25.   
4.0 CONCLUSION
4.1 This report summarises and provides update on the works that have been
undertaken and completed and those that are ongoing in relation to the extreme
weather event which occurred on the weekend of 7 October 2023 and which
was the wettest 2-day period on record for Scotland since 1891 in which Argyll
and Bute was the worst affected area.   
4.2 The report also provides an update on the cost estimates and these give rise to
£3.853m overspend that will require to be funded.  A number of options to fund
the overspend have been outlined within the report.     
5.0 IMPLICATIONS 
5.1 Policy – policies in place for climate change, coast protection etc where
applicable these policies are being worked to.
5.2 Financial – new costs pressures have no identified funds to respond to the
infrastructure damage. A Bellwin claim was progressed for eligible costs up to
February 2024.  Works not eligible for Bellwin will need to be funded, with
previous estimates receiving funding following an earlier report and additional
funding requirements now identified within this report.   
5.3  Legal – various land agreements necessary for individual locations.   
5.4  HR – none known.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known. 
5.5.2   Socio-economic Duty – none known. 
5.5.3  Islands – none known.
5.6 Climate Change – the impact of the storm is very closely linked to climate
change and the October event has highlighted to need for further adaptation
to be made to infrastructure to increase our resilience to future weather
events. The level of investment to improve resilience is expected to be
significant.  
5.7 Risk – significant risk of similar future events impacting our infrastructure.  
5.8  Customer Service – none known.  
5.9 Rights of the Child (UNCRC) – investment to improve our road network will
contribute to a safer environment for young people to thrive in.

Page 11

APPENDICES: 
Appendix A – A816 Bealach Mor (Ardfern/Kintraw) Landslip
Appendix B – Roads Reconstruction Schemes proposed to be paused 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure Services 
Councillor John Armour, Policy Lead for Roads, Transport and Amenity
Services 
5 August 2024 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service
Jim.Smith@argyll-bute.gov.uk