ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
15 AUGUST 2024
RURAL GROWTH DEAL – UPDATE AND DETAILED DESIGN COSTS 
1.0 EXECUTIVE SUMMARY
1.1 This report provides an update on the Rural Growth Deal (RGD). The RGD will
deliver £50m of investment from the Scottish and UK Governments for projects
that are a driver for inclusive and transformational economic growth across the
region.  The Council and key delivery partners will also provide a minimum of
£20m of match funding throughout the 10-year Deal programme.  
1.2 The Council, UK and Scottish Governments agreed the ‘Heads of Terms’ for the
RGD on the 11th February 2021. The Heads of Terms Agreement sets out the
general areas for investment and the Full Deal Agreement builds upon this in
more detail.  
1.3 Signing of the Full Deal Agreement was scheduled for 7th June 2024 however
required to be postponed due to calling of the General Election. The RGD
Programme Management Office (PMO) are liaising with Civil Servants at both
the UK and Scottish Government level to agree a revised date for Full Deal
Signing following the General Election. 
1.4 The RGD PMO have procured the services of the consultancy Stantec to assist
with the development of business cases for the RGD programme.  All Projects
have now had at least one iteration of an Outline Business Case (OBC) or Full
Business Case (FBC) submitted to Government. An update on the position of
RGD business cases is included in Table 1 of this report.
1.5 To date, costs associated with business case and project development works
have largely been funded from the Council’s Inward Investment Fund. Match
funding has also been secured from a number of key partners such as HIE and
Scottish Enterprise.  The Policy and Resources Committee have previously
approved the release of 4 tranches of funding totalling £600k from the Inward
Investment Fund with authority delegated to the Internal Programme Board to
authorise spend to support Rural Growth Deal project development work.  At the
time of writing this report, total approved spend on RGD project development
work stands at £569,358.
1.6 Where possible, the RGD PMO will seek to recoup capital costs from RGD
funding allocations however, it will not be possible to submit any claims for
funding until the Full Deal Agreement has been signed and Full Business Cases
for projects are endorsed by Central Government.  Costs associated with the

Page 2

development of project Full Business Cases will require to be met by the Council
and strategic partners at risk in advance of funding being approved by Central
Government. 
1.7 The Policy and Resources Committee are therefore asked to approve a further
£150k of funding from the Inward Investment Fund to support the development
of RGD Full Business Cases and any associated pre-construction works e.g.
planning, detailed design and consultancy support.
1.8 The RGD PMO will continue to seek external match funding to support project
development costs and meet funding gaps.  To date, the Council and key
funding partners have secured over £20m of match funding that will directly
support projects within the RGD programme.  Given the significant funding
secured to date, throughout the lifetime of the programme it is considered likely
that RGD partners will exceed the £20m match funding commitment set out in
the Heads of Terms Agreement.
1.9 In advance of the completion of the Full Business Case (FBC), there remains a
significant amount of project development work to be undertaken, across the
majority of RGD Projects. This includes detailed design, procurement, site
investigation works and statutory consents. 
1.10 The development of detailed design for projects is a key stage, however it
comes at considerable expense and will bring a degree of risk to the Council
and RGD Partners. The appointment of a Detailed Design team will include an
Architect, Quantity Surveyor, Engineers and Project Manager support. As a
general estimate, up to 10% of project capital budgets should be set aside for
Detailed Design cost.
1.11 Kintyre Seasports will be the first project to receive OBC approval and this
project is programmed to begin construction in Autumn 2025.  There is therefore
an urgent need to progress detailed design work.  Tenders for this work have
identified costs of circa £238k for the design, consultancy and engineering
support necessary to see this project through to practical completion.  These are
capital costs which will be re-claimed from RGD funds following endorsement of
the Full Business Case.  It should however be noted, that all costs incurred in
advance of FBC endorsement are at risk to the Council.  
RECOMMENDATIONS: 
• Members should note that a revised date for Full Deal Signing will be
arranged once a new UK Government is formed.
• Approval is sought from the Policy and Resources Committee for a
further drawdown of funding from the Inward Investment Fund (up to
£150k).  Similar to previous arrangements, funds will only be drawn down
subject to the Chief Executive and two Executive Directors of the Council
being satisfied that the monies are for the purpose of delivering the Rural
Growth Deal. Any further funding required in excess of the approved
value will require further approval from the Policy and Resources
Committee.

Page 3

• Members are asked to approve spend of up to £250k to support the next
stage of project development for Kintyre Seasports, including Detailed
Design works.

Page 4

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
15 AUGUST 2024
RURAL GROWTH DEAL – UPDATE AND DETAILED DESIGN COSTS 
2.0 INTRODUCTION
2.1 This report provides an update on the Rural Growth Deal (RGD). The RGD will
deliver £50m of investment from the Scottish and UK Governments for projects
that are a driver for inclusive and transformational economic growth across the
region.  The Council and key delivery partners will also provide a minimum of
£20m of match funding throughout the 10-year Deal programme.  
2.2 The Council, UK and Scottish Governments agreed the ‘Heads of Terms’ for
the RGD on the 11th February 2021. The Heads of Terms Agreement sets out
the general areas for investment and the Full Deal Agreement builds upon this
in more detail.  
2.3 Signing of the Full Deal Agreement was scheduled for 7th June 2024 however
required to be postponed due to the UK General Election on the 4th July. The
RGD PMO are liaising with Civil Servants at both the UK and Scottish
Government level to agree a revised date for Full Deal Signing following the
General Election.
2.4 The RGD PMO have procured the services of the consultancy Stantec to
assist with the development of business cases for the RGD programme.  All
Projects now have at least one iteration of an OBC or FBC submitted to
Central Government. An update on the position of RGD business cases is
included in Table 1 of this report.  
2.5 To date, costs associated with business case and project development works
have largely been funded from the Council’s Inward Investment Fund. Match
funding has also been secured from a number of key partners such as HIE
and Scottish Enterprise.  The Policy and Resources Committee have
previously approved the release of 4 tranches of funding totalling £600k from
the Inward Investment Fund with authority delegated to the Internal
Programme Board to authorise spend to support Rural Growth Deal project
development work.  At the time of writing this report, total approved spend on
RGD project development work stands at £569,358.
2.6 Where possible, the RGD PMO will seek to recoup capital costs from RGD
funding allocations however, it will not be possible to submit any claims for
funding until the Full Deal Agreement has been signed and Full Business
Cases for projects are endorsed by Central Government.  All costs incurred in

Page 5

advance of FBC endorsement are at the risk of the Council and project
stakeholders.  It should be noted that these costs are necessary in order to
progress projects through to FBC endorsement. 
2.8 The Policy and Resources Committee are therefore asked to approve a further
£150k of funding from the Inward Investment Fund to support the
development of RGD Full Business Cases and any associated pre-
construction works e.g. planning, detailed design and consultancy support.
2.9 The RGD PMO will continue to seek external match funding to support project
development costs and meet funding gaps.  To date, the Council and key
funding partners have secured over £20m of match funding that will directly
support projects within the RGD programme.  Given the significant funding
secured to date, throughout the lifetime of the programme it is considered
likely that RGD partners will exceed the £20m match funding commitment set
out in the Heads of Terms Agreement.
2.10 Kintyre Seasports will be the first project to receive OBC approval and this
project is programmed to begin construction in Autumn 2025.  There is
therefore an urgent need to progress the detailed design work necessary for
the project FBC.  Tenders for this work have identified costs of circa £238k for
the design, consultancy and engineering support necessary to see this project
through to practical completion.  These are capital costs which will be re-
claimed from RGD funds following endorsement of the Full Business Case.  It
should however be noted, that all costs incurred in advance of FBC
endorsement are at risk to the Council.   
3.0 RECOMMENDATIONS
• Members should note that a revised date for Full Deal Signing will be
arranged once a new UK Government is formed.
• Approval is sought from the Policy and Resources Committee for a
further drawdown of funding from the Inward Investment Fund (up to
£150k).  Similar to previous arrangements, funds will only be drawn down
subject to the Chief Executive and two Executive Directors of the Council
being satisfied that the monies are for the purpose of delivering the Rural
Growth Deal. Any further funding required in excess of the approved
value will require further approval from the Policy and Resources
Committee. 
• Members are asked to approve spend of up to £250k to support the next
stage of project development for Kintyre Seasports, including Detailed
Design works.

Page 6

4.0 DETAIL
4.1 Business Case Progress Update
4.1.1 The Council agreed the ‘Heads of Terms’ for the RGD on the 11th February
2021. The next key milestone is the signing of the Full Deal Agreement. This
was arranged for 7th June 2024, however required to be postponed due to the
announcement of a General Election. A revised date for Full Deal Signing will be
agreed once the new UK Government is formed and it is hoped that this
milestone can be reached by September 2024. 
4.1.2 Upon signing the Full Deal Agreement, the Council will enter year 1 of a 10-year
programme of delivery for the RGD.  It is currently anticipated that Year 1 will be
2024/25, with the Deal reaching completion in 2034/35. 
4.1.3 The RGD PMO have been working with Stantec and key delivery partners to
progress Business Cases for RGD projects.  All projects now have at least 1
iteration of an OBC or FBC submitted to UK and Scottish Government. The
RGD PMO and Project Leads have been working to address feedback received
and a number of OBCs are now nearing approval.  An update on Business Case
Progress for each RGD Project is provided in Table 1 below:-
Table 1 Business Case Tracker
Project Stage Next Milestone
Rothesay
Pavilion 
2nd iteration of FBC submitted
to Government on 8th May
2024. 
A number of meetings have
been held between
Government and the Council
to discuss conditions that
would allow endorsement of
the FBC to allow the next
stage of contracts to be
awarded. 
Conditional
Endorsement of
FBC 
Kintyre Seasports The OBC was approved by
Government on 4th July 2024.  
Detailed Design
Low Carbon
Economy - Islay
Government advised that
they were not content to
proceed with the project that
was in the first Outline
Business Case. Therefore
the project has gone back to
initial options appraisal stage.
Engagement with
stakeholders is ongoing to
redevelop project options.  
Completion of
options appraisal
and identification of
new preferred
option.

Page 7

Rural Skills
Accelerator
Programme OBC
A second iteration of the
OBC was submitted to
Government on 23rd May
2024.
Feedback to be
provided by
Government.  
Housing – Isle of
Mull
Second iteration of OBC
submitted on 2nd May 2024. 
Feedback/approval
of OBC
Housing – Isle of
Islay
Feedback received on the
first iteration OBC on 29th
May 2024. Project Leads are
considering feedback in
advance of re-engaging with
Stantec.    
Second iteration
OBC to be drafted
by Stantec.  
Clyde
Engineering &
Innovation Centre
Feedback on second iteration
OBC was received on 24th
April 2024. PMO and Stantec
currently working to address
outstanding comments. 
Third iteration to be
submitted to
Government. 
West Coast UAV 3rd iteration OBC submitted
to Government on 20th May
2024.   
Feedback/approval
of OBC
Marine
Aquaculture
Programme –
Marine Industry
Training Centre
Second iteration OBC
submitted to Government on
26th April 2024. 
Feedback to be
provided by
Government 
Marine
Aquaculture
Programme –
SAMS
International
Seaweed &
Shellfish Industry
R&D Centre
Feedback received on 2nd
April 2024 on second
iteration OBC. SAMS/HIE
currently reviewing feedback
and redrafting OBC.
Third iteration OBC
to be submitted to
Government
Marine
Aquaculture
Programme –
Marine
Environmental
Research
Laboratory
Second iteration OBC
submitted to Government in
June 2024.  
Feedback to be
provided by
Government.

Page 8

4.2 Full Business Case Costs
4.2.1 To date, costs associated with business case and project development works
have largely been funded from the Council’s Inward Investment Fund. Match
funding has also been secured from a number of key partners such as HIE and
Scottish Enterprise.  The Policy and Resources Committee have previously
approved the release of 4 tranches of funding totalling £600k from the Inward
Investment Fund with authority delegated to the Internal Programme Board to
authorise spend to support Rural Growth Deal project development work.  At the
time of writing this report, total approved spend on RGD project development
work stands at £569,358. 
4.2.2 There is an Earmarked Reserve of £540,897 for the Inward Investment Fund,
with £307,232 of this previously committed. Therefore there is a remaining
balance of £233,665 available to support the development of the Rural Growth
Deal.
4.2.3  A number of the Outline Business Cases are nearing approval and it is not
expected that further funds will be required to support Outline Business Cases,
with the exception of the Islay Low Carbon Economy project which is still at
options appraisal stage. The RGD PMO have been scoping requirements for
FBCs, and it is anticipated that the costs associated with development of the
FBC for each project will be in the region of £20k-£30k. At this time, a total of 14
FBCs will be required across the programme. Some of these will be funded by
RGD Partners such as HIE. 
4.2.4 The RGD PMO have commissioned Stantec to undertake the FBCs for the
Kintyre Seasports and Tobermory Housing projects, given these projects will be
delivered in the early phases of the RGD Programme. The FBC for Rothesay
Pavilion has already been completed and the Council is in the process of
agreeing a conditional endorsement of £9m of RGD funding for this project.
4.2.5 The Policy and Resources Committee are asked to approve a further £150k of
funding from the Inward Investment Fund to support the development of RGD
FBC’s and associated pre-construction works e.g. planning, detailed design and
consultancy support.  Aligned with previous arrangements, funds will only be
drawn down subject to the approval of the Council’s Chief Executive and two
Executive Directors. Any further drawdown from the Inward Investment will
require approval of the Policy and Resources Committee.
5.0 Detailed Design Costs
5.1 A significant amount of project development work is necessary in order to
complete Treasury Five Case compliant FBC’s.  This includes detailed design,
construction tenders and statutory consents.  In order to develop FBCs the
following milestones should be completed:
• Design to RIBA Stage 4 (Technical Design);
• All consents should be approved (including Planning, Building Warrant
etc);

Page 9

• Procurement – costs in the FBC should be based on a tendering
exercise;
• Match funding – must be identified and approved by funders;
• Any Legal agreements between the Council and Partners should be
finalised;
• Carbon Impact Assessments finalised; 
• Equalities Impact Assessments finalised; 
• Programme of works agreed. 
5.2 Pre-construction activities such as Detailed Design incur considerable
expense for the Council and RGD Partners. The appointment of a Detailed
Design team will include an Architect, Quantity Surveyor, Engineers and
Project Manager support. As a general estimate, up to 10% of project capital
budgets should allocated for Detailed Design costs. 
5.3 Detailed design has to be undertaken to inform the project FBC therefore
spend will be incurred at risk to the Council and project partners.  The figure
below details the approvals process for RGD projects in advance of funding
drawdown:- 
5.4 The key risk the to the Council and project partners is construction tenders
being unaffordable and projects having funding gaps requiring additional
match funding or a requirement to value engineer or reallocate RGD funds.  In
this scenario the Council and/or RGD Partners could have incurred significant
abortive costs associated with project development work.   
5.5 Funding of project development costs is a risk that is common across all City
Region and Growth Deals in the UK.  Appendix 1 includes projected
timescales for detailed design development and FBC submission for the wider
RGD programme. It should be noted that these are current projected
timescales and that it is likely that they may change depending on project
development progress. Projects are currently profiled to ensure compliance
with a funding drawdown of circa £5m per annum. 
5.8 Where there is a requirement to fund detailed design and project development
costs upfront, a report on each project will be brought to the Policy and
Resources Committee to allow Members to consider the request and
associated costs and risks. 
6.0 Kintyre Seasports   
6.1 Kintyre Seasports received OBC approval on 4th July 2024. This project seeks to
redevelop the existing Campbeltown Sailing Club facility into a modern
watersports facility. The total budget available for capital works through the
Outline Business Case
approved by
Government
1. Detailed
Design/Consents/Impact
Assessments Undertaken
2. Construction Tender 
Full Business Case
submitted to
Government for
endorsement
FBC endorsed by
Government
1. Contracts for
construction awarded
2. Claims made to
Government for project
costs quarterly

Page 10

Rural Growth Deal is £2m. The RGD PMO and Kintyre Seasports continue to
seek other opportunities for match funding. 
6.2 This project is programmed to begin construction in Autumn 2025, therefore
there is a urgent need to progress the detailed design work necessary for the
FBC.  This project has already scoped detailed design requirements and
undertaken a tender however was subsequently abandoned as the tendered
costs returned were in excess of the threshold for an unregulated procurement.
There was only one tender return with a value of circa £238k. The scope of
works included all detailed design and support through to handover of the new
facility.
6.3 Procurement activity has been undertaken on an “on behalf” of basis with Argyll
and Bute Council undertaking procurement activity on behalf of Kintyre
Seasports. It is proposed that Argyll and Bute Council would pay all invoices
associated with works, given that Kintyre Seasports would be unable to cash
flow the project themselves.
6.4 The RGD PMO and KSS are liaising with colleagues from the Council’s
Procurement Team to agree next steps.  The PMO are also investigating
opportunities associated with a design and build contract or a reduced scope of
works to try and limit financial risk to the Council and KSS.
6.5 Members are asked to approve spend of up to £250k to support the next stage
of project development for Kintyre Seasports, including Detailed Design works. It
is expected that the cost of this will be retrospectively claimed from the Rural
Growth Deal following endorsement of the project FBC by Central Government. 
With the exception of Rothesay Pavilion, this is the first project within the RGD
programme to reach detailed design stage. 
7.0 CONCLUSION
7.1 The next key milestone in the RGD process is the signing of the Full Deal
Agreement. It is anticipated that a revised date for Full Deal Signing will be
agreed with Central Government following the UK General Election on the 4th
July.   
7.2 The RGD PMO continue to work with key stakeholders and Stantec to develop
RGD projects and progress associated project business cases. To date, all
projects within the RGD programme have submitted at least one iteration of their
OBC or FBC to Central Government and have received feedback.  It should be
noted that this process can take several months.   
7.3 The Policy and Resources Committee have previously approved the release of
4 tranches of funding totalling £600k from the Inward Investment Fund with
authority delegated to the Internal Programme Board to authorise spend to
support Rural Growth Deal business case and project development work.  At the
time of writing this report, total approved spend on RGD development work
stands at £569,358.

Page 11

7.4 Following signing of the Full Deal Agreement, it will be necessary to draft FBC’s
for all projects.  Drawdown of RGD funding is subject to endorsement of FBC’s
by Central Government.  This will require further project development work such
as detailed design, planning and consultancy support which is necessary in
order to develop Treasury compliant FBC’s.
7.5 The Policy and Resources Committee are asked to approve a further £150,000
draw down from the Inward Investment Fund to support the development of Full
Business Cases and associated project work.    
7.6 The OBC for Kintyre Seasports will shortly be approved and the Policy and
Resources Committee are asked to approve spend of up to £250k on this
project to support the next stages of development, including detailed design
works. It is expected that these costs will be retrospectively claimed from the
RGD funds following endorsement of the FBC by Central Government.
7.7 Members are asked to note that all spend in advance of FBC endorsement is at
risk to the Council and key project partners however, this is necessary in order
to achieve endorsement of RGD projects by Central Government. 
8.0 IMPLICATIONS
8.1 Policy – The RGD is consistent with the Council’s Economic Strategy.
8.2 Financial –  RGD Projects require a level of upfront spend at risk to allow project
development to progress. Support will be required from Financial
Services. There are limited remaining funds in the Inward Investment
Fund to support Rural Growth Deal Development costs, however capital
costs can be claimed back from RGD funds following endorsement of
FBCs and at the discretion of the Section 95 Officer. 
8.3  Legal – The RGD may require input from Legal Services as part of the Full Deal
Signing.
8.4  HR – None at present.
8.5  Fairer Scotland Duty: Required as part of OBC process.
8.5.1   Equalities - protected characteristics - Equality Impact
Assessments are required for all RGD projects.
8.5.2   Socio-economic Duty - The Rural Growth Deal will follow
Scottish Government guidance on Inclusive growth including
measures to address socio-economic disadvantage
8.5.3   Islands – Islands impact assessments required as part of OBC
process where necessary.
8.6  Climate Change – Carbon Management Plans are required for all RGD
business cases.

Page 12

8.7 Risk – Spend incurred in advance of approval of FBCs will be at risk to lead
partner.
8.8 Customer Service – None at present. 
8.9 The Rights of the Child (UNCRC) – None at present. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Economic Growth 
Councillor Jim Lynch, Leader of Argyll and Bute Council 
June 2024                                      
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Jonathan Welch, Transformational Projects and Regeneration Manager
Jonathan.Welch@argyll-bute.gov.uk   
APPENDICES 
Appendix 1 – Rural Growth Deal Projected Programme (as at July 2024)

Page 13

Appendix 1: Rural Growth Deal Projected Programme (as at July 2024)
The following table shows the current projected delivery timeframe for RGD Projects.
It should be noted that there may be changes to the Programme as projects
progress through their development stages.
Project  OBC
Approval
Pre-
Construction
Phase*
FBC
Endorsement 
Projected
Construction
Start 
Rothesay Pavilion N/A Stage 1
works
ongoing
Conditional
Endorseme
nt expected
July 2024
Stage 2 & 3
due to start
September/
October
2024 
Kintyre Seasports  Received
July 2024
July 2024-
July 2025
Expected
September
2025
October
2025
Creating a low carbon
economy – Islay 
Project has
returned to
options
appraisal.
TBC TBC TBC
RSAP - South STEM
Hub (Dunoon) 
Rural Skills
Accelerator
Programme
Level OBC
is expected
to be
approved by
October
2024 
2024/25-
2025/26
Expected
2026/27
2026/27
RSAP - North STEM
Hub (Oban)
2025/26-
2026/27
Expected
2026/27
2026/27
RSAP - UHI Argyll
College Built
Environment (Dunoon)
2027/28-
2028/29
Expected
2028/29
2028/29
RSAP - Business Skills N/A Expected
December
2024
Delivery of
Business
Skills
Programme
to begin in
2025/26
Housing - Isle of Mull Expected
August
2024
2024-2025 Expected
December
2024
2025/26
Housing - Isle of Islay  Expected by
March 2025
2027/28 Expected
2027/28
2028/29
Clyde Engineering and
Innovation Cluster
Expected
August
2024
2027/28-
2028/29
Expected
2029/30
2029/30
West Coast Aviation,
UAV, Robotics and
Compliance Hub
Expected
August
2024
2030/31 Expected
2031/32
2032/33
MAP - Machrihanish
Innovation Campus
Expected
September
2024
2025/26 Expected
2025/26
2025/26
MAP - SAMS
International Seaweed
Expected
September
2024
2026/27-
2027/28
Expected
2027/28
2027/28

Page 14

and Shellfish Industry
R&D Centre
MAP - Marine Industry
Training Centre
Expected
October
2024
2026/27-
2027/28
Expected
2027/28
2027/28