Democracy Spraffa

Update: Argyll and Bute UK Shared Prosperity Fund Investment Plan Interventions

Argyll and Bute Council · 15 August 2024
Back to Policy and Resources Committee — 15 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND 
ECONOMIC GROWTH  
15th AUGUST 2024 
UPDATE: ARGYLL AND BUTE UK SHARED PROSPERITY FUND
INVESTMENT PLAN INTERVENTIONS   
1.0 HEADLINES 
1.1 The purpose of this paper is to provide an update for members of the committee on the
progress of the Argyll and Bute UK Shared Prosperity Fund (UKSPF) Investment Plan
project / programme interventions that are being delivered across Argyll and Bute. 
1.2 As the UKSPF is a successor to the previous EU structural funds. The overarching aim
of this funding is to build pride in place and increase life chances across the UK. 
1.3 As summarised in Table A1, Appendix A the project / programme activities outlined in
the Argyll and Bute UKSPF Investment Plan are all aligned to three key investment
priorities communities and place; supporting local business; and people and skills,
where each priority has predefined interventions, outputs and outcomes. In addition to
core UKSPF monies, the investment plan includes a focus on ring-fenced ‘Multiply’
funding to support the delivery of an area-based adult numeracy programme. The
substantive element of this funding is being delivered by UHI Argyll further to a
competitive procurement process. 
1.4 The Argyll and Bute Council UKSPF allocations to support delivery over three financial
years, specifically the final five months of 2022/23 and the next two financial years,
2023/24 and 2024/25, until the end of March 2025 are outlined in Table 1. At the
outset it was advised that allocations should be spent in year. However, given that the
2022/23 allocation was not approved until December 2022, funding was carried over
from 2022/23 into 2023/24 and likewise into the final year 2024/25. 
1.5 As noted in Table 1 the largest allocation of UKSPF budget is in the final financial year
2024/25 which is challenging. Through discussions at the Scottish Local Authorities
Economic Development (SLAED) Executive and Funding Group meetings, a request
was sought in writing to key ministers within the previous UK Government in April 2024
to extend the UKSPF delivery timescales by one-year, complete with capacity funding
to cover staffing costs, to enable all projects to complete spend and deliver, given the
significant delay to approving the year one allocation. The response noted that this
would be considered in the autumn spending review.  However, given the new UK
Government, such a request will need to be resubmitted to address this continued
uncertainty.

Page 2

2.0 RECOMMENDATIONS 
2.1 Members are asked to: 
• Note the content of this report and progress made. 
• Agree officers engage with the UK Government on the requirement for some
clarity on future funding streams, such as the UK Shared Prosperity Fund, in light
of the recent change of the UK Government. 
3.0 DETAIL 
3.1 On 13th April 2022 the UK Government published the full prospectus of the UKSPF, a
successor to the previous EU structural funds. The overarching aim of the UKSPF is to
build pride in place and increase life chances across the UK. This encompasses four
levelling up objectives and three investment priorities. 
The levelling up objectives are:
• Boost productivity, pay, jobs and living standards by growing the private
sector, especially in those places where they are lagging;
• Spread opportunities and improve public services, especially in those places
where they are weakest;
• Restore a sense of community, local pride and belonging, especially in those
places where they have been lost; and
• Empower local leaders and communities, especially in those places lacking
local agency. 
The Investment Priorities are:
• Communities and place;
• Supporting local business; and
• People and skills. 
The interventions list for Scotland as a whole can be found here and the objectives,
outcomes and outputs can be found here. 
3.2 Immediately following the General Election results of 4th July 2024, the new UK
Government signalled a move away from the use of the term ‘levelling up’ in ministerial
statements, with the phrase ‘local government’ replacing the term in departmental and
ministerial titles. At present, it is unclear what this may mean for any successor to the
UKSPF as there has not yet been formal policy announcements, although it is thought
that the broad priorities above will remain important. 
3.3 A summary of the Argyll and Bute allocation (which includes a 4% administration fee
for overall fund delivery) and current spend is outlined in Table 1 overleaf. The
percentages of the allocation by year are given, showing the largest allocation for core
UKSPF in 2024/25. It is a concern that the allocation for Multiply is 30.2% for 2022/23
did not take into account the shorter timescale for delivery. A delayed start to the
programme in 2022/23 resulted in an underspend which has been carried forward into

Page 3

the current year, with a knock-on effect for 2023/24. The UK Government has
permitted re-allocation of funds across activities within core UKSPF spend in 2022/23
but not in later years. 
3.4 Table 1 below shows the spend to date. Six-monthly reporting to UK Government on
spend for this current financial year is due in September, when an update forecast can
be given. Re-allocation of spend across years and projects has allowed us to maximise
delivery, and we will continue to work closely with delivery partners to do so where
possible throughout the remainder of the project. However, it will remain challenging to
deliver the entire allocation without an extension beyond of the end 2024/25 FY to
allow projects to complete and spend. 
Table 1 - UK Shared Prosperity Fund Allocations and Spend 2022/23 – 2024/25
Core 2022/23 2023/24 2024/25 Total
In-year allocations Core
UKSPF
12% 24% 64% 100%
£451,343 £902,686 £2,365,038 £3,719,067
Revised Forecast Spend
(including previous year
underspend)
- £1,323,641 £2,620,394 -
Spend £30,387 £1,068,285 - £1,098,672
Balance £420,955 £255,356 £2,620,394 £2,620,394
Multiply* 2022/23 2023/24 2024/25 Total
In-year allocations
Multiply
30% 35% 35% 100%
£234,698 £270,806 £270,806 £776,310
Spend £4,793.80 £218,497.75  
Underspend £229,904.20 £52,308.25  
* Multiply is an adult numeracy programme, which will support people with no or low-level maths skills
get back into work The scheme will offer free personal tutoring, digital training, and flexible courses to
improve adults’ confidence and numeracy skills. Full details on Multiply can be found here . As noted in
the text underspend in 2022/23 was carried over into core UKSPF activity in 2023/24 however, UK
government have confirmed this is not allowable for future years. 
N.B. Figures subject to rounding. 
3.5 A summary of projects under each of the three priorities, and spend to date is given in
Table A1, Appendix A. Significant activity has been delivered against the three
investment priorities as depicted in Table A1. Selected highlights are as follows. 
• Argyll and Bute Revenue and Benefits team, as part of their work under the
Communities and Place priority, have reached 581 people, supporting 268
households to reduce the cost of living, including through measures to improve
energy efficiency, and combat fuel poverty and climate change. 
• The Council’s Employability team offers UKSPF Training and Work Placements.
Since May 2023, they have helped 45 participants undertake a wide range of
training courses to provide valuable workforce skills. The UKSPF-Supported
Work Placement programme proved very successful, with 13 participants since
May 2023 continuing with their Work Placement host after the end of the
placement.

Page 4

• Within Supporting Local Businesses, delivery partners Argyll and Bute Business
Gateway had delivered 43 grants by the end of March 2024 to enterprises in the
local authority and assisted five entrepreneurs to be business ready. Some
testimonials (approved to share by the business) from the Business Gateway
support are outlined below: 
Dace McLellan, Rolling Pizza - mid Argyll – UKSPF Business Start-up Grant
recipient (originally posted on LinkedIn) 
Dace approached Business Gateway last year when the idea for the
business first began. Dace converted an old horse box into a van with a
wood-fired oven allowing her to cook fresh pizzas made to order from
any location. With support and guidance from her local Business
Gateway Adviser, Donald Melville, she accessed start-up funding through
the UK Shared Prosperity Fund which helped with the initial set-up costs. 
Dace noted “Business Gateway was a huge support to me when setting
up Rolling Pizza and has continued to be now we’re up and running. The
online system has been great for encouraging people to pre-order and
gives me an indication of potential earnings and I couldn’t have done that
without Business Gateway. Being in a rural area can often make it more
difficult to find business support, but Donald has been a fantastic help
and I really appreciate his guidance.” 
• Delivery partners InspirAlba has supported the People and Skills priority by
retraining 23 individuals in the local authority with 18 being supported to gain a
qualification or complete a course. 
• Third Sector Interface (TSI) has supported 52 volunteering opportunities. 
4.0 CONCLUSION 
4.1 The purpose of this paper is to provide an update for members of the committee on the
progress of the Argyll and Bute UK Shared Prosperity Fund (UKSPF) Investment Plan
project / programme interventions that are being delivered across Argyll and Bute. 
4.2 As noted above, spend is progressing, but it is challenging that most of the spend is
allocated into this financial year, 2024/25. This is exacerbated by knock-on effects from
a late start to the UKSPF resulting in further activity and spend being rolled over into
the final year of the programme. Clarity is required urgently whether the new UK
Government will grant a one-year extension to allow all projects and programmes to
complete delivery and spend, complete with additional capacity funding to support
staffing costs.

Page 5

5.0 IMPLICATIONS 
5.1  Policy: this project / programme interventions aligns with the proposals set the UKSPF
full prospectus. 
5.2  Financial: Argyll and Bute Council has been given an allocation of just under £4.5m
from the UKSPF to be spent by the end of March 2025. This is accompanied by £20k
of capacity funding to assist in the development and preparation of the investment plan
and the ability to use up to 4% of the allocation per annum to fund administration
support for the overall delivery of the Argyll and Bute UKSPF Investment Plan. 
5.3  Legal: all appropriate legal implications will be taken into consideration. 
5.4  HR: given the revenue nature of this fund, staffing requirements can be built in under
activity to deliver the predefined interventions, outputs and outcomes. The UK and
External Policy Team, Economic Growth, is supporting the requirement to administer,
monitor and evaluate the overall delivery of the Argyll and Bute UKSPF Investment
Plan. 
5.5  Fairer Scotland Duty:  the Fairer Scotland Duty, Part 1 of the Equality Act 2010, came
into force in April 2018. The duty places a legal responsibility on particular public
bodies in Scotland, such as Argyll and Bute Council, to pay due regard to (actively
consider) how they can reduce inequalities of outcome caused by socio-economic
disadvantage when making strategic decisions and how this has been implemented. 
5.5.1 Equalities: all activities will comply with all Equal Opportunities/Fairer Scotland Duty
policies and obligations.
5.5.2 Socio-economic Duty: all project / programme activities will comply with the council’s
socio-economic duty.
5.5.3 Islands: interventions under the UKSPF will be delivered across the Argyll and Bute
area, including island communities. 
5.6  Climate Change: there are a number of net zero and climate resilience interventions
across all the UKSPF investment priorities. 
5.7  Risk: to ensure all projects and programmes can conclude with no money returned to
the UK Government, clarity is required whether the new UK Government will grant a
one-year extension to allow all projects and programmes to complete delivery and
spend, complete with additional capacity funding to support staffing costs. 
5.8  Customer Service: none.   
5.9 The Rights of the Child (UNCRC): none. 
Kirsty Flanagan, Executive Director responsible for Economic Growth 
Councillor Math Campbell-Sturgess: Policy Lead for Business Development

Page 6

1st August 2024 
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
fergus.murray@argyll-bute.gov.uk 
Ishabel Bremner, Economic Growth Manager 
ishabel.bremner@argyll-bute.gov.uk 
Kevin Grant, Senior Development Officer, UK & External Policy Team, Economic Growth
kevin.grant@argyll-bute.gov.uk 
APPENDICES 
Appendix A: Summary of Argyll and Bute UKSPF Investment Plan Projects / Programmes

Page 7

Appendix A: Summary of Argyll and Bute UKSPF Investment Plan Projects /
Programmes 
Table A1: Summary of Argyll and Bute UKSPF Investment Plan Projects /Programmes
Communities and Place
Predefined Intervention Project Allocation 
(exc. admin)
Spend to 31st 
March 2024
S7: Funding for the development and
promotion of wider campaigns which
encourage people to visit and explore local
areas.
Tourism
Marketing
Support £155,000 £78,047
S8: Funding for impactful volunteering
and/or social action projects to develop
social and human capital in local places.
Community
Planning
Partnership
Climate Change
Working Group –
community
capacity building
£60,000 £11,294
S9: Investment in capacity building,
resilience (including climate change
resilience) and infrastructure support for
local civil society and community groups.
Extension of
Shaping Places
for Wellbeing
Support
£6,000 £224
Vibrant and Living
Spaces £304,262 £0
S10: Community measures to reduce the
cost of living, including through measures
to improve energy efficiency, and combat
fuel poverty and climate change.
Extension of
Flexible Food
Fund - grants,
advice and skills
support for
people struggling
with cost of living
£408,000 £225,865
S12: Investment and support for digital
infrastructure for local community facilities. Community Hubs £81,750 £1,577
S13: Support for linking communities
together and with employment
opportunities with a focus on
decarbonisation.
Pre-loved School
Uniform Project £140,000 £0
Sub-total allocation for Communities and Place £1,155,012 £317,008

Page 8

Supporting Local Businesses
Predefined Intervention Project Allocation 
(exc. admin)
Spend to 31st
March 2024
S14: Funding for the development and
promotion (both trade and consumer) of
the visitor economy, such as local
attractions, trails, tours and tourism
products more generally.
Tourism Sector
Support –
improved digital
infrastructure for
data monitoring,
evaluation & visitor
book ability
£45,000 £21,463
S15: SME development grants and
support, aligned with local and regional
sectoral priorities and growth potential.
The support is proven to leverage high
levels of private investment into
technologies that drive growth,
productivity, efficiency and resilience in
manufacturing.
Scientific Robotics
Academy £299,900 £77,380
S16: Research and development grants
supporting the development of innovative
products and services, with a particular
focus on low carbon goods and
environmental services, and climate
resilience. 
Innovation Support
Service providing
expert advice and
capability reviews
to help SMEs
create innovation
plans
£100,000 £1,600
S22: Support for growing the local social
economy, including community
businesses, cooperatives and social
enterprises.
Graduate
Apprenticeship
Opportunities in
the Third Sector
£71,154 £35,003
S26: Business support measures to drive
employment growth, particularly in areas
of higher unemployment.
Graduate
Placement
Programme
providing graduate
placement grants
covering staff,
training and travel
costs
£180,000 £33,154
S29: Support for new and existing
businesses and start-ups aligned with
local, regional and Scottish policy.
Business
Development
Package for local
SMEs, providing
enhanced start-up,
recovery and
growth support
comprising grants,
specialist advice
and intensive
support
programmes
£454,099 £105,276
Sub-total allocation for Supporting Local Businesses £1,150,153 £273,876

Page 9

People and Skills
Predefined Intervention Project Allocation
(exc. admin)
Spend to 31st
March 2024
S31: Employment support for
economically inactive people:
intensive support supplemented by
additional and/or specialist life and
basic skills (digital, English, maths
(Multiply) and ESOL) support where
there are local provision gaps.
Adult Literacy and
Numeracy Programme £165,559 £22,336
S33: Activities such as enrichment
and volunteering to improve
opportunities and promote wellbeing
Expansion of the Wider
Achievement
Programme for all
secondary schools
£125,000 £5,204
Pre-Employability
Support Programme
Work Placements
£402,489  £120,779
Positive Destinations
Programme, providing
support for young
people
£137,475 £123,175
S35: Support for employability
programmes and advice including
alignment with the No One Left Behind
agenda, Fair Start Scotland and
Scottish employability pipeline. This
could include tailored support to
address barriers to accessing
education and training courses.
Pre-Employability
Support Programme
Training
£97,765 £19,430
Supported Employment
Experience in the Third
Sector
£336,850 £166,162
Sub-total allocation for People and Skills £1,265,138 £457,086
Overall Allocation (exc. admin) £3,570,303 £1,047,970 
The above projects/programmes have been implemented using a mixture of delivery models (again
predefined by the UK Government) as follows:
• In-house provision;
• Procurement of service provision;
• Grants to public or private organisations; or
• Commissioning third party organisations.