ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
FINANCIAL REPORTS MONITORING PACK – 31 AUGUST 2024
1. INTRODUCTION 
1.1 This report provides a summary of the financial monitoring reports as at the end of
August 2024. There are five detailed reports, setting out the position as at 31 August
2024, which are summarised in this Executive Summary: 
 Revenue Budget Monitoring Report
 Monitoring of Financial Risks
 Capital Plan Monitoring Report
 Treasury Monitoring Report
 Reserves and Balances
2. DETAIL 
2.1 Revenue Budget Monitoring Report 
2.1.1 This report provides a summary of the current revenue budget monitoring position to
ensure net expenditure is contained within budget. It provides corporate and
departmental information with comparisons on a forecast outturn and a year to date
basis.
2.1.2 There is a forecast overspend of £4.096m as at the end of August 2024. The variances
are:
- Within Social Work, a forecast overspend of £1.470m relating to demand for
residential placements within Children and Families and Older Peoples Services.
- Within Roads and Infrastructure Services, a forecast overspend of £0.970m due
to increased bus contract renewals for Public and Pupil Transport across Argyll
and Bute, additional costs relating to repairs to the Belnahua Ferry, the Transport
of ASN pupils and two unrealized savings for additional income from Traffic
Regular Orders (TB13b) and Stadiums (TB12b). These overspends are partially
offset with additional income in Waste and reduction in Landfill Tax costs due to
reduced tonnage within Helensburgh Waste Disposal.
- An overspend of £0.780m is being reported in relation to the Weather Incident of
October 2023, this relates to the proportion of the total estimated cost which
Policy and Resources Committee on 15 August 2024 agreed to be funded from
Crown Estate funding and shows as an overspend at this time pending
confirmation of the funding for 2024-25.
- Within Education, a projected overspend of £0.693m due to the Schools
Residential Budget having a higher demand for placements than the budget
allows.
- Within Central Budgets, a forecast overspend of £0.271m is reported in relation
to the inflation on insurance being higher than estimated.
- Within Central Budgets, a forecast overspend of £0.252m for 2024-25 pay

Page 2

awards as the Scottish Government requires Councils to fund 3.2% while the
budget only has 3% built in. This is recognised within Other Operating Income
and Expenditure for August monitoring with the intention that it will be aligned to
departments once the pay award is finalised.
- Within Development and Economic Growth, a forecast overspend of £0.104m
due to increased temporary accommodation costs.
- Within Funding, an over-recovery of Council Tax income on second homes of
£0.328m.
- Within Executive Director Kirsty Flanagan, a projected over-recovery of vacancy
savings of £0.100m.
- Within Customer Support Services, a projected underspend of £0.016m from
Organisational Development.
2.1.3 There is a year to date overspend of £3.622m. More focus is on the forecast outturn
position, hence why sometimes the year to date position is not updated. The year to
date variances mainly relate to the timing of income and expenditure and recharging of
costs to capital. 
2.1.4 Total policy savings relevant to 2024-25 financial year amount to £6.467m. The table
below outlines their progress as at 31 August 2024. 
Category  No. of
Options 
2024-25
£000
2024-
25
FTE 
2025-26
£000
2025-
26
FTE
Future
Years
£000
Future
Years
FTE
Delivered 5 5,431.0 8.4 5,598.0 8.4 5,598.0 8.4
On Track to be
Delivered 8 915.0 6.5 796.0 6.5 796.0 6.5
Still to be
Implemented 1 0.5 0.0 0.5 0.0 0.5 0.0
Being Developed 0 0.0 0.0 0.0 0.0 0.0 0.0
Will not be achieved 2 120.0 0.0 170.0 0.0 170.0 0.0
Potential Shortfall 0 0.0 0.0 0.0 0.0 0.0 0.0
Delayed 0 0.0 0.0 0.0 0.0 0.0 0.0
TOTAL 16 6,466.5 14.9 6,564.5 14.9 6,564.5 14.9 
2.1.5 Two savings are categorised as will not be achieved and a cost pressure will be added
to the 2025-26 budget for the shortfall (£0.120m). 
Health and Social Care Partnership (HSCP) – Financial Update
2.1.6 The forecast outturn position at the end of August is an estimated overspend of
£2.070m for 2024-25 (£1.470m overspend for Social Work and £0.600m for Health).
The HSCP’s financial position will continue to be monitored and Financial Services staff
will engage with the HSCP Chief Financial Officer to ensure that mitigation actions are
in place to address the deficit and ensure that no additional funding is required from the
Council.

Page 3

2.2 Monitoring of Financial Risks 
2.2.1 This report outlines the process and approach developed in carrying out a financial risks
analysis and provides an update on the current assessment of financial risks. 
2.2.2 There are 7 Council wide revenue risks identified for 2024-25 currently amounting to
£3.592m.
2.2.3 There are currently 43 departmental risks totalling £6.793m. Of the 43 departmental
risks, 5 are categorised as likely. These will continue to be monitored and action taken
to mitigate or manage these risks.
2.2.4 The current top three risks in terms of the financial impact are noted in the table below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads
Maintenance -
Bridges,
Culverts & Sea
Defences
Extreme localised weather
may result in loss of bridge,
culvert, road or sea defence.
3 1,500
Roads and
Infrastructure
Services
Waste PPP -
Indexation
Historical payments made
towards Waste PPP based
on indexation rates have
been challenged by Renewi
resulting in a potential cost to
the council.
3 586
Financial
Services
Council Tax
Debt Collection
Recovery
Recovery of debt becomes
more difficult to pursue in the
current economic
climate. This is in relation to
historical debt that has
accumulated over many
years therefore any adverse
collection rates will impact on
the year end debt provision
as opposed to the in-year
financial position, hence no
forecast variance has been
reported within the current
year.
3 345

Page 4

2.2.5 
2.2.6
There have been 3 changes to the departmental risks since the report as presented to
the Council on 15 August 2024. These are outlined in paragraph 3.4.1 of the Financial
Risks Report.
Three other potential risks relating to funded childcare for 1 and 2 year olds, the
proposed new school campus on Mull and digital access for learners are covered in
section 3.6 of the Financial Risks report.
2.3 Capital Plan Monitoring Report
2.3.1 This report provides a summary of the current capital plan monitoring position.
Information is provided in terms of monitoring year to date budget, current full year
budget, future years total budget and funding and non-financial in terms of project
performance.
2.3.2 In recent years, the Council has agreed additional funding for the capital programme
totalling £11.100m to address specific costs related to dealing with COVID, inflationary
pressures arising as a consequence of the factors detailed in paragraph 2.3.3 below
and other cost pressures on the capital plan. To date, £9.240m has been allocated to
projects leaving a balance of £1.860m available for allocation as required.
2.3.3 The capital programme continues to see significant price increases as well as
disruptions to the supply chain and longer lead in times. The increased rate of inflation
impacts costs such as energy prices, labour, packaging and transport. These all have
an effect on the overall contract price and make it extremely challenging to manage
expenditure and the availability of supply. As a result of this it should be noted that there
are likely to be other significant financial impacts which are not quantifiable at this stage.
2.3.4 Actual net expenditure to date is £10.648m compared to a budget for the year to date of
£10.659m giving rise to an overspend for the year to date of £0.011m (0.10%).
2.3.5 The forecast outturn for 2024-25 is a forecast net expenditure of £36.248m compared to
an annual budget of £37.007m giving rise to a forecast overspend for the year of
£0.759m (2.05%).
2.3.6 The forecast total net projects costs on the capital plan are £192.882m compared to a
total budget for all projects of £192.791m giving rise to a forecast overspend for the
overall capital plan of £0.091m (0.05%).
2.3.7 In respect of total project performance, there are 150 projects within the capital plan,
140 are complete or on target, 4 are off target and recoverable and 6 projects are off
track.
2.4 Treasury Monitoring Report
2.4.1 This report provides information on the current levels and recent transactions in relation
to the capital financing limit, total borrowing, temporary borrowing and long term
borrowing and investments.

Page 5

2.4.2 There was no material movement in external borrowing for the period 1 July 2024 to 31
August 2024.
2.4.3 Borrowing is below the Capital Financing Requirement for the period to 31 August 2024,
at this stage in the financial year capital expenditure is below target.
2.4.4 The levels of investments were £61.702m at 31 August 2024. The average rate of
return achieved was 5.110 % which is above the target SONIA (Sterling Overnight Index
Average) rate for the same period of 4.950%.
2.5 Reserves and Balances
2.5.1 This report summarises the overall level of reserves and balances and monitors the
spending of the earmarked reserves, providing detailed information on the unspent
budget earmarked balances.
2.5.2 The Council has a total of £689.113m unusable reserves that are not backed with
resources. They are required purely for accounting purposes.
2.5.3 At 31 March 2024, the Council had a total of £121.701m of usable reserves. Of this:
 £2.763m relates to the Repairs and Renewals Fund
 £3.197m relates to Capital Funds
 £115.741m was held in the General Fund, with £107.443m of this balance
earmarked for specific purposes.
2.5.4 At the budget setting meeting on 22 February 2024, as part of the revenue budget,
Council agreed to the transfer Strathclyde Pension Fund contribution savings of
£6.875m relating to Council staff and £3.053m relating to Social Work staff to reserves.
It was also agreed that £1.875m of revenue surplus within 2024-25 be transferred to the
Capital Plan. As the commitments for these include expenditure within 2024-25 year,
these have been immediately recognised within the earmarked reserves balances to
allow them to be spent accordingly. In addition, Scottish Government funding in relation
to the 23-24 pay award has been notified at a value of £0.371m and this has been
reinstated to the Connect for Success earmarking as planned. This results in a total in-
year earmarked balance of £119.617m.
2.5.5 Of the earmarked balance of £119.617m:
 £58.040m is invested or committed for major initiatives/capital projects
 £10.124m has already been drawn down
 £20.998m is still to be drawn down in 2024-25
 £30.445m is planned to be spent in future years
2.5.6 The table below summarises the position of the unallocated General Fund balance.
Further explanation of the figures can be found at Section 3.4 of the Reserves and
Balances report.

Page 6

Heading Detail £000
Unallocated General Fund
as at 31 March 2024
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£6.039m
2,259
Current Forecast Outturn
for 2024-25 as at 30 June
2024
Per paragraph 3.4.2. (4,096)
Social Work outturn
adjustment
Per paragraph 3.4.3 - Social Work
would expect to transfer any surplus
to internal IJB reserves
1,470
Weather Incident Per P&R 15 Aug 24 – Likely use of
crown estate funding to offset
weather incident remaining costs
780
Estimated Unallocated
balance as at 31 March
2025 
413 
2.5.6 It can be seen that, after taking into consideration the current forecast outturn for 2024-
25 and the likely input of Crown Estate Funding to the remaining Weather Event
overspend, the Council is estimated to have a £0.413m surplus over contingency. 
2.5.7 As at 31 August 2024, the commitments against the Strathclyde Pensions fund gain
Transformation/Spend to Save projects earmarking are as follows: 
Description Commitment
£000
Drawn
Down at
31/08/24
£000
Data Platform Build Consultancy 40 0
Data Platform Build Consultancy (Contingency) 4 0
RIS Service Review 150 0
Conversational AI 31 0 
225 0 
Further details can be found on the Reserves and Balances report at section 3.7.4 
2.6 VIREMENTS OVER £0.200m (Revenue) 
2.6.1 Virement is the process of transferring budget between cost centres, services or
departments or between capital projects. The Council’s constitution notes that

Page 7

virements over £0.200m require approval by Council. This section of the report will be
used to outline revenue virements in the period that require approval. Capital
virements are included within the capital monitoring report. 
2.6.2 For the period July to August, there are 2 virements requiring authorisation: 
- £0.246m moved between cost centres within Social Work to offset savings
targets.
- £0.420m transferred from central utilities budget to: street lighting electricity costs
to offset the overspend (£0.220m) and Other Operating Income and Expenditure
(£0.200m). This is to reverse part of the original contingency allocated to utilities
for 2024-25 that is not required, noting that the £0.200m allocated to Other
Operating Income and Expenditure will be released back to the general fund in
2025-26. 
3. RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee:
a) Consider the revenue budget monitoring report as at 31 August 2024. 
b) Note the financial risks for 2024-25. 
c) Note the capital plan monitoring report as at 31 August 2024 and approve the
proposed changes to the capital plan outlined in Appendix 4 of that report. 
d) Note the treasury monitoring report as at 31 August 2024. 
e) Consider the reserves and balances report as at 31 August 2024. 
f) Recommend to Council that the revenue virements over £0.200m during July and
August 2024 are approved. 
g) Note the commitments/drawdowns from the Strathclyde Pension Fund gain
Transformation/Spend to Save projects earmarking. 
4. IMPLICATIONS
4.1 Policy – None.
4.2 Financial - Outlines the revenue and capital monitoring
for 2024-25 as at 31 August 2024
4.3 Legal - None.
4.4 HR - None.
4.5 Fairer Scotland Duty - None.
4.5.1 Equalities – protected characteristics - None.
4.5.2 Socio-economic Duty - None.
4.5.3 Islands - None.
4.6 Climate Change - None.
4.7 Risk - Risks are included in financial risks report.
4.8 Customer Service - None.
4.9 The Rights of the Child (UNCRC) - None.

Page 8

Kirsty Flanagan
Executive Director /Section 95 Officer
6 September 2024 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 9

REVENUE BUDGET MONITORING REPORT AS AT 31 AUGUST 2024 POLICY AND RESOURCES COMMITTEE
10 OCTOBER 2024
2024-25 Overall Position:
There is a forecast overspend of £4.096m as at the end of August 2024. Within Social Work, there is a forecast overspend of £1.470m
relating to demand for residential placements within Children and Families and Older Peoples Services. Within Executive Director Kirsty
Flanagan, there is a forecast overspend of £0.958m due to increased bus contract renewals for Public and Pupil Transport across Argyll and
Bute, additional costs relating to repairs to the Belnahua Ferry, the Transport of ASN pupils, Temporary Accommodation and two unrealised
savings for additional income from Traffic Regulation Orders (TB13b) and Stadiums (TB12b). These overspends are partially offset with
additional income in Waste, reduction in Landfill Tax costs due to reduced tonnage levels in Helensburgh Waste Disposal and vacancy
savings across the department. The Weather incident of October 2023 has resulted in a pressure from a revenue perspective of £3.567m as
reported to Policy and Resources Committee on 15 August 2024. Members agreed to how to fund this overspend in its entirety including
£0.780m from Crown Estates funding, however as the 2024-25 funding has not yet been confirmed there remains a variance reported at this
stage of £0.780m. Within Executive Director Douglas Hendry, there is a forecast overspend of £0.693m relating to school residential budget
having a higher demand for placements than budget allows. Within Central Budgets, an overspend of £0.271m is reported in relation to the
inflation on insurance being higher than estimated. There is also an overspend of £0.252m recognised in respect of the pay awards for 24-25
currently in negotiation as the Scottish Government requires Councils to fund 3.2% while the budget only has 3% built in. Within funding,
there is a projected over-recovery of income for Council Tax on 2nd Homes of £0.328m 
There is a year to date overspend of £3.622m. The year to date variances within the departments tend to relate to the timing of income and
expenditure and costs to capital not recharged yet.
Key Highlights as at August 2024:
 Council services are projecting an overspend of £4.096m as at 31 August 2024. This includes £1.470m from Social Work which would
be expected to be covered from reserves and £0.780m from the October 23 Weather Incident, which should be covered from Crown
Estate Funding. The remaining overspend is £1.846m.
 The latest offer in relation to the 2024-25 pay award requires Councils to fund a 3.2% increase with Scottish Government funding
between 3.2% and the current pay offers. This is for all bargaining groups. As this is more than is currently in the 2024-25 budget, this
creates a net pressure on the budget of £0.252m, which is recognised in Other Operating Income and Expenditure for August
monitoring with the intention that it will be aligned to departments once the pay award is finalised. At the time of writing, the teachers
pay award has been agreed but SJC and Chief Officers are still in negotiations.
Key Financial Successes:
Performance against budget for 2023-24 was an overall net favourable position of £1.728m underspend after adjusting for year-end
earmarking. This breaks down as:

Page 10

 £1.037m net overspend in relation to Council expenditure (excluding loans fund)
 £0.033m over-recovery of Council Tax income
 £5.932m underspend from the Loans Fund due to a higher return on investments than in the previous year, limiting new borrowing by
utilising cash balances instead, slippage within the capital programme and a one-off treasury gain as a result of a discount on the early
repayment of loans
 £3.200m of new unspent budget earmarkings
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Addressing service demand/expectation and the increasing challenges
facing departments across the Council in relation to the recruitment and
retention of suitably qualified and experienced staff.
Engagement and monitoring of both issues with departments to
assess how these challenges are affecting service capacity and
capability, staff attendance, utilisation of agency staff and costs.
Collaboration with services and other back-office teams to consider
and develop mitigating actions.
Achieving a favourable year-end position and achieving savings targets
in light of council wide risks to expenditure.
Robust monitoring of the financial position and delivery of savings to
ensure budget issues inform the budget monitoring process.
Monitoring Social Work expenditure and more widely the IJB position as
any overspend will transfer back to partner bodies in the first instance.
Continue to work closely with the CFO of the IJB to ensure that early
indication of any potential adverse financial outturn is identified and
corrective action is agreed as appropriate to reduce the risk to the
Council.
Identifying further savings and delivering services more efficiently with
less resources, as whilst a balanced 2024-25 budget was agreed in
February 2024 there are still significant budget gaps in future years.
The Council will continue to progress savings options identified,
refine options that require further development and seek to identify
further savings through themed reviews and business process
reviews. A longer term approach is being explored with the intention
to develop a pipeline of savings that can be delivered over a number
of years.
Maintaining or improving the level of service income recovered, for
example planning, building standards and car parking.
Actively monitor income recovery and ensure Council fees and
charges policies are regularly reviewed.
Managing spend in service areas which are demand led and, to some
extent, outwith service control, for example Winter Maintenance.
Use a risk-based approach to budget monitoring to focus additional
attention on these areas.
Ongoing requirement to fund unavoidable inflationary increases in areas
like utility costs, fuel, food etc.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.
Cost of living crisis impacting on pay inflation negotiations which could
result in pay awards above what is deemed affordable.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.

Page 11

Future ongoing impact on revenue budgets as a result of the delivery of
substantial capital projects such as Rothesay Pavilion and a new school
on Mull.
Ensure costs are identified and reported on early in the process so
Members are aware of the ongoing financial impact to budgets.
Monitor and report on these regularly as part of the routine budget
monitoring once the projects are complete.
Delivery of climate change measures which can be costly and result in
overspends.
The Council will look at financially sustainable options and closely
monitor the impact of these on the budget position.

Page 12

Forecast Outturn Position
There is a forecast underspend of £4.096m for 2024-25 as at 31 August 2024. 
Department
Annual
Budget
£'000
Forecast
Outturn
£'000
Current
Forecast
Variance
£'000
Previous
Forecast
Variance
£000 
Change
£000  Explanation
Chief Executive's Unit 1,191 1,191 0 0 0 
Executive Director (Douglas Hendry) 148,302 148,995 (693) (693) 0 The proejcted overspend is due to the Schools Residential Budget having a
higher demand for placements than budget allows. 
Executive Director (Kirsty Flanagan)  57,686  58,644  (958)  (1,060)  102
The projected overspend is due to increased bus contract renewals for Public
and Pupil Transport across Argyll and Bute, additional costs relating to repairs
to the Belnahua Ferry, the Transport of ASN pupils, Temporary Accommodation
and TRO Income which was a previously agreed saving to secure additional
income that has been unachievable. These overspends are partially offset with
additional income in Waste, reduction in Landfill Tax within Helensburgh Waste
Disposal and vacancy savings across the department. 
Weather Incident  2,787  3,567  (780)  (3,567)  2,787
The total pressure in relation to the Weather Incident of October 2023 from a
revenue perspective was quantifed at £3.567m. The meeting of Policy and
Resources on 15 August 2024 agreed on how to fund the total overspend
(£3.853m including capital) with £0.780m due to come from Crown Estate
Funding. As the amount of funding in relation to 2024-25 is not yet confirmed,
the variance reported at August is £0.780m. Other options would be explored if
funding is not confirmed or is insufficient.
Social Work 78,646 80,116 (1,470) (1,483) 13 The projected overspend is due to demand for residential placements within
Children and Families and Older People Services. 
Central Budgets  22,347  22,870  (523)  (523)  0
The projected overspend is due to pressure on the insurances budgets due to
inflation being higher than estimated (£0.271m) and a recognition that Scottish
Government have asked Councils to fund a further 0.2% increase for the pay
awards being negotiated for 24-25 (£0.252m).
Financed By (310,959) (311,287) 328 328 0 There is a projected over recovery of income for Council tax on second homes.
Total 0 4,096 (4,096) (6,998) 2,902

Page 13

Forecast outturn position for each Department from the start of the financial year 
Underspend
400 
(100) 
(600) 
(1,100) 
(1,600) 
Overspend
Chief Executive's Unit
Executive Director (Douglas Hendry)
Executive Director (Kirsty Flanagan)
Social Work
Central Budgets
Financed By 
Further information on the departmental forecast variances is included later on in the report.
£ 000 April
May
June
July
August
September
October
November
December
January
February

Page 14

Year to Date Position
The year to date position as at 31 August 2024 is an overspend of £3.622m and the main variances are noted below. 
Department
YTD
Actual
£'000
YTD
Budget
£'000
YTD
Variance
£'000 
Explanation
Chief Executive's Unit 499 497 (2) The year to date overspend can be attributed to profiling issues.
Executive Director (Douglas Hendry) 59,517 60,143 626 The year to date underspend is mainly due to the current budget profile which will
be refined through September and is partially offset by the pressure on the
Schools Residential Budget.
Executive Director (Kirsty Flanagan) 23,782 20,678 (3,104) The year to date overspend is mainly due to the profile of a number of budgets
across the department.
Weather Incident 1,899 0 (1,899) The year to date overspend can be attributed to profiling issues.
Social Work 18,877 18,234 (643) The year to date overspend is due to demand driven services within Children and
Families and Older People.
Central Budgets 3,625 5,025 1,400 The year to date underspend can be attributed to profiling issues.
Funding (131,366) (131,366) 0 
Total Net Expenditure (23,167) (26,789) (3,622)

Page 15

Expenditure to date against the remaining budget for each Department
100% 
75% 
50% 
25% 
0% 
YTD Actual £000 Remaining Budget £000 
Further information on the departmental year to date variances is included later on in the report.
Chief Executive's Unit
Executive Director (Kirsty Flanagan)
Executive Director (Douglas Hendry)
Social W
ork
Central Budgets
TOTAL

Page 16

OBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 AUGUST 2024 
YEAR TO DATE POSITION CURRENT PROJECTED FINAL OUTTURN
YTD
Actual 
£'000
YTD
Budget 
£'000
YTD
Variance 
£'000
Variance 
%
Annual Budget 
£'000
Forecast
Outturn 
£'000
Forecast
Variance 
£'000
Variance 
%
Departmental Budgets 
Chief Executive's Unit 499 497 (2) (0.4%) 1,191 1,191 0 0.0%
Executive Director (Douglas Hendry) 59,517 60,143 626 1.0% 148,302 148,995 (693) (0.5%)
Executive Director (Kirsty Flanagan) 23,782 20,678 (3,104) (15.0%) 57,686 58,644 (958) (1.7%)
Weather Incident 1,899 0 (1,899) 0.0% 2,787 3,567 (780) (28.0%)
Social Work 18,877 18,234 (643) (3.5%) 78,646 80,116 (1,470) (1.9%)
Total Departmental Budgets 104,574 99,552 (5,022) (5.0%) 288,612 292,513 (3,901) (1.4%)
Central Budgets    
Other Operating Income and Expenditure (3,321) 415 3,736 900.2% 3,531 3,783 (252) (7.1%)
Joint Boards 634 607 (27) (4.5%) 1,458 1,458 0 0.0%
Non-Controllable Costs 6,312 4,003 (2,309) (57.7%) 17,358 17,629 (271) (1.6%)
Total Central Budgets 3,625 5,025 1,400 27.9% 22,347 22,870 (523) (2.3%)
TOTAL NET EXPENDITURE 108,199 104,577 (3,622) (3.5%) 310,959 315,383 (4,424) (1.4%)
Financed By    
Aggregate External Finance (98,717) (98,717) 0 0.0% (249,731) (249,731) 0 0.0%
Local Tax Requirement (32,649) (32,649) 0 0.0% (63,278) (63,606) 328 (0.5%)
Contributions to General Fund 0 0 0 0.0% 12,174 12,174 0 0.0%
Earmarked Reserves 0 0 0 0.0% (10,124) (10,124) 0 0.0%
Total Funding (131,366) (131,366) 0 0.0% (310,959) (311,287) 328 (0.1%)
(Deficit)/Surplus for Period (23,167) (26,789) (3,622)  0 4,096 (4,096)

Page 17

SUBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 AUGUST 2024 
YEAR TO DATE POSITION CURRENT PROJECTED FINAL OUTTURN
YTD
Actual
£'000
YTD
Budget
£'000
YTD
Variance
£'000
Variance 
%
Annual
Budget
£'000
Forecast
Outturn
£'000
Forecast
Variance
£'000
Variance 
%
Subjective Category
Employee Expenses 72,558 72,247 (311) (0.4%) 191,498 194,062 (2,564) (1.3%)
Premises Related Expenditure 10,793 10,065 (728) (7.2%) 21,748 21,752 (4) (0.0%)
Supplies and Services 12,165 12,073 (92) (0.8%) 27,187 27,305 (118) (0.4%)
Transport Related Expenditure 6,482 5,358 (1,124) (21.0%) 18,288 18,692 (404) (2.2%)
Third Party Payments 77,383 74,771 (2,612) (3.5%) 191,488 192,000 (512) (0.3%)
Capital Financing 705 (2,026) (2,731)  10,626 10,626 0 0.0%
TOTAL EXPENDITURE 180,086 172,488 (7,598) (4.4%) 460,835 464,437 (3,602) (0.8%)
Income (203,253) (199,277) 3,976 (2.0%) (460,835) (460,341) (494) 0.1%
(Deficit)/Surplus for Period (23,167) (26,789) (3,622)  0 4,096 (4,096) 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.

Page 18

CHIEF EXECUTIVE’S UNIT – AS AT 31 AUGUST 2024 
The department is currently forecasting spend in line with budget.
The department has a year to date overspend of £0.002m (0.4%) which can be attributed to budget profiling issues.
Forecast Outturn Position Year to Date Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change 
£000 
Chief Executive 1,191 1,191 0 0 0
Totals 1,191 1,191 0 0 0 
Key Financial Successes:
 All savings options have been delivered.
 The department’s 2023-24 outturn position was an underspend of £0.006m. This resulted from an overall underspend of £0.014m offset
by earmarking of £0.008m due to an auto-carry forward for unspent grants.
Key Financial Challenges: Proposed Actions to address Financial Challenges:
To continue to deliver a high-quality service to support community
engagement and participation.
Regular monitoring, reflection and improvement cycle on service
provision to ensure most efficient use of staffing and financial

Page 19

resources to meet national and local policy requirements for quality
engagement.
To continue to deliver a high quality support service function to community
organisations and community planning partners during a time of challenge
arising from continuing reductions in funding.
Within the partnership working of the CPP we seek to establish
working groups and collate resources within this to deliver high
quality solutions to identified needs.
Demands for funding from community applications to the Supporting
Communities Fund higher than available annual funds by about 40%.
Continue to monitor fund criteria adapting this to align with priority
outcomes for Argyll & Bute and continue to support groups to seek
alternative sources of funding from our database of funding
providers.

Page 20

CHIEF EXECUTIVE’S UNIT – OBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Service Area YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Executive 158 157 (1) (0.6%) 414 414 0 0.0% Outwith reporting criteria.
Community Planning
& Development 341 340 (1) (0.3%) 777 777 0 0.0% Outwith reporting criteria. 
499 497 (2) (0.4%) 1,191 1,191 0 0.0% 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 21

CHIEF EXECUTIVE’S UNIT – SUBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000 
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000 
%
Variance  Explanation
Employee 389 377 (12) (3.2%) 1,012 1,012 0 0.0% Outwith reporting criteria.
Supplies and
Services 12 14 2 14.3% 21 21 0 0.0% Numerous small accumulating variances.
Transport 1 6 5 83.3% 14 14 0 0.0% Underspend on staff travel budgets.
Third Party 124 152 28 18.4% 224 224 0 0.0%
Year to date variance relates to the timing of
income / expenditure in relation to the Prosperity
fund.
Income (27) (52) (25) 48.1% (80) (80) 0 0.0%
Year to date variance relates to the timing of
income / expenditure in relation to the Prosperity
fund.
Totals 499 497 (2) (0.4%) 1,191 1,191 0 0.0% 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 22

CHIEF EXECUTIVE’S UNIT – RED VARIANCES AS AT 31 AUGUST 2024 
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation   
0 0.0% 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 23

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 AUGUST 2024 
The department is currently forecasting an overspend of £0.693m (0.5%) due to the Schools Residential Budget having a higher demand for
placements than budget allows.
The department has a year to date (YTD) underspend of £0.626m (1.0%). This underspend is mainly due to the current budget profile, which
will be refined through September, and is partially offset by the above pressure on the Schools Residential Budget.
Forecast Outturn Position
Service  Annual Forecast  Current Previous Change
Budget  Outturn Forecast  Forecast
Variance Variance
£000 £000 £000 £000 £000
Executive Director 156 156 0 0 0 (Douglas Hendry)
Head of
Commercial 10,347 10,347 0 0 0
Services
Head of Education 116,530 117,223 (693) (693) 0
Head of Legal and
Regulatory 21,269 21,269 0 0 0
Support
Totals 148,302 148,995 (693) (693) 0
Year to Date Position

Page 24

Key Financial Successes: 
The 2023-24 year-end consolidated outturn position was an under spend of £0.690m after adjusting for automatic earmarking. Contributing
factors included:
 Effective contract management of NPDO and Hub School contracts, including a lower-than-expected insurance premium due to the
annual renegotiation of insurance costs.
 Successful negotiations with utility suppliers achieved further historic water charge refunds and ongoing reductions to water rates.
 Implementation of NDEEF project resulting in recurring annual saving in utilities and a significant contribution to meeting Net Zero
targets.
 Rationalisation of office space through Our Modern Workspace Programme has reduced utility costs, printer costs and cleaning costs
as well as receiving Non-Domestic Rates relief for closed buildings.
 Income generation within Early Years, including expansion at Rothesay Joint Campus to accommodate care for children under the age
of 2
Key Financial Challenges: Proposed Actions to address Financial Challenges:
The legacy impact of COVID-19 on our young learners has led to an
increased demand on the additional support need functions of the
Education Service in response to the growing health and wellbeing
needs of our young people and their families. This increase is consistent
across Scotland.
Analysis and review of delivery models has taken place, robust
costings of any agreed changes to delivery model and continual
monitoring of associated budgets. Maximise use of Additional
Support for Learning Funding and Mental Health and Wellbeing
Funding whilst working collaboratively across Children’s Services.
Impact of the current cost of living crisis on the cost of the school day for
learners and their families.
Work with schools to ensure effective use of Strategic Equity
Funding and Pupil Equity Funding to close the poverty related
attainment gap and identify other funding sources to ensure equity
of experience for all children.
Impact of the current cost of living crisis on uptake in demand led service
areas like catering, design services and licensing.
Continually refine/develop systems to accurately forecast service
usage, budget outturn and future budget requirements. Strategies
in place to redesign services in line with demand.
Rising cost of material and labour costs within the Central Repairs
Budget across the department may result in a reduction in activity or
overspends.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as soon as known.
Ensure that the School Catering Service remains efficient and effective
as the impact of high inflation on produce and a requirement to adhere to
the Statutory Guidance supporting Nutritional Requirements for Food and
Drink in Schools (Scotland) Regulations 2020, has increased the cost of
producing a school meal.
Through good procurement of supplies and the introduction of a
school meal pre order app that will reduce food waste. Produce
meals that pupils want to eat through regular consultation and a
range of menu choices.

Page 25

The Council has a requirement to deliver 1140 hours of Early Learning
and Childcare (ELC) to eligible 2-year-olds and all 3–5-year-old children.
Following two years of reduced funding the service must continually
redesign to fit the resources available.
Robust service costings, financial monitoring and timely reporting
to ensure the service can be delivered within the available budget.
Medium term forecasting on population to shape ongoing service
redesign. Analysis of potential to extend income generation using
“spare” capacity to trial paid care for under 2’s
Impact of high inflationary uplifts within the NPDO/HUB School contracts. Ensuring continued effective contract management of NPDO/HUB
Schools to minimise the impact of high inflationary uplifts.
The Scottish Government has Ringfenced some Education funding which
is dependent on Maintaining Teacher Numbers (MTN) to a set level. The
target has increased for 2024-25 with no increase in funding.
Monitor teacher numbers and associated costs, highlighting any
budget pressures immediately. If teacher numbers fall due to
delays in recruitment, report the potential financial penalty to
departmental management.

Page 26

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Service  Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Executive
Director
(Douglas
Hendry)
Central/Management
Costs
142 153 11 7.2% 156 156 0 0.0% Outwith Reporting Criteria  
142 153 11 7.2% 156 156 0 0.0% 
Head of
Commercial
Services
Catering (144) (119) 25 (21.0%) 320 320 0 0.0% The YTD underspend is due to the
profile of the repair/replacement of
tools and equipment budget which
will be refined through September.
Head of
Commercial
Services
Central/Management
Costs
485 523 38 7.3% 1,726 1,726 0 0.0% Outwith Reporting Criteria
Head of
Commercial
Services
CHORD 68 50 (18) (36.0%) 49 49 0 0.0% The YTD over spend is due to the
timing of recharges required from
capital
Head of
Commercial
Services
Cleaning (82) (14) 68 (485.7%) 203 203 0 0.0% The YTD underspend is largely due
to the reduced use of bank staff.
Head of
Commercial
Services
Culture, Heritage,
Recreation & Sport
2,329 2,249 (80) (3.6%) 5,729 5,729 0 0.0% The YTD overspend is due to budget
profile of utilities and the central
repairs budget which will be refined
through September
Head of
Commercial
Services
Events &
Commercial
Catering
60 (16) (76) 475.0% 7 7 0 0.0% The YTD overspend is due to under-
recovery of income budgets within
Events and Commercial Cafes.
Finance are working closely with
Commercial Services to increase
income generation.
Head of
Commercial
Services
Property Portfolio (160) (141) 19 (13.5%) (189) (189) 0 0.0% The YTD underspend is due to the
current budget profile within Surplus
Properties, this will be refined
through September.
Head of
Commercial
Services
Property Services 549 607 58 9.6% 858 858 0 0.0% The YTD underspend is due to
delays in staff recruitment. This
variance will be removed when
vacancy savings are harvested.

Page 27

Head of
Commercial
Services
Shared Offices 426 558 132 23.7% 1,644 1,644 0 0.0% The YTD underspend is due to
profiling of the Central Repairs
Budget and Rental Income budgets
these will be refined through
September.  
3,531 3,697 166 4.5% 10,347 10,347 0 0.0% 
Head of
Education
Additional Support
for Learning
4,580 4,622 42 0.9% 12,148 12,148 0 0.0% Outwith Reporting Criteria
Head of
Education
Central/Management
Costs
1,139 1,029 (110) (10.7%) 2,697 2,697 0 0.0% The YTD overspend is mainly due to
the budget profile, which will be
refined through September. The
remainder is due to overspends in
licences, staff subsistence,
conference fees and travel budgets.
Head of
Education
Community Learning
& Development
4 2 (2) (100.0%) 15 15 0 0.0% The YTD overspend is due to utilities
costs within CLD premises for which
budgets will be rightsized throughout
the year.
Head of
Education
COVID 18 10 (8) (80.0%) 10 10 0 0.0% The YTD overspend will be rectified
through drawdown of earmarkings.
Head of
Education
Early Learning &
Childcare
6,808 6,819 11 0.2% 17,730 17,730 0 0.0% Outwith Reporting Criteria
Head of
Education
Primary Education 16,646 16,988 342 2.0% 41,278 41,277 1 0.0% The YTD underspend is mainly due
to the current budget profile which
requires to be refined through
September by AFA's.
Head of
Education
Pupil Support 1,154 993 (161) (16.2%) 2,677 3,370 (693) (25.9%) The YTD overspend is due to higher
than budgeted demand for Schools
Residential Placements. There has
been a forecast variance reported
through the ledger for this pressure.
Head of
Education
Schools - Central
Services
875 957 82 8.6% 2,507 2,507 0 0.0% The YTD underspend is due to the
budget profile of the 100 day promise
budget and curriculum for
excellence, this will be refined
through September.
Head of
Education
Secondary
Education
16,887 17,103 216 1.3% 37,468 37,469 (1) (0.0%) The YTD underspend is profile
related within staffing budgets which
will be rectified through September.  
48,111 48,523 412 0.9% 116,530 117,223 (693) (0.6%)

Page 28

Head of Legal &
Regulatory
Support
Central/Management
Costs
95 95 0 0.0% 263 263 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Community Safety 135 95 (40) (42.1%) 187 187 0 0.0% The YTD overspend will be partially
rectified through drawdown of
earmarkings and processing of
prepayments at year end.
Head of Legal &
Regulatory
Support
Elections 75 32 (43) (134.4%) 37 37 0 0.0% The YTD overspend is due to the
costs of postages and computer
software for running both the UK and
local elections, funding will be
reprofiled to cover this expenditure.
Head of Legal &
Regulatory
Support
Governance 212 209 (3) (1.4%) 749 749 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Governance, Risk &
Safety
212 197 (15) (7.6%) 552 552 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Legal Services 126 237 111 46.8% 687 687 0 0.0% The YTD underspend is due to
timing of licensing income. The
budget profile requires refinement..
Head of Legal &
Regulatory
Support
NPDO and Hub
Schools
6,227 6,258 31 0.5% 16,972 16,972 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Procurement,
Commercial and
Contract
Management
397 399 2 0.5% 1,140 1,140 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Trading Standards &
Advice Services
254 248 (6) (2.4%) 682 682 0 0.0% Outwith Reporting Criteria  
7,733 7,770 37 0.5% 21,269 21,269 0 0.0% 
59,517 60,143 626 1.0% 148,302 148,995 (693) (0.5%) 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 29

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – SUBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Employee 41,447 41,887 440 1.1% 108,331 108,331 0 0.0% The YTD underspend is mainly due to the current
budget profile of School Staffing and Property Services
staffing budgets which will be refined through
September.
Premises 3,350 3,141 (209) (6.7%) 8,904 8,904 0 0.0% The YTD overspend will be rectified by a drawdown
from the early years earmarked reserve and reprofiling
of utility costs in Primary and Secondary Schools.
Supplies and
Services
5,400 6,079 679 11.2% 14,862 14,862 0 0.0% The YTD underspend relates mainly to the current
budget profile of Schools Prepared Meals and
Educational Equipment budgets within the Education
Service, as well as the budget profile of Catering
Purchases and Replacement of Tools and Equipment
budget within Commercial Services.
Transport 186 137 (49) (35.8%) 341 341 0 0.0% The YTD overspend is due to small overspends within
staff travel budgets across all Services, this overspend
will be closely monitored.
Third Party 24,689 24,103 (586) (2.4%) 47,310 48,003 (693) (1.5%) The YTD overspend is mainly due to the timing of
invoices within NPDO and Hub Schools and the
reported budget pressure within the Schools
Residential Budget.
Income (15,555) (15,204) 351 (2.3%) (31,446) (31,446) 0 0.0% The YTD underspend is mainly due to the current
budget profile for receipt of grant income, donations
and income from other local authorities within the
Education Service. The current budget profile of
Licensing Fees and NPDO Schools requires to be
refined within Legal and Regulatory Services and will
be rectified through September.
Totals 59,517 60,143 626 1.0% 148,302 148,995 (693) (0.5%)

Page 30

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 31

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – RED VARIANCES AS AT 31 AUGUST 2024 
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation 
Education - Pupil Support  2,677  3,370  693  15.1% Higher than budgeted demand for placements within
Residential Schools. 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 32

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 AUGUST 2024 
The department has a forecast overspend of £0.958m (1.7%). This is due to increased bus contract renewals for Public and Pupil Transport
across Argyll and Bute, additional costs relating to repairs to the Belnahua Ferry, the Transport of ASN pupils, Temporary Accommodation and
two unrealised savings for additional income from Traffic Regulation Orders (TB13b) and Stadiums (TB12b). These overspends are partially
offset with additional income in Waste, reduction in Landfill Tax costs due to reduced tonnage levels in Helensburgh Waste Disposal and
vacancy savings across the department. 
The department has a year to date overspend of £3.104m (15.0%). This is mainly due to the profile of a number of budgets across the
department.
Forecast Outturn Position 
Service  Annual Forecast  Current Previous Change
Budget  Outturn Forecast  Forecast
Variance Variance
£000 £000 £000 £000 £000
Executive Director
(Kirsty Flanagan) (119) (219) 100 0 100
Head of Customer
Support Services
8,780 8,764 16 0 16
Head of
Development and
Economic Growth 8,793 8,897 (104) 0 (104)
Head of Financial
Services 6,909 6,909 0 0 0
Head of Roads
and Infrastructure
Services 33,323 34,293 (970) (1,060) 90
Totals 57,686 58,644 (958) (1,060) 102
Year to Date Position 
Key Financial Successes:

Page 33

The department had a challenging 2023-24 financial year with few financial successes largely due to the Weather Incident in October creating
substantial pressures as well as reduced income due to numerous ferry cancellations at our Piers & Harbours.
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Ensuring that services spend to budget and do not overspend after the
department had an overspend of £1.3m after automatic earmarkings in
2023-24.
Detailed monitoring in the key areas overspent in 2023-24 to flag up
concerns early and mitigate before becoming an overspend.
Department / Service ongoing ability to meet future savings / efficiency
requirements.
Monitoring of trends / expenditure levels / service configuration and
the Service Packages Policy Options savings process.
Rising cost of materials, software and consultancy services across the
service will result in a reduction in activity or overspends.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as soon as known.
Financial Services to continue to deliver a high-quality support service
function during a time of substantial uncertainty and challenge arising from
continuing reductions in funding whilst costs are increasing due to ongoing
high levels of inflation and service demand caused by world events.
Ensure the team is operating as efficiently and effectively as
possible by building resilience across the team and working
collaboratively with other services of the Council to support
evidence-based decision making.
Winter Maintenance costs are difficult to estimate as they are very much
dependant on the weather.
Close monitoring of Winter Maintenance activity and reporting of the
financial implications through the budget monitoring process. The
Council agreed the winter policy, setting out the intervention level
and locations to be treated. The number of treatments is determined
by weather conditions. The current budget provision provides for 56
full equivalent runs. There is a sophisticated weather monitoring
system in place consisting of several weather stations, this is
supported by a forecasting and meteorological service which is
collaboratively procured by West of Scotland local authorities.
Climate Change Mitigation impacting on the departments key
infrastructure due to increased inspection regimes will result in
overspends.
The Council will continue to tackle climate change, looking at
financially sustainable options and will closely monitor the financial
consequences.
Dangerous buildings costs as there is no budget for this expenditure and
the council has no control over the demand for the service.
Building Standards, Legal Services and Financial Services are
working closely to manage debt recovery and to consider other
options to minimise corporate risk exposure.

Page 34

Ferry Grant from Transport Scotland has stayed the same for 2024-25
despite increased costs for employee inflation as well as other general
inflationary increases.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as soon as known.
Due to the nature of the various components of Waste Management there
are ongoing challenges with:
• The introduction of the Deposit Return Scheme
• Uncertainty with recycling income/ gate fee costs due to the
volatility of the market
• Challenges in the legislative changes around the disposal of
Biodegradable Municipal Waste
• The Circular Economy Bill that has recently been passed and the
implications that may bring
To closely monitor all service components of Waste Management
and review the Waste Strategy in conjunction with our contractual
partner Renewi (previously Shanks).

Page 35

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Service 
Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Executive
Director (Kirsty
Flanagan)
Central/Management
Costs
113 113 0 0.0% (119) (219) 100 (84.0%) Forecast variance due to a
projected over-recovery of
vacancy savings.  
113 113 0 0.0% (119) (219) 100 (84.0%) 
Head of
Customer
Support Services
Central/Management
Costs
53 55 2 3.6% 167 167 0 0.0% Outwith reporting criteria
Head of
Customer
Support Services
Communications 130 125 (5) (4.0%) 322 322 0 0.0% Outwith reporting criteria
Head of
Customer
Support Services
Customer Service
Centres
494 516 22 4.3% 1,597 1,597 0 0.0% Outwith reporting criteria
Head of
Customer
Support Services
HR 1,085 1,032 (53) (5.1%) 2,370 2,354 16 0.7% YTD overspend due to costs for
the iTrent project that require to
be drawn down from earmarked
reserves.
Forecast variance due to
underspend in Organisational
Development
Head of
Customer
Support Services
ICT 1,968 1,902 (66) (3.5%) 4,342 4,342 0 0.0% YTD overspend due to the timing
of expenditure in comparison to
the profiling of budget and will be
rectified over the financial year.
Head of
Customer
Support Services
Registrars (45) (25) 20 (80.0%) (18) (18) 0 0.0% YTD underspend due to the
timing of income in comparison
to the profiling of budget and will
be rectified over the financial
year.  
3,685 3,605 (80) (2.2%) 8,780 8,764 16 0.2% 
Head of
Development &
Economic Growth
Airports 719 454 (265) (58.4%) 1,186 1,186 0 0.0% YTD variance due to profile of
budget for Private Contactors
which will be rectified over the
financial year.
Head of
Development &
Economic Growth
Building Control (102) (112) (10) 8.9% (125) (125) 0 0.0% Outwith reporting criteria

Page 36

Head of
Development &
Economic Growth
Central/Management
Costs
196 217 21 9.7% 572 572 0 0.0% Outwith reporting criteria
Head of
Development &
Economic Growth
Culture & Heritage 96 90 (6) (6.7%) 235 235 0 0.0% Outwith reporting criteria
Head of
Development &
Economic Growth
Development
Management
(114) (43) 71 (165.1%) 115 115 0 0.0% YTD variance due to over-
recovery of Planning Fee income
received which will be rectified
over the financial year.
Head of
Development &
Economic Growth
Development Policy 133 166 33 19.9% 465 465 0 0.0% YTD overspend due to the timing
of expenditure in comparison to
the profiling of budget and will be
rectified over the financial year.
Head of
Development &
Economic Growth
Economic
Development
(1,651) 1,238 2,889 233.4% 2,043 2,043 0 0.0% YTD variance due to grant
income received that has not yet
been spent and will be rectified
over the financial year.
Head of
Development &
Economic Growth
Environmental
Health
389 471 82 17.4% 1,241 1,241 0 0.0% YTD variance is due to timing of
Private Landlord Registration
income which will be rectified
over the coming months as well
as underspends in employee
costs.
Head of
Development &
Economic Growth
Environmental
Initiatives
22 22 0 0.0% 95 95 0 0.0% Outwith reporting criteria
Head of
Development &
Economic Growth
Housing 1,972 1,608 (364) (22.6%) 2,676 2,780 (104) (3.9%) YTD variance due to earmarked
reserve draw down being
required to fund expenditure in
the Strategic Housing Fund.
Forecast overspend reported
due to increased Temporary
Accommodation costs.
Head of
Development &
Economic Growth
Private Landlords (307) (10) 297 (2970.0%) 0 0 0 0.0% YTD variance is due to timing of
Short Term Let income which
will be rectified over the coming
months with any surplus being
earmarked at the end of the
year.
Head of
Development &
Economic Growth
Transportation
Policy
85 148 63 42.6% 290 290 0 0.0% YTD variance due to profile of
income which will be rectified
over the financial year.

Page 37

1,438 4,249 2,811 66.2% 8,793 8,897 (104) (1.2%) 
Head of Financial
Services
Accounting &
Budgeting
921 966 45 4.7% 2,559 2,559 0 0.0% Outwith reporting criteria
Head of Financial
Services
Internal Audit &
Fraud
120 132 12 9.1% 332 332 0 0.0% Outwith reporting criteria
Head of Financial
Services
Revenues & Benefits 1,072 1,178 106 9.0% 3,083 3,083 0 0.0% YTD underspend due to the
timing of cash flows in
comparison to the profiling of
budget and will be rectified over
the financial year.
Head of Financial
Services
Scottish Welfare
Fund
322 405 83 20.5% 935 935 0 0.0% YTD variance due to Flexible
Food Fund - Income from
Contribution from The UK
Shared Prosperity Fund -
UKSPF/010 - PR6 Payment
received in August,
income/expenditure virement to
be processed in September
period.  
2,435 2,681 246 9.2% 6,909 6,909 0 0.0% 
Head of Roads &
Infrastructure
Services
Amenity 1,839 1,752 (87) (5.0%) 3,218 3,238 (20) (0.6%) YTD variance mainly due to
delay in Interment Fees in
Cemeteries and timing of cash
flows in comparison to the
profiling of budget within Parks
which will be rectified over the
financial year.
Forecast variance due to under-
recovery of income which is
linked to a previously agreed
saving from 2018-19 for
Stadiums (TB12b).
Head of Roads &
Infrastructure
Services
Car Parking (323) (177) 146 (82.5%) (595) (595) 0 0.0% YTD variance due to the timing
of income in comparison to the
profiling of budget and will be
rectified over the financial year.
Head of Roads &
Infrastructure
Services
Central/Management
Costs
1,205 1,134 (71) (6.3%) 2,735 2,687 48 1.8% YTD variance due to profile of
internal recharge budget which
will be rectified for future
monitoring.
Forecast variance due to delay
in Route Optimisation project
resulting in a projected
underspend.

Page 38

Head of Roads &
Infrastructure
Services
Depots 198 201 3 1.5% (313) (313) 0 0.0% Outwith reporting criteria
Head of Roads &
Infrastructure
Services
Fleet & Transport 4,119 3,295 (824) (25.0%) 8,668 10,045 (1,377) (15.9%) YTD variance due to internal
fleet maintenance costs and
increased bus contracts for
Public Transport and Pupil
Transport.
Forecast overspend reported
due to increased contract costs
for Public & Pupil Transport as
well as projected increased
costs for Internal Pupil
Transport.
Head of Roads &
Infrastructure
Services
Infrastructure 187 254 67 26.4% 725 725 0 0.0% YTD variance due to the timing
of income in comparison to the
profiling of budget and will be
rectified over the financial year.
Head of Roads &
Infrastructure
Services
Marine (1,213) (2,029) (816) 40.2% (3,810) (3,560) (250) 6.6% YTD variance due to additional
costs for Ferry maintenance and
timing of income.
Forecast overspend for
additional maintenance costs for
Luing and Jura Ferries.
Head of Roads &
Infrastructure
Services
Network & Traffic
Management
87 16 (71) (443.8%) 138 238 (100) (72.5%) YTD variance due to shortfall in
income for Traffic Regulation
Orders.
Forecast overspend for an
unrealised saving for additional
income from Traffic Regulation
Orders.
Head of Roads &
Infrastructure
Services
Road Safety 42 76 34 44.7% 147 147 0 0.0% YTD underspend due to the
timing of cash flows in
comparison to the profiling of
budget and will be rectified over
the financial year.
Head of Roads &
Infrastructure
Services
Roads & Lighting 6,227 1,869 (4,358) (233.2%) 7,699 7,699 0 0.0% YTD variance due to the profile
of internal recharge budget
within the Roads and Lighting
Holding account, which will be
rectified over the financial year.

Page 39

Head of Roads &
Infrastructure
Services
Waste 3,743 3,639 (104) (2.9%) 14,711 13,982 729 5.0% YTD variance due to the timing
of income in comparison to the
profiling of budget and will be
rectified over the financial year.
Forecast underspend reported
as there is a reduction in Landfill
Tax costs due to reduction in
tonnage levels in Helensburgh
alongside additional recyclate
and commercial refuse income.  
16,111 10,030 (6,081) (60.6%) 33,323 34,293 (970) (2.9%) 
23,782 20,678 (3,104) (15.0%) 57,686 58,644 (958) (1.7%) 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 40

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – SUBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Employee 15,564 15,851 287 1.8% 43,235 43,519 (284) (0.7%) YTD variance mainly due to vacancies within the Roads and
Lighting Holding Account which are being covered by
external contractors.
Forecast overspend reported for additional Pupil Transport
costs which is partially offset with additional vacancy savings
projected and underspend in Training.
Premises 1,374 1,532 158 10.3% 4,020 4,020 0 0.0% YTD variance mainly due to the profile of the Street Lighting
electricity which will be profiled to rectify for next monitoring
period.
Supplies
and
Services
5,564 4,565 (999) (21.9%) 10,949 10,901 48 0.4% YTD variance mainly due to expenditure incurred in
Economic Development which will be funded from grant
income as well as the profile of budget across a number of
services which should be rectified by end of the financial
year.
Forecast variance reported due to the delay in the Route
Optimisation project.
Transport 5,998 4,934 (1,064) (21.6%) 16,906 17,256 (350) (2.1%) YTD variance due to additional costs for Ferry maintenance
and vehicle maintenance costs.
Forecast overspend for additional maintenance costs for
Luing and Jura Ferries.
Third Party 28,326 27,007 (1,319) (4.9%) 70,399 71,181 (782) (1.1%) YTD variance mainly due to grant payments within Economic
Development and Housing that either have or will be offset
with grant income once received as well as external
contractor costs within Roads that are covered by additional
income.
Forecast overspend due to increased contract costs for
Public Transport and additional Temporary Accommodation
costs in Housing.
Capital
Financing
0 0 0 0.0% 2,677 2,677 0 0.0% Outwith Reporting Criteria
Income (33,044) (33,211) (167) 0.5% (90,500) (90,910) 410 (0.5%) YTD variance mainly due to grant income received within
Economic Development and Housing to cover expenditure
incurred within Third party Payments, this is partially offset
with an overspend due to the profile of recharges within the
Roads Operational Holding Account which will be rectified
over the financial year.
Forecast underspend reported as there is a reduction in

Page 41

Landfill Tax costs due to reduction in tonnage levels in
Helensburgh alongside additional recylate and commercial
refuse income which is partially offset against two unrealised
savings for additional income from Traffic Regulation Orders
(TB13b) and Stadiums (TB12b).
Totals 23,782 20,678 (3,104) (15.0%) 57,686 58,644 (958) (1.7%) 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 42

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – RED VARIANCES AS AT 31 AUGUST 2024 
Service Area
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation 
Public Transport  5,266  6,143  (877)  (16.7%) New bus contracts in place for Public and
Pupil Transport. 
Pupil Transport - Internal  1,461  1,961  (500)  (34.2%)  Increased costs for transporting ASN pupils. 
Ferries  160  410  (250)  (156.3%) Maintenance costs for Luing and Jura
ferries. 
Traffic Regulation Orders  (150)  (50)  (100)  66.7% Unrealised saving for additional income from
Traffic Regulation Orders. 
Housing  742  846  (104)  (14.0%) Increased costs for B&B usage for
Temporary Accommodation. 
Vacancy Savings  (428)  (528)  100  (23.4%)  Projected over-recovery of vacancy savings. 
Waste Income  (2,324)  (2,854)  530  (22.8%) Additional commercial refuse and recyclate
income. 
Waste Disposal  1,989  1,756  233  11.7% Reduction in Landfill Tax costs due to
reduction in tonnage levels in Helensburgh
A red variance is a forecast variance which is greater than +/- £50,000.

Page 43

SOCIAL WORK – AS AT 31 AUGUST 2024 
The department is currently forecasting an overspend of £1.470m (1.9%). This is due to demand for residential placements within Children and
Families and Older People Services. 
The department has a year-to-date overspend of £0.643m (3.5%) which again is due to demand driven services within Children and Families
and Older People.
Forecast Outturn Position Year to Date Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
£000
Previous
Forecast
Variance
£000
Change 
£000 
Chief Officer Integration (3,069) (3,134) 65 18 47
Head of Strategic Planning
and Performance  470  464  6  1  5
Head of Health and
Community Care  43,187  44,287  (1,100)  (1,077)  (23)
Head of Acute and
Complex Care  21,375  21,143  232  194  38
Head of Children and
Families  16,683  17,356  (673)  (619)  (54)
Totals 78,646 80,116 (1,470) (1,483) 13 
Key Financial Successes: 
Delivered a balanced budget at the end of 2023/24 after utilising £1.826m of reserves. An additional amount of £0.209m was transferred to IJB
reserves and should allow for future investment and transformation across Social Work.
Key Financial Challenges: Proposed Actions to address Financial Challenges:

Page 44

Deliver the outstanding savings total for 2024/25 of £1.008m (as at July
2024).
Maintain a close working relationship with the HSCP Service
Improvement Team to quickly and efficiently identify and assess
options for delivering the outstanding savings.
Development and delivery of future service redesigns which will be
necessary to contain service expenditure within the allocated resource,
noting that in year savings still need to be identified for 24/25 to address
the 24/25 budget gap, as well as budget gaps in future years.
Support from finance to assist strategic managers to develop and
identify further savings and to look beyond the short term to identify
and plan the changes which will be needed to address the expected
ongoing budget challenges over the current, and future, years.
Use of agency staff to support service delivery across Social Work, but
particularly in Older People services, due to recruitment and retention
challenges within the service. Year to date spend at July 2024 of £1.5m.
Close working relationship with the HSCP to support the costing of
a plan to stabilise the service and ensure it is operationally and
financially sustainable. This includes an exit plan from the reliance
on agency staff.
Cost of living crisis affecting pay inflation negotiations and financial
sustainability of service providers, which could affect affordability and
sustainability of service delivery.
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.

Page 45

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Service  Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Chief Officer
Integration
Integration
Headquarters
158 154 (4) (2.6%) 596 597 (1) (0.2%) Outwith reporting criteria.
Chief Officer
Integration
Social Work
Central
Support
(455) (429) 26 (6.1%) (3,665) (3,731) 66 (1.8%) The YTD variance is outwith reporting criteria.
The forecast variance is due to underspends
in centrally held funds.  
(297) (275) 22 (8.7%) (3,069) (3,134) 65 (2.0%) 
Head of
Strategic
Planning &
Performance
Management
& Central
Costs
149 150 1 0.7% 438 437 1 0.2% Outwith reporting criteria.
Head of
Strategic
Planning &
Performance
Service
Development
11 15 4 26.7% 32 27 5 15.6% The YTD variance is due to timing differences
on charges to health boards. The forecast
variance is due to underspends on staff costs
as a result of vacant hours.  
160 165 5 27.3% 470 464 6 15.9% 
Head of
Health and
Community
Care
Management
& Central
Costs
181 189 8 4.2% 582 598 (16) (2.7%) Outwith reporting criteria.
Head of
Health and
Community
Care
Older People 10,243 9,651 (592) (6.1%) 42,605 43,689 (1,084) (2.5%) The YTD and forecast variance are due to the
latest known demands for care packages and
the cost of agency staff and payments to third
party providers.  
10,424 9,840 (584) (5.9%) 43,187 44,287 (1,100) (2.5%) 
Head of
Acute and
Complex
Care
Learning
Disabilities
1,148 1,330 182 13.7% 15,087 14,497 590 3.9% The YTD variance is due to timing differences
on charges to health boards and other income
lines. The forecast underspend reflects known
demands for LD services.
Head of
Acute and
Complex
Care
Management
& Central
Costs
26 50 24 48.0% 128 115 13 10.2% The YTD and forecast underspend are based
on current projected training costs and
supplies and services costs which could
improve as spend trend becomes clearer.

Page 46

Head of
Acute and
Complex
Care
Mental Health 555 323 (232) (71.8%) 3,056 3,630 (574) (18.8%) The YTD variance and forecast overspend is
based on current known demands for the
service and re-assessments of care packages.
Head of
Acute and
Complex
Care
Physical
Disability
848 982 134 13.7% 3,104 2,901 203 6.5% The YTD variance is due to re-assessed care
packages. The forecast underspend is due to
a combination of re-assessed needs packages
and attritions.  
2,577 2,685 108 3.5% 21,375 21,143 232 1.8% 
Head of
Children &
Families
Child
Protection
1,148 1,251 103 8.2% 3,613 3,511 102 2.8% The YTD variance is based on known
demands for the service coupled with deferred
income received from previous years. The
forecast underspend is due to demand for
contact and welfare services and deferred
income in the area teams budget lines.
Head of
Children &
Families
Children with
a Disability
422 417 (5) (1.2%) 1,038 1,047 (9) (0.9%) Outwith reporting criteria.
Head of
Children &
Families
Criminal
Justice
130 23 (107) (465.2%) 174 152 22 12.6% The YTD variance is due to timing of grant
income. The forecast underspend reflects
additional grant funding received along with
vacant posts.
Head of
Children &
Families
Looked After
Children
3,203 2,905 (298) (10.3%) 7,923 8,725 (802) (10.1%) The YTD variance is due to an increase in the
demand in the number of residential
placements. The forecast overspend reflects
current known demand for the service.
Currently have 17 children in residential
placements with potentially more under
consideration along with an overspend on staff
costs due to a re-grading process partially
offset by underspends in Adoption and
Fostering.
Head of
Children &
Families
Management
& Central
Costs
1,110 1,223 113 9.2% 3,935 3,921 14 0.4% The YTD variance is due to increased s12
payments. The forecast variance is outwith
reporting criteria.  
6,013 5,819 (194) (3.3%) 16,683 17,356 (673) (4.0%) 
GRAND
TOTAL  18,877 18,234 (643) (3.5%) 78,646 80,116 (1,470) (1.9%)

Page 47

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 48

SOCIAL WORK – SUBJECTIVE SUMMARY AS AT 31 AUGUST 2024 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Employee 13,803 12,898 (905) (7.0%) 34,711 36,468 (1,757) (5.1%) Both the YTD and forecast overspend is due
to the use of agency staff across the HSCP
partially offset by payroll underspends due to
vacancies.
Premises 726 720 (6) (0.8%) 1,701 1,704 (3) (0.2%) The YTD and forecast variance are outwith
the reporting criteria.
Supplies &
Services
830 756 (74) (9.8%) (354) (187) (167) 47.2% The YTD overspend is largely due to the
timing of payments relating to the purchase
of computer software and the forecast
outturn variances are due to the profiling of
savings options not yet achieved.
Transport 279 258 (21) (8.1%) 617 671 (54) (8.8%) The YTD variance is outwith reporting
criteria and the forecast overspend is due
mainly to an increase in transport charges
for Helensburgh Day Care
Third Party 22,065 21,597 (468) (2.2%) 66,345 67,389 (1,044) (1.6%) The YTD and forecast variance are due to
demand for purchased care services across
both Childrens and Adult Services.
Income (18,826) (17,995) 831 (4.6%) (24,374) (25,929) 1,555 (6.4%) The YTD and forecast over recovery of
income is mainly due to increased income
from fees, charges and recharges. 
Totals  18,877  18,234  (643)  (3.5%)  78,646  80,116  (1,470)  (1.9%)

Page 49

YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year.
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 50

SOCIAL WORK – RED VARIANCES AS AT 31 AUGUST 2024 
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance  Explanation
Social Work
Central Support (3,665) (3,731) 66 (1.8%) The YTD variance is outwith reporting criteria. The forecast variance is due to underspends in
centrally held funds.
Looked After
Children  7,923  8,725  (802)  (10.1%)
The YTD variance is due to an increase in the demand in the number of residential placements. The
forecast overspend reflects current known demand for the service. Currently have 17 children in
residential placements with potentially more under consideration along with an overspend on staff
costs due to a re-grading process partially offset by underspends in Adoption and Fostering.
Child Protection 3,613 3,511 102 2.8%
The YTD variance is based on known demands for the service coupled with deferred income
received from previous years. The forecast underspend is due to demand for contact and welfare
services and deferred income in the area teams budget lines. 
Older People  42,605  43,689  (1,084)  (2.5%) The YTD and forecast variance are due to the latest known demands for care packages and the
cost of agency staff and payments to third party providers. 
Physical Disability  3,104  2,901  203  6.5% The YTD variance is due to re-assessed care packages. The forecast underspend is due to a
combination of re-assessed needs packages and attritions. 
Learning Disability  15,087  14,497  590  3.9% The YTD variance is due to timing differences on charges to health boards and other income lines.
The forecast underspend reflects known demands for LD services.
Mental Health 3,056 3,630 (574) (18.8%) The YTD variance and forecast overspend is based on current known demands for the service and
re-assessments of care packages. 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 51

MONITORING OF SAVINGS – AS AT 31 AUGUST 2024
New policy savings were identified for the three year period 2024-25 to 2026-27 and these were agreed by Council in February 2024. Council
agreed to policy savings of £0.665m on a recurring basis.
The position of historical policy saving options is as follows:
- 2023/24 – those not delivered or that have further increases in value in 2024-25 onwards total £5.387m
- 2022/23 – those not delivered or that have further increases in value in 2024-25 onwards total £0.170m
- 2021/22 – those not delivered total £0.041m
- 2020/21 – all delivered
- 2019/20 – all delivered
- 2018/19 - those not delivered total £0.204m
The 2024-25 savings have been removed from departmental budgets, however, it is important to monitor whether the saving has actually been
delivered to ensure that costs are not continuing resulting in an overspend by the end of the year. It is also important to ensure that any
preparatory work required to deliver savings in future years is on track.
There is one saving where the department has indicated it will not be achieved in full and one saving categorised as having a potential shortfall,
as summarised below: 
Saving Saving
Agreed
Status Detail Shortfall/
Delayed
Value
TB13b Roads and
Amenity Services
charging (non-statutory
services)
Feb-18 Will not be achieved in
full.
The original proposal was to introduce charges for providing lighting
design and increase charges by 20% for road construction consents,
skips, scaffolds, hoarding, permits and licences. Whilst some
additional income has been generated through third party works,
opportunities are expected to be limited over the foreseeable future
due to staff shortages and other competing demands.
A cost pressure will be added to the 2025-26 budget for this shortfall
and the service will look at other potential savings as part of the RIS
Review.
£100,000

Page 52

TB12b Stadiums Feb-18 Will not be achieved in
full.
The potential partnership relating to Mossfield has not materialised.
More clubs are now using the all weather facilities and this has had
an impact on Council income, therefore it is unlikely the full saving
will ever be achieved.
A cost pressure will be added to the 2025-26 budget for this shortfall
and the service will look at other potential savings as part of the RIS
Review.
£20,000 
All policy saving options previously agreed are noted in the table below for information.

Page 53

Template Ref Saving
Agreed
Service Service Delivery
Area
Savings Option 2024-25 2024-25 Status of Implementation
£000 FTE
Executive Director Douglas Hendry     
CS01 Feb-22 Commercial
Services
Property Services Climate Change & Resource Efficiency 63.0 0.00 On Track to be Delivered
202425 008 Feb-24 Commercial
Services - Live
Argyll
Live Argyll 10%
reduction
10% reduction to the Management Fee
paid to Live Argyll Leisure Trust from the
Council.
363.00 0.0 Delivered
202425 011 Feb-24 Education Positive Starts Referrals to the Positive Starts support
scheme have been reducing year on year,
furthermore the Early Years team no
longer have capacity to quality assure and
administer this budget to a level where
they can ensure a positive impact for
children and families or best value in
relation to the service. Referrals come
form Health and Social Work, not
Education however the HSCP were not
willing to manage this budget.
40.0 0.00 Delivered
202425 009 Feb-24 Governance,
Risk and
Safety
Governance
Restructure
Reorganisation of Governance team and
remove posts that are currently vacant.
The proposed restructure will ensure
current level of service will be maintained.
62.00 2.5 On Track to be Delivered
Executive Director Kirsty Flanagan     
DEG01 Feb-22 Development
and Economic
Growth
Economic Growth Crown Estate Administration Contribution
to Project Delivery
107.00 0.0 Delivered
FIS2324-001 Feb-23 Financial
Services
Treasury
Management
Service Concessions - Alteration to
accounting treatment to align the
repayment of borrowing relating to new
schools over their asset life. Guidance
from Scottish Government now permits
this change of accounting treatment.
Further detail will be provided to Council in
due course.
4,861.0 0.00 Delivered
FIS2324-002 Feb-23 Financial
Services
Revenues and
Benefits
The Service has identified savings
through rightsizing of budgets, an
organisational restructure with investment
in modern apprenticeships and temporary
staff designed to boost income from the
billing of additional local taxes and the
recovery of associated debt. In addition
efficiency savings from increased
productivity, increased levels of process
automation and moving more customers
to transact with the service over the
internet will allow previously outsourced
review works to be carried out internally.
466.00 3.0 On Track to be Delivered
R&I15 Feb-21 Roads and
Infrastructure
Roads and
Infrastructure
Emergency services support and fuel
provision from our fuel supplies
0.50 0.0 Still to be Implemented
202425 012 Feb-24 Roads and
Infrastructure
Roads and
Infrastructure
Services (RIS)
Review
A RIS Review was undertaken during
2023/24 and the implementation of the
outcomes will begin in 2024-25. It is
anticipated that further efficiency savings
will be achievable in future years but the
level of which are not known at this stage.
200.00 0.0 On Track to be Delivered
R&I09 Feb-21 Roads and
Infrastructure -
Operations
Roads and
Infrastructure -
Operations
Road inspections find and fix - reduce
reactive work by proactivity. Moving to AI
technology as technology develops
40.00 1.0 On Track to be Delivered
RIS2324-001 Feb-23 Roads and
Infrastructure
Services
School Crossing
Patrollers
Support Communities to move to different
approaches to delivering School Crossing
Patrols through engagement with Parent
Council and Communities.
60.00 8.4 Delivered
TB13b Feb-18 Roads and
Infrastructure
Services
Roads and
Infrastructure
Services
Roads & Amenity Services charging (non-
statutory services)
100.0 0.00 Will not be achieved
TB13b Feb-18 Roads and
Infrastructure
Services
Roads and
Infrastructure
Services
Roads & Amenity Services charging (non-
statutory services)
50.0 0.00 On Track to be Delivered
TB12b Feb-18 Roads and
Infrastructure
Services
Amenity Services Review charges for stadiums to enable
improvement work
20.00 0.0 Will not be achieved
TB12b Feb-18 Roads and
Infrastructure
Services
Amenity Services Review charges for stadiums to enable
improvement work
10.00 0.0 On Track to be Delivered
TB09 Feb-18 Roads and
Infrastructure
Services
Public Conveniences Public Conveniences - Progress
sustainable models including turnstiles
and franchising; establish simpler asset
transfer process
24.00 0.0 On Track to be Delivered
TOTAL     6,466.5 14.9

Page 54

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
10 OCTOBER 2024
FINANCIAL RISKS ANALYSIS 2024-25 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to provide a summary of the key financial risks
facing the Council.
1.2 A number of Council wide risks, both revenue and capital, have been identified
along with risks for each department and service of the Council. For each
departmental risk the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix.
1.3 There are 7 Council wide revenue risks identified for 2024-25 currently amounting
to £3.592m.
1.4 There are currently 43 departmental risks totalling £6.793m. Of the 43
departmental risks, 5 are categorised as likely.
1.5 The financial risks are monitored routinely and actions put in place to continue to
mitigate the risks.

Page 55

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
10 OCTOBER 2024
FINANCIAL RISKS ANALYSIS 2024-25 
2.  INTRODUCTION 
2.1 This report outlines the process and approach developed in carrying out a
financial risks analysis and provides a note of the current assessment of financial
risks for 2024-25.
3 DETAIL 
3.1 Introduction 
3.1.1 The Council is currently in a period of significant financial challenge. In
developing its budget to address both restricted resources and cost and demand
pressures there are a number of financial risks the Council needs to consider and
manage.
3.1.2 There are a number of risks that affect the income or expenditure across the
whole council and these have been identified. Financial risks have been
considered by each department and service of the Council.
3.1.3 For each risk, the financial impact has been quantified and the likelihood
assessed based on the standard risk matrix as follows: 
1 – Remote
2 – Unlikely
3 – Possible
4 – Likely
5 – Almost Certain
3.1.4 The Argyll and Bute Integrated Joint Board (IJB) with responsibility for Social
Work and a range of Health services was established and came into effect on 1
April 2016. The IJB is responsible for financial and strategic oversight of these
services. It is the responsibility of the IJB to consider the individual financial risks
associated with Integration Services and they are therefore not contained within
this report. A Council wide risk has been included in respect of the IJB being
unable to deliver the social care service within the budget allocated.
3.2 Council Wide Risks 
Revenue 
3.2.1 The 2024-25 budget includes a 3% pay award assumption for all staff groups.
Negotiations on the 2024-25 award are in progress and it is likely that the Trade
Unions will looking to negotiate a deal at more than 3%. However, the

Page 56

affordability for Local Government has to be considered and based on future
estimates, anything above a 3% pay award is deemed to be unaffordable, hence
why the budget outlook has been based on 3%. This is a situation that will be
kept under close review as the pay negotiations advance during the year and the
assumption will be adjusted as required. For each 1% more than the 3% built in,
there would be an additional cost of around £1.264m. The financial risk is
recognised at £1.264m at this stage. Note that this is for SJC, Chief Officer and
Teaching Staff. A risk in relation to Councillor pay is noted at section 3.2.4.
3.2.2 Utility costs remain a volatile area and it is difficult to accurately predict how the
prices could vary. With the volatility of utilities pricing it is very difficult to predict
the impact going forward but a financial risk based on a 10% variation on the
2023-24 actual spend plus 2024-25 non-pay inflation is £0.650m. 
3.2.3 The estimated level of council tax income is based on current and forecast Band
D equivalents and non-payment rates. This reflects our most recent experience in
terms of the council tax base and likely collection rates. A 1% variation in council
tax income amounts to approximately £0.633m. 
3.2.4 The Scottish Local Authorities Remuneration Committee (SLARC) have been
working on proposals in relation to Councillor Remuneration which would result in
increases to Councillor pay and a budget pressure of £0.178m for Argyll and Bute
if backdated to 1 April 2024. The Scottish Government have indicated that they
would be open to agreeing the changes with an implementation date of 1 April
2025 but a recent COSLA Leaders update advised that a regulatory pathway
remains open for an uplift to be backdated to April 2024 subject to local
government funding. COSLA will continue to work with the Scottish Government
over the summer and a full paper will be taken to the COSLA Leadership
Sounding Board in August. 
3.2.5 At the budget meeting on 22 February 2024, the Council agreed 4 new policy
savings options that would deliver savings over the period 2024-25 to 2026-27.
The savings to be delivered in 2024-25 amount to £0.665m. Whilst the Council
have a good track record in delivering savings, a 10% shortfall on this savings
target would amount to £0.067m. 
3.2.6 In respect of the Health and Social Care Partnership, it is the responsibility of the
Chief Officer and Chief Financial Officer to manage the HSCP financial position.
If an overspend is forecast, a budget recovery plan will be prepared and
submitted to the IJB, the Council and NHS Highland. Where recovery plans are
unsuccessful and an overspend occurs at the financial year end, and the HSCP
has insufficient reserves to meet the overspend, then the partners will be required
to make additional payments to the HSCP. Whilst any additional payments by the
Council and NHS Highland will be deducted from future years funding, there is still
a financial risk that the Council may have to pay out additional monies in year. As
at 31 August 2024, the net HSCP outturn in 2024-25 is estimated to be a £2.070m
overspend (Social Work forecasting an overspend of £1.470m and an overspend
of £0.600m from Health). As the IJB holds significant financial reserves, there is a
nil value on the risk.

Page 57

3.2.7 There is an ongoing requirement to fund unavoidable inflationary cost increases in
areas like fuel, food etc. Inflation has been falling and the Bank of England
estimates that it should continue to fall this year. We will continue to closely
monitor the situation and update our financial forecasts using the best information
available to us. A 1% general inflation increase has been included with a financial
impact of £0.800m. 
3.2.8 The Council wide risks are noted within the table below. 
Description Likelihood Assessed
Financial Impact
£000
Pay Award Exceeding 3% 3 1,264
Energy costs increase by 20% greater
than anticipated
3 650
1% variation in Council Tax Income 2 633
Councillor Pay Changes 3 178
10% shortfall on Savings Options 2 67
IJB refer to Council for additional
funding to deliver social work services
1 0
1% variation of General Inflation Risk 4 800
Total  3,592 
Capital 
3.2.9 The finance settlement announcement on 19 December 2023 provided details of
the Local Government funding for 2024-25 and there is therefore certainty as to
what our funding is in respect of the General Capital Grant and the specific capital
grants already distributed. 
3.2.10 The capital plan for 2024-25 includes an estimate of £0.750m in respect of capital
receipts. This is based on an assessment provided by the Special Projects Team
in January 2024. A 10% variation equates to £0.075m and this would require to
be managed across the capital programme. 
3.2.11 General feedback from Scotland Excel and the Project Managers indicates that
price increases and uncertainty continue to be experienced as well as disruptions
to the supply chain and longer lead times, particularly in relation to the
construction sector and material availability.
3.2.12 The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all influence the overall contract price and make it
extremely challenging to manage expenditure and the availability of supply.
3.2.13 While it has been possible to estimate the impact of these pressures on some
projects, and therefore either include those projections within the capital
monitoring report or adjust the capital programme accordingly, for others it is
more difficult, and no forecast has been projected at this stage but there are likely
to be further significant financial impacts not yet reported.

Page 58

3.3 Departmental/Service Risks 
3.3.1 The detail of each departmental financial risk is included within Appendix 1. The
following table provides a summary of the number of risks within each department
and likelihood category with the financial impact. 
Department 1 - Remote 2 - Unlikely 3 - Possible 4 - Likely 5 - Almost
Certain Total
No £000 No £000 No £000 No £000 No £000 No £000
Chief
Executive's
Unit 
0 0  0  0  0  0  0  0  0  0  0  0
Executive
Director
Douglas
Hendry 
2 20  6  560  9  730  3  435  0  0  20  1,745
Executive
Director Kirsty
Flanagan 
4 285  2  140  15  4,373  2  250  0  0  23  5,048
Total 6 305 8 700 24 5,103 5 685 0 0 43 6,793 
3.3.2 The current top three risks in terms of the financial impact are noted in the table
below. 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Roads and
Infrastructure
Services
Roads
Maintenance –
Roads, Bridges,
Culverts & Sea
Defences
Extreme localised weather may
result in loss of road access,
bridges, culverts, road or sea
defence.
3 1,500
Roads and
Infrastructure
Services
Waste PPP -
Indexation
Historical payments made
towards Waste PPP based on
indexation rates have been
challenged by Renewi resulting
in a potential cost to the council.
3 586
Financial
Services
Council Tax Debt
Collection
Recovery
Recovery of debt becomes more
difficult to pursue in the current
economic climate. This is in
relation to historical debt that
has accumulated over many
years therefore any adverse
collection rates will impact on
the year end debt provision as
opposed to the in-year financial
position, hence no forecast
3 345

Page 59

variance has been reported
within the current year.   
3.3.3 The risks which are likely, are noted below: 
SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL
IMPACT
£000
Council Wide
- Commercial
Services
Council Wide
Central Repairs
Increased demands on
central repair budgets
(CRA) due to a decrease in
Capital funding, increase in
statutory and emergency
repairs and increases in
supplier/contractor charges.
This impacts on all
departments of the Council
with a Central Repairs
Budget.
4 300
Development
and
Economic
Growth
Homelessness
Temporary
Accommodation
Income
Unpredictable number of
Homeless applications.
Inability to recover rent.
Increase costs of property
maintenance and tenancy
change over.
4 150
Roads and
Infrastructure
Services
Fleet
Maintenance
Increased costs to maintain
internal fleet due to
inflationary increases on
vehicles parts.
4 100
Legal and
Regulatory
Support
NPDO –
Increase in
insurance costs
within NPDO
Schools
Increase in insurance costs
as a result of the long-term
effects of Covid-19 on the
insurance market and flood
claims.
4 75
Legal and
Regulatory
Support
Elections More than 1 by-election
required outwith standard
election cycle.
4 60 
3.4 Changes to Financial Risks since last report 
3.4.1 There have been 3 changes to the departmental risks since the financial risks
report was presented to the Policy and Resources Committee on 15 August 2024:

Page 60

- A new ‘possible’ risk of £0.316m relating to charitable relief for Arms
Length External Organisations (ALEO) to recognise that a review being
undertaken by the Scottish Government may impact the charitable relief for
ALEO’s.
- The risk in relation to Waste - Compost Like Output (CLO) has increased
from £0.164m to £0.311m as per information received on stockpiles. There
is still ongoing legal negotiations, levels could fluctuate and will be
monitored over the financial year, hence why no variance has been
reported at this time.
- The risk in relation to Roads Maintenance – Roads, Bridges, Culverts &
Sea Defences has increased from £0.750m to £1.500m to include the
increased risk of landslides as well as other weather related incidents.
3.5 Monitoring of Financial Risks
3.5.1 Financial risks will be reviewed and monitored on a two monthly basis and will be
included in the pack of financial reports submitted to Policy and Resources
Committee.
3.6 Potential Future Risks
3.6.1 Scottish Government are, over the next 2 years, proposing to extend funded
childcare to all 1 and 2 year olds across Scotland. This brings significant financial
and qualitative risks to the service. The needs and legislative requirements for this
age range would mean significant capital work across our estate and in many
settings there is not the space so extensions would be required. Having this age
range in the same play space as 3/4 year olds seriously impacts on the ability of
practitioners to effectively support age appropriate learning and play. It is
uncertain when this risk will arise.
3.6.2 The Council’s bid to the Scottish Governments Learning Estate Investment
Programme (LEIP) for funding for a new school campus on Mull was successful
and a report was considered by Council on 24 April 2024. Approval was granted
to utilise £5m of £9m previously earmarked funds to develop the Business Case.
The Scottish Government will fund up to 50% of eligible costs and the estimated
cost is £43m, with £41m deemed eligible, however these are just estimates at this
stage. Potential future risks could arise in relation to site selection, design,
construction and associated borrowing costs.
3.6.3 In its present configuration, Argyll and Bute Council’s digital network does not
have the capacity to accommodate the requirements of the Education Services
vision nor the Scottish Government’s vision for digital access over the next four
years, including a device for every learner, which would entail a large increase in
the number of devices accessing the network. The network requires to be
redesigned to allow digital access on the scale proposed by the Scottish
Government. In addition to investment in bandwidth, device management and
protection, there is a requirement to replace existing network hardware in all
schools. Following an independent consultation on the network by Insight, IT and

Page 61

Education have co-authored a paper “Resourcing Educations Digital Aspirations”
that identifies the work required to meet the Scottish Governments expectations.
COSLA have raised this issue with the Scottish Government and there is an
expectation that this will be fully funded as it is a Scottish Government
commitment but there remains a risk associated with this.
4 CONCLUSION 
4.1 This report summarises the key financial risks facing the Council. There are 7
Council wide risks and 43 departmental risks identified with 5 categorised as
likely. The financial risks are monitored routinely and actions put in place to
continue to mitigate the risks.
5 IMPLICATIONS 
5.1 Policy - None.
5.2 Financial - The financial value of each risk is included within the
appendix.
5.3 Legal - None.
5.4 HR - None.
5.5 Fairer Scotland Duty - None.
5.5.1 Equalities – protected
characteristics -
None.
5.5.2 Socio-economic Duty - None.
5.5.3 Islands - None.
5.6 Climate Change - None.
5.7 Risk - Financial risks are detailed within the appendix.
5.8 Customer Service - None.
5.9 The Rights of the Child
(UNCRC) -
None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
6 September 2024
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services
APPENDICES
Appendix 1 – Detail of Department/Service financial risks 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 62

APPENDIX 1 
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 AUGUST 2024 
As at 30 June 2024 As at 31 August 2024
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE 
LIKELIHOOD
FINANCIAL
IMPACT
£000 
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Commercial Services Catering Costs - Provision of
Meals to Early Years Children
The Children and Young People (Scotland) Act placed duties
on Councils to provide meals in an Early Years setting to
entitled children where sessions span over lunch time. The
total quantum of grant funding is reducing and may not be
sufficient to fund the additional costs depending on uptake
and the additional costs to support the meal provision in
partner provider settings.
Joint strategy with procurement colleagues to reduce
potential impact of supplier charges. Control food
wastage/portion controls.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Catering Purchases Increased supplier charges and higher than average inflation
on food costs. In addition to this the Scottish Government
reviewed the regulations that govern the food and drinks
provided in schools and implemented revised regulations.
The revised standards focus on reducing sugar, reducing red
processed meat and increasing fibre. Thus far, there has
been an increase in costs in produce and a reduction in
demand for school meals.
Joint strategy with procurement colleagues to reduce
potential impact of supplier charges. Control food
wastage/portion controls; introduction of online ordering to
help manage food waste. Analysis and regular review of
menu choices.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Catering - Implementation of
Universal Free School Meals in
Primary Schools for P6 and P7
pupils
The Scottish Government may not give the local authority
adequate funds to support the policy to expand free school
meals in primary schools to include P6 and P7 pupils (the
scheme has already been implemented for P1 to P5 pupils).
Additionally, In 2023-24 Special Schools and Learning
Centres received FSM to S6 Level. Although expansion
paused for full implementation for P6&7, FSM will be
expanded through entitlement to Scottish Child Payment
and will be implemented in February 2025.
Senior Manager connected into the ASSIST FM Committee
and will continue to ensure the Council's viewpoint will be
considered.
2 100 2 100
Executive Director
Douglas Hendry
Commercial Services Rental Income from Properties Due to current economic climate, there may be reduced
ability to recover rental income from leased properties or
place suitable tenants in properties as leases come to an
end.
Management of leasehold properties by Estates team, any
issues with debt recovery being dealt with in line with
Council debt recovery policy.
2 60 2 60
Executive Director
Douglas Hendry
Commercial Services Surplus Properties Ongoing market difficulties lead to increased numbers of
surplus properties, in addition, as Our Modern Workspace
Project gains traction more properties will become surplus
to operational requirements. There are residual running
costs associated with all surplus properties.
One Council property team in place who will monitor market
conditions and work with prospective tenants/ purchasers to
let/sell surplus properties.
3 50 3 50
Executive Director
Douglas Hendry
Commercial Services Leisure Service Level
Agreements
Increase in RPI and/or other running costs (eg utilities,
payroll etc) resulting in requests for additional funding.
Monitoring annual alteration to contract RPI rate,
communication with service providers and mitigation
through financial forecasting and review of existing budget.
3 50 3 50
Executive Director
Douglas Hendry
Council Wide -
Commercial Services
Council Wide Central Repairs Increased demands on central repair budgets (CRA) due to a
decrease in Capital funding, increase in statutory and
emergency repairs and increases in supplier/contractor
charges. This impacts on all departments of the Council with
a Central Repairs Budget.
Joint strategy with procurement colleagues to reduce
potential impact of supplier/contractor charges. Close
monitoring of central repairs budgets and commitments and
instructing only statutory tests/inspections and essential
repairs.
4 300 4 300

Page 63

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE 
LIKELIHOOD
FINANCIAL
IMPACT
£000 
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Education ASN Support Demand for ASN support continues to increase. Scottish
Government statistics suggest a 3% year on year increase,
resulting in an additional resource requirement. Particularly
where gaps in our enhanced provision exist. The medium-
term detriments on the development of young children
which occurred as a consequence of service closures during
the COVID pandemic have increased demands on the service
as children require additional support to catch up. The
Additional Support for Learning National Implementation
plan continues to inform our strategic direction in line with
the Angela Morgan Review.
Service is currently looking at alternative options for service
delivery to mitigate the inescapable pressures. Continuing to
ensure robust assessment of needs, monthly monitoring of
budget, any delays in recruitment factored into projections
to enable informed decision making on allocation of funding
for new/amended /additional support packages. Following a
full ASN review, the service are currently investing in the
development of four new learning centres in order to
provide greater equity in meeting the more complex needs
of some learners as well as considering plans to develop
enhanced wellbeing resources across our learning estate in
future. This aims to reduce the frequency of children having
to be educated in high cost out of area placements.
3 200 3 200
Executive Director
Douglas Hendry
Education Pre-Five Units - retention of
partner providers
Failure in the commissioning or retention of pre-five partner
provider units to deliver 1140 hours would result in an
increased pressure on the Council to deliver the service.
Annual financial appraisal; Support network; Short-term cash
injections.
3 100 3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Children and Young People
(Scotland) Act - ELC 1140 hours
The Council has been required to deliver 1140 hours of Early
Learning and Childcare since August 2021. The Scottish
Government has committed to funding this and the Council
has revised its service model to align it to the Scottish
Government's reduced funding profile. A risk remains that
actual costs of delivery exceed the Government Grant in any
given year. For example, if child numbers are higher than
estimated, this may require additional staffing which has not
been built included in the staffing model funded by Scottish
Government. Scottish Government has included within
scope for this parliamentary session plans to further expand
on eligibility for 1140 hours to all 2 year olds and some one
year olds. As yet there has been no funding commitment.
However this will place unknown cost pressures on both our
capital and revenue budgets
Continuous monitoring and review of the service model,
usage and resources.
3 100 3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Education (Scotland) Act
The Education (Scotland) Act 2000 requires Councils to
undertake assessments of the need for the provision of
Gaelic Medium Primary Education (GMPE) and the duty to
support and promote Gaelic Education. This may lead to
additional staffing requirements depending upon the
demand for Gaelic from parents.
Continuous monitoring and review of the service model and
resources available within budget.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Hub DBDA/DBFM Schools -
Litigation
Increased risk of the requirement to litigate to conclude final
capital contract payments due.
Monitoring claims and mitigation through robust challenge
of any additional claims.
2 150 2 150
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Contract RPI for NPDO and Hub
Schools
Increase in RPI would result in higher costs. Monitoring annual alteration to contract RPI rate and
mitigation through financial forecasting and review of
existing budget.
3 100 3 100

Page 64

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE 
LIKELIHOOD
FINANCIAL
IMPACT
£000 
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO - Increase in insurance
costs within NPDO Schools
Increase in insurance costs as a result of the long-term
effects of Covid-19 on the insurance market and flood
claims.
Monitoring annual alteration to contract insurance rate and
mitigation through financial forecasting and review of
existing budget.
4 75 4 75
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Elections More than 1 by-election required outwith standard election
cycle.
Outwith direct management control. 4 60 4 60
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services - Litigation Increased number of litigation cases. Ensure Legal Services are gateway to access all legal advice
and that advice is sought at earliest opportunity.
3 50 3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO/Hub DBFM contract
management efficiencies
Reduction in ability to generate contract management
efficiencies.
Monitoring annual efficiencies generated and mitigation
through robust contract management and application of
contract specifications / requirements.
2 50 2 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Licensing Reduced numbers of licensing applications leading to
reduced income.
Monitoring of trends and reporting the financial impact in
the budget monitoring.
3 30 3 30
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Children's Panel Increased number of referrals increasing costs through
increases in the running costs.
Maximise the use of council facilities/resources for panel
session in the first instance.
1 10 1 10
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services Failure to minimise Council wide use of external legal advice. Ensure legal services are gateway to access all legal advice. 1 10 1 10
Executive Director
Kirsty Flanagan
Customer Support
Services
Software Licences Potential risk of being under licensed for software which will
be identified via software audits which would incur
additional costs.
ICT security and compliance officer in post and duties include
review of systems to ensure fully licenced.
2 100 2 100
Executive Director
Kirsty Flanagan
Customer Support
Services
Additional Bandwidth for
Education
Additional costs required to be incurred in relation to
additional bandwidth required to deliver the Education
Digital Strategy due to a more digitalised learning
curriculum.
Work closely with Education on Digital Devices for All
strategy to ensure necessary IT is in place.
3 50 3 50
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Homelessness Temporary
Accommodation Income
Unpredictable number of Homeless applications. Inability to
recover rent. Increase costs of property maintenance and
tenancy change over.
Provision of Housing Options information and advice service
to minimise number of applicants proceeding to full
homeless application. Implementation of Rapid Rehousing
Plan.
4 150 4 150
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Dangerous Buildings
interventions
Building Standards having to deal with an increasing level of
dangerous building work which has significant financial
implications for Council.
Monitor activity and seek to recover costs from the owner. 3 100 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning Fee Penalties Potential that the Scottish Government may sanction
penalties due to poor performance by the Planning
Authority. The Scottish Government has recently appointed
a national Planning Performance Champion however the
detail of how this role intends to incentivise
improvement/penalise poor performance at a local
authority level remains unclear at this time
Maintain high levels of performance as articulated by
performance markers detailed in Planning Performance
Framework annual report.
1 100 1 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fee shortfalls Due to downturn in economic / building activity, in
particular renewable energy development and other major
developments could lead to planning fee income shortfalls
leading to revenue budget pressures.
Current income levels are looking more positive, however,
we are dependent on some high value applications coming
in which, if they don't materialise, will impact the overall
position. Will continue to monitor Development
Management income and expenditure tightly and investigate
further income generation streams.
3 100 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Building Warrant fee shortfalls Due to loss of commercial income and downturn in
economic / building activity, building warrant fee income
shortfalls leading to revenue budget pressures.
Continue to monitor Building Standards income and
expenditure tightly and investigate further income
generation streams.
1 50 1 50

Page 65

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE 
LIKELIHOOD
FINANCIAL
IMPACT
£000 
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Environmental Health- export
certificates
Downturn in requests for export certificates as a result of UK
withdrawal from EU, changes to international trading
agreements or business economy. Reduction in demand
creates a budget pressure on environmental health budget.
Monitor income and resources required for export health
certificates / attestations required to support the export
market. Continue with food safety regulation activities
associated and support at 3rd country audits. Pursue debt
rigorously with key customers through seeking regular
payments.
2 40 2 40
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Animal Health Carrying out livestock seizure to protect welfare of the
animals
Monitor activity and seek to recover costs from the disposal
of the animals.
1 10 1 10
Executive Director
Kirsty Flanagan
Financial Services Council Tax Debt Collection
Recovery
Recovery of debt becomes more difficult to pursue in the
current economic climate. This is in relation to historical
debt that has accumulated over many years therefore any
adverse collection rates will impact on the year end debt
provision as opposed to the in-year financial position, hence
no forecast variance has been reported within the current
year.
Robust monitoring of arrangements with debt collection
agency and performance against target collection rates.
3 345 3 345
Executive Director
Kirsty Flanagan
Financial Services NDR Aleo Baseline Scottish Government are going to undertake a review the
current Arms Length External Organisations (ALEO) baseline
for 2024-25 which could increase the pressure on the
balance of costs vs relief.
Outwith direct management control.   3 316
Executive Director
Kirsty Flanagan
Financial Services Housing Benefit Subsidy Loss of Housing Benefit Subsidy due to exceeding LA error
threshold.
Processes in place for handling of claims accurately and
efficiently.
1 125 1 125
Executive Director
Kirsty Flanagan
Financial Services Sundry Debt Recovery Recovery of debt becomes more difficult to pursue in the
current economic climate.
Additional staff are being put in place in the Sundry Debt
Team who will work jointly with Legal Services to enhance
the robustness of the Council's debt recovery processes.
3 85 3 85
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Roads Maintenance - Roads,
Bridges, Culverts & Sea
Defences
Extreme localised weather may result in loss of road access,
bridges, culverts, road or sea defence.
Routine inspections to deal with potential weak areas -
based on a stitch in time repair regime.
3 750 3 1,500
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Waste PPP - Indexation Historical payments made towards Waste PPP based on
indexation rates have been challenged by Renewi resulting
in a potential cost to the council.
Conversations are in place between Council and Renewi with
the aim of minimising the potential impact.
3 586 3 586
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Roads Maintenance - Roads
Network
Adverse weather conditions result in deterioration of the
road network necessitating greater spend on repair of
defects.
Manage maintenance budgets to ensure that spend is
prioritised to deal with safety defects.
3 230 3 230
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Car Parking Income Reduced number of visitors to the area and use of council
owned car parks resulting in a reduction in income.
Closely monitor income levels throughout the year,
especially in high visitor seasons.
3 200 3 200
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Piers & Harbours Income Changes to ferry services resulting in reduced berthing and
passenger income.
Closely monitor passenger number information coming from
CalMac to identify any emerging trends with reducing
passenger numbers.
3 200 3 200
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Waste - Compost Like Output
(CLO)
Compost Like Output is an element of waste that has been
heat treated and can only be used for landfill site
restoration. Renewi are currently producing more CLO than
we need and it is building up in our landfill sites - this has
been flagged up as a concern by SEPA and will need to be
removed.
Discussions ongoing with Renewi and the Council on steps
forward and what element the council is responsible for.
3 164 3 311
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Winter Maintenance Adverse weather conditions which require greater than
budgeted number of gritting runs.
Monitor weather conditions and apply gritting policy to
minimise costs.
3 150 3 150

Page 66

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE 
LIKELIHOOD
FINANCIAL
IMPACT
£000 
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Street Lighting Age of lighting stock requires greater maintenance as health
and safety becomes a consideration.
Manage maintenance budgets to ensure that spend is
prioritised to deal with safety defects.
3 100 3 100
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Ferry Services Grant from Transport Scotland covers the cost of running
the ferry services within Argyll and Bute which has not been
increased for 2024-25 which could result in additional costs
for the Council to fund the Ferry services.
Closely monitoring financial position throughout the year to
highlight any potential pressures. Discussions will continue
to take place with Transport Scotland on an annual basis to
request additional funding that is required for that year.
3 100 3 100
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Fleet Maintenance Increased costs to maintain internal fleet due to inflationary
increases on vehicle parts.
Review of Fleet underway to determine where reductions
could possibly be made.
4 100 4 100     
42 5,580 43 6,793

Page 67

ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
CAPITAL BUDGET MONITORING REPORT – 31 AUGUST 2024 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the position of the capital budget as at 31 August
2024. The report provides information on the financial position in respect of the capital
plan and the performance in terms of delivery of capital plan projects. 
1.2 Financial Position: 
• Current Year to Date – actual net expenditure to date is £10,648k compared
to a budget for the year to date of £10,659k resulting in an underspend for the
year to date of £11k (0.10%).
• Forecast Outturn for 2024-25 – forecast net expenditure for the full financial
year is £36,248k compared to an annual budget of £37,007k giving rise to a
forecast underspend for the year of £759k (2.05%).
• Total Capital Plan – forecast total net project costs on the total capital plan
are £192,882k compared to a total budget for all projects of £192,791k giving
rise to a forecast overspend for the overall capital plan of £91k (0.05%).
1.3 Project Delivery: 
• Asset Sustainability – Out of 85 projects there are 81 projects (95%) on
track, 1 project (1%) off track but recoverable and 3 projects (4%) off track.
• Service Development - Out of 43 projects there are 41 projects (95%) on
track, 2 projects (5%) off track but recoverable and no projects are off track.
• Strategic Change – Out of 22 projects there are 18 projects (82%) on track,
1 project (5%) off track but recoverable and 3 projects (14%) off track. 
1.4 The Capital Programme is funded by various income streams as detailed in Appendix
5. Additional funding has been added: Strategic Housing Fund Contribution, Priority
Investment Fund and contributions from reserves. 
1.5 The Council is projecting £750k of capital receipts this financial year. The estimated
level of receipts will be kept under review as market conditions change, as will values
following due diligence undertaken by prospective purchasers on the condition of
asset.

Page 68

ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
CAPITAL BUDGET MONITORING REPORT – 31 AUGUST 2024 
2.0 INTRODUCTION 
2.1 This report provides an update on the position of the capital budget as at 31 August
2024. The report provides information on the financial position in respect of the capital
plan and the performance in terms of delivery of capital plan projects.
2.2 Following the decision at Policy and Resources Committee on 9 December 2021, the
Rothesay Pavilion project was put on pause whilst potential funding options were being
considered. At the budget meeting in February 2023 additional funding was allocated to
this project which will allow the project to progress towards success by supporting
completion of certain work stages. The financial information included within this report
now includes amounts relating to Phase 1 of the Rothesay Pavilion project. 
2.3 Surveys have been completed in the Councils Learning Estates in relation to
RAAC with only 1 building confirmed as having it present with steps underway for its
removal. This will include a decant of the students for approximately 9 months plus total
removal and replacement of the roof during 2024. Funding of £3m was allocated as part
of the 2024-25 budget setting process. Additional funding of £406k has been allocated
via the Capital Contract Increase Fund to meet the now increased contract costs.
2.4 The Councils bid to the Scottish Governments Learning Estate Investment Programme
(LEIP) for funding for a new school campus on Mull was successful. While this is good
news and will provide welcome investment in the school estate it does come with a
financial pressure that is required to be funded if the project is to proceed. The Scottish
Government will fund up to 50% of eligible costs therefore the Council will be required
to fund circa £20m. At April Council it was agreed to commence the Business Case,
undertake engagement, commence site selection processes and establish governance
arrangements. Any future capital budget provision will be built into future budget
estimates and approved as part of the budget setting process. 
2.5 A £1m cost pressure was identified during 2021-22 in relation to repairs to the A884
Ardbeg Sea Wall, where severe storm damage resulted in failure of the sea wall on
Bute. Emergency works were carried out and a permanent solution is currently being
developed. Additional funding of £1m was allocated for this purpose at the Council
meeting on 24 February 2022 however there remains a risk that costs will exceed this.
Feasibility report underway to progress the permanent works and estimated costs. 
2.6 The impact of the pandemic along with the UK exit from the European Union, the
Russian invasion of Ukraine and sanctions on Russian owned entities has seen
significant price increases as well as disruptions to the supply chain and longer lead in
times. The increased rate of inflation impacts costs such as energy prices, labour,
packaging and transport. These all have an effect on the overall contract price and make
it extremely challenging to manage expenditure and the availability of supply. 
2.7 As a result of this it should be noted that there are likely to be other significant financial
impacts which are not quantifiable at this stage, as follows: 
• Rothesay Pavilion – despite additional funding being awarded there remains a
funding gap to allow full completion of the original intended works.
• Harbour Investment Programme – likely to be contractual cost increases in future
years (expected to be funded from increased fees and charges).

Page 69

• In general, capital contracts across the programme are seeing significant price
increases. 
Although the direct impact of COVID on most local services has reduced or even ceased
altogether over the last 12 months, COVID-19 in conjunction with the UK exit from the
European Union and the Russian invasion of Ukraine, continues to affect worldwide
supply chains.
2.8 In recent years additional funding of £11.100m has been allocated to the capital
programme for this purpose which has mitigated the impact to date however, as detailed
in the table below. With £9.240m already allocated or committed this results in £1.860m
of the fund remaining unallocated to projects facing inflationary pressures. 
Funding for Capital Inflationary Pressures £m
COVID-19 Funding 0.257
February 2021 Budget Meeting - Capital Cost Pressures 4.646
February 2022 Budget Meeting - Capital Cost Pressures 3.900
February 2023 Budget Meeting – Capital Projects Inflation
Pressures 2.000
February 2024 Budget Meeting - Capital Cost Project Protection 0.297
Total Additional Funding Allocated to Capital 11.100
Allocated to Projects within Capital Programme (5.779)
Committed for future years (3.461)
Balance Remaining 1.860 
3.0 RECOMMENDATIONS 
3.1 Note the contents of this report and the financial summaries as detailed in Appendix 8
and approve the proposed changes to the capital plan detailed in Appendix 4.

Page 70

4.0 CURRENT YEAR TO DATE FINANCIAL POSITION 
4.1 Overall Position 
Actual net expenditure to date is £10,648k compared to a budget for the year to date of
£10,659k resulting in an underspend for the year to date of £11k (0.10%). 
4.2 Project/Department Position 
The table below shows the year to date net expenditure against the year to date budget
by project type and service: 
Project Type: 
Year to
Date
Budget
£'000 
Year to
Date
Actual
£'000 
Variance
£'000
Asset Sustainability 6,924 6,837 87
Service Development 857 933 (76)
Strategic Change 2,878 2,878 0
Total 10,659 10,648 11
Service:   
ICT 250 250 0
Education 2,721 2,754 (33)
Live Argyll 800 801 (1)
Health & Social Care Partnership 1,129 1,144 (15)
Shared Offices 159 159 0
Roads & Infrastructure 3,414 3,369 45
Development & Economic Growth 525 510 15
CHORD 1,661 1,661 0
Total 10,659 10,648 11 
Material variances are explained in Appendix 1 and there are a number of small
variances contributing to the year to date underspend.

Page 71

5.0 FORECAST OUTTURN 2024-25 
5.1 Overall Position
Forecast net expenditure for the full financial year is £36,248k compared to an annual
budget of £37,007k giving rise to a forecast underspend for the year of £759k (2.05%). 
5.2 Project/Department Position
The table below shows the forecast expenditure and budget for the year by project type and
service. 
Project Type: 
Annual
Budget
£'000 
Forecast
Outturn
£'000 
Forecast
Variance
£'000
Asset Sustainability 26,623 26,809 (186)
Service Development 6,156 6,345 (189)
Strategic Change 4,228 3,104 1,124
Total 37,007 36,258 749
Service:   
ICT 1,611 1,611 0
Education 7,790 7,835 (45)
Live Argyll 1,125 1,125 0
Health & Social Care Partnership 2,335 2,351 (16)
Shared Offices 2,596 1,798 798
Roads & Infrastructure 19,977 19,970 7
Development & Economic Growth 2,372 2,372 0
CHORD (799) (804) 5
Total 37,007 36,258 749 
Material variances are explained in Appendix 2 and there are a number of smaller variances
contributing to the forecast underspend.

Page 72

6.0 TOTAL PROJECT COSTS 
6.1 Overall Position 
Forecast total net project costs on the total capital plan are £192,882k compared to a total
budget for all projects of £192,791k giving rise to a forecast overspend for the overall
capital plan of £91k (0.05%). 
6.2 Project/Department Position
The table below shows the forecast expenditure and budget for the total capital plan by
project type and service. 
Project Type: 
Capital
Plan
Budget
£'000 
Forecast
Project
Costs
£'000 
Total
Capital
Plan
Variance
£'000
Asset Sustainability 52,674 52,581 93
Service Development 28,359 28,548 (189)
Strategic Change 111,758 111,753 5
Total 192,791 192,882 (91)
Service:   
ICT 5,934 5,934 0
Education 43,911 43,956 (45)
Live Argyll 3,037 3,037 0
Health & Social Care Partnership 3,936 3,952 (16)
Shared Offices 18,393 18,393 0
Roads & Infrastructure 61,037 61,072 (35)
Development & Economic Growth 6,929 6,929 0
CHORD 49,614 49,609 5
Total 192,791 192,882 (91) 
Material variances are explained in Appendix 3 and there are a number of smaller
variances leading to the forecast overspend.

Page 73

7.0 TOTAL PROJECT PERFORMANCE 
7.1 Overall Position 
There are 150 projects within the Capital Plan, 140 are Complete or On Target, 4 are Off
Target and Recoverable and 6 projects are Off Track. 
7.2 Project Position 
The table below shows the Performance Status of the Projects in the Capital Plan. 
Project Type: 
Complete/
On Target 
Off Target/
Recoverable
Off
Target/
Problem  Total
Asset Sustainability 81 1 3 85
Service Development 41 2 0 43
Strategic Change 18 1 3 22
Total 140 4 6 150
Service:
ICT 4 0 0 4
Education 25 1 0 26
Live Argyll 16 0 0 16
Health & Social Care
Partnership  20  0  0  20
Shared Offices 16 0 2 18
Roads & Infrastructure 36 2 4 42
Development &
Economic Growth  18  0  0  18
CHORD 5 1 0 6
Total 140 4 6 150

Page 74

50  
Problem
70
80
90      
20
30 
On
Target 
40
0
60
10
7.3 Chart of Performance Status 
The graph provides a view of the Performance Status of the Projects included in the Capital
Plan:

Page 75

8.0 OFF TRACK PROJECTS 
8.1 The Off-Track projects are noted in the table below and a variance report is included in
Appendix 6. 
Project Type Project What is Off
Track?
Explanation
Shared Offices
– Strategic
Change
Clean Energy –
NDEEF1
Current Year
Expenditure
Slippage into 2025-26.
Reprofile to forecast when
final retentions are due to
be released.
Shared Offices
– Strategic
Change
Clean Energy –
NDEEF2
Current Year
Expenditure
Slippage into 2025-26 and
2026-27. Delays in Scottish
Government issuing
framework meaning the
project is unlikely to start
until 2025-26.
RIS – Asset
Sustainability
Coast Change
Adaptation
Current Year
Expenditure
Acceleration from 2025-26.
Original 2024-25 spend
profile omitted grant monies
due to external partner from
Scottish Government. This
is a correction of the
spending profile.
RIS – Asset
Sustainability
Claonaig Slip Current Year
Expenditure
Acceleration from 2025-26
of future block allocation
RIS – Asset
Sustainability
Lighting Current Year
Expenditure
Slippage into 2025-26. 3
Schemes are not going to
progress until 2025-26.
Profile corrected to reflect
updated scheduling of
works.
RIS – Strategic
Change
LED Scheme Current Year
Expenditure
Slippage into 2025-26.
Further saving generating
upgrades are still to be
investigated so full spend will
not occur within 2024-25. 
9.0 STRATEGIC CHANGE PROJECTS 
9.1 Appendix 7 gives detailed information in respect of the Strategic Change Projects within the
Capital Plan. The appendix gives details of the forecast cost of each project against the
approved budget, the start and anticipated completion date of the project and an assessment
of the risks of the project and, if these are not green, gives an explanation of the problem.

Page 76

10.0 CHANGES TO CAPITAL PLAN 
10.1 The table below shows proposed changes to the Capital Plan at summary level which include
slippages, accelerations and virements. Explanations relating to the specific projects involved
can be seen in Appendix 4. 
The updated gross expenditure capital plan incorporating these proposed changes can be
found in Appendix 9. 
Department 
Prev.
Agreed
Changes
2024-25 
£’000 
2024-25 
£’000 
2025-26 
£’000 
2026-27 
£’000 
Future
Years 
£’000 
Total
Capital
Plan 
£’000
Asset
Sustainability 0 279 (279) 0 0 0
Service
Development 0 0 0 0 0 0
Strategic Change 0 (1,119) 834 285 0 0
Total 0 (840) 555 285 0 0 
Service:      
ICT 0 0 0 0 0 0
Education 0 0 0 0 0 0 
Live Argyll  0  0  0  0  0  0
Health & Social
Care Partnership 0 0 0 0 0 0
Shared Offices 0 (798) 513 285 0 0
Roads &
Infrastructure  0  (42)  42  0  0  0
Development &
Economic Growth 0 0 0 0 0 0
Major Projects 0 0 0 0 0 0
Total 0 (840) 555 285 0 0 
11.0 FUNDING 
11.1 The Capital Programme is funded by various income streams as detailed in Appendix 5.
Additional funding has been added: Strategic Housing Fund Contribution, Priority Investment
Fund and contributions from reserves.

Page 77

12.0 IMPLICATIONS 
12.1 Policy – Monitors progress against the capital plan. 
12.2 Financial – Monitors funding and commitments of the capital plan. 
12.3 Legal – Available funding may not address all Statutory and Regulatory requirements in
relation to Health and Safety.
12.4 HR – Available funding may have an impact on the sustainability of the Property Design Team
and Infrastructure Design Team.
12.5 Fairer Scotland Duty – None. 
12.5.1 Equalities – protected characteristics – None. 
12.5.2 Socio-economic Duty – None. 
12.5.3 Islands – None.
12.6 Climate Change – The Council is committed to addressing climate change via projects within
the capital plan. 
12.7 Risk – There are risks around increasing capital contract costs and the level and timing of
capital receipts.
12.8 Customer Service – None. 
12.9 The Rights of the Child (UNCRC) - None.
Kirsty Flanagan
Executive Director / Section 95 Officer
26 September 2024
Policy Lead for Finance and Commercial Services – Councillor Ross Moreland
APPENDICES
- Appendix 1 – Year To Date finance variance explanations
- Appendix 2 – Forecast Outturn variance explanations
- Appendix 3 – Total Project finance variance explanations
- Appendix 4 – Changes to Capital Plan and Financial Impact
- Appendix 5 – Capital Funding
- Appendix 6 - Off Track project variance reports
- Appendix 7 - Cumulative spend, completion dates and risks relating
to significant capital projects.
- Appendix 8 - Financial Summary – Overall
- Financial Summary – Executive Director Douglas Hendry
- Financial Summary – Executive Director Kirsty Flanagan
- Appendix 9 - Updated/Revised Capital Plan 
For further information contact: Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 78

APPENDIX 1 – Year to Date Financial Variance Explanations
Listed below are the projects where the variance is +/- £50k. 
Project
YTD
Budget
£’000
YTD
Actual
£’000
(Over)/
Under
Variance
£’000 
Explanation
Other variances under £50k   11 Total value of non-material variances less than +/-£50k
Total   11

Page 79

APPENDIX 2 – Outturn Variance Explanations
Listed below are the projects where the current year variance is +/- £50k. 
Project 
Annual
Budget
£’000 
Outturn
£’000
Total
(Over)/
Under
Forecast
Variance
£’000 
Explanation
Clean Energy – NDEEF 1 222 124 98 Slippage into 2025-26. This is a correction of the spending profile in line with
anticipated payment of retentions.
Clean Energy – NDEEF 2 590 0 590 Slippage into 2025-26 and 2026-27. Delays in Scottish Government issuing
framework meaning unable to start project until 2025-26.
Coastal Change Adaptation 67 147 (80) Acceleration from 2025-26. Original 2024-25 spend profile omitted grant monies
due to external partner from Scottish Government. This is a correction of the
spending profile.
Claonaig Slip 1,142 1,600 (458) Acceleration into 2024-25. Acceleration of future year’s block allocation to fund
Claonaig Slip.
Lighting 694 325 369 Slippage into 2025-26. 3 Schemes are not going to progress until 2025-26.
Profile corrected to reflect updated scheduling of works.
Street Lighting LED
Replacement
621 300 321 Slippage into 2025-26. Further saving generating upgrades are still to be
investigated so full spend will not occur within 2024-25.
Net Zero 366 256 110 Slippage into 2025-26 and vired to NDEEF1. See NDEEF1 variance report for
details.
Lochgilphead Depot
Rationalisation 15 115 (100) Acceleration from 2025-26 RIS Block allocation to fund the feasibility studies.
Other variances under £50k   (91) Total value of non-material variances less than +/-£50k.
Total   759

Page 80

APPENDIX 3 – Total Project Finance Variances
Listed below are the projects where the total project variance is +/- £50k. 
Project 
Capital
Plan
Budget
£’000 
Forecast
Project
Costs
£’000
Total (Over)/
Under
Forecast
Variance
£’000 
Explanation
Other variances under £50k   (91) Total value of non-material variances less than +/-£50k. Project Managers are working to
reduce these small individual overspends by identifying underspends elsewhere within the
capital plan.
Total   (91)

Page 81

APPENDIX 4 – Changes to Capital Plan and Financial Impact
OVERALL COST CHANGES 
Project 2024-25
£’000
2025-26
£’000
2026-27
£’000
Future
Years
£’000
Total
Capital
Plan £’000 
Recommendation  Explanation
Net Zero (110)     Vire and slip budget
into NDEEF
The additional works carried out in NDEEF1
contributes to lowering the Council’s carbon
footprint and as such could have been part of
the Net Zero project. Request for budget to
be vired to NDEEF1
Clean Energy - NDEEF1  110    Additional budget
rec’d from Net Zero
Budget from Net Zero to cover the additions
scope of NDEEF1. See NDEEF1 Variance
Report
Total Cost Changes (110) 110 0 0 0   
SLIPPAGES AND ACCELERATIONS
Project
2024-
25
£’000
2025-
26
£’000
2026-
27
£’000
Future
Years
£’000
Total Capital
Plan
£’000
Recommendation Explanation
Clean Energy – NDEEF1 (98) 98   0 Slip budget from
2024-25
Slippage into 2025-26. This is a correction
of the spending profile in line with
anticipated payment of retentions.
Clean Energy – NDEEF2 (590) 305 285  0 Slip budget from
2024-25
Slippage into 2025-26 and 2026-27. Delays
in Scottish Government issuing framework
meaning unable to start project until 2025-
26.
Coastal Change Adaptation 80 (80)   0 Accelerate 2025-26
budget into 2024-25
Acceleration into 2024-25. Original 2024-25
spend profile omitted grant monies due to
external partner from Scottish Government.
This is a correction of the spending profile.
Claonaig Slip / Block Allocation 458 (458)    Accelerate 2025-26
budget into 2024-25
Acceleration into 2024-25. Acceleration of
future year’s block allocation to fund
Claonaig Slip.
Lighting (369) 369   0 Slip budget from
2024-25
Slippage into 2025-26. 3 Schemes are not
going to progress until 2025-26. Profile
corrected to reflect updated scheduling of
works.
LED Scheme (321) 321   0 Slip budget from
2024-25
Slippage into 2025-26. Further saving
generating upgrades are still to be
investigated so full spend will not occur
within 2024-25.

Page 82

Lochgilphead Depot Rationalisation /
Block Allocation
100 (100)    Accelerate 2025-26
budget into 2024-25
Acceleration from 2025-26’s RIS Block
Allocation to fund feasibility studies.
Depot Rationalisation / Block
Allocation
10 (10)    Accelerate 2025-26
budget into 2024-25
Acceleration from 2025-26’s RIS Block
Allocation to fund feasibility studies.
Total Slippages and Accelerations (730) 445 285 0 0  
Net Impact of Changes (840) 555 285 0 0

Page 83

CAPITAL PROGRAMME FUNDING Appendix 5 
2024-25 2025-26 2026-27
Estimated
Capital
Funding
Carry
Forwards
from 23-24
Slippage /
Acceleration 
Additional
Funding 
Updated Capital
Funding Available
Estimated
Capital
Funding
Carry
Forwards
from 23-24
Slippage /
Acceleration 
Additional
Funding
Updated
Capital
Funding
Available
Estimated
Capital
Funding
Carry
Forwards
from 23-24
Slippage /
Acceleration 
Additional
Funding
Updated
Capital
Funding
Available
General Capital Grant 9,042 0 0 0 9,042 9,069 0 0 629 9,698 8,834 0 0 0 8,834
Capital Grant - Area Control Accounts 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Transfer to Revenue for Private Sector Housing Grant (PSHG) -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033 -1,033 0 0 0 -1,033
Capital Receipts 750 -138 0 0 612 750 0 0 0 750 400 0 0 0 400
Flooding Allocation 156 0 0 0 156 156 0 0 0 156 0 0 0 0 0
Ring Fenced Capital Grant 379 0 0 0 379 618 650 0 0 1,268 0 0 0 0 0
Restricted Funding 2,553 5,140 0 1,846 9,539 84 6,573 0 28 6,685 0 0 0 0 0
Funded by Reserves 10,061 2,342 -18 3,358 15,743 1,412 -92 -80 1,506 2,746 -38 0 0 0 -38
Additional Funding from Revenue 0 0 0 4 4 0 0 0 0 0 0 0 0 0 0
Insurance 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Harbour Investment Programme 24,110 -60 0 0 24,050 39,000 -5,750 0 0 33,250 17,585 7,112 0 0 24,697
Prudential Borrowing 17,567 -1,334 -782 0 15,451 166 1,600 635 0 2,401 376 -803 285 0 -142
Loans Fund Review 431 0 0 0 431 0 0 0 0 0 0 0 0 0 0
COVID Funding 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 
64,016 5,950 -800 5,208 74,374 50,222 2,981 555 2,163 55,921 26,124 6,309 285 0 32,718 
BREAKDOWN OF ADDITIONAL FUNDING 
Additional Funding 2024-25 2025-26 2026-27 Reported Source
Capital Contract Increase Fund 706 28  June - 2024-25 Restricted Funds
Transport Scotland Active Travel  395  June - 2024-25 Scottish Government
Nature Restoration Fund  234  June - 2024-25 Scottish Government
Strategic Housing Fund Contribution 250   June - 2024-25 Restricted Funds
Inward Investment Fund allocation to RGD Projects 16   June - 2024-25 Restricted Funds
Revenue Contribution 4   June - 2024-25 Revenue
Weather Event - reserves funded 2,922 1,100  July - 2024-25 Earmarked Reserves
Islands Fund, PBI, Crown Estates allocation to RGD Projects 800   July - 2024-25 Restricted Funds
RAAC Investigation  406  July - 2024-25 Earmarked Reserves
Strategic Housing Fund Contribution 74   Aug - 2024-25 Restricted Funds
Priority Investment Fund 186   Aug - 2024-25 Reserves
Reserves - Gartbreck 250   Aug - 2024-25 Reserves
5,208 2,163 0

Page 84

OFF TRACK PROJECT Appendix 6
Project Name: Clean Energy - NDEEF1 Project Manager: Craig Houston Risk: Med
Initial Start Date: Proposed End Date:
How was this project initially funded?
Council Reserves
Please detail any additional funding.
Council reserves
Virements from other Capital Budgets
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Clean Energy - NDEEF1 profile has been updated to reflect the additional scope of works and retentions.
What has caused the issue outlined above?
The scope of the project increased, with additional works added to install LED lights at Tarbert School. NDEEF1 contributes to lowering the Council’s carbon
footprint and achieving Net Zero, so to cover the additional costs, funds will be vired from the Net Zero budget line that is already within the Capital Plan. As
such the budget from Net Zero and existing NDEEF1 budget is slipped out of 2024-25 into 2025-26.
What action will be taken to rectify this issue?
Virement of budget from Net Zero to NDEEF1 is requested and profile updated to reflect when retentions are due to be paid.
What are the implications of the action proposed?
Overspend funded and project back on track.

Page 85

OFF TRACK PROJECT Appendix 6
Project Name: Clean Energy - “NDEEF2” Project Manager: Craig Houston Risk:Low
Initial Start Date: TBC Proposed End Date: TBC
How was this project initially funded?
Earmarked reserves
Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Slippage from 2024-25 into 2025-26 and 2026-27
What has caused the issue outlined above?
What is provisionally called “NDEEF2” is a new Scottish Government Framework that will replace that which was followed for the delivery of NDEEF1. There
has been a delay in the new framework being made available to the Council and as such it has not been possible to progress the project. If framework
becomes available in November as is currently expected, consultancy will take place over the following 6 months with project expenditure expected in 2025-26
and 2026-27.
What action will be taken to rectify this issue?
Budgets slipped into 2025-26 and 2026-27 to reflect delays in framework being issued.
What are the implications of the action proposed?
Delays in progressing “NDEEF2” while framework is developed and timeline extension required for climate change earmarked reserve.

Page 86

OFF TRACK PROJECT Appendix 6
Project Name: Coastal Change Adaptation Project Manager: Elsa Simoes Risk: Low
Initial Start Date: 2021-22 Proposed End Date: Ongoing
How was this project initially funded?
Specific General Capital Grant
Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Acceleration of budget from 2025-26 into 2024-25.
What has caused the issue outlined above?
When setting spend profile for 2024-25, the payment of grant monies to Luing Community for their approved Coastal Change Adaptation case study was
omitted. As such, the budget for Luing was sitting within 2025-26 and acceleration required to correct this as payment has been made to Luing.
What action will be taken to rectify this issue?
Accelerate budget from 2025-26 into 2024-25.
What are the implications of the action proposed?
Profile correction only.

Page 87

OFF TRACK PROJECT Appendix 6
Project Name: Claonaig Landslip Project Manager: Elsa Simoes Risk:Low
Initial Start Date: 2020-21 Proposed End Date: To be confirmed
How was this project initially funded?
General Capital Grant
Capital Contract Increase Fund
Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Acceleration of future years budget into 2024-25.
What has caused the issue outlined above?
Project was to be part funded from within the RIS Capital Programme. Budget accelerated from 2025-26 Block Allocation to allow works to progress in 2024-25.
What action will be taken to rectify this issue?
Bugdet accelerated from 2025-26 Block Allocation.
What are the implications of the action proposed?
No implications, funding had already been agreed and as such is solely a profiling update.

Page 88

OFF TRACK PROJECT Appendix 6
Project Name: Lighting Project Manager: Kevin McIntosh Risk: Med
Initial Start Date:
N/A
Proposed End Date:
N/A
How was this project initially funded?
General Capital Grant
Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Slippage of current year forecasted expenditure.
What has caused the issue outlined above?
Innellan Road Scheme - Materials purchased though installation costs slipped out of 2024-25 into 2025-26.
Kilnahew Drive Scheme - Materials purchased though installation costs slipped out of 2024-25 into 2025-26.
St Moderns Way Scheme - Materials purchased though installation costs slipped out of 2024-25 into 2025-26.
Slippage also includes budget which is still to be allocated to a scheme. This has been slipped out of 2024-25 into 2025-26. These schemes are yet to be
identified & developed.
What action will be taken to rectify this issue?
Budget will be slipped and delivery will take place within the newly projected timeframe.
What are the implications of the action proposed?
Completion of schemes delayed.

Page 89

OFF TRACK PROJECT Appendix 6
Project Name: LED Scheme Project Manager: Kevin McIntosh Risk: Low
Initial Start Date: 01/08/2016 Proposed End Date: To be confirmed
How was this project initially funded?
Prudential Borrowing
Please detail any additional funding.
Previously Reported Committee and Date: Next Reported Committee and Date:
Why is the project classified as off target?
Forecasted expenditure slipping from 2024-25 into 2025-26
What has caused the issue outlined above?
The amount being slipped is outstanding budget after the identified column and lamp replacements are installed. Further saving generating upgrades to the
LED Street Lights are to be investigated and as such the spend will not occur within 2024-25.
What action will be taken to rectify this issue?
Budget slipped into 2025-26.
What are the implications of the action proposed?
Additional revenue savings once further improvements are identified and implemented.

Page 90

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 7 
Capital Expenditure Dates Risks 
Strategic Change Projects
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Estimated
Completion
Date
Project
Risks
Identified  Explanation
Campbeltown Flood Scheme 13,748 1,780 15,925 15,925 01/08/2016 31/03/2025 Green 
CHORD Oban 7,326 500 7,905 7,905 27/10/2016 31/03/2026 Green Issues with contract close out impacting on timescales.
CHORD Rothesay 21,046 2,606 23,652 23,657 01/05/2024 31/03/2025 Green Project recommenced and awaiting Rural Growth Deal acceptance.
Harbour Investment Programme 9,295 24,093 91,335 91,335 01/04/2017 31/03/2028 Green 
Dunoon Primary 10,637 232 10,869 10,869 18/12/2014 30/04/2020 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Replacement of Oban High 2,844 406 3,250 3,250 24/04/2014 31/01/2019 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Clean Energy - NDEEF1 1,109 124 1,441 1,331 01/04/2021 31/03/2025 Green 
Clean Energy - NDEEF2 0 0 1,140 1,140 01/04/2024 31/03/2027 Green 
Street Lighting LED Replacement 3,279 300 3,900 3,900 01/08/2016 31/12/2025 Green Tender for final package of works still to be awarded.
Helensburgh Waterfront Development 24,111 281 24,392 24,392 01/04/2017 31/03/2025 Green Physically complete, retentions outstanding
TIF - Halfway House Roundabout 66 287 640 640 tbc tbc Green Scope of project still to be determined - budget to be reprofiled.
Kirn Primary School 10,085 34 10,119 10,119 24/04/2014 31/10/2017 Green Physically complete - negotiations with contractor delaying payment of final sums outstanding.
Helensburgh Office Rationalisation 11,538 300 11,838 11,838 25/04/2013 31/12/2022 Green Physically complete - project subject to legal dispute.
CHORD Dunoon 12,499 23 12,522 12,522 03/02/2012 09/03/2018 Green Physically complete - negotiations with contractor regarding potential construction defect.
Kilmory Business Park Phase 2AA 60 1,035 1,129 1,129 01/02/2022 01/09/2025 Green Development Agreement still to be concluded.
Carbon Management - Non Education 29 21 50 50 01/04/2015 31/12/2025 Green Projects being determined.
Campbeltown Office Rationalisation 595 1 596 596 01/02/2015 31/03/2019 Green Project complete in full - no further expenditure expected.
TIF - Oban Airport Business Park 505 85 590 590 22/01/2015 31/12/2025 Green 
Campbeltown Schools Redevelopment 2,092 38 2,130 2,130 16/02/2012 30/11/2018 Green Physically complete - negotiations with contractor delaying payment of financial sums outstanding.
CHORD - Helensburgh - Comet Works 0 25 25 25 01/04/2023 31/03/2025 Green Art project proposed for 24-25.
TIF - Lorn/Kirk Road 2,169 1 2,170 2,170 22/01/2015 31/03/2021 Green Project complete in full - no further expenditure expected.
Net Zero 0 256 256 366 tbc tbc Green 
Strategic Change Total 133,033 32,428 225,874 225,879 
Project Risk Classifications:
Green - Risks can be managed and are viewed as stable or reducing.
Amber - Risks are increasing but are still manageable.
Red - Risks are increasing or have increased to such an extent they may affect delivery of the project.

Page 91

ARGYLL AND BUTE COUNCIL - CAPITAL PLAN MONITORING REPORT - OVERALL COUNCIL Appendix 8 FINANCIAL SUMMARY - NET EXPENDITURE 31 August 2024 
Current Financial Year To Date 
(Over)/Under
Budget Actual Variance
£000s £000s £000s
Full Year This Financial Year 
(Over)/Under
Budget Forecast Variance
£000s £000s £000s
Total Project Costs 
(Over)/Under
Budget 2025-26 Variance
£000s £000s £000s
EXPENDITURE   
Asset Sustainability Projects
Executive Director Douglas Hendry
Executive Director Kirsty Flanagan
4,784
2,161
4,801
2,202
(17)
(41)
13,013
15,998
13,030
16,167
(17)
(169)
22,513
33,249
22,530
33,139
(17)
110
Asset Sustainability Total 6,945 7,003 (58) 29,011 29,197 (186) 55,762 55,669 93
Service Development Projects
Executive Director Douglas Hendry
Executive Director Kirsty Flanagan
25
2,437
57
2,496
(32)
(59)
193
12,384
237
12,529
(44)
(145)
15,572
46,096
15,616
46,241
(44)
(145)
Service Development Total 2,462 2,553 (91) 12,577 12,766 (189) 61,668 61,857 (189)
Strategic Change Projects
Campbeltown Schools Redevelopment
Dunoon Primary
Replacement of Oban High
Kirn Primary School
Carbon Management - Non Education
Campbeltown Office Rationalisation
Helensburgh Office Rationalisation
Clean Energy - NDEEF1
Clean Energy - NDEEF2
Net Zero
Campbeltown Flood Scheme
Street Lighting LED Replacement
Harbour Investment Programme
Harbour Investment Programme Non - PB
TIF - Lorn/Kirk Road
TIF - Oban Airport Business Park
TIF - Halfway House Roundabout
CHORD - Helensburgh - Comet Works
CHORD Dunoon
CHORD Oban
CHORD Rothesay
Helensburgh Waterfront Development
HWD - FFE (Funded by LA)
Kilmory Business Park Phase 2AA
0
0
0
0
0
0
0
0
0
0
1,211
6
1,945
0
0
0
0
0
0
0
1,623
34
0
4
0
0
0
0
0
0
0
0
0
0
1,211
6
1,945
0
0
0
0
0
0
0
1,623
34
0
4
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
38
232
406
34
21
1
300
222
590
366
1,780
621
24,050
43
1
85
287
25
23
500
2,611
281
34
1,035
38
232
406
34
21
1
300
124
0
256
1,780
300
24,050
43
1
85
287
25
23
500
2,606
281
34
1,035
0
0
0
0
0
0
0
98
590
110
0
321
0
0
0
0
0
0
0
0
5
0
0
0
2,130
10,869
3,250
10,119
50
596
11,838
1,331
1,140
366
15,925
3,900
91,292
43
2,170
590
640
25
12,522
7,905
23,657
24,392
350
1,129
2,130
10,869
3,250
10,119
50
596
11,838
1,441
1,140
256
15,925
3,900
91,292
43
2,170
590
640
25
12,522
7,905
23,652
24,392
350
1,129
0
0
0
0
0
0
0
(110)
0
110
0
0
0
0
0
0
0
0
0
0
5
0
0
0
Strategic Change Total 4,823 4,823 0 33,586 32,462 1,124 226,229 226,224 5
Total Expenditure 14,230 14,379 (149) 75,174 74,425 749 343,659 343,750 (91)
INCOME 
Asset Sustainability
Executive Director Douglas Hendry
Executive Director Kirsty Flanagan
0
(21)
0
(166)
0
145
(1,570)
(818)
(1,570)
(818)
0
0
(2,270)
(818)
(2,270)
(818)
0
0
Asset Sustainability Total (21) (166) 145 (2,388) (2,388) 0 (3,088) (3,088) 0
Service Development Projects
Executive Director Douglas Hendry
Executive Director Kirsty Flanagan
0
(1,605)
0
(1,620)
0
15
0
(6,421)
0
(6,421)
0
0
(7,741)
(25,568)
(7,741)
(25,568)
0
0
Service Development Total (1,605) (1,620) 15 (6,421) (6,421) 0 (33,309) (33,309) 0
Strategic Change Projects
Helensburgh Office Rationalisation
Dunoon Primary
Campbeltown Flood
Harbour PB
01 TIF - Lorn/Kirk Road
H'burgh CHORD Public Realm Imprv
Helensburgh Waterfront Development
HWD - FFE (Funded by LA)
Rothesay CHORD
Kilmory Business Park Phase 2AA
Kilmory Business Park Phase 2AA - HIE
CHORD - Dunoon Waterfront
CHORD - Oban
0
0
0
(1,945)
0
0
0
0
0
0
0
0
0
0
0
0
(1,945)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
(24,050)
0
0
(2,320)
0
(2,009)
(829)
(150)
0
0
0
0
0
(24,050)
0
0
(2,320)
0
(2,009)
(829)
(150)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
(349)
(137)
(270)
(91,292)
(2,057)
(570)
(7,979)
(350)
(8,854)
(829)
(150)
(10)
(1,624)
(349)
(137)
(270)
(91,292)
(2,057)
(570)
(7,979)
(350)
(8,854)
(829)
(150)
(10)
(1,624)
0
0
0
0
0
0
0
0
0
0
0
0
0
Strategic Change Total (1,945) (1,945) 0 (29,358) (29,358) 0 (114,471) (114,471) 0
Total Income (3,571) (3,731) 160 (38,167) (38,167) 0 (150,868) (150,868) 0
Net Total 10,659 10,648 11 37,007 36,258 749 192,791 192,882 (91)

Page 92

MONITORING REPORT
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR DOUGLAS HENDRY 
Appendix 8
31 August 2024
Current Financial Year To Date Full Year This Financial Year Total Project Costs
Budget Actual Variance Budget Forecast Variance Budget Forecast Variance
£000s £000s £000s £000s £000s £000s £000s £000s £000s
EXPENDITURE 
Asset Sustainability
Education 2,721 2,722 (1) 7,066 7,067 (1) 12,520 12,521 (1)
Live Argyll 800 801 (1) 1,104 1,104 0 1,741 1,741 0
Health and Social Care Partnership 1,104 1,119 (15) 3,722 3,738 (16) 4,777 4,793 (16)
Shared Offices 159 159 0 1,121 1,121 0 3,475 3,475 0
Asset Sustainability Total 4,784 4,801 (17) 13,013 13,030 (17) 22,513 22,530 (17)
Service Development Projects  
Bowmore Primary School - Pre 5 Unit 0 0 0 0 0 0 149 149 0
Clyde Cottage - 600 hour provision 0 0 0 0 0 0 556 556 0
Craignish Primary School - Pre 5 Extension 0 0 0 0 0 0 400 400 0
Iona Primary School - Pre 5 Unit 0 0 0 0 0 0 490 490 0
Islay High and Rosneath Primary School Pitches 0 0 0 0 0 0 719 719 0
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 491 491 0
Early Learning and Childcare 0 0 0 0 0 0 850 850 0
Early Learning and Childcare - 1140 Hours 0 32 (32) (12) 32 (44) 7,762 7,806 (44)
CO2 Monitoring - Covid Mitigation in Schools 0 0 0 113 113 0 192 192 0
Early Learning and Childcare - 1140 Hours - CFCR 0 0 0 0 0 0 1,379 1,379 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 38 38 0 38 38 0
Riverside Leisure Centre Refurbishment 0 0 0 0 0 0 1,246 1,246 0
Dunclutha Childrens Home 25 25 0 54 54 0 1,300 1,300 0
Service Development Total 25 57 (32) 193 237 (44) 15,572 15,616 (44)
Strategic Change Projects
Campbeltown Schools Redevelopment 0 0 0 38 38 0 2,130 2,130 0
Dunoon Primary 0 0 0 232 232 0 10,869 10,869 0
Replacement of Oban High 0 0 0 406 406 0 3,250 3,250 0
Kirn Primary School 0 0 0 34 34 0 10,119 10,119 0
Carbon Management - Non Education 0 0 0 21 21 0 50 50 0
Campbeltown Office Rationalisation 0 0 0 1 1 0 596 596 0
Helensburgh Office Rationalisation 0 0 0 300 300 0 11,838 11,838 0
Clean Energy - NDEEF1 0 0 0 222 124 98 1,331 1,441 (110)
Clean Energy - NDEEF2 0 0 0 590 0 590 1,140 1,140 0
Net Zero 0 0 0 366 256 110 366 256 110
CHORD Oban 0 0 0 500 500 0 7,905 7,905 0
CHORD Rothesay 1,623 1,623 0 2,611 2,606 5 23,657 23,652 5
CHORD - Helensburgh - Comet Works 0 0 0 25 25 0 25 25 0
CHORD Dunoon 0 0 0 23 23 0 12,522 12,522 0
Helensburgh Waterfront Deveopment 34 34 0 281 281 0 24,392 24,392 0
HWD - FFE (Funded by LA) 0 0 0 34 34 0 350 350 0
Kilmory Business Park Phase 2AA 4 4 0 1,035 1,035 0 1,129 1,129 0
Strategic Change Total 1,661 1,661 0 6,719 5,916 803 111,669 111,664 5
Total Expenditure 6,470 6,519 (49) 19,925 19,183 742 149,754 149,810 (56)
INCOME
Asset Sustainability
Education 0 0 0 (125) (125) 0 (125) (125) 0
Health and Social Care Partnership 0 0 0 (1,441) (1,441) 0 (2,141) (2,141) 0
Shared Offices 0 0 0 (4) (4) 0 (4) (4) 0
Asset Sustainability Total 0 0 0 (1,570) (1,570) 0 (2,270) (2,270) 0
Service Development Projects
Sandbank Gaelic Pre Five Unit 0 0 0 0 0 0 (485) (485) 0
Early Learning and Childcare 0 0 0 0 0 0 (918) (918) 0
Early Years 1140 Hours 0 0 0 0 0 0 (6,300) (6,300) 0
Bowmore Primary School - Gaelic Medium Grant 0 0 0 0 0 0 (38) (38) 0
Service Development Total 0 0 0 0 0 0 (7,741) (7,741) 0
Strategic Change
Helensburgh Office Rationalisation 0 0 0 0 0 0 (349) (349) 0
Dunoon Primary School 0 0 0 0 0 0 (137) (137) 0
H'burgh CHORD Public Realm Imprv 0 0 0 0 0 0 (570) (570) 0
Helensburgh Waterfront Development 0 0 0 (2,320) (2,320) 0 (7,979) (7,979) 0
HWD - FFE (Funded by LA) 0 0 0 0 0 0 (350) (350) 0
Rothesay CHORD 0 0 0 (2,009) (2,009) 0 (8,854) (8,854) 0
CHORD - Dunoon Waterfront 0 0 0 0 0 0 (10) (10) 0
CHORD - Oban 0 0 0 0 0 0 (1,624) (1,624) 0
Kilmory Business Park Phase 2AA 0 0 0 (829) (829) 0 (829) (829) 0
Kilmory Business Park Phase 2AA - HIE 0 0 0 (150) (150) 0 (150) (150) 0
Strategic Change Total 0 0 0 (5,308) (5,308) 0 (20,852) (20,852) 0
Total Income 0 0 0 (6,878) (6,878) 0 (30,863) (30,863) 0 
Net Departmental Total 6,470 6,519 (49) 13,047 12,305 742 118,891 118,947 (56)

Page 93

MONITORING REPORT Appendix 8
FINANCIAL SUMMARY NET EXPENDITURE - EXECUTIVE DIRECTOR KIRSTY FLANAGAN 31 August 2024 
Current Financial Year To Date 
(Over)/Under
Budget Actual Variance
£000s £000s £000s
Full Year This Financial Year 
Year End (Over)/Under
Budget Forecast  Variance
£000s £000s £000s
Total Project Costs 
(Over)/Under
Budget Forecast Variance
£000s £000s £000s
EXPENDITURE 
Asset Sustainability Projects
Roads & Infrastructure Services 1,927 1,968 (41) 14,729 14,898 (169) 30,071 29,961 110
Customer Support Services 234 234 0 1,269 1,269 0 3,178 3,178 0
Asset Sustainability Total 2,161 2,202 (41) 15,998 16,167 (169) 33,249 33,139 110
Service Development Projects
Preliminary design for Regional Transport projects 0 0 0 16 16 0 221 221 0
Campbeltown Old Quay 0 0 0 0 0 0 1,381 1,381 0
Fleet Management - Prudential Borrowing 1,565 1,565 0 2,152 2,152 0 4,826 4,826 0
Fleet Management 0 0 0 258 258 0 4,760 4,760 0
Public Transport Operation Vehicles 233 233 0 233 233 0 233 233 0
Oban Bus Congestion - Bus Partnership Fund 0 0 0 0 0 0 50 50 0
Lismore Ferry 0 0 0 35 35 0 672 672 0
HITRANS Ferry Fund 0 0 0 0 0 0 0 0 0
Oban Depot Development Project 0 0 0 (35) 0 (35) 2,189 2,224 (35)
Lochgilphead Depot Rationalisation 15 74 (59) 15 115 (100) 169 269 (100)
Jackson's Quarry Refurbishment 0 0 0 0 0 0 285 285 0
Depot Rationalisation 0 0 0 0 10 (10) 0 10 (10)
Witchburn Road Demolition 0 0 0 0 0 0 158 158 0
Weather Incident October 2023 83 83 0 3,208 3,208 0 4,634 4,634 0
Safe Streets, Walking and Cycling (CWSS) 0 0 0 619 619 0 4,157 4,157 0
SPT - bus infrastructure 0 0 0 25 25 0 1,430 1,430 0
Cycleways - H&L (FSPT) 0 0 0 497 497 0 3,402 3,402 0
Helensburgh Public Realm - Arts Strategy Fund 0 0 0 25 25 0 53 53 0
Town Centre Funds 65 65 0 334 334 0 4,190 4,190 0
Rural Growth Deal 272 272 0 1,068 1,068 0 1,307 1,307 0
Dunoon Cycle Bothy 43 43 0 80 80 0 563 563 0
Dunoon STEM Hub 7 7 0 2,427 2,427 0 2,558 2,558 0
Ardrishaig North Active Travel 3 3 0 49 49 0 880 880 0
Nature Restoration Fund 0 0 0 835 835 0 1,069 1,069 0
Gibraltar Street Public Realm Improvements 57 57 0 97 97 0 250 250 0
Hermitage Park 0 0 0 26 26 0 3,388 3,388 0
Glenmorag Car Park 4 4 0 4 4 0 4 4 0
Applications Projects 16 16 0 342 342 0 3,193 3,193 0
Arinagour, Coll - Site Investigation and Preliminary dev 74 74 0 74 74 0 74 74 0
Service Development Total 2,437 2,496 (59) 12,384 12,529 (145) 46,096 46,241 (145)
Strategic Change Projects 
Campbeltown Flood Scheme 1,211 1,211 0 1,780 1,780 0 15,925 15,925 0
Street Lighting LED Replacement 6 6 0 621 300 321 3,900 3,900 0
Harbour Investment Programme 1,945 1,945 0 24,050 24,050 0 91,292 91,292 0
Harbour Investment Programme - Non PB 0 0 0 43 43 0 43 43 0
TIF - Lorn/Kirk Road 0 0 0 1 1 0 2,170 2,170 0
TIF - Oban Airport Business Park
TIF - Halfway House Roundabout
0
0
0
0
0
0
85
287
85
287
0
0
590
640
590
640
0
0
Strategic Change Total 3,162 3,162 0 26,867 26,546 321 114,560 114,560 0
Total Expenditure 7,760 7,860 (100) 55,249 55,242 7 193,905 193,940 (35)
INCOME 
Asset Sustainability
Roads & Infrastructure Services (21) (166) 145 (818) (818) 0 (818) (818) 0
Asset Sustainability Total (21) (166) 145 (818) (818) 0 (818) (818) 0
Service Development Projects  
Applications Projects 0 0 0 0 0 0 (437) (437) 0
Safe Streets, Walking and Cycling 0 0 0 (376) (376) 0 (2,988) (2,988) 0
SPfT 0 0 0 (25) (25) 0 (1,268) (1,268) 0
Cycleways - H&L (FSPT) 0 0 0 (500) (500) 0 (3,502) (3,502) 0
Town Centre Funds 0 0 0 (512) (512) 0 (2,730) (2,730) 0
Rural Growth Deal 0 (15) 15 (396) (396) 0 (507) (507) 0
Dunoon STEM Hub 0 0 0 (2,050) (2,050) 0 (2,558) (2,558) 0
Ardrishaig North Active Travel 0 0 0 0 0 0 (50) (50) 0
Dunoon Cycle Bothy 0 0 0 (298) (298) 0 (563) (563) 0
Gibraltar Street Public Realm Improvements 0 0 0 0 0 0 (250) (250) 0
Hermitage Park 0 0 0 0 0 0 (3,319) (3,319) 0
Glenmorag Car Park 0 0 0 (4) (4) 0 (4) (4) 0
Fleet Management - PB (1,565) (1,565) 0 (2,152) (2,152) 0 (4,826) (4,826) 0
Fleet Management (9) (9) 0 (9) (9) 0 (58) (58) 0
Millpark Depot Demolition Insurance 0 0 0 0 0 0 (53) (53) 0
Oban Depot - Mill Park Insurance Claim 0 0 0 0 0 0 (1,681) (1,681) 0
Oban Depot - Revenue Contribution 0 0 0 (67) (67) 0 (67) (67) 0
Lismore Ferry 0 0 0 0 0 0 (500) (500) 0
Witchburn Road Demolition 0 0 0 0 0 0 (157) (157) 0
Oban Bus Congestion - Bus Partnership Fund (31) (31) 0 (32) (32) 0 (50) (50) 0
Service Development Total (1,605) (1,620) 15 (6,421) (6,421) 0 (25,568) (25,568) 0
Strategic Change Projects 
Campbeltown Flood 0 0 0 0 0 0 (270) (270) 0
Harbour PB (1,945) (1,945) 0 (24,050) (24,050) 0 (91,292) (91,292) 0
01 TIF - Lorn/Kirk Road 0 0 0 0 0 0 (2,057) (2,057) 0
Strategic Change Total (1,945) (1,945) 0 (24,050) (24,050) 0 (93,619) (93,619) 0
Total Income (3,571) (3,731) 160 (31,289) (31,289) 0 (120,005) (120,005) 0
Net Departmental Total 4,189 4,129 60 23,960 23,953 7 73,900 73,935 (35)

Page 94

CAPITAL PLAN 2024-25
Overall Summary      
APPENDIX 9 
Previous
Years  2024-25  2025-26  2026-27  2027-28   Total
Service £000s £000s £000s £000s £000s  £000s
Education 38,545 7,915 3,466 1,988  0 51,914
Shared Offices 13,242 1,802 3,035 667  0 18,746
ICT 2,851 1,611 1,221 688  0 6,371
RIS 38,918 47,063 45,921 28,907  0 160,809
DEG 19,251 6,533 941 0  0 26,725
HSCP 1,246 3,776 1,055 0  0 6,077
Live Argyll 1,275 1,125 169 468  0 3,037
CHORD 65,358 4,509 113 0  0 69,980
Overall Total 180,686 74,334 55,921 32,718  0 343,659

Page 95

CAPITAL PLAN 2024-25         APPENDIX 9
Education         
Previous         
Years 2024-25 2025-26 2026-27 2027-28  Total
Category Service Project £000s £000s £000s £000s £000s  £000s
Asset Sustainability Education Block Allocation - Education 0 568 520 1,988  0 3,076  
Digital Inclusion 20-21 0 9 0 0  0 9  
Free School Meals 0 0 434 0  0 434  
Pre-5's/Nurseries 0 0 0 0  0 0  
Preliminary RAAC Investigation 0 2,390 1,006 0  0 3,396  
Primary Schools 0 3,013 1,280 0  0 4,293  
Secondary Schools 0 1,086 226 0  0 1,312
Asset Sustainability Total   0 7,066 3,466 1,988  0 12,520
Service Development Education Bowmore Primary School - Gaelic Medium Grant 0 38 0 0  0 38  
Bowmore Primary School - Pre Five Unit 149 0 0 0  0 149  
Clyde Cottage - 600 hours provision 556 0 0 0  0 556  
CO2 Monitoring - Covid Mitigation in Schools 79 113 0 0  0 192  
Craignish Primary School - Pre Five Extension (600 hours funding) 400 0 0 0  0 400  
Early Learning and Childcare 850 0 0 0  0 850  
Early Learning and Childcare - 1140 Hours 7,774 -12 0 0  0 7,762  
Early Learning and Childcare - 1140 Hours - CFCR 1,379 0 0 0  0 1,379  
Iona Primary School - Pre Five Unit (600 hours funding) 490 0 0 0  0 490  
Islay High & Rosneath PS Pitches 719 0 0 0  0 719  
Sandbank Gaelic Pre Five Unit 491 0 0 0  0 491
Service Development Total   12,887 139 0 0  0 13,026
Strategic Change Education Campbeltown Schools Redevelopment 2,092 38 0 0  0 2,130  
Dunoon Primary School 10,637 232 0 0  0 10,869  
Kirn Primary School 10,085 34 0 0  0 10,119  
Replacement of Oban High School 2,844 406 0 0  0 3,250 
Strategic Change Total 25,658 710 0 0 0 26,368
Overall Total 38,545 7,915 3,466 1,988 0 51,914

Page 96

CAPITAL PLAN 2024-25          APPENDIX 9
Shared Office             
Previous       
Years  2024-25 2025-26 2026-27 2027-28  Total
Category Service Project £000s  £000s £000s £000s £000s  £000s
Asset Sustainability Shared Offices 52 Sinclair Street Flats - CFCR  0 0 0 0  0 0  
Block Allocation  0 320 427 382  0 1,129  
Burnett Building  0 107 0 0  0 107  
Helensburgh and Lomond Civic Centre  0 140 0 0  0 140  
Kilmory Castle  0 0 1,545 0  0 1,545  
Legionella Control Works  0 12 0 0  0 12  
Our Modern Workspace  0 542 0 0  0 542
Asset Sustainability Total    0 1,121 1,972 382  0 3,475
Strategic Change Shared Offices Campbeltown Office Rationalisation 595 1 0 0 0 596  
Clean Energy - NDEEF1 1,109 124 98 0 0 1,331  
Clean Energy - NDEEF2 0 0 855 285 0 1,140  
Helensburgh Office Rationalisation (FPB,REC) 11,538 300 0 0 0 11,838  
Net Zero 0 256 110 0 0 366 
Strategic Change Total 13,242 681 1,063 285 0 15,271
Overall Total 13,242 1,802 3,035 667 0 18,746

Page 97

CAPITAL PLAN 2024-25
ICT        
APPENDIX 9   
Previous         
Years 2024-25 2025-26 2026-27 2027-28  Total
Category Service Project £000s £000s £000s £000s £000s  £000s
Asset Sustainability ICT Block Allocation - ICT 0 132 0 688  0 820  
PC Replacement 0 561 669 0  0 1,230  
Server Sustainability 0 488 400 0  0 888  
Telecomms Network 0 88 152 0  0 240
Asset Sustainability Total   0 1,269 1,221 688  0 3,178
Service Development ICT Applications Projects 2,851 342 0 0  0 3,193 
Service Development Total 2,851 342 0 0 0 3,193
Overall Total 2,851 1,611 1,221 688 0 6,371

Page 98

CAPITAL PLAN 2024-25         APPENDIX 9
Roads and Infrastructure Services         
Previous         
Years 2024-25 2025-26 2026-27 2027-28  Total
Category Service Project £000s £000s £000s £000s £000s  £000s
Asset Sustainability RIS Block Allocation 0 110 3,628 3,823  0 7,561  
Bridge Strengthening 0 141 1,243 0  0 1,384  
Bute Sea Wall Repairs 0 633 0 0  0 633  
Claonaig Landslip 0 1,600 0 0  0 1,600  
Coastal Change Adaptation 0 147 157 0  0 304  
Coastal Protection 0 196 0 0  0 196  
Environmental Projects 0 721 0 0  0 721  
EV Quick Chargers 0 52 0 0  0 52  
Flood Prevention 0 1,041 156 0  0 1,197  
Footway Improvements 0 219 0 0  0 219  
Gartbreck - Capping 0 194 0 0  0 194  
Glengorm - Cell and Transfer Station (PB) 0 249 0 0  0 249  
Helensburgh CHORD - Signage etc 0 10 0 0  0 10  
Helensburgh Flood Mitigation 0 0 427 0  0 427  
Investment in Active Travel 0 200 0 0  0 200  
Lighting 0 325 369 0  0 694  
Local Bridge Maintenance Fund 0 230 4,760 0  0 4,990  
Play Park Renewal 0 547 391 0  0 938  
POPs Waste 0 86 0 0  0 86  
Public Convenience Upgrades 0 118 109 0  0 227  
Roads Reconstruction 0 8,043 0 0  0 8,043  
Roads Reconstruction - Helensburgh CHORD 0 47 0 0  0 47  
Roads Reconstruction - Oban CHORD 0 3 0 0  0 3  
Tobermory Car Park 0 96 0 0  0 96
Asset Sustainability Total   0 15,008 11,240 3,823  0 30,071
Service Development RIS Campbeltown Old Quay 1,381 0 0 0  0 1,381  
Fleet Management 4,502 258 0 0  0 4,760  
Fleet Management - Prudential Borrowing 2,674 2,152 0 0  0 4,826  
Jackson's Quarry Refurbishment 285 0 0 0  0 285  
Lismore Ferry Replacement 637 35 0 0  0 672  
Lochgilphead Depot Rationalisation 154 15 0 0  0 169  
Oban Bus Congestion - Bus Partnership Fund 50 0 0 0  0 50  
Oban Depot Development 2,224 -35 0 0  0 2,189  
Preliminary design for Regional Transport projects (tif) 205 16 0 0  0 221  
Public Transport Operation Vehicles 0 233 0 0  0 233  
Weather Incident 326 3,208 1,100 0  0 4,634  
Witchburn Road Demolition 158 0 0 0  0 158
Service Development Total   12,596 5,882 1,100 0  0 19,578
Strategic Change RIS Campbeltown Flood Scheme 13,748 1,780 10 387  0 15,925  
Harbour Investment Programme Non PB 0 43 0 0  0 43

Page 99

Strategic Change RIS Harbour Investment Programme PB 9,295 24,050 33,250 24,697 0 91,292  
Street Lighting LED Replacement 3,279 300 321 0 0 3,900 
Strategic Change Total 26,322 26,173 33,581 25,084 0 111,160
Overall Total 38,918 47,063 45,921 28,907 0 160,809

Page 100

CAPITAL PLAN 2024-25 APPENDIX 9
Development and Economic Growth 
Previous 
Years 2024-25 2025-26 2026-27  2027-28  Total
Category Service Project £000s £000s £000s £000s  £000s  £000s
Service Development DEG Ardrishaig North Active Travel 831 49 0  0  0 880  
Arinagour, Coll - Site Investigation and Preliminary 0 74 0  0  0 74  
Cycleways - H&L (FSPT) 2,905 497 0  0  0 3,402  
Dunoon Cycle Bothy 483 80 0  0  0 563  
Dunoon STEM Hub 131 2,427 0  0  0 2,558  
Gibraltar Street Public Realm Improvements 153 97 0  0  0 250  
Glenmorag Car Park PC 0 4 0  0  0 4  
Helensburgh Public Realm - Arts Strategy Fund 3 25 25  0  0 53  
Hermitage Park 3,362 26 0  0  0 3,388  
Nature Restoration Fund 0 835 234  0  0 1,069  
Rural Growth Deal 239 1,068 0  0  0 1,307  
Safe Streets, Walking and Cycling (CWSS) 3,143 619 395  0  0 4,157  
SPT - bus infrastructure 1,405 25 0  0  0 1,430  
Town Centre Funds 3,856 334 0  0  0 4,190  
West Coast UAV Innovation Logistics and Trainin 0 0 0  0  0 0
Service Development Total   16,511 6,160 654  0  0 23,325
Strategic Change DEG 01 TIF - Lorn/Kirk Road 2,169 1 0  0  0 2,170  
09 TIF - Oban Airport Business Park 505 85 0  0  0 590  
TIF - Halfway House Roundabout 66 287 287  0  0 640
Strategic Change Total 2,740 373 287 0 0 3,400
Overall Total 19,251 6,533 941 0 0 26,725

Page 101

CAPITAL PLAN 2024-25 APPENDIX 9
Health & Social Care Partnership 
Previous 
Years 2024-25 2025-26 2026-27  2027-28  Total
Category Service Project £000s £000s £000s £000s  £000s  £000s
Asset Sustainability HSCP Ardfenaig 0 12 0  0  0 12  
Capital Property Works 0 55 0  0  0 55  
Eadar Glinn 0 34 0  0  0 34  
Glencruitten Hostel 0 301 0  0  0 301  
Greenwood/Woodlands 0 1 0  0  0 1  
HSCP - 102 East King Street "Jean's Both 0 4 0  0  0 4  
Kintyre Care Home 0 150 650  0  0 800  
Lorn Resource Centre 0 15 0  0  0 15  
Shellach View 0 2 0  0  0 2  
Struan Lodge Boiler 0 700 0  0  0 700  
Thomson Home Rothesay 0 270 370  0  0 640  
Tigh An Rudha HFE 0 2,178 35  0  0 2,213
Asset Sustainability Total   0 3,722 1,055  0  0 4,777
Service Development HSCP Dunclutha Childrens Home 1,246 54 0  0  0 1,300
Service Development Total 1,246 54 0 0 0 1,300
Overall Total 1,246 3,776 1,055 0 0 6,077

Page 102

CAPITAL PLAN 2024-25         APPENDIX 9
Live Argyll         
Previous         
Years 2024-25 2025-26 2026-27 2027-28  Total
Category Service Project £000s £000s £000s £000s £000s  £000s
Asset Sustainability Live Argyll Aqualibrium 0 63 104 0  0 167  
Capital Property Works 0 24 0 382  0 406  
Corran Halls Gaelic Centre 0 19 0 86  0 105  
Kintyre Community Education Centre 0 6 0 0  0 6  
Lochgilphead Community Ed Centre 0 411 0 0  0 411  
Riverside Leisure Centre - Health Suite Upgrade 0 140 0 0  0 140  
Rothesay Swimming Pool 0 24 65 0  0 89  
The Moat Centre 0 393 0 0  0 393  
Victoria Halls, Helensburgh 0 24 0 0  0 24
Asset Sustainability Total   0 1,104 169 468  0 1,741
Service Development Live Argyll Riverside Leisure Centre Refurbishment 1,246 0 0 0  0 1,246
Service Development Total   1,246 0 0 0  0 1,246
Strategic Change Live Argyll Carbon Management 29 21 0 0  0 50 
Strategic Change Total 29 21 0 0 0 50
Overall Total 1,275 1,125 169 468 0 3,037

Page 103

CAPITAL PLAN 2024-25           APPENDIX 9
Major Projects           
Previous           
Years 2024-25 2025-26  2026-27  2027-28  Total
Category Service Project £000s £000s £000s  £000s  £000s  £000s
Strategic Change CHORD CHORD - Dunoon 12,499 23  0  0  0 12,522  
CHORD - Helensburgh -Public Realm Imprv 0 25  0  0  0 25  
CHORD - Oban 7,326 500  79  0  0 7,905  
CHORD - Rothesay 21,046 2,611  0  0  0 23,657  
Helensburgh Waterfront Development 24,111 281  0  0  0 24,392  
HWD - FFE 316 34  0  0  0 350  
Kilmory Business Park Phase 2AA 60 1,035  34  0  0 1,129 
Strategic Change Total 65,358 4,509 113 0 0 69,980
Overall Total 65,358 4,509 113 0 0 69,980

Page 104

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
TREASURY MANAGEMENT MONITORING REPORT – 31 AUGUST 2024
1.0. EXECUTIVE SUMMARY
1.1. This report sets out the Council’s treasury management position for the period 1 July
2024 to 31 August 2024 and includes information on:
 Overall borrowing position
 Borrowing activity
 Investment activity
 Economic background
 Interest rate forecast
 Prudential Indicators
1.2. Estimated borrowing is below the Capital Financing Requirement for the period to 31
August 2024, at this stage in the financial year capital expenditure is below target.
1.3. There was no material net movement in external borrowing in the period 1 July 2024 to 31
August 2024.
1.4. The levels of investments were £61.702m at 31 August 2024. The rate of return achieved
was 5.110% compared to the target SONIA rate which was 4.950%. 
1.5. The Council has significant cash balances which are invested in accordance with its
Annual Treasury Management Strategy on the basis of security first, liquidity second and
then return.

Page 105

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
TREASURY MANAGEMENT MONITORING REPORT – 31 AUGUST 2024
2.0. INTRODUCTION
2.1. This report sets out the Council’s treasury management position for the period 1 July
2024 to 31 August 2024 and includes information on: 
 Overall borrowing position
 Borrowing activity
 Investment activity
 Economic background
 Interest rate forecast
 Prudential Indicators
3.0. DETAIL
Overall Borrowing Position
3.1. The table below details the estimated capital financing requirement (CFR) and compares
this with the estimated level of external debt at 31 March 2024. The CFR represents the
underlying need for the Council to borrow to fund its fixed assets and accumulated capital
expenditure. 
Forecast Forecast Forecast
2024/25 2025/26 2026/27
£000 £000 £000
CFR at 1 April 332,394 359,657 382,492
Net Capital Expenditure 39,455 35,761 24,555
Less Loans Fund Principal Repayments -6,254 -6,691 -6,962
Less: NPDO Repayment -5,938 -6,235 -6,844
Estimated CFR 31 March 359,657 382,492 393,241
Less Funded by NPDO -105,846 -100,611 -94,767
Estimated Net CFR 31 March 253,811 281,881 298,474
Estimated External Borrowing at 31 March 
190,835  209,152  227,472
Gap 62,976 72,729 71,002 
3.2. Borrowing is below the Capital Financing Requirement for the period to 31 August
2024. The Council has delayed taking out any new long term borrowing, as rates are
expected to drop towards the end of 2024 plus the Council has significant cash
balances which reduces the need to borrow in the short term.
3.3. The Council’s Treasury Management Strategy states that any decision to borrow in
advance will be within forward approved Capital Financing Requirement estimates.
3.4. The Council’s estimated net capital financing requirement at 31 August 2024 is
£253.811m. The table below shows how this has been financed. £113.604m is
funded by loans and there are substantial internal balances of £201.909m of which
£61.702m are currently invested, as detailed in section 3.7, leaving a net internal

Page 106

balance of £140.207m. 
Position at
30/06/24 
Position at
31/08/24
£000 £000
Loans 114 114
Net Internal Balances 141 140
Total CFR 255 254 
3.5. During the period from 1 July 2024 to 31 August 2024, there was no material net
movement on external borrowing. The analysis of the movement in borrowing is
shown in the table below: 
Actual
£m
External Loans Repaid 1st July 2024 to 31st August 2024  (0)
Borrowing undertaken 1st July 2024 to 31st August 2024  0
Net Movement in External Borrowing (0) 
3.6. The table below summarises the movement in the rate of temporary borrowing at
the start and end of the period. 
% Rate
Temp borrowing at 1st July 2024 4.75%
Temp borrowing at 31st August 2024 4.75%

Page 107

Investment Activity
3.7. The average rate of return achieved in the Council’s investments to 31 August 2024 was
5.110% compared to the SONIA (Sterling Overnight Index Average) rate for the same period of
4.950%. At 31 August 2024 the Council had £61.702m of short term investments at an
average rate of 5.110%. The table below details the counterparties that the investments
were placed with, the maturity date, the interest rate and the credit rating applicable for
each counterparty. 
Counterparty Maturity Amount £000 Interest Rate Rating S&P
Clydesdale Bank Instant Access 302 4.90% Short Term A-2, Long
Term A-
London Borough of Croydon 10/10/2024 5,000 4.10% AA
Goldman Sachs 25/10/2024 5,000 5.34% Short Term A-1, Long
Term A+
Al Rayan 07/11/2024 5,000 5.35% Short Term P-1, Long
Term A2 (Moody's)
Al Rayan 08/11/2024 5,000 5.35% Short Term P-1, Long
Term A2 (Moody's)
ANZ 05/09/2024 5,000 5.24% Short Term A-1+,
Long Term AA-
DBS 18/09/2024 5,000 5.31% Short Term A-1+,
Long Term AA-
ANZ 25/10/2024 5,000 5.25% Short Term A-1+,
Long Term AA-
MMF- Federated Call 14,700 5.08% AAA
Money Market Fund - Aberdeen Standard Call 8,500 5.04% AAA
MMF - Aviva Call 3,200 5.04% AAA     
Total  61,702   
3.8. All investments and deposits are in accordance with the Council’s approved list of
counterparties and within the limits and parameters defined in the Treasury Management
Practices. The counterparty list is constructed based on assessments by leading credit
reference agencies adjusted for additional market information available in respect of
counterparties. 
3.9. The Council has significant cash balances which are invested in accordance with its
Annual Treasury Management Strategy.

Page 108

Economic and Interest Rate Forecasts
3.10. The latest economic background is shown in Appendix 1 with the interest rate forecast in
Appendix 2. 
Prudential Indicators
3.11. The prudential indicators for 2024-25 are attached in Appendix 3. 
4.0. CONCLUSION
4.1 During the period from 1 July 2024 to 31 August 2024 there was no overall net material
movement of external borrowing and it is currently below the Capital Financing Requirement.
There are substantial internal balances, of which £61.702m is currently invested. The average
rate of investment returns during the period was 5.110%. 
5.0. IMPLICATIONS
5.1. Policy None 
5.2. Financial Complies with Annual Treasury Strategy 
5.3. Legal None 
5.4. HR None 
5.5. Fairer Duty Scotland:
5.5.1 Equalities – protected characteristics  None
5.5.2 Socio-economic Duty None
5.5.3 Islands None 
5.6. Climate Change None 
5.7. Risk None 
5.8. Customer Service None 
5.9 The Rights of the Child (UNCRC) None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
16 September 2024 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services 
Appendix 1 – Economic Background
Appendix 2 – Interest Rate Forecast
Appendix 3 – Prudential Indicators 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 109

Appendix 1 – Economics Update (Note that this appendix remains unchanged from what was
reported to Policy and Resources Committee on 15 August 2024 as the next update is not due
to be published until after the end of September) 
 The first quarter of 2024/25 saw:
- GDP growth flatlining in April following positive Q4 2023/24 growth figures of 0.7% q/q.
- A stalling in the downward trend in wage growth, with the headline 3myy rate staying at 5.9%
in April.
- CPI inflation falling from 2.3% in April to 2.0% in May.
- Core CPI inflation decreasing from 3.9% in April to 3.5% in May.
- The Bank of England holding rates at 5.25% in May and June.
- 10-year gilt yields climbing to 4.35% in April, before closing out at 4.32% in May.
 The news that the economy grew by 0.7% q/q in Q4 2023/24 confirmed that it moved out of its very
mild technical recession that prevailed at the back end of 2023. However, data released for April
and May so far shows a slight stalling in the recovery, with GDP data for April coming out at 0.0%
m/m, as inclement weather weighed on activity. Moreover, the fall in the composite Purchasing
Manager Index output balance from 53.0 in May to 51.7 in June confirms tepid growth.
 On a more positive note, the 2.9% m/m increase in retail sales volumes in May more than reversed
the 1.8% m/m drop in April as rainfall returned to seasonal norms. The strength was broad-based
across the retail sector, including online, (+5.9% m/m) suggesting an underlying strengthening in
sales beyond weather effects. With inflation falling back to target, Bank Rate likely to be reduced
soon and with consumer confidence improving, retail sales may well continue to strengthen.
 Stronger consumer spending, as low inflation allows households’ real incomes to strengthen and
the drag from higher interest costs fades, suggests that real consumption will strengthen
substantially over the next two years. However, investment will only make a modest contribution to
GDP growth. With the industrial sector still 12% smaller than in 2019, excess capacity will continue
to cap the need for industrial firms to invest. But improving business sentiment should raise
investment by services’ firms. Further, a fall in mortgage rates should trigger a recovery in residential
investment. Overall, strong consumer spending is likely to be the backbone of GDP growth, along
with government consumption. Our colleagues at Capital Economics forecast that following GDP
growth of 1.0% in 2024, activity will continue to surprise to the upside with GDP growth of 1.5% for
both 2025 and 2026 (consensus forecasts are 1.2% and 1.4% respectively).
 Nonetheless, the on-going stickiness of wage growth in April will be a lingering concern for the Bank
of England. The 3myy rate of average earnings growth stayed at 5.9% in April (consensus 5.7%),
whilst the more timely 3m annualised rate rebounded from 5.9% to 9.3%. This stickiness partly
reflected April’s 9.8% increase in the minimum wage. This leaves the Bank of England’s forecast
for a fall back in regular private sector pay growth from 5.8% in April to 5.1% in June looking a
challenge.
 Despite the stickiness of wage growth in April, sharp falls in employment and a move up in
unemployment suggests that wage growth will soon be back on a downward path. The 139,000 fall
in employment in the three months to April was accompanied by a rise in the unemployment rate
from 4.3% to 4.4%. This was the fourth increase in a row and took it to its highest level since
September 2021. The rise would have been larger were it not for the 132,000 increase in inactivity
in the three months to April as the UK’s disappointing labour market participation performance since
the pandemic continued. The vacancies data also paint a picture of a slowly cooling labour market.
The number of job vacancies fell from an upwardly revised 908,000 to 904,000, leaving vacancies
31% below the peak in May 2022, but 11% above the pre-pandemic level.

Page 110

 The fall in CPI inflation in May back to the Bank’s 2% target for the first time since July 2021 will
have come as welcome news to the Bank. Furthermore, with CPI inflation of 3.3% in the US and
2.6% in the Euro-zone in May, the UK appears to have won the race to get CPI inflation back to
2.0%. A further easing in food inflation from 2.8% in April to 1.6% in May played a part in the fall in
overall CPI inflation and with food producer price inflation at just 0.2% in May, food price inflation
will probably soon fall to zero.
 The core rate also fell back from 3.9% to 3.5%. Within that, core goods CPI inflation slipped below
zero for the first time since October 2016. As expected, clothing/footwear, recreation/culture and
restaurants/hotels categories inflation declined, reflecting base effects from big increases last May.
While services inflation fell from 5.9% to 5.7%, this decline was smaller than the Bank of England
expected (forecast 5.3%). And the timelier three-month annualised rate of services prices has
rebounded from 8.5% to 9.2%. This suggests that the persistence in domestic inflation that the Bank
is worried about is fading more slowly than it thought. Even so, there is scope for inflation to fall
further.
 There was little chance that the Bank would cut rates at its June meeting, given upside surprises
on services CPI inflation and wage growth. But several developments implied a rate cut is getting
closer (August?). First, two members of the MPC, Ramsden and Dhingra voted again to reduce
rates immediately to 5.00%. Second, despite the recent run of stronger inflation and activity, the
minutes noted “indicators of inflation persistence had continued to moderate” and that a range of
indicators suggest pay growth had continued to ease. And there was new wording that members of
the MPC will consider all the information available and how this affects the assessment that the
risks from inflation persistence are receding “as part of the August forecast round”.
 Throughout the quarter there was a degree of volatility in the gilt market and, by way of example,
the 10-year gilt yield rose from 4.05% on 2nd April to finish at 4.15% on 28th June but it has exceeded
4.30% on several occasions. Overall, investors judged that interest rates will need to remain high
for longer to keep inflation around the 2.0% target.
 Meanwhile, the FTSE 100 broke through the 8,000 mark in April for the first time since its brief three-
day flutter in February last year and reached a record closing high of 8,446 on 15th May. However,
by the end of the quarter, despite AI-fuelled rises in the US S&P500, it finished rather tamely and
had fallen back to 8,164. Arguably, significant interest rate cuts and an on-going UK economic
recovery will be required for a further resurgence to take hold.
PWLB maturity Certainty Rates 1st April to 30th June 2024
 Gilt yields and PWLB rates remained relatively stable between 1st April and 30th June. Having said
that, the spread between the low and high points during the quarter was between 0.3% and 0.45%
across the curve.
 The 50-year PWLB Certainty Rate target for new long-term borrowing (the low point of our forecast
on a two-year timeline) started 2024/25 at 4.00% and increased to 4.20% on 28th May. As can be
seen, with rates remaining elevated across the whole of the curve, it is advised to not borrow long-
term unless the Authority wants certainty of rate and judges the cost to be affordable.

Page 111

MPC meetings 9th May and 20th June 2024
 On 9th May, the Bank of England’s Monetary Policy Committee (MPC) voted 7-2 to keep Bank Rate
at 5.25%. This outcome was repeated on 20th June.
 Nonetheless, with UK CPI inflation now back at 2% and set to fall further over the coming months,
Ramsden and Dhingra – who voted again to reduce rates immediately to 5.00% in June – may
shortly be joined by some members in the no-change camp, for whom the June decision was “finely
balanced” as the upside news on services price inflation was more likely to be a reflection of one-
off effects and volatile components rather than factors that would push up “medium-term inflation”.

Page 112

Appendix 2 – Interest Rate Forecast (Note that this appendix remains unchanged from what was
reported to Policy and Resources Committee on 15 August 2024 as the next update is not due
to be published until after the end of September) 
The Council has appointed Link Group as its treasury advisors and part of their service is to assist the
Council to formulate a view on interest rates. The PWLB rate forecasts below are based on the Certainty
Rate (the standard rate minus 20 bps) which has been accessible to most authorities since 1st
November 2012. For Housing Revenue Account authorities, the lower Housing Revenue Account
(HRA) PWLB rate has also been available since 15 June 2023 (standard rate minus 60 bps) but is
available for HRA borrowing only.
The latest forecast, updated on 28th May, sets out a view that both short and long-dated interest rates
will start to fall once it is evident that the Bank of England has been successful in squeezing excess
inflation out of the economy, despite a backdrop of a stubbornly robust economy and a tight labour
market. 
Moreover, whatever the shape of domestic data, recent gilt market movements have been heavily
influenced by the sentiment pertaining to US monetary policy. Again, inflation and labour data has
proven sticky and the market’s expectation for rate cuts has gradually reduced throughout the course
of the year, so that possibly rates may not be cut more than once, or possibly twice, before the end of
2024. In any event, even if the Bank of England starts to cut rates first, it may mean that the medium
and longer parts of the curve take longer to fully reflect any such action until the US yield curve shifts
lower too. Given the potential inflationary upside risk to US treasuries if Trump wins the presidential
election in November (increased tariffs on imports from China for example), therein lies a further risk
to yields remaining elevated for longer.
Closer to home, the General Election is not expected to have a significant impact on UK monetary
policy. There is minimal leeway for further tax cuts or added spending without negatively impacting
market sentiment. It may even be the case that the Bank of England will steer clear of an August rate
cut – should that be supported by the inflation data – in favour of weighing up fiscal policy implications
and market sentiment in the aftermath of the election. 
Accordingly, Link’s central case is still for a rate cut before the end of September, but we are not
committed to whether it will be in August or September. Thereafter, the path and speed of rate cuts is
similar to that which we previously forecast, with Bank Rate eventually falling to a low of 3% by H2
2026.
However, given the increased uncertainty surrounding Link’s central gilt market forecasts, and the
significant issuance that will be on-going from several of the major central banks, it has marginally
increased its PWLB forecasts by c20 to 30 basis points across the whole curve since the previous
quarter. 
In summary, regarding PWLB rates, movement in the short-end of the curve is expected to reflect Link’s
Bank Rate expectations to a large degree, whilst medium to longer-dated PWLB rates will remain
influenced not only by the outlook for inflation, domestically and globally, but also by the market’s
appetite for significant gilt issuance (£200bn+ for each of the next few years). As noted at the Link
March Strategic Issues webinars, there is upside risk to that part of our forecast despite the Debt
Management Office skewing its issuance to the shorter part of the curve.

Page 113

 Money market yield forecasts are based on expected average earnings by local authorities for 3 to
12 months.
 The Link forecast for average earnings are averages i.e., rates offered by individual banks may
differ significantly from these averages, reflecting their different needs for borrowing short-term cash
at any one point in time.

Page 114

Appendix 3 – Prudential Indicators 
PRUDENTIAL INDICATOR 2024-25 2024-25 2025-26 2026-27
(1). EXTRACT FROM BUDGET     
Forecast
Outturn
Original
Estimate
Forecast
Outturn
Forecast
Outturn
Capital Expenditure £'000 £'000 £'000 £'000
Non - HRA 39,455 43,320 35,761 24,555
TOTAL 39,455 43,320 35,761 24,555     
Ratio of financing costs to net revenue stream    
Non - HRA 4.54% 4.36% 4.44% 4.49%     
Net borrowing requirement    
brought forward 1 April * 332,394 320,025 359,657 382,492
carried forward 31 March * 359,657 351,041 382,492 393,241
in year borrowing requirement 27,263 31,016 22,835 10,749     
In year Capital Financing Requirement    
Non - HRA 27,263 31,016 22,835 10,749
TOTAL 27,263 31,016 22,835 10,749     
Capital Financing Requirement as at 31 March    
Non - HRA 359,657 351,041 382,492 393,241
TOTAL 359,657 351,041 382,492 393,241

Page 115

PRUDENTIAL INDICATOR 2024-25 2025-26 2026-27
(2). TREASURY MANAGEMENT PRUDENTIAL INDICATORS £'M £'M £'M    
Authorised limit for external debt -   
borrowing 251 280 288
other long term liabilities 109 109 104
TOTAL 360 389 392    
Operational boundary for external debt -   
borrowing 246 275 283
other long term liabilities 106 106 101
TOTAL 352 381 384    
Upper limit for fixed interest rate exposure   
Principal re fixed rate borrowing 190% 190% 190%    
Upper limit for variable rate exposure   
Principal re variable rate borrowing 60% 60% 60%    
Upper limit for total principal sums invested for over 364 days £20m £20m £20m
(per maturity date)   
Maturity structure of new fixed rate borrowing during 2024/25 upper limit lower limit
under 12 months 30% 0%
12 months and within 24 months 30% 0%
24 months and within 5 years 30% 0%
5 years and within 10 years 40% 0%
10 years and above 100% 0%

Page 116

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
RESERVES AND BALANCES – UPDATE AS AT 31 AUGUST 2024 
1 EXECUTIVE SUMMARY
1.1 The main purpose of this report is to advise Members of the overall level of
reserves held by the Council as well as providing detail on the monitoring of the
earmarked balances held within the General Fund.
1.2 The Council has a total of £689.113m unusable reserves that are not backed with
resources. They are required purely for accounting purposes.
1.3 At 31 March 2024 the Council had a total of £121.701m of usable reserves. Of this:
 £2.763m relates to the Repairs and Renewals Fund
 £3.197m relates to Capital Funds
 £115.741m was held in the General Fund, with £107.443m of this balance
earmarked for specific purposes.
1.4 At the budget setting meeting on 22 February 2024, as part of the revenue budget,
Council agreed to the transfer Strathclyde Pension Fund contribution savings of
£6.875m relating to Council staff and £3.053m relating to Social Work staff to
reserves. It was also agreed that £1.875m of revenue surplus within 2024-25 be
transferred to the Capital Plan. As the commitments for these include expenditure
within 2024-25 year, these have been immediately recognised within the
earmarked reserves balances to allow them to be spent accordingly. In addition,
Scottish Government funding in relation to the 23-24 pay award has been notified
at a value of £0.371m and this has been reinstated to the Connect for Success
earmarking as planned. This results in a total in-year earmarked balance of
£119.617m.
1.5 Of the earmarked balance of £119.617m:
 £58.040m is invested or committed for major initiatives/capital projects
 £10.124m has already been drawn down
 £20.998m is still to be drawn down in 2024-25
 £30.455m is planned to be spent in future years
1.6 There is an upcoming review of Earmarked reserves being presented to Council on
26th September 2024, the impact of which is not included within the figures
contained in this report. Any adjustments required will be included within the next
reporting period.
1.7 The Council’s General Fund contingency is set at 2% of net expenditure for 2024-
25 and amounts to £6.039m. At the beginning of the financial year there was
£2.259m of unallocated General Fund Balance (over and above contingency).
After taking into consideration the current forecast outturn for 2024-25 and the

Page 117

likely input of Crown Estate Funding to the remaining Weather Event overspend,
the Council is estimated to have a £0.413m surplus over contingency.

Page 118

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 10 OCTOBER 2024
RESERVES AND BALANCES - UPDATE AS AT 31 AUGUST 2024 
2. INTRODUCTION 
2.1 This report outlines current balances on the Council’s reserves, both usable and
unusable. It also provides detail on the monitoring of the earmarked balances
within the General Fund. 
3. DETAIL 
3.1 Types of Reserves 
3.1.1 Usable Reserves - Councils have powers to establish certain resource backed
reserves which can be used to fund expenditure. The powers of councils to
establish reserves are laid out in Schedule 3 of the Local Government
(Scotland) Act 1975. These allow councils to establish a Renewal and Repairs
Fund, Insurance Fund and Capital Fund. Councils can also establish a Useable
Capital Receipts Reserve. The Council must also maintain a General Fund and
can earmark balances for specific purposes within the General Fund.
3.1.2 Unusable Reserves – Councils are also required to establish certain reserves
that are not backed by resources. They are required purely for accounting
purposes and do not represent resources available for councils to utilise. The
Pensions Reserve, Revaluation Reserve, Capital Adjustment Account, Financial
Instruments Adjustment Account and Accumulated Absences Account are
examples of unusable reserves. 
3.2 Reserve Balances at 31 March 2024 
3.2.1 The balances on each type of reserve at 31 March 2024 are set out in the two
tables below, per the Unaudited Accounts for 2023-24. 
Unusable Reserves £000
Revaluation Reserve 180,661
Capital Adjustment Account 249,093
Financial Instruments Adjustment Account (1,585)
Pensions Reserve 269,216
Accumulated Absences Account (8,272)
Total Unusable Reserves 689,113 
Usable Reserves £000
Repairs and Renewals Fund 2,763
Capital Fund and Usable Capital Receipts Reserve 3,197
General Fund 115,741
Total Usable Reserves 121,701
Total Reserves 810,814

Page 119

3.2.2 The Revaluation Reserve represents the unrealised gains in the valuation of
fixed assets. The Capital Adjustment Account represents the difference
between depreciation based on proper accounting practice and statutory
charges for financing capital expenditure. The Financial Instruments Adjustment
Account represents the difference between gains and losses on borrowing and
statutory capital financing charges. The Pensions Reserve represents the
difference between pension costs based on proper accounting practice and
payments made for pension costs. The Accumulated Absences Account
represents the costed difference between holiday pay entitlement and actual
holidays taken at 31 March.
3.2.3 The Repairs and Renewals Fund was established to support funding of renewal
and replacement of school equipment. Schools can only draw on the Repairs
and Renewals Fund to the extent they have previously paid into the Fund and
contributions must be contained within schools devolved budgets.
3.2.4 The Capital Fund was established to receive all capital receipts generated by
the Council and can be used to support the capital plan or meet the principal
repayments on loan charges. The Council decides as part of the budget
process each year how it wishes to draw funding from the Capital Fund.
3.2.5 The Usable Capital Receipts Reserve relates to the accumulated unspent
capital receipts from sale of council houses prior to transfer of the housing
stock. The reserve forms part of the Council’s Strategic Housing Fund and can
only be used for investment in social housing. The reserve will be used in
accordance with the approach to investing in housing agreed by the Council in
August 2012.
3.3 General Fund
3.3.1 The General Fund balance at 31 March 2024 can be analysed as follows: 
Balance
31/03/24
£000
Balance on General Fund as at 31 March 2023  86,356
Increase to General Fund balance at end of 2023-24  29,385
Earmarked Balances* (107,443)
Contingency allowance at 2% of net expenditure (6,039)
Unallocated balance as at 31 March 2024 2,259 
* Note that the earmarked balance of £107.443m includes £35.658m of new
earmarked reserves relating to the Service Concessions gain as detailed at
paragraph 3.6.
3.3.2 The General Fund includes balances that the Council has agreed to earmark for
specific purposes. Some of these earmarked balances will be spent during the
current financial year and some of them will be held over and spent in later
years. The table below shows the balance at 31 March 2024, the new amounts
earmarked from the Strathclyde Pension Fund savings (see section 3.7), the

Page 120

amount from the revenue budget for Capital agreed at Council in February
2024, the amount returned to earmarking from Scottish Government funding for
the 2023-24 pay award, the amounts that are currently invested or set aside for
major initiatives, the amount already spent and planned to be spent in the
current year, the amount to be spent in future years and any sums no longer
required to be earmarked. Appendix 1 provides further details on the
breakdown of unspent budget earmarkings. Officers have reviewed and
updated the spending profiles. 
3.4  Unallocated General Fund Balance
3.4.1 The Council’s General Fund contingency is set at 2% of net expenditure for
2024-25 and amounts to £6.039m. At the beginning of the financial year there
was £2.259m of unallocated General Fund Balance (over and above
contingency). After taking into consideration the current forecast outturn for

Page 121

2024-25 and the likely input of Crown Estate Funding to the remaining Weather
Event overspend, the Council is estimated to have a £0.413m surplus over
contingency. 
3.4.2 The revenue budget position as at 31 August 2024 was estimated to be a
£4.096m overspend, of which £1.470m relates to Social Work. 
3.4.3 Social Work, as a part of the Integrated Joint Board (IJB), are able to hold any
surplus within reserves therefore it is expected that any under or overspend that
materialises would be transferred to/from the IJB reserves and the General
Fund of the Council would not be impacted.
3.4.4 In relation to the adverse weather event of October 2023, it was agreed at the
Policy and Resources meeting on 15 August 2024 to continue the roads
reconstruction schemes and the overspend be funded as follows: 
£000
Utilise some of the unallocated capital funding for street
lighting and cable and column replacements
100
Use Priorities Investment Fund 944
Use Crown Estate Funding* 780
Borrowing for additional expenditure and use £50k in the
loans fund for street lighting improvements toward the
cost of borrowing
2,029
Total 3,853 
* Adjustments for the above, excluding Crown Estate Funding, have been
processed in the ledger as at August. As the Crown Estate Funding for 2024-
25 has not been confirmed yet, the Section 95 Officer will advise Members
before the end of the calendar year if funding has still not been confirmed at
that time or if funding confirmed is insufficient. 
3.4.5 The table below summarises the position of the unallocated General Fund
balance taking into consideration the points noted above. 
Heading Detail £000
Unallocated General Fund
as at 31 March 2024
This is the balance that is
unallocated over and above the 2%
contingency, which amounts to
£6.039m
2,259
Current Forecast Outturn
for 2024-25 as at 30 June
2024
Per paragraph 3.4.2. (4,096)
Social Work outturn
adjustment
Per paragraph 3.4.3 - Social Work
would expect to transfer any surplus
to internal IJB reserves
1,470
Weather Incident Per P&R Committee 15 Aug 24 –
Likely use of crown estate funding to
offset weather incident remaining
costs.
780

Page 122

Estimated Unallocated
balance as at 31 March
2025 
413 
3.5 Loans Fund Review
3.5.1 At the Council meeting on 27 February 2020, it was agreed that the one-off re-
profiling gain of £20.561m generated by the loans fund review should be used
partly to create a provision for the increasing principal repayments over the next
10 years (£7.649m) with the remainder of the gain (£12.912m) used to fund
known liabilities/cost pressures. The £12.912m has now been transferred to
Earmarked Reserves in full. 
3.6 Service Concessions 
3.6.1 At the Council meeting on 23 February 2023 it was agreed that the Council
adopt the financial flexibility introduced by the Scottish Government relating to
Service Concession contracts. This resulted in a one-off retrospective gain of
£36.038m. The commitments associated with this were further refined at the
Council meeting on 22 February 2024 and it was agreed that £0.380m be
transferred into the general fund balance, leaving a one-off gain of £35.658m
which is now being held in earmarked reserves. Appendix 2 provides
information on these commitments. 
3.7 Strathclyde Pension Fund Reserves 
3.7.1 The Strathclyde Pension Fund reported an exceptionally strong set of results
with a surplus of almost £9bn which has allowed a reduction in the employer
contribution rate. Argyll and Bute Council is seeing a reduction in employer
contributions from 19.3% to 6.5% over 2024-25 and 2025-26, before reverting
to a sustainable long-term rate in the third year of 17.5%. For the Council, the
one-off saving in the first two years associated with a reduction to 6.5% is
£6.875m per year. On 22 February 2024, Council agreed to allocate the
cumulative gain in the first two years of £13.750m as follows: 
Description 2024-25
£000
2025-26
£000
Total
£000
Realised saving 6,875 6,875 13,750
£2m in 24-25 to balance revenue budget (2,000)  (2,000)
£3.750m allocation to capital plan (3,750)  (3,750)
£2m to be directed towards
Transformation/ Spend to save projects (1,125) (875) (2,000)
£2m in 25-26 to balance revenue budget  (2,000) (2,000)
£2m in 26-27 to balance revenue budget  (2,000) (2,000)
£2m allocation to capital plan  (2,000) (2,000) 
0 0 0 
3.7.2 The £6.875m from the 2024-25 revenue budget saving has been logged within
the earmarkings with the commitments noted above to allow expenditure to be
made against them.

Page 123

3.7.3 For Social Work, the SPF saving is £3.053m per annum and is being ring
fenced within the Council reserves for utilisation by the HSCP in the future.
This amount is also being logged with the earmarkings in 2024-25 to allow
expenditure to be made if required.
3.7.4 As at 31st August 2024, the commitments against the Strathclyde Pensions fund
for Transformation/Spend to Save projects are as follows: 
Description Commitment
£000
Drawn
Down at
31/08/24
£000
Data Platform Build Consultancy 40 0
Data Platform Build Consultancy (Contingency) 4 0
RIS Service Review 150 0
Conversational AI 31 0 
225 0 
- £0.040m for Data Platform Build Consultancy – to fund external consultants
to help build a data platform which will provide a new approach to how Argyll
and Bute organises and accesses its data to support strategic decision
making. Note that a further £0.004m is being allowed as a contingency to
cover any unexpected costs arising from the purchase of additional technical
components for the solution
- £0.150m towards the RIS Service review. A report was presented to the
Environment, Development and Infrastructure (EDI) Committee on 20 June
2024 regarding the need for external support to assist in the delivery of
stages 2 to 4 of the review to allow RIS to continue to deliver its current day-
to-day services. The EDI committee approved the report, recommending to
Council that the £0.150m required was funded from the Strathclyde Pension
fund gain transformational pot and this was subsequently agreed by Council
on 27 June 2024.
- £0.031m towards an investment in a one-year proof of concept contract to
implement Conversational AI across the web, voice and social media
channels for the Council
4. CONCLUSION 
4.1 The report outlines the overall reserves and balances for the Council covering
the purpose and level of each reserve. It also provides detail as to expenditure
against earmarked balances held within the General Fund. 
4.2 As at 31 August 2024 the estimated unallocated General Fund, after taking into
consideration the current forecast outturn for 2024-25 is estimated to have a
£0.413m surplus over contingency.

Page 124

5. IMPLICATIONS 
5.1 Policy - Earmarked funds and funds set aside for delivery of
Single Outcome Agreement are available to support
Council Policy.
5.2 Financial - Outlines the balances held with the Council’s usable
and unusable reserves.
5.3 Legal - None.
5.4 HR - None.
5.5 Fairer Scotland Duty- None.
5.5.1 Equalities – protected
characteristics -
None.
5.5.2 Socio-economic Duty - None.
5.5.3 Islands - None.
5.6 Climate Change - None.
5.7 Risk - A contingency of £6.039m (equivalent to 2% of net
expenditure) has been set aside as part of the
general fund. This has been subject to a risk
assessment.
5.8 Customer Service - None.
5.9 The Rights of the Child
(UNCRC) -
None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
6 September 2024
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services
APPENDICES
Appendix 1 – Earmarked Reserves breakdown of unspent budget
Appendix 2 – Earmarked Reserves breakdown of Service Concessions earmarkings 
For further information contact Anne Blue, Head of Financial Services
anne.blue@argyll-bute.gov.uk

Page 125

APPENDIX 1 
Earmarked Reserves - Unspent Budget
As at 31 August 2024 
Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
001 Chief Executive's Unit Community
Planning
Service Concessions - Priorities Investment
Fund (Area Plans)
200,000 86,838  113,162 13,162 100,000 As agreed by Policy and Resources Committee on 23 October 23 - drawdown of
£200,000 from the Priorities Investment Fund to fund two temporary posts and
associated costs to produce meaningful area plans
100,000 100,000 0
002 Chief Executive's Unit Community
Planning
Communities and Partnership Team 8,855 0  8,855 8,855 0 The funds have originated from externally sourced income due to an employee
being seconded to the Scottish Community Development Centre (SCDC). The funds
will be used to support the team in relation to meeting its priorities of Building Back
Better (Communities), Climate Change and the review of the Argyll and Bute
Outcome Improvement Plan.
8,855 0 0
003 Executive Director (Douglas
Hendry)
Across Services /
Commercial
Services
Information Management (Estates Survey
Work)
12,697 0  12,697 12,697 0 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of
change as outlined in the BV Review. The planned initiatives include: Estates Survey
work £122k, Digitalisation of Title Deeds £92k, document management and
workflow system for Planning, Building Standards and Environmental Health £77k
and a balance of funding to explore information management solutions in a strategic
and coherent way £209k. This balance relates to Estates Survey Work. Having a
procured supplier to provide floor plans at short notice is required to be able to
react quickly to requests. If this isn't available Estates would need to go through the
procurement process again which would delay any projects by several months.
There isn’t a detailed plan to use this resource it is more about being able to react
quickly and not delay projects.
12,697 0 0
004 Executive Director (Douglas
Hendry)
Across Services /
Education
Digital Projects (Supply Staff Booking
System)
15,200 0  15,200 9,900 5,300 To deliver a number of Digital Service Transformation Projects with a commitment
of £0.035m towards a Supply Staff Booking system. Phase 1 of the project is nearing
completion.
9,900 5,300 0
005 Executive Director (Douglas
Hendry)
Commercial
Services
Rothesay Pavilion Charity 750,000 0  750,000 0 750,000 Agreed at Council meeting February 2020, £750k additional revenue support subject
to conditions which seek to minimise the risk to the Council as far as is reasonably
practicable including requirement for adequate business and financial management
and regular reporting by RPC. This funding is to support Rothesay Pavilion Charity in
the first 2 years of the building being operational.
0 750,000 0
006 Executive Director (Douglas
Hendry)
Commercial
Services
Rothesay Pavilion Essential repairs 306,400 0  306,400 0 306,400 Essential repairs to deal with potential health and safety risks and to avoid further
deterioration. Budget provision was approved by the Policy and Resources
Committee on 21 August 2014.
0 306,400 0
007 Executive Director (Douglas
Hendry)
Commercial
Services
Commercial Investment Manager post and
specialist consultant technical resource
(previously Asset Management Fund)
104,000 24,758  79,242 79,242 0 The Asset Management Fund has been redirected to Capital going forward but the
interest for 2023-24 is to be used towards a Commercial Investment Manager Post.
This is because funding of £200k from the Asset Management Fund was agreed at
ELT in June 22 for the post, along with specialist consultancy and technical resources
that will be required to support early projects. Note, the £104k represents the
balance of the £200k commitment.
104,000 0 0
008 Executive Director (Douglas
Hendry)
Commercial
Services
Estates - NDR Revaluation Appeals 59,938 0  59,938 29,969 29,969 The Council agreed to make provision to meet the cost of appealing Non Domestic
Rates (NDR) revaluations which were imposed from April 2017. The remaining funds
were carried forward to the 2023/24 revaluation cycle however a recent change in
position by the Scottish Government may restrict the appeals which can be made.
This is still under discussion and Gerald Eve Surveyors have been appointed as
specialist advisers on this matter, who are progressing 2023-26 appeals. In the event
that appeals are limited there may be an opportunity to utilise Gerald Eve for more
general valuation advice subject to Procurement approval.
29,969 29,969 0
009 Executive Director (Douglas
Hendry)
Commercial
Services
Mid Argyll Community Pool 30,000 30,000  0 0 0 At the Council Budget meeting on 22 February 2024, the Council committed to a one-
off investment of £0.030m to Mid Argyll Community Pool in response to an external
funding request.
30,000 0 0
010 Executive Director (Douglas
Hendry)
Commercial
Services
MacTaggart Leisure Islay 30,000 30,000  0 0 0 At the Council Budget meeting on 22 February 2024, the Council committed to a one-
off investment of £0.030m to MacTaggart Leisure, Islay in response to an external
funding request.
30,000 0 0

Page 126

Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
011 Executive Director (Douglas
Hendry)
Commercial
Services
Site Investigation Works 21,013 0  21,013 21,013 0 For Site Investigation works in relation to Tweeddale Street Car Park and Oban
Airport Business Park, exploring commercial opportunities to develop the sites and
raise revenue income for Argyll and Bute Council. HUB North were instructed to
procure contractors to undertake the site investigations these are now complete.
The remainder of the budget is intended to be utilised for other site investigation
and pre-development works to further develop commercial opportunities across the
council area.
21,013 0 0
012 Executive Director (Douglas
Hendry)
Education ASN Review 1,255,000 0  1,255,000 565,000 690,000 To fund capital costs of ASN adaptations as part of ASN Review to increase equity of
provision across Argyll and Bute. This will be subject to a business case as part of
the wider ASN review. Update: Business case now approved and working group set
up with quotes for works being carried out Jan 2024.
565,000 690,000 0
013 Executive Director (Douglas
Hendry)
Education Reduced Teacher Staffing Costs - Strike
Action
800,000 800,000  0 0 0 To fund one off savings in 2024-25 from the underspend in staffing from strike
action.
800,000 0 0
014 Executive Director (Douglas
Hendry)
Education (2023 Digital Projects) School WiFi
Upgrades
166,924 0  166,924 166,924 0 To extend WiFi coverage within school settings through the purchase of additional
hardware such as access points, switches and other networking hardware. This will
result in more flexible learning spaces and support the growing number of devices
within schools. Project now underway and if budget not fully utilised it is hoped that
the balance could be diverted to assist with Capital costs of Education Network
Paper.
166,924 0 0
015 Executive Director (Douglas
Hendry)
Education Education Transformation Fund 144,637 0  144,637 0 144,637 At the Council meeting on 27 February 2020, it was agreed to input £400k into
Education Digital Learning. The additional funds have been spent in 20/21, 21/22
and 22/23 as part of the ongoing transformation work in the Education service,
focussing on digital and virtual learning technology and the development of learning
clusters.
0 144,637 0
016 Executive Director (Douglas
Hendry)
Education MCR Pathways Pilot 80,000 0  80,000 80,000 0 Funding to support implementation of MCR Pathways mentoring programme within
three secondary schools for 2023-24 academic year. Funding will allow the
employment of a dedicated Co-ordinator within each setting to develop and
implement the programme which is designed to benefit care experienced and other
disadvantaged pupils through targeted mentoring support.
80,000 0 0
017 Executive Director (Douglas
Hendry)
Education Gaelic Specific Grant 30,000 30,000  0 0 0 Gaellic Specific Grant £30k - This earmarking refers to the Council contribution
towards the Gaelic grant for 22-23 and will fund the costs of Gaelic Language
Principal Teacher in 24-25 academic year.
30,000 0 0
018 Executive Director (Douglas
Hendry)
Education (2023 Digital Projects) Cashless Catering 30,000 4,996  25,004 5,004 0 To support the ongoing implementation of the new cashless catering system during
the testing and roll out phase.
10,000 0 0
019 Executive Director (Douglas
Hendry)
Education Skype for Business for Education / Digital
Projects (Skype for Business)
10,000 0  10,000 0 10,000 To fund the initial capital costs for the implementation of Skype for Business for
Education. This will bring the Education service in line with other council
departments and will improve staff collaboration and modernise school telephony
to deliver the service more efficiently and cost effectively.
0 10,000 0
020 Executive Director (Douglas
Hendry)
Education Education Learning Estate Condition
Surveys
1,815 0  1,815 0 0 To fund the delivery of School Core Facts (SCF) compliant Condition Surveys for
prioritised School Buildings.
0 0 0
021 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
Education Purchasing Officers 210,000 0  210,000 168,000 42,000 The earmarked funds will be used to fund an education purchasing team within the
Procurement Service for two years. The team will embed good procurement
practice, train headteachers on current procurement process requirements, develop
spend plans that evidence best value.
168,000 42,000 0
022 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
Information Management (Digitalisation of
Title Deeds)
92,000 0  92,000 20,500 71,500 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of
change as outlined in the BV Review. The planned initiatives include: Estates Survey
work £122k, Digitalisation of Title Deeds £92k (delay on spending due to COVID-19),
document management and workflow system for Planning, Building Standards and
Environmental Health £77k and a balance of funding to explore information
management solutions in a strategic and coherent way £209k
20,500 51,000 20,500
023 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
(2023 Digital Projects) Replacement of
Council Chambers Online Meeting
Equipment
50,071 5,353  44,718 0 44,718 Current online meeting system is less than resilient and has failed on a number of
occasions, leading to issues at strategic committees. A condition assessment by the
incumbent maintenance contractor has highlighted that the current equipment is
now at end of life and unsupportable due to the obsolescence of the system.
Discussions with ICT have taken place to identify a simpler more robust solution to
be procured. 
NUWAY system and maintenance, system installed, ongoing maintenance contract
to 2030
5,353 44,718 0
024 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
Councillor IT Equipment 44,557 0  44,557 22,000 22,557 There is currently no budget for the provision and renewal of IT equipment for
members. The earmarking identifies a resource to utilise spend for that purpose to
ensure that members have continued support in maintaining and replacing vital IT
equipment.
22,000 22,557 0

Page 127

Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
025 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
Digital Projects: Hybrid Council meetings 43,302 12,000  31,302 0 0 The funding will be used to maintain the ICT equipment used to support the
provision of on-line and hybrid Council meetings. Will be used to fund Public-I
licence over 3 years - for livestreaming Council meetings.
12,000 0 0
026 Executive Director (Douglas
Hendry)
Legal and
Regulatory
Support
Debt Counselling & Welfare Rights 21,452 5,265  16,187 735 0 To meet the cost of a Debt Counselling and Welfare Rights Management System. 6,000 0 0
027 Executive Director (Douglas
Hendry)
Non
Departmental /
Legal and
Regulatory
Services
Community Resilience Fund 71,999 0  71,999 5,000 0 Fund established in 2012/13 to be spent over more than one year. Fund reduced at
the Council meeting on 11 February 2016. Used to cover the costs of emergency
phone lines and a contract with Aggreko for generators if required in an Emergency
Planning/Civil contingencies incident. These costs amount to approximately £5k per
year.
5,000 0 0
028 Executive Director (Kirsty Flanagan) Across Services /
Customer Support
Services
Digital Projects (Increase in Schools
Bandwidth)
63,455 0  63,455 0 63,455 To complete one of a number of Digital Service Transformation projects with a
commitment of £0.064m to increase Schools Bandwidth.
0 0 63,455
029 Executive Director (Kirsty Flanagan) Across Services /
Customer Support
Services
Digital Projects (Replacement Learning
Management System)
11,470 0  11,470 11,470 0 To deliver a number of Digital Service Transformation Projects with an original
commitment of £0.030m towards a replacement Learning Management System
£0.030m. This money will be used to pay for consultancy for an interface between
itrent and totara. Profiled for 24/25 based on decision to do a phased
implementation of itrent.
11,470 0 0
030 Executive Director (Kirsty Flanagan) Across Services /
Development and
Economic Growth
Information Management (Document
Management and Workflow for Planning,
Building Standards and Environmental
Health)
21,177 0  21,177 21,177 0 Hoping to implement the replacement for IDOX in March 2024 but there have been
severe issues/delays with the new programme
21,177 0 0
031 Executive Director (Kirsty Flanagan) Customer Support
Services
(2023 Digital Projects) iTrent Project 320,555 0  320,555 320,555 0 Combination of parallel running of the new iTrent system alongside the legacy
systems for up to 18 months whilst iTrent is implemented and additional staffing
resource to implement iTrent in late June 2024 and support staff for the first 3
months of operation through summer 2024. Total includes £73k from Financial
services for funding additional staffing resource to implement the payroll
components of the iTrent HR and Payroll System by the end of June 2024 and
support staff for the first 3 months of operation during summer 2024.
320,555 0 0
032 Executive Director (Kirsty Flanagan) Customer Support
Services
Growing our Own and Modern Apprentices 109,150 0  109,150 44,000 25,150 Funding earmarked to support trainee development and modern apprenticeship
opportunities based on priority workforce risk areas. A Trainee Regulatory Services
post has been proposed by the manager who was unable to secure a suitable
candidate for the original advert. The spend would be spread over 24/25 and 25/26
once a suitable candidate is in post
44,000 25,150 0
033 Executive Director (Kirsty Flanagan) Customer Support
Services
Security Operations Centre Subscription 71,188 0  71,188 0 71,188 There is a requirement to pay for a 3-year subscription at £60,000 per annum with a
cost pressure being added to the ICT revenue budget to cover the costs from 2026-
27 onwards.
0 71,188 0
034 Executive Director (Kirsty Flanagan) Customer Support
Services
(2023 Digital Projects) Resilient Website
Project
60,000 0  60,000 60,000 0 Cybersecurity action to move to a cloud based website platform that would improve
resilience and enable service continuity in the event of a cyber attack. Procurement
in progress for resilient website solution and Scotgov Cloud Services Project
providing input. Contract Award expected by end 2023. Procurement in progress for
resilient website solution. Contract Award expected FQ1 2024-5 and full £60k
spend in that year. Payment milestones in CARR will be 25% on Contract Award, 25%
on Cloud Site Provisioning, 25% on Site migration and 25% on full go live cutover.
60,000 0 0
035 Executive Director (Kirsty Flanagan) Customer Support
Services
(2023 Digital Projects) Digital Project
Officer
34,121 0  34,121 34,121 0 Employ a temporary Digital Project Officer as part of OD changes - additional
member of staff required to action changes, unable to recruit so existing staff
increasing hours.
34,121 0 0
036 Executive Director (Kirsty Flanagan) Customer Support
Services
Implementation of Gaelic Language Plan 30,000 0  30,000 10,000 20,000 Agreed at Council Meeting February 2021. Provision of funding for delivery and
implementation of the council’s Gaelic Language Plan in recognition of the
contribution that Gaelic makes to economic growth and to the tourism sector, and
to enable delivery of key activities within the plan which currently receive no
revenue funding. In discussion with Bord na Gaidhlig about a 3-year Gaelic Plan
funding programme as opposed to individual grant applications for specific projects.
This earmarking would be used to provide match funding for that 3 year programme
of projects.
10,000 20,000 0

Page 128

Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
037 Executive Director (Kirsty Flanagan) Customer Support
Services
Business Development Training 27,025 0  27,025 10,000 17,025 £27k budget from original Business Development Training earmarking remaining at
31/03/24. This budget is funding ongoing leadership development, coaching, action
learning sets and commissioned training including Priority Management.
10,000 17,025 0
038 Executive Director (Kirsty Flanagan) Customer Support
Services
Learning and Development 19,436 0  19,436 10,000 9,436 In order to maximise the opportunities and efficiencies of digital learning, this
funding will be used to support the extension of digital learning in order to deliver
the Digital Learning Strategy, which was approved in FQ4 20/21. This money is to
support the additional digital learning capacity required to build online elements of
AB365 and other key digital learning as we increase our digital learning offering
linked to the digital skills survey and review of corporate training. Delays in
recruitment meant this has been reprofiled for spend in 24/25
10,000 9,436 0
039 Executive Director (Kirsty Flanagan) Customer Support
Services
(2023 Digital Projects) Digital Engagement
Services Developer
15,677 0  15,677 15,677 0 To fund 50% of a new temporary LGE10 post. The post is a Digital Engagement
Services Developer that will be provide capacity to deliver service efficiencies
through the use of the new CREATE/RPA software. The other 50% of the post can
be funded from a current vacancy.
15,677 0 0
040 Executive Director (Kirsty Flanagan) Customer Support
Services
Establishing HR Service Centre 13,824 0  13,824 13,824 0 To facilitate the implementation of technical efficiency improvements and new
processes. This money will be used to support phase two of the itrent project.
Spend reprofiled for 2024/25 following delays in itrent project.
13,824 0 0
041 Executive Director (Kirsty Flanagan) Development &
Economic Growth
Planning Income 60,000 0  60,000 60,000 0 To fund additional resources to support and develop the Council's planning service.
Whilst recruitment issues within Argyll and Bute were largely been resolved during
2022/23, the requirement for the operation of the DM Service with reduced staffing
levels over an extended period of time, coupled with the increasing demand for
development post-Covid, and uncertainty caused by the introduction of National
Planning Framework 4 has given rise to a substantial backlog of case work and has
had a significant adverse impact on processing times for planning applications. 
Plans to utilise this on additional staff costs in 24-25 in order to reduce the backlog.
60,000 0 0
042 Executive Director (Kirsty Flanagan) Development and
Economic Growth
Oban TIF (Tax Incremental Financing) 214,158 0  214,158 214,158 0 Will be used to fund the TIF Programme office for a further 3 years as well as the
programme office for Rural Growth Deal beyond the funding that was agreed at
Council for this in February 2021.
214,158 0 0
043 Executive Director (Kirsty Flanagan) Development and
Economic Growth
Service Concessions - Priorities Investment
Fund (Project Officer for Housing
Emergency)
200,000 0  200,000 70,000 130,000 As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of
£200,000 from the Priorities Investment Fund to fund a Project Officer to assist in
accelerating the work of the Housing Emergency.
70,000 130,000 0
044 Executive Director (Kirsty Flanagan) Development and
Economic Growth
Strategic Events & Festivals 41,260 0  41,260 41,260 0 At the Council meeting on 25 February 21, a decision was taken to agree £90k
funding for Events and Festivals for 22/23, in order that the application process can
commence during 21/22 and that this agreed figure be augmented by any
underspend remaining from the 20/21 financial year. At 24 February 22, decision
made to agree £90k for 23/24, in order that the application process can commence
during 22/23 and that this agreed figure be augmented by any underspend
remaining from the 21/22 financial year. Applications have been received and
payments will be made in 23-24. Final balance (£41,260) to be spent in 24/25
41,260 0 0
045 Executive Director (Kirsty Flanagan) Development and
Economic Growth
Screen Machine 28,000 0  28,000 28,000 0 At the Council Budget meeting on 22 February 2024, the Council committed to a one-
off investment of £0.028m to Screen Machine in response to an external funding
request.
28,000 0 0
046 Executive Director (Kirsty Flanagan) Development and
Economic Growth
International Eight Metre Association
World Cup
10,000 10,000  0 0 0 At the Council Budget meeting on 22 February 2024, the Council committed to a one-
off investment of £0.010m to the International Eight Metre World Cup in response
to an external funding request.
10,000 0 0
047 Executive Director (Kirsty Flanagan) Financial Services Revenue and Benefits BPR - extra staff to
implement savings targets
86,955 0  86,955 86,955 0 On 23 February 2023, the Council agreed to the implementation of savings option
FIS2324-002 in relation to the Revenue and Benefits - Income Generation and
Business Process Review. This included an extra 4 FTE of staff. Delays in
recruitment have caused slippage in the allocated budget for these posts.
86,955 0 0
048 Executive Director (Kirsty Flanagan) Financial Services Scotland Loves Local 57,453 0  57,453 57,453 0 As agreed by Council 22 February 24, a £57,453 underspend from the Scotland Loves
Local scheme to be allocated to support measures to help with the costs of living by
funding member organisations of the Community Food Forum, ALI Energy, Argyll
and Bute Citizens Advice Bureau and Bute Advice Centre, with detailed proposals to
be agreed by the Executive Director with responsibility for Finance, in consultation
with the Leader, Depute Leader and Leader of the Largest Opposition Group. Details
of the agreed spend are to be reported to elected members.
57,453 0 0

Page 129

Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
049 Executive Director (Kirsty Flanagan) Financial Services Financial Systems 33,748 0  33,748 33,748 0 The council is required to implement the IFRS16 Leases accounting standard from
the 1st April 2024.
33,748 0 0
050 Executive Director (Kirsty Flanagan) Financial Services Accounting and Budgeting Team Resilience 47,883 0  47,883 8,000 39,883 Training and examination fees for 6 staff who are currently undertaking their
professional CIPFA/ACCA training. In addition funding the further training of 1 of our
auditors and providing finance business partner training to a group of our existing
professional staff.
8,000 8,000 31,883
051 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Waste Variation Monies 1,241,752 30,929  1,210,823 550,823 660,000 Waste Variation Monies - £1.242m balance at 31/03/24: This will be used to
fund/part-fund various waste infrastructure projects that will support the council’s
compliance with the 2026 ban on the Landfill of Biodegradable Municipal Waste.
£582K in 2024-25 consisting of :- Island restoration/capping, Helensburgh transfer
station, recycling improve. fund (island sites) design costs, recycling campaign
publicity, technology trial on blue bin recycling participation, consultancy costs
relating to additional monitoring data for SEPA and waste PPP site conversion.
£660K in 2025-26 consisting of:- Island restoration/capping, Helensburgh transfer
station design costs during construction, consultancy costs relating to additional
monitoring data for SEPA and waste PPP site conversion.
581,752 660,000 0
052 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Service Concessions - Priorities Investment
Fund (Strategic Development Framework)
450,000 0  450,000 225,000 225,000 As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of
£450,000 to procure consultancy support to assist in driving forward the Strategic
Development Frameworks.
225,000 225,000 0
053 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
3G pitches / Tarbert Sports Pitches 287,835 81,158  206,677 7,149 199,528 In November 2018, the Council agreed to a maintenance funding package to be
progressed for a number of 3G pitches including Tarbert. This funding will provide
an estimated 6.5 years’ worth of ongoing maintenance up to 2025-26. There is the
potential to extend the continued upkeep of the pitches until 2026-27 given the
earmarking available will not be fully utilised by the end of 2025-26. However, there
will be potential redundancy costs for 2 employees that will need to be covered
from the remaining balance. Paper on proposed extension to be prepared.
88,307 199,528 0
054 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Green Transport Initiatives 140,000 0  140,000 140,000 0 At the Council meeting on 27 February 2020, it was agreed to input £400k in Green
transport, investment in footway and cycle path maintenance supporting the
healthy wellbeing and green agenda. Spend has been delayed due to COVID and
this will be taken forward in 23/24. £260k Footways Reconstruction programme now
spent and will be drawn down against capital programme during 23/24. £140k
Ardrishaig North Project spent in 22/23 and drawn down in 24/25 (capital
expenditure).
140,000 0 0
055 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Climate Change 40,942 0  40,942 40,942 0 At the Council meeting on 27 February 2020, it was agreed to input £500k budget to
mitigate the impacts of weather related damage and climate change with specific
emphasis on gully cleaning and drainage improvements. Spend has been delayed
due to COVID and the intention is to spend the funds on 2 Gully Motors plus staff
over next 2 years. Vehicles have been received and budget will be drawn down to
cover their cost. The remaining budget will be used towards running the vehicles.
40,942 0 0
056 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Amenity Services introduction of
management information system
28,099 0  28,099 0 0 Delay with introduction of amenity time recording system due to increased costs.
Discussions ongoing to find alternative cheaper solution. The software/system
being introduced by HR/Payroll during 2023-24 offers a time-recording facility.
Although not included in the current HR/Payroll spec, once the new system is up and
running, the proposal would be to investigate the time-recording system to see if
viable for amenity time recording purposes.
0 0 0
057 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Services
(2023 Contract Inflation Adjustments)
Waste PPP
223,261 0  223,261 223,261 0 Proposal to merge with ref 134, to be used to assist with the Council's compliance
with the 2026 ban on the Landfill of Biodegradable Municipal Waste and supporting
the overall Waste Strategy.
223,261 0 0
058 Executive Director (Kirsty Flanagan) Roads and
Infrastructure
Services
Weather Incident costs not covered by
Bellwin claim.
198,000 0  198,000 198,000 0 £839k was set aside at budget meeting in February 2024 as part of the unallocated
general fund balance workings to cover the weather incident costs not covered by
the Bellwin Claim. As £641k was utilised during 23-24, the balance of £0.198m is
being earmarked for costs expected in 24-25.
198,000 0 0
059 Non Departmental Non
Departmental
Service Concessions - Replace previous
loans fund principal repayment holiday
5,400,000 0  5,400,000 5,400,000 0 As agreed at Council meeting 23 February 2023 - The one-off retrospective benefit
will be used to replace exercising the principal repayment holiday that was
previously agreed by Council.
5,400,000 0 0
060 Non Departmental Non
Departmental
Pay Inflation Contingency 1,700,000 0  1,700,000 1,700,000 0 Negotiations for the 2024/25 pay award are ongoing but initial discussions suggest it
will be beyond the 3% increase currently built into the budget outlook. £1.7m
equates to approximately a 1% pay rise therefore providing a contingency at this
level is prudent
1,700,000 0 0

Page 130

Ref Department Service Description Opening
Balance
Budget
Drawdown
New
earmarkings
in year
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
061 Non Departmental Non
Departmental
Underwriting development of Rothesay
Pavilion
1,000,000 0  1,000,000 1,000,000 0 Funding to meet additional costs identified as necessary for the refurbishment of
Rothesay Pavilion (£1m).
1,000,000 0 0
062 Non Departmental Non
Departmental
Oban TIF (Tax Incremental Financing -
Excess NDR)
875,651 0  875,651 0 875,651 This is the surplus NDR after paying all Loans Charges in respect of TIF infrastructure
projects. This fund will be used in the future as TIF projects are delivered.
Discussions in place on future ff the next TIF project (Oban Airport) which will utilise
this reserve. If the project does not go ahead, we will need to return NDR to
Scottish Government
0 875,651 0
063 Non Departmental Non
Departmental
Treasury Gain 294,000 294,000  0 0 0 To fund one off operational saving 202425 003 as agreed by Council when setting
2024/25 budget in February 2024.
294,000 0 0
064 Non Departmental Non
Departmental
Information Management (Balance of
Funding)
200,469 0  200,469 200,469 0 To support a number of initiatives in respect of improving the Council's information
management in line with the transformation agenda and increasing the pace of
change as outlined in the BV Review. This was the balance of funding to explore
information management solutions in a strategic and coherent way £209k.
Committed for MS 365 project - D Logan/I Jackson. Paper went to DMT in Dec.
200,469 0 0
065 Non Departmental Non
Departmental
Engagement with Hub North re provision
of services for older adults and vulnerable
people across Argyll and Bute
100,000 0  100,000 70,000 30,000 At the Council budget meeting February 23, an allocation of £0.1m from the
Unallocated General Fund balance for the Health and Social Care Partnership to
engage, in partnership with the Council, with Hub North to develop a strategic
business case in relation to the provision of services for older adults and other
vulnerable people across Argyll and Bute. It is intended that this will be spent on an
on-going business case and options appraisal work with Hub and that a sizable
proportion will be spent during 24/25
70,000 30,000 0
066 Non Departmental Non
Departmental
Spend to Save Route Optimisation
Software
82,775 0  82,775 0 82,775 One-off re-profiling gain as a result of the loans fund review to fund known
liabilities/cost pressures as agreed at budget setting meeting in February 2020. The
route optimisation project has been delayed due to staff turnover and absences,
recent meetings involving the Council and Routewear have set out future objectives
and the project has been extended to 2025-26.
0 82,775 0
067 Non Departmental Non
Departmental
CHARTS 80,000 55,000  25,000 25,000 0 At the Council Budget meeting on 22 February 2024, the Council committed to
£0.075m one-off investment in CHARTS in response to an external funding request
will be spent in 24-25. There remains £0.005m from a COVID earmarking for CHARTS
as well.
80,000 0 0
068 Non Departmental Non
Departmental
Council Strathclyde Pension Fund Saving 24-
25 (£2m to balance 24-25 budget) 
2,000,000 2,000,000 0 0 0 This is part of the revenue budget for 24-25 and is the saving on pension budgets
resulting from the drop in employers pension rate. The total of £6.875m is split as
follows: £2m to balance the budget, £3.75m allocation to capital plan, per budget
meeting 22 February 24 and the balance of £1.125m going towards what will be
total of £2m over the two years pot to be directed to transformation and projects
that will save revenue in the future.
2,000,000  
069 Non Departmental Non
Departmental
Council Strathclyde Pension Fund Saving 24-
25 (£3.75m allocation to capital plan) 
0 3,750,000 3,750,000 0 3,750,000 This is part of the revenue budget for 24-25 and is the saving on pension budgets
resulting from the drop in employers pension rate. The total of £6.875m is split as
follows: £2m to balance the budget, £3.75m allocation to capital plan, per budget
meeting 22 February 24 and the balance of £1.125m going towards what will be
total of £2m over the two years pot to be directed to transformation and projects
that will save revenue in the future. 
0 3,750,000
070 Non Departmental Non
Departmental
Council Strathclyde Pension Fund Saving 24-
25 (£2m to be directed to transformation
and projects that will save revenue in the
future) 
0 1,125,000 1,125,000 0 1,125,000 This is part of the revenue budget for 24-25 and is the saving on pension budgets
resulting from the drop in employers pension rate. The total of £6.875m is split as
follows: £2m to balance the budget, £3.75m allocation to capital plan, per budget
meeting 22 February 24 and the balance of £1.125m going towards what will be
total of £2m over the two years pot to be directed to transformation and projects
that will save revenue in the future.  
1,125,000
071 Non Departmental / Social Work Non
Departmental
Social Work Strathclyde Pension Fund
Saving 24-25 
0 3,053,000 3,053,000 0 3,053,000 This is part of the revenue budget for 24-25 and is the saving on Social Work pension
budgets resulting from the drop in employers pension rate - to be held in Council
reserves for utilisation by the HSCP in future.  
3,053,000
072 Non Departmental Non
Departmental
Capital Plan  0 1,875,000 1,875,000 0 1,875,000 At the budget meeting on 22 February 2024, Council agreed to transfer £1.875m
from the revenue budget over to the capital plan.  
1,875,000    
18,509,179 3,500,297 11,803,000 26,811,882 12,139,043 14,469,172  15,639,340 4,550,334 9,918,838

Page 131

APPENDIX 2 
Earmarked Reserves - Service Concessions
As at 31 August 2024 
Ref Department Service Description Opening
Balance
Budget
Drawdown
Remaining
Balance
Still to be
drawndown in
24-25
Planned to
spend in
future years
Plans for Use Amount
Planned to
be Spent in
2024-25
Amount Planned
to be Spent in
2025-26
Amount
Planned to
be Spent
from
2026/27
onwards
001 Chief Executive's Unit Community
Planning
Service Concessions - Priorities Investment
Fund (Area Plans)
200,000 86,838 113,162 13,162 100,000 As agreed by Policy and Resources Committee on 23 October 23 - drawdown of
£200,000 from the Priorities Investment Fund to fund two temporary posts and
associated costs to produce meaningful area plans
100,000 100,000 0
002 Executive Director (Kirsty Flanagan) Development and
Economic Growth
Service Concessions - Priorities Investment
Fund (Project Officer for Housing
Emergency)
200,000 0 200,000 70,000 130,000 As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of
£200,000 from the Priorities Investment Fund to fund a Project Officer to assist in
accelerating the work of the Housing Emergency.
70,000 130,000 0
003 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Service Concessions - Biodegradable
Municipal Waste (BMW) Ban
3,500,000 0 3,500,000 0 3,500,000 As agreed at Council meeting 23 February 2023 - Ensuring Argyll and Bute is able to
better address the challenges faced by a remote/rural/ island region in complying
with the forthcoming national BMW ban.
£1.5m earmarked for revenue pressures with £2m for capital projects, mainly a
Waste Transfer Station in Helensburgh.
0 3,500,000 0
004 Executive Director (Kirsty Flanagan) Roads &
Infrastructure
Service Concessions - Priorities Investment
Fund (Strategic Development Framework)
450,000 0 450,000 225,000 225,000 As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of
£450,000 to procure consultancy support to assist in driving forward the Strategic
Development Frameworks.
225,000 225,000 0
005 Non Departmental Non Departmental Service Concessions - Learning Estate
Investment Strategy
8,000,000 0 8,000,000 0 8,000,000 As agreed at Council meeting 23 February 2023 - Signalling council’s commitment to
working in partnership to secure new schools for Argyll and Bute, through substantial
investment to support future-proofing of Argyll and Bute’s schools estate.
0 8,000,000 0
006 Non Departmental Non Departmental Service Concessions - Replace previous
loans fund principal repayment holiday
5,400,000 0 5,400,000 5,400,000 0 As agreed at Council meeting 23 February 2023 - The one-off retrospective benefit
will be used to replace exercising the principal repayment holiday that was previously
agreed by Council.
5,400,000 0 0
007 Non Departmental Non Departmental Service Concessions - Rothesay Pavilion 4,772,000 0 4,772,000 0 4,772,000 As agreed at Council meeting 23 February 2023 - Building on previous commitments
to securing a future for this building of international, national and local significance
with additional contribution to the overall funding target which requires collective
action; helping project to progress towards success with funding that supports
completion of certain work stages and securing wind/watertight status.
0 4,772,000 0
008 Non Departmental Non Departmental Service Concessions - Priorities Investment
Fund
4,742,000 758,000 3,984,000 0 3,984,000 As agreed at Council meeting 23 February 2023 - Safeguarding future investment in
Priorities for Argyll and Bute by making long-term use of service concession gain to
establish dedicated fund to lever in, secure and support key strategic investments in
this year and future years.
758,000 3,984,000 0
009 Non Departmental Non Departmental Service Concessions - Roads Investment to
Capital
3,546,000 0 3,546,000 0 3,546,000 As agreed at Council meeting 23 February 2023 - Augmenting overall allocation for
roads repair and maintenance programme with additional funds to bring up to £8m
total investment for 2024/25.
0 3,546,000 0
010 Non Departmental Non Departmental Service Concessions - Capital Projects
Inflation Pressures
2,000,000 0 2,000,000 0 2,000,000 As agreed at Council meeting 23 February 2023 -Boosting resilience of Capital
Programme and providing added support as required for key capital/infrastructure
projects - £2m.
Further allocation agreed Council meeting 22 February 24 - increase capital contract
earmarking to protect current capital projects in plan £0.297m
0 2,000,000 0
011 Non Departmental Non Departmental Service Concessions - Priorities Investment
Fund (Capital Programme)
1,028,000 0 1,028,000 0 1,028,000 As agreed by Council on 22 February 2024- transfer of £1,028,000 from the Priorities
Investment Fund to the Capital plan 
1,028,000 0
012 Non Departmental Non Departmental Service Concessions - New refuse collection
vehicles
700,000 0 700,000 700,000 0 As agreed at Council meeting 23 February 2023 - Enhancing waste and recycling uplift
arrangements through placing orders for new refuse vehicles.
700,000 0 0
013 Non Departmental Non Departmental Service Concessions - Climate Change 640,000 9,331 630,669 -9,331 640,000 As agreed at Council meeting 23 February 2023 - Continuing our track record of
investing in climate change with funding to further enhance school estate climate
change measures, with allocations for primary and secondary schools across the area
in Campbeltown, Dunoon, Helensburgh, Lochgilphead, Oban and Rothesay.
0 640,000 0
014 Non Departmental Non Departmental Service Concessions - New Jet Patcher
Vehicle
250,000 0 250,000 250,000 0 As agreed at Council meeting 23 February 2023 - Complementing multi-million pound
capital investment in roads repair and maintenance with new jet patcher order to
support delivery of programme.
250,000 0 0
015 Non Departmental Non Departmental Service Concessions - New Road Marking
Vehicle
230,000 0 230,000 0 230,000 As agreed at Council meeting 23 February 2023 - Completing suite of investments in
new fleet procurement, to support delivery of roads repair and maintenance
programme, with order for additional road marking vehicle.
0 230,000 0   
35,658,000 854,169 34,803,831 6,648,831 28,155,000  7,503,000 28,155,000 0