ARGYLL AND BUTE COUNCIL     POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD           5 December 2024 
CLIMATE CHANGE BOARD UPDATE & DECARBONISATION TRACKER 
1.0 EXECUTIVE SUMMARY  
1.1 This report provides an overview of key highlights from the Decarbonisation
Plan Tracker, offering a strategic snapshot of recent progress. Significant
developments include the completion of an 86kW solar PV system at
Cardross Primary School and substantial progress in our LED streetlight
replacement programme, which has reduced annual CO2 emissions by 92%
since 2015/16.Through strategic funding management, we have secured and
begun implementing £1,979,827 from the Energy Efficient Scotland
Programme and £2.56M for active travel initiatives. Our electric vehicle
infrastructure now includes 37 charging points, while waste management has
been strengthened by £1.5 million in Scottish Government funding for landfill
ban compliance.  
1.2      Community engagement continues to expand through our partnership with
Argyll Community Trust (ACT), supporting 39 community groups and
establishing specialist environmental teams for rainforest and peatland
restoration. The Net Zero Route Map is being rescoped with external partners,
complemented by our adoption of the Scottish Government's ClimateOS
platform to enhance our climate action planning capabilities.  
1.3    These achievements demonstrate Argyll and Bute Council's ongoing
commitment to climate action, balancing infrastructure improvements with
community engagement and strategic planning to advance our
decarbonisation goals. 
2.0  RECOMMENDATIONS 
2.1  The Policy and Resources Committee are asked to consider the updates
contained at Section 5  of the report and the full Decarbonisation Tracker update
contained within Appendix A.

Page 2

ARGYLL AND BUTE COUNCIL      POLICY & RESOURCES COMMITTEE
CLIMATE CHANGE BOARD         5 December 2024 
CLIMATE CHANGE BOARD UPDATE & DECARBONISATION TRACKER 
3.0 INTRODUCTION 
3.1  This report provides an overview of key highlights from the Decarbonisation
Plan Tracker, offering a strategic snapshot of recent progress. Significant
developments include the completion of an 86kW solar PV system at
Cardross Primary School and substantial progress in our LED streetlight
replacement programme, which has reduced annual CO2 emissions by 92%
since 2015/16. Through strategic funding management, we have secured and
begun implementing £1,979,827 from the Energy Efficient Scotland
Programme and £2.56M for active travel initiatives. Our electric vehicle
infrastructure now includes 37 charging points, while waste management has
been strengthened by £1.5 million in Scottish Government funding for landfill
ban compliance.  
3.2 Community engagement continues to expand through our partnership with
Argyll Community Trust (ACT), supporting 39 community groups and
establishing specialist environmental teams for rainforest and peatland
restoration. The Net Zero Route Map is being rescoped with external partners,
complemented by our adoption of the Scottish Government's ClimateOS
platform to enhance our climate action planning capabilities.  
3.3 These achievements demonstrate Argyll and Bute Council's ongoing
commitment to climate action, balancing infrastructure improvements with
community engagement and strategic planning to advance our
decarbonisation goals. 
4.0       RECOMMENDATIONS 
4.1 The Policy and Resources Committee are asked to consider the updates
contained at Section 5  of the report and the full Decarbonisation Tracker update
contained within Appendix A.

Page 3

5.0 SUMMARY UPDATES OF CLIMATE CHANGE BOARD 
5.1 Renewable Energy and Energy Efficiency
5.1.1 Notable recent projects include the 86kW roof-mounted solar PV system at
Cardross Primary School, commissioned during the October 2024 school
holidays. Through the Non-Domestic Energy Efficiency Framework (NDEEF),
we have invested £1,520,315 of the £1,979,827 Scottish Government grant in
energy efficiency projects, with key installations at Tarbert School, Kilmory
Nursery, and Cardross Primary School. 
5.1.2  The ongoing LED streetlight replacement programme has already
transformed 14,312 streetlights, with approximately 130 luminaires remaining
to be upgraded in the Lorn Area. These luminaires are on order, and works
are expected to be completed by the end of 2024. This comprehensive
upgrade has significantly reduced carbon emissions, with annual CO2
emissions dropping from 3,140 tonnes in 2015/16 to just 264 tonnes year-to-
date in September 2024.   
5.1.3 The procurement strategy for the next batch of sites (NDEEF2) is underway,
targeting a £2 Million spend-to-save investment. We are currently awaiting the
Scottish Government's launch of the new NDEEF framework, now anticipated
in January/February 2025. 
5.1.4 In September 2024, Argyll and Bute Council was awarded £1,979,827 through
the Scottish Government's Energy Efficient Scotland – Area Based Scheme
(ABS). To date, £1,520,315 has been spent facilitating insulation measures
for privately owned and privately rented properties across mainland and island
addresses. The programme offers non-means tested grants between £9,000
and £21,600 to eligible households, supporting a "Fabric First" approach to
reducing household energy consumption. A joint project with Argyll
Community Housing Association has already seen 80 properties insulated in
Bute and Tarbert, contributing to both the Council's and Scottish
Government's carbon reduction targets.  
5.2 Economic Development and Renewable Energy
5.2.1 The council continues to support the Argyll and Bute Renewable Association
(ABRA), with meetings held in October 2024 to review the Renewable Energy
Action Plan. Progress has been made on strategic energy initiatives, including
ongoing discussions with SSE Networks about grid capacity upgrades to
275kV. The Carbon Neutral Islands programme has seen significant
developments, with funding secured for two projects on Islay through the
Carbon Neutral Islands Capital Fund. These projects, being delivered by Islay
Energy Trust and Islay Development Initiative, include solar installations on
community buildings and a community orchard and forestry project. The Rural
Growth Deal's Low Carbon Islay project continues to progress, with amended
proposals being prepared following an initial outline business case rejection.   
5.2.3 Offshore renewable developments continue to advance. Scottish Power
Renewables are progressing the Machair Wind project, expected to seek
consent during the mid-2020s. ESB is developing the Malin Wind project, a

Page 4

floating wind proposal awarded through the INTOG leasing round, with
generation anticipated in the early 2030s.  
5.3 Active Travel and Transportation
5.3.1 The council has expanded its electric vehicle charging network to 37 charging
points, with eight new rapid chargers installed through the HiTRANS funding
programme. 
5.3.2 The Active Travel Team secured £2.56M external challenge funding for 22
active travel projects across Argyll and Bute in 2023/24. Key developments
include creating smartphone apps for Tobermory and Bowmore and
progressing design work for various town routes. The Oban Town Centre
North Active Travel Improvements concept design was rejected by the OLI
Area Committee on 25 June 2024. Officers continue working to develop an
Argyll and Bute Active Travel Strategy to be presented to elected members by
the end of 2024, which is increasingly becoming a pre-requirement for
accessing Scottish Government active travel funding.   
5.3.3 The strategy development references recent census data highlighting that
20% of households have no car access, and 34% are multiple car
households, underscoring the importance of alternative travel options.
5.3.4 A key strategic development is the opportunity to develop a comprehensive
Council Travel Plan in 2024/25, with initial external support funded by
Strathclyde Partnership for Transport (SPT). This initiative requires cross-
service collaboration, particularly from Commercial Services for estates and
property considerations, Financial Services regarding travel expenses, and
HR & OD for future travel policy development. This corporate approach will
help embed sustainable travel practices across council operations. 
5.4 Water Efficiency 
5.4.1 The Water Efficiency Audit programme has made significant progress, with a
comprehensive asset verification exercise substantially complete. Material
water savings have been identified and recovered, with a focused programme
to introduce water efficiency measures set to conclude by Q1 2025. Reducing
our consumption of water not only reduces carbon footprint and reduces bills
but also enhances our resilience to changing climate conditions. 
5.5 Net Zero Route Map (NZRM)
5.5.1 Our Net Zero Route Map is currently being re-scoped, with Request for
Information (RFI) responses received in June 2024. Opportunities to take on
refined set of offers to the market are currently being explored. We are
pursuing a collaborative approach, planning to co-develop the strategy in-
house with specialist external partners. This strategic document will be crucial
in guiding our long-term decarbonisation efforts.
5.5.2 As part of the Scottish Government's national implementation programme,
Argyll and Bute Council has adopted the ClimateOS platform, developed by
ClimateView. This Impact Intelligence platform supports our climate transition
planning through advanced emissions modelling and data analysis. The
Climate Change Officer and LHEES Officer are currently undertaking training

Page 5

through the Scottish Climate Intelligence Service (SCIS) to maximise the
platform's capabilities. This strategic development, which connects our local
authority with all 32 Scottish councils through interconnected emissions data,
will be crucial in guiding our long-term decarbonisation efforts and supporting
evidence-based decision making. 
5.6 Community and Environmental Engagement
5.6.1 Our partnership with Argyll Community Trust (ACT) continues to drive climate
action. We have supported 39 community groups with climate action funding,
initiated Carbon Literacy training programs, and are developing a Climate
Action Strategy aligned with the Community Planning Partnership's objectives.
5.6.2 ACT has established a Rainforest Squad with National Lottery Heritage Fund
support, focusing on woodland management in North Knapdale and recruiting
specialists for rainforest restoration. Peatland restoration projects continue on
Islay, Jura, and mainland Argyll, with ACT now employing 34 people in the
environmental sector. 
5.6.3 The Climate Action Strategy's second draft was reviewed by the Climate
Change Working Group in October, with plans to submit a final version to the
CPP Management Committee by year-end. ABCAN has collaborated with
Sniffer/Adaptation Scotland to develop a bilingual 'Climate Community
Adaptation Routemap' launched during Mod week in Oban. 
5.6.4 Carbon Literacy Training continues through the Cooler Futures schools
programme, with the first Primary 7 cohort completing full Carbon Literacy. A
climate change learning festival is planned for Lochgilphead Joint Campus,
focusing on education and sustainable skills development.   
5.7 Communication and Outreach
5.7.1 External communications continue to promote actions the council is taking,
and actions that others can take, to develop a climate-friendly Argyll and Bute.
Key initiatives include: 
The council has actively lobbied for funding to protect lifeline routes and
infrastructure against severe weather impacts. Communications have focused
on diverse climate action messages, including the Better Journeys Campaign,
promotion of active travel apps, and encouraging community participation in
climate initiatives. 
Notable communication efforts have highlighted: 
• Scottish Government Flood Resilience consultation. 
• Council securing Scottish Government funding for waste ban
compliance.
• Hermitage being recognised by Keep Scotland Beautiful as one of
Scotland's best green spaces. 
• Argyll and Bute Carbon Literacy Network offering free climate change
training.

Page 6

• Social media campaigns encouraging recycling and waste reduction. 
• Press release highlighting a 6% reduction in carbon emissions in
2022/23, resulting in an overall 32.8% reduction since reporting began
in 2015/16. 
5.7.2 Specific campaigns have included the Better Journeys photo competition,
promotion of walking routes, pre-loved school uniform scheme, and
engagement during Scottish Climate Week with daily social media posts.   
6.0 CONCLUSION
6.1 Argyll and Bute Council continues to demonstrate leadership in local climate
action, making meaningful progress across environmental, social, and
infrastructure domains. Our strategic approach balances innovative project
implementation, community engagement, and fiscal responsibility, positioning
us at the forefront of local government climate response. 
7.0 IMPLICATIONS
7.1 Policy – Meeting obligations and commitment to Climate Change.
7.2 Financial – No direct linkage in this paper.
7.3  Legal – Meeting requirements of the Climate Change (Scotland) Act 2009,
and   the Climate Change (Emissions Reduction Targets) (Scotland) Act 2019.
7.4  HR – None.
7.5  Fairer Scotland Duty: 
7.5.1   Equalities - protected characteristics – None. 
7.5.2   Socio-economic Duty – None. 
7.5.3  Islands – None.
7.6 Climate Change – Direct link updating activities of the Climate Change Board
and projects that will address climate change. 
7.7 Risk – Not addressing impacts or causes of climate change can lead to  
increased cost or censure if targets are not met.
7.8  Customer Service – None.
7.9      UNCRC – United Nations Convention on the Rights of the Child - None 
Douglas Hendry, Executive Director with responsibility for Commercial
Services

Page 7

Policy Lead Climate Change & Environment, Councillor Luna Martin 
7 November 2024                                                  
For Further Information:-
Ross McLaughlin, Head of Commercial Services 
Helensburgh and Lomond Civic Centre
ross.mclaughlin@argyll-bute.gov.uk 
APPENDICES
Appendix A – Climate Change Decarbonisation Tracker – November 2024

Page 8

Appendix A – Climate Change Decarbonisation Plan Tracker
ACTION  LEAD (L) AND
PARTNERS 
TARGET or
MILESTONE 
FUNDING  COMMENTS  
W1 –Develop and Implement Waste
Strategy 
(L) Roads and
Amenity Services,
Community,
commercial
customers 
Implementation of
the Waste Strategy
transitioning to
Landfill ban
compliant Residual
Waste Recovery
solutions by 2025. 
External funding and support being
sought from the Scottish
Government 
Please see Environment,
Development & Infrastructure
Reports – links below: 
WASTE UPDATE.pdf (argyll-
bute.gov.uk) Waste Update – EDI
committee 20/6/24 
GENERAL WASTE UPDATE.pdf EDI
committee 12/9/24 
W2 – Promote the Waste Hierarchy
through community Education  
(L) Roads and
Amenity Services 
Evidence of
community
Education 
Not secured  New Web content and Education
materials for Primary and Secondary
Schools were developed and
delivered to online Education
Environment Summit October 21
and the COP 26 Event on the 6th
November 21. Advised that this
action has paused/stopped. 
W3 – Reduce Council use of disposable
and single use plastics across all
departments and settings  
(L) Procurement
and Commercial
Services, all
Council Services  
Adoption of new
working practices
and procurement 
No specific funding in place,
research required to impact on
operation costs 
A report on Single Use Plastic went
to the Policy and Resources
Committee on 9 December 2021,
and the following recommendations
were approved: 
• Note and consider that the
various Services that currently
purchase SUP products consider
whether these products are
essential or if there is a
potential alternative that would

Page 9

meet the Service requirements,
prior to orders being placed via
PECOS or contacting the
Procurement, Commercial and
Contract Management Team
(PCCMT) for a procurement
process to be carried out. 
• Note and consider that the
Sustainable Procurement Policy
will be updated to reflect the
Climate Change Board desire to
limit SUP where possible –
wording has been included in
the Annual Review 2023/2024
version of the Procurement
Strategy 2022/2025 as follows:
“To provide procurement
support to any strategic
decisions taken by the Council in
relation to the usage of Single
Use Plastic products and their
recyclability.”  
• Note and consider that the
Commodity Sourcing Strategy
templates used for Regulated
Procurements have been
updated to include a question
regarding SUP. 
Changes in legislation were brought
into force by the Scottish
Government on the 1st June 2022
restricting single-use plastic cutlery,
plates, straws, drink stirrers and

Page 10

balloon sticks, expanded
polystyrene food containers and
expanded polystyrene cups and
other beverage containers, as well
as all products made of oxo-
degradable plastic.   
Some products already changed and
others under review.  
W4 – Extend and explore pre-ordering
for school food to reduce food waste 
(L) Commercial
Services
and  Education  
Evidence of
extension of pre-
ordering & food
waste reduction 
Project funded and solution
procured 
Full implementation of Cashless
Catering and Pre-ordering system is
completed. 
E1 – Deliver Renewable Sourcing
Strategy 2 
(L) Commercial
Services  
Adoption of
Strategy 
RSS2 consultancy work funding to
be confirmed; expectation is that
project implementation will be
through combinations of prudential
borrowing (subject to business case
approvals) and/or external funding.  
RSS2 next stage development work
includes specification
development and preparation of
invitation to tender for specialist
consultancy support. Current work
in progress; intended to be market
tested early 2024.  It is now
considered that RSS2 will be
included within the Net Zero
Routemap. Following limited
response from hubNorth and
some discussions with other
potential providers, we have gone
to the market with a further RFI
and responses received in June
2024 will be used in the
development of the procurement
strategy for Argyll & Bute Council
Net Zero Routemap.

Page 11

Net Zero Route Map is currently
being rescoped following returns
of RFIs. Opportunities to take a
refined set of offers to the market
are currently being explored. It is
expected the NZRM will be co-
developed in-house alongside
specialist external partner/s. 
E2 – Delivery of Non-domestic Energy
Efficiency Framework (NDEEF)
Projects    
(L) Commercial
Services  
Evidence of delivery
of projects 
Project development work is funded
by combinations of the Scottish
Government and the procured
provider (costs absorbed within the
tender process).  
Funding for project implementation
will come from Council approved
capital allocations: 
• Climate Change 20/21 -
£500K 
• Climate Change 21/22 -
£600K 
• Asset Sustainability
–  £175K 
Non Domestic Energy Efficiency
Fund (NDEEF1) Energy Performance
Contract was signed on 16 July 2021
(circa £1.25m investment with 10
year payback). The originally
intended mini project list has been
fully delivered. Following on from
the P&R Committee report in May
2023: May PR - Climate Change -
NDEEF Progress update.pdf (argyll-
bute.gov.uk), four final mini
projects, which were added as
contract variations, remained to be
implemented. Tarbert School LED
lighting was installed in the 2023
school summer recess; Kilmory
Nursery solar pv was installed in
September 2023; the intended low
carbon heating solution and pv
installation at Cardross PS have
been intentionally delayed whilst we
try to access a recently launched
funding scheme: Scotland’s Public
Sector Heat Decarbonisation Fund |
Salix Finance.  A bid was submitted

Page 12

by the 5/12/23 fund deadline (value
£460K with the Council needing to
contribute 20% of that). Bid
outcomes will be communicated
February 2024.  Bid was
unsuccessful and subsequently
£150k of funding which was in the
2025/26 capital plan for a
replacement heating system has
been brought forward. Delivery of
the high efficiency heating system
will be Summer 2024. High
efficiency heating system installed
and commissioned during Summer
2024 including full BEMS controls
upgrade and 4G wireless router
install for remote monitoring of
system and optimisation of
performance. 
86kW roof mounted solar PV system
installed and commissioned at
Cardross Primary School during
October 2024 school holidays. This
was the final NDEEF1 mini project
and now concludes the installation
phase of this project. The
Monitoring and Verification (M+V)
Phase undertaken by the
independent M+V Specialists EEVS
Insight Ltd will run until Q3 2025.
The final 15% contract retention
payment will be released on

Page 13

successful independent verification
of the Investment Grade Proposal
(IGP) energy savings. 
In addition to the above, the
procurement sourcing strategy for
the next batch of sites, using
designation NDEEF2, is under
way.  A spend to save investment of
£2Million is being
targeted.  Awaiting formal Scottish
Government launch of new NDEEF
framework which is currently
expected Oct 2024.  Launch date of
new framework now anticipated to
be Jan/Feb 2025. 
E3 – Delivery of additional solar
installations at Council assets    
(L) Commercial
Services  
Evidence of delivery
of projects 
Consultancy work funding to be
confirmed; expectation is that
project implementation will be
through combinations of prudential
borrowing (subject to business case
approvals) and/or external funding. 
Best solar pv opportunities are
being delivered within NDEEF (Ref
item E2) and advantage is also being
taken to install solar pv solutions
within the asset sustainability
capital programme where
possible  e.g. as a component of
roof upgrades. 
The potential for a large solar pv
ground array at the Kilmory Estate is
currently being limited due to
electric grid constraints –
engagement with SSEN is ongoing to
try to identify solutions.

Page 14

The Council now has 27no solar pv
installations in operation amounting
to over 1.3MW capacity. 
DRAX have offered installation of
free solar pv at Dalmally PS as part
of the community benefits flowing
from the planned expansion of Ben
Cruachan power station. Discussions
have been going on from June
2024. 
No significant updates on DRAX
solar offer except the Dalmally
proposal has been deemed not-
financially viable by DRAX.
Alternative sites or technologies are
currently being considered.    
E4 – Delivery of Water Efficiency Audits
across our Estate 
(L) Commercial
Services  
Evidence of delivery
of projects 
Works items are generally small
scale and are being funded through
existing approved budgets where
possible; otherwise costs will be met
from savings generated. 
Significant Council wide asset
verification exercise and ensuring
water use minimised.  
The asset verification element of
this project is substantially complete
and substantial savings have been
identified and recovered. A case
study is being prepared to
demonstrate the range of tasks
undertaken and to convey the scale
of savings made and refunds
received. The final stage of work
involves an exercise to reduce water
consumption (with carbon
emissions reduction) over a number

Page 15

of sites and is underway.  Program
to introduce Water efficiency
measures has commenced and will
be complete by Q1 2025. Costs
finalised and a program developed
for the introduction of water
efficiency measures focussing on
reducing consistent excessive
consumption at public toilets.
Material water savings have been
identified and recovered, with a
focused programme to introduce
water efficiency measures set to
conclude by Q1 2025. 
E5– Delivery of Energy Efficiency
Scotland Programme 
(L) Housing
Services,
Registered Social
Landlords  
Evidence of delivery
of projects 
Funding amounts are determined by
localised factors and is paid as
a  proportion of the Scottish
Governments’ Heat In Buildings
Strategy  
In September 2024 Argyll and Bute
Council was awarded a Grant of
 
£1,979,827 through the Scottish
Government’s Energy Efficient
Scotland – Area Based Scheme
(ABS) to facilitate the installation of
insulation measures to privately
owned and privately rented
properties in mainland and island
addresses throughout Argyll and
Bute.  Non-means tested grants of
between £9,000 and £21,600 are
available to eligible households for
the application of insulation,
helping to significantly reduce
household consumption of energy
on a “Fabric First” basis

Page 16

contributing towards both the
Council’s and Scottish
Government’s carbon reduction
targets.    The Council also
continues to investigate avenues to
work in partnership with RSLs in
Argyll and Bute.  Whilst these
carbon reductions do not
contribute directly to the Council’s
Decarbonisation Plan they help to
reduce carbon usage across Argyll
and Bute. 
E6 – Complete LED streetlight
replacement programme 
(L) Roads and
Infrastructure
Services 
Evidence of delivery
of projects 
Fully funded through prudential
borrowing 
Works have gone well though there
are still approx.130 Luminaires to be
upgraded to LED in the Lorn Area –
The Luminaires are on order –
Works should be completed by end
2024/early 2025. The Council has
14442 streetlights in total so carbon
emissions have already been greatly
reduced by the LED Upgrade
Project. 
In 2015/16, figures were CO2 totals
– 3140 tonnes.   
2024/25 emissions are forecast to
be reduced again.  Year to date (end
of September 2024) carbon totals –
264 tonnes.

Page 17

E7 – Continue support of ABRA and
review Renewable Energy Strategy
annually 
(L) Economic
Development 
Evidence of delivery
of projects 
Officer resource to support
currently funded 
ABRA met in October 2024 and
reviewed the REAP.  SSE Networks
continue upgrade works to power
the transmission grid at
275kv.   Work continues on
proposals for the Low Carbon Islay
project through the Rural Growth
Deal.  Funding for 2 projects
through the Carbon Neutral Islands
Capital Fund  has been secured and
these are being delivered by Islay
Energy Trust (installation of solar on
community buildings) and Islay
Development Initiative (a
community orchard and forestry
project).  The CNI award is currently
embargoed but hopefully will be
announced shortly.  
E8 – Continue support for offshore
development of renewables 
(L) Economic
Development 
Evidence of delivery
of projects 
(expected late
2020s/early 2030s) 
Officer resource to support
currently funded 
Scottish Power Renewables are
progressing the Machair Wind
project and ESB are progressing
Malin Wind, both are expecting to
seek consent during the mid-2020s
with generation commencing in the
early 2030s.  
T1 – Develop a Fleet Replacement
Strategy supportive of fuel efficient,
electric and hybrid vehicles    
(L) Roads and
Infrastructure
Services 
Adoption of
Strategy 
Part for current financial year  The Fleet Replacement Strategy is
complete but is subject to on-going
change in line with legislative
changes as it is an operational
document. 
T2 – Develop a vehicle routing system
that will reduce road miles for
operations  
(L) Roads and
Infrastructure
Services 
Evidence of delivery
of projects 
Part for current financial year  This is progressing. The project has
slipped slightly due to staff
availability and the data gathering

Page 18

and cleansing stage taking longer
than we might have hoped. There
was a report to EDI in March which
sets out the revised position and
project timeline.    
T3 – Develop an electric vehicle
infrastructure strategy    
(L) Roads and
Infrastructure
Services 
Evidence of delivery
of projects 
Part for current financial year 
The development of the EV network
is funded by external grant monies
from Transport Scotland, and the
costs of developing the strategy in
terms of staff time are covered via
existing budgets 
Ultimately the cost recovery model  
The strategy and expansion plan is
in place – we cannot move forward
with a delivery programme until
such time as our funding from SG is
confirmed. The national EVIF
programme is seeing some delays
and changes in guidance and
application process. All Councils are
in the same position and we are in
discussions with TS/SG on how the
programme will operate going
forward and when we are likely to
see a funding award.    
We have, through a separate fund
accessed via HiTRANS, progressed
the installation of 8 new rapid
chargers across the area in the last
quarter of 2023 and these are in
place and being well used.  This
brings our network up to 37. 
We have also introduced new
charges which are designed to cover
all asset management costs for the
network. These costs fall now to the

Page 19

Council after having previously been
funded through grants.    
We are also continuing to progress
installs at Council hub offices with
the next sites being Union St
Rothesay and Kintyre House
Campbeltown. 
We have now secured a provisional
allocation of £1million from Scottish
Government to expand our EV
network and are currently out to
tender for a site assessment
exercise.  Further reports on this will
be made to EDI committee as
appropriate. 
T4 – Support Digital by Default theme
Service Review & Recovery Plan to
reduce need to travel 
All Council
Departments 
Evidence of delivery
of projects 
Part for current financial year  Council is adopting ‘Our Modern
Workspace’ programme and  Digital
First approach as services change
and evolve post pandemic.   
T5 – Develop new active travel plans
for Council buildings and our towns 
(L) Economic
Development 
Evidence of delivery
of projects 
No active travel funding is provided
by Council.  All costs, including
internal staff costs (1.7FTE), have to
be funded via successfully securing
external challenge funds. As all
active travel work is currently reliant
on securing external funding, the
projects which are progressed are
those which can successfully secure
external challenge funding. 
The purpose of active travel is to
make it as easy as possible and help
to encourage individuals, businesses
and visitors to choose to walk,
wheel or cycle for local
journeys.  Increasing activity and
reducing sedentary behaviour has
significant health benefits and can
increase accessibility to essential
services, education, employment,
retail and leisure.  Walking and

Page 20

External competitive challenge
funds are time consuming to secure
and projects have to be shaped to
fit with external funders’ aspirations
and requirements by the 1.7FTE
Active Travel staff in the Strategic
Transportation Team. However, at
present these are the only available
source(s) of funding made available
to deliver active travel
improvements. 
2023/24 Progress 
The 1.7FTE Active Travel Team
secured £2.56M external challenge
funding in 23/24 for development
and delivery of 22 active travel
projects across Argyll and Bute,
requiring 18 separate competitive
challenge funding applications to 5
separate funds. 
Projects funded via the active travel
team within Strategic
Transportation in 2023/24
included: 
• New cycle parking at the
community owned Port Ellen
Playing Fields Community
Development, Islay. 
cycling are lower cost travel modes
and, if they are a viable option, can
help the 20% of households (2022
census) reduce social isolation and
other households reduce their
reliance on private cars, particularly
multiple car households (34% of
Argyll and Bute households; 2022
census). 
No Council funding is currently
expended on Active Travel work,
with all costs, including internal staff
costs (1.7FTE), having to be funded
via successfully securing external
challenge funds. As all active travel
work is currently reliant on securing
external funding, therefore the
projects which are progressed are
those which can successfully secure
external challenge funding. 
Argyll and Bute Active Travel
Strategy: Officers are working to
develop an Argyll and Bute Active
Travel Strategy and present it to
members for approval.  The Active
Travel Strategy will provide the
overarching context for the Council
to support and promote active
travel across the Council area.
Having an adopted and current
Active Travel Strategy is increasingly
becoming a pre-requirement to

Page 21

• Funded Cycling UK to run
the Dunoon Cycle Bothy 
• Funded ACT to upcycle 65
bikes to return to the local Mid-
Argyll Community to increase
opportunities to cycle. 
• Creation of new
Smartphone Apps for Tobermory
and Bowmore (adding to the
existing popular apps for
Campbeltown, Dunoon,
Helensburgh, Oban and Rothesay) 
• Design work progressed for
ambitious walking and cycling
projects including: 
• Campbeltown, commenced
initial design work on Phase 4
Active Travel Improvements
(Esplanade and Kinloch Park)
(initial Feasibility). 
• Dunoon, Town Centre to
Hunters Quay Active Travel route
(Concept Design). 
• Helensburgh: Helensburgh –
Cardross – Dumbarton Cyclepath
(Developed Design)and
Helensburgh – Garelochhead
Cycleway (final Technical Design). 
• Islay, Bowmore to Bridgend
Path (with Islay Community Access
Group) (final Technical Design). 
access Scottish Government derived
active travel funding. 
Active Travel Delivery Plan: 
Following approval of Active Travel
Strategy, an Active Travel Delivery
Plan will be developed to create a
prioritised list of active travel
projects for the whole of Argyll and
Bute. 
Active Travel Projects: The majority
of external funding available is
provided by the Scottish
Government via a number of
distribution organisations who are
paid to administer these funds.  The
focus for Scottish Government
Active Travel funding is to develop
and deliver infrastructure projects
and associated behaviour change. 
As such, the focus for the very
limited staff capacity in the Active
Travel Team has been to develop
and deliver infrastructure projects
across Argyll and Bute with a focus
on our main towns and locations
with strong community support. 
Active Travel Plans for Towns: There
are Active Travel Plans in place for
the main towns in Argyll and Bute,
albeit some are now quite historic.

Page 22

• Jura, Craighouse to Corran
Sands Active Travel Route
(Concept Design). 
• Lochgilphead: Front Green
to Crinan Canal (Concept
Design)and Town Centre to Joint
Campus Active Travel Routes (final
Technical Design). 
• Rothesay, Pavilion to Albert
Pier Active Travel Improvements
(Concept Design). 
Oban, Oban Town Centre
North  Active Travel
Improvements (George St and
Corran Esplanade) (Concept
Design) – concept design
proposals rejected by OLI Area
Committee on 25 June 2024. 
The town Active Travel Plans focus
on identifying potential active travel
route networks for key towns. 
These provide a framework for the
development of new active travel
routes, which will enable and
encourage residents, businesses and
visitors to choose to travel more
actively.  No funding is currently
secured to enable the Active Travel
Plans for towns to be updated. 
Council Staff Travel Plan: Officers
are exploring options to develop a
Council Staff Travel Plan at zero cost
to the Council.  However, this is
challenging due to the ongoing
uncertainty of longer-term staff
profiles and bases.  There is
currently no funding secured to
enable this work to be progressed.   
It should be noted that successful
Staff Travel Plans require to have
strong support from senior
managers/elected members, who
also require to act in accordance
with the Plan, and from enabling
departments, e.g. finance and
HROD.  Once developed, to be fully
effective it is likely that a Staff Travel
Plan would require changes to the
Council’s travel policies and
expenses policies.

Page 23

Staff Travel Plans focus on measures
to make it easier and preferable for
staff to choose to walk, cycle, use
public transport or car share to
commute to work or for work
journeys, or use economical pool
vehicles for work journeys.   A travel
plan should encourage staff to
choose the most economical and
least environmentally damaging
travel mode.  Engagement will be
required with services which
manage staff in buildings and/or
council buildings as this is essential
to creating deliverable and effective
travel plans for staff.  This includes
Estates, HROD, SMT and building
users.  
PA1 – Review Council Flooding &
Coastal Protection Policy 
(L) Roads and
Infrastructure
Services 
Review of policy  No specific funding in place,
research required to impact on
operation costs 
Reviews are in process.    
PA2 – Review Council Sustainable
Procurement Policy 
(L) Procurement   Review of policy   No specific funding in place,
research required to impact on
operation costs 
This policy is reviewed on an annual
basis.