ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
5th DECEMBER 2024
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS 
1.0 EXECUTIVE SUMMARY
1.1 This report provides an update on the Rural Growth Deal (RGD) and specifically costs
associated with Business Case and Project Development. The RGD will deliver £50m of
investment from the Scottish and UK Governments for projects that are a driver for
inclusive and transformational economic growth across the region. The Council and key
delivery partners will also provide a minimum of £20m of match funding throughout the
10-year Deal programme.  
1.2 The RGD Programme Management Office (PMO) continue to work with the UK and
Scottish Governments to confirm the signing of the Full Deal Agreement, which
represents the next key milestone for the Rural Growth Deal. This was postponed in
June 2024 following the announcement of the General Election.
1.3 A number of RGD projects now have approved Outline Business Cases and further
project development work is necessary to inform the Full Business Cases which will
enable drawdown of funding from Central Government.   This includes detailed design,
procurement, site investigation works and statutory consents such as planning. 
1.4 To date, costs associated with business case and project development works have
largely been funded from the Council’s Inward Investment Fund. Match funding has also
been secured from a number of key partners such as Highlands and Islands Enterprise
and Scottish Enterprise.  The Policy and Resources Committee have previously
approved the release of 5 tranches of funding totalling £750k from the Inward
Investment Fund (IIF).  The RGD Internal Programme Board have delegated authority
to authorise spend from the IIF to support RGD project development work. At the time
of writing this report, total approved spend on RGD business case and project
development work stands at £572,658.
1.5 Where possible, the RGD PMO will seek to recoup project costs from RGD capital
funding allocations however, it will not be possible to submit any claims for funding until
Full Business Cases for projects are endorsed by Central Government.  As such, any
costs incurred in advance are at risk to the Council and strategic partners.     
1.6 It is currently estimated that there could be a cost pressure in the region of £3.183m
over the lifetime of the Rural Growth Deal, which can be associated with project
development costs. The majority of these costs will be reclaimed through RGD capital
funding, once Full Business Cases are endorsed by Government. It is also anticipated
that an estimated further £220k of funding will be required to be spent on Business
Cases. This is not reclaimable from RGD capital funds and will be met by the Internal
Investment Fund and through partner match funding. 
RECOMMENDATIONS: 
The Policy and Resources Committee are asked to:

Page 2

a) Note that the total estimated essential development costs to inform Treasury
Five compliant Full Business Cases for all projects amount to £3.183m and
these costs require to be incurred in advance of Central Government
endorsement at risk to the Council and lead delivery partners. 
b) Agree that the Council sets aside a fund from the Priorities Investment Fund to
the value of £0.700m that can pay for the development costs for Council
projects on the basis that all will be paid back by the end of Year 10.  
c) Agree that any cash flow funding requests for projects led by external partners
will be brought to P&R for approval as and when a request for funding is made
and considered on a case by case basis.    
d) Delegate to the Internal Programme Board (Chief Executive and Executive
Directors) to approve pre-development funding requests relating to Council led
projects up to a threshold of £250k per project from the new Fund.

Page 3

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
5th December 2024
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS 
2.0 INTRODUCTION
2.1 This report provides an update on the Rural Growth Deal (RGD) and specifically costs
associated with Business Case and Project Development. The RGD will deliver £50m of
investment from the Scottish and UK Governments for projects that are a driver for
inclusive and transformational economic growth across the region. The Council and key
delivery partners will also provide a minimum of £20m of match funding throughout the
10-year Deal programme.  
2.2 The RGD Programme Management Office (PMO) continue to work with the UK and
Scottish Government to agree a date for signing the Full Deal Agreement, which
represents the next key milestone for the RGD. This was previously scheduled for
the 7th June 2024 however, was postponed following the announcement of the UK
General Election.
2.3 A number of RGD projects now have approved Outline Business Cases and further
project development work is necessary to inform the Full Business Cases, which,
following endorsement will enable drawdown of RGD funding from Central
Government.   The pre-development work necessary to inform Full Business Cases
includes detailed design, procurement, site investigation works and statutory
consents such as planning. 
2.4 To date, costs associated with business case and project development works have
largely been funded from the Council’s Inward Investment Fund (IIF). Match funding
has also been secured from a number of key partners such as Highlands and Islands
Enterprise and Scottish Enterprise.  The Policy and Resources Committee have
previously approved the release of 5 tranches of funding from the IIF totalling £750k,
with authority delegated to the Internal Programme Board to authorise spend to
support Rural Growth Deal project development work. At the time of writing this
report, total allocated approved spend on RGD project development work stands at
£572,658.
2.5 Where possible, the RGD PMO will seek to recoup capital costs from RGD funding
allocations however, it will not be possible to submit any grant claims until Full
Business Cases for projects are endorsed by Central Government.  All costs incurred
in advance of endorsement are at the risk to the Council and/or key delivery partners.  
2.6 Given the fixed budgets on RGD projects, the most signficiant risk is construction
tenders being unaffordable.  This will require additional match funding to be sought,
value engineering to be undertaken or in the worst case scenario abandonment of
tenders.  There are mechanisms within the RGD Programme to enable change
however, it is uncertain if any abortive costs incurred can be claimed from capital
budgets.  As such, there is a risk that the Council and/or key delivery partners will
require to repay such costs in the event of tenders being abandoned.

Page 4

2.7 Tables 2-4 below, set out further detail of estimated at risk project development costs
across the RGD programme. 
3.0 RECOMMENDATIONS
The Policy and Resources Committee are asked to: 
a) Note that the total estimated essential development costs to inform Treasury
Five compliant Full Business Cases for all projects amount to £3.183m and
these costs require to be incurred in advance of Central Government
endorsement at risk to the Council and lead delivery partners. 
b) Agree that the Council sets aside a fund from the Priorities Investment Fund to
the value of £0.700m that can pay for the development costs for Council
projects on the basis that all will be paid back by the end of Year 10.  
c) Agree that any cash flow funding requests for projects led by external partners
will be brought to P&R for approval as and when a request for funding is made
and considered on a case by case basis.    
d) Delegate to the Internal Programme Board (Chief Executive and Executive
Directors) to approve pre-development funding requests relating to Council led
projects up to a threshold of £250k per project from the new Fund.   
4.0 DETAIL
4.1 Full Business Case Costs
4.1.1 In line with City Region and Growth Deal protocols, HM Treasury Green Book compliant
Full Business Cases require to be endorsed by the UK and Scottish Government in
order to enable drawdown of funding.  This requires significant staff and financial
resource to be allocated to projects and it should be noted that business cases will
require several iterations in order to achieve endorsement from Central Government.
4.1.2 It is essential that the Council and key delivery partners plan for Full Business Case and
associated project development costs throughout the lifecycle of the RGD programme
to ensure these can be monitored and managed appropriately.  As such, the RGD PMO
have scoped requirements for FBCs, and estimated costs and timescales are detailed
in Table 1 below.  It should be noted that these are estimated costs at this stage and all
works will be awarded in line with Local Government Procurement protocols following
competitive tenders: 
Table 1: Full Business Case Requirements (as at October 2024):
Project Lead
Partner
Expected
approach to
FBC
Estimated
FBC Cost
Expected Year
of Expenditure
Kintyre
Seasports
Argyll &
Bute
Council in
partnership
with Kintyre
Seasports   
Stantec & Blue
Sea Consulting
have been
commissioned
to complete
FBC. 
£52,000 2024/25-
2025/26

Page 5

Low Carbon
Economy –
Islay
TBC TBC £30,000 -
£50,000
(OBC
requires to
be
completed)
2031/32
Rural Skills
Accelerator
Programme –
Dunoon STEM
Hub
Argyll &
Bute
Council
Will be
undertaken in-
house by the
Economic
Growth
Manager with
support from
Education.
£5,000
(contingency)
2045/25-
2025/26
Rural Skills
Accelerator
Programme –
SAMS STEM
Hub
Scottish
Association
for Marine
Science
TBC £25,000 2025/26
Rural Skills
Accelerator
Programme –
Business Skills
Highlands
and Island
Enterprise
Highlands and
Islands
Enterprise to
complete in-
house. 
- 2024/25
Housing – Isle
of Mull
Argyll &
Bute
Council
Stantec have
been
commissioned
to complete
FBC.
£26,000 2024/25-
2025/26
Housing – Isle
of Islay
Argyll &
Bute
Council
Expect that
consultant
support will be
required to
complete the
FBC
£26,000 2026/27
Clyde
Engineering &
Innovation
Centre
Argyll &
Bute
Council
Expect that
consultant
support will be
required to
complete the
FBC
£30,000 2028/29
West Coast
UAV Hub
Argyll &
Bute
Council
Expect that
consultant
support will be
required to
complete the
FBC
£30,000 2031/32
Marine
Aquaculture
Programme –
UHI Argyll Expect that
consultant
support will be
£30,000 2026/27

Page 6

Marine Industry
Training Centre
required to
complete the
FBC
Marine
Aquaculture
Programme –
SAMS
International
Seaweed &
Shellfish
Industry R&D
Centre
Scottish
Association
for Marine
Science
Expect that
consultant
support will be
required to
complete the
FBC
£30,000 2025/26
Marine
Aquaculture
Programme –
Marine
Environmental
Research
Laboratory
University of
Stirling 
University of
Stirling will
complete with
in-house
resource. 
- 2025/26 
4.1.3 Members should note that the estimates provided are subject to change as the RGD
Programme moves forward. The RGD PMO will work with key delivery partners to
ensure that resources are efficiently utilised. In instances where total procurement
spend is less than £2m, there may be an opportunity to complete Business Justification
Cases instead of FBCs, which could reduce cost, however this will require to be agreed
by Government on a case by case basis. The RGD PMO will continue to scope options
for match funding to assist with project development costs.
4.1.4 Argyll and Bute Council Led Projects: 
Argyll and Bute Council are currently leading on 6 projects within the RGD programme.
It is expected that the Inward Investment Fund will support project development costs
for these projects. As of October 2024, there is circa £255k of funding remaining in the
Inward Investment Fund which to date is unallocated. The following is a summary of
some of the project development work anticipated for RGD projects being managed and
delivered by the Council:- 
• Full Business Cases for Argyll and Bute Council led projects – 4
FBCs at an estimated total cost of £100k.
• It should be noted that funding for the FBCs for Kintyre Seasports and
the Housing – Isle of Mull projects has already been allocated within the
approved spend from the IIF.  The FBC for Rothesay Pavilion has also
been completed however, further work will be necessary to secure full
endorsement from Central Government. 
• Islay Low Carbon – this project has returned to options appraisal stage
and there is a requirement to complete both an OBC and an FBC for the
preferred option. Estimated total costs are £30k-£50k.
• Further demand studies - It has been identified through the OBC
feedback process that further demand studies will be required for the
CEIC and West Coast UAV Hub propoals. An estimated total cost for
this work could be in the region of £40k.

Page 7

• FBC Feedback Support – Experience to date has identified that FBCs
will require multiple iterations prior to endorsement by Central
Government. As such, it will be necessary to allow contingency in project
budgets to account for the endorsement process and associated
consultancy costs. An additional £5k per FBC at a total estimated cost of
£30k has been factored in at this stage.
4.1.5 The estimated expenditure on the work above is circa £220k. The RGD is a 10 year
programme therefore there will be an element of cost inflation and unexpected costs
which may require to be met from the IIF. It is therefore considered that there is a risk
that current funding allocated to the IIF may be insufficient to meet all future costs.   The
RGD PMO will work with Project Leads to identify match funding opportunties to support
project development costs.  Project leads will also seek to capitalise as much work as
possible and re-claim costs from RGD capital funding following endorsement of Full
Business Cases. 
4.1.6 Partner Led Projects:
There are currently 5 projects which are being led by partner organisations, these are
within the Marine Aquaculture Programme and Rural Skills Accelerator Programme.
These projects will require funding to support their Full Business Case and project
development costs.  
4.1.7 It is not considered viable for the Council to accept financial risk on projects that they
will not own and/or operate following completion.  As such, key delivery partners will
require to accept a level of financial risk in order to deliver projects using RGD funding. 
There could however, be a requirement for the Council to assist with cash flow and
procurement on behalf of some project stakeholders.   
4.1.8 The RGD PMO will work with Project Leads to fully scope their funding requirements for
Full Business Cases. 
4.2  Project Development Costs
4.2.1 A significant amount of project development work is necessary in order to complete
Treasury Five Case compliant FBCs.  This includes detailed design, construction
tenders and statutory consents.  In order to develop FBCs the following milestones
should be completed: 
• Design to RIBA Stage 4 (Technical Design);
• All consents should be approved (including Planning, Building Warrant etc);
• Procurement – costs in the FBC should be based on a tendering exercise;
• Match funding – must be identified & approved by funders;
• Any Legal agreements between the Council and Partners should be finalised;
• Carbon Impact Assessments finalised; 
• Equalities Impact Assessments finalised; 
• Programme of works agreed. 
4.2.2 Pre-construction activiites such as Detailed Design incur considerable expense for lead
deliverty partners. The appointment of a Detailed Design team will include an Architect,
Quantity Surveyor, Engineers and Project Management support. As a general estimate,
up to 10% of project capital budgets requires to be allocated for pre-development costs.

Page 8

4.2.3 Detailed design is a requirement for project FBC’s and will require spend to be incurred
in advance of Central Government endorsement at risk to the Council and lead delivery
partners.  The figure below details the approvals process for RGD projects in advance
of funding drawdown:- 
4.2.4 Table 4 and 5 below, sets out an estimated expenditure profile of when project
development costs are anticpated to be incurred throughout the RGD Programme
alongside when when it is anticipated the we will be able to claim for the project
development costs.  Further information at project level is contained within Table 2 and
Table 3.  
Table 2: Projected Profile of RGD Project Development Costs 
Table 3: Projected Claim Profile of RGD Project Development Costs 
Table 4: Summary Profile of estimated RGD Development Costs and Drawdown (All 
Projects): 
Table 5 Summary Profile of estimated RGD Development Costs and Drawdown (ABC
Projects Only): 
Outline Business Case
approved by Government
1. Detailed
Design/Consents/Impact
Assessments Undertaken
2. Construction Tender 
Full Business Case submitted
to Government for
endorsement
FBC endorsed by
Government
1. Contracts for construction
awarded
2. Claims made to
Government for project
costs quarterly
Project Development Costs Year  1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
Kintyre Seasports £125,000 £125,000 £250,000
Dunoon STEM Hub £20,000 £20,000
SAMS STEM Hub £100,000 £100,000
Islay Low Carbon £50,000 £100,000 £150,000 £300,000
Housing - Mull £20,000 £20,000
Housing - Islay £100,000 £100,000
CEIC £300,000 £300,000 £600,000
West Coast UAV £200,000 £200,000 £400,000
Machrihanish Innovation Campus £250,000 £250,000
SAMS CSSID-e £250,000 £250,000
MITC £121,000 £121,000 £121,000 £530,000 £893,000
Total £145,000 £866,000 £221,000 £421,000 £830,000 £50,000 £300,000 £350,000 £0 £0 £3,183,000
Project Development Costs Year  1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
Kintyre Seasports £250,000 £250,000
Dunoon STEM Hub £20,000 £20,000
SAMS STEM Hub £100,000 £100,000
Islay Low Carbon £300,000 £300,000
Housing - Mull £20,000 £20,000
Housing - Islay £100,000 £100,000
CEIC £600,000 £600,000
West Coast UAV £400,000 £400,000
Machrihanish Innovation Campus £250,000 £250,000
SAMS CSSID-e £250,000 £250,000
MITC £363,000 £530,000 £893,000
Total £0 £270,000 £370,000 £613,000 £630,000 £600,000 £0 £0 £700,000 £0 £3,183,000
Year 1
£000
Year 2
£000
Year 3
£000
Year 4
£000
Year 5
£000
Year 6
£000
Year 7
£000
Year 8
£000
Year 9
£000
Year 10
£000 Total
Expenditure 145 866 221 421 830 50 300 350 0 0 3183
Income 0 270 370 613 630 600 0 0 700 0 3183
Cash Flow -145 -596 149 192 -200 550 -300 -350 700 0
Cumulative Cash Flow -145 -741 -592 -400 -600 -50 -350 -700 0 0
Year 1
£000
Year 2
£000
Year 3
£000
Year 4
£000
Year 5
£000
Year 6
£000
Year 7
£000
Year 8
£000
Year 9
£000
Year 10
£000 Total
Expenditure 145 145 100 300 300 50 300 350 0 0 1690
Income 0 270 20 0 100 600 0 0 700 0 1690
Cash Flow -145 125 -80 -300 -200 550 -300 -350 700 0
Cumulative Cash Flow -145 -20 -100 -400 -600 -50 -350 -700 0 0

Page 9

4.2.5 It can be seen from Table 2 above that the total estimated development costs for all
projects amount to £3.183m and as previously outlined these costs require to be
incurred in advance of Central Government endorsement at risk to the Council and lead
delivery partners.  There is a requirement for cash flow and the maximum amount of
cash flow required at any one time is £0.741m and this occurs in Year 2.  The PMO
office will be looking for the lead delivery partners to assist with the cash flow and
therefore bear the risk, however, this may not be possible for them to do.  
4.2.6 If we only account for the projects that are Council led then the maximum amount of
cash flow required at any one time is £0.700m and this occurs in Year 8. It is
recommended that the Council sets aside a fund to the value of £0.700m that can pay
for the development costs on the basis that all will be paid back by the end of Year 10. 
It is suggested that the Council allocate from the Priorities Investment Fund.   The
maximum cash flow exposure is based on the assumption that the Full Business Cases
are approved and the development costs become claimable; there remains a risk that
this isn’t the case and projects are abandoned due to unviable costs and/or unmet
funding gaps .  Therefore, the profile of expenditure and income will be kept under close
review and updates provided to Members as part of regular Rural Growth Deal
reporting.    
4.2.7 It is proposed that any cash flow funding requests for projects led by external partners
will be brought to P&R for approval as and when a request for funding is made.  Input
will be necessary from Legal Services to ensure that the appropriate funding
agreements are put into place to reduce the risk to the Council. 
4.2.8 Members should note the following points, regarding specific projects:
• Kintyre Seasports – the tender for Detailed Design costs was returned in
September 2024 and is now in the evaluation process.  Members approved
spend of up to £250k to support the next stage of project development including
Detailed Design works in August 2024.
• Dunoon STEM Hub – the majority of development costs will be met through
match funding from the Clyde Mission Fund.
• Isle of Mull Housing – the majority of development costs have been met
through a successful application to the Scottish Government’s Islands
Programme. Therefore a smaller sum will be required to be met through the
RGD Capital funds. This is specific to the enabling infrastructure, FBC costs will
require to come from Inward Investment Fund.  
•  Marine Aquaculture Programme Projects – these projects are all led by
external partners and to date OBC costs have been support by Highlands and
Islands Enterprise.  Lead partners have indicated they may struggle to cash flow
project development costs such as detailed design. 
• Clyde Engineering & Innovation Cluster – To date project development costs
for this project have been funded via Section 75 funds relating to the adjacent
Waitrose development.  This project also forms part of propsals drafted for
funding from the previous UK Government’s Levelling Up programme.
4.2.9 Members are asked to agree delegated authority to the Internal Programme Board
(Chief Executive and Executive Directors) to approve pre-development funding requests
relating to Council led projects up to a threshold of £250k per project from the Fund

Page 10

proposed in para 3.0. This will be necessary to avoid delays to RGD business cases
and is consistent with the existing approval process for Inward Investment Fund
funding.   
4.3 Project Development Risks
4.3.1 Funding of project development costs is a risk that is common across all City and
Region Growth Deals in the UK. To date, Government have been resolute that they will
not fund project development costs in advance of the endorsement of  project Full
Business Cases.
4.3.2 As set out above, Treasury 5 FBCs incur significant cost to the Council and lead
delivery partners and all spend is at risk in advance of FBC’s being endorsed by Central
Government.  The key risk the to the Council and project partners is projects requiring
to be abandoned due to unviable costs and/or unmet funding gaps.  This is unlikely to
be confirmed until construction tenders have been undertaken.  
4.3.3 In a worst case scenario, where value engineering and applications for match funding
are unsuccessful the Council or partners will be left with abortive project development
costs which can not be funded from RGD capital budgets in the absence of a viable Full
Business Case. 
4.3.4 Protocols are in place to manage change across the RGD programme and any decision
to re-alloate project funding which deviates from the Heads of Terms Agreement will
require approval from Central Government.
5.0 CONCLUSION  
5.1 The Policy and Resources Committee have previously approved the release of 5
tranches of funding totalling £750k from the Inward Investment Fund with authority
delegated to the Internal Programme Board to authorise spend to support Rural Growth
Deal business case and project development work.  At the time of writing this report,
total approved spend on RGD development work stands at £572,658.
5.2 Following signing of the Full Deal Agreement, it will be necessary to draft FBCs for all
projects within the RGD Programme.  Drawdown of RGD funding is subject to
endorsement of FBCs by Central Government.  This will require further project
development work such as detailed design, planning and consultancy support which is
necessary in order to develop Treasury compliant FBCs.
5.3 Members are asked to note that all spend in advance of FBC endorsement is at risk to
the Council and key project partners however, this is necessary in order to achieve
endorsement of RGD projects by Central Government.  Where possible, all capital costs
incurred will be reclaimed from RGD capital budgets following endorsement of FBC’s by
Central Government.
5.4 There is still a significant amount of work required to get to endorsement of FBCs, which
brings a level of risk to the Council and partners. The Council will require to incur spend
at risk in order to undertake the project development work necessary to inform FBC’s. 
Key RGD delivery partners will also require to spend at risk on their projects the RGD
PMO will work proactively with all stakeholders to ensure that risk is managed and

Page 11

mitigated. This may include requests to the P&R Committee to support external
partners cash flow business case development work.  
5.5 The RGD PMO will work with colleagues from Financial Services to manage financial
risk throughout the lifetime of the RGD Programme.  The RGD programme will also be
subject to robust financial monitoring and evaluation as set out in the RGD Financial
Plan which will be endorsed by Central Government as part of the suite of documents
required for Full Deal Signing.
6.0 IMPLICATIONS
6.1 Policy – The RGD is consistent with the Council’s Economic Strategy.
6.2 Financial –  RGD Projects require a level of upfront spend at risk to allow project
development to progress. It is recommended that the Council sets aside a fund
to the value of £0.700m that can pay for the development costs on the basis
that all will be paid back by the end of Year 10.  It is suggested that the Council
allocate from the Priorities Investment Fund. 
6.3  Legal – The RGD may require input from Legal Services as part of the Full Deal
Signing.
6.4  HR – None at present.
6.5  Fairer Scotland Duty: Required as part of OBC process.
6.5.1   Equalities - protected characteristics - Equality Impact Assessments
are required for all RGD projects.
6.5.2   Socio-economic Duty - The Rural Growth Deal will follow Scottish
Government guidance on Inclusive growth including measures to
address socio-economic disadvantage
6.5.3   Islands – Islands impact assessments required as part of OBC
process where necessary.
6.6  Climate Change – Carbon Management Plans are required for all RGD business
cases. 
6.7 Risk – Spend incurred in advance of approval of FBCs will be at risk to lead partner.
6.8 Customer Service – None at present. 
6.9 The Rights of the Child (UNCRC) – None at present. 
Kirsty Flanagan Executive Director with responsibility for Development and Economic
Growth 
Council Leader: Councillor Jim Lynch 
20 November 2024                                      
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk

Page 12

Jonathan Welch, Transformational Projects & Regeneration Manager
Jonathan.Welch@argyll-bute.gov.uk   
Aileen Semple, Rural Growth Deal Project Officer
Aileen.Semple@argyll-bute.gov.uk