ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES
COMMITTEE
ROAD AND INFRASTRUCTURE
SERVICES 
5 DECEMBER 2024 
OCTOBER 2023 WEATHER EVENT – NOVEMBER 2024 UPDATE 
1.0 INTRODUCTION 
1.1 This is a follow up to the report presented to the Policy and Resources
Committee on 15 August 2024 in respect of the October 2023 weather event.   
Policy and Resources Committee - October 2023 Weather Event (item 18)   
2.0 RECOMMENDATIONS
2.1 It is recommended that the Policy and Resources Committee:- 
a. Notes the updates on the current position of the projects; and 
b. Agrees that further updates on the October 2023 Weather Event are
made to the Environment, Development and Infrastructure Committee
rather than to the Policy and Resources Committee.

Page 2

3.0 DETAIL
3.1 The following table summarises works locations as at November 2024 where
works were still outstanding.   
Update on Works Progress, Scheduled Completion & Estimated Total Costs 
LOCATION ONGOING
WORKS/PROGRESS
UPDATE
SCHEDULED
COMPLETION 
Previous Update 
Current Update
ESTIMATED TOTAL
COSTS 
Previous Update 
Current Update
A816-110
Cuilfail Hotel
Bridge,
Kilmelford  
Upstream training walls,
bridge parapets,
pedestrian walkway,
scour protection and
upstream debris barrier
works being carried out
in November 2024. 
Some final work required
in Spring 2025 due to
SEPA delays and
changed advice received
in final week of in-water
works, additional SEPA
Licencing now required. 
No additional costs
identified at this stage.
Site works due to re-
start mid August 2024
aiming to be complete
before winter. 
£200k (revenue) 
£2.086m (capital) 
Programmed and on
track for early
December 2024 
Majority of works
programmed and on
track for completion in
early December 2024 
with upstream north
training wall works
completed in Spring
2025
£200k (revenue) 
£2.086m (capital)
- NO CHANGE
B844-010
Kilninver
Bridge 
Phase 1 works
completed October
2023. 
Designs for Phase 2
works being carried out
in-house with a view to
works being tendered
mid 2025.   
Any risks incurred from
the delays to the Phase
2 works are being
monitored and controlled
to ensure the road
network remains safe. 
Phase 1 – October 2023
Phase 2 - Late Summer
2026 
£180k (revenue) –
Phase 1 
Phase 2 works being
incorporated into
Bridge Replacement
scheme already
funded
Phase 1 – October
2023
- NO CHANGE
- WORKS
COMPLETED 
Phase 2 - Late
Summer 2026
- NO CHANGE
£180k (revenue) –
Phase 1 
Phase 2 works being
incorporated into
Bridge Replacement
scheme already
funded
- NO CHANGE
C30 Ford to Works completed and July 2024 £864k (revenue)

Page 3

Malevich    road fully reopened.   July 2024
- NO CHANGE 
- WORKS
COMPLETED
£864k (revenue)
- NO CHANGE 
- FINAL COSTS
B836-060
Balliemore
Bridge, Glen
Lean 
Further to significant
delays and additional
costs incurred from
diversion of OpenReach
apparatus within
damaged bridge,
demolition of the existing
bridge is ongoing – due
to be completed late
2024. 
New bridge construction
planned early 2025.
Late 2024 / Early 2025  £1150m (revenue) 
£1.448m (capital) 
Programmed for
completion Spring
2025
£1.150m (revenue) 
£1.448m (capital)
- NO CHANGE 
A816 Bealach
Mor, Kintraw,
Ardfern Works
to February 
2024
Initial response including
clearance and quarry
works.
Further clearance and
scaling/stabilisation
works
Construction of Bypass 
and Loop road.
New Item included for
clarity 
£2.285m (revenue) 
February 2024
- WORKS
COMPLETED
£2.285m (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern Works
March to
September
2024
Stability, drainage and
safety works. 
Standing by and ongoing
maintenance. 
Traffic management to
September. 
Contractor Project
Management Costs
New Item included for
clarity 
£1.995m (revenue) 
September 2024
- WORKS
COMPLETED
£1.995m (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern Works
to 
Ongoing works to
bypass road continue for
vehicle safety barrier,
edge markers. 
Monitoring of Kintraw
hillside in place to
manage movement of
traffic onto bypass route
when necessary. 
New Item included for
clarity 
£220k (revenue) 
December 2024 £220k (revenue)
- NO CHANGE

Page 4

A816 Bealach
Mor, Kintraw,
Ardfern catch
pits at base of
unstable
slope  /
Rockfall
barrier
Rockfall protection
barriers have been
installed within the road
corridor and traffic has
been moved back to the
A816 under traffic lights
without a convoy
system. 
End of September 2024  £400k (revenue) 
End of September
2024
- WORKS
COMPLETED
£400k (revenue)
- NO CHANGE
A816 Bealach
Mor, Kintraw,
Ardfern
convoy system
‘v’ fixed traffic
lights
Traffic has been moved
back to the A816 under
traffic lights without a
convoy system. 
Traffic lights operating
on generator power until
mains electric supply
secured. 
Mains electric
connection being
progressed for traffic
lights. 
Ongoing traffic lights
operation until new,
permanent road
alignment.
Removal of Convoy
system - End of
September 2024   
Generator power – to
end of March 2025 
New mains power
connection by end of
March 2025 
Traffic Light operation –
ongoing until
permanent, new road
£255k (revenue) 
Removal of Convoy
system - End of
September 2024  
- NO CHANGE
- COMPLETED 
Generator power – to
end of March 2025
- NO CHANGE 
New mains power
connection by end of
March 2025
- NO CHANGE 
Traffic Light operation
– ongoing until
permanent, new road
- NO CHANGE 
£255k (revenue)
- NO CHANGE

Page 5

A816 Bealach
Mor, Kintraw,
Ardfern –
permanent
diversion onto
a widened
alignment of
the emergency
route   
Following receipt of a
high value quotation
from the existing
Specialist Contractor to
deliver scheme in full
accordance with design
standards, we are
assembling a feasibility
options report with the
Contractor – aiming to
select the preferred
option. 
The preferred option
shall be presented for
approval and shall
clearly include all
identified, known risks.   
Once the preferred
option has been
approved, a ground
investigation and
consultations with
stakeholders will take
place to inform the
design and build
contract. 
A design and build
contract shall be
prepared and tendered
via an open process to
ensure best value is
secured.
3 – 5 years    £1.1m (Capital) 
3 – 5 years   £1.1m (capital)
- NO CHANGE,
HOWEVER
ESTIMATED COSTS
WILL BE REVISED
AS OPTIONS, 
DESIGN AND
TENDER STAGES
PROGRESS 
3.2 It is proposed that any future reports on the October 2023 Weather Event will
be presented to the Environment, Development and Infrastructure Committee. 
4.0 CONCLUSION
4.1 This report summarises and provides update on the works that have been
undertaken and completed and those that are ongoing in relation to the extreme
weather event which occurred on the weekend of 7 October 2023 and which
was the wettest 2-day period on record for Scotland since 1891 in which Argyll
and Bute was the worst affected area.

Page 6

5.0 IMPLICATIONS 
5.1 Policy – policies in place for climate change, coast protection etc where
applicable these policies are being worked to.
5.2 Financial – No further financial implications identified at this time.  
5.3  Legal – various land agreements necessary for individual locations.   
5.4  HR – none known.
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known. 
5.5.2   Socio-economic Duty – none known. 
5.5.3  Islands – none known.
5.6 Climate Change – the impact of the storm is very closely linked to climate
change and the October event has highlighted to need for further adaptation
to be made to infrastructure to increase our resilience to future weather
events. The level of investment to improve resilience is expected to be
significant.  
5.7 Risk – significant risk of similar future events impacting our infrastructure.  
5.8  Customer Service – none known.  
5.9 Rights of the Child (UNCRC) – investment to improve our road network will
contribute to a safer environment for young people to thrive in. 
Kirsty Flanagan, Executive Director with responsibility for Roads and
Infrastructure Services 
Councillor John Armour, Policy Lead for Roads, Transport and Amenity
Services 
26 November 2024 
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Service 
Jim.Smith@argyll-bute.gov.uk 
Elsa Simoes Infrastructure Design Manager 
Elsa.Simoes@argyll-bute.gov.uk