MINUTES of MEETING of POLICY AND RESOURCES COMMITTEE held in the ON A
HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY
MICROSOFT TEAMS 
on THURSDAY, 20 FEBRUARY 2025 
Present: Councillor Jim Lynch (Chair) 
Also present:
Councillor John Armour
Councillor Gordon Blair
Councillor Math Campbell-Sturgess
Councillor Audrey Forrest
Councillor Kieron Green
Councillor Amanda Hampsey 
Councillor Jan Brown
Councillor Fiona Howard 
Councillor Reeni Kennedy-Boyle
Councillor Luna Martin
Councillor Dougie McFadzean
Councillor Yvonne McNeilly
Councillor Ross Moreland
Councillor Gary Mulvaney 
Councillor Tommy Macpherson
Councillor Peter Wallace
Attending: Pippa Milne, Chief Executive
Douglas Hendry, Executive Director
Kirsty Flanagan, Executive Director
Carolyn Earl, Interim Head of Financial Services 
Jane Fowler, Head of Customer and Support Services 
Ross McLaughlin, Head of Commercial Services
Fergus Murray, Head of Development and Economic Growth 
Suzanne Mason, Engagement and Communities Lead
Shona Barton, Governance Manager
Jonathan Welch, Transformational Projects and Regeneration Manager
Fergus Walker, Revenues and Benefits Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Mark Irvine and Liz McCabe. 
2. DECLARATIONS OF INTEREST (IF ANY) 
There were no declarations of interest intimated. 
3. MINUTES 
The Minutes of the meeting of the Policy and Resources Committee held on 5
December 2024 were approved as a correct record. 
* 4. FINANCIAL REPORTS MONITORING PACK - 31 DECEMBER 2024 
The Committee gave consideration to a report providing a summary of the financial
monitoring reports as at 31 December 2024. 
Decision 
The Policy and Resources Committee agreed to – 
1. note the revenue budget monitoring report as at 31 December 2024;

Page 2

2. note the financial risks for 2024-25; 
3. note the capital plan monitoring report as at 31 December 2024 and approve the
proposed changes to the capital plan outlined in Appendix 4 of that report; and 
4. note the reserves and balances report as at 31 December 2024. 
(Reference: Report by Section 95 Officer dated 17 January 2025, submitted) 
Councillor Luna Martin left the meeting during consideration of the next item of
business. 
* 5. BUDGETING PACK 2025-26 
The Committee gave consideration to the full package of papers included in the
budgeting pack in relation to the revenue and capital budgets for 2025-26. 
Decision 
The Policy and Resources Committee agreed to refer consideration of the Budgeting
Pack 2025-26 to the Council meeting on 27 February 2025, without
recommendation. 
(Reference: Budgeting Pack 2025-26 dated 13 February 2025, submitted) 
* 6. TREASURY MANAGEMENT STRATEGY AND ANNUAL INVESTMENT
STRATEGY 2025-26 
The Committee gave consideration to a report presenting the draft Treasury
Management Strategy and Annual Investment Strategy for 2025-26, and the
Prudential and Treasury Indicators for 2025-26 to 2027-28.   
Decision 
The Policy and Resources Committee – 
1. noted the Treasury Management Strategy and Annual Investment Strategy for
2025-26, and the Prudential and Treasury Indicators for 2025-26 to 2027-28; and 
2. agreed to refer the report to full Council for approval. 
(Reference: Report by Section 95 Officer dated 10 February 2025, submitted) 
7. ARGYLL AND BUTE UK SHARED PROSPERITY FUND INVESTMENT PLAN,
TRANSITION YEAR 2025/26 
The Committee gave consideration to a report presenting the Argyll and Bute UK
Shared Prosperity Fund (UKSPF) Transitional Year Investment Plan for 2025/26. 
Decision 
The Policy and Resources Committee –

Page 3

1. noted the content of the report; 
2. approved the Argyll and Bute UKSPF Transitional Year Investment Plan for
2025/26; and 
3. agreed that a progress report on the investment plan for 2025/26 would be
presented at the Policy and Resources Committee in October 2025. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 6 February 2025, submitted) 
8. FUTURE OF THE ARGYLL AND BUTE FLEXIBLE FOOD AND FUEL FUND 
The Committee gave consideration to a report presenting a contingency plan for
funding the Argyll and Bute Flexible Food and Fuel Fund for 2025/26, leveraging a
combination of the UK Shared Prosperity Fund (SPF) and earmarked reserves for
Revenues and Benefits administration works. 
Decision 
The Policy and Resources Committee – 
1. acknowledged the work done to date to directly support people to cope with food
and fuel poverty and other cost of living pressures, with over £4.3m in financial
benefits delivered and almost 2,000 households and 800 children receiving the
help that they need; 
2. recognised the importance of extending the fund so that people in Argyll and Bute
who need help can continue to get support; 
3. welcomed and agreed the plan to extend the Flexible Food and Fuel Fund to 31
March 2026, supported by the following funding sources: 
• UK Shared Prosperity Fund (60% of £204,000): £122,400 
• Earmarked reserves: £189,600 
• Total cost for 2025/26: £312,000 
4. noted the recent correspondence to the Committee from Argyll and Bute Citizen’s
Advice Bureau and agreed that officers would continue to explore potential for
any future additional partnership working that may be possible. 
(Reference: Report by Executive Director with responsibility for Finance dated 13
January 2025, submitted) 
9. SUPPORTING COMMUNITIES FUND 2025-26 
The Committee gave consideration to a report detailing proposals for an improved
process for the Supporting Communities Fund in 2025/26, adding to the outlined
proposals approved by Policy & Resources Committee in December 2024. 
Decision

Page 4

The Policy and Resources Committee agreed – 
1. a focus on digital first with promotion of an online application; 
2. non-digital application available if needed to ensure fairness and equality; 
3. a shorter application – one of the key asks from the community survey; 
4. maximum funding which can be applied reduced from £2,500 to £1,500 - allowing
more community groups to be awarded funding; 
5. groups eligible to apply continue to be all third sector organisations in Argyll and
Bute, with additional criteria of: ‘who have a turnover of £150,000 or less’; and 
6. funding is to remain available for projects that come under one or more of the
following criteria: Fairer, Resilient, Greener and Creative. 
(Report by Chief Executive dated 29 January 2025, submitted) 
* 10. SUSTAINABLE PROCUREMENT STRATEGY 2025/2028 - DRAFT DOCUMENT
AND CONSULTATION 
The Committee gave consideration to a report seeking approval for the draft revised
Sustainable Procurement Strategy 2025/2028. 
Decision 
The Policy and Resources Committee – 
1. noted the key changes to the Sustainable Procurement Strategy 2025/2028, and
the changes made to the strategy following the consultation period; and 
2. recommended to the Council agreement of the revised final Sustainable
Procurement Strategy 2025/2028, and the publication on the council’s website in
April 2025 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 17 December 2024, submitted) 
11. EQUALITY OUTCOMES 2025-2029 
The Committee gave consideration to a report detailing work which has been
undertaken to develop a new set of Equality Outcomes which will cover the period
May 2025 to April 2029 as required to comply with the Public Sector Equality Duty. 
Decision 
The Policy and Resources Committee approved the following set of Equality
Outcomes for the period 2025-2029 – 
1. We make access to information and services easier for people with protected
characteristics.

Page 5

2. Our communities are safe for, and welcoming to, people with protected
characteristics. 
3. We raise awareness of issues and challenges faced by people with protected
characteristics along with ways to accommodate and support them. 
4. Argyll and Bute welcomes New Scots and supports them. 
5. We ensure people with protected characteristics are enabled to progress. 
6. Our work relating to equalities and people with protected characteristics is
coordinated across the organisation and its partners and is strategically aligned. 
(Reference: Report by Executive Director with responsibility for Customer Support
Services dated 14 January 2025, submitted) 
12. CONSERVATION AREA REGENERATION SCHEME (CARS) PROJECT 15-19
ARGYLL STREET, LOCHGILPHEAD 
The Committee gave consideration to a report seeking approval to award an
additional Private Sector Housing Grant of £21,220, to help bridge the budget
shortfall for external building works at 15-19 Argyll Street, Lochgilphead. 
Decision 
The Policy and Resources Committee approved utilisation of the £21,220 balance of
Private Sector Housing Grant allocated to the Lochgilphead CARS projects by Full
Council on 21st February 2019 to bridge the funding shortfall at the 15-19 Argyll
Street Lochgilphead CARS project. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 6 January 2025, submitted) 
13. COMMUNITY REGENERATION PARTNERSHIP FUNDING 
The Committee gave consideration to a report detailing 5 priority projects to put
forward for potential funding from the Community Regeneration Partnership. 
Decision 
The Policy and Resources Committee – 
1. approved the updated list of priority projects included at Appendix 1 of the report,
which will form the basis of further negotiations with the UK and Scottish
Governments; and 
2. noted that all funding requires to be committed by financial year 26/27 and would
be subject to business case approvals by Ministry of Housing, Communities and
Local Government Ministers. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated January 2025, submitted)

Page 6

14. CROWN ESTATES FUNDING  ALLOCATION 2025/26 
The Committee gave consideration to a report setting out proposals for the allocation
of the remaining Crown Estates budget allocated in the 2024/25 financial year. 
Decision 
The Policy and Resources Committee – 
1. considered and approved the time sensitive proposals set out in Table 1 of the
report for the remaining Crown Estates budget allocated in the 2024/25 financial
year; and 
2. noted that a further report would be brought back to the Policy and Resources
Committee identifying priority projects for the 2025/26 Crown Estates funding
allocation. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 16 January 2025, submitted) 
* 15. STRATEGIC EVENTS AND FESTIVALS FUND - ROUND 7 2025-26 
The Committee gave consideration to a report providing an update on Round 7
(2025/26) of the Council’s Strategic Events and Festivals Fund (SEF) and details of
the applications submitted and the applications recommended to receive funding. 
The report also sought agreement to allocate a minimum of £90,000 funding to allow
for a SEF Round 8 in 2026/27. 
Decision 
The Policy and Resources Committee– 
1. agreed to the award of eligible SEF Round 7 grants amounting to £106,036 as
detailed in Table 1 of the report;  
2. agreed that any SEF Round 7 grant offer be formally issued upon confirmation
from the event organisation that the event is confirmed as going ahead, match
funding is in place and the event still meets the SEF Round 7 criteria; 
3. agreed to continue delegation of powers to the Executive Director with
responsibility for Development and Economic Growth to allow any subsequent
amendment to existing grant requests due to changes to the event/event budget.
Any amendment to a current grant request/offer would only be considered if the
amendment related to either the same level or a reduction in the request and
constitute up to 75% of legitimate and eligible expenditure. Similarly, if there was
a reduction in the final event costs that would result in delivery of a profit more
than £10,000 (all of which must be reinvested to future events) to the
organisation and that this was sustained over a 3-year period, the final retention
(10%) would not be paid out on the third year of the grant; 
4. agreed to recommend to Council that as part of the budget in February 2025, that
they agree a minimum of £90,000 base funding for Strategic Events and Festivals
in order that the application process can commence for Round 8 (2026/27); and

Page 7

5. agreed and recommended to Council that any underspend from SEF Round 6
(2024/25) was earmarked and used to augment a future SEF round. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 6 December 2024, submitted) 
16. ROYAL NATIONAL MOD 2028 
The Committee gave consideration to a report seeking approval in principle on An
Comunn’s offer for Argyll and Bute to host the Royal National Mòd (RNM) in 2028. 
Decision 
The Policy and Resources Committee – 
1. agreed in principle to hosting the RNM in Dunoon or Oban in 2028 and for the
requirement to enter into an agreement with An Comunn to provide a maximum
of £200K financial support over a four year period with the final payment in
financial year 2028-2029;  
2. agreed to the Council working with Live Argyll to secure the use of the venues for
the duration of the RNM at no cost to the RNM; and 
3. noted that the An Comunn Board meet in March 2025 and had requested that the
Council provide an in principle decision by this date. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 5 February 2025, submitted) 
17. POLICY AND RESOURCES COMMITTEE WORK PLAN 
The Policy and Resources Committee Workplan was before the Committee for
noting. 
Decision 
The Policy and Resources Committee noted the content of the Workplan as at 20
February 2025. 
(Reference: Policy and Resources Committee Workplan dated 20 February 2025,
submitted)