ARGYLL AND BUTE COUNCIL     POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH                   21ST AUGUST 2025
ROADS AND INFRASTRUCTURE
COMMERCIAL SERVICES 
NATURE RESTORATION FUND – PROGRESS TO DATE AND 25/26 SPEND
OPTIONS 
1.0 EXECUTIVE SUMMARY 
1.1  In July 2021 the Scottish Government launched the Nature Restoration Fund,
which provided £10 million of funding for financial year 2021-22 for projects
addressing biodiversity loss and climate change, half of which was delivered via
Local Authorities. Since that date the Council has received further tranches of
funding and projects were agreed by the Policy and Resources Committee on
12 October 2023 and 7 December 2023.  Following a suspension of funds by
Scottish government in 2024 a further tranche of funding split into revenue
(£84k) and capital (£355k) has been allocated to the council for spend in
2025-26. 
1.2  The Nature Restoration Fund aims to support large-scale, multi-year, multi-
partner projects, which deliver transformative changes to deliver nature
recovery.  Consequently, some projects must be phased over several years to
deliver significant improvements to the natural environment.   
1.3  This report updates members on projects previously agreed to be taken
forward (See Appendix 1) and proposes several projects to be delivered in
2025-26 (See Appendix 2) 
1.4  The Scottish Government have a further fund available to Local Authorities and
Scotland’s National Parks for local nature restoration projects. This fund is
accessed via a bidding process which is open to the Council and is also open
to projects that help Scotland's species, woodlands, rivers and seas back on
the road to recovery. Council Officers have looked at this fund however there
is a need for further feasibility work to be done to make a credible bid and this
is reflected in the proposed new projects. 
2.0 RECOMMENDATIONS 
2.1  It is recommended that Policy and Resources Committee:-

Page 2

(a) Note the progress made regarding the previously agreed allocation of
Nature Restoration Funding in Appendix 1 of this report; 
(b)  Consider and approve the proposed projects in Appendix 2 of this
report noting that there is still a balance of funds to be allocated; and 
(c)  Agree delegated Authority to the Executive Directors with responsibility for
Development and Economic Growth and Commercial Services in
consultation with the Policy Leads with responsibility for Planning and
Regulatory Services and Climate Change, Renewables and Net Zero to
amend the distribution of this funding in relation to approved projects in
Appendix 2 if considered necessary. 
3.0 DETAIL 
3.1  The proposed strategic goal for the Nature Restoration Fund is “to catalyse
action at scale to protect and restore nature and Scotland’s biodiversity in land
and at sea”. The fund has an increased focus on outcomes which address the
main drivers of the decline in biodiversity – on land, over-exploitation of the natural
environment and addressing its consequences, habitat loss and fragmentation,
and invasive non-native species – particularly rural biodiversity. 
3.2  The Fund has four strategic themes to be delivered across all the funding
streams: - 
• Habitat restoration – management for enhancement and connectivity;
• Freshwater restoration, including hydrological change;
• Eradication of invasive non-native species impacting on nature; and
• Coastal and marine management to promote restoration and resilience. 
3.3  The Council has been allocated £835,000 of funding since 2021. This new
allocation for 2025/26 is £84k revenue and £355k capital. 
2021/22 £108,000
2022/23 £238,000
2023/24 £489,000
2024/25 0
2025/26 £439,000 
3.4  Previous agreed funding has now been fully committed with projects either
completed, contracts signed and underway or pending legal agreements
and/or suitable weather to carry out agreed actions. A full breakdown of
progress made is contained in Appendix 1 of this report. 
3.5  The new funding confirmed by the Scottish Government is now split between
revenue and capital. In terms of revenue funding officers have identified the
need for additional feasibility works to assist the council on our journey to net
zero and improve our biodiversity on key sites.  It will also cover

Page 3

administrative costs of the council. It is also anticipated that this work will
potentially assist the council, and our partners, to make a bid to other parts of
the Scottish Government nature restoration funding that is competitive in
nature. This work will also help identify future projects that could be a recipient
of future council nature restoration funding subject to member approval and
the Government providing new funding.   
3.6  In terms of the capital element of the fund, council officers have identified
several options for extending existing projects that have proved successful.
This approach takes account of officer capacity to undertake these works
given many competing priorities we now must deal with.  These have been
included in Appendix 2 of this report, and they focus on the council’s
extensive estate including our road network, council land and additional
assets that contain opportunities to improve/restore nature. 
4.0 CONCLUSION
4.1  This report notes the good progress made to date in relation to previous
allocations of the Scottish Government Nature Restoration Fund as identified
in Appendix 1 of this report. The report goes on to recommend that the
Council take forward several deliverable revenue and capital projects via the
new allocation of the Nature Restoration Fund for 2025-26. These projects are
identified in Appendix 2 of this report. 
5.0 IMPLICATIONS
5.1 Policy - There are no policy implications arising directly from this report.
5.2 Financial - There are no direct financial implications arising from this report,
however, it should be noted that some of the projects do remove a financial cost
to the Council, and therefore can be classed as cost avoidance for the 
Local Authority.
5.3  Legal - There are no legal requirements arising directly from this report.
5.4  HR - There is a resource requirement for staff to implement the projects.
5.5 Customer Service - Communities across Argyll and Bute will benefit from this 
funding.
5.6 Risk - There is a risk of loss of funding should the Council not spend this 
funding allocated by the Scottish Government.
5.7 Climate Change - The Nature Restoration Fund aims to support large-scale,
multi-year, multi-partner projects which deliver transformative change to drive 
forward nature recovery and address biodiversity loss and climate change.
5.8  Fairer Scotland Duty – None arising from this report.
5.9 Equalities - protected characteristics – None arising from this report. 
5.10 Consumer Duty - None arising from this report.

Page 4

5.11 Island Communities - None arising directly from this report.
5.12 Children’s Rights and Wellbeing – None arising from this report. 
Kirsty Flanagan, Executive Director with responsibility for Development and
Infrastructure Services
Douglas Hendry, Executive Director with overall responsibility for Commercial
Services 
Councillor Kieron Green, Policy Lead for Planning and Regulatory Services 
Councillor Luna Martin, Policy Lead for Climate Change, Renewables and Net
Zero
11th July 2025                                                  
For further information contact: 
Fergus Murray, Head of Development and Economic Growth
Fergus.Murray@argyll-bute.gov.uk 
Stephen Hall, Interim Head of Road and Infrastructure Services
Stephen.Hall@argyll-bute.gov.uk 
Ross McLaughlin, Head of Commercial Services 
Ross.Mclaughlin@argyll-bute.gov.uk 
APPENDICES
Appendix 1 - List of Projects previously approved by Elected Members
Appendix 2 – List of recommended projects

Page 5

APPENDIX 1 - LIST OF PROJECTS PREVIOUSLY APPROVED BY ELECTED MEMBERS
Nature Restoration Funding
Projects         
Agreed at Policy and
Resources Committee (12
October 2023) £258,000   
Agreed at Policy and
resources Committee (7
December 2023) £575,000   
Contingency/Surplus funding £2,000   
£835,000   
OPTION INDICATIVE
COST
COMMENT CATEGORY UPDATE - July 2025
School Biodiversity Fund £68,000 Competitive fund for local schools to develop
Biodiversity Action Plans for their respective
grounds. Tree planting, food growing,
education materials (Cooler Futures –
potential partnership with ACT)
Habitat restoration Fully Committed

Page 6

Tree Planting Fund £75,000 Competitive fund to grant funds to local
groups, schools or community organisations
to plant native trees across Argyll and Bute.
Community / place /
biodiversity- habitat
creation/enhancement /
carbon sequestration.
Fully Committed
School food waste composting £60,000 In schools that don’t have food waste uplift
investigate setting up of local composting
solutions to be used onsite.
Education / minor cost
avoidance on waste
front/ organic fertiliser
for school plantings.
Fully Committed
Control of invasive non- native
species on Council assets
(spraying or removal Japanese
Knotweed, Rhododendron
ponticum etc).
£100,000 It’s a legal requirement to control INNS.
Proposed four year eradication plan based on
repeat applications of Glyphosate or other
approved chemical to target hotspot areas of
worst species with the aim to be successful.  .
Applications generally need to be made over
a 3 - 4 year period. This proposal will be
carried out within the road corridor or other
areas of Council controlled land but with a
requirement for adjacent landowners to carry
out treatments to land which they control.
Locations are extensive across Argyll and
Bute.  The intention would be to carry out the
majority of these works deploying Council
trained resource. However, in extremely
dense areas, where there will be a need to
carry out some works through stem
injections, a contractor would be sought due
to the intense labour requirement for this
task.
Cost avoidance /
benefit on council
assets, community,
place and biodiversity.
Fully committed - on track,
first applications of this
season just about
complete. Training
courses being sought to
have employees trained
and qualified in stem
injection treatment. This
will allow the Council to
treat more dense areas
and those areas close to
waterways more
effectively. Contractor
assistance being sought to
assist in treating the Black
Lynn in Oban this year
and the following year.

Page 7

Woodland Planting at
Dalinlonghart Dunoon
£100,000 Previous forested area was harvested, there
is an obligation on the part of the Council to
replant this site which is adjacent to the
landfill site currently operated by Renewi
(which will transfer back to the Council at the
end of the PPP contract in Sept 2026). 
This will remove a future financial pressure
for the cost of the planting and will also
produce a long term income source when the
timber can be harvested and sold to the
commercial market.
Nature Restoration -
Benefit to Council
assets, cost avoidance,
carbon sequestration
for climate change and
woodland biodiversity.
Fully committed -
27/06/2025. Works
complete, including: tree
planting, ATV tracks, INNs
removal, final fencing.
Woodland clearance and
native replanting at Kilmory
Estate / Kilmory Business Park
£50,000 Woodland around Kilmory Estate and
Screening Business Park over mature and
likely require felling and re-planting. Using a
mix of native species that will enhance local
biodiversity.  
Habitat Restoration SLA delivered to act to
produce a woodland
management PIN and a
plan for renovation of the
walled garden
Woodland clearance and
native replanting at Kilmory
Estate / Kilmory Business Park
£50,000 Woodland creation in and around Kilmory
Estate and Screening Business Park over
mature and likely require felling and re-
planting. Using a mix of native species that
will enhance local biodiversity.  Note that in
October 2023, the P&R Committee agreed to
£50k of funding – this brings the total of this
project to £100k of funding as it better reflects
the scale of the works involved.
Habitat Restoration-
removal of INNS and
native tree planting
which will contribute to
biodiversity and carbon
sequestration for
climate change.
SLA delivered to act to
produce a woodland
management plan and a
plan for renovation of the
walled garden

Page 8

Nature Networks Mapping
project (as per NPF4) (to be
re-named Local Nature
Conservation Site Review) 
£25,000 The primary purpose of a Nature Network is
ecological connectivity. This connectivity is
required for fully functioning and healthy
ecosystems. One of these priorities is
establishing Nature Networks through
Nature-based solutions, which provide
multiple advantages supporting biodiversity,
climatic resilience, and societal well-being.
Contributes to 30 x 30 objectives
https://www.nature.scot/professional-
advice/protected-areas-and-species/30-30-
and-nature-networks/30-30-explained
Habitat Restoration Fully committed - Enviro
Centre appointed
19.06.25. The project will
run until 12.06.26.
Argyll and Bute Local
Biodiversity Action Plan refresh
£30,000 To develop a clear new framework for Local
Biodiversity Action within Argyll and Bute for
the next 10 years ( this is to ensure delivery)
in order to contribute to 30 x 30 , Nature
Networks and contribute to the delivery SBS 
across Scotland by 2045.
Habitat Restoration Fully committed - Enviro
Centre appointed
19.06.25. The project will
run until 12.06.26
Reed bed restoration at
Glengorm and Gartbreck
landfill sites
£60,000 Restoration of reed bed filtration systems
which are in place to filter and treat leachate
from landfill sites
Coastal and Marine
management
The report was submitted
to SEPA in April.
Additional sampling and
monitoring  required on
site given that the 
unusually dry spell caused
some issues. Await SEPA
advice to progress

Page 9

Perennial Plants – Bowmore
Public Realm
£25,000 The purchase of native shrubs and perennial
plants for the flower beds at Bowmore Public
Realm.
Habitat Restoration Discussions are ongoing
with a Third Sector Partner
who is keen to come on
board with this project. A
planting plan has been
drawn up and shared with
the group for their input.
Proposal for works to
commence this autumn
with current plant material
being removed, new soil
imported and new planting
material incorporated.
From there on the third
sector group will maintain
this area.

Page 10

Play park enhancements
(total based over 2 – 3 year
programme)
£80,000 This proposal is to complement the ongoing
Play Park Renewal Fund and would further
enhance that programme by converting some
areas of tired and aged hard landscaping to
meadow. The additional areas of grass
cutting would be negligible, and this proposal
would remove long term maintenance costs
associated with hard paving and also
approve the local aesthetics.
Benefit to council
assets, cost avoidance,
carbon sequestration,
water absorption,
community, place and
biodiversity in terms of
habitat creation that
benefits pollinator’s.
Locations identified are at
the following play areas,
Tobermory, Ardrishaig,
Sandbank, Rothesay,
Saddell Street, Jock's
Boat, with several areas
identified in Helensburgh
and Lomond, final
adjustments to
Helensburgh locations
currently underway to
ensure the task remains
within budget. Preparation
works will commence
October, for germination to
take place spring 2026.
These works will be
carried out on grassland
bankings etc., however
there are ongoing
maintenance costs of
grass cutting, collection
and removal and also
disposal costs, with proper
wildflower areas having a
lifespan of three years,
four maximum and
requiring to be replaced at
this point, repeating all the
current ongoing works.
This should be reminded
for future investment
opportunities.

Page 11

Dunbeg Community Woodland
(Help to mitigate impact of
peatland)
£60,000 As above. Community / Place,
Carbon sequestration
which helps to address
climate change and
Biodiversity.
Working with LINK / West
Highland RSL, to update
planting proposals and
planning engagement with
local community group to
refine plans prior to
tendering planting works
which is planned for the
end of FQ3.
Former skating pond in
Helensburgh (local nature
conservation site and link to
local nature networks)
£50,000 Opening up some areas of invasive
vegetation to allow wildlife and other users
access to open water.   
Nature
restoration/water
quality.
Fully committed - Scott
and Simmons appointed
3rd April.  Ecology and
drainage surveys
underway. A community
consultation opened on
26th May and ran until 7th
July 2025.  This included
work with local primary
schools and an open day
at the Skating Pond.
TOTAL £833,000

Page 12

APPENDIX 2 - LIST OF RECOMMENDED PROJECTS     
Funding Allocated
2025/2026:   
Revenue £84,000  
Capital £355,000  
Total £439,000           
NUMBER 
OPTION INDICATIVE COST COMMENT CATEGORY
Revenue Capital
1
Integrated
Carbon
Sequestration,
Biodiversity
Restoration, and
Climate
Adaptation on
Council Land
£50,000  A strategic initiative to leverage Nature
Restoration Funding (NRF) for a
comprehensive programme on Argyll & Bute
Council’s own land assets. The programme
will utilise NRF Development Phase funding
for essential mapping, assessment, and pilot
project design. The programme will
systematically map, assess, and enhance
these assets to deliver three interlinked
outcomes: carbon sequestration,
biodiversity recovery, and climate adaptation
through nature-based solutions. 
Biodiversity & Habitat
Restoration, carbon
sequestration
enhancement, and
nature based climate
adaptation.

Page 13

2
Former skating
pond in
Helensburgh
(local nature
conservation site
and link to local
nature networks) 
£75,000  Costs are likely to be in excess of £250k
and will need to be phased over, at a
minimum, NCF financial allocation years
25/26 and 26/27.  Potential phase 1 delivery
- drainage and environmental/biodiversity
works incl invasive species removal, phase
2 delivery - paths infrastructure and
environmental interpretation.  
Nature restoration/water
quality.
3
Biodiversity
Action Plan
implementation
£34,000 £26,000 The Biodiversity Action Plan which has been
commissioned and is in preparation will, in
combination with the reviewed Local Nature
Conservation Sites, identify a
comprehensive list of Biodiversity
Improvement Actions, and LNCS
management measures that are within the
control of the Council to implement.  This is
anticipated to  be ready for FQ1 2026.
Nature restoration

Page 14

4
Dunbeg
Community
Woodland and
Biodiversity
Enhancement /
Visitor
Interpretation.   £100,000 
The existing allocation for the community
woodland will not cover all phases of the
planned planting.  In addition, Phase 4
development is intended to enhance the
adjacent wetlands, and there is opportunity
to advance this proposal and include greater
community benefit by potentially including
visitor interpretation and wetland walkway. 
This will be a multi phased project as part of
a wider Dunbeg Corridor development.   Nature restoration
5
Oban Airport
Peat mitigation
and invasive
species
eradication.   £50,000 
The Oban Business Park is being
redeveloped.  There is a need to manage
peat on site and deal with invasive species
found on the site following detailed site
investigation works.  Nature restoration 
6
Intervention on
the public road
network relating
to invasive
species
eradication.   £104,000  Nature restoration

Page 15

TOTAL £84,000 £355,000    
£439,000