ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21ST AUGUST 2025
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS UPDATE 
1.0 EXECUTIVE SUMMARY
1.1 The Rural Growth Deal, signed on 10 March 2025, will deliver £50m of
investment from the Scottish and UK Governments for projects that are a driver
for inclusive and transformational economic growth across the region. The
Council and key delivery partners will also provide a minimum of £20m of match
funding throughout the 10-year Deal programme.  
1.2 This report provides an update on the Rural Growth Deal (RGD) and
specifically costs associated with project development and follows on from the
report presented to the Policy and Resources Committee on 5 December
2024.   
1.3 Following on from the approvals at the Policy and Resources Committee on 5
December 2024, the RGD Programme Management Office (PMO) continue to
review project timescales and development costs and have identified that the
current threshold of delegated authority to the Internal Programme Board is
likely to be insufficient for some projects and risks slowing progress with the
programme.  The overall value of maximum cash flow requirement has also
been updated.  
1.4 The total estimated development costs for all projects (as shown in Table 2)
are now estimated to be £2.831m – this is reduced from the estimated figure
of £3.183m reported in December 2024.  
1.5 As agreed at Policy and Resources Committee on 5 December 2024, the
Council would set aside a fund from the Priorities Investment Fund to the
value of £0.700m that can pay for the development costs for Council projects
on the basis that all will be paid back by the end of Year 10.  This cash flow
support requirement has now increased to £0.850m (see Table 5, Year 5). 
The maximum cash flow exposure is based on the assumption that the Full
Business Cases are approved and the development costs become claimable. 
Members are asked to note that there remains a risk of abortive development
costs if projects do not progress beyond Full Business Case.    
1.6 As part of the review of project development costs, it has now been identified
that there are likely to be instances where the agreed delegated authority
threshold of £250k will be insufficient to meet pre-construction project
development costs. Where project development costs exceed £250k, there is

Page 2

currently a requirement for approval to be sought from the Policy and
Resources Committee.  This creates risk of delay to projects.   It is therefore
considered prudent to ask the Policy and Resources Committee to consider
increasing the current level of delegated authority to the Internal Programme
Board up to a maximum threshold of 15% of each project. 
1.7 The monitoring of cash flow spend/income against the funds allocated from
the Priority Investment Fund will require to be regularly reported by officers
from the Rural Growth Deal PMO and Financial Services to the Internal
Programme Board initially and when required to the Policy and Resources
Committee.   
RECOMMENDATIONS 
The Policy and Resources Committee are asked to:- 
a) Agree that the Council increases the amount set aside from the Priorities
Investment Fund from £0.700m to £0.850m to cash flow the development
costs for the Council.  This cash flow support will be fully paid back by the
end of Year 10.    
b) Delegate to the Internal Programme Board (Chief Executive and
Executive Directors), in consultation with the Leader and Depute Leaders
to approve pre-development funding requests relating to Council led
projects up to a maximum threshold of 15% of each project, subject to
there being sufficient cash flow available.  (This is an increase to the
£0.250m threshold agreed in December 2024.)

Page 3

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
21ST AUGUST 2025
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS UPDATE 
2.0 INTRODUCTION
2.1 The Rural Growth Deal, signed on 10 March 2025, will deliver £50m of
investment from the Scottish and UK Governments for projects that are a driver
for inclusive and transformational economic growth across the region. The
Council and key delivery partners will also provide a minimum of £20m of match
funding throughout the 10-year Deal programme.  
2.2 This report provides an update on the Rural Growth Deal (RGD) and specifically
costs associated with project development and follows on from the report
presented to the Policy and Resources Committee on 5 December 2024.   
3.0 RECOMMENDATIONS
The Policy and Resources Committee are asked to:- 
a) Agree that the Council increases the amount set aside from the Priorities
Investment Fund from £0.700m to £0.850m to cash flow the development
costs for the Council.  This cash flow support will be fully paid back by the
end of Year 10.    
b) Delegate to the Internal Programme Board (Chief Executive and Executive
Directors), in consultation with the Leader and Depute Leaders to approve
pre-development funding requests relating to Council led projects up to a
maximum threshold of 15% of each project, subject to there being sufficient
cash flow available.  (This is an increase to the £0.250m threshold agreed in
December 2024.) 
4.0 DETAIL
4.1 The majority of RGD projects now have approved Outline Business Cases and
are considering the next stages of project development work to inform their Full
Business Cases. The pre-development work necessary to inform Full Business
Cases includes detailed design, procurement, site investigation works and
statutory consents. Rural Growth Deal funds only become available for
drawdown from Central Government, when a project has an endorsed Full
Business Case. All costs incurred in advance of endorsement are at the risk to
the Council and/or key delivery partners.

Page 4

4.2 As previously advised to Members, there is a significant amount of project
development work necessary in order to complete Treasury Five Case
compliant FBCs.  This includes detailed design, construction tenders and
statutory consents.  In order to develop FBCs the following milestones should be
completed:
• Design to RIBA Stage 4 (Technical Design);
• All consents should be approved (including Planning, Building Warrant
etc.);
• Procurement – costs in the FBC should be based on a tendering
exercise;
• Match funding – must be identified & approved by funders;
• Any Legal agreements between the Council and Partners should be
finalised;
• Carbon Impact Assessments finalised; 
• Equalities Impact Assessments finalised; 
• Programme of works agreed.
4.3 As a general estimate, 10%-15% of project capital budgets requires to be
allocated for pre-construction development costs.led Design/ents/Impact
essments  Construction Tender  
4.4 The Policy and Resources Committee on 5 December 2024 agreed the
following:
• Council sets aside a fund from the Priorities Investment Fund to the value
of £0.700m that can pay for the development costs for Council projects
on the basis that all will be paid back by the end of Year 10. 
• Any cash flow funding requests for projects led by external partners will
be brought to P&R for approval as and when a request for funding is
made and considered on a case by case basis. 
• Delegated authority to the Internal Programme Board (Chief Executive
and Executive Directors) to approve pre-development funding requests
relating to Council led projects up to a threshold of £250k per project from
the new Fund.
4.5 Following on from the approvals at the Policy and Resources Committee on 5
December 2024, the RGD Programme Management Office (PMO) continue to
review project timescales and development costs and have identified that the
current threshold of delegated authority to the Internal Programme Board is
likely to be insufficient for some projects and risks slowing progress with the
programme.  The overall value of maximum cash flow requirement has also
been updated.  
4.6 The RGD Programme Management Office continue to scope project timescales
and development costs. Table 1 provides an update on current estimated
projected development timescales and estimated costs for projects that are
going to require project development support.

Page 5

Table 1: Project Development Timescales (projects that are likely to have
to spend at risk)
Project Project
Developme
nt Period
Estimated
project
developme
nt costs 
Estimate
d capital
cost
Estimated
FBC
Endorseme
nt
First
drawdow
n of Rural
Growth
Deal
funds
(financial
year)
Argyll and Bute Council led projects:
Kintyre
Seasports
2024-2026 £201,700 £2.5m-
£3m
March 2026 2025/26
Islay Low
Carbon
Currently
estimating
2029-2032
£300,000 £3m 2031/32 2032/33
Housing –
Isle of Mull
2025-2026 £80,000 £2.5m January
2026
2025/26
Housing –
Isle of Islay
2026-2027 £100,000 £3m 2027/28 2028/29
Clyde
Engineerin
g &
Innovation
Centre
2027-2029 £700,000-
£1,000,000
(£850,000
mid-point)
£7m-
£10m
2028/29 2029/30
West Coast
UAV Hub
2029-2031 £300,000 £4m 2030/31 2032/33
RGD Partner led projects:
SAMS
STEM Hub
2025-2026 £200,000 £1.75m 2026/27 2026/27
UHI Argyll –
Built
Environme
nt
2026-2028 £200,000 £1.5m 2028/29 2029/30
SAMS C-
SSIDe
2025-2027 £600,000 £6m 2026/27 2027/28 
4.7  Table 2 and 3 below set out the detailed projected profile of expenditure and
claims for project development costs for those projects requiring cash flow
support .  Table 4 and Table 5 summarise this profile to demonstrate the cash
flow implications.

Page 6

Table 2: Projected Profile of RGD Project Development Costs 
Table 3: Projected Claim Profile of RGD Project Development Costs 
Table 4: Summary Profile of estimated RGD Development Costs and Drawdown
(All Projects): 
Table 5: Summary Profile of estimated RGD Development Costs and Drawdown
(ABC Projects Only): 
4.8 The total estimated development costs for all projects (as shown in Table 2) are
now estimated to be £2.831m – this is reduced from the estimated figure of
£3.183m reported in December 2024.  
4.9 As agreed at Policy and Resources Committee on 5 December 2024, the
Council would set aside a fund from the Priorities Investment Fund to the value
of £0.700m that can pay for the development costs for Council projects on the
basis that all will be paid back by the end of Year 10.  This cash flow support
requirement has now increased to £0.850m (see Table 5, Year 5).  The
maximum cash flow exposure is based on the assumption that the Full Business
Cases are approved and the development costs become claimable.  Members
are asked to note that there remains a risk of abortive costs if projects do not
progress beyond Full Business Case.    
2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33 2033/34
Year  1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
Argyll & Bute Council led projects
Kintyre Seasports 41,700.00£ 160,000.00£ 201,700.00£   
Islay Low Carbon 50,000.00£       100,000.00£ 150,000.00£ 300,000.00£   
Housing - Mull 80,000.00£   80,000.00£      
Housing - Islay 100,000.00£ 100,000.00£   
CEIC 500,000.00£ 350,000.00£ 850,000.00£   
West Coast UAV 150,000.00£    150,000.00£ 300,000.00£   
RGD Partner led projects
SAMS STEM Hub 200,000.00£ 200,000.00£   
UHI Argyll - Built Environment 100,000.00£ 100,000.00£ 200,000.00£   
SAMS CSSID-e 200,000.00£ 400,000.00£ 600,000.00£   
Total 41,700.00£ 640,000.00£ 600,000.00£ 600,000.00£ 350,000.00£ 200,000.00£    250,000.00£ 150,000.00£ -£               -£     2,831,700.00£
Project Development Costs
2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33 2033/34
Year  1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Total
Argyll & Bute Council led projects
Kintyre Seasports 201,700.00£ 201,700.00£   
Islay Low Carbon 300,000.00£ 300,000.00£   
Housing - Mull 80,000.00£   80,000.00£      
Housing - Islay 100,000.00£ 100,000.00£   
CEIC 850,000.00£    850,000.00£   
West Coast UAV 300,000.00£ 300,000.00£   
RGD Partner led projects
SAMS STEM Hub 200,000.00£ 200,000.00£   
UHI Argyll - Built Environment 200,000.00£    200,000.00£   
SAMS CSSID-e 600,000.00£ 600,000.00£   
Total -£             281,700.00£ 200,000.00£ 600,000.00£ 100,000.00£ 1,050,000.00£ -£               -£               600,000.00£ -£     2,831,700.00£
Projected Claim Profile

Page 7

4.10 The following Rural Growth Deal projects are not deemed to currently require
project development cash flow support:
• Dunoon STEM Hub – it is deemed that there is sufficient match
funding available from existing funds to cover development costs,
without need to spend RGD funds at risk, in advance of business
case endorsement 
• Rothesay Pavilion – this project is already in delivery phase, post
conditional approval of the Full Business Case 
• Business Skills – this is a revenue project with minor
development costs
• Machrihanish Innovation Campus – at this time, the University
of Stirling have not indicated that they will require cash flow
assistance. 
• Marine Industry Training Centre – this project is currently being
re-scoped following a decision by UHI Argyll to not proceed with
the project. When more is known about the future of the project
and associated funding, estimates on any funding requirements
will be made.
4.11 Where possible, projects will identify match funding opportunties to reduce
reliance on the Priority Investment Fund and reduce financial risk exposure. For
example, the Clyde Engineering and Innovation Centre project continues to
access funding via previously agreed Section 75 monies, and RGD housing
projects have been supported by funding from the Strategic Housing Fund and
other external grants such as the Scottish Governments Islands Programme. 
4.12 The Policy and Resource Committee also agreed that any cash flow funding
request for projects led by external parties will be brought to Policy and
Resources for approval as and when a request for funding is made and
considered on a case by case basis.  The RGD PMO have held initial
discussions to scope cash flow requirements for RGD partner led projects.
While no formal requests for funding support have been made to the PMO at
this stage, it is likely that the Scottish Association for Marine Science (SAMS)
may require cash flow support for their projects. The PMO will continue to work
with SAMS and HIE to identify where cash flow support may be required. UHI
Argyll continue to work through the Outline Business Case process for their
project and will review project development costs following endorsement of the
project Outline Business Case by the Scottish Government. 
4.13 Should future cash flow support be approved by Committee, this will be subject
to robust funding agreements with external partners to minimise potential risk to
the Council.
4.14 As part of the review of project development costs, it has now been identified
that there are likely to be instances where the agreed delegated authority
threshold of £250k will be insufficient to meet pre-construction project
development costs. Where project development costs exceed £250k, there is
currently a requirement for approval to be sought from the Policy and Resources

Page 8

Committee.  This creates risk of delay to projects. 
4.15 As a general estimate, 10-15% of project capital budgets requires to be
allocated for pre-development costs. Therefore, it is estimated that projects with
an overall capital budget of more than £2.5m are likely to exceed the current
level of delegated authority for pre-construction development costs.  For
example, a Council led project such as the Clyde Engineering and Innovation
Cluster has an estimated capital cost in the region of £7-10m, therefore
development costs could range from £700k-£1m. 
4.16 It is therefore considered prudent to ask the Policy and Resources Committee to
consider increasing the current level of delegated authority to the Internal
Programme Board up to a maximum threshold of 15% of each project, subject
to there being sufficient cash flow available. 
4.17 The monitoring of cash flow spend/income against the funds allocated from the
Priority Investment Fund will require to be regularly reported by officers from the
Rural Growth Deal PMO and Financial Services to the Internal Programme
Board initially and when required to the Policy and Resources Committee.    
4.18 Members are reminded that the current funding mechanisms for the RGD
programme require lead partners to incur pre-construction project development
costs at risk and in advance of FBC endorsement.  
4.19 In a scenario where tendered costs are unaffordable, project leads will aim to
secure additional match funding or consider value engineering where possible.
Members should note that value engineering can incur additional design fees. 
4.20 Central Government will not currently fund abortive costs on RGD projects and
the lead funding partners carry the risk of all costs incurred prior to FBC
endorsement.
4.21 If Rural Growth Deal projects are unable to proceed, the associated funding will
require to be reallocated within the wider programme. There are protocols in
place to manage change across the RGD programme and any decision to re-
allocate project funding which deviates from the Full Deal Agreement will require
Ministerial Level approval from both the UK and Scottish Governments. 
5.0 CONCLUSION  
5.1 The majority of RGD projects have now had their Outline Business Cases
approved by Central Government and are scoping project development
requirements necessary for Full Business Cases. A significant amount of work is
required to get to this stage, including detailed design, procurement, site
investigation works and statutory consents. As such, pre-construction activities
will incur significant development costs. 
5.2 Members are asked to note that all spend in advance of FBC endorsement is at
risk to the Council and key project partners and this is necessary due to the
current funding mechanisms on city region and growth deals.  Where possible,
all costs incurred will be reclaimed from RGD capital budgets following

Page 9

endorsement of FBCs by Central Government, however there is a risk over the
lifetime of the RGD programme that the Council will have to fund any abortive
project development costs.
5.3 The Policy and Resources Committee has previously agreed delegated
authority of up to £250k to the Internal Programme Board to cashflow RGD
project development costs. On review of the programme, this level of delegated
authority is now deemed insufficient and risks delay to the programme.  The
Policy and resources Committee are therefore asked to consider a request to
increase the level of delegated authority to the Internal Programme Board for
pre-development funding up to a maximum threshold of 15% of each project,
subject to there being sufficient cash flow. 
5.4 The Policy and Resources Committee are also asked to increase the cash flow
maximum to £0.850m on the basis that all will be paid back by the end of Year
10.  
6.0 IMPLICATIONS
6.1 Policy – The RGD is consistent with the Council’s Economic Strategy.
6.2 Financial – RGD Projects require a level of upfront spend at risk to allow
project development to progress. There is a risk that where projects do not
proceed, the Council will have to absorb incurred spend on project
development costs via the Priority Investment Fund. 
6.3  Legal – Legal will be required to draft funding agreements with any RGD
Partners who require cash flow funding support.
6.4  HR – None at present.
6.5 Customer Service: None.
6.6  Risk: Risk of abortive spend for any costs incurred prior to FBC endorsements
by Central Government.
6.7  Climate Change: None.
6.8  Fairer Scotland Duty: Required as part of Business Case process.
6.9 Equalities - protected characteristics - Equality Impact Assessments are
required for all RGD projects.
6.10 Customer Duty – None at present. 
6.11 Island Communities: None.
6.12 Childrens rights and wellbeing – None at present. 
Kirsty Flanagan Executive Director with responsibility for Development and
Economic Growth 
Council Leader: Councillor Jim Lynch

Page 10

22 July 2025                                      
For further information contact: 
Fergus Murray, Head of Development and Economic Growth 
Fergus.Murray@argyll-bute.gov.uk 
Jonathan Welch, Transformational Projects & Regeneration Manager
Jonathan.Welch@argyll-bute.gov.uk   
Aileen Semple, Rural Growth Deal Project Officer
Aileen.Semple@argyll-bute.gov.uk