MINUTES of MEETING of POLICY AND RESOURCES COMMITTEE held ON A HYBRID
BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY MICROSOFT
TEAMS on THURSDAY, 21 AUGUST 2025 
Present: Councillor Jim Lynch (Chair) 
Councillor John Armour
Councillor Math Campbell-Sturgess
Councillor Audrey Forrest
Councillor Kieron Green
Councillor Mark Irvine 
Councillor Luna Martin
Councillor Dougie McFadzean
Councillor Ross Moreland
Councillor Gary Mulvaney 
Attending: Pippa Milne, Chief Executive
Douglas Hendry, Executive Director
Kirsty Flanagan, Executive Director
Carolyn Earl, Interim Head of Financial Services
Fergus Murray, Head of Development and Economic Growth
Ross McLaughlin, Head of Commercial Services
Shona Barton, Governance Manager 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Amanda Hampsey, Reeni
Kennedy-Boyle, Liz McCabe, Yvonne McNeilly and Dougie Philand. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest intimated. 
The Chair ruled and the Committee agreed in order to facilitate smooth running of the
agenda, to vary the order of business and to take item 15 as the last item of the meeting. 
This would  allow the Committee to deal with all of the business which could be taken in
public before moving into private session. 
3. MINUTES 
The Minutes of the meeting of the Policy and Resources Committee held on 8 May 2025
were approved as a correct record. 
4. FINANCIAL MONITORING OVERVIEW - 30 JUNE 2025 
The Committee gave consideration to a report providing a summary of the overall financial
position of the Council for 2025-26 as at 30 June 2025. 
Decision 
The Policy and Resources Committee – 
1. noted the revenue budget monitoring report as at 30 June 2025; 
2. noted the capital plan monitoring report as at Quarter 1 and approved the proposed
budget changes to the Capital Plan outlined in paragraphs 4.3 to 4.6 of that report;

Page 2

3. noted the 2025-26 financial risks report; and 
4. noted the reserves and balances report as at 30 June 2025. 
(Reference: Report by Section 95 Officer dated 30 July 2025, submitted) 
5. BUDGET OUTLOOK 2026-27 TO 2030-31 
The Committee gave consideration to a report summarising the Budget Outlook for the 5
year period 2026-27 to 2030-31 and providing an update to the position previously
reported to the Policy and Resources Committee in May 2025. 
Decision 
The Policy and Resources Committee noted the current Budget Outlook position for the
period 2026-27 to 2030-31. 
(Reference: Report by Section 95 Officer dated 31 July 2025, submitted) 
6. PROPOSAL TO REVIEW THE SCHEME FOR THE ESTABLISHMENT OF
COMMUNITY COUNCILS IN ARGYLL AND BUTE: PHASE ONE
FEEDBACK 
The Committee gave consideration to a report providing an update on feedback received
following an 8 week public consultation on the proposals to amend the local Scheme for
the Establishment of Community Councils and suggesting further amendments based on
the feedback received. 
Decision 
The Policy and Resources Committee – 
1. noted the feedback received following the stage one consultation outlined in Appendix
1 to the submitted report; 
2. agreed to carry out a second phase 8-week consultation with the public and
community councils, based on the draft revised Scheme for the Establishment of
Community Councils at Appendix 2 to the submitted report and Best Practice
Agreement at Appendix 3 to the submitted report; and 
3. noted that in terms of the agreed timetable for the review, a further report on the
second stage consultation, including consideration of grant funding, and any final
proposals would be submitted to a specially convened Council meeting on 26
November 2025.   
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 11 July 2025, submitted) 
7. CROWN ESTATES FUNDING ALLOCATIONS 2025/26 AND REDIRECTION
OF PREVIOUSLY ALLOCATED PROJECT FUNDING 
The Committee gave consideration to a report bringing forward proposals for the 2025-26
allocation of Crown Estates Funding, recommending a change to funding previously

Page 3

agreed for a Building Aires style campervan site in Dunoon (Glen Morag car park) and
recommending a change to the funds allocated for Kintyre Sea Sports (KSS). 
Decision 
The Policy and Resources Committee – 
1. agreed to the allocation of the Crown Estate funding for 2025/26 to the projects
outlined in Table 1, paragraph 4.2.1 of the submitted report; 
2. agreed to varying the use of previously allocated Crown Estate funding assigned to a
now confirmed unviable project Building Aires style campervan site in Dunoon
(Glenmorag Car Park) for a simpler, smarter and more sustainable Aires Project in
Cowal; and 
3. noted the update provided in relation to the planning application for the new Kintyre
Sea Sports facility and approved the revised scope of project activities to be funded
from the £200k of Crown Estates Funding previously approved by the Policy and
Resources Committee in February 2025. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 1 July 2025, submitted) 
8. ISLANDS COST CRISIS EMERGENCY FUND 2025/26 
The Committee gave consideration to a report providing an overview of the proposed
arrangements for the Islands Cost Crisis Emergency Fund in 2025/26. 
Decision 
The Policy and Resources Committee – 
1. noted the funding announced by the Scottish Government for the 2025/26 financial year
for Local Authorities with responsibility for islands; and 
2. agreed to the allocation of the Islands Cost Crisis Emergency Fund for 2025/26 to
support the projects set out below:- 
ICCEF 2025/26 Distribution 
Targeting Fuel Poverty with ALI
energy’s Affordable Warmth Service
£120,000
Food Bank Grants  £25,000
TOTAL ICCEF 25/26 £145,000 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 2 July 2025, submitted)

Page 4

9. PLACE BASED INVESTMENT PROGRAMME FUNDING ALLOCATIONS
2025/26 
The Committee gave consideration to a report advising that the Place Based Investment
Programme Offer of Grant from Scottish Government had been received on 25 June 2025
and had confirmed partial release of funding resulting in a reduction from £496,000 to
£388,368, with the remaining £107,632 subject to the Scottish budget position later in the
year. 
Decision 
The Policy and Resources Committee agreed to the reprioritisation of projects set out in
Table 1, paragraph 3.2 of the submitted report following Scottish Government notification
that this funding would now be received in two tranches. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 1 July 2025, submitted) 
10. RURAL GROWTH DEAL - PROJECT DEVELOPMENT COSTS UPDATE 
The Committee gave consideration to a report providing an update on the Rural Growth
Deal (RGD) and specifically costs associated with project development and followed on
from the report presented to the Policy and Resources Committee on 5 December 2024. 
Decision 
The Policy and Resources Committee – 
1. agreed that the Council increase the amount set aside from the Priorities Investment
Fund from £0.700m to £0.850m to cash flow the development costs for the Council,
noting that the cash flow support would be fully paid back by the end of Year 10; and 
2. delegated to the Internal Programme Board (Chief Executive and Executive Directors),
in consultation with the Leader and Depute Leaders to approve pre-development
funding requests relating to Council led projects up to a maximum threshold of 15% of
each project, subject to there being sufficient cash flow available, noting that this was
an increase to the £0.250m threshold agreed in December 2024. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 22 July 2025, submitted) 
11. NATURE RESTORATION FUND - PROGRESS TO DATE AND 25/26
SPEND OPTIONS 
The Committee gave consideration to a report providing an update on the Nature
Restoration Fund, the projects previously agreed to be taken forward and proposing
several projects to be delivered in 2025-26. 
Decision 
The Policy and Resources Committee – 
1. noted the progress made regarding the previously agreed allocation of Nature
Restoration Funding in Appendix 1 of the submitted report;

Page 5

2. approved the proposed projects in Appendix 2 of the submitted report noting that there
was still a balance of funds to be allocated; and 
3. agreed delegated authority to the Executive Directors with responsibility for
Development and Economic Growth and Commercial Services in consultation with the
Policy Leads with responsibility for Planning and Regulatory Services and Climate
Change, Renewables and Net Zero to amend the distribution of this funding in relation
to approved projects in Appendix 2 to the submitted report if considered necessary. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth and Executive Director with responsibility for Commercial Services
dated 11 July 2025, submitted) 
12. CLIMATE CHANGE BOARD - PERFORMANCE REPORT & PUBLIC
SECTOR DUTIES RETURN 
The Committee gave consideration to a report providing the Committee with an analysis of
the Council's 2023/24 climate performance, in line with its statutory duties under the
Climate Change (Scotland) Act 2009. The report presented an analysis of the Council’s
most recent emissions data for the 2023/24 period, contextualised with findings from the
analysis of national Public Bodies Climate Change Duties Report prepared by the
Sustainable Scotland Network (SSN). The report provided the committee with an
assessment of the Council’s current performance, enabling informed strategic decisions to
be made to accelerate the Council’s progress towards meeting climate change
commitments. 
Decision 
The Policy and Resources Committee – 
1. noted progress towards net zero and the challenges identified in the Council’s 2023/24
Public Sector Duties Submission which included a 3.8% rise in previous financial year
but 31% reduction overall; and 
2. endorsed the strategic priorities outlined to accelerate climate action and ensure
progress towards the Council’s net zero targets. 
(Reference: Report by Executive Director with responsibility for Commercial Services
dated 21 August 2025) 
13. CLIMATE CHANGE BOARD UPDATE & DECARBONISATION TRACKER 
The Committee gave consideration to a report providing an overview and update of recent
activity completed or underway by the Climate Change Board. 
Decision 
The Policy and Resources Committee – 
1. noted the contents of the submitted report and the key implications for the Council
arising from the Scottish Government’s consultation on new statutory guidance for
Public Bodies' Climate Change Duties; and

Page 6

2. noted the updates from the Climate Change Board including Drax LED installations,
SG Consultation on draft Statutory Guidance for public bodies, Burnett Building
Climate Adaptation, the Nature Restoration Fund Initiative, the climate change
focussed work of the CPP, and the developments in the Kilmory grounds with ACT. 
(Reference: Report by Executive Director with responsibility for Commercial Services
dated 21 August 2025, submitted) 
14. COMMUNITY EMPOWERMENT (SCOTLAND) ACT 2015 - UPDATE -
EXPRESSIONS OF INTEREST / ASSET TRANSFER REQUESTS /
PARTICIPATION REQUESTS / REPORTING REQUIREMENTS 
The Committee gave consideration to a report advising on the operation of the processes
in regard to formal Asset Transfer Requests (ATR) and Participation Requests in terms of
the Community Empowerment (Scotland) Act 2015; current live informal Expressions of
Interest (EOI’s) which may become subject to a formal asset transfer request or be dealt
with out with the formal asset transfer request process; current live ongoing or agreed
Participation Requests received by the Council; and the annual reporting requirements in
respect of Asset Transfer Requests and Participation Requests set out in Section 95 and
32 of the Community Empowerment (Scotland) Act 2015 respectively. 
Decision 
The Policy and Resources Committee noted the content of the submitted report. 
(Reference: Report by Executive Director with responsibility for Commercial Services
dated 30 June 2025, submitted) 
15. POLICY AND RESOURCES COMMITTEE WORKPLAN 
The Policy and Resources Committee Workplan was before the Committee for noting. 
Decision 
The Policy and Resources Committee noted the content of the Workplan. 
(Reference: Policy and Resources Committee Workplan dated August 2025, submitted) 
The Committee resolved in terms of Section 50(A)(4) of the Local Government (Scotland)
Act 1973 to exclude the press and public for the following item of business on the grounds
that it was likely to involve the disclosure of exempt information as defined in Paragraph 6
of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. 
16. KILMORY BUSINESS PARK - COMMERCIAL ESTATE & PORTFOLIO 
The Committee gave consideration to a report advising of an economic development
opportunity in relation to Kilmory Business Park. 
Decision 
The Policy and Resources Committee agreed the recommendations as detailed within the
submitted report.

Page 7

(Reference: Report by Section 95 Officer and Executive Director with responsibility for
Commercial Services dated 29 July 2025, submitted)