ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 04 DECEMBER 2025
FINANCIAL MONITORING OVERVIEW – 31 OCTOBER 2025  
1. INTRODUCTION 
1.1  This report provides a summary of the overall financial position of the council for
2025-26 as at 31 October 2025.  It outlines the key highlights from the detailed
financial monitoring reports in respect of the following: 
• Revenue Budget;
• Capital Plan (Quarter 2, 30 September 2025);
• Financial Risks; and
• Reserves and Balances. 
2. DETAIL 
2.1 Revenue Budget 
2.1.1 
2.1.2 
2.1.3
This report provides a summary of the actual and forecast outturn expenditure and
income of the council in comparison to the approved 2025-26 revenue budget. 
Since last reporting, the net expenditure budget has increased by £5.651m to
reflect funding for ferries, now provided within the Scottish Government Grant
Settlement as part of the General Revenue Grant, rather than Specific Grant
(£2.810m) and amounts drawn down from earmarked reserve balances (£2.841m).
The revised 2025-26 revenue net expenditure budget now totals £334.376m. 
There are also two budget virements over £200k, requiring committee approval. 
The recently approved pay awards for SJC and Chief Officers, and Teachers are
not yet reflected within the budget monitoring position, however, it is currently
anticipated that this will be funded in full through additional Scottish Government
funding, with no impact on the financial position of the council in 2025-26. 
2.1.4  As at 31 October 2025, there is an overall forecast underspend of £0.480m on the
approved revenue budget for the year.  This underspend is in respect of a forecast
over-recovery of Council Tax income, estimated at £0.500m, offset by a net
overspend of £0.020m across council services. 
2.1.5  It is anticipated that savings in debt interest costs will be achieved during the year,
providing an opportunity to redirect resources to future council priorities, including
the forecast 2026-27 budget gap.  At this stage, it is deemed prudent to assume no
variance in the 2025-26 forecast outturn position in this respect. 
2.1.6 The 2025-26 approved budget savings options, to be achieved in 2025-26, total
£2.762m.  There are 15 savings options impacting 2025-26, of which 8 have been
delivered (£1.375m), with the remaining 7 on track to be delivered (£1.387m).

Page 2

Progress on the delivery of approved savings options will continue to be monitored
throughout the year.   
2.1.7  The 2025-26 HSCP forecast outturn position in respect of Social Work services as
at 31 October 2025 is an overspend of £0.733m.  However, the HSCP expect this to
be managed from within available HSCP reserves, with no impact on the council’s
forecast financial position.  This represents a significant financial risk to the council
that will continue to be monitored on an ongoing basis throughout the year. 
2.2 
2.2.1 
2.2.2 
2.2.3 
2.2.4 
2.2.5 
2.2.6 
2.2.7 
Capital Plan 
This report provides an update on financial performance and the delivery of capital
projects against the approved capital plan budget resources and timescales as at
Quarter 2, 30 September 2025. 
A number of budget changes totalling £1.852m are proposed, reflecting previously
approved investment in respect of the Education ASN Review (£1.255m) and Mull
Joint Campus (£0.434m); and available resources in respect of the TIF Oban
Airport Project (£0.163m). 
Approved gross expenditure on the capital plan, excluding spend incurred in prior
years, totals £212.124m, while project specific income, excluding amounts
accounted for in prior years, totals £12.263m.  This gives approved net expenditure
of £199.861m to be incurred across 2025-26 and future years. 
Forecast gross expenditure and project specific income, taking account of budget
changes, have been profiled across 2025-26, 2026-27 and future years.  The
resulting forecast gross expenditure profile as at Quarter 1 is £76.308m 2025-26,
£64.467m 2026-27 and £71.522m future years, while forecast project specific
income is profiled £12.243m 2025-26.  The profile of forecast expenditure will be
reviewed and updated throughout the year, with an explanation of future movements
reported to committee.   
Actual gross expenditure of £24.298m has been incurred during the first quarter of
2025-26, representing 31.8% of the £76.308m gross expenditure forecast for the
year.  No project specific income has been received during the quarter. 
Forecast gross expenditure across 2025-26 and future years totals £212.297m,
compared to an approved budget of £212.124m, giving rise to a forecast overspend
of £0.173m (0.1%).  Forecast income is in line with budget at £12.243m. 
There are 126 projects within the approved Capital Plan. Of this total, 123 or 98%
are Complete or On Track and 3 are Off Track and Experiencing Problems
2.3 Financial Risks 
2.3.1  This report provides an update on the current known financial risks facing the council
in 2025-26.   
2.3.2 There are 7 quantifiable council wide risks identified for 2025-26, with a potential
annual value totalling £5.1m, and with varying degrees of likelihood.  In addition,

Page 3

there are 32 departmental/service risks, with a potential annual value totalling
£4.156m, of which 5 are categorised as ‘Likely’ (annual value £1.210m).   
2.3.3 There have been no changes to the quantifiable risks since last reporting.  Financial
risks will continue to be monitored and reviewed on an ongoing basis, with actions
put in place to mitigate or manage these risks.   
2.4 Reserves and Balances 
2.4.1 This report summarises the overall level of reserves and balances held by the council
and monitors the use of the earmarked reserves held within the General Fund.   
2.4.2 The council has a total of £406.347m unusable reserves that are not backed with
resources.  These are required purely for accounting purposes. 
2.4.3 
2.4.4
As at 31 March 2025, the council held usable reserves, totalling £121.235m,
comprising the following: 
• £3.608m Repairs and Renewals Fund;
• £3.358m Capital Funds; 
• £1.564m Capital Grants Unapplied; and
• £112.705m General Fund, with £105.161m of this balance earmarked for specific
purposes. 
The 2025-26 opening earmarked reserves balance of £105.162m includes a
significant level of reserves in respect of major infrastructure or projects of strategic
importance.  It is currently anticipated that a total of £22.349m will be drawn down
during 2025-26, with £7.501m drawn down in the year to date.  The expected
drawdown includes £2.953m to balance the 2025-26 budget; as previously approved
by Council in February 2025.  Financial support of £30k for Mid Argyll Community
Pool is also assumed, subject to Member approval.  Similar to previous years, a
review of earmarked reserves is now underway and will subsequently be reported to
members, taking cognisance of strategic priorities and the financial challenges
currently facing the council. 
2.4.5 The council’s General Fund contingency is set at 2% of estimated net revenue
expenditure for 2025-26, which amounts to £6.539m.  At the beginning of the
financial year, there was an unallocated General Fund Balance of £1.004m over and
above the general contingency.  This is currently forecast to increase to £1.246m as
at 31 March 2026.   
2.4.6 The table below summarises the current position on the unallocated General Fund
balance.  
Heading Detail £000
Unallocated General Fund
as at 1 April 2025
Unallocated balance over and above
the 2% general contingency
(£6.539m)
1,004
Current Forecast Outturn
for 2025-26 as at 31
October 2025 
Per Revenue Budget Monitoring report 480

Page 4

Standby Rate Increase –
2025-26 Cost
To fund 2025-26 cost of the Standby
Rate increase, approved by Council
26 November
13
Royal National MOD To fund financial support to Royal
National MOD over 4 years, subject to
member approval
225
Forecast Unallocated General Fund as at 31 March 2026 1,246 
3.  RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee: 
a) Approve the budget changes set out in Section 3 of the 2025-26 Revenue
Budget Monitoring report and Section 4 of the Capital Plan Monitoring
report; 
b) Approve 2025-26 financial support of £30k to Mid Argyll Community Pool
from the Priorities Investment Fund, as outlined within paragraph 3.3.6 of
the Reserves and Balances report; 
c) Note the contents of the 2025-26 Revenue Budget Monitoring, Financial
Risks, and Reserves and Balances reports as at 31 October 2025; and
Capital Plan Monitoring report as at Quarter 2, 30 September 2025; and 
d) Recommend to Council that the revenue budget virements over £0.200m,
set out at paragraph 3.2 of the Revenue Budget Monitoring report, are
approved. 
4. IMPLICATIONS 
4.1  Policy –                                                        None.
4.2 Financial -  Outlines the 2025-26 financial position
of the council as at 31 October 2025.
4.3 Legal -  None.
4.4
4.5
4.6
4.7
HR – 
Customer Service - 
Risk –
Climate Change -
None.
None.
Outlines 2025-26 Financial Risks.
None
4.8 Fairer Scotland Duty - None
4.9 Equalities – protected characteristics -  None.
4.10 Consumer Duty - None.
4.11 Island Communities - None.
4.12 Children’s Rights and Wellbeing - None.

Page 5

Kirsty Flanagan
Executive Director /Section 95 Officer
20 November 2025 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services 
For further information contact Carolyn Earl, Interim Head of Financial Services
Carolyn.Earl@argyll-bute.gov.uk

Page 6

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
04 DECEMBER 2025
2025-26 REVENUE BUDGET MONITORING – 31 OCTOBER 2025  
1. EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to provide a summary of the financial
performance of the council against the approved 2025-26 revenue budget as at
31 October 2025. It reports on the monitoring of forecast net expenditure across
services, in comparison to the approved annual budget, and provides an
explanation of significant variances. Details of actual expenditure incurred during
2025-26 to date are also provided. The report reflects proper accounting practice;
and is based on information contained within the council’s financial systems,
estimation techniques and the professional judgement of council officers. 
1.2 
1.3
Since last reporting, the net expenditure budget has been increased by a further
£5.651m to reflect funding for ferries now being provided within the Scottish
Government Grant Settlement as part of the General Revenue Grant, rather than
Specific Grant (£2.810m) and amounts drawn down from earmarked reserve
balances (£2.841m). The revised 2025-26 revenue net expenditure budget now
totals £334.376m.  There are also two budget virements over £200k, requiring
committee approval. 
The recently approved pay awards for SJC and Chief Officers, and Teachers are
not yet reflected within the budget monitoring position, however, it is currently
anticipated that this will be funded in full through additional Scottish Government
funding, with no impact on the financial position of the council in 2025-26.   
1.4 
1.5 
1.6 
1.7
Overall, there is a forecast underspend of £0.480m for the year on the council’s
approved 2025-26 revenue budget. This is due to a forecast over-recovery of
Council Tax income, currently estimated at £0.500m, partially offset by a net
overspend across services, totalling £0.020m. 
The forecast net overspend across services (£0.020m) comprises a forecast
overspend of £0.419m within the Executive Directorate (Kirsty Flanagan), offset
by a net underspend of £0.066m within the Executive Directorate (Douglas
Hendry) and an underspend of £0.333m across Central budgets.  This position
will be monitored and reviewed on an ongoing basis, with regular updates
reported to committee throughout the year.   
It is anticipated that savings in debt interest costs will be achieved during the year,
providing an opportunity to redirect resources to future council priorities, including
the forecast 2026-27 budget gap.  At this stage, it is deemed prudent to assume no
variance in the 2025-26 forecast outturn position in this respect. 
The 2025-26 revenue budget includes approved savings totalling £2.762m.  At
this stage, all approved savings have either been delivered or are on track to be
delivered. Progress on delivery will continue to be monitored throughout the year. 
1.8  The HSCP is currently forecasting an overspend of £0.733m in respect of Social
Work services. However, the HSCP expect this to be managed from within

Page 7

1.9
existing HSCP reserves, with no impact on the council’s forecast position for the
year.  This represents a significant financial risk to the council.                                                                                                                                
There are a number of financial risks, which may impact the financial position of
the council during 2025-26.  These are outlined in a separate financial risks
report.

Page 8

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
04 DECEMBER 2025
2025-26 REVENUE BUDGET MONITORING – 31 OCTOBER 2025  
2. INTRODUCTION 
2.1 
2.2
The main purpose of this report is to provide a summary of the financial
performance of the council against the approved 2025-26 revenue budget as at
31 October 2025.  It reports on the monitoring of forecast net expenditure across
services, in comparison to the approved annual budget, and provides an
explanation of significant variances.  Details of actual expenditure incurred during
2025-26 to date are also provided.   
The report has been prepared in accordance with proper accounting practice. 
Financial forecasts are based on information contained within the council’s
financial systems, estimation techniques and the professional judgement of
council officers. 
3. BUDGET CHANGES 
3.1 
3.2 
3.3
The 2025-26 revenue net expenditure budget as at 31 August 2025 totalled
£328.725m.  This reflected the use of earmarked reserve balances totalling
£2.953m to balance the 2025-26 budget, approved by Council in February 2025,
including £331k in respect of deferred savings options, funded from the Priorities
Investment Fund.  Since last reporting, the net expenditure budget has increased
by £5.651m to reflect funding for ferries now provided within the Scottish
Government Grant Settlement as part of the General Revenue Grant, rather than
Specific Grant (£2.810m) and amounts drawn down from earmarked reserve
balances (£2.841m).  The revised 2025-26 revenue net expenditure budget now
totals £334.376m. 
Virement is the process of transferring budget between cost centres, services or
departments.  The Council’s constitution requires member approval of budget
virements over £200k. There are two budget virements requiring approval, as
follows: 
a) Re-alignment of NDR budgets – NDR 2025-26 budget right-sizing
adjustment (£0.321m) held in Sundry Services, now allocated across
services; and
b) Re-alignment of ASN budget – Re-alignment of ASN budget resources
within Education (£0.392m) to allow greater clarity for budget monitoring
purposes. 
The 2025-26 budget included a 3% pay award assumption across all workforce
categories, at all grades, based on the Public Sector Pay Policy of 9% over the 3
years 2025-26 to 2027-28.  The pay award for SJC and Chief Officers has now
been agreed at 4% for 2025-26 and 3.5% for 2026-27.  Negotiations in respect of
the pay award for teachers have also now concluded, with 7.5% agreed over the
2 years 2025-26 and 2026-27 (4% from 1 August 2025, rising to 4.25% from 1
April 2026, and 3.25% from 1 August 2026).  At this stage, the expectation is that
the increased cost of the 2025-26 pay award for all council and HSCP Social

Page 9

Work services employees will be fully funded from additional Scottish Government
grant funding, with no impact on the financial position of the council in 2025-26. 
This has not yet been reflected within the budget monitoring position and will also
remain subject to financial risk until confirmation of additional funding. 
4. 
4.1 
4.1.1 
4.2 
4.2.1 
4.2.2 
4.2.3 
4.3 
4.3.1 
SUMMARY FINANCIAL POSITION 
2025-26 Overall Council Financial Position 
There is currently an overall forecast underspend of £0.480m or 0.1% for the year
on the council’s approved 2025-26 revenue budget.  This is due to a forecast
over-recovery in funding in respect of Council Tax income, currently estimated at
£0.500m, partially offset by a net overspend across council services, totalling
£0.020m.  A summary of the forecast net expenditure for the year, in comparison
to the approved budget, both on a departmental and subjective basis, is outlined
within Appendix 1.  This also provides information in respect of council-wide
operational challenges and proposed mitigating actions. 
Council Services Net Expenditure 
At this stage, there is a forecast net overspend on approved service net
expenditure budgets, totalling £0.020m.  This comprises a forecast net
underspend of £0.066m in respect of Executive Directorate (Douglas Hendry), a
forecast overspend of £0.419m in respect of Executive Directorate (Kirsty
Flanagan) and a forecast underspend of £0.333m across Central budgets.  This
position will be monitored and reviewed on an ongoing basis, with regular updates
reported to committee throughout the year. 
A more detailed analysis of the financial position at service level for each
Executive Directorate is given within Appendix 2.  The forecast net underspend in
respect of Executive Directorate (Douglas Hendry) is largely due to delayed
spend in 100 Day Promise funding and Catering efficiency savings, offset by
demand for Schools Residential placements.  Within Executive Directorate (Kirsty
Flanagan), the most significant adverse variance is in respect of a forecast under-
recovery in ferry berthing income within Roads and Infrastructure Services,
aligned to the publication of the Cal Mac winter timetable.  Appendix 2 also
provides information in respect of service specific operational challenges and
proposed mitigating actions. 
The forecast underspend across Central budgets includes an underspend of
£0.200m in respect of Utlities, however, this is challenging to forecast and will be
subject to actual usage over the winter months.  There is also a forecast
underspend in Payments to Joint Boards (£0.133m), with the council’s
contribution to the Valuation Joint Board now confirmed at below the budgeted
level.   
Loans Fund 
The council’s treasury position is actively managed in line with the approved
2025-26 Treasury Management Strategy and Annual Investment Strategy, in
order to minimise debt interest costs.  In addition, as at 31 March 2025, the
council’s external borrowing was below the level required to finance capital
investment.  It had been possible to defer new external borrowing due to the

Page 10

4.3.2 
4.4 
4.4.1 
4.4.2 
4.4.3 
4.5 
4.5.1 
significant level of internal reserve balances held by the council.  This position will
be impacted by the planned use of earmarked reserves in 2025-26, however, it is
expected to continue to some extent throughout 2025-26.  Furthermore, there has
been slippage experienced in the delivery of the approved capital programme. 
These factors will impact the net financing costs incurred during the year. 
A review of the current Loans Fund and projected debt position of the council is
recommended, to highlight potential opportunities within the existing budget for
recurring or one-off savings, or the capacity to meet future capital investment
priorities, such as the LEIP school.  This will be progressed under the wider
review of capital arrangements, approved as part of the 2025-26 revenue budget,
to be undertaken during 2025-26.  A report on this review will be submitted to
members later in the year.  At this stage, it is deemed prudent to assume that any
potential budget underspend will be redirected to future council priorities, which
may include a contribution to the 2026-27 forecast budget gap, with no impact on
the revenue budget position in 2025-26.   
Council Funding 
Council Tax 
A more sophisticated financial modelling tool has been developed to assist with
Council Tax income projections for 2025-26 and future years.  The forecast level
of Council Tax income is based on current and forecast Band D equivalents, and
reflects actual collection levels to date; and projected levels for the remainder of
the year, based on historical payment profile and collection rate data. 
There is a forecast over-recovery of Council Tax income for the year, in
comparison to the approved annual budget of £70.204m.  This is currently
estimated at £0.500m or 0.7% but will be subject to ongoing review and
refinement, as the year progresses.   
The 2024-25 final outturn included additional Council Tax income of £1.234m in
respect of 2024-25 and prior years, an element of which was expected to be
recurring in 2025-26 and future years.  A significant element of this additional
income (some £0.5m) related to the reclassification of self-catering units as
domestic dwellings by the Assessor, following completion of both the 2022-23 and
2023-24 canvasses during the year, which saw the transfer of properties from the
Non-domestic Rates to Council Tax registers.  There is a significant level of
uncertainty in respect of the regulatory environment in this respect, with a risk of
appeals being granted and properties returning to Non-domestic Rates.  This
uncertainty in respect of both timing and financial value, presents an added
element of complexity in respect of Council Tax income projections.  The financial
risk in this respect will be subject to ongoing review throughout the year with
regular updates provided as part of the separate financial risks report. 
HSCP Financial Position 
In respect of the Health and Social Care Partnership (HSCP), it is the
responsibility of the Chief Officer and Chief Financial Officer to manage the HSCP
financial position.  If an overspend is forecast, a budget recovery plan will be
prepared and submitted to the IJB, Argyll and Bute Council and NHS Highland. 
Where recovery plans are unsuccessful and an overspend occurs at the financial

Page 11

4.5.2 
4.6 
4.6.1 
4.7 
4.7.1
year end, and the HSCP has insufficient reserves to meet the overspend, then the
partners will be required to make additional payments to the HSCP.  The council’s
contribution would reflect the element of the overspend related to Social Work. 
Whilst any additional payments by the council and NHS Highland will be deducted
from future years funding, there is a risk that the council may require to make an
additional unbudgeted contribution to the HSCP during the year.     
As at 31 October 2025, the HSCP is forecasting an overspend of £0.733m for the
year in respect of Social Work services, due to demand for residential placements
within both Children and Families and Older People Services.  However, the
HSCP expect this to be managed from within available HSCP reserves, with no
impact on the council’s forecast financial position.  This represents a significant
financial risk to the council.  The financial position of the HSCP in respect of
Social Work services will continue to be monitored on an ongoing basis
throughout the year. 
2025-26 Year to Date Financial Position 
Actual services net expenditure incurred during the year to date totals £172.172m. 
This indicates an overspend of £8.494m in comparison to the current profiled
budget to 31 October 2025.  However, the year to date variances within services
largely relate to the timing of income and expenditure, and outstanding recharges
to capital projects.  Further detailed information in respect of the year to date
position is included at summary level within Appendix 1 and at service level within
Appendix 2. 
Approved Revenue Budget Savings 
The 2025-26 revenue budget included approved Operational/Management and
Policy savings options to be delivered in 2025-26, totalling £2.762m.  The delivery
of these savings will be monitored throughout the year, with progress updates
regularly reported to committee.  A summary of the position as at 31 October
2025 is provided within Appendix 3.  There are 15 savings options impacting
2025-26, of which 8 have been delivered (£1.375m), with the remaining 7 on track
to be delivered (£1.387m).  
5. 
5.1 
FINANCIAL RISKS 
Financial risks are monitored and reviewed on an ongoing basis, with actions put
in place to continue to mitigate or manage these risks.  There are a number of
both council-wide and service specific financial risks, which may impact the
financial position of the council during 2025-26.  These are outlined in a separate
financial risks report.   
6. CONCLUSION 
6.1 This report summarises the financial performance of the council in respect of the
approved 2025-26 revenue budget as at 31 October 2025. 
7.  IMPLICATIONS

Page 12

7.1 Policy - None.
7.2 Financial - Outlines the financial position of the council in respect of
the approved 2025-26 revenue budget. 
7.3 Legal -  None.
7.4 HR -  None.
7.5 Customer Service - None.
7.6 Risk -  Details of Financial Risks are separately reported.
7.7 Climate Change -  None.
7.8 Fairer Scotland Duty - None.
7.9 Equalities – Protected
Characteristics - 
None.
7.10 Consumer Duty-  None.
7.11 Island Communities - None.
7.12 Children’s Rights and
Wellbeing -  None.
Kirsty Flanagan
Executive Director/Section 95 Officer
20 November 2025
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services
APPENDICES
Appendix 1 – Summary Financial Position as at 31 October 2025
Appendix 2 – Departmental Financial Position as at 31 October 2025
Appendix 3 – Approved 2025-26 Revenue Budget Savings
For further information contact Carolyn Earl, Interim Head of Financial Services
Carolyn.Earl@argyll-bute.gov.uk

Page 13

FINANCIAL POSITION AS AT 31 OCTOBER 2025 Appendix 1 
OBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 OCTOBER 2025  
YEAR TO DATE (YTD) POSITION CURRENT PROJECTED FINAL OUTTURN
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual
Budget
Forecast
Outturn
Forecast
Variance
Variance
£'000 £'000 £'000 % £'000 £'000 £'000 %
Departmental Budgets                
Chief Executive's Unit 580 564 (16) (2.8%) 1,241 1,241 0 0.0%
Executive Director (Douglas Hendry) 87,514 87,671 157 0.2% 160,906 160,840 66 0.0%
Executive Director (Kirsty Flanagan) 41,669 32,055 (9,614) (30.0%) 66,205 66,624 (419) (0.6%)
Social Work 37,724 37,355 (369) (1.0%) 81,945 81,945 0 0.0%
Total Departmental Budgets 167,487 157,645 (9,842) (6.2%) 310,297 310,650 (353) (0.1%)
Central Budgets  
Other Operating Income and
Expenditure (3,307) 1,168 4,475 383.1% 3,566 3,366 200 5.6%
Joint Boards 657 890 233 26.2% 1,525 1,392 133 8.7%
Non-Controllable Costs 7,335 3,975 (3,360) (84.5%) 18,988 18,988 0 0.0%
Total Central Budgets 4,685 6,033 1,348 22.3% 24,079 23,746 333 1.4%
TOTAL NET EXPENDITURE 172,172 163,678 (8,494) (5.2%) 334,376 334,396 (20) (0.0%)
Financed By  
Scottish Government Grant Funding (138,214) (138,214) 0 0.0% (266,037) (266,037) 0 0.0%

Page 14

Local Tax Requirement (49,281) (49,281) 0 0.0% (70,204) (70,704) 500 (0.7%)
Net Contributions to General Fund 0 0 0 0.0% 9,366 9,366 0 0.0%
Earmarked Reserves 0 0 0 0.0% (7,501) (7,501) 0 0.0%
Total Funding (187,495) (187,495) 0 0.0% (334,376) (334,876) 500 (0.2%)
(Deficit)/Surplus for Period (15,323) (23,817) (8,494)   0 (480) 480 0.1%

Page 15

SUBJECTIVE SUMMARY – OVERALL COUNCIL POSITION AS AT 31 OCTOBER 2025 
YEAR TO DATE (YTD) POSITION CURRENT PROJECTED FINAL OUTTURN  
YTD
Actual
YTD
Budget
YTD
Variance
Variance Annual
Budget
Forecast
Outturn
Forecast
Variance
Variance  
£'000 £'000 £'000 % £'000 £'000 £'000 %
Subjective Category                
Employee Expenses 112,993 111,372 (1,620) (1.5%) 207,561 207,050 511 0.3%
Premises Related Expenditure 12,873 12,358 (515) (4.2%) 24,168 23,987 181 0.8%
Supplies and Services 18,501 17,165 (1,336) (7.8%) 29,169 29,119 50 0.2%
Transport Related Expenditure 9,131 7,652 (1,479) (19.3%) 19,935 19,935 0 0.0%
Third Party Payments 105,615 107,265 1,649 1.5% 195,860 196,393 (533) (0.3%)
Capital Financing 1,938 (2,836) (4,774)   11,356 11,356 0 0.0%
TOTAL EXPENDITURE 261,051 252,976 (8,075) (3.2%) 488,049 487,840 209 0.0%
Income (276,374) (276,793) (419) 0.2% (488,049) (488,320) 271 (0.1%)
(Deficit)/Surplus for Period (15,323) (23,817) (8,494)   0 (480) 480   
Notes
YTD represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.

Page 16

Key Financial Challenges Proposed Actions to address Financial Challenges
Addressing service demand/expectation and the increasing challenges
facing departments across the council in relation to the recruitment and
retention of suitably qualified and experienced staff.
Engagement and monitoring of both issues with departments to
assess how these challenges are affecting service capacity and
capability, staff attendance, utilisation of agency staff and costs.
Collaboration with services and other back-office teams to consider
and develop mitigating actions.
Achieving a favourable year-end position and achieving savings targets
in light of council wide risks to expenditure. 
Robust monitoring of the financial position and delivery of savings to
ensure budget issues inform the budget monitoring process.
Identifying further savings and delivering services more efficiently with
less resources, as whilst a balanced 2025-26 budget was agreed in
February 2025 there are still significant budget gaps in future years.
The council will continue to progress savings options identified, refine
options that require further development and seek to identify further
savings through themed reviews and business process reviews. A
longer-term approach is being explored with the intention to develop
a pipeline of savings that can be delivered over a number of years.
Maintaining or improving the level of service income recovered, for
example planning, building standards and car parking. 
Actively monitor income recovery and ensure council fees and
charges policies are regularly reviewed. 
Managing spend in service areas which are demand led and, to some
extent, outwith service control, for example Winter Maintenance. 
Use a risk-based approach to budget monitoring to focus additional
attention on these areas.
Ongoing requirement to fund unavoidable inflationary increases in areas
like utility costs, fuel, food etc. 
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes. 
Future ongoing impact on revenue budgets as a result of the delivery of
substantial capital projects such as Rothesay Pavilion and a new school
on Mull.
Ensure costs are identified and reported on early in the process so
Members are aware of the ongoing financial impact to budgets.
Monitor and report on these regularly as part of the routine budget
monitoring once the projects are complete.
Delivery of climate change measures which can be costly and result in
overspends.
The council will look at financially sustainable options and closely
monitor the impact of these on the budget position.

Page 17

CHIEF EXECUTIVE’S UNIT – AS AT 31 OCTOBER 2025 
The department is currently forecasting spend in line with budget. 
The department has a year to date underspend of £0.016m (4.2%) which can be attributed to budget profiling issues. 
Forecast Outturn Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
(Oct)
£000
Previous
Forecast
Variance
Reported
to P&R
(Aug) 
£000
Change 
£000
Chief Executive 1,241 1,241 0 0 0
Totals 1,241 1,241 0 0 0 
Year to Date Position 
Key Financial Successes: 
• All savings options have been delivered. 
• The department’s 2024-25 outturn position was an underspend of £0.020m. This resulted from an overall underspend of £0.055m offset
by earmarking of £0.035m due to an auto-carry forward for unspent grants. 
0%
25%
50%
75%
100%
Chief Executive
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 18

CHIEF EXECUTIVE’S UNIT – AS AT 31 OCTOBER 2025 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
To continue to deliver a high-quality service to support community
engagement and participation.
Regular monitoring, reflection and improvement cycle on service
provision to ensure most efficient use of staffing and financial
resources to meet national and local policy requirements for quality
engagement.
To continue to deliver a high quality support service function to community
organisations and community planning partners during a time of challenge
arising from continuing reductions in funding.
Within the partnership working of the CPP we seek to establish
working groups and collate resources within this to deliver high
quality solutions to identified needs.
Demands for funding from community applications to the Supporting
Communities Fund higher than available annual funds by about 40%.
Continue to monitor fund criteria adapting this to align with priority
outcomes for Argyll & Bute and continue to support groups to seek
alternative sources of funding from our database of funding
providers.

Page 19

CHIEF EXECUTIVE’S UNIT – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Service Area YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Executive 287 271 (16) (5.9%) 511 511 0 0.0% Outwith reporting criteria.
Community Planning
& Development 293 293 0 0.0% 730 730 0 0.0% Outwith reporting criteria.  
580 564 (16) (2.8%) 1,241 1,241 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 20

CHIEF EXECUTIVE’S UNIT – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 616 593 (23) (3.9%) 1,095 1,095 0 0.0% The variance is profile related and will be refined
later in the year.
Supplies and
Services 19 17 (2) (11.8%) 22 22 0 0.0% The variance is profile related and will be refined
later in the year.
Transport 6 9 3 33.3% 15 15 0 0.0% The variance is profile related and will be refined
later in the year.
Third Party 59 66 7 10.6% 230 230 0 0.0% The variance is profile related and will be refined
later in the year.
Income (121) (121) 0 0.0% (121) (121) 0 0.0% Outwith reporting criteria.
Totals 580 564 (16) (2.8%) 1,241 1,241 0 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 21

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 OCTOBER 2025 
The department is currently forecasting an underspend position of £0.066m (0.04%). Within Education this is a result of slippage in 100 day
promise budget and maintaining teacher number budgets, due to delays in recruitment, the majority of this is offset by the Schools Residential
Budget having a higher demand for placements than budget allows. In Commercial Services the forecast variance of £0.070m is due to lower
use of bank staff and delays in recruitment. The department has a year to date (YTD) underspend of £0.157m (0.2%).  This is mainly due to
delays in recruitment and the current budget profile, partially offset by the overspend in Schools Residential Budget. 
Forecast Outturn Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
(Oct) 
£000
Previous
Forecast
Variance
Reported
to P&R
(Aug) 
£000
Change 
£000
Executive Director
(Douglas Hendry) 345 345 0 0 0
Head of
Commercial
Services
10,521 10,451 70 0 70
Head of Education 128,570 128,574 (4) (183) 179
Head of Legal and
Regulatory
Support
21,470 21,470 0 0 0
Totals 160,906 160,840 66 (183) 249 
Year to Date Position

Page 22

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 OCTOBER 2025 
Key Financial Successes: 
The 2024-25 year-end consolidated outturn position was an under spend of £0.767m after adjusting for automatic earmarking. Contributing
factors included:
• Continuation of NDEEF and expansion of CEEF projects resulting in recurring annual saving in utilities and a significant contribution to
meeting net zero targets.
• Received funding from DRAX for energy saving lighting in 7 schools, located in the area surrounding Cruachan Power Station, to the
value of £148.8k, with potential for further funding.
• Further rationalisation of office space through Our Modern Workspace Programme has reduced utility costs, printer costs and cleaning
costs as well as receiving Non-Domestic Rates relief for closed buildings. 
• Income generation within Early Years, including expansion at Rothesay Joint Campus to accommodate care for children under the age
of 2.
• Successful grant applications to Bord na Gaidlig and Armed Forces Covenant Grant for Early Years.
• Effective contract management of NPDO and Hub School contracts, including a lower-than-expected insurance premium due to the
annual renegotiation of insurance costs.
• Successful funding awards have enabled the Welfare Rights Team to expand its service. In 2024-25 the whole team have helped
residents of Argyll and Bute claim £4.45m in additional benefits that they were entitled to.  The support is targeted at some of the most
vulnerable in our communities and makes a significant difference to families and individuals both financially and to their overall health
and wellbeing. 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
The legacy impact of COVID-19 on our young learners has led to an
increased demand on the additional support need functions of the
Education Service in response to the growing health and wellbeing
needs of our young people and their families. This annual increase in
assessed need is consistent across Scotland.
Continuous analysis and review of delivery models, robust costings
of agreed changes to the current delivery model being
implemented in August 2025 and continual monitoring of
associated budgets. Maximise use of Additional Support for
Learning Funding and Mental Health and Wellbeing Funding whilst
working collaboratively across Children’s Services.
Impact of the current cost of living crisis on the cost of the school day for
learners and their families.
Collaborate with schools to ensure effective use of Strategic Equity
Funding, Pupil Equity Funding and SG Core Curriculum funding to
close the poverty related attainment gap and identify other multi
agency funding sources to ensure equity of experience for all
children.

Page 23

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – AS AT 31 OCTOBER 2025 
Impact of the current cost of living crisis on uptake in demand led service
areas like catering, design services and licensing.
Continually refine/develop systems to accurately forecast service
usage, budget outturn and future budget requirements. Strategies
in place to redesign services in line with demand.
Reductions to Capital Funding and rising cost of statutory and regulatory
work along with rising material and labour costs across departments may
result in a reduction in activity or overspends within the Central Repairs
Budgets.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as soon as known,
regular meetings with Property Services. 
Ensure that the School Catering Service remains efficient and effective
as the requirement to comply with the Statutory Guidance supporting
Nutritional Requirements for Food and Drink in Schools (Scotland)
Regulations 2020, has increased the cost of producing a school meal.
Continue working with finance to review the efficiency of the
service, through good procurement of supplies and the use of a
school meal pre order app that reduces food waste. Produce meals
that pupils want to eat through regular consultation and a range of
menu choices.
The Council has a requirement to deliver 1140 hours of Early Learning
and Childcare (ELC) to eligible 2-year-olds and all 3–5-year-old children.
Following several years of reduced funding and a requirement to set a
sustainable hourly rate for our valued partner providers, the service must
continually redesign to fit the resources available. 
Robust service costings, financial monitoring and timely reporting
to ensure the service can be delivered within the available budget.
Medium to longer term forecasting on population to shape ongoing
service redesign. Analysis of potential to extend income generation
using “spare” capacity to expand paid care for under 2’s
Impact of high inflationary uplifts within the NPDO/HUB School contracts.  Ensuring continued effective contract management of NPDO/HUB
Schools to minimise the impact of high inflationary uplifts. 
The Scottish Government has increased the amount of ringfenced
Education funding.  This funding is dependent on maintaining teacher
numbers to a set level. Additionally, Councils have been asked to make
progress towards reduced teacher class contact time.
Monitor teacher numbers and associated costs, highlighting any
budget pressures or potential penalties should staffing levels fall
below target.  Collaboration with the Education Service to prepare
robust costings for the impact of any reduction in teacher class
contact time.
The demand for residential school placements for our children is growing
and the costs for this service have had higher than budgeted inflation
due to a reduction in Government financial assistance for Grant Aided
Special Schools (GASS), impact of changes to National Insurance and
commitment for providers to pay real living wage.  These placements are
jointly funded by Education and Social Work.
Monitoring of placements and costs, collaborative working with
other services to ensure that decisions are taken jointly by all
services and all options have been considered and costed.

Page 24

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director
(Douglas
Hendry)
Central/Management
Costs
604 279 (325) (116.5%) 345 345 0 0.0% The YTD overspend variance is
due to £314k of Storm Eowyn
Costs for repairs to Council
Properties being coded here.
Additionally, the Education Review
costs have been coded here and
this variance will be rectified
through draw downs from an
earmarked reserve.    
604 279 (325) (116.5%) 345 345 0 0.0%  
Head of
Commercial
Services
Catering 43 97 54 55.7% 514 444 70 13.6% The YTD underspend of £54k is
due to lower than budgeted staff
and catering purchase costs.  A
favourable forecast variance of
£70k has been processed in
October to reflect the full year
projected outturn. 
Head of
Commercial
Services
Central/Management
Costs
746 742 (4) (0.5%) 1,593 1,593 0 0.0% Outwith Reporting Criteria
Head of
Commercial
Services
CHORD 64 57 (7) (12.3%) 38 38 0 0.0% Outwith Reporting Criteria
Head of
Commercial
Services
Cleaning (81) (63) 18 (28.6%) 130 130 0 0.0% The YTD underspend is due to
lower than anticipated use of bank
staff.
Head of
Commercial
Services
Culture, Heritage,
Recreation & Sport
3,067 3,107 40 1.3% 5,765 5,765 0 0.0% Outwith Reporting Criteria
Head of
Commercial
Services
Events & Commercial
Catering
75 (12) (87) 725.0% 8 8 0 0.0% This YTD overspend is due to
lower than forecasted income in
commercial café's which is mainly
as a result of the temporary
closure of Pier Point Café.
Head of
Commercial
Services
Property Portfolio (194) (156) 38 (24.4%) (187) (187) 0 0.0% The YTD underspend is profile
related and will be refined through
November.

Page 25

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of
Commercial
Services
Property Services 133 327 194 59.3% 1,001 1,001 0 0.0% The YTD underspend is due to
delays in recruitment.  This will be
reduced through harvesting
vacancy savings.
Head of
Commercial
Services
Shared Offices 517 577 60 10.4% 1,659 1,659 0 0.0% The YTD underspend is due to
reduction in building costs as a
result of office rationalisation.    
4,370 4,676 306 6.5% 10,521 10,451 70 0.7%  
Head of
Education
Additional Support for
Learning
7,056 7,027 (29) (0.4%) 13,547 13,547 0 0.0% Outwith Reporting Criteria
Head of
Education
Central/Management
Costs
1,743 1,619 (124) (7.7%) 2,719 2,719 0 0.0% The YTD overspend is due to
payment of subscriptions, PVG's,
SRCO, Licensing, IT software;
budget will require to be identified
for these spends.
Head of
Education
Community Learning
& Development
2 2 0 0.0% 15 15 0 0.0% Outwith Reporting Criteria
Head of
Education
COVID 0 0 0 0.0% 0 0 0 0.0% Outwith Reporting Criteria
Head of
Education
Early Learning &
Childcare
10,753 10,868 115 1.1% 19,268 19,268 0 0.0% The YTD underspend is profile
related and will be refined through
November.
Head of
Education
Primary Education 23,710 24,020 310 1.3% 43,766 43,697 69 0.2% The YTD underspend is mainly
due to delays in recruitment. 
Under the Scheme of Devolved
School Management schools are
permitted flexibility at year end,
therefore no forecast variance will
be processed. A forecast variance
has been processed for slippage
in UFSM budget
Head of
Education
Pupil Support 2,743 2,592 (151) (5.8%) 4,671 5,254 (583) (12.5%) The YTD overspend is due to the
higher demand for Residential
School placements than budget
allows as well as some offsetting
profile related variances.  A
forecast variance has been
processed for the current pressure
in Residential Placements.
Head of
Education
Schools - Central
Services
1,341 1,249 (92) (7.4%) 2,440 2,040 400 16.4% The YTD overspend is profile
related and will be refined through
November.  This is offset by an

Page 26

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
underspend in 100 Day Promise
Budget due to delays in
recruitment. A favourable forecast
variance has been processed to
reflect this.
Head of
Education
Secondary Education 24,265 24,596 331 1.4% 42,144 42,034 110 0.3% The YTD underspend is mainly
due to delays in recruitment. 
Under the Scheme of Devolved
School Management schools  are
permitted flexibility at year end,
therefore no forecast variance will
be processed for £221k of this
underspend. The remainder is
slippage in Secondary School
Headquarter budgets due to
delays in recruitment and a
favourable forecast variance has
been processed to reflect this.    
71,613 71,973 360 0.5% 128,570 128,574 (4) (0.0%)  
Head of Legal &
Regulatory
Support
Central/Management
Costs
150 144 (6) (4.2%) 269 269 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Community Safety 175 144 (31) (21.5%) 197 197 0 0.0% The YTD overspend is due to
removal of cost pressure funding
for annual system costs, budget
will need to be identified for this.
Head of Legal &
Regulatory
Support
Elections 18 13 (5) (38.5%) 16 16 0 0.0% The YTD over spend is profile
related and will be refined through
November.
Head of Legal &
Regulatory
Support
Governance 415 342 (73) (21.4%) 752 752 0 0.0% The YTD overspend is due to
miscoding of retirement entries
and will be rectified through
November.
Head of Legal &
Regulatory
Support
Governance, Risk &
Safety
320 302 (18) (6.0%) 584 584 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Legal Services 347 281 (66) (23.5%) 768 768 0 0.0% The YTD overspend is profile
related and will be refined through
November.

Page 27

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of Legal &
Regulatory
Support
NPDO and Hub
Schools
8,495 8,481 (14) (0.2%) 16,958 16,958 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Procurement,
Commercial and
Contract
Management
652 671 19 2.8% 1,264 1,264 0 0.0% Outwith Reporting Criteria
Head of Legal &
Regulatory
Support
Trading Standards &
Advice Services
355 365 10 2.7% 662 662 0 0.0% Outwith Reporting Criteria    
10,927 10,743 (184) (1.7%) 21,470 21,470 0 0.0%      
87,514 87,671 157 0.2% 160,906 160,840 66 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 28

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 64,184 64,229 45 0.1% 117,821 117,311 510 0.4% Although the YTD underspend is Outwith Reporting
Criteria, we are reporting a Full Year Outturn position of a
£401k underspend due to slippage in recruitment within
100 day Promise Budget.
Premises 4,911 4,565 (346) (7.6%) 10,493 10,493 0 0.0% The YTD overspend is mainly profile related within
Central Repairs and Minor Repairs with £314k being
Storm Eowyn property repair costs coded under Exec
Director DH, some of which may be covered by
Insurance.
Supplies and
Services
8,470 8,762 292 3.3% 15,191 15,121 70 0.5% The YTD underspend within supplies and services is
mainly profile related which will be refined through
November. The forecast variance of £70k is due lower
than anticipated catering purchases within the School
Meal Service.
Transport 260 213 (47) (22.1%) 377 377 0 0.0% The YTD overspend position is due to a high level of
essential staff travel within Education. 
Third Party 30,436 30,200 (236) (0.8%) 47,467 47,981 (514) (1.1%) The YTD overspend is due to the budget pressure within
School Residential Budget and a forecast variance has
been processed to reflect the higher than budget demand
for this service.
Income (20,747) (20,298) 449 (2.2%) (30,443) (30,443) 0 0.0% The YTD over recovery of income is due to the current
budget profile which will be refined through November,
partially offset by an under recovery of School Meal
Income in Hermitage Academy and Oban High.
Totals 87,514 87,671 157 0.2% 160,906 160,840 66 0.0%   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 29

EXECUTIVE DIRECTOR (DOUGLAS HENDRY) – RED VARIANCES SUMMARY AS AT 31 OCTOBER 2025 
Service Area
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Education - Pupil Support 4,675 5,259 (584) (12.5%) Higher than budgeted demand for placements within
Residential Schools Budget.
Education - School Support 2,683 2,283 400 14.9% Recruitment delays within 100 day Promise Budget.
Commercial Services - Catering 514 444 70 13.6% Recruitment delays and lower than anticipated catering
purchases.
Education - Primary Education 43,766 43,697 70 0.2% Recruitment delays within Universal Free School Meal
Budget.
Education - Secondary Education 42,144 42,034 110 0.3% Recruitment delays within Secondary Education HQ 
A red variance is a forecast variance which is greater than +/- £50,000.

Page 30

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 OCTOBER 2025 
Currently there is a forecast overspend of £419k in the department reported, mainly driven by anticipated under-recovery of ferry berthing
income – finance officers will continue to work with their respective services throughout November to provide updates. 
The department has a year to date overspend of £9.614m (30.0%). This is currently being driven by profiling of budget for 2025-26 not aligning
to actual spend/income (especially around Waste), lag in capital works progressing through final measures, accruals/prepayments from the
2024-25 year end that are still to come through and drawdowns from ear-markings which have not taken place yet. 
Forecast Outturn Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
(Oct)
£000
Previous
Forecast
Variance
Reported
to P&R
(Aug) 
£000
Change 
£000
Executive Director
(Kirsty Flanagan) (226) (226) 0 0 0
Head of Customer
Support Services
10,218 10,241 (23) (23) 0
Head of
Development and
Economic Growth 9,197 9,241 (44) (25) (19)
Head of Financial
Services 7,492 7,492 0 0 0
Head of Roads
and Infrastructure
Services 39,524 39,876 (352) 32 (384)
Totals 66,205 66,624 (419) (16) (403) 
Year to Date Position 
0%
25%
50%
75%
100%
Executive
Director (Kirsty
Flanagan)
Head of
Customer
Support
Services
Head of
Development
and Economic
Growth
Head of
Financial
Services
Head of Roads
and
Infrastructure
Services
Expenditure to date against the remaining budget for each
Service
YTD
Actual
£000
Remaining Budget
£000

Page 31

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 OCTOBER 2025 
Key Financial Successes:
The department had a challenging 2024-25 financial year with a net overspend of £2.124 million reported after automatic earmarkings were
applied. This was primarily driven by increased costs in school and public transport contracts, heightened maintenance requirements across
piers, harbours and the Belnahua Ferry, escalated winter maintenance expenses, unachieved savings from the RIS review due to contractor
delays, offset partially by over-recovered vacancy savings and higher-than-anticipated Planning and Building Warrant income. 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Ensuring that services spend to budget and do not overspend. Detailed monitoring in the key areas overspent in 2024-25 to flag up
concerns early and mitigate before becoming an overspend. 
Department / Service ongoing ability to meet future savings / efficiency
requirements.
Monitoring of trends / expenditure levels / service configuration and
the Service Packages Policy Options savings process.
Rising cost of materials, software and consultancy services across the
service will result in a reduction in activity or overspends.
Costs are monitored regularly and contained as much as possible
with any unavoidable overspends highlighted as early as possible.
Financial Services to continue to deliver a high-quality support service
function during a time of substantial uncertainty and challenge arising from
continuing reductions in funding whilst costs are increasing due to
forecasted timelines for reductions in inflation having now been revised.
Ensure the team is operating as efficiently and effectively as
possible by building resilience across the team and working
collaboratively with other services of the Council to support
evidence-based decision making. 
Winter Maintenance costs are difficult to estimate as they are very much
dependant on the weather. 
Close monitoring of Winter Maintenance activity and reporting of the
financial implications through the budget monitoring process. The
Council agreed the winter policy, setting out the intervention level
and locations to be treated. The number of treatments is determined
by weather conditions. There is a sophisticated weather monitoring
system in place consisting of several weather stations, this is
supported by a forecasting and meteorological service which is
collaboratively procured by West of Scotland local authorities.
Climate Change Mitigation impacting on the department’s key
infrastructure will result in overspends as a result of increased inspection
and maintenance activity.
The Council will continue to tackle climate change, looking at
financially sustainable options and will closely monitor the financial
consequences.

Page 32

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – AS AT 31 OCTOBER 2025 
Dangerous buildings costs as there is no budget for this expenditure and
the council has no control over the demand for the service.
Building Standards, Legal Services and Financial Services are
working closely to manage debt recovery and to consider other
options to minimise corporate risk exposure. 
Due to the nature of the various components of Waste Management there
are ongoing challenges with:
• The delay of the Deposit Return Scheme.
• Uncertainty with recycling income/gate fee costs due to the           
volatility of the market.
• Challenges in the legislative changes around the disposal of      
Biodegradable Municipal Waste.
• The Circular Economy Bill that has recently been passed and the
implications that may bring. 
To closely monitor all service components of Waste Management
and review the Waste Strategy in conjunction with our contractual
partner Biffa.
Berthing income from CalMac Ferries Larger CalMac ferries that normally berth at Craignure have been
removed due to ongoing issues in the wider fleet, replaced with
much smaller vessels (MV Isle of Mull having the biggest impact).
The recent release of the winter timetable and vessel deployment
means there is expected to be a significant drop in income. Finance
Contact will be working with the service through the month to
understand the full impact of this.
Overspends showing in Roads & Lighting due to a lag in completed capital
works progressing through final measures.
Roads Operatives to be prompted to complete measures as soon
as schemes are complete so that income will be recorded more
timeously.

Page 33

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Service
Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Executive
Director (Kirsty
Flanagan)
Central/Management
Costs
223 200 (23) (11.5%) (226) (226) 0 0.0% £19k overspend on Consultants in
regards RIS review. The be funded
from Earmarked Reserve 194c    
223 200 (23) (11.5%) (226) (226) 0 0.0%  
Head of
Customer
Support
Services
Central/Management
Costs
87 85 (2) (2.4%) 176 189 (13) (7.4%) Outwith Reporting Criteria
Head of
Customer
Support
Services
Communications 204 206 2 1.0% 360 360 0 0.0% Outwith Reporting Criteria
Head of
Customer
Support
Services
Customer Service
Centres
1,019 981 (38) (3.9%) 1,783 1,783 0 0.0% Outwith Reporting Criteria
Head of
Customer
Support
Services
HR 1,876 1,841 (35) (1.9%) 3,147 3,157 (10) (0.3%) Outwith Reporting Criteria
Head of
Customer
Support
Services
ICT 3,071 2,920 (151) (5.2%) 4,796 4,796 0 0.0% £121k overspend in Microsoft
enterprise agreement - any
overspend for MS365 will be drawn
down from earmarked reserve 071
at year end.  Some over/under
profiling throughout and overspnd
in application salary costs due to
budget in 00803 - Pay inflation not
being profiling out yet centrally.
Head of
Customer
Support
Services
Registrars (15) (45) (30) 66.7% (44) (44) 0 0.0% Use of registrars is down
compared to anticipated budget
YTD, this will be monitored over
the upcoming months. 
Registration income has been
overestimated since the post
pandemic single year surge. 
Registration income has been
under recovered the past few

Page 34

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
years, this resulting in a cost
pressure.    
6,242 5,988 (254) (4.2%) 10,218 10,241 (23) (0.2%)  
Head of
Development
& Economic
Growth
Airports 611 680 69 10.2% 1,272 1,272 0 0.0% Small variance due to income
ahead of budget on fuel purchases
by £52k YTD
Head of
Development
& Economic
Growth
Building Control (202) (77) 125 (162.3%) (60) (60) 0 0.0% YTD income higher than budget
due to fee restructure
Head of
Development
& Economic
Growth
Central/Management
Costs
356 329 (27) (8.2%) 629 629 0 0.0% Outwith Reporting Criteria
Head of
Development
& Economic
Growth
Culture & Heritage 76 77 1 1.3% 235 235 0 0.0% Outwith Reporting Criteria
Head of
Development
& Economic
Growth
Development
Management
(10) 40 50 125.0% 301 301 0 0.0% YTD variance due to higher than
expected income
Head of
Development
& Economic
Growth
Development Policy 366 218 (148) (67.9%) 385 385 0 0.0% YTD Variance due to £132k of
Strategic Development Framework
Helensburgh spend  with no
budget and unallocated saving in
Dev Policy
Head of
Development
& Economic
Growth
Economic Development 1,276 1,519 243 16.0% 1,850 1,850 0 0.0% YTD variance due to UK Shared
Prosperity Fund Grant fully
received and spend ongoing 
Head of
Development
& Economic
Growth
Environmental Health 733 756 23 3.0% 1,391 1,416 (25) (1.8%) Outwith Reporting Criteria
Head of
Development
Environmental Initiatives 65 62 (3) (4.8%) 118 118 0 0.0% Outwith Reporting Criteria

Page 35

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
& Economic
Growth
Head of
Development
& Economic
Growth
Housing 4,114 2,321 (1,793) (77.3%) 2,763 2,782 (19) (0.7%) YTD variance due to Strategic
Housing Fund funded from
earmarkings still to be drawn down
(£2m set aside in earmarking 152)
Head of
Development
& Economic
Growth
Private Landlords (226) (19) 207 (1089.5%) 0 0 0 0.0% Short Term LETS has no budgets,
£240k of income YTD against £32k
of spend)
Head of
Development
& Economic
Growth
Transportation Policy 213 133 (80) (60.2%) 313 313 0 0.0% YTD variance due to Sustrans
grants still to be received although
issues with the Sustrans Grant
portal have been rectified    
7,372 6,039 (1,333) (22.1%) 9,197 9,241 (44) (0.5%)  
Head of
Financial
Services
Accounting & Budgeting 1,599 1,501 (98) (6.5%) 2,776 2,776 0 0.0% Additional employee costs driving
the overall variance, including
agency costs linked to Itrent
Head of
Financial
Services
Internal Audit & Fraud 192 202 10 5.0% 355 355 0 0.0% Outwith Reporting Criteria
Head of
Financial
Services
Revenues & Benefits 747 906 159 17.6% 3,280 3,280 0 0.0% YTD underspend due to the timing
of cash flows in comparison to the
profiling of budget and will be
rectified over the financial year.
Head of
Financial
Services
Scottish Welfare Fund 648 641 (7) (1.1%) 1,081 1,081 0 0.0% Outwith Reporting Criteria    
3,186 3,250 64 2.0% 7,492 7,492 0 0.0%

Page 36

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of Roads
&
Infrastructure
Services
Amenity 2,848 2,342 (506) (21.6%) 3,413 3,414 (1) (0.0%) Largest variance across amenities
continues to relate to under-
recovery of interment income. Also
during July aged debt was written
off relating to the Pavilion café
which went into liquidation during
2024 - funding to cover this to be
discussed with the budget holder. 
Lastly street sweeper external hire
costs high given 2 Council
sweeper vehicles written off and
external hire charges are high -
awaiting information from
Fleet/Service on leasing sweeper
vehicles going forward before
confirming Forecast Variance.
Head of Roads
&
Infrastructure
Services
Car Parking (666) (540) 126 (23.3%) (557) (557) 0 0.0% Over recovery of DPE Fines vs
forecast and incorrect profiling of
maintenance spend.
Head of Roads
&
Infrastructure
Services
Central/Management
Costs
2,100 1,928 (172) (8.9%) 1,426 1,426 0 0.0% Stephen Hall was covering the
Head of Service post. Awaiting
final invoices and then will be
drawn down from earmarked
reserves and any differences will
be included as a forecast variance.
Additional variance made up of
training costs, due to profile not
matching YTD spend.
Head of Roads
&
Infrastructure
Services
Depots 234 205 (29) (14.2%) (292) (292) 0 0.0% Internal Refuse Collection
Recharge profile is still incorrect -
to be corrected in November
Head of Roads
&
Infrastructure
Services
Fleet & Transport 6,893 6,389 (504) (7.9%) 11,719 11,567 152 1.3% Continuing overspend in cost of
internal fleet repairs. Lease costs
paid in advance will be accrued at
year end
Head of Roads
&
Infrastructure
Services
Infrastructure 301 347 46 13.3% 765 765 0 0.0% Design fees over recovered versus
level of fee income required, fee
rate has been adjusted to reduce
future income levels to correct over
recovery.

Page 37

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of Roads
&
Infrastructure
Services
Marine (2,042) (3,136) (1,094) 34.9% (708) (173) (535) 75.6% Under recovery of berthing income,
Ferries budget lines requiring
reprofiling, 
Head of Roads
&
Infrastructure
Services
Network & Traffic
Management
124 111 (13) (11.7%) 237 237 0 0.0% TRO income behind the forecast -
TRO income subject to demand for
TROs. Service will monitor and
variance will be reported once
confirmed.
Head of Roads
&
Infrastructure
Services
Road Safety 70 46 (24) (52.2%) 159 159 0 0.0% Error in the budget resulted in
saving being profiled incorrectly.
The actual YTD Budget should be
£71k which would produce a YTD
underspend of £1k. The
underspend is likely to be
harvested for vacancy savings.
Error in profile to be updated
Head of Roads
&
Infrastructure
Services
Roads & Lighting 7,353 3,003 (4,350) (144.9%) 8,071 8,229 (158) (2.0%) Profiling errors within the roads
trading account - primarily due to
the lag on processing measures
after completing capital schemes.
N20 needs fully reprofiled to
resolve and will be actioned before
close of November.

Page 38

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of Roads
&
Infrastructure
Services
Waste 7,431 5,883 (1,548) (26.3%) 15,291 15,101 190 1.2% The adverse variance relates
mainly to commercial refuse,
external hires cost and profiling of
waste PPP payments. In addition
£170K of earmarked funding is yet
to be drawn down and will be
arranged during November. Work
is underway by the service to
recover additional income from gap
sites, unable to confirm at this
stage if the target income of £700K
will be achieved.  Forecast
Variance - Over-recovery
anticipated by year end in relation
to recyclates sale of glass.    
24,646 16,578 (8,068) (48.7%) 39,524 39,876 (352) (0.9%)      
41,669 32,055 (9,614) (30.0%) 66,205 66,624 (419) (0.6%)   
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 39

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 25,564 25,661 97 0.4% 47,334 47,334 0 0.0% YTD variance mainly due to vacancies within the Roads and
Lighting Holding Account which are being covered by
external contractors
Premises 1,650 1,801 151 8.4% 4,258 4,277 (19) (0.5%) YTD variance mainly due to the profile of the Depot internal
recharges.
Supplies
and
Services
8,093 6,477 (1,616) (25.0%) 11,234 11,254 (20) (0.2%) YTD variance mainly due to purchase of materials within
Roads, which will be offset against additional income over the
coming months, alongside payments made against UK
Shared Prosperity Fund which will be offset with grant
income once received
Transport 8,364 6,983 (1,381) (19.8%) 18,393 18,393 0 0.0% Outstanding peofiling against the Ferries budget to reflect
additional Scottish Government Funding, part of the overall
block grant this year
Third Party 38,863 38,587 (276) (0.7%) 74,119 74,270 (151) (0.2%) YTD variance mainly due to underspends on private
contractors and transport operator payments, with profiling
being the main driver of this and will begin to smooth out over
the next few reporting periods.
Capital
Financing
0 0 0 0.0% 2,949 2,949 0 0.0% Outwith Reporting Criteria
Income (40,865) (47,454) (6,589) 13.9% (92,082) (91,853) (229) 0.3% YTD variance due to profile of income recharges within the
Roads Operational Holding Account on account of capital
works still progressing through final measures, internal refuse
recharge being processed later than profiled and recharge to
education not yet done.
Totals 41,669 32,055 (9,614) (30.0%) 66,205 66,624 (419) (0.6%)

Page 40

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%

Page 41

EXECUTIVE DIRECTOR (KIRSTY FLANAGAN) – RED VARIANCES AS AT 31OCTOBER 2025 
Service Area Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Roads & Lighting 8,072 8,230 (158) (2.0%) An overspend of £158k is forecast mainly due to the reliance on
external contractors and related vehicle costs (£138k) in street
lighting as a result of internal staffing capacity being focused on
delivering other capital works and higher than expected public
liability claims and rising external software costs (£20k).
Waste 15,291 15,101 190 1.2% The forecast underspend reflects an expected over-recovery of
income from the sale of glass for recycling.
Marine
(708) (173) (535) 75.6% The forecast is due to updated expected under-recovery in ferry
berthing incoming due to the announcements for the Cal Mac Ferry
Timetable alongside the overhaul programme.
Fleet & Transport 11,719 11,567 152 1.3% Forecast updated to relfect year-end recharge as other side of this
workings had a different budgeted amount, but recharge will
always match 
Red Variance is a forecast variance which is greater than +/- £50k

Page 42

SOCIAL WORK – AS AT 31 OCTOBER 2025 
The department is currently forecasting an overspend of £0.733m (0.9%). This is due to demand for residential placements within Children and
Families and Older People Services. The Integration Joint Board will be expected to recover this position by the end of the financial year or
offset the overspend from its budget reserves. Consequently, there is a reported forecast variance of zero. 
The department has a year-to-date overspend of £0.369m (1.0%) which again is due to demand driven services within Children and Families
and Older People along with timing differences for reserves drawdowns and grant income. 
Forecast Outturn Position 
Service Annual
Budget 
£000
Forecast
Outturn 
£000
Current
Forecast
Variance
(Oct) 
£000
Previous
Forecast
Variance
Reported 
(Aug) 
£000
Change 
£000
Chief Officer
Integration (1,948) (1,948) 0 0 0
Head of
Strategic
Planning and
Performance 508 508 0 0 0
Head of Health
and Community
Care 44,851 44,851 0 0 0
Head of Acute
and Complex
Care 21,663 21,663 0 0 0
Head of Children
and Families 16,871 16,871 0 0 0
Totals 81,945 81,945 0 0 0 
Year to Date Position 
Key Financial Successes: 
Delivered a balanced budget at the end of 2024/25 after utilising £2.553m of pension reserves held in the council and £0.156m of IJB
reserves. 
-115%
-90%
-65%
-40%
-15%
10%
35%
60%
85%
110%
Chief Officer
Integration
Head of Adult
Services
Head of Children
and Families
Head of
Strategic
Planning and
Performance
Expenditure to date against the remaining budget
for each Service
YTD
Actual
£000
Remaining Budget
£000

Page 43

SOCIAL WORK – AS AT 31 OCTOBER 2025 
Key Financial Challenges: Proposed Actions to address Financial Challenges:
Deliver the savings total for 2025/26 of £2.047m. Maintain a close working relationship with the HSCP Service
Improvement Team to quickly and efficiently identify and assess
options for delivering the outstanding savings. 
Development and delivery of future service redesigns which will be
necessary to contain service expenditure within the allocated resource,
noting that in year savings still need to be identified for 2025/26 to address
the 2025/26 budget gap, as well as budget gaps in future years. 
Support from finance to assist strategic managers to develop and
identify further savings options and to look beyond the short term to
identify and plan the changes which will be needed to address the
expected ongoing budget challenges over the current, and future,
years.
Cost of the use of agency staff to support service delivery across Social
Work, but particularly in Older People services, due to recruitment and
retention challenges within the service. Year to date spend at August 2025
of £1.707m. 
Close working relationship with the HSCP to support the costing of
a plan to stabilise the service and ensure it is operationally and
financially sustainable. This includes an exit plan from the reliance
on agency staff. 
Cost of living crisis affecting pay inflation negotiations and financial
sustainability of service providers, which could affect affordability and
sustainability of service delivery. 
Ensure emerging issues are highlighted as soon as possible so that
the financial impact can be evaluated and reported through the
budget monitoring and preparation processes.

Page 44

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Service Service Area
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Chief Officer
Integration
Integration
Headquarters
336 890 554 62.3% 1,726 1,726 0 0.0% The year to date variance is due to timing
differences in third party payments and
income recharges.  The forecast variance is
due to unallocated budgets held to offset
likely overspends in other service areas
including care at home and care home
placements.
Chief Officer
Integration
Social Work
Central Support
(161) (196) (35) 17.9% (3,674) (3,674) 0 0.0% The YTD and forecast variance are due to
timing difference on vacancy savings targets
offset by other timing differences in supplies
and services.    
175 694 519 80.1% (1,948) (1,948) 0 0.0%  
Head of
Strategic
Planning &
Performance
Management &
Central Costs
250 246 (4) (1.6%) 474 474 0 0.0% The YTD and forecast variances are outwith
reporting criteria
Head of
Strategic
Planning &
Performance
Service
Development
20 19 (1) (5.3%) 34 34 0 0.0% The YTD and forecast variances are outwith
reporting criteria    
270 265 (5) (6.9%) 508 508 0 0.0%  
Head of
Health and
Community
Care
Management &
Central Costs
232 265 33 12.5% 608 608 0 0.0% The YTD and forecast variance are both due
to staff vacancies.
Head of
Health and
Community
Care
Older People 20,500 20,207 (293) (1.5%) 44,243 44,243 0 0.0% The YTD and forecast outturn variance
reflects the demand for care home
placements, home care packages and the
use of agency staff partially offset by
increased income from self funders in the
HSCP's care homes.    
20,732 20,472 (260) (1.3%) 44,851 44,851 0 0.0%  
Head of
Acute and
Complex
Care
Learning
Disabilities
4,613 4,586 (27) (0.6%) 14,915 14,915 0 0.0% The YTD and forecast variance are both due
to staff vacancies.

Page 45

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Head of
Acute and
Complex
Care
Management &
Central Costs
55 52 (3) (5.8%) 116 116 0 0.0% The YTD and forecast variance are both due
to staff vacancies.
Head of
Acute and
Complex
Care
Mental Health 1,356 1,215 (141) (11.6%) 3,392 3,392 0 0.0% The YTD variance is due to staff vacancies
partially offset by spend on agency staff and
timing differences with payments to third
parties.  The forecast overspend is due to
current commitments for residential
placements and the use of agency staff in
assessment and care management.
Head of
Acute and
Complex
Care
Physical Disability 1,437 1,470 33 2.2% 3,240 3,240 0 0.0% The YTD variance is outwith reporting
criteria.  The forecast variance is due to
demand for residential placements.    
7,461 7,323 (138) (15.7%) 21,663 21,663 0 0.0%  
Head of
Children &
Families
Child Protection 1,887 1,908 21 1.1% 3,827 3,827 0 0.0% The YTD and forecast variances are outwith
reporting criteria
Head of
Children &
Families
Children with a
Disability
483 471 (12) (2.6%) 1,083 1,083 0 0.0% The YTD and forecast variances are outwith
reporting criteria
Head of
Children &
Families
Criminal Justice 29 22 (7) (31.8%) 272 272 0 0.0% The YTD variance is due to timing
differences on government grant income. 
The forecast variance is outwith reporting
criteria.
Head of
Children &
Families
Looked After
Children
4,781 4,193 (588) (14.0%) 7,605 7,605 0 0.0% The YTD variance is due to timing
differences on third party payments and the
forecast variance is due to demand for
residential placements partially offset by
forecast underspends in adoption and
fostering.
Head of
Children &
Families
Management &
Central Costs
1,906 2,007 101 5.0% 4,084 4,084 0 0.0% The YTD variance is due to timing
differences on third party payments and
income from health boards and other bodies. 
The forecast variance is due to vacant posts
in the integrated care area teams and
forecast underspends in third party
payments.    
9,086 8,601 (485) (5.6%) 16,871 16,871 0 0.0%  
GRAND
TOTAL   37,724 37,355 (369) (1.0%) 81,945 81,945 0 0.0%

Page 46

SOCIAL WORK – OBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 47

SOCIAL WORK – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
Subjective
Category
YTD
Actual
£000
YTD
Budget
£000
YTD
Variance
£000
%
Variance
Annual
Budget
£000
Forecast
Outturn
£000
Forecast
Variance
£000
%
Variance Explanation
Employee 20,754 19,100 (1,654) (8.7%) 36,611 36,611 0 0.0% Both the YTD and forecast underspends are
due to staff vacancies across HSCP partially
offset by the use of agency staff. 
Premises 808 522 (286) (54.8%) 1,644 1,644 0 0.0% The YTD and forecast overspends are due
to unbudgeted property maintenance and
refuse collection costs within our Care
Homes. 
Supplies &
Services
1,052 826 (226) (27.4%) 783 783 0 0.0% The YTD and forecast overspend are largely
due to a re-profiling of savings options that
will no longer be achieved this financial year.
Transport 480 409 (71) (17.4%) 684 684 0 0.0% The YTD variance is due to increased costs
of pool cars within the care at home service
area. The forecast variance is outwith
reporting criteria.
Third Party 35,226 35,896 670 1.9% 69,641 69,641 0 0.0% The YTD and forecast variance are due to
demand for purchased care services across
both Childrens and Adult Services.
Income (20,596) (19,398) 1,198 (6.2%) (27,418) (27,418) 0 0.0% The YTD variance is due to timing difference
in re-charges to health boards and forecast
variance is due to profiling of reserves
drawdowns.
Totals 37,724 37,355 (369) (1.0%) 81,945 81,945 0 0.0%

Page 48

SOCIAL WORK – SUBJECTIVE SUMMARY AS AT 31 OCTOBER 2025 
YTD is year to date and represents the actual or budgeted expenditure and income for the financial year so far.
Forecast Outturn is the estimate now of what expenditure or income will be for the whole of the financial year. 
The Variance is the difference between budget and actual or forecast outturn.
A positive variance is when actual or forecast expenditure is less than budget or actual or forecast income is more than budget.
A negative variance is shown in brackets and is when actual or forecast expenditure is more than budget or actual or forecast income is less
than budget.
An explanation is given for any variance which exceeds £50,000 or 10%.

Page 49

MONITORING OF BUDGET SAVINGS OPTIONS APPROVED FEBRUARY 2025 Appendix 3
POSITION AS AT 31 OCTOBER 2025
2025-26 2025-26 2026-27 2026-27 Future
Years
Future
Years
£000 FTE £000 FTE £000 FTE
EDU 001
25/26
Executive
Director Douglas
Hendry
Education Services Education Services Education Service are about to commence a review of the
service, in a similar way to Roads and Infrastructure.  The
savings figure represents a target level of savings for Year 1
only at this stage, as the review progresses, further savings
will be identified.
200 0.0 200 0.0 200 0.0 On Track to be Delivered
LRS 003
25/26
Executive
Director Douglas
Hendry
Governance Governance Following a review of the Governance Team it is proposed to
take advantage of a retirement within the team to re-
structure. The revised team structure will allow for better use
of available resource and ensure that key priority areas service
levels are maintained.
33 2.0 44 2.0 44 2.0 Delivered
LA 001
25/26
Executive
Director Douglas
Hendry
Live Argyll Live Argyll 10% cut to Live Argyll Management Fee - savings options to
deliver this level of saving will be determined by the Live Argyll
Board.
0 0.0 311 tbc 311 tbc On Track to be Delivered
CS 001
25/26
Executive
Director Douglas
Hendry
Community Sport Community Sport Removal of payments to Camanachd Association and Scottish
Rugby at £10,000 each. 
0 0.0 20 0.0 20 0.0 On Track to be Delivered
CS 002
25/26
Executive
Director Douglas
Hendry
Council Catering
Service
Council Catering
Service
Over the last year the department has been revising delivery
models to increase efficiency and effectiveness of the service
and are able to reduce the budget as a result of this.
50 0.0 50 0.0 50 0.0 Delivered
CS 003
25/26
Executive
Director Douglas
Hendry
Property Services Property Services Condition Surveys - due to favourable market conditions and
the frequency to undertake the condition surveys a one-off
saving of £50k can be made in 2025/26.
50 0.0 0 0.0 0 0.0 Delivered
LRS 001
25/26
Executive
Director Douglas
Hendry
Schools Contracts -
NPDO/DBFM
Schools Contracts -
NPDO/DBFM
As part of contract management measures there has been a
contractual review of the ongoing base budget requirements
and the base can be reduced on a recurring basis going
forward.
108 0.0 108 0.0 108 0.0 Delivered
LRS 002
25/26
Executive
Director Douglas
Hendry
Elections Elections The annual budget for elections of £36,751 covers the running
costs of the election office £4,848 with the balance of £31,903
being available to fund by-elections for the Council and
Community Councils. Given that these are unpredictable and
as such outwith our control it is proposed that this is treated
as a centrally funded cost pressure going forward with the
budget of £31,903 being removed from the core budget.
32 0.0 32 0.0 32 0.0 Delivered
FS 001
25/26
Executive
Director Kirsty
Flanagan
Financial Services Financial Services Increase in Agency Income from Scottish Water and a
reduction in supplies and services budgets following a review.
51 0.0 51 0.0 51 0.0 On Track to be Delivered
Template
Ref
Department Service Service Delivery Area Savings Option Status of Implementation

Page 50

2025-26 2025-26 2026-27 2026-27 Future
Years
Future
Years
£000 FTE £000 FTE £000 FTE
Template
Ref
Department Service Service Delivery Area Savings Option Status of Implementation
DEG 001
25/26
Executive
Director Kirsty
Flanagan
Development Policy Development Policy Re-organisation of the service and the posts therein that carry
out specific functions creating a better structure for the
future.
44 1.0 44 1.0 44 1.0 On Track to be Delivered
DEG 002
25/26
Executive
Director Kirsty
Flanagan
Development Projects
(Planning)
Development Projects
(Planning)
Introduction of new charges for returned applications,
retrospective planning applications and discharge of planning
conditions/confirmation of compliance.   For future years
assumed increase income as a result of SG review of statutory
planning fees.
45 0.0 45 0.0 145 0.0 On Track to be Delivered
RIS 001
25/26
Executive
Director Kirsty
Flanagan
Roads and
Infrastructure Services
Roads and
Infrastructure Services
A review of Roads and Infrastructure is currently being carried
out.  Stage 1 was reported to EDI in June 2024 and Stage 3-4
are progressing.  Savings are expected to be identified and
Members will be asked to agree each saving option when it is
identified.  The savings figure represents a target level of
savings.
300 tbc 800 tbc 800 tbc On Track to be Delivered
RIS 002
25/26
Executive
Director Kirsty
Flanagan
Commercial Waste Commercial Waste A high level review of self-catering units has highlighted that
some do not have commercial waste contracts.  A further
more detailed review will be carried out but it is anticipated
that there is additional income that can be budgeted for.  This
saving will be monitored and reported during the year.
700 0.0 700 0.0 700 0.0 On Track to be Delivered
CW 001
25/26
Non
Departmental
Council Wide Council Wide Following a review of some supplies and services budgets,
there are a number of small efficiencies that can be made
within various cost centres will limited impact.
47 0.0 49 0.0 88 0.0 On Track to be Delivered
CPD 001
25/26
Chief Executive's
Unit
Community Planning
and Development
Community Planning
and Development
Staffing efficiencies through workforce planning and service re-
shaping to better meet needs from communities on assets and
funding.
38 1.0 63 1.0 63 1.0 Delivered
Loans FundFunding Loans Fund Loans Fund A detailed review of the loans fund will be undertaken,
however, it is anticipated that a one-off saving of at least
£0.500m will be achievable within 2024-25 that could be
earmarked and used to balance the 2025-26 budget.  The
saving is a result of slippage in the capital programme and a
better return on interest rate estimates. 
500 0.0 0 0.0 0 0.0 Delivered
Funding Funding Funding Funding After the Council set its 2024/25 budget, the SG allocated the
Island Cost Crisis Funding that was to be used to support
increasing service costs in islands.  As our budget was already
set, this funding was set aside and can be carried forward and
used to help balance the 2025/26 budget on a one-off basis.
564 0.0 0 0.0 0 0.0 Delivered
TOTAL 2,762 4.0 2,517 4.0 2,656 4.0

Page 51

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE  
FINANCIAL SERVICES 4 DECEMBER 2025 
CAPITAL PLAN MONITORING REPORT - 2025-26 QUARTER 2 
1.0 EXECUTIVE SUMMARY 
1.1  This report provides an update on financial performance and the delivery of
capital projects against the approved Capital Plan budget resources and
timescales as at Quarter 2, 30 September 2025. 
1.2 A number of budget changes totalling £1.852m are proposed, reflecting
previously approved investment in respect of the Education ASN Review
(£1.255m) and Mull Joint Campus (£0.434m); and available resources in
respect of the TIF Oban Airport Project (£0.163m). 
1.3  Financial Position: 
• Capital Plan Budget – Approved gross expenditure totals £212.124m,
while income totals £12.263m, resulting in approved net expenditure of
£199.861m, to be incurred across 2025-26 and future years. 
• Capital Plan Forecast – Forecast gross expenditure totals £212.297m,
compared to an approved budget of £212.124m, giving rise to a forecast
overspend of £0.173m (0.1%) across 2025-26 and future years. Forecast
income is in line with budget at £12.263m. 
• 2025-26 Actual To Date – Actual gross expenditure of £24.298m has been
incurred in the year to date, representing 31.8% of the £76.308m gross
expenditure forecast for the year.  No project specific income has been
received in the year to date. 
1.4 Physical Delivery: 
• Asset Sustainability – Of the 84 projects, there are currently 83 projects
(99%) on track and 1 project off track.
• Service Development - Of the 26 projects, there are currently 25 projects
(96%) on track and 1 project off track.
• Strategic Change – Of the 16 projects, there are currently 15 projects
(94%) on track and 1 project off track.  
1.5  There are a number of known risks, specifically related to the Capital Plan,
which may impact delivery within available resources and target timescales. 
The monitoring and review of risks will be undertaken on an ongoing basis
throughout the year.

Page 52

ARGYLL AND BUTE COUNCIL  POLICY AND RESOURCES COMMITTEE  
FINANCIAL SERVICES 4 DECEMBER 2025 
CAPITAL PLAN MONITORING REPORT – 2025-26 QUARTER 2 
2.0 INTRODUCTION 
2.1 This monitoring report provides an update on financial performance and the
delivery of capital projects against the approved Capital Plan budget resources
and timescales as at Quarter 2, 30 September 2025.  The report reflects proper
accounting practice, and is based on information contained within the council’s
financial systems, estimation techniques and the professional judgement of
council officers. 
2.2  A key function of the council’s treasury management service is the funding of the
authority’s capital investment plans.  The Capital Plan provides a guide to the
borrowing need of the authority, essentially informing longer-term cash flow
planning.  The CIPFA Code of Practice on Treasury Management (the Code)
and regulatory environment requires governance reporting on treasury
management to be undertaken on a quarterly basis.  In line with this guidance,
the responsibility for the monitoring and scrutiny of treasury management
activities, strategy and policies is delegated to the Audit and Scrutiny Committee. 
The Code also requires full Council to receive a Treasury Management Strategy,
Mid-year Review and Annual Report.  The Capital Plan Monitoring report is also
prepared on a quarterly basis, in order to support treasury governance reporting
requirements. 
2.3 The report compares the forecast expenditure with the approved budget for each
project within the plan and provides a profile of forecast expenditure over 2025-
26 and future years.  Details of actual expenditure incurred and project specific
income received during 2025-26 to date are also provided.
3.0  RECOMMENDATIONS 
3.1 It is recommended that the Policy and Resources Committee note the contents
of this report and approve the proposed budget changes to the Capital Plan, as
detailed within section 4. 
4.0 BUDGET CHANGES 
4.1 Previously Approved Budget Changes 
There is a requirement to increase project gross expenditure by £1.689m to
reflect previously approved capital investment, funded from within the current
funding framework, including existing earmarked reserves, as outlined in the
table below. 
Project Service Category 2025-26
£000
ASN Review EDU Asset Sustainability 1,255
Mull Joint Campus EDU Strategic Change 434
Total   1,689

Page 53

4.2  Proposed Budget Changes 
There is a requirement to increase project gross expenditure by £0.163m to
reflect the cost of preliminary works, funded from Tax Increment Financing (TIF)
resources, as outlined in the table below. 
Project Service Category 2025-26
£000
Oban Airport Business Park DEG Strategic Change 163
Total   163 
4.3 The following budget virements between individual projects are requested to
manage project costs within overall available resources and in accordance with
council priorities: 
Budget
Virement From
Budget
Virement To
Amount
£000
Explanation
Server
Sustainability
Telecomms
Network
15 Reprioritisation of IT Block
Allocation resources to manage
Telecomms Network
requirements within available
resources.
Coastal
Protection
Bute Sea
Wall Repairs
100 Reprioritisation of RIS Block
Allocation resources to manage
increased costs of Bute Sea
Wall repairs, with tender
submissions higher than
assumed within the original
budget allocation. 
Total  115 
4.4 Summary 
The revised approved Capital Plan gross expenditure budget, excluding spend
incurred in prior years and reflecting the proposed changes outlined above, totals
£212.124m, while project specific income on this basis totals £12.263m.  This
gives revised approved net expenditure on capital plan projects under
completion, excluding net expenditure incurred in prior years, of £199.861m 
4.5 The revised approved gross expenditure budget for individual capital projects
within the plan is outlined within Appendix 1, whilst project specific income is
outlined within Appendix 2.  This also includes details of the forecast spend,
profiled across 2025-26 and future years, in comparison to the approved  project
budgets; together with actual spend to date. 
5.0 CAPITAL FINANCING 
5.1 There is an overall funding framework in place to finance the Capital Plan net
expenditure, comprising the following: 
• General Capital Grant;
• General Capital Receipts from Asset Sales;
• Capital Financed from Current Revenue; and 
• Borrowing.

Page 54

5.2 There is a rolling 3 year target for capital receipts from asset sales, forming part
of the overall funding framework for the 2025-28 Capital Plan.  The level of
receipts that may reasonably be achieved over the 3 years 2025-28 totals
£1.750m, profiled £0.750m 2025-26 and £0.500m across each of the years
2026-27 and 2027-28. Receipts of £0.938m have been received to date in 2025-
26. Updated forecasts for 2025-26 and future years will be provided in future
capital monitoring reports. 
5.3 The ongoing monitoring of the Capital Plan and the impact on borrowing is
reported as part of the Treasury Management reporting requirements to the Audit
and Scrutiny Committee and Council throughout the year.  For example, any
slippage in planned capital expenditure from 2025-26 into future years will have
an impact on the council’s forecast borrowing requirements. 
5.4 The annual debt charges arising from borrowing require to be managed within
available revenue resources.  This includes reserve balances earmarked for
capital projects and additional revenue income related to prudential borrowing
projects, such as the Harbour Investment Programme, and Tax Increment
Financing (TIF). 
5.5 The Section 95 Officer will take a strategic approach to manage the impact of
capital investment on the council’s revenue budget, including the use of
earmarked reserves, to ensure that capital investment is affordable, prudent and
sustainable. 
6.0 SPEND PROFILE 
6.1 The profile of forecast expenditure across 2025-26, 2026-27 and future years
continues to be reviewed and updated throughout the year, with an explanation
of movements reported to committee.  This is expected to include project
slippage from 2025-26 and 2026-27 into 2026-27 and future years, and
potentially acceleration from 2026-27 and future years into 2025-26 and 2026-
27. 
6.2 Forecast gross expenditure and project specific income have been profiled
across 2025-26, 2026-27 and future years.  This takes account of the budget
changes outlined within Section 4.  The resulting forecast gross expenditure
profile as at Quarter 2 is £76.308m 2025-26, £64.467m 2026-27 and £71.522m
future years, while forecast project specific income is profiled £12.263m 2025-
26.   
6.3  The table below provides a summary of the movements from the previously
reported position as at Quarter 1 2025-26.  More detailed explanations of re-
profiling in respect of project slippage are provided within Appendix 3. 
Forecast Gross Expenditure 
2025-26 2026-27 Future
Years Total
£000 £000 £000 £000
Qu.1 Profile 75,384 63,546 71,522 210,452
Qu.2 Budget Changes 1,852 0 0 0
Variance Movement (7) 0 0 0
Re-profiling (921) 921 0 0
Qu.2 Profile 76,308 64,467 71,522 212,297

Page 55

7.0 SUMMARY FINANCIAL POSITION 
7.1 Actual gross expenditure of £24.298m has been incurred during the year to
Quarter 2 2025-26, representing 31.8% of the £76.308m gross expenditure
forecast for the year.  There has been no actual project specific income received
in the year to date in respect of the £12.263m forecast for 2025-26. 
7.2 The forecast gross expenditure on the Capital Plan across 2025-26 and future
years totals £212.297m, compared to an approved budget, excluding prior year
spend, of £212.124m, giving rise to a forecast overspend for the overall capital
plan of £0.173m (0.1%).  Forecast income is in line with budget at £12.263m. 
This gives forecast net expenditure of £200.034m, against a comparable
approved budget of £199.861m.   
7.3  The following table provides a comparison of the forecast gross expenditure
across 2025-26 and future years with the approved Capital Plan budget, by
project type and across services. The forecast variance comprises an overspend
of £125k in respect of Lochgilphead Depot Rationalisation, together with a
number of variances across specific projects, individually less than £50k.  There
are currently no variances in respect of project specific income to be reported. 
Project Type:
Capital
Plan
Budget           
£000
Forecast
Outturn       
£000  
Variance
(Over)/
Under         
£000
Asset Sustainability 51,341 51,341 0
Service Development 10,017 10,162 (145)
Strategic Change 150,766 150,794 (28)
Total  212,124 212,297 (173)
Service:      
Central - Storm Provision 900 900 0
CHORD  22,016 22,016 0
Development & Economic Growth  6,377 6,425 (48)
Education  11,113 11,113 0
Health & Social Care Partnership 2,935 2.935 0
ICT  2,537 2,537 0
Live Argyll  1,470 1,470 0
Roads & Infrastructure 158,928 159,053 (125)
Shared Offices 5,848 5,848 0
Total 212,124 212,297 (173) 
8.0 STRATEGIC CHANGE PROJECTS 
8.1 Detailed information in respect of the Strategic Change Projects within the
Capital Plan is provided within Appendix 4. For each project, this gives details of
the forecast spend against the approved budget; the start and anticipated
completion date; and an assessment of risk, using a RAG status.  Where the
RAG status of a project is not Green, an explanation is provided. 
9.0 CAPITAL PLAN DELIVERY

Page 56

9.1 There are a total of 126 projects within the overall Capital Plan. Of this total, 123
or 98% are Complete or On Track, and 3 are Off Track or Experiencing
Problems. 
9.2 The table below provides a summary of the delivery status of the projects within
the Capital Plan by project type and across services. 
Project Type:
Complete/
On Track
Off Track/
Recoverable
Off
Track/
Problem
Total
Asset Sustainability 83 0 1 84
Service Development 25 0 1 26
Strategic Change 15 0 1 16
Total 123 0 3 126
Service:    
ICT 3 0 0 3
Education 11 0 0 12
Live Argyll 11 0 0 11
HSCP 19 0 0 19
Shared Offices 18 0 0 18
Roads & Infrastructure 37 0 3 40
Dev & Economic Growth 20 0 0 20
CHORD 4 0 0 4
Total 123 0 3 126 
9.3  Details of the projects currently designated as ‘Off Track’ are summarised in
the table below. 
Project
Type
Project
Title
What is
Off Track?
Explanation
RIS - Asset
Sustainabili
ty
Environmen
tal Projects
Progress
on delivery
Slippage from 2025-26 into
2026-27. 
RIS -
Service
Developme
nt
Lochgilphea
d Depot
Rationalisati
on
Total
forecast
spend
There is a forecast
overspend of £125k overall.
The additional costs are
associated with the removal
and replacement of
Bishopton Road Depot with
a temporary structure after
the building became
dangerous. Overspend
relates to previous years
costs, mainly year end
design and property
recharges, as well as some
late invoices. This
overspend is being
addressed at the Depot
Rationalisation Board. 
RIS –
Strategic
Change
Campbelto
wn Flood
Scheme
Progress
on delivery
Slippage from 2025-26 into
2026-27.

Page 57

10.0 CAPITAL PLAN RISKS 
10.1 The council’s funding bid to the Scottish Government’s Learning Estate
Investment Programme (LEIP) for a new school campus on Mull was successful.
While this is good news and will provide welcome investment in the school
estate, it will not meet the full cost of the project.  The funding gap requires to be
met by the council and presents a financial pressure. The Scottish Government
will fund up to 50% of eligible costs, with the balance of circa. £20m to be funded
by the council. 
10.2 At the budget meeting in February 2024, £1.1m of funding was set aside as an
initial high level estimate of works anticipated to be required at the A816 Bealach
Mor to convert the temporary road, put in place following the October 2023
landslip, into a permanent road.  An options study as now been carried out to
explore a number of options for this stretch of road going forward.  A report will
be presented to EDI in September 2025 outlining 9 options, which have been
shortlisted to 4 at this stage.  The preferred option cost estimate is significantly
higher than the budget set aside in February 2024, estimated to be between
£7.25m and £8.5m.  Further work is required to develop a business case options
appraisal and we would look to get independent design and project management
consultants to take this forward.  Once we have firmer proposals, this will be
reported to Council and consideration will need to be given as to how the shortfall
will be funded.   
10.3 The capital programme is continuing to see significant price increases, as well
as supply chain disruptions, due to the impact of world events on the global
economy, inflationary increases and additional costs from suppliers, due to the
challenges in delivering capital projects within our geographical location.  In
recent years, additional funding has been allocated to capital projects to deal
with these cost pressures, which has mitigated the impact to date.  However,
there remains a financial risk in respect of projects, where contracts have yet to
be entered into. 
10.4 The continued impact on worldwide supply chains may also impact delivery
timescales.  It will be challenging to manage these impacts within available
resources and target completion timescales.  Mitigating actions will be taken to
manage financial risk, for example, re-profiling, project re-design, re-engineering
or curtailment, and the re-prioritisation of uncommitted resources across the
programme.  However, there remains a risk that it will not be possible to manage
potential increased costs within the approved capital resources. 
10.5 The funding framework for the approved Capital Plan includes an assumed level
of capital receipts from asset sales.  Whilst the target of £0.750m for the current
financial year has been achieved, future years remain subject to assets being
made available for sale and changing market conditions.  The level of receipts
that may reasonably be achieved will be kept under review, to reflect changing
market conditions and due diligence undertaken on asset condition. 
11.0 IMPLICATIONS 
11.1 Policy  Monitors progress against the Capital Plan. 
11.2 Financial  Monitors financial performance on delivery of the
Capital Plan.

Page 58

Kirsty Flanagan 
Executive Director / Section 95 Officer 
31 October 2025                                                  
Policy Lead for Finance and Commercial Services – Councillor Ross 
APPENDICES: 
Appendix 1 – Capital Plan Monitoring – Gross Expenditure
Appendix 2 – Capital Plan Monitoring – Project Income
Appendix 3 – Re-profiling of Forecast Spend
Appendix 4 – Strategic Change Projects 
For further information contact: 
Carolyn Earl, Interim Head of Financial Services
carolyn.earl@argyll-bute.gov.uk 
11.3 Legal  Highlights where available funding may not address
all Statutory and Regulatory requirements in relation
to Health and Safety. 
11.4 HR Available funding may have an impact on the
sustainability of the Property Design Team and
Infrastructure Design Team. 
11.5  Customer Service None
11.6 Risk  There are risks to the delivery of the Capital Plan
within available resources and delivery timescales
and these continue to be monitored and reviewed, as
outlined in the report. 
11.7 Climate Change The Council is committed to addressing climate
change via delivery of projects within the Capital
Plan. 
11.8 Fairer Scotland Duty None 
11.9 Equalities – protected
characteristics 
None
11.10 Consumer Duty None 
11.11 Island Communities None 
11.12 Children’s Rights and
Wellbeing 
None

Page 59

Argyll and Bute Council Appendix 1
Capital Plan Monitoring Report
as at Quarter 2 2025-26
Gross Expenditure
Original
Budget
Budget
Changes
Revised
Budget
Forecast
Outturn
Variance
(Over)
/Under
Budget
Prior
Years
Actual
2025-26 2026-27 Future
Years
Total Capital
Plan
Prior
Years
Actual
2025-26
to Quarter
2
Total
Service Category Project Title £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Central Asset Sustainability Central Storm Provision -                900           900             900              -           -           900           -           -           900                  -            -          -            
Asset Sustainability Total -                900           900             900              -           -           900           -           -           900                  -            -          -            
Central Total -                900           900             900              -           -           900           -           -           900                  -            -          -            
CHORD Strategic Change CHORD - Dunoon 19                 -           19               19                -           -           19             -           -           19                    -            -          -            
CHORD - Helensburgh -Public Realm Imprv 25                 -           25               25                -           3               22             -           -           25                    3               3             6                
CHORD - Oban 629               -           629             629              -           -           629           -           -           629                  -            53           53              
CHORD - Rothesay 45,414          -           45,414        45,414         -           25,337      8,554        11,523      -           45,414             25,337      2,990      28,327       
Helensburgh Waterfront Development 443               -           443             443              -           -           443           -           -           443                  -            733         733            
HWD - FFE 350               -           350             350              -           316           34             -           -           350                  316           -          316            
Kilmory Business Park Phase 2AA 1,121            26             1,147          1,147           -           355           774           18             -           1,147               355           256         611            
Strategic Change Total 48,001          26             48,027        48,027         -           26,011      10,475      11,541      -           48,027             26,011      4,035      30,046       
CHORD Total 48,001          26             48,027        48,027         -           26,011      10,475      11,541      -           48,027             26,011      4,035      30,046       
DEG Service Development Albert Pier Demolition - Crown Estate Funding -                40             40               40                -           2               38             -           -           40                    2               28           30              
Ardrishaig North Active Travel 880               -           880             880              -           917           37-             -           -           880                  917           63-           854            
Arinagour, Coll - Site Investigation 90                 -           90               110              20-            110           -            -           -           110                  110           -          110            
Cycleways - H&L (FSPT) 3,402            -           3,402          3,402           -           3,113        289           -           -           3,402               3,113        -          3,113         
Dunoon Cycle Bothy 662               -           662             662              -           592           70             -           -           662                  592           10           602            
Dunoon STEM Hub 2,513            -           2,513          2,513           -           150           613           1,750        -           2,513               150           22           172            
Gibraltar Street Public Realm Improvements 250               -           250             250              -           248           2               -           -           250                  248           -          248            
Glenmorag Car Park PC 4                   -           4                 4                  -           4               -            -           -           4                      4               -          4                
Helensburgh Public Realm - Arts Strategy Fund 53                 -           53               53                -           4               49             -           -           53                    4               -          4                
Hermitage Park 26                 -           26               26                -           -           26             -           -           26                    -            -          -            
Nature Restoration Fund 1,244            -           1,244          1,244           -           26             1,218        -           -           1,244               26             160         186            
Rural Growth Deal 1,319            -           1,319          1,319           -           698           621           -           -           1,319               698           595         1,293         
Safe Streets, Walking and Cycling (CWSS) 4,161            -           4,161          4,161           -           3,411        750           -           -           4,161               3,411        -          3,411         
SPT - bus infrastructure 1,430            -           1,430          1,430           -           1,405        25             -           -           1,430               1,405        -          1,405         
Tier 1 Active Travel Route Design and Planning 93                 -           93               93                -           103           10-             -           -           93                    103           2-             101            
Town Centre Funds 4,190            -           4,190          4,190           -           4,134        56             -           -           4,190               4,134        173-         3,961         
Service Development Total 20,317          40             20,357        20,377         20-            14,917      3,710        1,750        -           20,377             14,917      577         15,494       
Strategic Change 01 TIF - Lorn/Kirk Road 1                   -           1                 1                  -           -           1               -           -           1                      -            -          -            
09 TIF - Oban Airport Business Park 987               384           1,371          1,371           -           996           375           -           -           1,371               996           375         1,371         
Oban Business Park - Buliding Costs (Not TIF Funded) -                -           -              28                28-            13             15             -           -           28                    13             15           28              
TIF - Halfway House Roundabout 640               -           640             640              -           66             574           -           -           640                  66             -          66              
Strategic Change Total 1,628            384           2,012          2,040           28-            1,075        965           -           -           2,040               1,075        390         1,465         
DEG Total 21,945          424           22,369        22,417         48-            15,992      4,675        1,750        -           22,417             15,992      967         16,959       
Education Asset Sustainability Block Allocation - Education 2,266            1,988        4,254          4,254           -           -           278           1,988        1,988        4,254               -            -          -            
Digital Inclusion 20-21 9                   -           9                 9                  -           -           9               -           -           9                      -            -          -            
Free School Meals 454               -           454             454              -           -           454           -           -           454                  -            115         115            
Preliminary RAAC Investigation 1,175            -           1,175          1,175           -           -           1,175        -           -           1,175               -            1,391      1,391         
Primary Schools 2,237            628           2,865          2,865           -           -           2,865        -           -           2,865               -            2,292      2,292         
Secondary Schools 260               627           887             887              -           -           887           -           -           887                  -            474         474            
Asset Sustainability Total 6,401            3,243        9,644          9,644           -           -           5,668        1,988        1,988        9,644               -            4,272      4,272         
Service Development Bowmore Primary School - Gaelic Medium Grant 47                 -           47               47                -           16             31             -           -           47                    16             -          16              
CO2 Monitoring - Covid Mitigation in Schools 192               -           192             192              -           79             113           -           -           192                  79             -          79              
Early Learning and Childcare - 1140 Hours 8,017            -           8,017          8,017           -           7,836        181           -           -           8,017               7,836        7             7,843         
Service Development Total 8,256            -           8,256          8,256           -           7,931        325           -           -           8,256               7,931        7             7,938         
Strategic Change Campbeltown Schools Redevelopment 38                 -           38               38                -           -           38             -           -           38                    -            -          -            
Dunoon Primary School 232               -           232             232              -           -           232           -           -           232                  -            -          -            
Kirn Primary School 34                 -           34               34                -           -           34             -           -           34                    -            -          -            
Mull Joint Campus 208               434           642             642              -           208           434           -           -           642                  208           303         511            
Replacement of Oban High School 406               -           406             406              -           -           406           -           -           406                  -            -          -            
Strategic Change Total 918               434           1,352          1,352           -           208           1,144        -           -           1,352               208           303         511            
Education Total 15,575          3,677        19,252        19,252         -           8,139        7,137        1,988        1,988        19,252             8,139        4,582      12,721       
HSCP Asset Sustainability Ardfenaig -                -           -              -               -           -           -            -           -           -                   -            34           34              
Block Allocation - HSCP -                382           382             382              -           -           -            -           382           382                  -            -          -            
Capital Property Works 9                   -           9                 9                  -           -           9               -           -           9                      -            -          -            
Eadar Glinn 28                 -           28               28                -           -           28             -           -           28                    -            4             4                
Approved Plan Budget v Forecast Gross Expenditure Forecast Outturn Profile Actual Gross Expenditure

Page 60

Argyll and Bute Council Appendix 1
Capital Plan Monitoring Report
as at Quarter 2 2025-26
Gross Expenditure
Original
Budget
Budget
Changes
Revised
Budget
Forecast
Outturn
Variance
(Over)
/Under
Budget
Prior
Years
Actual
2025-26 2026-27 Future
Years
Total Capital
Plan
Prior
Years
Actual
2025-26
to Quarter
2
Total
Service Category Project Title £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Approved Plan Budget v Forecast Gross Expenditure Forecast Outturn Profile Actual Gross Expenditure
Glencruitten Hostel 30                 -           30               30                -           -           30             -           -           30                    -            115         115            
Greenwood/Woodlands 15                 -           15               15                -           -           15             -           -           15                    -            16           16              
East King Street 1                   -           1                 1                  -           -           1               -           -           1                      -            1             1                
Kintyre Care Home 617               -           617             617              -           -           617           -           -           617                  -            64           64              
Lorn Resource Centre -              -           -                   40          
Shellach View 23                 -           23               23                -           -           23             -           -           23                    -            23           23              
Struan Lodge Boiler 651               -           651             651              -           -           651           -           -           651                  -            5             5                
Thomson Home Rothesay 761               -           761             761              -           -           761           -           -           761                  -            33           33              
Tigh An Rudha HFE 389               -           389             389              -           -           389           -           -           389                  -            134         134            
Asset Sustainability Total 2,524            382           2,906          2,906           -           -           2,524        -           382           2,906               -            469         469            
Service Development Dunclutha Childrens Home 29                 -           29               29                -           -           29             -           -           29                    -            -          -            
Service Development Total 29                 -           29               29                -           -           29             -           -           29                    -            -          -            
HSCP Total 2,553            382           2,935          2,935           -           -           2,553        -           382           2,935               -            469         469            
ICT Asset Sustainability Block Allocation - ICT 820               688           1,508          1,508           -           -           -            820           688           1,508               -            -          -            
PC Replacement 664               -           664             664              -           -           664           -           -           664                  -            551         551            
Server Sustainability 193               15-             178             178              -           -           178           -           -           178                  -            178         178            
Telecomms Network 101               86             187             187              -           -           187           -           -           187                  -            96           96              
Asset Sustainability Total 1,778            759           2,537          2,537           -           -           1,029        820           688           2,537               -            825         825            
ICT Total 1,778            759           2,537          2,537           -           -           1,029        820           688           2,537               -            825         825            
Live Argyll Asset Sustainability Aqualibrium 54                 -           54               54                -           -           54             -           -           54                    -            7             7                
Block Allocation - Live Argyll 394               382           776             776              -           -           12             382           382           776                  -            -          -            
Corran Halls Gaelic Centre 105               -           105             105              -           -           19             86             -           105                  -            4             4                
Lochgilphead Community Ed Centre 34                 -           34               34                -           -           34             -           -           34                    -            1             1                
Queen's Hall - Legionella Works 4                   -           4                 4                  -           -           4               -           -           4                      -            4             4                
Riverside Leisure Centre 13                 305           318             318              -           -           318           -           -           318                  -            7             7                
Rothesay Swimming Pool 91                 -           91               91                -           -           91             -           -           91                    -            24           24              
The Moat Centre 21                 -           21               21                -           -           21             -           -           21                    -            16           16              
Victoria Halls, Helensburgh 3                   -           3                 3                  -           -           3               -           -           3                      -            3             3                
Asset Sustainability Total 719               687           1,406          1,406           -           -           556           468           382           1,406               -            66           66              
Service Development Riverside Leisure Centre Refurbishment 43                 -           43               43                -           -           43             -           -           43                    -            43           43              
Service Development Total 43                 -           43               43                -           -           43             -           -           43                    -            43           43              
Strategic Change Carbon Management 50                 -           50               50                -           29             21             -           -           50                    29             -          29              
Strategic Change Total 50                 -           50               50                -           29             21             -           -           50                    29             -          29              
Live Argyll Total 812               687           1,499          1,499           -           29             620           468           382           1,499               29             109         138            
RIS Asset Sustainability Block Allocation - RIS 3,601            3,823        7,424          7,424           -           -           222-           3,823        3,823        7,424               -            -          -            
Bridge Strengthening 1,516            -           1,516          1,516           -           -           708           808           -           1,516               -            399         399            
Bute Sea Wall Repairs 522               100           622             622              -           -           522           -           -           522                  -            89           89              
Claonaig Landslip 12-                 12             -              -               -           -           -            -           -           -                   -            35-           35-              
Coastal Change Adaptation 246               250           496             496              -           -           246           250           -           496                  -            24           24              
Coastal Change Adaptation - Case Study - Inverlussa, Jura -                50             50               50                -           -           50             -           -           50                    -            3             3                
Coastal Change Adaptation - Case Study - Laggan Bay, Isla -                50             50               50                -           -           50             -           -           50                    -            3             3                
Coastal Change Adaptation - Case Study - Tiree -                60             60               60                -           -           60             -           -           60                    -            4             4                
Coastal Protection 694               100-           594             594              -           -           694           -           -           694                  -            9             9                
Environmental Projects 688               -           688             688              -           -           91             597           -           688                  -            1             1                
EV Quick Chargers 31                 -           31               31                -           -           31             -           -           31                    -            4             4                
Flood Prevention 437               156           593             593              -           -           437           -           156           593                  -            55           55              
Footway Improvements 97                 -           97               97                -           -           97             -           -           97                    -            -          -            
Gartbreck - Capping 42-                 42             -              -               -           -           -            -           -           -                   -            -          -            
Glengorm - Cell and Transfer Station (PB) 249               -           249             249              -           -           249           -           -           249                  -            30           30              
Helensburgh CHORD - Signage etc 10                 -           10               10                -           -           10             -           -           10                    -            -          -            
Helensburgh Flood Mitigation 427               -           427             427              -           -           427           -           -           427                  -            -          -            
Investment in Active Travel 200               -           200             200              -           -           200           -           -           200                  -            -          -            
Lighting 320               -           320             320              -           -           320           -           -           320                  -            4             4                
Local Bridge Maintenance Fund 4,733            -           4,733          4,733           -           -           389           4,344        -           4,733               -            87           87              
Play Park Renewal 917               -           917             917              -           -           917           -           -           917                  -            226         226            
POPs Waste 86                 -           86               86                -           -           86             -           -           86                    -            -          -            
Public Convenience Upgrades 149               -           149             149              -           -           149           -           -           149                  -            1             1

Page 61

Argyll and Bute Council Appendix 1
Capital Plan Monitoring Report
as at Quarter 2 2025-26
Gross Expenditure
Original
Budget
Budget
Changes
Revised
Budget
Forecast
Outturn
Variance
(Over)
/Under
Budget
Prior
Years
Actual
2025-26 2026-27 Future
Years
Total Capital
Plan
Prior
Years
Actual
2025-26
to Quarter
2
Total
Service Category Project Title £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Approved Plan Budget v Forecast Gross Expenditure Forecast Outturn Profile Actual Gross Expenditure
Roads Reconstruction 2,527            8,000        10,527        10,527         -           -           10,527      -           -           10,527             -            3,322      3,322         
Roads Reconstruction - Helensburgh CHORD 37                 -           37               37                -           -           37             -           -           37                    -            -          -            
Roads Reconstruction - Oban CHORD 3                   -           3                 3                  -           -           3               -           -           3                      -            -          -            
Roads Safety and Improvement Fund 60                 -           60               60                -           -           60             -           -           60                    -            1             1                
Tobermory Car Park 96                 -           96               96                -           -           96             -           -           96                    -            -          -            
Asset Sustainability Total 17,592          12,443      30,035        30,035         -           -           16,234      9,822        3,979        30,035             -            4,227      4,227         
Service Development Depot Rationalisation 10                 -           10               10                -           -           10             -           -           10                    -            -          -            
EV Infrastructure Fund 56                 -           56               56                -           19             37             -           -           56                    19             11           30              
Fleet Management 258               -           258             258              -           -           258           -           -           258                  -            -          -            
Fleet Management - Prudential Borrowing 773               -           773             773              -           -           773           -           -           773                  -            205         205            
Jackson's Quarry Refurbishment 285               -           285             285              -           285           -            -           -           285                  285           -          285            
Lismore Ferry Replacement 35                 -           35               35                -           -           35             -           -           35                    -            -          -            
Lochgilphead Depot Rationalisation 269               -           269             394              125-          394           -            -           -           394                  394           12           406            
Oban Depot Development 37-                 37             -              -               -           -           -            -           -           -                   -            2             2                
Preliminary design for  Regional Transport projects (tif) 16                 -           16               16                -           -           16             -           -           16                    -            -          -            
Weather Incident 4,634            -           4,634          4,634           -           2,287        2,347        -           -           4,634               2,287        553         2,840         
Zero Waste Scotland - Recycling Improvement Fund 63                 829           892             892              -           63             829           -           -           892                  63             95           158            
Service Development Total 6,362            866           7,228          7,353           125-          3,048        4,305        -           -           7,353               3,048        878         3,926         
Strategic Change Campbeltown Flood Scheme 15,939          -           15,939        15,939         -           14,986      242           711           -           15,939             14,986      11           14,997       
Harbour Investment Programme Non PB 53                 -           53               53                -           -           53             -           -           53                    -            -          -            
Harbour Investment Programme PB 143,046        -           143,046      143,046       -           19,896      22,729      36,700      63,721      143,046           19,896      7,758      27,654       
Street Lighting LED Replacement 3,900            -           3,900          3,900           -           3,343        557           -           -           3,900               3,343        4             3,347         
Strategic Change Total 162,938        -           162,938      162,938       -           38,225      23,581      37,411      63,721      162,938           38,225      7,773      45,998       
RIS Total 186,892        13,309      200,201      200,326       125-          41,273      44,120      47,233      67,700      200,326           41,273      12,878    54,151       
Shared Offices Asset Sustainability 5-7 East Clyde Street - Coastal Communities Fund 389               -           389             389              -           -           389           -           -           389                  -            2             2                
Argyll House, Dunoon 3                   -           3                 3                  -           -           3               -           -           3                      -            3             3                
Block Allocation - Shared Offices 887               345           1,232          1,232           -           -           468           382           382           1,232               -            -          -            
Burnett Building 243               12             255             255              -           -           255           -           -           255                  -            255         255            
Graham Williamson IT Building 1                   2               3                 3                  -           -           3               -           -           3                      -            3             3                
Helensburgh and Lomond Civic Centre 11                 23             34               34                -           -           34             -           -           34                    -            34           34              
Kilmory Castle 1,545            -           1,545          1,545           -           -           1,545        -           -           1,545               -            8             8                
Our Modern Workspace 452               -           452             452              -           -           452           -           -           452                  -            128         128            
Asset Sustainability Total 3,531            382           3,913          3,913           -           -           3,149        382           382           3,913               -            433         433            
Strategic Change Campbeltown Office Rationalisation 596               -           596             596              -           595           1               -           -           596                  595           -          595            
Clean Energy - NDEEF1 1,441            -           1,441          1,441           -           1,203        238           -           -           1,441               1,203        -          1,203         
Clean Energy - NDEEF2 1,140            -           1,140          1,140           -           -           855           285           -           1,140               -            -          -            
Helensburgh Office Rationalisation  (FPB,REC) 300               -           300             300              -           -           300           -           -           300                  -            -          -            
Net Zero 256               -           256             256              -           -           256           -           -           256                  -            -          -            
Strategic Change Total 3,733            -           3,733          3,733           -           1,798        1,650        285           -           3,733               1,798        -          1,798         
Shared Offices Total 7,264            382           7,646          7,646           -           1,798        4,799        667           382           7,646               1,798        433         2,231         
Overall Total 284,820        20,546      305,366      305,539       173-          93,242      76,308      64,467      71,522      305,539           93,242      24,298    117,540     
Original
Budget
Budget
Changes
Revised
Budget
Forecast
Outturn
Variance
(Over)
/Under
Budget
Prior
Years
Actual
2025-26 2026-27 Future
Years
Total Capital
Plan
Prior
Years
Actual
2025-26
to Quarter
2
Total
Category £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Asset Sustainability 32,545          18,796      51,341        51,341         -           -           30,060      13,480      7,801        51,341             -            10,292    10,292       
Service Development 35,007          906           35,913        36,058         145-          25,896      8,412        1,750        -           36,058             25,896      1,505      27,401       
Strategic Change 217,268        844           218,112      218,140       28-            67,346      37,836      49,237      63,721      218,140           67,346      12,501    79,847       
Overall Total 284,820        20,546      305,366      305,539       173-          93,242      76,308      64,467      71,522      305,539           93,242      24,298    117,540     
Approved Plan Budget v Forecast Gross Expenditure Forecast Outturn Profile Actual Gross Expenditure

Page 62

Argyll and Bute Council Appendix 2
Capital Plan Monitoring Report
as at Quarter 2 2025-26
Income
Original
Budget
Budget
Changes Revised Budget Forecast Income
Variance
(Over)
/Under
Budget
Prior Years Actual 2025-26 2026-27 Future
Years
Total
Capital
Plan
Prior Years Actual 2025-26 to
Quarter 2 Total
Service Category Project Title £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Chord Strategic Change Helensburgh Waterfront Development 2,320-             -           2,320-                       2,320-                         -            -                                2,320-        -          -          2,320-        -                                -           -                
Rothesay CHORD 9,697-             9,697-                       9,697-                         -            7,688-                            2,009-        -          -          9,697-        7,688-                            -           7,688-            
Kilmory Business Park Phase 2AA - SG RCGF 829-                829-                          829-                            -            -                                829-           -          -          829-           -                                -           -                
Kilmory Business Park Phase 2AA - HIE 150-                150-                          150-                            -            -                                150-           -          -          150-           -                                -           -                
Strategic Change Total 12,996-           -           12,996-                     12,996-                       -            7,688-                            5,308-        -          -          12,996-      7,688-                            -           7,688-            
Chord Total 12,996-           -           12,996-                     12,996-                       -            7,688-                            5,308-        -          -          12,996-      7,688-                            -           7,688-            
DEG  Service Development Cycling, Walking and Safer Routes (CWSR) 2,988-             2,988-                       2,988-                         -            2,612-                            376-           -          -          2,988-        2,612-                            -           2,612-            
SPT - bus infrastructure 1,268-             1,268-                       1,268-                         -            1,243-                            25-             -          -          1,268-        1,243-                            -           1,243-            
Cycleways - H&L (SPT) 3,502-             3,502-                       3,502-                         -            3,210-                            292-           -          -          3,502-        3,210-                            -           3,210-            
Town Centre Funds 2,730-             2,730-                       2,730-                         -            2,468-                            262-           -          -          2,730-        2,468-                            -           2,468-            
Rural Growth Deal 835-                835-                          835-                            -            126-                               709-           -          -          835-           126-                               -           126-               
Dunoon STEM Hub 2,558-             2,558-                       2,558-                         -            508-                               2,050-        -          -          2,558-        508-                               -           508-               
Ardrishaig North Active Travel 50-                  50-                            50-                              -            50-                                 -            -          -          50-             50-                                 -           50-                 
Dunoon Cycle Bothy 566-                566-                          566-                            -            566-                               -            -          -          566-           566-                               -           566-               
Gibraltar Street Public Realm Improvements 250-                250-                          250-                            -            250-                               -            -          -          250-           250-                               -           250-               
Glenmorag Car Park PC 4-                    -           4-                              4-                                -            -                                4-               -          -          4-               -                                -           -                
Albert Pier - Toilet Demolition (Crown Estates) 40-                  -           40-                            40-                              -            -                                40-             -          -          40-             -                                -           -                
Service Development Total 14,791-           -           14,791-                     14,791-                       -            11,033-                          3,758-        -          -          14,791-      11,033-                          -           11,033-          
DEG Total 14,791-           -           14,791-                     14,791-                       -            11,033-                          3,758-        -          -          14,791-      11,033-                          -           11,033-          
Education Asset Sustainability Tobermory Top Flat 125-                -           125-                          125-                            -            -                                125-           -          -          125-           -                                -           -                
Asset Sustainability Total 125-                -           125-                          125-                            -            -                                125-           -          -          125-           -                                -           -                
Service Development Early Years 1140 Hours 6,300-             -           6,300-                       6,300-                         -            6,300-                            -            -          -          6,300-        6,300-                            -           6,300-            
Bowmore Primary School - Gaelic Medium Grant 47-                  47-                            47-                              -            47-                                 -            -          -          47-             47-                                 -           47-                 
Service Development Total 6,347-             -           6,347-                       6,347-                         -            6,347-                            -            -          -          6,347-        6,347-                            -           6,347-            
Education Total 6,472-             -           6,472-                       6,472-                         -            6,347-                            125-           -          -          6,472-        6,347-                            -           6,347-            
HSCP Asset Sustainability Kintyre Care Home 753-                -           753-                          753-                            -            -                                753-           -          -          753-           -                                -           -                
Thomson Home Rothesay 157-                -           157-                          157-                            -            -                                157-           -          -          157-           -                                -           -                
Capital Property Works 260-                -           260-                          260-                            -            -                                260-           -          -          260-           -                                -           -                
Asset Sustainability Total 1,170-             -           1,170-                       1,170-                         -            -                                1,170-        -          -          1,170-        -                                -           -                
HSCP Total 1,170-             -           1,170-                       1,170-                         -            -                                1,170-        -          -          1,170-        -                                -           -                
RIS Asset Sustainability EV Quick Chargers 6-                    -           6-                              6-                                -            -                                6-               -          -          6-               -                                -           -                
Environmental Projects 400-                -           400-                          400-                            -            -                                400-           -          -          400-           -                                -           -                
Public Convenience Upgrades 200-                -           200-                          200-                            -            -                                200-           -          -          200-           -                                -           -                
Asset Sustainability Total 606-                -           606-                          606-                            -            -                                606-           -          -          606-           -                                -           -                
Strategic Change Fleet Management 49-                  -           49-                            49-                              -            49-                                 -            -          -          49-             49-                                 -           49-                 
Oban Depot - Revenue and EVC funding 67-                  -           67-                            67-                              -            -                                67-             -          -          67-             -                                -           -                
EV Infrastructure Fund 56-                  -           56-                            56-                              -            56-                                 -            -          -          56-             56-                                 -           56-                 
Zero Waste Scotland - Recycling Improvement Fund 892-                -           892-                          892-                            -            63-                                 829-           -          -          892-           63-                                 -           63-                 
Weather Incident 500-                -           500-                          500-                            -            500-                               -            -          -          500-           500-                               -           500-               
Campbeltown Flood Scheme 270-                -           270-                          270-                            -            270-                               -            -          -          270-           270-                               -           270-               
Harbour Investment Programme - Crown Estates 10-                  -           10-                            10-                              -            10-                                 -            -          -          10-             10-                                 -           10-                 
Strategic Change Total 1,844-             -           1,844-                       1,844-                         -            948-                               896-           -          -          1,844-        948-                               -           948-               
RIS Total 2,450-             -           2,450-                       2,450-                         -            948-                               1,502-        -          -          2,450-        948-                               -           948-               
Shared Offices Asset Sustainability 5-7 East Clyde Street - Coastal Communities Fund 400-                -           400-                          400-                            -            -                                400-           -          -          400-           -                                -           -                
Asset Sustainability Total 400-                -           400-                          400-                            -            -                                400-           -          -          400-           -                                -           -                
Shared Offices Total 400-                -           400-                          400-                            -            -                                400-           -          -          400-           -                                -           -                
Totals -38,279 -           -38,279 -38,279 -            -26,016 -12,263 -          -          -38,279 -26,016 -           -26,016
Original
Budget
Budget
Changes Revised Budget Forecast Income
Variance
(Over)
/Under
Budget
Prior Years Actual 2025-26 2026-27 Future
Years
Total
Capital
Plan
Prior Years Actual 2025-26 to
Quarter 2 Total
Category £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
Asset Sustainability 2,301-             -           2,301-                       2,301-                         -            -                                2,301-        -          -          2,301-        -                                -           -                
Service Development 21,138-           -           21,138-                     21,138-                       -            17,380-                          3,758-        -          -          21,138-      17,380-                          -           17,380-          
Strategic Change 14,840-           -           14,840-                     14,840-                       -            8,636-                            6,204-        -          -          14,840-      8,636-                            -           8,636-            
Overall Total 38,279-           -           38,279-                     38,279-                       -            26,016-                          12,263-      -          -          38,279-      26,016-                          -           26,016-          
Approved Income Budget v Forecast Income Forecast Income Profile Actual Income
Approved Income Budget v Forecast Income Forecast Income Profile Actual Income

Page 63

APPENDIX 3 – Changes to Capital Plan and Financial Impact 
SLIPPAGES AND ACCELERATIONS
Project
2025-
26
£’000
2026-
27
£’000
Future
Years
£’000
Total
Capital
Plan
£’000
Recommendation Explanation
Environmental Projects (597) 597 0 0 Slip budget from 2025-26
to 2026-27
Slippage into 2026-27. Ground investigations and
land acquisitions will delay works out of 2025-26.
Campbeltown Flood
Scheme
(324) 324 0 0 Slip budget from 2025-26
to 2026-27
Slippage into 2026-27. Property Flood Resilience
contract no longer forecast to be awarded in 2025-
26.
Total Slippages and
Accelerations (921) 921 0 0

Page 64

Strategic Change Projects - Cumulative Spend, Start/Finish Dates and Project Risks APPENDIX 4
Strategic Change Projects - Greater than £1m Budget
Prior Years
Spend
£'000
Current Year
Forecast
£'000
Total Project
Forecast
£'000
Total Project
Budget
£'000
Project Start
Date
Estimated
Completion
Date
Project
Risks
Identified Explanation
Campbeltown Flood Scheme 14,986 242 15,939 15,939 01/08/2016 31/03/2027 Red Property Flood Resilience works slipped into 2026-27.
CHORD Rothesay 25,337 8,554 45,414 45,414 01/05/2024 31/03/2027 Green
Harbour Investment Programme 19,896 22,782 143,099 143,099 01/04/2017 31/03/2028 Red
Project in progress - Whilst resources haven’t been comitted there are concerns over the potential
costs of Craignure exceeding the previously allocated budget.
Clean Energy - NDEEF1 1,203 238 1,441 1,441 01/04/2021 31/03/2026 Green
Clean Energy - NDEEF2 0 855 1,140 1,140 01/04/2024 31/03/2027 Green
Street Lighting LED Replacement 3,343 557 3,900 3,900 01/08/2016 31/12/2025 Green
Kilmory Business Park Phase 2AA 355 774 1,147 1,147 01/02/2022 31/03/2026 Green
TIF - Oban Airport Business Park 996 375 1,371 1,371 22/01/2015 31/03/2028 Green
All remaining Strategic Change Projects falling under £1m 1,230 2,604 3,549 3,521
Strategic Change Total Gross Expenditure 67,346 37,836 218,140 218,112
Gross Capital Expenditure Dates Risks

Page 65

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
04 DECEMBER 2025
FINANCIAL RISKS ANALYSIS 2025-26 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to provide a summary of the known key
financial risks facing the council in 2025-26, as at 31 October 2025. 
1.2  A number of council wide financial risks, both revenue and capital, have been
identified, in addition to specific departmental or service risks.  For each
quantifiable risk, the potential annual financial impact has been estimated; and the
likelihood of the risk materialising assessed, based on a standard risk matrix. 
1.3 There are currently 7 council wide quantifiable risks identified for 2025-26, with a
potential annual value totalling £5.1m, and with varying degrees of likelihood. 
1.4 There are currently 32 departmental/service risks, with a potential annual value
totalling £4.156m, of which 5 are categorised as ‘Likely’ (annual value £1.210m).   
1.5 There have been no changes to the quantifiable risks since last reporting. 
Financial risks will continue to be monitored and reviewed on an ongoing basis,
with actions put in place to mitigate or manage these risks.

Page 66

ARGYLL AND BUTE COUNCIL
FINANCIAL SERVICES
POLICY AND RESOURCES COMMITTEE
04 DECEMBER 2025
FINANCIAL RISKS ANALYSIS 2025-26  
2. INTRODUCTION 
2.1 This report outlines the process and approach to financial risk assessment, and
provides details of the known key financial risks facing the council in 2025-26, as
at 31 October 2025. 
3 DETAIL 
3.1 Process and Approach 
3.1.1 The council continues to experience significant financial challenges and
uncertainty.  In developing its budget to address both funding, and cost and
demand pressures, consideration is given to financial risk.  However, both existing
and new or emerging financial risks require to be monitored and reviewed on an
ongoing basis throughout the year, with actions put in place to mitigate or manage
these risks.  Risks that cannot be mitigated or managed may have a detrimental
impact on the financial position of the council. 
3.1.2 There are a number of risks that may impact income or expenditure across the
entire council.  These are identified as council wide risks.  In addition, specific
financial risks impacting each department or service of the council have been
considered.  These are identified as departmental/service risks.   
3.1.3 For each quantifiable risk, the potential annual financial impact has been
estimated; and the likelihood assessed, based on the following standard risk
matrix: 
1 – Remote
2 – Unlikely
3 – Possible
4 – Likely
5 – Almost Certain 
3.1.4 The Argyll and Bute Integrated Joint Board (IJB) with responsibility for Social
Work and a range of Health services was established and came into effect on 1
April 2016.  The IJB is responsible for financial management and strategic
oversight of these services.  It is the responsibility of the IJB to consider the
individual financial risks associated with Integration Services and these risks are
therefore not contained within this report.  A council wide risk has been included
in respect of the IJB being unable to deliver the social care service within the
budget allocated.

Page 67

3.2 
3.2.1 
3.2.2
Council Wide Risks 
General 
There is a risk of further severe weather incidents, requiring both revenue and
capital expenditure to be incurred.  Whilst there may be additional funding
available through the Bellwin Scheme, this is limited to eligible revenue
expenditure and there is an assumption that local authorities will meet a
proportion of the costs of emergency incidents from within existing resources. 
The threshold, over which councils can claim for eligible expenditure is 0.2% of a
local authority's budgeted net revenue expenditure.  For Argyll and Bute Council,
this equates to £0.654m for 2025-26.  As part of the 2025-26 budget process,
£2.9m was provided for severe weather related costs (£2m from the Priorities
Investment Fund and £0.9m within the Capital Plan).  However, by their very
nature, it is difficult to estimate potential additional costs and there remains a risk
of costs being incurred above the level currently provided for within financial
plans.  It is therefore deemed prudent to recognise a financial risk in this respect. 
A risk value of £1m is deemed to be reasonable. 
The council is generally able to recover all input VAT incurred on its expenditure,
subject to certain conditions being met.  Some activities are VAT exempt, such
as, the lease of land or property, where the land or property has not been opted to
tax.  VAT incurred on expenditure attributable to exempt activities, such as, capital
investment in property development or refurbishment must be less than 5% of the
total VAT incurred in the year.  A breach of this 5% limit would result in VAT paid
on all expenditure attributable to exempt activities being irrecoverable.  As
opportunities to support economic development are explored, it is increasingly
likely that the council will enter into commercial arrangements, such as in respect
of Rothesay Pavilion.  The tax position in respect of these arrangements requires
to be given due consideration, with mitigations put in place, as appropriate, for
example, opting to tax land and property.  This position will be subject to ongoing
monitoring and review, to ensure that the council continues to remain within the
5% threshold and recover all VAT incurred. 
Revenue  
3.2.3 The 2025-26 budget included a 3% pay award assumption across all workforce
categories, at all grades, based on the Public Sector Pay Policy of 9% over the 3
years 2025-26 to 2027-28.  The pay award for SJC and Chief Officers has now
been agreed at 4% for 2025-26 and 3.5% for 2026-27.  In addition, the Teachers
pay award has been agreed at 7.5% over the 2 years 2025-26 and 2026-27 (4%
from 1 August 2025, rising to 4.25% from 1 April 2026, and 3.25% from 1 August
2026).  At this stage, the expectation is that the increased cost of the 2025-26 pay
award will be fully funded from additional Scottish Government grant funding,
however, a potential annual risk value of £0.7m has been retained pending
confirmation of additional Scottish Government funding.   
3.2.4 Whilst the 2025-26 approved budget provides for inflationary increases, there is a
risk of continued volatility in utilities pricing and demand can also be subject to
unpredictable weather extremes.  At this stage, a potential annual risk value

Page 68

equivalent to 10% of the annual utilities budget provision is deemed reasonable. 
This equates to £0.9m.  It is anticipated that this risk value may reduce as the
year progresses. 
3.2.5  The estimated level of Council Tax income is based on current and forecast Band
D equivalents, and reflects our expected collection rates, based on historical data. 
A potential annual risk value equivalent to 1% of the annual Council Tax income
budget is deemed reasonable in this respect.  Furthermore, there is currently a
significant level of uncertainty in respect of the classification of self-catering units
as either non-domestic or domestic dwellings, which may impact Council Tax
income, presenting an additional risk to financial planning assumptions.  These
factors equate to a combined estimated risk value of £1m.  
3.2.6 
3.2.7 
3.2.8
In respect of the Health and Social Care Partnership (HSCP), it is the
responsibility of the Chief Officer and Chief Financial Officer to manage the HSCP
financial position.  If an overspend is forecast, a budget recovery plan will be
prepared and submitted to the IJB, Argyll and Bute Council and NHS Highland. 
Where recovery plans are unsuccessful and an overspend occurs at the financial
year end, and the HSCP has insufficient reserves to meet the overspend, then the
partners will be required to make additional payments to the HSCP.  The council’s
contribution would reflect the element of the overspend related to Social Work. 
Whilst any additional payments by the council and NHS Highland will be deducted
from future years funding, there is a risk that the council may require to make an
additional unbudgeted contribution to the HSCP during the year.   
As at 31 October 2025, the forecast outturn for 2025-26 on Social Work services
is an overspend of £0.733m.  This includes an assessment on the delivery of
approved savings, including the £0.500m of unidentified savings built into the
budget, as part of the recovery plan.  At this stage, the HSCP expect the forecast
overspend to be managed within available HSCP reserves.  However, the
financial situation facing Social Work is extremely challenging due to increases in
service demand; complexity of cases; increasing costs; and difficulty recruiting
permanent staff and, therefore, having to rely on agency staff, at an additional
cost.  There is a risk that the level of overspend will increase beyond the level that
can be managed through available reserves as the year progresses.  A potential
annual risk value equivalent to 1% of the approved budgeted contribution is
deemed reasonable.  This equates to £0.9m.  It is also recognised that any
potential unbudgeted use of reserves or additional funding, required for 2025-26,
will have implications for the HSCP 2026-27 and future years’ budget outlook. 
The 2025-26 budget includes both Operational/Management and Policy savings
options, totalling £2.762m.  Whilst the council has a good track record in
delivering savings, there is a risk that this target will not be fully delivered.  A
potential annual risk value equivalent to a 10% shortfall in the annual savings
target is deemed reasonable.  This equates to £0.3m. 
3.2.9  There is an ongoing requirement to fund unavoidable inflationary cost increases
across a number of areas such as food and fuel. Inflation is currently exceeding
the latest Bank of England forecasts but is expected will fall back towards the 2%
government target later in the year.  This position will continue to be closely

Page 69

3.2.10 
3.2.11 
3.2.12
monitored, with financial forecasts updated to reflect information available, on an
ongoing basis.  The annual budget is underpinned by inflationary assumptions,
however, there is a risk that inflationary impacts have been under-estimated. A
potential annual risk value equivalent to 10% of the inflationary assumptions in
respect of relevant non-pay budgets is deemed reasonable.  This equates to
£0.3m. 
Capital 
The funding framework for the approved Capital Plan includes capital receipts
from asset sales, estimated at £0.750m in 2025-26 and £1.750m over the 3 years
2025-28.  This is based on an assessment provided by the Estates Team in
January 2025, however, is subject to changing market conditions.  The level of
receipts that may reasonably be achieved will be kept under review, to reflect
changing market conditions and due diligence undertaken on asset condition. 
Any variation from this assumption will require to be managed within the overall
Capital Plan resources. It is generally the case that the capital programme
experiences slippage throughout the year and as such, this risk is expected to be
manageable.   
At the budget meeting in February 2024, £1.1m of funding was set aside as an
initial high level estimate of works anticipated to be required at the A816 Bealach
Mor to convert the temporary road into a permanent road.  An options study has
been carried out to explore a number of options for this stretch of road going
forward.  A report will be presented to EDI in September 2025 outlining 9 options,
which have been shortlisted to 4 at this stage.  The preferred option cost estimate
is significantly higher than the budget set aside in February 2024, estimated to be
between £7.25m and £8.5m.  Further work is required to develop a business case
options appraisal and we would look to get independent design and project
management consultants to take this forward.  Once we have firmer proposals,
this will be reported to Council and consideration will need to be given as to how
the shortfall will be funded. 
The capital programme is continuing to see significant price increases caused by
rising inflation and additional costs from suppliers, due to the challenges in
delivering capital projects within our geographical location.  Previous inflationary
contingencies set aside for the capital programme have now been fully allocated
but there could be other cost pressures in respect of projects within the current
capital programme, where contracts have yet to be entered into.  It will be
challenging to manage these impacts within available resources and target
completion timescales.  Mitigating actions will be taken to manage financial risk,
for example, re-profiling, project re-design, re-engineering or curtailment, and the
re-prioritisation of uncommitted resources across the programme.  However, there
remains a risk that costs could increase for the projects that are included within
the capital plan. 
Council Wide Summary 
3.2.13  The council wide risks are summarised within the following table.

Page 70

Description Likelihood Assessed
Financial Impact
£m
Unbudgeted Severe Weather costs 3 1.0
Unfunded Pay Award 3 0.7
Utilities cost increases 3 0.9
Council Tax Income reduction 3 1.0
IJB refer to Council for additional
funding to deliver social work services
3 0.9
Shortfall in Savings delivery  2 0.3
Variation in non-pay inflation  3 0.3
Total  5.1 
3.3  Departmental/Service Risks 
3.3.1 Specific service financial risks are detailed within Appendix 1.  The following table
provides a summary of the number of risks within each department, across each
likelihood category, together with the potential annual financial impact value. 
Department 1 - Remote 2 - Unlikely 3 - Possible 4 - Likely 5 - Almost
Certain
Total
No £000 No £000 No £000 No £000 No £000 No £000
Chief
Executive's
Unit
0 0 0 0 0 0 0 0 0 0 0 0
Executive
Director
Douglas
Hendry
0 0 6 510 9 780 2 360 0 0 17 1,650
Executive
Director
Kirsty
Flanagan
4 375 1 100 7 1,181 3 850 0 0 15 2,506
Total 4 375 7 610 16 1,961 5 1,210 0 0 32 4,156 
3.3.2  The current top 3 risks in terms of financial impact are noted in the table below. 
Service Risk Title Risk Description Likelihood
Financial
Impact
£000
Roads and
Infrastructure
Services
Piers &
Harbours
Income
Changes to ferry services resulting in
reduced berthing and passenger
income.
4 600
Financial
Services
NDR
ALEO
Baseline
Scottish Government are going to
undertake a review of the current Arms
Length External Organisations (ALEO)
baseline for 2024-25 which could
increase the pressure on the balance of
costs vs relief.
3 316

Page 71

Council Wide
- Commercial
Services
Council
Wide
Central
Repairs
Increased demands on central repair
budgets (CRA) due to a decrease in
Capital funding, increase in statutory
and emergency repairs and increases in
supplier /contractor charges.  This
impacts on all departments of the
Council with a Central Repairs Budget.
4 300 
3.3.3  The risks, which are considered likely total £1.210m and are detailed in the
following table: 
Service Risk Title Description of Risk Likelihood
Financial
Impact
£000
Roads and
Infrastructure
Services
Piers &
Harbours
Income
Changes to ferry services resulting in
reduced berthing and passenger income.
4 600
Council Wide
- Commercial
Services
Council Wide
Central Repairs
Increased demands on central repair
budgets (CRA) due to a decrease in
Capital funding, increase in statutory and
emergency repairs and increases in
supplier/contractor charges.  This
impacts on all departments of the
Council with a Central Repairs Budget.
4 300
Development
and
Economic
Growth
Homelessness
Temporary
Accommodation
Income
Unpredictable number of Homeless
applications. Inability to recover rent. 
Increased costs of property maintenance
and tenancy change over.
4 150
Roads and
Infrastructure
Services
Fleet
Maintenance
Increased costs to maintain internal fleet
due to inflationary increases on vehicle
parts.
4 100
Legal and
Regulatory
Support
Elections Should a by-election be required this
would be an immediate cost pressure as
budget has been removed. 
4 60 
3.3.4 
3.4
In addition to the specified service risks, there is a risk in respect of waste
(Compost Like Output, CLO), which at this point, is unquantifiable.  Financial
provision of £500k has been reflected within the annual accounts for the year
ending 31 March 2025 in respect of CLO.  This estimated liability was calculated
on a basis agreed with Biffa, however, remains subject to approval by the Scottish
Environment Protection Agency, SEPA.  There is a risk that SEPA may require
the disposal of CLO as landfill of contaminated waste, which would result in
significantly higher costs.  At this stage, it is not clear to what extent the existing
waste earmarked reserve may mitigate this risk and any additional cost would
result in the unplanned depletion of the earmarked reserve. 
Changes to Financial Risks 
3.4.1 There have been no changes to the quantifiable risks since last reporting,
although a level of certainty has been achieved in relation to anticipated 2025-26
funding from the Department for Environment, Food & Rural Affairs, DEFRA in
respect of Extended Producer Responsibility.  However, uncertainty remains in
respect of funding and expenditure commitments for future years.    
3.5 Monitoring of Financial Risks

Page 72

3.5.1  Financial risks are monitored and reviewed on an ongoing basis, with actions put
in place to continue to mitigate or manage these risks.  The updated position on
financial risks will continue to be regularly reported to committee.     
3.6 Future Years’ Risks 
3.6.1 Financial risks impacting 2026-27 and future years will be reported as part of the
2026-27 Budget Pack.  
4 CONCLUSION 
4.1 This report summarises the known key financial risks facing the council in 2025-
26.  There are 7 council wide and 32 service specific quantifiable risks identified,
with 5 categorised as ‘Likely’.  These risks are monitored and reviewed on an
ongoing basis, with actions put in place to continue to manage or mitigate the
risks.   
5 IMPLICATIONS 
5.1 Policy - None.
5.2 Financial -  Outlines the potential annual value of financial risks. 
5.3 Legal -  None.
5.4 HR -  None.
5.5 Customer Service- None.
5.6 Risk -  Provides details of financial risks.
5.7 Climate Change -  None.
5.8 Fairer Scotland Duty -  None.
5.9 Equalities - protected
characteristics -
None.
5.10 Consumer Duty -  None.
5.11 Island Communities -  None. 
5.12 Children’s Rights and
Wellbeing - 
None. 
Kirsty Flanagan
Executive Director/Section 95 Officer
20 November 2025 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services 
APPENDICES
Appendix 1 – Departmental/Service Financial Risks 
For further information contact Carolyn Earl, Interim Head of Financial Services
Carolyn.Earl@argyll-bute.gov.uk

Page 73

APPENDIX 1
DEPARTMENT/SERVICE FINANCIAL RISKS AS AT 31 OCTOBER 2025
DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Commercial Services Catering Costs - Provision of
Meals to Early Years Children
The Children and Young People (Scotland) Act placed duties on Councils to
provide meals in an Early Years setting to entitled children where sessions span
over lunch time.  The total quantum of grant funding is reducing and may not be
sufficient to fund the additional costs depending on uptake and the additional
costs to support the meal provision in partner provider settings.
Joint strategy with procurement colleagues to reduce potential impact
of supplier charges.  Control food wastage/portion controls.
2 100
Executive Director
Douglas Hendry
Commercial Services Rental Income from Properties Due to current economic climate, there may be reduced ability to recover rental
income from leased properties or place suitable tenants in properties as leases
come to an end.
Management of leasehold properties by Estates team, any issues with
debt recovery being dealt with in line with Council debt recovery
policy.
2 60
Executive Director
Douglas Hendry
Commercial Services Surplus Properties Ongoing market difficulties lead to increased numbers of surplus properties, in
addition, as Our Modern Workspace Project gains traction more properties will
become surplus to operational requirements. There are residual running costs
associated with all surplus properties.
One Council property team in place who will monitor market
conditions and work with prospective tenants/ purchasers to let/sell
surplus properties.
3 50
Executive Director
Douglas Hendry
Commercial Services Leisure Service Level
Agreements
Increase in RPI and/or other running costs (eg utilities, payroll etc) resulting in
requests for additional funding.
Monitoring annual alteration to contract RPI rate, communication
with service providers and mitigation through financial forecasting and
review of existing budget.
3 100
Executive Director
Douglas Hendry
Commercial Services LiveArgyll Service Fee Inability to deliver required services within available budget resources (e.g.. pay
award and ENICs budget pressures), resulting in increased service fee request.
Communication with service providers and mitigation through
monitoring and review of budget monitoring information and
forecasts.
3 100
Executive Director
Douglas Hendry
Council Wide -
Commercial Services
Council Wide Central Repairs Increased demands on central repair budgets (CRA) due to a decrease in Capital
funding, increase in statutory and emergency repairs and increases in
supplier/contractor charges.  This impacts on all departments of the Council with
a Central Repairs Budget.
Joint strategy with procurement colleagues to reduce potential impact
of supplier/contractor charges. Close monitoring of central repairs
budgets and commitments and instructing only statutory
tests/inspections and essential repairs.
4 300
Executive Director
Douglas Hendry
Education ASN Support Demand for ASN support continues to increase. Scottish Government statistics
suggest a 3% year on year increase, resulting in an additional resource
requirement particularly where gaps in our enhanced provision exist. The
medium-term detriments on the development of young children which occurred
as a consequence of service closures during the COVID pandemic have increased
demands on the service as children require additional support to catch up.  The
Additional Support for Learning National Implementation plan continues to
inform our strategic direction in line with the Angela Morgan Review.
Service is currently looking at alternative options for service delivery
to mitigate the inescapable pressures. Continuing to ensure robust
assessment of needs, monthly monitoring of budget, any delays in
recruitment factored into projections to enable informed decision
making on allocation of funding for new/amended /additional support
packages. Following a full ASN review, the service are currently
investing in the development of four new learning centres in order to
provide greater equity in meeting the more complex needs of some
learners as well as considering plans to develop enhanced wellbeing
resources across our learning estate in future.  This aims to reduce the
frequency of children having to be educated in high cost out of area
placements.
2 50
Executive Director
Douglas Hendry
Education Pre-Five Units - retention of
partner providers
Failure in the commissioning or retention of pre-five partner provider units to
deliver 1140 hours would result in an increased pressure on the Council to
deliver the service.
Annual financial appraisal, uplift of sustainable rate to providers;
Support network; Short-term cash injections.
2 100
As at 31 October 2025

Page 74

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Douglas Hendry
Education Children and Young People
(Scotland) Act - ELC 1140 hours
The Council has been required to deliver 1140 hours of Early Learning and
Childcare since August 2021. The Scottish Government has committed to funding
this and the Council has revised its service model to align it to the Scottish
Government's reduced funding profile.  A risk remains that actual costs of
delivery exceed the Government Grant in any given year.  For example, if child
numbers are higher than estimated, this may require additional staffing which
has not been included in the staffing model funded by Scottish Government.  
Continuous monitoring and review of the service model, usage and
resources.
3 100
Executive Director
Douglas Hendry
Education Legislative Requirements -
Education (Scotland) Act
The Education (Scotland) Act 2000 requires Councils to undertake assessments of
the need for the provision of Gaelic Medium Primary Education (GMPE) and the
duty to support and promote Gaelic Education. This may lead to additional
staffing requirements depending upon the demand for Gaelic from parents.
Continuous monitoring and review of the service model and resources
available within budget.
3 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Hub DBDA/DBFM Schools  -
Litigation
Increased risk of the requirement to litigate due to latent defects in a number of
schools
Ongoing reporting of issues and monitoring of actions taken to repair. 2 150
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Contract RPI for NPDO and Hub
Schools
Increase in RPI would result in higher costs. Monitoring annual alteration to contract RPI rate and mitigation
through financial forecasting and review of existing budget.
3 100
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO - Increase in insurance
costs within NPDO Schools
Increase in insurance costs as a result of the long-term effects of Covid-19 on the
insurance market and flood claims.
Monitoring annual alteration to contract insurance rate and mitigation
through financial forecasting and review of existing budget.
3 75
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Elections Should a bi-election be required this would be an immediate cost pressure as
budget has been removed.
Outwith direct management control. 4 60
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Legal Services - Litigation Increased number of litigation cases. Ensure Legal Services are gateway to access all legal advice and that
advice is sought at earliest opportunity.
3 150
Executive Director
Douglas Hendry
Legal and Regulatory
Support
NPDO/Hub DBFM contract
management efficiencies
Reduction in ability to generate contract management efficiencies. Monitoring annual efficiencies generated and mitigation through
robust contract management and application of contract
specifications / requirements.
2 50
Executive Director
Douglas Hendry
Legal and Regulatory
Support
Licensing Reduced numbers of licensing applications leading to reduced income. Monitoring of trends and reporting the financial impact in the budget
monitoring.
3 55
Executive Director
Kirsty Flanagan
Customer Support
Services
Software Licences Potential risk of being under licensed for software which will be identified via
software audits which would incur additional costs.
ICT security and compliance officer in post and duties include review
of systems to ensure fully licenced. 
2 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Homelessness Temporary
Accommodation Income
Unpredictable number of Homeless applications. Inability to recover rent. 
Increase costs of property maintenance and tenancy change over.
Provision of Housing Options information and advice service to
minimise number of applicants proceeding to full homeless
application. Implementation of Rapid Rehousing Plan.
4 150
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Dangerous Buildings
Interventions
Building Standards having to deal with an increasing level of dangerous building
work which has significant financial implications for Council.
Monitor activity and seek to recover costs from the owner. 3 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning Fee Penalties Potential that the Scottish Government may apply sanction penalties due to poor
performance by the Planning Authority. The Scottish Government has recently
appointed a national Planning Performance Champion however the detail of how
this role intends to incentivise improvement/penalise poor performance at a
local authority level remains unclear at this time.
Maintain high levels of performance as articulated by performance
markers detailed in Planning Performance Framework annual report.
1 100
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Planning fee shortfalls Due to downturn in economic / building activity, in particular renewable energy
development and other major developments could lead to planning fee income
shortfalls leading to revenue budget pressures.
Current income levels are looking more positive, however, we are
dependent on some high value applications coming in which, if they
don't materialise, will impact the overall position.  Will continue to
monitor Development Management income and expenditure tightly
and investigate further income generation streams.
1 100

Page 75

DEPARTMENT SERVICE TITLE OF RISK DESCRIPTION OF RISK MITIGATING ACTIONS IN PLACE
LIKELIHOOD
FINANCIAL
IMPACT
£000
Executive Director
Kirsty Flanagan
Development and
Economic Growth
Building Warrant fee shortfalls Due to loss of commercial income and downturn in economic / building activity,
building warrant fee income shortfalls leading to revenue budget pressures.
Continue to monitor Building Standards income and expenditure
tightly and investigate further income generation streams.
1 50
Executive Director
Kirsty Flanagan
Financial Services NDR ALEO Baseline Scottish Government are going to undertake a review of the current Arms Length
External Organisations (ALEO) baseline for 2024-25 which could increase the
pressure on the balance of costs vs relief.
Outwith direct management control. 3 316
Executive Director
Kirsty Flanagan
Financial Services Housing Benefit Subsidy Loss of Housing Benefit Subsidy due to exceeding LA error threshold. Processes in place for handling of claims accurately and efficiently. 1 125
Executive Director
Kirsty Flanagan
Financial Services Sundry Debt Recovery Recovery of debt becomes more difficult to pursue in the current economic
climate. 
Additional staff are being put in place in the Sundry Debt Team who
will work jointly with Legal Services to enhance the robustness of the
Council's debt recovery processes.
3 85
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Roads Maintenance - Roads
Network
Adverse weather conditions result in deterioration of the road network
necessitating greater spend on repair of defects.
Manage maintenance budgets to ensure that spend is prioritised to
deal with safety defects.
3 230
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Car Parking Income Reduced number of visitors to the area and use of council owned car parks
resulting in a reduction in income.
Closely monitor income levels throughout the year, especially in high
visitor seasons.
3 200
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Piers & Harbours Income Changes to ferry services resulting in reduced berthing and passenger income. As
Cal Mac work to provide services across their network, an ageing fleet and delays
to new ferries coming into service is meaning larger ferries are being removed
from routes where we have the berthing infrastructure (mostly Craignure).
Smaller ferries are allowing for services to operate but the drop in income can be
up to 75% per berthing.
Closely monitor passenger number information coming from CalMac
to identify any emerging trends with reducing passenger numbers.
4 600
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Winter Maintenance Adverse weather conditions which require greater than budgeted number of
gritting runs.
Monitor weather conditions and apply gritting policy to minimise
costs.
3 150
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Street Lighting Age of lighting stock requires greater maintenance as health and safety becomes
a consideration.
Manage maintenance budgets to ensure that spend is prioritised to
deal with safety defects.
3 100
Executive Director
Kirsty Flanagan
Roads and
Infrastructure Services
Fleet Maintenance Increased costs to maintain internal fleet due to inflationary increases on vehicle
parts.
Review of Fleet underway to determine where reductions could
possibly be made.
4 100
32 4,156

Page 76

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 04 DECEMBER 2025
RESERVES AND BALANCES – UPDATE AS AT 31 OCTOBER 2025 
1 EXECUTIVE SUMMARY 
1.1 The main purpose of this report is to advise Members of the nature and level of
reserves and balances currently held by the council.  It also provides details of the
earmarked reserve balances held within the General Fund and the unallocated
General Fund balance.   
1.2 The council had a total of £406.347m unusable reserves as at 31 March 2025 that
are not backed with resources. These are required purely for accounting purposes. 
1.3 As at 31 March 2025, the council had a total of £121.235m usable reserves,
comprising the following: 
• £3.608m Repairs and Renewals Fund;
• £3.358m Capital Funds; 
• £1.564m Capital Grants Unapplied; and
• £112.705m General Fund, with £105.162m of this balance earmarked for
specific purposes.
1.4 
1.5 
The 2025-26 opening earmarked reserves balance of £105.162m includes a
significant level of reserves in respect of major infrastructure or projects of
strategic importance.  It is currently anticipated that a total of £22.349m will be
drawn down during 2025-26, while £7.501m has been drawn down in the year to
31 October 2025, for previously approved specific purposes.  The expected use 
includes £30k financial support for Mid Argyll Community Pool, subject to Member
approval.  Similar to previous years, a review of earmarked reserves is now
underway and will subsequently be reported to members, taking cognisance of
strategic priorities and the financial challenges currently facing the council. 
The council’s General Fund contingency is set at 2% of estimated net revenue
expenditure for 2025-26, which amounts to £6.539m.  At the beginning of the
financial year, there was an unallocated General Fund Balance of £1.004m over
and above the general contingency.  After taking into consideration the current
revenue budget forecast outturn and commitments for 2025-26, this surplus is
forecast to increase to £1.246m as at 31 March 2026.

Page 77

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 04 DECEMBER 2025
RESERVES AND BALANCES – UPDATE AS AT 31 OCTOBER 2025 
2 INTRODUCTION 
2.1 This report outlines the nature and level of reserves and balances, both usable
and unusable, currently held by the council.  It also provides details of the
earmarked reserve balances held within the General Fund and the unallocated
General Fund balance. 
3. DETAIL 
3.1 Types of Reserves 
3.1.1 Usable Reserves - Councils have powers to establish certain resource backed
reserves, which can be used to fund expenditure.  The powers of councils to
establish reserves are laid out in Schedule 3 of the Local Government (Scotland)
Act 1975.  These allow councils to establish a Renewal and Repairs Fund,
Insurance Fund and Capital Fund. Councils can also establish a Capital Grants
Unapplied and Useable Capital Receipts Reserve.  The council must also
maintain a General Fund and can earmark balances for specific purposes within
the General Fund. 
3.1.2 Unusable Reserves – Councils are also required to establish certain reserves
that are not backed by resources. These are required purely for accounting
purposes and do not represent resources available for councils to utilise. The
Pensions Reserve, Revaluation Reserve, Capital Adjustment Account, Financial
Instruments Adjustment Account and Accumulated Absences Account are
examples of unusable reserves. 
3.2 Reserve Balances as at 31 March 2025 
3.2.1  The balances on each type of reserve as at 31 March 2025 are set out in the
tables below, per the Pre-audit Annual Accounts for 2024-25. 
Unusable Reserves £000
Revaluation Reserve 179,662
Capital Adjustment Account 256,344
Financial Instruments Adjustment Account (1,413)
Pensions Reserve (16,984)
Accumulated Absences Account (11,262)
Total Unusable Reserves 406,347 
Usable Reserves £000
Capital Grants Unapplied 1,564
Capital Fund and Usable Capital Receipts Reserve 3,358

Page 78

Repairs and Renewals Fund 3,608
General Fund  112,705
Total Usable Reserves  121,235
Total Reserves  527,582 
3.2.2  The Revaluation Reserve represents the unrealised gains in the valuation of fixed
assets. The Capital Adjustment Account represents the difference between
depreciation based on proper accounting practice and statutory charges for
financing capital expenditure. The Financial Instruments Adjustment Account
represents the difference between gains and losses on borrowing and statutory
capital financing charges. The Pensions Reserve represents the difference
between pension costs based on proper accounting practice and payments made
for pension costs. The Accumulated Absences Account represents the costed
difference between holiday pay entitlement and actual holidays taken as at 31
March 2025.
3.2.3 The Capital Grants Unapplied Fund holds capital grants and contributions that
have been received but not yet used to fund capital expenditure. 
3.2.4  The Capital Fund was established to receive all capital receipts generated by the
council and can be used to support the capital plan or meet the principal
repayments on loan charges. The council decides as part of the budget process
each year how it wishes to draw funding from the Capital Fund. 
3.2.5 The Usable Capital Receipts Reserve relates to the accumulated unspent capital
receipts from the sale of council houses prior to the transfer of the housing stock.
The reserve forms part of the council’s Strategic Housing Fund and can only be
used for investment in social housing. The reserve will be used in accordance with
the approach to investing in housing, agreed by Council in August 2012. 
3.2.6 The Repairs and Renewals Fund was established to support funding of renewal
and replacement of school equipment.  Schools can only draw on the Repairs and
Renewals Fund to the extent they have previously paid into the Fund and
contributions must be contained within schools devolved budgets. 
3.3 General Fund 
3.3.1  The General Fund balance as at 31 March 2025 can be analysed as follows: 
Balance
£000
Balance on General Fund as at 31 March 2024 115,741
Movement in General Fund balance during 2024-25 (3,036)
Earmarked Balances (105,162)
Contingency allowance at 2% of net expenditure (6,539)
Unallocated balance as at 31 March 2025 1,004 
3.3.2  The General Fund includes reserve balances that Council has agreed to earmark
for specific purposes, as outlined within the 2024-25 year end report to Council.

Page 79

The movement in the balance of earmarked reserves during 2024-25 is given in
the table below. 
£000
Earmarked Balance as at 31 March 2024 107,443
Funds used during 2024-25 (26,457)
New automatic earmarking at the end of 2024-25 (as per policy
on end of year flexibility)
8,278
Earmarking previously agreed and created during 2024-25 13,298
New earmarking proposals for approval 2,600
Earmarked Balance as at 31 March 2025 105,162 
3.3.3 The 2025-26 opening earmarked reserves balance of £105.162m includes a
significant level of reserves in respect of major infrastructure or projects of
strategic importance.  Similar to previous years, a review of earmarked reserves
is now underway and will subsequently be reported to members, taking
cognisance of strategic priorities and the financial challenges currently facing the
council. 
3.3.4 An element of the earmarked reserve balances will require to be drawn down in
2025-26, to meet expenditure incurred during the current financial year.  This
includes £2.953m to balance the 2025-26 budget as previously approved by
Council in February 2025.  To assist with financial planning, a review of the
projected use of reserves, aligned to service plans, has been undertaken by
officers, with the projected use of resources profiled across 2025-26 and future
years.  The movement in the reserves balance during 2025-26 and the profile of
planned spend across 2025-26 and future years will be monitored and reviewed
on an ongoing basis throughout the year, with regular update reports to
committee. 
3.3.5 
3.3.6
A summary of the earmarked reserves position by category is provided within
Appendix 1, while Appendix 2 provides a summary of the position across services
and departments, as at 31 October 2025.  A detailed analysis is given within
Appendix 3, outlining the purpose of each earmarked reserve, the opening
balance, amounts drawn down to date and the planned use of reserves across
2025-26 and future years.  It is currently anticipated that a total of £22.349m will
be drawn down during 2025-26, while £7.501m has been drawn down in the year
to 31 October 2025, for previously approved specific purposes. 
It had not been possible to consider an external funding request from Mid Argyll
Community (MAC) Pool as part of the 2025-25 budget process.  However,
financial support is now being sought for 2025-26, in order to safeguard the
continued provision of services.  Details of this request are outlined within
Appendix 4.  In light of the organisation’s current financial position, Members are
requested to approve financial support to MAC Pool in 2025-26 of £30k, to be
funded from the Priorities Investment Fund earmarked reserve.  This has been
reflected within the expected use of reserves in 2025-26. 
3.3.7 It should be noted that the council’s earmarked reserves include a historic balance
in relation to Social Work of £0.014m as at 31 October 2025.  As per CIPFA
LASAAC Guidance, any new earmarking relating to the HSCP since financial year

Page 80

2020-21 must be held as a creditor on the Balance Sheet rather than an
earmarking within the council’s General Fund as this is money due to the HSCP. 
The balance held in this manner as at 31 March 2025 was £2.247m and does not
include the £0.500m of the Strathclyde Pension Fund saving in 2025-26 that
Council agreed to ring fence to support future HSCP transformation. 
3.4 Unallocated General Fund Balance 
3.4.1  The council’s General Fund contingency is set at 2% of estimated net revenue
expenditure for 2025-26, which amounts to £6.539m.   At the beginning of the
financial year, there was an unallocated General Fund Balance of £1.004m over
and above the general contingency.   After taking into consideration the current
revenue budget forecast outturn and commitments for 2025-26, this surplus is
forecast to increase to £1.246m as at 31 March 2026. 
3.4.2 
3.4.3 
3.4.4
The revenue budget monitoring position as at 31 October 2025 is a forecast
underspend of £0.480m. This is due to a forecast over-recovery of Council Tax
income, estimated at £0.500m; partially offset by net overspends across services,
totalling £0.020m. There is also a forecast overspend of £0.733m in respect of
Social Work services, however, the HSCP expect this to be managed from within
available HSCP reserves. 
At its meeting of 26 November 2025, Council approved an increase to the current
Standby Rate of pay to £130 per week from December 2025, at a cost of £13k in
2025-26, to be funded from the unallocated General Fund balance.  The full year
recurring implications of this approval from 2026-27 (£41k) is reflected within the
current Budget Outlook. 
Subject to member approval, it is recommended that financial support is provided
to the Royal National MOD, to be funded from the unallocated General Fund
balance.  This totals up to a maximum of £225k (up to £200k An Comunn + £25k
LiveArgyll) over 4 years from 2025-26. 
3.4.5  The following table summarises the current position on the unallocated General
Fund balance, taking into consideration the points noted above. 
Description £000
Unallocated General Fund
as at 1 April 2025
Unallocated balance over and
above the 2% general contingency
(£6.539m)
1,004
Current Forecast Outturn
for 2025-26 as at 31
October 2025
Per Revenue Budget Monitoring
report
480
Standby Rate Increase –
2025-26 Cost
To fund 2025-26 cost of the Standby
Rate increase, approved by Council
26 November
13
Royal National MOD To fund financial support to Royal
National MOD over 4 years, subject
to member approval
225
Forecast Unallocated General Fund as at 31 March 2026 1,246

Page 81

4. CONCLUSION 
4.1 This report outlines the nature and level of reserves and balances held by the
council.  It also provides details of the earmarked reserve balances held within the
General Fund and the unallocated General Fund balance.   
4.2 After taking account of the current forecast outturn for 2025-26, the council’s
unallocated General Fund balance, over and above the general contingency
balance of £6.539m, is forecast to be £1.246m as at 31 March 2026. 
5.  IMPLICATIONS 
5.1 Policy - Earmarked funds and funds set aside
for delivery of Single Outcome
Agreement are available to support
council policy.
5.2 Financial - Outlines the balances held within the
council’s usable and unusable
reserves.    
5.3 Legal -  None.
5.4 HR -  None.
5.5 Customer Service None.
5.6 Risk -  A contingency of £6.539m (equivalent
to 2% of net expenditure) has been
set aside as part of the General Fund. 
This has been subject to a risk
assessment. 
5.7 Climate Change - None.
5.8 Fairer Scotland Duty -  None.
5.9 Equalities - protected characteristics - None.
5.10 Consumer Duty -  None. 
5.11 Island Communities - None. 
5.12 Children’s Rights and Wellbeing - None. 
Kirsty Flanagan
Executive Director/Section 95 Officer 
20 November 2025 
Councillor Ross Moreland, Policy Lead for Finance and Commercial Services 
APPENDICES
Appendix 1 – Earmarked Reserves Summary by Category as at 31 October 2025
Appendix 2 - Earmarked Reserves Summary by Service as at 31 October 2025
Appendix 3 – Earmarked Reserves Detailed Analysis as at 31 October 2025
Appendix 4 – Funding Request – MAC Pool 
For further information contact Carolyn Earl, Interim Head of Financial Services
Carolyn.Earl@argyll-bute.gov.uk

Page 82

Appendix 1
Earmarking
Category
Opening Balance
1 April 2025 - per
year end
published report
New
Earmarkings in
year
Movement
between
categories
Invested or
committed for
major initiatives
/capital projects
Drawn-down to
2025-26 Budget
as at 31 October
2025
Remaining
Balance as at 31
October 2025
Released to
General
Fund
£ £ £ £ £ £ £
Strategic Housing
Fund 10,141,692 10,141,692 10,141,692
Investment in
Affordable Housing 3,024,000 3,024,000 3,024,000
Capital Projects 37,493,675 37,493,675 37,493,675
Lochgilphead and
Tarbert
Regeneration
288,579 288,579 288,579
Support for Rural
Growth Deal 441,690 441,690 441,690
Piers and Harbours
Investment Fund 5,303,977 5,303,977 5,303,977
Scottish
Government
Initiatives
1,156,530 333,118 823,412
CHORD 0 0
DMR Schools 1,205,590 1,205,590 0
Energy Efficiency
Fund 214,521 214,521
Unspent Grant 12,184,971 155,219 1,841,399 10,343,572
Unspent Third
Party Contribution 408,975 42,582 366,393
Previous Council
Decision - Other 4,274,925 720,486 19,800 4,255,125
Redundancy
Provision 2,659,358 480,000 2,179,358
Connect for
Success Fund 899,721 65,802 833,919
Fleet - Timing
Delay 483,661 483,661 483,661
Hermitage Park 56,383 56,383
Priorities
Investment Fund 1,426,800 138,550 1,288,250
Unspent Budget 14,294,911 328,465 13,966,446
SPF -
Transformation/spe
nd to save -
Council
2,004,764 92,951 1,911,813
Severe weather
related cost
reserve
4,244,000 4,244,000
To balance 25/26
Budget 2,952,661 2,952,661 0
Totals 105,161,384 0 0 58,052,979 7,500,918 97,660,466 0

Page 83

Appendix 2
Service
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £
Community Planning 307,672                  121,949                  126,656                  181,016                  -                         
Chief Executive's Unit Total 307,672                 121,949                 126,656                 181,016                 -                         
Commercial Services 1,862,482              13,867                    76,577                    1,483,905              302,000                 
Education 9,775,650              2,496,404              4,274,365              5,213,859              287,426                 
Legal and Regulatory Support 663,875                  48,705                    282,412                  351,183                  30,280                   
Executive Director (Douglas Hendry) Total 12,302,007            2,558,976              4,633,354              7,048,947              619,706                
Customer Support Services 1,681,376              77,481                    619,887                  618,489                  443,000                 
Development and Economic Growth 6,296,428              606,127                  3,472,140              2,466,060              358,228                 
Financial Services 1,406,862              275,494                  799,188                  607,674                  -                         
Roads and Infrastructure Services 13,013,640            72,035                    4,468,424              1,664,018              6,881,199             
Executive Director (Kirsty Flanagan) Total 22,398,306            1,031,137              9,359,639              5,356,241              7,682,427             
Council wide 5,252,661              2,952,661              3,852,661              900,000                  500,000                 
Non Departmental 64,833,188            782,303                  4,323,269              9,296,654              51,213,264           
Other Operating Income and Expenditure 53,892                    53,892                    53,892                    -                          -                         
Non Departmental Total 70,139,741            3,788,856              8,229,822              10,196,654            51,713,264           
Adult Services 13,658                    -                          -                          13,658                    -                         
Social Work Total 13,658                    -                          -                          13,658                    -                         
Total 105,161,384         7,500,918              22,349,471            22,796,516            60,015,397

Page 84

Appendix 3
Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
1 Service Concessions - Priorities Investment Fund (Area Plans)
As agreed by Policy and Resources Committee on 23 October 23 - drawdown of £200,000 from the Priorities Investment Fund to fund two temporary
posts and associated costs to produce meaningful area plans 108,793                 88,115                   20,678                   90,000                   18,793                   -                        
2 NHS Highland and other CPP Partners Contribution Towards
the CPP Running and Project Costs CPP action plan will be finalised qtr 4 and spending happening from then 83,368                   -                         83,368                   -                         83,368                   -                        
3 Community Planning - temp post to support communities Community engagement support spending in 25/26 & 26/27 63,855                   17,850                   46,005                   20,000                   43,855                   -                        
5 Gaelic Development
To fund Gaelic specific work and project work of the Community Planning Partnership including the development of the new 10 year Outcome
Improvement Plan 15,984                   15,984                   -                         15,984                   -                         -                        
7 Recovered unspent third sector grant funding. To be distributed through the Supporting Communities Fund for communities based projects across Argyll and Bute. 672                        -                         672                        672                        -                         -                        
220 NHS Highland and other CPP Partners Contribution Towards
the CPP Running and Project Costs Spending plan as outlined in SLA 35,000                   -                         35,000                   -                         35,000                   -                        
307,672                 121,949                 185,723                 126,656                 181,016                 -                        
307,672                 121,949                 185,723                 126,656                 181,016                 -                        
10
Rothesay Pavilion Charity
Agreed at Council meeting February 2020,Unspent Budget Earmarking 010 of £750k additional revenue support subject to conditions which seek to
minimise the risk to the Council as far as is reasonably practicable including requirement for adequate business and financial management and regular
reporting by RPC.  This funding is to support Rothesay Pavilion Charity in the first 2 years of the building being operational.  Merged September 24 per
Council decision with CHORD earmarking 094 £409k which was about building up a provision towards future Council commitment to provide up to
£150,000 per annum running costs for Rothesay Pavilion.
Additional revenue support subject to conditions which seek to minimise the risk to the Council as far as is reasonably practicable including
requirement for adequate business and financial management and regular reporting by RPC. 1,159,204             -                         1,159,204             -                         1,159,204             -                        
11
Climate Change Programme
At the Council Budget meeting on 24 February 2022, the Council committed to additional investments with £0.500m for Climate Change, building on
previous £1.1m investments, including projects within Argyll and Bute’s schools.  Expenditure in 23/24, draw down in 24/25.
Capital spend agreed to be moved by S Clark and C Earl 302,000                 -                         302,000                 -                         -                         302,000                
13
Energy Efficiency Fund
The Central Energy Efficiency Fund (CEEF) was launched by SG in 2004 to support the delivery of energy efficiency and renewable energy measures.  The
original  allocation of funding was £286k and part of the stipulation of the funding was that any savings from energy efficiencies were reinvested into
the fund in energy efficiency measures.  The terms and conditions attached to the fund expired on 31 March 2016, however there is an expectation that
local authorities will maintain a revolving energy efficiency fund to support future carbon reducing projects. 214,521                 -                         214,521                 -                         214,521                 -                        
14 Commercial Investment Manager post and specialist
consultant technical resource (previously Asset Management
Fund)
The Asset Management Fund has been redirected to Capital going forward but the interest for 2023-24 is to be used towards a Commercial Investment
Manager Post.  This is because funding of £200k from the Asset Management Fund was agreed at ELT in June 22 for the post, along with specialist
consultancy and technical resources  that will be required to support early projects.  The post is now vacant and plans are still to be devised. 79,242                   -                         79,242                   -                         79,242                   -                        
15
Estates - NDR Revaluation Appeals
The Council agreed to make provision to meet the cost of appealing Non Domestic Rates (NDR) revaluations which were imposed from April 2017. The
remaining funds were carried forward to the 2023/24 revaluation cycle however a recent change in position by the Scottish Government may restrict
the appeals which can be made. This is still under discussion and Gerald Eve Surveyors have been appointed as specialist advisers on this matter, who
are progressing 2023-26 appeals. In the event that appeals are limited there may be an opportunity to utilise Gerald Eve for more general valuation
advice subject to Procurement approval. 59,938                   -                         59,938                   50,000                   9,938                     -                        
18
Site Investigation Works
For Site Investigation works and pre-development works exploring and developing commercial opportunities across Argyll and Bute.
Having a procured supplier to provide floor plans at short notice is required to be able to react quickly to requests. If this isn't available Estates would
need to go through the procurement process again which would delay any projects by several months. There isn’t a detailed plan to use this resource it
is more about being able to react quickly and not delay projects. 33,710                   -                         33,710                   12,710                   21,000                   -                        
19
Free Sanitary Provision Scheme
To fund the continued implementation of the scheme through increased provision of reusable products, improved provision in rural communities by
working in partnership with Education and improving the storage of products in toilets so that they are more readily available. A dedicated officer was
appointed in November 2022 to develop the scheme and increase provision across Argyll and Bute including a postage facility. 13,867                   13,867                   -                         13,867                   -                         -                        
Commercial Services Total 1,862,482             13,867                   1,848,615             76,577                   1,483,905             302,000                
9 Digital Projects (Supply Staff Booking System)
To deliver a number of Digital Service Transformation Projects with a commitment of £0.035m towards a Supply Staff Booking system.  Phase 1 of the
project is nearing completion. 5,300                     5,300                     -                         5,300                     -                         -                        
20
EDU - Early Learning & Childcare - 1140 Hours Expansion
The funds will be utilised to improve and expand the Argyll and Bute Early Years Delivery Plan for 1140 hours which will increase access to affordable
Early Learning and Childcare across the Council area. There is a detailed plan of spend which has been shared with S95 officer and Head of Finance.  The
Scottish Government were happy for us to move ahead with plan instead of losing funding.  For 2024-25 the ring fencing has been removed, however
the wording of the letter states funds must still be used for Early Years. 3,906,651             395,258                 3,511,393             811,370                 3,095,281             -                        
21 ASN Review
Transferred from Education to fund ASN review upgrades in Islay High School, Castlehill Primary School, Tobermory High School and Hermitage
Academy 967,574                 -                         967,574                 -                         967,574                 -                        
23
Provision for Learning Estate Investment Programme
At the Council Budget meeting on 24 February 2022, the Council committed to additional investments - £1m to help safeguard and support future
learning for Argyll and Bute's Learning Estate Investment programme. Update: The LEIP funding bid was approved by SG late 2023. Council approval
granted at 25th April 2024 meeting to commence business case, undertake engagement exercises and site selection process. Permission was also
approved for spend up to £5m. 1,000,000             -                         1,000,000             434,000                 566,000                 -                        
25 DSM - Devolved School Management Scheme To be spent in accordance with DSM regulations. 1,205,590             1,205,590             -                         1,205,590             -                         -                        
Chief Executive's Unit
Community Planning
Executive Director (Douglas Hendry)
Commercial Services
Education
Community Planning Total
Chief Executive's Unit Total

Page 85

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
27 100 Day Promise - Increase Teacher and Pupil Support
Assistant Numbers
Scottish Government initiative to increase the number of teachers and support assistants in schools. Required to fund teachers to end of academic year
and beyond. 593,197                 -                         593,197                 93,197                   500,000                 -                        
29
Access to Counsellors in Schools
Government initiative to support delivery of the access to school counselling service, in line with the commitment set out in Programme for
Government. The delivery of the service will enable children and young people to be supported with issues affecting their mental health and wellbeing.
The service is currently seeking the views of head teachers around the need for increased counselling for under 10s.  Service is also engaged in multi-
agency discussions around the development of a single point of access and the School Counselling monies will help support the development of this in
collaboration with HSCP. 275,251                 275,251                 -                         275,251                 -                         -                        
31 Pupil Equity Fund Carry Forward To provide targeted support for children and young people affected by poverty to achieve their full potential.  Funding is used over the academic year. 274,549                 274,549                 -                         274,549                 -                         -                        
32 Additional Support Needs - Additional Support for Learning
Project
Government initiative to support the provision of support staff in schools as part of 'Support for Additional Support for Learning Implementation'. The
funding will be used to supplement the ASN Assistants budget 25-26 by funding additional support need hours required due to a lack of local specialist
provision in some areas, as well as for vital training for visual and hearing impairment specialists which a significant number of Argyll and Bute's children
require. 216,557                 -                         216,557                 216,557                 -                         -                        
35
Strategic Equity Fund
Strategic Equity Funding must provide targeted support for children and young people (and their families if appropriate) affected by poverty to achieve
their full potential, focusing on targeted improvement activity in literacy, numeracy and health and wellbeing. The Strategic Equity Fund Spending Plan
will enhance staffing, provide teacher cover and support to schools not in receipt of PEF funding, to be spent by the end of the 2024-25 academic year. 84,235                   84,235                   -                         84,235                   -                         -                        
36
MCR Pathways Pilot
Funding to support implementation of MCR Pathways mentoring programme within three secondary schools for 2025-26 academic year. Funding will
allow the employment of a dedicated Co-ordinator within each setting to develop and implement the programme which is designed to benefit care
experienced and other disadvantaged pupils through targeted mentoring support. 80,000                   -                         80,000                   -                         80,000                   -                        
37
Scottish Milk and Healthy Snack Scheme (SMHSS)
The Scottish Milk and Healthy Snack Scheme funds a daily portion of plain fresh cow’s milk (or specified alternative) and a healthy snack (fruit or
vegetables) for pre-school children spending 2 hours or more in the care of a regulated day care provider and/or childminders that has registered for
the Scheme.  The unspent grant from 2024/25 will contribute towards the cost of the scheme in 2025/26. 71,846                   71,846                   -                         71,846                   -                         -                        
40 EDU - Music Instructors Scottish Government Initiative to support music tuition. Unspent amount designated for expansion of the service within the 2024/25 academic year. 44,000                   44,000                   -                         44,000                   -                         -                        
41 Youth Music Initiative To fund YMI projects across the remainder of the academic year 2024/25. 40,647                   40,647                   -                         40,647                   -                         -                        
42 Gaelic Specific Grant
Gaelic Specific Grant £30k - This earmarking refers to the Council contribution towards the Gaelic grant for 22-23 and will fund the costs of Gaelic
Language Principal Teacher in 25-26 academic year. 30,000                   30,000                   -                         30,000                   -                         -                        
43 (2023 Digital Projects) Cashless Catering
To support the ongoing implementation of the new cashless catering system during the testing and roll out phase.
£20k released back to General Fund September 24 per Council decision as no longer required. 5,004                     -                         5,004                     -                         5,004                     -                        
46 Scottish Attainment Challenge - Care Experienced CYP
Funding
To provide targeted support for care experienced children and young people to achieve their full potential. The balance funds a Virtual Head Teacher
and Health and Wellbeing Family Support Workers. Earmarked funding is allowing the Virtual HT to create impact both within Education but also to
drive forward work around The Promise across partners and other services. 8,007                     8,007                     -                         8,007                     -                         -                        
53 Play on Pedals
Unspent Play On Pedals grant to allow the procurement of a fleet of cycles and helmets to support delivery across up to 19 nurseries, as well as other
equipment and maintenance. 1,553                     1,553                     -                         1,553                     -                         -                        
54 Food for Thought
Ardrishaig Primary £872 and Gigha Primary & ELC £403 have orders pending and plans for the remaining balance of the Food for Thought Grant.  Will be
spent in 2025-26 1,275                     1,275                     -                         1,275                     -                         -                        
197
Education Network Programme
Council agreed to merge 030/033/034/049 as they all related to the Education Network Programme:
EMR030 - Additional Teaching/Support in Schools/Digital Devices/Family Home Learning Support Fund - Continuation of funding for additional staffing,
teachers, support staff, additional devices for pupils and additional family/home learning programmes. £351k at 31/03/24.
EMR033 - School WiFi Upgrades - To extend WiFi coverage within school settings through the purchase of additional hardware such as access points,
switches and other networking hardware. This will result in more flexible learning spaces and support the growing number of devices within schools.
Project now underway and if budget not fully utilised it is hoped that the balance could be diverted to assist with Capital costs of Education Network
Paper. £167k at 31/03/24.
EMR 034 - Education Transformation Fund - At the Council meeting on 27 February 2020, it was agreed to input £400k into Education Digital Learning. 
The additional funds have been spent in 20/21, 21/22 and 22/23 as part of the ongoing transformation work in the Education service, focussing on
digital and virtual learning technology and the development of learning clusters.  £145k at 31/03/24.
EMR 049 - Skype for Business for Education - To fund the initial capital costs for the implementation of Skype for Business for Education.  This will bring
the Education service in line with other council departments and will improve staff collaboration and modernise school telephony to deliver the  service
more efficiently and cost effectively. £10k at 31/03/24. 612,686                 -                         612,686                 612,686                 -                         -                        
198 ASN Review Upgrades - Capital
Transferred from Education to fund ASN review upgrades in Islay High School, Castlehill Primary School, Tobermory High School and Hermitage
Academy 287,426                 -                         287,426                 -                         -                         287,426                
205 Foundation Apprenticeships Foundation Apprentice Income to cover employee and material costs for remainder of academic year 2024-25 42,582                   42,582                   -                         42,582                   -                         -                        
206 School Meal Debt Grant Scottish Government Grant funding - overpayment received from SG combined with debtors balances yet to be written off 9,774                     4,365                     5,409                     9,774                     -                         -                        
207 Gaelic Learners in Primary Schools 9GLPS)
The Gaelic Learners in Primary Schools grant funding is funding for Tutor costs and online training sessions.  The unspent grant will be utilised in 2025-
26 in accordance to current spending plans. 7,661                     7,661                     -                         7,661                     -                         -                        
208
Bord na Gaidhlig - Gaelic Plans Fund
The Education Service is in receipt of grant funding from Bord na Gaidhlig from the Gaelic Plans Fund.  Within Education the grant is part-funding the
Furan Gaelic Centre and Online Team Teaching.  The Grant Income Profile does not match the Expenditure Profile with the result that surplus funding
from 2024-25 requires to be carried forward to help offset a shortfall in the Grant Income Profile in 2025-26. 2,790                     2,790                     -                         2,790                     -                         -

Page 86

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
209 Raise - Drax Funding
The Drax Community Fund provides small grants and donations of up to £2,000 to support local projects and programmes that deliver social and
economic benefit within the communities where Drax operates. £1,998 awarded, remaining funds, project to June 25 1,311                     1,311                     -                         1,311                     -                         -                        
210 Raise - RSC Funding Royal society of Chemistry for £500, The Inspiring Young Chemist Fund. 184                        184                        -                         184                        -                         -                        
9,775,650             2,496,404             7,279,246             4,274,365             5,213,859             287,426                
57
Meridian BCMS (Business Continuity Management System)
Meridian BCMS (Business Continuity Management System)
For period covering: 19th February 2024 – 18th February 2027
Civil Contingencies System, this earmarking will be used over the next 6 years for maintenance costs for Meridian BCMS 37,376                   19,800                   17,576                   19,800                   17,576                   -                        
58 LRS - Housing Services - Welfare Rights
Grant agreement between the Improvement Service and Argyll and Bute Council for participation in the Welfare Advice and Health Partnerships- ‘Test
and Learn’ Programme 19,535                   19,535                   -                         19,535                   -                         -                        
59
Education Purchasing Officers
The earmarked funds will be used to fund an education purchasing team within the Procurement Service for two years.  The team will embed good
procurement practice, train headteachers on current procurement process requirements, develop spend plans that evidence best value. 210,000                 -                         210,000                 -                         210,000                 -                        
60
CCTV Maintenance
Maintenance of CCTV systems.  Funds transferred from external bodies (Police Scotland) to maintain systems for future years Council Decision of 20
Sept 2007.  Merged with funds from Community Safety Partnership to be used for Community Safety Partnership purposes.
98,426                   2,151                     96,275                   50,595                   47,831                   -                        
61
Information Management (Digitalisation of Title Deeds)
To support a number of initiatives in respect of improving the Council's information management in line with the transformation agenda and increasing
the pace of change as outlined in the BV Review.  The planned initiatives include: Digitalisation of Title Deeds £92k - document management. Staffing
now in place for this project to be completed. 92,000                   -                         92,000                   46,000                   46,000                   -                        
62
Welfare Rights Support
As agreed at the Council Meeting on 25 February 2021 - an allocation of £0.172m.  As part of our focus on Improving Opportunities for People and
Communities, agrees to provide additional resources to proactively support people experiencing poverty and hardship, by investing in two additional
Welfare Rights support staff for two years. 66,728                   -                         66,728                   66,728                   -                         -                        
63
(2023 Digital Projects) Replacement of Council Chambers
Online Meeting Equipment
Current online meeting system is less than resilient and has failed on a number of occasions, leading to issues at strategic committees. A condition
assessment by the incumbent maintenance contractor has highlighted that the current equipment is now at end of life and unsupportable due to the 
obsolescence of the system. Discussions with ICT have taken place to identify a simpler more robust solution to be procured.
NUWAY system and maintenance, system installed, ongoing maintenance contract to 2030 44,718                   7,219                     37,499                   7,219                     7,219                     30,280                  
64 Councillor IT Equipment
There is currently no budget for the provision and renewal of IT equipment for members. The earmarking identifies a resource to utilise spend for that
purpose to ensure that members have continued support in maintaining and replacing vital IT equipment. 44,557                   -                         44,557                   22,000                   22,557                   -                        
66
Debt Counselling & Welfare Rights
To meet the cost of a Debt Counselling and Welfare Rights Management System.
Balance of £15k released back to General Fund per Council decision September 24 and an associated cost pressure built in to 2025-26 budget cover the
routine annual costs. 735                        -                         735                        735                        -                         -                        
211 MS365 Completion of Project Rollout Additional Funding required to complete the MS365 project 49,800                   -                         49,800                   49,800                   -                         -                        
663,875                 48,705                   615,170                 282,412                 351,183                 30,280                  
Executive Director (Douglas Hendry) Total 12,302,007           2,558,976             9,743,031             4,633,354             7,048,947             619,706                
68 Digital Projects (Increase in Schools Bandwidth)
To complete one of a number of Digital Service Transformation projects with a commitment of £0.064m to increase Schools Bandwidth.  Committed for
MS 365 project - D Logan/I Jackson. Paper went to ELT in Dec 24. 63,455                   -                         63,455                   -                         63,455                   -                        
69
Digital Projects (Replacement Learning Management System)
To deliver a number of Digital Service Transformation Projects with an original commitment of £0.030m towards a replacement Learning Management
System £0.030m.  This money will be used to pay for consultancy for an interface between iTrent and totara. Profiled for 24/25 based on decision to do
a phased implementation of itrent. 11,470                   -                         11,470                   11,470                   -                         -                        
71
Microsoft Licensing Costs
To meet  licensing and set-up costs for the Microsoft 365 rollout.  The spend is profiled and reported to MS365 board each month. Currently projecting
£74k 24/25, 272k 25/26, 454k 26/27  but all subject to change if licence upgrades are required for Power BI or Teams Telephony.  The above profile
would mean we will exhaust earmarkings in 26/27 but still expect to have a cost pressure in 26/27 of £27,309 and a much larger cost pressure from
27/28 onwards of at least £377k. Sept 25 update - Theres has been a delay to the Copilot project resulting in a slight reduction in the drawndown for 25-
26.  257,266 is required from earmarkings in 25-26. 726,632                 -                         726,632                 257,266                 469,366                 -                        
72
ICT computer replacement
At the Council Budget meeting on 23 February 2023, the Council committed to supporting the council's digital resilience and overall efficiency with
investment in ICT assets.  £88k will be drawn down in 24-25 for expenditure incurred in 23-24, £323k drawn down in 25-26 for expenditure planned in
24-25 with the balance of £120k drawn down in 26-27.
Capital spend agreed to be moved by S Clark and C Earl 443,000                 -                         443,000                 -                         -                         443,000                
74
Skills Development Scotland
ER074 24-25 -  £151k - We receive the money from Skills Development Scotland (SDS) to enable us to deliver Foundation and Modern Apprenticeship
programmes.  The money covers the salaries of the two Tutors we employ and also any materials we require to deliver the programmes.  Update:  This
is being spent on contract overlaps around the move from Resourcelink, Crown, Iken to ITrent.  Delay in start of project due to resource in ITrent. 
Reprofiled for 25-26.
Agreed by Council September 24 to merge with 085 Establishing HR Service Centre (£14k) - To facilitate the implementation of technical efficiency
improvements and new processes.  This money will be used to support phase two of the itrent project.  Spend reprofiled  following delays in itrent
project.  164,760                 -                         164,760                 164,760                 -                         -                        
75
Growing our Own and Modern Apprentices
Funding earmarked to support trainee development and modern apprenticeship opportunities based on priority workforce risk areas.  A Trainee
Regulatory Services post has been proposed by the manager who was unable to secure a suitable candidate for the original advert. The spend will be in
25/26 once a suitable candidate is in post. Post interviewed for, awaiting references.  Successful candidate unlikely to start before April 25.
Balance of £40k released back to General Fund per Council decision September 24 as only £69k is still required for the intended purpose. 69,150                   -                         69,150                   69,150                   -                         -                        
Education Total
Legal and Regulatory Support
Legal and Regulatory Support  Total
Executive Director (Kirsty Flanagan)
Customer Support Services

Page 87

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
76
Security Operations Centre Subscription
There is a requirement to pay for a 3-year subscription at £60,000 per annum with a cost pressure being added to the ICT revenue budget to cover the
costs from 2026-27 onwards.  Sept 25 update - Invoice for year 3 for Quorum Cyber Security is 42,405.87.  28,782 will be used in 26-27 to offset next
year's expected cost 42,406 plus inflation. 71,188                   42,406                   28,782                   42,406                   28,782                   -                        
77
(2023 Digital Projects) Resilient Website Project
Cybersecurity action to move to a cloud based website platform that would improve resilience and enable service continuity in the event of a cyber
attack.  Procurement in progress for resilient website solution and Scotgov Cloud Services Project providing input. Contract Award expected by end
2023. Procurement in progress for resilient website solution.   Contract Award expected FQ1 2024-5.  3 year contract has been awarded to BigBlueDoor. 
14k spend 24/25, 29.5k in 25/26 and 16.5k in 26/27. 46,000                   29,500                   16,500                   29,500                   16,500                   -                        
78 (2023 Digital Projects) Digital Project Officer
Employ a temporary Digital Project Officer as part of OD changes - additional member of staff required to action changes, unable to recruit so existing
staff increasing hours. 34,121                   -                         34,121                   34,121                   -                         -                        
79
Implementation of Gaelic Language Plan
Agreed at Council Meeting February 2021.  Provision of funding for delivery and implementation of the council’s Gaelic Language Plan in recognition of
the contribution that Gaelic makes to economic growth and to the tourism sector, and to enable delivery of key activities within the plan which
currently receive no revenue funding.  In discussion with Bord na Gaidhlig about a 3-year Gaelic Plan funding programme as opposed to individual grant
applications for specific projects. This earmarking would be used to provide match funding for that 3 year programme of projects.  3 year match funding
approved December 2024.
Sept 2025 confirmed no spending in 25-26, moved on one year 30,000                   -                         30,000                   -                         30,000                   -                        
80
Business Development Training
£27k budget from original Business Development Training earmarking 080 remaining at 31/03/24.  This budget is funding ongoing leadership
development, coaching, action learning sets and commissioned training including Priority Management.
Agreed by Council September 24 to merge with 24-25 EMR 082 - In order to maximise the opportunities and efficiencies of digital learning, this funding
will be used to support the extension of digital learning in order to deliver the Digital Learning Strategy, which was approved in FQ4 20/21. This money
is to support the additional digital learning capacity required to build online elements of AB365 and other key digital learning as we increase our digital
learning offering linked to the digital skills survey and review of corporate training. Delays in recruitment meant this has been reprofiled for spend in
24/25. 11,214                   5,575                     5,639                     11,214                   -                         -                        
81
Bord na Gaidhlig
Grant funding from Bord na Gaidhlig. Ongoing spend ad hoc to deliver on commitments in the Gaelic Language Plan. Grant income from GLAIF
continues to be added to this total and then paid out to projects. Sept 2025 confirmed no spending in 25-26, moved on one year 10,386                   -                         10,386                   -                         10,386                   -                        
1,681,376             77,481                   1,603,895             619,887                 618,489                 443,000                
70 Information Management (Document Management and
Workflow for Planning, Building Standards and
Environmental Health)
Hoping to implement the replacement for IDOX in March 2024 but there have been severe issues/delays with the new programme . 
Dec 24 Project has been scrapped as it was not working. Awaiting procurement to write termination of contract legal documents, until this is completed
we will not know if any further cost are due.
Amount moved to 2026-27 21,177                   -                         21,177                   -                         21,177                   -                        
86
Crown Estates
2024-25 Crown Estates Grant to be spent on a number of projects.
2023-24 grant funding for Coastal Communities Fund (Crown Estates)  Original EMR086- £838k
2022-23 grant funding for Coastal Communities Fund (Crown Estates).  Balance remaining at 23-24 year end £981  (EMR087).  Projects ongoing -
Rockfield Centre (£60k), Campbeltown War Memorial (£17k) and Bowmore Hall (£53k).  The remaining projects are underway with no confirmed spend -
Jura Passenger Ferry (£100k), Pier Feasibility Studies (£100k), Airport Resilience (£100k), Cemetery Maintenance (£300k), Kilmartin Car Park (£50k) and
Electric Charging Points (£200k). 
2021/22 Crown Estate Funding (Coastal Communities Fund) - £857k remaining at 23-24 year end- EMR088).   The remaining projects are underway -
Tarbert Public Realm (£196k - contract in place, spend during 24-25), Kilmory Industrial Estate (£150k - no indication of when will be needed), Rothesay
Kiddies Corner (£44k, no indication of when will be drawn down at present), Jura Community Gigsbit Programme (£50k, no indication of when will be
spent), Dunoon Cycle Bothy (£145k, work ongoing to progress this project, hopefully will be spent 24-25),  Dunoon STEM hub (£150k, work ongoing to
progress this project, hopefully will be spent 24-25), Glenmorag Caravan Site (£100k, works are starting with spend expected during 24-25), £22k
contingency.
2020/21 Crown Estate Funding (Coastal Communities Fund) with  balance at 31/03/24 of £419k 24-25 EMR089).  Remaining balance for Campbeltown
Community Action Plan (£50k), Helensburgh Clyde Street (£350k), Bute Community Land Bike Transfer Station (£10k) Modular Hub Lochgilphead (£5k)
and Tarbert Public Realm (£4k) to be spent in 24-25. 2,776,190             433,808                 2,342,382             1,000,000             1,776,190             -                        
90
UK Shared Prosperity Fund (UKSPF)
2022-23 grant funding for UK Shared Prosperity Fund (UKSPF).  Funding can be spent up to end of March 2025 & 2023-24 grant funding for UK Shared
Prosperity Fund (UKSPF).
spend currently £742K grant of £2.5m received in April, all to be spent by March 2025.
Dec 24 Some projects are currently underspent and any underspent may have to be returned to the Govt. we have been advised a further allocation will
be made in 25/26.
Sept 25 - to be drawn down by end of 25/26 as project ends any unspent funds to be returned to Govt
Year end 24-25
The UK Government have extended the UKSPF for a final, transitional year (2025/26). MoU has been signed for the funding. However, the UK
Government has indicated that, rather than asking for money to be returned, they will reduce the amount they send us in FY25/26  by our underspend
from the 2022-2025 programme, so that it ‘works out’. i.e. we have been allocated c £1.4million for this FY so are expecting roughly the balance based
on the funds remaining in the reserve to be sent to us to fund this years programme. An amount will to remain which is administration funding used
within our team. So effectively we are expecting what you have there to be ‘topped up’ relatively soon and then spent by end of the FY.
2024-25 grant funding for UK Shared Prosperity Fund (UKSPF). 1,079,897             -                         1,079,897             1,079,897             -                         -                        
91 Scottish Government Islands Programme 2023-24 grant funding for Scottish Govt Islands Programme. (Tobermory Housing RGD) 324,085                 74,214                   249,871                 270,045                 54,040                   -                        
92 Place based investment programme
Projects approved at 12 August 2021 P&R Committee totalling £821k, Remaining funds committed. Includes 2023-24 grant funding for Place Based
Investment Programme. 232,779                 31,878                   200,901                 232,779                 -                         -                        
Development and Economic Growth
Customer Support Services Total

Page 88

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
93
Short Term Lets
These monies are to fund the STL licensing scheme until the renewal period of 27/28 as the majority for the licences will have renewal dates of 2027.
There will also be ongoing staffing costs, maintenance fees for ICT systems and ongoing fees associated with short-term let licensing. Income from the
scheme is intended to be directed to delivering the licensing scheme 232,604                 -                         232,604                 -                         232,604                 -                        
95
LHEES (Local Heat & Energy Strategy)
This is used to finance the delivery of the Local Heat and Energy Strategy, involving resourcing a full time member of staff and use of external
consultants.  This is fulfilling a statutory requirement for the Council.  Production of the LHEES will be instrumental in achieving funding for the
decarbonisation of heat and energy use in Argyll and Bute’s Buildings.
SC Update - used to cover any overspend in c centre, underspent at present so most moved to future years 61,105                   -                         61,105                   10,000                   51,105                   -                        
97
Islands Infrastructure Fund
2022-23 grant funding for Islands Infrastructure Fund.
Dec 24 Draw down will be in Q4 24/25
Can be released 35                          -                         35                          35                          -                         -                        
98
Shelter Scotland Housing Funding
Contribution from Shelter Scotland to fund 50% of a 2 year temporary Empty Homes Officer.  Post holder now in place with remainder of costs to be
incurred and earmarking drawn down in 25-26.
Dec 24  Costs partially drawdown remainder by Q4.  Post funded by HSCP in future years 9,373                     -                         9,373                     9,373                     -                         -                        
101
Coastal Communities (Capital)
2020/21 Crown Estate Funding (Coastal Communities Fund) totalling £1.504m. Expenditure/allocation to projects delayed due to covid, now allocated
as per report to P&R on 18 Feb 2021. Projects include Dunoon STEM Hub 100k, Dunoon Cycle Bothy 249k,  Ardrishaig North Project 50k and Arrochar
car park £90k.   Agreed Capital move to 27/28 with C Earl and S Clark 155,219                 -                         155,219                 -                         -                         155,219                
102
Staycation and Marketing Argyll and Bute
As agreed at the Council Meeting on 25 February 2021 with an original allocation of £0.800m.   This will include provision of additional waste disposal
facilities and other facilities that will be informed by the Motorhome and Informal Camping Survey.
As agreed at Council on 24 February 2022, Staycation investment £0.100m.  Augments the 2021/22 £0.5m staycation initiative with an additional
investment of £100k, including support for community groups and partners in the provision of facilities which can support increasing staycation visitor
numbers during the tourist periods. A further £155k committed for 24-25 across Clipper Race (£30k), Road Signs (£50k) and Marketing (£75k). 
Balance of £62k released back to General Fund per Council decision September 24 leaving the balance of £155k which is required for the intended
purpose.
Dec 24 marketing £56250, & clipper both drawn down, roads 50 still in discussions 68,750                   -                         68,750                   68,750                   -                         -                        
104
Lochgilphead CARS
Conservation Area Regeneration Scheme for Lochgilphead  Grants awarded to upgrade conservation areas in Lochgilphead such as shop fronts, town
centre accommodation and other priority buildings. No drawdown required in 23/24 .These are multi year projects with spend generally increasing
towards the end of the project life. Spend committed for 2024-25 and beyond. Project runs until March 2026. 200,000                 -                         200,000                 200,000                 -                         -                        
105 Service Concessions - Priorities Investment Fund (Project
Officer for Housing Emergency)
As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of £200,000 from the Priorities Investment Fund to fund a Project
Officer to assist in accelerating the work of the Housing Emergency.
Dec 24 post holder now in place awaiting further instruction from Budget holder 200,000                 34,806                   165,194                 65,000                   135,000                 -                        
106 Helensburgh CARS
Conservation Area Regeneration Scheme for Helensburgh.  Grants awarded to upgrade conservation areas in Helensburgh such as shop fronts, town
centre accommodation and other priority buildings.  37,486                   -                         37,486                   37,486                   -                         -                        
107
Strategic Events & Festivals
At the Council meeting on 25 February 21, a decision was taken to agree £90k funding for Events and Festivals for 22/23, in order that the application
process can commence during 21/22 and that this agreed figure be augmented by any underspend remaining from the 20/21 financial year.  At 24
February 22, decision made to agree £90k for 23/24, in order that the application process can commence during 22/23 and that this agreed figure be
augmented by any underspend remaining from the 21/22 financial year.  Applications have been received and payments will be made in 23-24. Final
balance (£41,260) to be spent in 24/25 1,460                     -                         1,460                     1,460                     -                         -                        
108
Tackling Digital Exclusion Top-Up Fund
As agreed at the Council Meeting on 25 February 2021  to support communities and in some cases individuals that are missing out on national
programmes due to logistics and economies of scale.  
Earmarking was originally £217,600 but £177,600 has been released back to the general fund.  The  balance is committed  for Mobile Mapping (£25k)
with expenditure expected during 24-25 and the current Kerrera project (£15k) in 25-26. 14,000                   -                         14,000                   14,000                   -                         -                        
109
Economic Development - temp post to support economic
recovery
As agreed at Policy & Resources committee on 9 December 2021, allocation of £0.055m to a post to support the economic and social recovery together
with the building back stronger themes.  To be used to fund Settlement Project Support Officer during 23-24.  Post holder resigned Dec 23.
Dec 24 looking unlikely post will be filled though negotiations still taking place
Year End 24-25
Management decided to carry on with this post for a further year, position is now filled and employment commences  on 2nd June 2025.   We also just
had notification that the SG will contribute £22,500 towards costs to be claimed at end of year 35,895                   -                         35,895                   35,895                   -                         -                        
111
Gypsy Traveller Grant/LACER Funding (Gypsy Travellers)
Local Authority COVID Economic Recovery Fund grant.  This funding would pay for MECOPP (Minority Ethnic Carers of People Project) to engage with
the Gypsy Travellers community on the important subject of the cost of living increases, fuel poverty and the impact of factors such as their remote rural
locations and the facilities available to them for everyday living  have on their livelihoods. This was originally LACER and additional funding routed
through SG for Gypsy Traveller sites received on behalf of ACHA (the sites have been transferred to ACHA). This therefore isn't all a Council budget. The
ACHA element of funding was for site improvements - hence the planned roadway improvements
Sept update - 10k for road improvements to be spent 25/26 (Service think Earmarking is only 10K - a previous value was not drawn down in 22/23)
Year end 24/25 awaiting invoice from ACHA for payment for roadway improvements expected q1 25/26 32,826                   -                         32,826                   10,000                   22,826                   -                        
112
Screen Machine
At the Council Budget meeting on 22 February 2024, the Council committed to a one-off investment of £0.028m to Screen Machine in response to an
external funding request.
Dec 24  Grant offer has now been sent out but payment now not due until Q1 25/26 5,000                     5,000                     -                         5,000                     -                         -

Page 89

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
115
LACER Funding (Sector Support Grant)
Local Authority COVID Economic Recovery Fund grant.  This will provide funding, either part of the small  business development grant or standalone, to
help micros and small business to implement projects that contribute to the sector as well as benefitting the business, for example: Tourism and
hospitality, food and drink or retail.  With option to provide additional business support to hard hit areas including Bute and Kintyre where
unemployment remains higher than average - support via specialist advice, locally tailored grants to meet local priorities and targeted marketing
activity. to be split £115,000 for Shop fronts and £35,000  Business support via Business Gateway. As at 31/03/2024 Shop fronts have £9860 remaining
and Bus support £9050. The Bus support element along with ER refs 122 & 124 (totalling 36130) are to be spent on Digital Reviews as agreed at P&R
committee on 09.05.2024. We expect to commit all the spend in this FY 24-25, but as suppliers are paid for work only after it has been completed, some
of the costs may not actually be defrayed until Q1 25-26
Shop fronts now all spent Business support ongoing 4,606                     702                        3,904                     4,606                     -                         -                        
116
EH Covid Posts
Funding initially for 2 posts for 2 years.  Posts were initially recruited to with one leaving and the other going on maternity leave resulting in delays in
expenditure.  Council agreed September 24 to allow a change of use as unable to recruit to the posts.  To be used to fund additional costs related to the
review and assessment of site investigation reports and provide support to consultants. 13,062                   -                         13,062                   13,062                   -                         -                        
117
LACER Funding (Shop Local)
Local Authority COVID Economic Recovery Fund grant.  This funding would provide funding to continue the Shop Local scheme into 2023/24 and
2024/25, buying additional cards and allow the cards to gather momentum and support local businesses.
Dec 24 spend should be through by Q4 24/25 5,997                     1,200                     4,797                     5,997                     -                         -                        
118
LACER Funding (Small Business Development Grant)
Local Authority COVID Economic Recovery Fund grant.  This funding will provide funding of between £500 and £5,000 to help existing micro and small
businesses to improve their resilience or growth via projects to implement green initiatives, implement digital development, implement marketing
improvements and improve efficiency/innovation. 
This along with ER 115 & 122  (totalling 36130) are to be spent on Digital Reviews as agreed at P&R committee on 09.05.2024 We expect to commit all
the spend in this FY 24-25, but as suppliers are paid for work only after it has been completed, some of the costs may not actually be defrayed until Q1
25-26
Year End 24-25 funds will not all be fully spent until q2 25/26 12,651                   7,919                     4,732                     12,651                   -                         -                        
119
LACER Funding (New Enterprise Support Grant)
Local Authority COVID Economic Recovery Fund grant.  This funding would provide £3,000 grants to help new businesses start up and establish. 
This along with ER 115 & 124  (totalling 36130) are to be spent on Digital Reviews as agreed at P&R committee on 09.05.2024 We expect to commit all
the spend in this FY 24-25, but as suppliers are paid for work only after it has been completed, some of the costs may not actually be defrayed until Q1
25-26
Year End 24-25 funds will not all be fully spent until q2 25/26 12,329                   -                         12,329                   12,329                   -                         -                        
204 Planning Services
Depending on the outcome of a number of S36 Windfarm planning applications, this earmarking will be used to cover consultation advice and a
potential public inquiry if applications are refused. 300,000                 -                         300,000                 150,000                 150,000                 -                        
212 Community Led Local Development 2024-25 grant funding for Community Led Local Development 82,466                   -                         82,466                   82,466                   -                         -                        
213 Empty Business Property Officer To fund Empty Business Property Officer post into 26-27. 73,118                   -                         73,118                   50,000                   23,118                   -                        
214 Addressing Depopulation Fund  - Private Sector Resettlement
Officer To fund Addressing Depopulation post during 25-26. 56,309                   16,600                   39,709                   56,309                   -                         -                        
215 Levelling Up Partnership Funds 2024-25 grant funding for Levelling Up Fund 45,000                   -                         45,000                   45,000                   -                         -                        
221
Short Term Lets
These monies are to fund the STL licensing scheme until the renewal period of 27/28 as the majority for the licences will have renewal dates of 2027.
There will also be ongoing staffing costs, maintenance fees for ICT systems and ongoing fees associated with short-term let licensing. Income from the
scheme is intended to be directed to delivering the licensing scheme 126,109                 -                         126,109                 -                         -                         126,109                
222 Rothesay Pavilion
Additional revenue support subject to conditions which seek to minimise the risk to the Council as far as is reasonably practicable including requirement
for adequate business and financial management and regular reporting by RPC. 76,900                   -                         76,900                   -                         -                         76,900                  
Development and Economic Growth Total 6,296,428             606,127                 5,690,301             3,472,140             2,466,060             358,228                
121
Benefit Admin Grant
Grant monies which would have to be repaid if not utilised for intended purpose.  Benefit Administration activities in the build up to the migration of
Housing Benefit to Universal Credit.  These monies are committed to cover ongoing Benefit Administration activities in 22/23, 23/24 and 24/25 when it
is now expected that the full migration of working age Housing Benefit caseload to Universal Credit will be complete.  Monies will be used to implement
the recommended changes from the recent Revs and Bens BPR including ongoing improvements to the Council's debt recovery policies (£50,000), build
resilience including staff overtime, outsourcing of Housing Benefit processing during the transition and cover casual staff for the Universal Credit
migration (£20,500). Monies also set aside for additional works to the value of £40,000 with the software suppliers around enhancing the Revs and
Bens system, automating processes and transitioning customers to use digital gateways to contact the service. 155,166                 -                         155,166                 20,000                   135,166                 -                        
122
Housing Benefits Private
Specific funding allocation for Housing Benefit including DHP. Funds will be used to continue to support vulnerable people initially financially affected by
the COVID-19 outbreak but now facing the cost of living crisis to sustain their tenancies.  This earmarking will help offset potential overspends in the
DHP/ Scottish Welfare Fund budget going forward. 107,444                 -                         107,444                 50,000                   57,444                   -                        
123
Flexible Food Fund
Financial Insecurity funding from Scottish Government routed into the Argyll and Bute Flexible Food and Fuel Fund (ABFFFF) is aimed at tackling
financial insecurity for adults and families across Argyll and Bute.  Working in partnership with the Community Food Forum, Bute Advice Centre and
ALIenergy, households with low incomes and no access to cash savings can apply for immediate financial support.  The Fund helps support daily living
expenses.   Since inception in January 2021 until March 2023 client gain in extra benefits income for families was £3.8 million with 2,500 families had
been supported. The project has been extended to 31 March 2025 with funding coming from the UK Shared Prosperity Fund and this earmarking to
support it. The Council's Financial Inclusion and Advice Group have proposed that monies from the Flexible Funding for Supporting People at tier 4
COVID earmarking should be used to support this project to ensure it can continue to the contract end date of 31 March 2025. The Scottish Government
have provided this funding and have endorsed this award winning project promoting it as part of the solution to end the need for foodbanks nationally. 22,561                   22,561                   -                         22,561                   -                         -                        
124 Revenue and Benefits BPR  - extra staff to implement savings
targets
On 23 February 2023, the Council agreed to the implementation of savings option FIS2324-002 in relation to the Revenue and Benefits - Income
Generation and Business Process Review.   This included an extra 4 FTE of staff.  Delays in recruitment have caused slippage in the allocated budget for
these posts.  86,955                   -                         86,955                   -                         86,955                   -                        
Financial Services

Page 90

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
125
Cost of Living Payments - Admin funding
Administration funding associated with Scottish Government schemes to issue monies to Low income Households for the Cost of Living Payments. To
provide additional staffing to help with the backlog and to support the administration of the double charges on second homes in 2024/2025. We
continue to receive a large number of enquiries from this customer profile particularly given upcoming changes being made by the Assessor at DABVJB 72,550                   72,550                   -                         72,550                   -                         -                        
126
Flexible Funding for Supporting People while at Tier 4 COVID
Funding from SG to strengthen local authority responses to meet emerging needs and support people in their communities struggling with the
restrictions and guidance at all protection levels re COVID, particularly those at risk through health and social inequalities. This support could cover the
same types of support.  In June 2021 the Council agreed to support 20 projects led by a range of Council officers, officers from the HSCP and members
of the third sector to deliver wide ranging support across our region.  A report will be presented to members in due course. 58,981                   32,000                   26,981                   58,981                   -                         -                        
128
Pandemic Support Payments (CTR - Admin)
Administration funding associated with Scottish Government schemes to issue monies to CTR recipients. Provide additional staffing to support the
recovery from backlog of Council Tax administration caused by Pandemic Support Payment process, further administration duties related to LACER fund
and also to support any further Scottish Government funding initiatives that occur during 24/25 51,968                   51,968                   -                         51,968                   -                         -                        
129 Financial Systems The council is required to implement the IFRS16 Leases accounting standard  from the 1st April 2024. 33,748                   -                         33,748                   33,748                   -                         -                        
130 Accounting and Budgeting Team Resilience
Training and examination fees for 6 staff who are currently undertaking their professional CIPFA/ACCA training.  In addition funding the further training
of 1 of our auditors and providing finance business partner training to a group of our existing professional staff. 36,055                   3,509                     32,546                   8,000                     28,055                   -                        
131 FIS - BEIS Energy Grants
Grant monies which would have to be repaid if not utilised for intended purpose, Additional staff to cover pressures of administering double charge of
council tax in 2nd homes £28k 27,590                   27,590                   -                         27,590                   -                         -                        
132 Self Isolated Support Grant Unspent admin funding for processing Self isolation Support Grants. 5,316                     5,316                     -                         5,316                     -                         -                        
201 Food banks
At the budget meeting in February 2025, it was agreed that general reserve would contribute £5k to each of the 12 foodbanks across Argyll and Bute
and its islands making a total investment of £60k to assist local families in coping with the cost of living pressures 60,000                   -                         60,000                   60,000                   -                         -                        
216 LACER Funding Food banks - make payment to 12 local community food organisations 64,260                   60,000                   4,260                     64,260                   -                         -                        
217
Empty Property Relief
This represents unspent Scottish Government Empty Property Relief monies earmarked as business grant funding to incentivise the regeneration of
business properties within our communities. Although the earmarking appears under Financial Services, the funds will be drawn down by colleagues in
Economic Development to support grant-funded projects. 224,214                 -                         224,214                 224,214                 -                         -                        
218
FIS - Scottish Welfare Fund - Community Care Grants
This balance comprises underspent Scottish Welfare Fund monies from 2024/2025, combined with additional Scottish Government funding received in
February 2024 for SWF activity. We anticipate drawing down circa £200,000 this yearend to cover SWF overspend in 2025/26, and the remaining funds
are likely to be required to support Crisis Grant and Community Care Grant activity in 2026/27. Maintaining current priority award levels within the
Fund is essential to ensuring that individuals can access the support needed to establish and sustain new tenancies. If these monies were instead taken
as savings, the burden of expenditure could transfer to Housing and Social Care Services, as they would need to fund essential household items and
tenancy setup costs. This could slow the transition of individuals from temporary accommodation into permanent housing, leading to additional cost
pressures within core service budgets. 400,054                 -                         400,054                 100,000                 300,054                 -                        
1,406,862             275,494                 1,131,368             799,188                 607,674                 -                        
133
Service Concessions - Biodegradable Municipal Waste (BMW)
Ban
As agreed at Council meeting 23 February 2023 - Ensuring Argyll and Bute is able to better address the challenges faced by a remote/rural/ island region
in complying with the forthcoming national BMW ban.  
Following a project review of the Helensburgh Waste Transfer Station this is no longer going ahead.  The earmarking continues to be required to assist
with the financial pressures in relation to BWW Ban compliance and the end of the PPP contract.  The proposal is to amalgamate this reserve with the
existing waste earmarking, reference 134.
Agreed C Earl and S Clark Capital moved to 27/28 3,500,000             -                         3,500,000             -                         -                         3,500,000            
134
Waste Variation Monies
Waste Variation Monies remaining of  - £1m, to be used to assist with the Council's compliance with the 2026 ban on the Landfill of Biodegradable
Municipal Waste and supporting the overall Waste Strategy)
£990K in 2025-26  consisting of:- Island restoration/capping, waste PPP conversion of sites (including consultants for waste PPP MBT conversion
monitoring and sign off), consultancy costs relating to additional monitoring data for SEPA and Recycling Improve Fund design works.
£10K in 2026-27 consisting of:-  consultancy costs relating to additional monitoring data for SEPA. 1,000,043             -                         1,000,043             1,000,043             -                         -                        
135
Roads Reconstruction programme
At the Council Budget meeting on 23 February 2023, the Council committed to augmenting overall allocation for the roads repair and maintenance
programme with additional funds to bring up to £8m total investment for 2023/24 and 2024/25.  This will be drawn down to the capital plan during 24-
25 and 25-26. Agreed C Earl and S Clark Capital moved to 27/28 1,042,000             -                         1,042,000             0                             -                         1,042,000            
136 Footpath improvements
At the Council Budget meeting on 23 February 2023, the Council committed to providing additional funding for footpath improvements across Argyll
and Bute. Spend forecast for 23/24, draw down in 24/25. Agreed C Earl and S Clark Capital moved to 27/28 219,000                 -                         219,000                 0                             -                         219,000                
137
Vehicle Replacement
Timing delay in fleet replacement causing one-off saving.   Vehicles purchased and received in 22/23 for £174k, draw down to capital will be processed
in 23/24.  remainder has been spent in 23-24 and will be drawn down in 24-25. Agreed C Earl and S Clark Capital moved to 27/28 483,661                 -                         483,661                 0                             -                         483,661                
138 Service Concessions - Priorities Investment Fund (Strategic
Development Framework)
As agreed by Policy and Resources Committee on 15 February 2024 - drawdown of £450,000 to procure consultancy support to assist in driving forward
the Strategic Development Frameworks. 433,804                 72,035                   361,769                 433,804                 -                         -                        
139
Active Travel
At the Council Budget meeting on 24 February 2022, the Council committed to additional investments.  For Active Travel £0.500m for further
improvements for footpaths and pavements and supporting safer routes to schools across Argyll and Bute. Some capital expenditure to be incurred in
22-23 and drawn down in 23-24, remainder planned to be spent in 23-24 and drawn down in 24-25.
Agreed C Earl and S Clark Capital moved to 27/28 181,000                 -                         181,000                 -                         -                         181,000                
141
3G pitches / Tarbert Sports Pitches
In November 2018, the Council agreed to a maintenance funding package to be progressed for a number of 3G pitches including Tarbert. This funding
was proposed to provide an estimated 6.5 years’ worth of ongoing maintenance up to 2025-26. There is the potential to extend the continued upkeep
of the pitches until 2026-27 given the earmarking available will not be fully utilised by the end of 2025-26.  However, there will be potential redundancy
costs for 1 employee that will need to be covered from the remaining balance. Paper on proposed extension to be prepared.
Sept update - Note comment earmark may not be fully utilised 213,769                 -                         213,769                 150,000                 63,769                   -                        
Financial Services Total
Roads and Infrastructure Services

Page 91

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
143
Hermitage Park
The Hermitage Park regeneration project has a significant investment from the Heritage Lottery Fund (HLF) which has a requirement to have a 10 year
Management and Maintenance Plan.  This will be partly funded by existing Council revenue budgets but should also be supplemented by any additional
income which can be generated from park activities.  Part of the HLF conditions are that all income generated by the park should be retained to support
the Management and Maintenance Plan and a result of this requirement, any unspent income generated by the park is retained for future years
requirements. Notification at the start of August 2024 that the lessee of the Pavilion cafe in the park has gone into liquidation.  Awaiting a conclusion
from the liquidators to determine the potential extent of the aged debt to be written off. It is expected the aged debt with be written off in full, a total
of £42.5.  It is anticipated the earmarking will assist with the aged debt write off as well as continue to fund park maintenance.  Should the full £42.5K
be covered by this earmarking it will significantly reduce funding for the Park. This could leave the project in a precarious position going forward.  It
should also be noted that the park has stopped generating income to top up the reserve, given the library and pop up kiosk are currently located in the
Pavilion.  To date the Service have had no update on the timescales on these temporary arrangements. 56,383                   -                         56,383                   30,796                   25,587                   -                        
144 Parking Grant
Grant from Scottish Transport for the assessment of footway parking required under the Transport (Scotland) Act 2019.  Assessment criteria from the
Scottish Gov which will take approx. 12 months to complete throughout 23/24 with work then to follow in 24/25. 50,013                   -                         50,013                   50,013                   -                         -                        
145
Mercury Abatement - Crematorium
Phase 1 and 2 of Cardross Crematorium work completed. Phase 3 of the Cardross Crematorium works commenced April 2024. Delayed by Property
Services in appointing a Contractor. As a consequence the work will not be concluded until 2025-26. These works will ensure DDA (Disability
Discrimination Act) compliance. 14,456                   -                         14,456                   14,456                   -                         -                        
146
Climate Change
At the Council meeting on 27 February 2020, it was agreed to input £500k budget to mitigate the impacts of weather related damage and climate
change with specific emphasis on gully cleaning and drainage improvements.  Spend has been delayed due to COVID and the intention is to spend the
funds on 2 Gully Motors plus staff over next 2 years. Vehicles have been received and budget will be drawn down to cover their cost. The remaining
budget will be used towards running the vehicles. Sept 25 exercise moved on 1 year 40,942                   -                         40,942                   -                         40,942                   -                        
150
Piers and Harbours Investment Fund
Funding generated through increased harbour fees and charges in order to generate funds to meet the costs of the prudential borrowing required to
develop and maintain the Council's harbour assets and infrastructure. Under the Harbours Act 1964, section 42, as a statutory harbour undertaker, the
Council must prepare an annual statement of accounts relating to the harbour activities and any associated activities for each harbour for which it is the
statutory harbour authority. This requirement cannot be satisfied by the preparation of a statement of accounts which relates to other Council activities
in addition to harbour activities.  In essence, any surplus in the Piers and Harbours budget must be reinvested in the marine asset and reflected in
accounts.  Reserve will not be needed until circa 2026-27 when borrowing costs will exceed the additional income received in revenue and reserve will
then be used to pay borrowing costs.
Income from P&H to be used to pay of Prudential Borrowing costs for Harbour Investment Programme.
5,303,977             -                         5,303,977             2,789,311             1,335,720             1,178,946            
151
Weather Incident costs not covered by Bellwin claim.
£839k was set aside at budget meeting ng in February 2024 as part of the unallocated general fund balance workings to cover the weather incident
costs not covered by the Bellwin Claim.  As £641k was utilised during 23-24, the balance of £0.198m is being earmarked for costs expected in 24-25.
Sept 25 - Moved on one year as no weather incident 198,000                 -                         198,000                 -                         198,000                 -                        
199 Cardross Cremator - Capital £26,592 transferred from ER 145 to fund capital cost relating to the cremator at Cardross during 24-25. Agreed C Earl and S Clark move Capital to 27/28 26,592                   -                         26,592                   -                         -                         26,592                  
200 Gartbreck Cell - Capital
£250k transferred from Waste Variation ER 134 to fund capital cost relating to Gartbreck Cell during 24-25. Agreed C Earl and S Clark move Capital to
27/28 250,000                 -                         250,000                 -                         -                         250,000                
13,013,640           72,035                   12,941,605           4,468,424             1,664,018             6,881,199            
Executive Director (Kirsty Flanagan) Total 22,398,306           1,031,137             21,367,169           9,359,639             5,356,241             7,682,427            
202
Top up to Transformation/Spend-to-save fund
In order to support the longer term budget approach it is certain that there will be a requirement for some up-front expenditure which could range
from buying in expertise to challenge the status quo in some service areas, providing seed corn funding for the development of new ways to deliver
services, commissioning business case preparation for opportunities that could deliver savings/increased income in the future and staff time to manage
what is going to have to be a significant programme of transformation/service re-design.  1,000,000             -                         1,000,000             250,000                 250,000                 500,000                
203
Storm Eowyn
The estimated gap for Storm Eowyn was estimated at £0.712m in June 2025.  This gap does not include any costs for Helensburgh Leisure Centre.  On
the basis that the Council will require to undertake a technical assessment that will not be covered by the Insurers like for like cover and in the
knowledge that not all costs incurred by the Council will ultimately be recoverable, it would be prudent to set aside some funding to cover any
additional costs to ensure that the HLC is suitably reinstated for use at the earliest opportunity.  A total earmarking of £1.2m.  1,300,000             -                         1,300,000             650,000                 650,000                 -                        
219 GF - to be used to fund 2025-26 Budget GF - to be used to fund 2025-26 Budget 2,952,661             2,952,661             -                         2,952,661             -                         -                        
5,252,661             2,952,661             2,300,000             3,852,661             900,000                 500,000                
152
Strategic Housing Fund
Accumulation of Council tax collected from the second homes discount on properties is earmarked as part of the Strategic Housing Fund balance.   Plans
in place to utilise £11.472m over the next 5 years to provide affordable housing as part of the Strategic Housing Improvement Plan which will utilise this
reserve as well as future income expected from Council Tax on second homes.
Strategic Housing Fund. Council tax collected during 2024-25 from the second homes discount on properties. Requires to be earmarked as part of the
Strategic Housing Fund balance. 10,141,692           -                         10,141,692           2,000,000             2,000,000             6,141,692            
153
Service Concessions - Learning Estate Investment Strategy
As agreed at Council meeting 23 February 2023 - Signalling council’s commitment to working in partnership to secure new schools for Argyll and Bute,
through substantial investment to support future-proofing of Argyll and Bute’s schools estate. Agreed C Earl and S Clark move Capital to 27/28 8,000,000             -                         8,000,000             -                         -                         8,000,000            
154 Service Concessions - Replace previous loans fund principal
repayment holiday
As agreed at Council meeting 23 February 2023 - The one-off retrospective benefit will be used to replace exercising the principal repayment holiday
that was previously agreed by Council. 5,400,000             -                         5,400,000             -                         -                         5,400,000            
Roads and Infrastructure Services Total
Council wide
Non Departmental
Council wide Total
Non Departmental

Page 92

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
155
Rothesay Pavilion - Capital Spends (previously service
concession)
Original earmarking 155 was called Service Concessions - Rothesay Pavilion but renamed to Rothesay Pavilion - Capital spends.  At Council Meeting
September 24, it was agreed to merge the 4 capital earmarkings for Rothesay Pavilion into one line with the narrative indicating the sources. 
Earmarkings 012, 155, 167 and 170 combined under reference 155.
ER155 - Service Concessions - Rothesay Pavilion £4.772m - As agreed at Council meeting 23 February 2023 - Building on previous commitments to
securing a future for this building of international, national and local significance with additional contribution to the overall funding target which
requires collective action; helping project to progress towards success with funding that supports completion of certain work stages and securing
wind/watertight status.
ER012 - Rothesay Pavilion Essential Repairs £306k - Essential repairs to deal with potential health and safety risks and to avoid further deterioration. 
Budget provision was approved by the Policy and Resources Committee on 21 August 2014.
ER167 - Rothesay Pavilion (Recovery and Renewal Fund)  - £1.360m- As agreed at Council on 24 February 2022, this is provision for future recovery,
regeneration and renewal, as well as any future pressures which may arise following the Covid-19 pandemic through a dedicated Recovery and Renewal
Fund.
ER170 - Underwriting development of Rothesay Pavilion - Funding to meet additional costs identified as necessary for the refurbishment of Rothesay
Pavilion (£1m).
Agreed C Earl and S Clark move Capital to 27/28 7,438,400             -                         7,438,400             -                         -                         7,438,400            
156
Service Concessions - Priorities Investment Fund
As agreed at Council meeting 23 February 2023 - Safeguarding future investment in Priorities for Argyll and Bute by making long-term use of service
concession gain to establish dedicated fund to lever in, secure and support key strategic investments in this year and future years.  Going to P&R for
approval Dec 2025 - 30k for McPool 1,007,000             -                         1,007,000             361,000                 646,000                 -                        
156b Service Concessions - Priorities Investment Fund (Storm Cost
Reserve)
Agreed at Council meeting February 27 2025 - Storm Costs, plus agreed amount in  P&R Paper - 15th August 2024 - Agenda Item 18 as not utilised in
24/25 2,944,000             -                         2,944,000             -                         2,944,000             -                        
156c
Service Concessions - Priorities Investment Fund (Creation of
Business Cases for Future Development of Leisure Facilities in
Dunoon)
Agreed at Council meeting February 27 2025 - Funding allocated towards creation of a business case for future development of leisure facilities in
Dunoon 200,000                 -                         200,000                 200,000                 -                         -                        
156f Service Concessions - Priorities Investment Fund (CHARTS) Agreed at Council meeting February 27 2025  to fund CHARTS - funding capped at 75k 75,000                   50,000                   25,000                   75,000                   -                         -                        
156g Service Concessions - Priorities Investment Fund (AITC) Agreed at Council meeting February 27 2025  to fund AITC 75,000                   18,750                   56,250                   75,000                   -                         -                        
156h Service Concessions - Priorities Investment Fund (Islay Pool) Agreed at Council meeting February 27 2025  to fund Islay Pool 30,000                   30,000                   -                         30,000                   -                         -                        
156i Service Concessions - Priorities Investment Fund (National
Patk) Agreed at Council meeting February 27 2025  to fund National Park 10,000                   10,000                   -                         10,000                   -                         -                        
156j Service Concessions - Priorities Investment Fund (Clipper
Race) Agreed at Council meeting February 27 2025  to fund clipper Race, plus remainder of agreed amount in P&R meeting on 9th May 2024 29,800                   29,800                   -                         29,800                   -                         -                        
157 Service Concessions - Roads Investment to Capital
As agreed at Council meeting 23 February 2023 - Augmenting overall allocation for roads repair and maintenance programme with additional funds to
bring up to £8m total investment for 2024/25.  Agreed C Earl and S Clark move Capital to 27/28 1,246,000             -                         1,246,000             -                         -                         1,246,000            
158 Investment in Affordable Housing Agreed at Council Meeting 11 February 2016.  This balance reduces as the Loans to RSL balances are reducing. 3,024,000             -                         3,024,000             -                         -                         3,024,000            
159
Redundancy Costs
One-off re-profiling gain as a result of the loans fund review to fund known liabilities/cost pressures as agreed at budget setting meeting in February
2020. Future redundancies provision. Given the budget gap over the next 5 years and 61% of our costs being staff costs, redundancy costs are likely to
increase and there is a need to provide for possibility of covering those costs. 2,659,358             480,000                 2,179,358             100,000                 100,000                 2,459,358            
160
Further Capital pressures per budget pack February 22
As agreed at Council on 24 February 2022, a provision for Capital contract increases £3.900m.
£1.133m draw down in 24-25 for Campbeltown Flood plus a further £0.468 for other capital increases.
£0.322m draw down in 25-26 for ICT and £0.279 in 26-27.
Agreed C Earl and S Clark move Capital to 27/28
£0.446m is unallocated 1,302,000             -                         1,302,000             -                         -                         1,302,000            
161
Capital Budget
At the Council Budget meeting on 22 February 2024, the Council committed to allocating released earmarkings amounting to £2.212m towards the
Capital budget.
Agreed C Earl and S Clark move Capital to 27/28 2,212,000             -                         2,212,000             -                         -                         2,212,000            
162
Capital Budget (Previously Asset Management Fund)
At the Council meeting on 22 February 24, it was agreed that the balance in this reserve be allocated to the Capital budget.  Exact profile not known for
the capital projects this will be funding but likely draw down will be 25-26. Agreed C Earl and S Clark move Capital to 27/28 151,190                 -                         151,190                 -                         -                         151,190                
163
Service Concessions - Capital Projects Inflation Pressures
As agreed at Council meeting 23 February 2023 -Boosting resilience of Capital Programme and providing added support as required for key
capital/infrastructure projects - £2m.
Further allocation agreed Council meeting 22 February 24 - increase capital contract earmarking to protect current capital projects in plan £0.297m
Agreed C Earl and S Clark move Capital to 27/28 2,000,000             -                         2,000,000             -                         -                         2,000,000            
164 Pay Inflation Contingency
Negotiations for the 2024/25 pay award are ongoing but initial discussions suggest it will be beyond the 3% increase currently built into the budget
outlook. £1.7m equates to approximately a 1% pay rise therefore providing a contingency at this level is prudent 1,297,550             -                         1,297,550             700,000                 597,550                 -                        
166 Campbeltown Flood Prevention Funding agreed as part of the Loans Fund Review for Campbeltown Flood Prevention.  Agreed C Earl and S Clark move Capital to 27/28 1,331,000             -                         1,331,000             -                         -                         1,331,000            
168 Regeneration and Economic sustainability in Lochgilphead
and Tarbert.
Agreed at Council Meeting 11 February 2016.  £761k will be drawn down in 24-25 to fund prior years expenditure for Lochgilphead Front Green and
Ardrishaig North.  £289k unallocated. Agreed C Earl and S Clark move Capital to 27/28 288,579                 -                         288,579                 -                         -                         288,579                
169 Service Concessions - Priorities Investment Fund (Capital
Programme)
As agreed by Council on 22 February 2024- transfer of £1,028,000 from the Priorities Investment Fund to the Capital plan. Agreed C Earl and S Clark
move Capital to 27/28 1,028,000             -                         1,028,000             -                         -                         1,028,000            
171
Oban TIF (Tax Incremental Financing - Excess NDR)
This is the surplus NDR after paying all Loans Charges in respect of TIF infrastructure projects.  This fund will be used in the future as TIF projects are
delivered.   Discussions in place on future ff the next TIF project (Oban Airport) which will utilise this reserve.  If the project does not go ahead, we will
need to return NDR to Scottish Government 875,651                 -                         875,651                 -                         875,651                 -

Page 93

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
172 Oban TIF
Will be used to fund the TIF Programme office for a further 3 years as well as the programme office for Rural Growth Deal beyond the funding that was
agreed at Council for this in February 2021. 1,526,750             -                         1,526,750             -                         751,929                 774,821                
173 Service Concessions - New refuse collection vehicles
As agreed at Council meeting 23 February 2023 - Enhancing waste and recycling uplift arrangements through placing orders for new refuse vehicles.
Agreed C Earl and S Clark move Capital to 27/28 700,000                 -                         700,000                 -                         -                         700,000                
174
Connect for Success Fund (previously Supporting
Organisational Change) - amended February 24 per ELT)
One-off re-profiling gain as a result of the loans fund review to fund known liabilities/cost pressures as agreed at budget setting meeting in February
2020 - Provision to support organisational change (£0.500m)
It is proposed to supplement the existing 'Supporting Organisational Change' reserve first established in February 2020 with a further £1.2m to enable
the Council to deliver longer term, more fundamental, service redesign which will require funding to support the identification and delivery of  solutions
that take account of future requirements and community engagement and deliver longer term revenue and benefits to the Council
899,721                 65,802                   833,919                 100,000                 406,271                 393,450                
175
Service Concessions - Climate Change
As agreed at Council meeting 23 February 2023 - Continuing our track record of investing in climate change with funding to further enhance school
estate climate change measures, with allocations for primary and secondary schools across the area in Campbeltown, Dunoon, Helensburgh,
Lochgilphead, Oban and Rothesay. Agreed C Earl and S Clark move Capital to 27/28 610,343                 -                         610,343                 -                         -                         610,343                
176
Inward investment Fund
Agreed at Council Meeting 11 February 2016.   Original balance of funding was £833k for Rural Growth Deal - P&R Committee have already approved
spend of £600k leaving a balance of £233k uncommitted. The approved spend consists of consultancy, project development and design and the
remaining £233k will be used for the same purpose to complete design work and get endorsed full business cases to allow RGD projects to commence.
Agreed C Earl and S Clark move Capital to 27/28 441,690                 -                         441,690                 -                         -                         441,690                
179 Capital Inflation cost pressures
Further allocation agreed Council meeting 22 February 24 - increase capital contract earmarking to protect current capital projects in plan £0.297m
Agreed C Earl and S Clark move Capital to 27/28 297,000                 -                         297,000                 -                         -                         297,000                
181 Capital pressure
Pressure identified on the 20/21 COSLA COVID costs spreadsheets - requires to be earmarked to be drawn down when required against the Capital Plan. 
To be incurred during 23-24 and drawn down in 24-25. Agreed C Earl and S Clark move Capital to 27/28 257,000                 -                         257,000                 -                         -                         257,000                
182 Service Concessions - New Jet Patcher Vehicle
As agreed at Council meeting 23 February 2023 - Complementing multi-million pound capital investment in roads repair and maintenance with new jet
patcher order to support delivery of programme.  Agreed C Earl and S Clark move Capital to 27/28 250,000                 -                         250,000                 -                         -                         250,000                
183
Service Concessions - New Road Marking Vehicle
As agreed at Council meeting 23 February 2023 - Completing suite of investments in new fleet procurement, to support delivery of roads repair and
maintenance programme, with order for additional road marking vehicle.  Agreed C Earl and S Clark move Capital to 27/28 230,000                 -                         230,000                 -                         -                         230,000                
184
Information Management (Balance of Funding)
To support a number of initiatives in respect of improving the Council's information management in line with the transformation agenda and increasing
the pace of change as outlined in the BV Review.  This was the balance of funding to explore information management solutions in a strategic and
coherent way £209k.  Committed for MS 365 project - D Logan/I Jackson. Paper went to DMT in Dec. 200,469                 -                         200,469                 200,469                 -                         -                        
185
Levelling up bid costs (Recovery and Renewal Fund)
As agreed at Council on 24 February 2022, Recovery and Renewal Fund £1.547m.  This is provision for future recovery, regeneration and renewal, as
well as any future pressures which may arise following the Covid-19 pandemic through a dedicated Recovery and Renewal Fund.  Commitments have
been made against this fund as follows: Levelling up bid costs £0.150m, Scotland Loves Local overspend £0.037m and Rothesay Pavilion £1.360m. 150,000                 -                         150,000                 150,000                 -                         -                        
186 Engagement with Hub North re provision of services for older
adults and vulnerable people across Argyll and Bute
At the Council budget meeting February 23, an allocation of £0.1m from the Unallocated General Fund balance for the Health and Social Care
Partnership to engage, in partnership with the Council, with Hub North to develop a strategic business case in relation to the provision of services for
older adults and other vulnerable people across Argyll and Bute.  It is intended that this will be spent on an on-going business case and options
appraisal work with Hub and that a sizable proportion will be spent during 24/25 95,005                   -                         95,005                   -                         95,005                   -                        
187
Spend to Save Route Optimisation Software
One-off re-profiling gain as a result of the loans fund review to fund known liabilities/cost pressures as agreed at budget setting meeting in February
2020.  The route optimisation project has been delayed due to staff turnover and absences, recent meetings involving the Council and Routeware have
set out future objectives and the project has been extended to 2025-26. Further delays anticipated due to our GIS system and Routeware system
compatibility issues. 55,484                   -                         55,484                   -                         55,484                   -                        
188 CHARTS
At the Council Budget meeting on 22 February 2024, the Council committed to £0.075m one-off investment in CHARTS in response to an external
funding request will be spent in 24-25. There remains £0.005m from a COVID earmarking for CHARTS as well. 5,000                     5,000                     -                         -                         5,000                     -                        
189
Levelling up Fund bids per P&R February 22
£15k to be drawn down in 2024-25 for post that is currently in place. £55k to be utilised in 2024-25 for Student Summer post, contaminated land
consultants, ICT development, increased costs for current staff on a temp arrangement and to part fund 2 year temporary Regulatory Service Officer
post.
Not all spend has been agreed yet and business cases are pending.
Alan Morrison is budget holder 70,000                   -                         70,000                   70,000                   -                         -                        
190 Scotland Loves Local Overspend (Recovery and Renewal
Fund)
As agreed at Council on 24 February 2022, Recovery and Renewal Fund £1.547m.  This is provision for future recovery, regeneration and renewal, as
well as any future pressures which may arise following the Covid-19 pandemic through a dedicated Recovery and Renewal Fund.  Commitments have
been made against this fund as follows: Levelling up bid costs £0.150m, Scotland Loves Local overspend £0.037m and Rothesay Pavilion £1.360m. 37,000                   -                         37,000                   37,000                   -                         -                        
194b Council Strathclyde Pension Fund Saving 24-25 (£3.75m
allocation to capital plan)
This is part of the revenue budget for 24-25 and is the saving on pension budgets resulting from the drop in employers pension rate.  The total of
£6.875m is split as follows: £2m to balance the budget, £3.75m allocation to capital plan, per budget meeting 22 February 24 and the balance of
£1.125m going towards what will be total of £2m over the two years pot to be directed to transformation and projects that will save revenue in the
future. Agreed C Earl and S Clark move Capital to 27/28 3,361,742             -                         3,361,742             -                         -                         3,361,741            
194c Council Strathclyde Pension Fund Saving 24-25 (£2m to be
directed to transformation and projects that will save
revenue in the future)
This is part of the revenue budget for 24-25 and is the saving on pension budgets resulting from the drop in employers pension rate.  The total of
£6.875m is split as follows: £2m to balance the budget, £3.75m allocation to capital plan, per budget meeting 22 February 24 and the balance of
£1.125m going towards what will be total of £2m over the two years pot to be directed to transformation and projects that will save revenue in the
future. RIS Review £150k 25-26 cost coming from this to 7000000000 1,004,764             92,951                   911,813                 185,000                 819,764                 -                        
196 Capital Plan
At the budget meeting on 22 February 2024, Council agreed to transfer £1.875m from the revenue budget over to the capital plan. Agreed C Earl and S
Clark move Capital to 27/28 1,875,000             -                         1,875,000             -                         -                         1,875,000            
64,833,188           782,303                 64,050,885           4,323,269             9,296,654             51,213,264           Non Departmental Total
Other Operating Income and Expenditure

Page 94

Ref Description Plans for Use
Opening Balance
1 April 2025
Drawndown 2025-
26 as at 31
October
Remaining
Balance as at 31
October
Planned Spend FY
2025-26
Planned Spend
2026-27
Planned Spend
2027/28 onwards
£ £ £ £ £ £
191 Educational Support to Ukrainian Children and Young People
Balance of grant received in 2022-23 for provision of childcare and education support to Ukrainian children and young people. Spending plan includes
teaching and support staff within schools. 53,892                   53,892                   -                         53,892                   -                         -                        
Other Operating Income and Expenditure Total 53,892                   53,892                   -                         53,892                   -                         -                        
Non Departmental Total 70,139,741           3,788,856             66,350,885           8,229,822             10,196,654           51,713,264          
192
See Hear Funding
Funding has been received specifically from the Scottish Government to support activity around implementation of the See Hear recommendations and
the identified priorities of individual Sensory Partnerships. No plans for spend in current financial year, funds will be used in the next two years in
accordance with the See Hear plan and Argyll and Bute's BSL Local plan. 13,658                   -                         13,658                   -                         13,658                   -                        
Adult Services Total 13,658                   -                         13,658                   -                         13,658                   -                        
Social Work Total 13,658                   -                         13,658                   -                         13,658                   -                        
Grand Total 105,161,384         7,500,918             97,660,466           22,349,471           22,796,516           60,015,397          
Adult Services
Social Work

Page 95

Appendix 4
Funding Request – Mid Argyll Community (MAC) Pool 
1. Introduction 
1.1 
1.2 
1.3
Over the last three financial years, both Mid Argyll Community (MAC) Pool
and MacTaggart Leisure Centre, Islay have received additional financial
support from the council, over and above budgeted Service Level Fees.   
As part of the 2025-26 budget process, a number of funding requests from
external organisations were received for consideration.  Members agreed to
fund external funding requests from the Priorities Investment Fund earmarked
reserve, totalling £210k, including £30k in respect of MacTaggart Leisure
Centre, Islay.  At that point, MAC Pool had not been in a position to submit a
detailed 2025-26 funding request within the required timescale for
consideration as part of the budget process, with a newly formed Board in its
infancy.   
As part of the 2024-25 budget process a funding request for £30k was
approved in respect of MAC pool.  A similar funding request for £30k has now
been received for 2025-26.   
2. Mid Argyll Community (MAC) Pool 
2.1 
2.2 
2.3 
2.4 
3. 
3.1 
MAC Pool supports 600 swimmers per week to learn to swim, for recreation,
to keep active and to aid recovery from injury or illness. 
Whilst income from activities is expected to increase year on year, this is not
expected to be sufficient to manage inflationary and other budget pressures. 
Employee costs have increased due to inflation and increases in the national
living wage, and energy costs have also significantly increased over the last
couple of years.   
The organisation has been successful in securing £180k from Heritage and
Islands Enterprise funding to meet the costs of required capital works within
the building and are pursuing other potential funding sources.  However, this
will not provide funding to meet ongoing operational costs. 
Officers have reviewed current year cashflow forecasts and deem the request
reasonable to safeguard service delivery in 2025-26.  In addition, the level of
reserves held is not sufficient to manage recurring budget pressures and
additional funding may also be requested for future years, in order to ensure
that the organisation remains a going concern. 
Conclusion 
Additional funding of £30k in 2025-26 is deemed appropriate to provide
required revenue support for the continued provision of the range of health,

Page 96

3.2
wellbeing, swimming and leisure functions in Mid Argyll.  As such, Members
are requested to approve financial support to MAC Pool in 2025-26 of £30k, to
be funded from the Priorities Investment Fund earmarked reserve. 
Funding requests for future years will require to be considered as part of the
budget process for 2026-27 and future years.