Democracy Spraffa

Supplementary Agenda Pack 1 - Mid Argyll, Kintyre and the Islands Area Community Planning Group 010524

Argyll and Bute Council · 1 May 2024
Back to Mid Argyll, Kintyre and the Islands Area Community Planning Group — 1 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Kilmory, Lochgilphead, PA31 8RT
Tel: 01546605522 
DX 599700 LOCHGILPHEAD
30 April 2024 
SUPPLEMENTARY PACK 1 
MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMUNITY PLANNING GROUP -ON A
HYBRID BASIS IN THE CONFERENCE ROOM, IONAD CHALUIM CHILLE ILE (ISLAY GAELIC
CENTRE), ISLAY AND BY MICROSOFT TEAMS on WEDNESDAY, 1 MAY 2024 at 10:30 AM. 
I enclose herewith Item 4 (b) (Argyll and Bute Climate Action: Developing a Climate Strategy
and Action Plan for Argyll and Bute) and Item 11 (f) (Scottish Canals Update), which were not
included on the original agenda for the above meeting. 
ADDITIONAL ITEMS 
4. CLIMATE CHANGE 
(b) Argyll and Bute Climate Action: Developing a Climate Strategy and Action
Plan for Argyll and Bute (Pages 3 - 6) 
Report by Climate Change Project Manager – ACT Now, Argyll and the
Isles Coast and Country Side Trust (ACT) 
11. PARTNER UPDATES 
(l) Scottish Canals Update (Pages 7 - 10) 
Mid Argyll, Kintyre and the Islands Area Community Planning Group 
Contact: Iona Campbell, Senior Committee Assistant; Tel:  01436 658 801
Public Document Pack

Page 2

This page is intentionally left blank

Page 3

Date: 16 April 2024 
Argyll and Bute Climate Action: developing a Climate Change
Strategy and Action Plan for Argyll and Bute. 
1.0 Purpose 
The purpose of this report is to provide an update on the Community Planning
Partnership’s Argyll And Bute Climate Action project: developing a Climate Change
Strategy and Action Plan for Argyll and Bute. 
2.0 Recommendations 
The CPG is asked to note the approach and status of the project outlined in the
report. 
3.0 Background 
The CPP sub-group working on climate change is known as the Climate Change
Working Group. Its work is currently centred on producing a Climate Change
Strategy and Action Plan for Argyll and Bute. The plan is to be produced by
employing a Climate Change Project Manager to lead on the process. Argyll & the
Isles Coast and Countryside Trust (ACT) are the employing body and the post is fully
funded by the CPP funded from end October 2023 to October 2025.
This update sets out the current position.
4.0 Detail 
4.1 Progress
Following a literature review and a series of meetings with key Community Planning
Partnership and wider regional and national partners, an initial outline strategy was
presented to the Climate Change Working Group meeting of 20 March.
The structure was informed by best and most appropriate exemplars from across
Scotland, and by feedback from Steering Group and wider partner meetings
including the emphasis placed on brevity and avoidance of duplication. Points
discussed at the CWG and subsequently reported to the CPP Management
Committee on 10 April reported included
Page 3 Agenda Item 4b

Page 4

• The strategy is to support partners to identify or create opportunities to meet
existing duties: not a mandate to create new duties
• Outcomes from key national climate strategies have been mapped and aligned
with the three CPP Transport, Housing and Community Wellbeing outcomes.
• The group supported the principle of early production of a strategy paper
describing strategic approach, and then emphasis on development of the action
plan, rather than producing both towards the end of the funded period
• Use existing reporting mechanisms, principally the Public Body Climate Duty
reporting requirements, where possible rather than create new requirements
• Use existing data where possible and work within limitations of trying to fill data
gaps where there are no mandated requirements
• Recognise and work within the limits of the areas where CPP partners have
control and where they can seek to influence. Notably, private sector emissions
may be outwith the scope of influence for the CPP, but it remains important that
businesses can be supported to reduce emissions.
• The proposed national adaptation strategy places high expectations on the role of
communities as part of an overall resilience response.
• Engagement has been predominantly with institutions and key contacts but
working closely with the grassroots engagement programme of the Climate 
Action Network Hub work funded by Scottish Government which has greatly
extended reach. The strategy project is also adding value to the Hub work.
• The project is also collaborating with the CPP workstream developing Area Plans
(working name) 
4.2  Next Steps 
Immediate next steps are:
• Ongoing engagement – noting the importance of engaging with young people
and how branding and identity may support this
• Ongoing engagement in conjunction with Climate Hubs
• Gap analysis, risk and opportunity assessment methodologies with further
guidance from key CPP contacts
• Followed by risk and opportunity assessment workshops, potentially grouped by
CPP Outcomes 
4.3 Governance
The project manager is line managed by ACT and guided and supported by the
project Steering Group, a sub-set of the CPP Climate Change Working Group
chaired by Rona Gold. 
The CPP Climate Change Working Group will moderate its activity while this project
is ongoing, and proposed new Terms of Reference reflect a change of emphasis to
Page 4

Page 5

sharing expertise and knowledge to support the development and delivery of the
strategy. 
The project is working closely with the Argyll & Bute Climate Action Network Hub
(ABCAN), which sits within the wider suite of Act Now climate projects in which ACT
is engaged. The Hub has Scottish Government funding, and is overseen by a
collaboration between ACT, Argyll & Bute Third Sector Interface and Time for
Change Argyll & Bute. 
Andy Macpherson, Climate Change Project Manager 
For more information, please contact:
Andy Macpherson
andy@act-now.org.uk 
Page 5

Page 6

This page is intentionally left blank

Page 7

Crinan Canal planned winter works programme 2023/24 and dummy lock reactive works –
update 
We’re delighted to have reached another milestone in these winter works, rewatering Crinan Basin,
the dummy lock, and the sea lock! 
Our teams are busy with the final pieces of work and site take-down, and we are now on schedule to
reopen the canal on Monday 29th April, a day earlier than anticipated. 
We also look forward to welcoming you to our community meeting this week – please note that this
has moved from today to tomorrow; the meeting will now be on Thursday 25th April, at 6.30pm in the
Egg Shed, Ardrishaig. 
What have we been doing?
At lock 15, the Crinan sea lock, we completed the last of the mechanical and electrical works before
removing the scaffolding from the lock chamber. We also removed the temporary dam upstream of
the lock and completed the repointing work on the back wall in Crinan Basin, below the car park. 
Next, we began dry commissioning the new lock gates and completed snagging works, before
preparing to rewater the basin and the locks. 
Rewatering was completed last week – this was a faster process than last year, as we just had to raise
the water level between locks 13 and 14 by around 1m, before filling the basin, dummy lock, and sea
lock. 
We were then able to use the 130-tonne crane on the over-lock platform to remove the stop planks
downstream of the sea lock. The Crinan Canal operations team transported these via pontoon along
the canal to lock 10, where a smaller crane lifted them out. 
Next, we moved the 130-tonne crane on to the road at Crinan and used it to take apart and remove the
crane platform – this was also transported via the canal to lock 10, with the assistance of the canal
operations team. 
We then began our reinstatement works around the basin, including completing the installation of new
electrical bollards and removing the temporary pedestrian bridge over lock 14. Access has now
reverted to over the lock 14 gates. 
What are we doing now?
Now that the canal is rewatered, we’re carrying out wet commissioning of the new lock gates. 
The team are also progressing with the site take-down; work requiring the 130-tonne crane finished
yesterday, and our temporary road closure alongside the Crinan Basin has now been lifted. 
Page 7 Agenda Item 11l

Page 8

This week, all construction equipment held at the lock 10 car park will be transported to Ardrishaig,
and our site cabins in the Crinan Basin car park are scheduled to be removed. Therefore, please be
aware that the road to and from Crinan will be busier this week with heavy vehicles. 
In addition to works at the sea lock, we also have a team working at locks 12 and 13 at Dunardy,
installing the stone quadrants that are used in operation with the balance beams. These works should
be finished towards the end of next week, and don’t affect the reopening of the canal. 
What will we be doing next?
We will continue the site take-down and continue with reinstatement and landscaping works around
the basin. 
The safety fencing around the dummy lock will remain, so there will be no public access over the
dummy lock. 
Crinan dummy lock – reactive works
We are carrying out a phased programme of works to repair a leak at the Crinan dummy lock, which
was the original sea lock until the 1930s. 
These works are subject to regulatory consent, and thanks to our teams and our partners at Historic
Environment Scotland, we have been able to carry out the first phase of the repair in tandem with the
sea lock gate replacement winter works. 
This first phase of work involved driving sheet piling down into the base of the lock chamber, in front
of the old downstream gates. We then created a berm, or embankment, of stones on the canal-side of
the piling to ensure strength and stability, before pouring a high-strength concrete between the piles
and the old downstream gates. Finally, the piles were cut to size. 
While the first phase of repair works at the dummy lock are complete, there will be return works for
the second phase, therefore some of the reinstated surfaces around the sea lock and dummy lock are
temporary, not the finished surface. 
The second phase of works is not anticipated to require a canal closure, and we’ll share more
information about this as plans and regulatory permissions progress. 
Electricity bollard upgrade works at Bellanoch Marina
The new electrical bollards at Bellanoch have been installed and are now in operation. 
Reopening of Crinan Basin car park, lock 10 car park, and the road beside Crinan Basin
The car park at lock 10 will be open from this Friday, 26th April, and we hope to reopen the Crinan
Basin car park and the lay by alongside Crinan Basin from this Saturday, 27th April. 
As we’ve mentioned previously, we will place temporary traffic barriers along the section of wall that
we removed in the lay by. We will fully reinstate this wall once we have completed the second phase
of works at the dummy lock. 
The temporary road closure alongside Crinan Basin has now finished – this was the final road closure
for these winter works. 
We will provide an update on the reopening of the car parks on our Ongoing Works page on the
Scottish Canals website and on the Crinan Canal Facebook page. 
Keep up to date
We remain committed to keeping local residents, businesses and other stakeholders informed of the
winter works programme, and continue to do so via:
Page 8

Page 9

Email updates
We circulate email updates regularly throughout the works programme; if you would like to receive
these updates, please email CrinanWinterWorks@scottishcanals.co.uk. 
Your details will not be held for any other purpose and will not be passed on to any third parties.
Anyone already signed up to receive Crinan winter works updates will continue to do so unless you
advise us otherwise. 
Community meetings
We will continue to hold our quarterly community forum meetings; the next meeting will be Thursday
25th April, at 6.30pm in the Egg Shed, Ardrishaig. 
Online updates
We continue to share updates on the Scottish Canals website. You can find more general information
and updates about the works online on our Projects page at bit.ly/CrinanWinterWorks23-24. 
We’ll share notice of specific road closures, towpath closures, and diversions, on our Ongoing Works
page at bit.ly/OngoingWorks_CrinanWinterWorks23-24. 
We will also share updates on the Crinan Canal Facebook page and the Scottish Canals’ Facebook
page. 
If you have any concerns during this programme of works, you can the local Scottish Canals office on
01546 603210 (09:00 – 17:00, Mon – Fri) or you can email
CrinanWinterWorks@scottishcanals.co.uk 
Alternatively, you can contact Mackenzie Construction on 0141 633 5555 (08:00 – 17:00, Mon - Fri). 
Yours sincerely, 
Laurie Piper 
Head of Customer Experience
Scottish Canals                     