Caledonian MacBrayne Update – Update on Works at Kennacraig 
Kennacraig works are progressing well with wall construction, fendering and dredging works on the
south berth are taking place concurrently. There is a short pause of dredging works due to the
change of plan from land disposal of dredge material to sea disposal. Nevertheless, the works are
currently ahead of programme and this has been mainly achieved through there being less
requirement to drill intermediate sockets on the South Berth and also by installing the permanent
tubes concurrently with the drilling operations.