Democracy Spraffa

Caledonian Macbrayne: New Islay Vessel Enabling Works

Argyll and Bute Council · 6 November 2024
Back to Mid Argyll, Kintyre and the Islands Area Community Planning Group — 6 November 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

New Islay Vessel
Enabling Works

Page 2

Caledonian MacBrayne Clyde & Hebridean Ferries
Agenda
ØBackground
ØTimeline
ØKennacraig Update
ØColonsay Update
ØPort Askaig Update
ØQuestions

Page 3

Caledonian MacBrayne Clyde & Hebridean Ferries
Background
ØCMAL are required to undertake port enabling works at Kennacraig, Port Askaig and Colonsay to accommodate
the new Islay vessels.
ØThere is a separate project underway for the development at Port Ellen, this is awaiting funding approval.
ØIn conjunction with these works, Argyll and Bute Council (A&BC) plan to modify the layout of Port Askaig to
accommodate the increased capacity of the new vessels (107 PCU).The existing capacity at Port Askaig is 91
PCU.
Vessel Delivery Timeline:
ØMV Isle of Islay is expected to be delivered in Q1 2025
ØMV Loch Indaal in Q2 2025.
ØMV Lochmor in Q3 2025.
ØMV Claymore in Q4 2025.

Page 4

Caledonian MacBrayne Clyde & Hebridean Ferries
Project Timeline
Kennacraig:
Start Date: 13 November 2023​
•South Berth (Linkspan) Closure: Early January 2024 – Mid August 2024​
•North Berth Closure: Mid - August 2024 – January 2025​
•Kennacraig Completion: On track to complete by Spring 2025​
•Kennacraig shall remain open for all scheduled ferry services as 1 berth will always be available​
Port Askaig:
Start Date: 07 February 2024​
•6 Week Closure: 19 June – 30 July 
•Port Askaig Completion: On track to complete by Spring 2025
•All Port Askaig sailings were diverted to Port Ellen during the 6-week closure. The remainder of the works 
at Port Askaig shall be programmed around the scheduled sailings. ​
​
Colonsay
Start Date: 01 April 2024​
•Colonsay Completion: On track to complete by end of November 2024​
•Colonsay shall remain open for all scheduled ferry services as the berth will always be available,
completion is expected

Page 5

Caledonian MacBrayne Clyde & Hebridean Ferries
Kennacraig

Page 6

Caledonian MacBrayne Clyde & Hebridean Ferries
Kennacraig South Berth – Scope of works
• Install temporary fixed ramp profile in advance. This is necessary to improve the reliability of
the ferry service during the period where the North Berth is the only available berth​
• Refurbishment of existing linkspan​
• Construction of new retaining walls in front of existing Wall B (initial section)​
• Construction of new retaining Walls D1 & D2​
• Modifications / Upgrades to existing fenders on all 3 No. dolphins & Infill Pier​
• Dredging ​
• Electrical works to facilitate future shore power for use during overnight berthing
CMAL

Page 7

Caledonian MacBrayne Clyde & Hebridean Ferries
Kennacraig North Berth – Scope of works
•Remove temporary fixed ramp profile and construct permanent fixed ramp
profile 
•Construction of new retaining walls in front of existing Walls A & B (residual
section) 
•Modifications / Upgrades to existing fenders on all 3No. dolphins & Infill Pier 
•Dredging
CMAL

Page 8

Caledonian MacBrayne Clyde & Hebridean Ferries
Kennacraig
Colonsay

Page 9

Caledonian MacBrayne Clyde & Hebridean Ferries
Colonsay Scope of works
• Upgrade of existing fenders and bollards on the Pier – Roundhead. ​
• Dredging 
• Toe reinforcement and scour protection mattress to existing piles​
CMAL

Page 10

Caledonian MacBrayne Clyde & Hebridean Ferries
Kennacraig
Colonsay
Port Askaig
Port Askaig

Page 11

Caledonian MacBrayne Clyde & Hebridean Ferries
Port Askaig Scope of Works
• Remove and upgrade the fenders on the existing quay wall and dolphin 
• Install the foundations for Mooring Aid system located at the Access Deck 
• Electrical works to facilitate future shore power for use during overnight berthing
CMAL
• Increase capacity of marshalling area to accommodate the new vessels
• Re-kerbing
• Line painting
Argyll and Bute Council

Page 12

Caledonian MacBrayne Clyde & Hebridean Ferries
Any Questions?