A83
3 Month "Lookahead"
Programme
North West Bridges/Structures - Please note that none of these are confirmed and most are likely to change, potential dates only
Scheme Name/location Brief Description/TTM Proposed Start Proposed End
A83 110 Aray Bridge Invert Scour - EXTERNAL Temporary traffic lights 02-Sep-24 20-Dec-24
A83 280 W30 Taylor’s Bay Scour Repair Temporary traffic lights 13-Jan-25 31-Jan-25
A83 120 Douglas Water Expansion Joint Replacement- - EXTERNAL Temporary traffic lights 15-Jan-25 07-Mar-25
A83 230 Glenburn Invert Repairs - EXTERNAL Temporary traffic lights 17-Feb-25 14-Mar-25
A83 80 Fyne Joint Replacement - EXTERNAL Temporary traffic lights 17-Mar-25 28-Mar-25
Scheme Name Brief Description/TTM Proposed Start Proposed End
A83 South of Port Ann Works Complete 22-Oct-24 24-Oct-24
A83 Bellochuntay (Argyll Hotel) Works Complete 27-Oct-24 29-Oct-24
A83 Approach to Kilmory Roundabout Works Complete 29-Oct-24 30-Oct-24
A83 Tarbert Works Complete 31-Oct-24 04-Nov-24
A83 South of Tangy Works Complete 05-Nov-24 12-Nov-24
A83 Drishaig to Strone Works Complete 12-Nov-24 14-Nov-24
A83 Honeymoon Bridge Works Complete 01-Dec-24 11-Dec-24
A83 North of Dunderave Works Complete 15-Dec-24 18-Dec-24
A83 West of Ardgartan Surfacing - Closures with Amnesties 14-Jan-25 15-Jan-25
A83 Loch Fyne Spa Surfacing - Closures with Amnesties 31-Mar-25 31-Mar-25
A83 Ardrishaig Surfacing - Convoy working 09-Mar-25 18-Mar-25
North West - Minor Improvement schemes, potential dates
Scheme Name Brief Description/TTM Proposed Start Proposed End
A83 RABT Traffic Management 01-Apr-24 31-Mar-25
A83 RABT Traffic Management 01-Apr-24 31-Mar-25
A83 RABT Traffic Management 01-Apr-24 31-Mar-25
A83 OMR Medium Term Solution
Completion of Old Military road
Improvements, Glen Croe - No TM as off
A83 24-Feb-25 28-Feb-25
A83 Hesco Bund Access and Maintenance
Maintenance of Landslide Mitigation on
Old Military Road, Glen Croe - No TM as
off A83 20-Jan-25 31-Jan-25
A83 RaBT Cabin Pad
Instatlation of base for permanent site of
welfare facilities for ongoing RABT
Monitoring and inspections - No TM as
off A83 18-Nov-24 22-Nov-24
A83 Furnace (Auchendrain) Landslip
Verge and drainage improvements -
TTL's 17-Feb-25 28-Feb-25
A83 RABT Barrier repairs, Ph 4, 7, 2 & 12
Debris Barrier maintenance and repairs -
TM covered by Operational managemnt
above 10-Feb-25 04-Apr-25
A83 RaBT Ph 3 A B Slip
Installation of debris flow barrier - TM
covered by Operational managemnt
above 10-Feb-25 10-Apr-25
A83 RaBT Deer Fencing Assessment - The Paddock
Fence repairs above A83 - No TM as off
A83 03-Mar-25 21-Mar-25
A83 North of Inveraray Sea Wall Repairs Seawall maintenance repairs - TTL's 03-Feb-25 28-Feb-25
North West - Routine footway, signing and drainage schemes, potential dates
Scheme Name Brief Description/TTM Proposed Start Proposed End
A83 Succoth
Repair wall and filterstone repacement /
Lane closure with TTLs 03-Mar-25 14-Mar-25
A83 Loch Fyne Oyster Bar Drainage works 03-Mar-25 07-Mar-25
A83 Ardrishaig Drainage
Essentially a Cat 1 to clear culvert. BT
cable has been inserted into culvert and
we are awaiting removal of the BT cable. 24-Feb-25 25-Feb-25
A83 North Cottage Tayinloan
Installation of kerbing and gullies / lane
closre with TTLs. 17-Feb-25 27-Feb-25
A83 Tabet Hotel Works Complete 06-Sep-24 06-Sep-24
A83 Dalmore Farm Drainage works 13-Feb-25 14-Feb-25
A83 Tarbert to Cambeltown Signs
Replacement of signs and installation of
bollards and VMPs / lane closure with
TTLs. 03-Feb-25 28-Mar-25
North West - Strategic Road Safety schemes, potential dates
Scheme Name Brief Description/TTM Proposed Start Proposed End
A83 22/23 between Clachan and Cairndow signing improvements carry over 16-Sep-24 07-Jan-25
A83 Kilmory Rouundabout Safety Improvements - Signs 10-Mar-25 14-Mar-25
North West Planned Maintenance - surfacing.  Again proposed dates
Traffic Management associated with
Operational Management of Rest and be
Thankful.
Version: 3.0 16/01/2025