Housing Emergency Update

Argyll and Bute Council · 27 August 2025
Back to Mid Argyll, Kintyre and the Islands Area Community Planning Group — 27 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Community Planning
Partnership 
MAKI Area Community Planning Group 
27th August 2025 
Housing Emergency Update 
Summary 
In June 2023 the Council declared a Housing Emergency. There was a stake
holders’ event in November 2023 which resulted in a Housing Emergency
Action Plan being agreed in June 2024. The Community Planning Partnership
is key to bringing forward many of the actions within the Plan. The
Community Planning Partnership Outcomes Improvement Plan has
highlighted housing as 1 main issue to be addressed through the Plan. This
report will highlight housing activity in Argyll and Bute to address the Housing
Emergency and also focus on the actions within the Action Plan of particular
relevance to the Community Planning Partnership. 
1. Purpose    
The purpose of this report is to provide CPG Members with a high
level synopsis of the considerable volume of wide-ranging activity,
which is underway, often well in advance of houses being completed
and handed over, such is the long term nature of development.  This
synopsis is a snapshot of activity in the housing system in the last six
months.     
2. Recommendations    
CPG members are asked to consider the content of the report   
3. Background    
Contained in the Full Report 
4. Detail    
Contained in the Full Report

Page 2

5. Conclusions    
Contained in the Full Report 
6. CPP Outcomes    
Does your report relate to any of the following:    
Outcome Tick as appropriate (🗸)
Community Wellbeing 
Housing  🗸
Transport Infrastructure 
For further information please contact:   
Fergus Murray – Head of Development and Economic Growth
fergus.murray@argyll.bute.gov.uk 
Matt Mulderrig –   Development Policy and Housing Manager 
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte – Team Lead – Housing Strategy                      
douglas.whyte@argyll-bute.gov.uk

Page 3

ARGYLL AND BUTE COUNCIL      MAKI CPG
DEVELOPMENT AND ECONOMIC 
GROWTH    27th August 2025  
HOUSING EMERGENCY UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 In June 2023 the Council’s Environment, Development and Infrastructure (EDI)
Committee declared a Housing Emergency due to a consistent reduction in the
supply of housing, a steady increase in demand for housing across all tenures
and increasing levels of un-affordability. 
1.2 In November 2024, Council agreed an update to the Local Housing Strategy,
incorporating the Housing Emergency Action Plan, and a set of Housing
Emergency Progress Metrics.  It was agreed these would all be reported to
Council annually in November.   
1.3 The purpose of this report is to provide CPG Members with a high level synopsis
of the considerable volume of wide ranging activity which is underway, often well
in advance of houses being completed and handed over, such is the long term
nature of development.  This synopsis is a snapshot of activity in the housing
system in the last six months.   
1.4 Activity includes: engaging directly with Scottish Government; developing
Strategic Development Frameworks to facilitate long-term delivery, securing
national funding investment into housing projects in the area; working towards
delivery of worker housing on Mull,  engaging with infrastructure providers to
provide worker housing; and partnering with RSL’s and community housing
groups to facilitate housing developments. 
RECOMMENDATION 
CPG members are asked to consider the content of the report.

Page 4

ARGYLL AND BUTE COUNCIL      MAKI CPG
DEVELOPMENT AND ECONOMIC     27th AUGUST 2025
GROWTH   
HOUSING EMERGENCY UPDATE 
2.0 INTRODUCTION 
2.1 The purpose of this report is to inform CPG Members on progress made in
terms of the Council tackling the Housing Emergency in Argyll and Bute.  The
last report on this issue was to Council in November 2024 Nov 2024 LHS
Update and Housing Emergency Report .  This report focuses on progress
since that date.   
3.0 RECOMMENDATIONS 
3.1 CPG members are asked to consider the content of the report. 
4.0 DETAIL 
4.1 In November 2024, Council agreed an update to the Local Housing Strategy
Incorporating the Housing Emergency Action Plan, and a set of Housing
Emergency Progress Metrics.  It was agreed these would all be reported to
Council annually in November.  The purpose of this report is to provide CPG
members with a high level synopsis of the considerable volume of wide ranging
activity which is underway, often well in advance of houses being completed and
handed over, such is the long term nature of development.  This synopsis is a
snapshot of activity in the housing system in the last six months.

Page 5

Homes Consented
4.2 From the declaration of the Housing Emergency in June 2023 until the end of
February 2025 the Council granted planning consent for 860 residential units. 
Scottish Government Engagement 
4.3 In November 2024, Members of the Scottish Government,  Local Government,
Housing and Planning Committee, visited Oban.  They met with the Council’s
leader Jim Lynch, CEO Pippa Milne, other senior council officials, and
representatives from the Link Housing Group together with a representative
from the Colonsay Community Development Company. The day also included
a visit to the Dunbeg Corridor housing development.  The Scottish
Government has produced a report of the visit which can be accessed here: 
Scottish Govt Report on Housing Emergency Visit to Argyll and Bute .  A
number of requests and suggestions for Scottish Government were made at the
meeting and these are summarised in appendix 1 to this report. 
Preparing Strategic Development Frameworks
4.4 In January 2025 consultants were engaged, to develop the Strategic
Development Frameworks for Oban (OSDF) and Helensburgh (HSDF).  Both
these are intended to identify long-term 20-40 years strategic development
opportunities.  By doing this we will set a long term framework that can be used
to direct infrastructure investment and create a pipeline of deliverable
development land, particularly housing supply but also other related community,
public service and economic development land.  Initial desk-top and baseline
surveys have been ongoing and the development of preliminary options for

Page 6

assessment.  Early engagement with community representatives, members, and
key stakeholders are planned over the summer months.  These pieces of work
will ultimately feed in to LDP3. 
Securing External Housing Funding Investment
4.5 The Council has continued to develop Business Cases for the proposals for a
worker accommodation pilot on Mull, and market housing for principal home
occupation on Islay.  In addition to the £3m Rural Growth Deal investment
allocated to these projects, the Community Regeneration Fund has potentially
been identified to provide up to a further £5m investment to enabling housing
projects. 
Improving Home Energy Efficiency and Fuel Poverty
4.6 A Local Heat and Energy Efficiency Strategy was approved by Council in
November.  This sets out a policy framework that assists in reducing fuel poverty
in the long term.  Officers will now work to identify deliverable projects, and use
the LHEES to support funding applications.
4.7 The HEEPS:ABS Programme allows homeowners and private rented tenants
to reduce their energy bills, assists with the cost-of-living crisis and reduces
energy consumption contributing to a reduction in climate change   The
Council fully utilised it HEEPS:ABS funding of £1,979,827 for 24/25.  Looking at
the full history of HEEPS:ABS Programmes, from 2013 to Sept 2024, there have
been 4,161 energy improvement measure installations in Argyll and Bute. 
There has been a focus on external and internal wall insulation.  Most of the
properties are owner occupied, many built between 1950 and 1983.  A
significant proportion are in the most deprived areas of Argyll and Bute. Most
properties experience a benefit in their EPC ratings meaning warmer and more
efficient homes.

Page 7

Worker Accommodation from Infrastructure Providers
4.8 Officers continue to work with SSEN to deliver their worker housing strategy in
association with the delivery of the overhead power line projects they have
ongoing.  Principle activity has seen the development of dedicated worker
accommodation being provided at Kilmory Industrial Estate and other locations. 
The effect of this is to significantly reduce the impact on the local housing
market, but also to provide servicing and infrastructure investment in the Kilmory
Industrial Estate.  There is ongoing engagement with SSEN at a Senior
Management level.  One priority begin explored is the potential for further
investment by SSEN in legacy housing, and options are still being explored.

Page 8

Empty Homes for Workers
4.9 Our Empty Homes Officer project, working with the HSCP solely to assist empty
homes owners to bring back properties in to use for HSCP staff has received
national recognition through an award from the Empty Homes Network.  This
project is directly supporting the retention and recruitment of the key workforce
required to sustain essential services and making the best use of existing stock. 
The role has directly enabled homes and bed spaces for use by HSCP workers
on Coll, Tiree, Islay and in Connel.

Page 9

RSL Housing Provision & Pipeline
4.10 ACHA has submitted a planning application for 37 units at Dalintober,
Campbeltown and has programmed a site start by end of 2025 subject to
achieving grant funding. 
4.11 ACHA is negotiating with Islay Estates to unlock delivery of 17 units at Bowmore
Phase 4 which has planning consent.  The Council is engaging with both parties
to identify how necessary infrastructure might be facilitated. 
4.12 ACHA has acquired land in Port Ellen, Islay which was identified in the LDP for
50 units (H3025).  They are now exploring detailed design to identify an
appropriate number of units and efficient use of the site.

Page 10

4.13 ACHA has acquired a site in Glenmachrie, Islay which has potential to deliver up
to 27 units but this density of development needs to be explored with the
planning department. 
4.14 ACHA is pursuing purchase of a site in Tayvallich which is part of H3015 in
LDP2 and has potential to deliver 2 – 4 units.

Page 11

4.15 ACHA is exploring potential acquisition of land in Tarbert on LDP2 allocation
H3024 which has the potential to deliver between 50 and 100 units. 
4.16 ACHA has acquired Tarbert Police Station and are working on designs for
conversion to a 2 bed bungalow. 
4.17 West Highland Housing Association is in the process of delivering 12 social rent
and 4 shared equity units at Port Charlotte, Islay, and completion is planned for
August 2025.

Page 12

4.18 West Highland is developing detailed designs for a further 6 units on the Port
Charlotte site. 
4.19 West Highland has handed over 16 social rent units and 4 shared equity units at
Port Ellen, Islay.  Work is underway to deliver a further 20 units as Phase 5 of
Imeraval, and this is due for completion December 2025.   The Council Roads
Department is engaging with Calmac to facilitate delivery of the necessary road
surfacing materials.

Page 13

4.20 West Highland has commenced advance infrastructure works for 5 units at Port
Mor, Colonsay, and due to complete in October 2025. 
4.21 Fyne Homes has submitted a planning application for 16 units in Inveraray, but
awaits re-design to account for noise mitigation resulting from adjacent BEAR
Scotland depot.

Page 14

4.22 Fyne Homes purchased land for the Baddens Phase 10 development and is
currently pursuing planning consent for 14 units with a programmed completion
date currently being November 2026. 
4.23 Fyne Homes has been granted a planning permission in principle for
development of 55 units at Burns Brae/Wallace Way Lochgilphead.  The site
has been acquired from the Council and detailed designs are being developed.

Page 15

Community Housing Projects
4.24 Colonsay Community Development Company (CCDC) have delivered of a 9 unit
mixed tenure development at Scalasaig (SHF funding and loan included). 
4.25 Isle of Gigha Heritage Trust is close to completion of 5 affordable units at
Ardminish. 
4.26 Colonsay Community Development Company (CCDC) continue to advertise 3
self-build plots.
4.27 Islay Development Initiative is pursuing a variety of housing proposals and the
Council is engaging with them to pull together a single housing document
approach.

Page 16

4.28 Tayvallich Housing Initiative has registered as a Private Landlord and has let
two properties.  They are exploring 3 sites with a potential to deliver 20
affordable homes. 
5.0 Argyll and Bute Outcomes Improvement Plan 2024 -2034
5.1 The Community Planning Partnership has been actively engaged with other
partners in trying to find ways to tackle the Housing Emergency in Argyll and
Bute. The Housing Emergency Action Plan identified several actions which the
CPP can assist with delivering:-
• Freedom to use Scottish Government housing funding more flexibly and
as an allocation within local administrative control
• Create funding mechanisms for Community Housing Trusts to finance
feasibility studies, professional fees and approval processes
• Deliver seasonal and temporary workforce accommodation using short
term occupancy agreements
• Develop a strategic approach to evidencing the need for workforce
housing in the public sector
• Deliver emergency workforce housing options including the use of
modular, temporary and tiny homes
• Identify and map public sector land and buildings which could provide
workforce housing via repurposing and change of use
• Develop a better range if housing options for older people to encourage
movement in existing housing stock
5.2 The Outcomes Improvement Plan produced by the Community Planning
Partnership has Housing as one of the main 3 outcomes which the Partnership
will focus on for the duration of the Plan.
5.3 There will be a CPP Development Day later this year with a focus on housing
and how the Partners can continue to work together to deliver on the actions
within the Housing Emergency and also how Partners can meaningfully deliver
on the fact that housing is one of the 3 main topics within the Outcomes
Improvement Plan.   
6.0  CONCLUSION
6.1 The Housing Emergency was declared due to a whole housing system failure and
addressing the issues behind the failure will take time to address and require a
partnership approach. Members requested periodic update in activity addressing
the Housing Emergency.  This report demonstrates the wide range of actions that
are being taken forward within the context of reduced resources for the delivery
of new homes at a national level.  That said, the council continues to work with
the Government, key agencies such as the Community Planning Partnership and

Page 17

our housing delivery partners to make progress including exploring new methods
and solutions to tackle housing shortages across the local authority area, but
many of these will take time to come to fruition. 
7.0 IMPLICATIONS 
7.1 Policy - the ongoing activity is consistent with current Council priorities and the
Local Housing Strategy vision and outcomes which are directly aligned with
the overarching objectives of the Outcome Improvement Plan – outcome 2:
Housing.  
7.2 Financial - none directly arising from this report but future housing delivery
actions will require additional funding at some stage from the Council and our
partners if delivery is to be accelerated
7.3  Legal – None. 
7.4  HR – None.
7.5 Customer Service – None.  
7.6 Risk - there is a risk of depopulation, damage to the economy a risk to
delivering essential services in the local authority area if partners cannot
effectively tackle the Housing Emergency.
7.7 Climate Change – new housing in the right location helps reduce carbon
outputs when delivered using renewable energy and other measures. Making
best use of existing stock by delivering energy efficiency measures helps
towards achieving climate change targets. 
7.8  Fairer Scotland Duty – Socio-economic Duty – the delivery of housing across
Argyll and Bute facilitates socio-economic opportunities for all. The housing
plans in the report link to the Child Poverty Strategy
7.9 Equalities - protected characteristics - the activity outlined in the report is
consistent with the aims and objectives set out in the Local Housing Strategy
which is subject to an EQIA. There are targets within the housing plans to
deliver housing which meet the needs of specialist groups
7.10 Consumer Duty – none
7.11 Island Communities – many of the housing projects detailed in the report are
being delivered on islands which will provide many benefits such as
employment and the continued delivery of essential services to island
communities.
7.12 Children’s Rights and Wellbeing – the delivery of more housing will enable
more children to have a safe secure environment. The housing plans also
have clear links to the Child Poverty Strategy.

Page 18

Kirsty Flanagan
Executive Director with responsibility for Development and Economic Growth
Councillor Jim Lynch Council Leader and Policy Lead for Housing
July 2025                                                  
For further information contact: 
Fergus Murray – Head of Development and Economic Growth
fergus.murray@argyll.bute.gov.uk 
Matt Mulderrig –   Development Policy and Housing Manager 
matt.mulderrig@argyll-bute.gov.uk 
Douglas Whyte – Team Lead – Housing Strategy                      
douglas.whyte@argyll-bute.gov.uk

Page 19

Appendix 1 
Actions suggested for Scottish Government during meeting with Scottish
Government Local Government, Planning and Housing Committee (Nov 2024) 
Actions suggested for the Scottish Government: 
• Market failure needs intervention and radical thinking, and there needs to be a long-
term and continuous approach to housing. 
• More funding flexibility is required, such as with the housing infrastructure fund (HIF).
Devolution of funding to councils could be considered. 
• The council would like to be able to accrue funds from underspend in the Affordable
Homes Supply Programme (AHSP). 
• There needs to be advance investment in critical infrastructure (such as a new access
road to Dunbeg in Oban). 
• The AHSP Grant Benchmark threshold is too low to buy back properties – there needs
to be a higher % of funding. 
• Community housing trusts are looking to deliver housing, but without expertise in
development they need support and seed funding. 
• Key worker housing is important, and the council needs to be able to provide shorter
tenures and dispose of sites. However, funding through the AHSP and other funds will
not allow this. 
• A pilot of shorter tenures is taking place in Mull, which the council would like to fund
through Resource Planning Assumptions. 
• Regulations on housing and planning need to be more joined-up in order to tackle a
complex system, considering the impact of regulation on the whole system (such as a
possible cladding levy negatively impacting on housing supply). 
• For example, currently an increase in council tax for second homes can be avoided by
property owners registering their main residence in another authority (which is not
charging increased council tax) as their second property; a combined approach across
authorities may therefore be needed.  
• Consideration of a new Planning Use class for ‘non-principal homes’ would augment
provisions for increased council tax, short-term let licensing and planning control areas. 
• Need for compulsory sales orders and for a land and property tax, which could lead to
less people likely to ‘sit’ on land and property. 
The need for flexibility in funding and regulations: 
• With the Rural and Islands Housing Fund completions need to take place pre-election,
which limits the feasibility studies that can be carried out now (as any project is unlikely
to be completed pre-election). This demonstrates the need for long term certainty of
funding, and the hope is that the fund will be reinstated post election. 
• There need to be more flexible grant conditions in the Affordable Housing Supply
Programme and other funds. 
• Important to avoid unintended impacts of legislation e.g.: 
o Infrastructure levy would have negative impact on builds 
o Cladding levy – would be unfair for local developers who haven’t used cladding 
o Passivhaus standard – there are few contractors available, and they would not
go to remote builds. Something instead ‘near’ Passivhaus would be sufficient and
more cost effective.

Page 20

• Investment in renewals and transmission to the national grid could have an impact on
housing – local distribution of renewable energy is needed.