ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND THE      
ISLANDS AREA COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
7 SEPTEMBER 2022 
TARBERT AND LOCHGILPHEAD REGENERATION FUND – PROJECTS UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides an update on the 6 projects which Mid Argyll, Kintyre and
the Islands Area Committee agreed on 6 September 2017 focusing on those
projects which have not previously been reported to committee as complete. 
Lochgilphead Front Green (LA10) 
1.2 The main body of works were completed by 12 August 2022 and the site
reopened that evening. An opening ceremony is planned following completion
but details for this have yet to be agreed. 
1.3 We procured the works at Lochgilphead during a time of considerable uncertainty
with the ongoing Covid pandemic and other changes such as the UK leaving the
EU. In order to protect the Council’s position, the project entered the construction
phase with a considerable contingency allowance attached to anticipated risks.
At the time of writing, we believe that there is likely to be approximately £55,000
of contingency remaining once all costs associated with the project have been
covered, the exact amount cannot be confirmed until all commercial matters have
been settled with the contractor. We are asking Committee to continue with this
pragmatic approach and enable any surplus funding from the Lochgilphead Front
Green Project to be allocated to the Ardrishaig North Public Realm project which
is due to start on site shortly. 
Ardrishaig North Public Realm (LA13) 
1.4 Following appointment of P1 Solutions Ltd as the main contractor for this project
work on site is expected to commence on 29 August 2022. The contractor
indicates that there should be a construction period of eight months. During the
construction period the contractor will minimise disruption as much as possible
but the site will require closure to ensure the safety of members of the public and
site workers. Updates on the project are being issued by email to interested
parties and published on the Council’s website at www.argyll-
bute.gov.uk/ardrishaig/public-realm.

Page 2

Ardrishaig Gleaner Site (LA17) 
1.5 There have been a number of discussions between the Head of Development
and Economic Growth and senior members of Scottish Canals in relation to
Phase 2 of the site and how that could be developed. Whilst there are no firm
proposals at this stage we believe that it is beneficial to retain the allocated funding
against the phase 2 and that proposals will continue to be developed. We are
looking at whether there is an opportunity to gain support for development of this
site through the Rural Growth Deal via the tourism and place element of funding. 
RECOMMENDATIONS 
Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to: 
1. Note the progress made with the projects as detailed within the report; and
2. Recommend to Policy and Resources Committee the transfer of any unspent
funding from the Lochgilphead Front Green project to support the ongoing
delivery of the Ardrishaig North Public Realm project.

Page 3

ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND THE      
ISLANDS AREA COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
7 SEPTEMBER 2022 
TARBERT AND LOCHGILPHEAD REGENERATION FUND – PROJECTS UPDATE 
2.0 INTRODUCTION 
2.1 This report provides an update on the 6 projects which Mid Argyll, Kintyre and
the Islands Area Committee agreed on 6 September 2017 (ratified by Policy and
Resources Committee) should form the Tarbert and Lochgilphead Regeneration
Fund and proceed to full business case. The projects include:  
Project
Ref.
Project  Status
T02 Barmore Road (A83)/Garvel Road junction
improvement
Complete
T11 Tarbert Harbour facilities Complete
LA10 Lochgilphead Front Green Ongoing at time of
writing report
LA11 Argyll Street Complete
LA13 Ardrishaig North Public Realm Improvements Ongoing
LA17  Gleaner Oil Site  Phase 1
complete, phase 2
ongoing 
Whilst some projects have been successfully completed, as agreed, our focus is
now on successfully delivering the remaining agreed projects. The report below
provides an update on the remaining ongoing projects. 
3.0 RECOMMENDATIONS 
3.1 Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to: 
1. Note the progress made with the projects as detailed within the report; and
2. Recommend to Policy and Resources Committee the transfer of any unspent
funding from the Lochgilphead Front Green project to support the ongoing
delivery of the Ardrishaig North Public Realm project.

Page 4

4.0 DETAIL 
Lochgilphead Front Green (LA10) 
4.1 Works started on the Lochgilphead Front Green project on 31 May 2021
following the appointment of contractors Hawthorn Heights Limited in March
2021. During the course of the project, we have been able to add in a number of
elements of the project which were removed during a value engineering
exercise. As works progressed, it became clear that some of the contingency
allocated to identified risks would not be required and as such we were able to
include in the contract the landmark and car parking signage which was
something that members had been keen to see included. We also extended the
natural stone in the square so that it meets the seating wall, this was felt to be
beneficial in terms of long term maintenance, and upgraded the grass works to
the coastal edge from seeding to turf. Additional Town Centre Funding enabled
us to upgrade and extend the A83 footway works and change the surface finish
from resin bound gravel to natural stone to match into the works completed in
Colchester Square and Argyll Street as well as extending works in front of the
public toilets building. All of these works have added additional time to the works
on the Front Green. 
4.2 The project has also been impacted by delays some of which are being widely
experienced across the construction industry and are impacting availability of
site labour, supplies and materials. As a result of the additional works and the
other delays, the completion date for the works moved from the end of January
2022 to 12 August 2022. The majority of the site was reopened to the public on
the evening of 12 August 2022. Some parts of the site were closed off to enable
recently laid turf to establish and the remedial works to the site compound are
still required to be completed, following the removal of site welfare facilities this
part of the site will be seeded with grass which will also require time to establish. 
4.3 An opening ceremony is planned following completion but details for this have
yet to be agreed. A 12 months defects period will follow completion and it is
anticipated that a number of works will be required during this period. 
4.4  A schedule of before and after photographs is included at Appendix 1. 
4.5 The funding allocated for the Lochgilphead Front Green project has enabled us
to attract external funding into the area, for every £1 of funding through the Tarbert
and Lochgilphead Regeneration Fund a further additional 30p of external funding
has been attracted to the project. 
4.6 We procured the works at Lochgilphead during a time of considerable uncertainty
with the ongoing Covid pandemic and other changes such as the UK leaving the
EU. In order to protect the Council’s position, the project entered the construction
phase with a considerable contingency allowance attached to anticipated risks.
As the project progressed, some of the contingency has been expended and, as
detailed above, some of this has been released to enable additional works to be
undertaken. At the time of writing, we believe that there is likely to be

Page 5

approximately £55,000 of contingency remaining once all costs associated with
the project have been covered, the exact amount cannot be confirmed until all
commercial matters have been settled with the contractor. 
4.7 Previously when funding has remained available at the end of a project, it has
been agreed that this should be transferred into other ongoing Tarbert and
Lochgilphead Fund projects to enable them to progress. We are asking
Committee to continue with this approach and enable any surplus funding from
the Lochgilphead Front Green Project to be allocated to the Ardrishaig North
Public Realm project. 
Ardrishaig North Public Realm (LA13) 
4.8 Our previous report on this project identified that we had applied for funding from
Sustrans to help to deliver the works, the project had secured support and funding
from Sustrans for the design works. Unfortunately the funding application for the
construction phase was unsuccessful and as a result of this we were required to
undertake a period of value engineering and reduce the scope of works before
proceeding with the procurement exercise. This exercise was undertaken at a
time of significant volatility within the construction sector with prices for some
items raising exponentially over very short periods of time. 
4.9 In June 2022 we completed the procurement exercise and awarded a contract to
P1 Solutions Ltd. At the time of writing, the preconstruction phase is expected to
extend to the end of August with works on site commencing on 29 August 2022.
The works to be completed are shown on the drawing at Appendix 2. 
4.10 Information from the contractor indicates that there should be a construction
period of eight months and they expect to undertake works commencing in the
garden area between the car parks and working along the waterfront before
moving onto the car park and A83 frontage. 
4.11 During the construction period the contractor will minimise disruption as much as
possible but the site will require closure to ensure the safety of members of the
public and site workers. During the construction period there will be access to the
public toilets and the North Hall. Car parking on the Southern Car Park will be
unaffected however the north car park will be closed and is expected to be utilised
by the contractor for their compound. 
4.12 Updates on the project are being issued by email to interested parties and
published on the Council’s website at www.argyll-bute.gov.uk/ardrishaig/public-
realm. 
Ardrishaig Gleaner Site (LA17) 
4.13 This project is being delivered by Scottish Canals with a grant being provided
through the Tarbert and Lochgilphead Regeneration Fund. Phase 1 of the
Gleaner Site, the award winning Egg Shed, was completed in 2019. The Egg
Shed was recognised by the Royal Incorporation of Architects in Scotland (RIAS)
in their 2021 awards.

Page 6

4.14 There have been a number of discussions between the Head of Development
and Economic Growth and senior members of Scottish Canals in relation to
Phase 2 of the site and how that could be developed. Whilst there are no firm
proposals at this stage we believe that it is beneficial to retain the allocated funding
against the phase 2 and that proposals will continue to be developed. We are
looking at whether there is an opportunity to gain support for development of this
site and the Crinan Canal through the Rural Growth Deal via the tourism and place
element of funding. 
5.0 CONCLUSION 
5.1 Funding through the Tarbert and Lochgilphead Regeneration Fund has
successfully completed a number of projects in Tarbert, Ardrishaig and
Lochgilphead.  The main focus of activity continues to be delivering the remaining
of the agreed six projects with work now focusing on Ardrishaig. There remain a
high number of risks associated with delivery of the remaining projects however
these will continue to be monitored and managed where possible. Should an
underspend remain once the agreed six projects have been completed this will
be reported to Committee so that arrangements can be agreed as to how this
should be allocated. 
5.2 An update on the projects will be made to Committee during 2023. 
6.0 IMPLICATIONS 
6.1 Policy 
The projects will support the overarching objective and long term
outcomes of the Council’s Corporate Plan, Argyll and Bute Outcome
Improvement Plan, the Local Development Plan, the Economic Strategy.
It will deliver the Tarbert and Lochgilphead Regeneration Fund. 
6.2 Financial 
A total of £3 million is allocated through the Tarbert and Lochgilphead
Regeneration Fund. Expenditure at August 2022 is £2,042,863.98
including the grants made for Tarbert Harbour and Gleaner Phase 1 site,
works completed at Garvel Road, Tarbert, Lochgilphead Front Green and
Ardrishaig North Public Realm. 
6.3  Legal 
Working with procurement colleagues in regard to management of
contracts and tendering process. Leases, licences and memorandums of
understanding with third party progressed by the legal team where
necessary. 
6.4  HR 
Support required from colleagues across the Council particularly Roads
and Infrastructure Services who are the asset owners for the Lochgilphead

Page 7

Front Green and Ardrishaig North. 
6.5  Fairer Scotland Duty: 
6.5.1 Equalities - protected characteristics   
Equalities and Socio Economic Impact Assessments have been carried
out. 
6.5.2 Socio-economic Duty  
See above 
6.5.3 Islands 
No impacts anticipated. 
6.6. Climate Change 
Construction works undertaken as a result of the Tarbert Lochgilphead
Regeneration Fund will result in carbon emissions although it is
anticipated that these will be restricted to the construction period. Works
at Lochgilphead Front Green raise the ground level of part of the green
and may offer a form of climate change adaptation. 
6.7 Risk  
There remain a number of risks associated with all the ongoing projects
including those associated with external funding, public perception,
construction working, costs, covid-19 and Brexit etc. Project Risk
Registers are being maintained. 
6.8  Customer Service  
None at this time 
Kirsty Flanagan – Executive Director with responsibility for Development and  
Economic Growth 
Policy lead – Robin Currie 
16 August 2022 
Appendix 1 – Lochgilphead Front Green Photographs
Appendix 2 – Ardrishaig North Public Realm Landscape Plan 
For further information contact: 
Anna Watkiss, Senior Development Officer, Development and Economic Growth, Tel.
01546 604344