Roads and Infrastructure Services Update

Argyll and Bute Council · 7 September 2022
Back to Mid Argyll, Kintyre & the Islands Area Committee — 7 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL                                          MAKI AREA COMMITTEE     
ROADS AND INFRASTRUCTURE                     SEPTEMBER 2022
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 This report format and frequency for these reports were agreed as part of the
previous Council. The purpose of the report is to provide a general update on
key activities of the Service over recent months and to enable a discussion on
key, high level topics and projects. As part of developing future committee
structure and workplans the purpose and effectiveness of this standing item
should be reviewed. 
1.2 As part of the normal course of business we provide all members with regular
weekly briefings on topical projects and ongoing service delivery. We have been
doing this weekly for over 60 editions now and these prove to be a useful tool for
regular service updates. They are all available as part of the wider resource
portal on the Member Zone system which also includes specific topic briefing
sheets and key policy documents. We are also in the process of developing a
seminar programme on specific topics which we are hoping to make as
interactive as possible with various site visits.     
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Area Committee note and consider the contents of this
report, and provide feedback on the content, format and frequency. 
3.0 DETAIL 
COVID Absence/Resource Availability 
3.1 For the period of the previous report two reports in March then June absence
rates as a result of self-isolation requirements remained high in the case of the
former report and tapered down more in line with pre-COVID trends in the latter
report. This remains largely the case, and absence levels continue to be in line
with pre-COVID trends, although there do remain a few isolated absences
attributed to COVID, the overwhelming percentage of absences are non-COVID
related 
3.2 A more pressing issue in terms of resource availability is around recruitment

Page 2

particularly for manual roles in our Operations team. We are finding that we are
having to go out three or four times for some posts, and even then we continue
to have some long-term unfilled vacancies. At the time of writing this report
there are 18 vacant posts which we are trying to recruit to in our Operations
team. Even in the posts we are successfully recruiting to, we are finding that
we have far fewer applicants than we would have done for similar posts
previously. 
Capital Roads Reconstruction Programme 
3.3 The focus of the roads reconstruction programme is to recover the network
through the delivery of a mix of carriageway resurfacing schemes,
patching/surface dressing and in-situ road surface recycling, which follow the
principles set out within the Roads Asset Management Plan. 
3.4 This Council has approximately £100M of backlog maintenance in the road
network. This means that over £100M would need to be invested to bring the
road network up to an A1 standard. Most councils are in a very similar position.
Clearly in the current financial climate we are not going to see the level of
investment required to bring the road network up to an A1 condition. However,
over the last decade there has been a carefully applied strategy of delivering
revenue and capital funding collectively and delivering a series of works
designed to minimise reactive work, carry out right first time repairs wherever
possible and to deliver surfacing techniques and specifications which
maximizes the amount of repairs and resurfacing which is delivered. As with
almost all council services there is insufficient funding available to treat all the
sections of road that we’d like to do, the focus being on treating sections where
we can maximise the financial return and in so doing reduce the amount of
reactive repairs varied out. Unfortunately, the available funding means that
almost all roads authorities, including Argyll and Bute, are unable to treat every
section of road they would like to do.  
3.5 The total programme for this financial year for roads reconstruction is £8million
Council capital allocation and £1.6million from the Strategic Timber Transport
Scheme, which is used to match fund existing schemes on the council network
where timber extraction is programmed to be carried out. 
3.6 Oil and bitumen prices have increased significantly this year, and the situation
with costs is highly fluctuating.  Coated roadstone used for surfacing our road and
footways has increased by approximately 20%. This will impact our programmes
of work. A report detailing the implications of the recent price increases was
presented to the June ED&I Committee. 
3.7 The Council capital allocation for the MAKI area is £2,621,610, and the scheme
list is available on the Council website here. As well as the programme itself, the
online resources include financial values and short explanations of engineering
methods/solutions.   
3.8  Overall progress with the programme has been excellent and works remain on
schedule. As well as the full programme [link above] which is updated monthly,

Page 3

we provide weekly updates on schemes via our weekly briefing. At the time of
writing this report 39 of the 49 individual schemes in MAKI have been completed. 
Winter Maintenance  
3.9 The annual winter policy update is being reported to EDI in September. The
proposed policy is largely unchanged from previous years and should it be agreed
it will form the basis of the delivery of our winter maintenance activities over winter
22/23.   
3.10 A key aspect of the winter service is the provision of public information on what
we do and why we do it. There is a range of online resources available on the
Council website here. 
Campbeltown Flood Prevention Scheme 
3.11 We have been providing regular updates o this scheme through previous EDI
reports, various press releases and coverage in several editions of our weekly
briefings. In summary, a contractor, Dawson WAM, has been appointed to deliver
the scheme. We expect that by the time this report is considered at Committee
the contractor will have mobilised to site and set up or be setting up their site
compound. We have prepared a specific webpage for the scheme which is
available here. The webpage has helpful background information in a FAQ-type
format, and it will host regular monthly project updates. There is an option for
anyone interested to sign up to an email mailing list to have these monthly updates
sent on to them directly. 
3.12 At the time of writing this report we are finalising with the contractor a programme
of pop-up information events where members of the project team will be on hand
to give an overview of the project and to answer any queries from residents,
businesses etc. 
3.13 We are planning to arrange a specific session for local members with the
contractor and project team including a site walk-round and project overview. At
the time of writing we are aiming to have this session at some point in September
once the contractor has mobilised to site. 
3.14 This is an exciting scheme which will see major works at various areas throughout
the town, all progressing with a view to addressing long-standing flooding issues.
The nature of some of the works is such that they will cause disruption – we are
hoping to keep that disruption to a minimum and crucially, to provide good, early
information to people about what is planned for when, and how it will affect them. 
Gartbreck landfill cell works. 
3.15 In our weekly briefings editions 61 and 62 we provided the following updates on
these important works: 
Islay’s Gartbreck landfill site cell extension is nearing completion. This will provide
landfill capacity to the start of the Biodegradable Municipal Waste (BMW) landfill

Page 4

ban together with capacity for non BMW material beyond the ban and a further
update following last week’s update – we now expect these works to be complete
by the end of the month. As a community benefit through the project, the
contractors are donating £1200 to Gortonvogie Residential Home.  
3.16 At the time of writing this report the above remains the positon – by the time of the
committee we would hope to be able to provide a further verbal update   
Play Park Funding 
3.17 Funding of £76,000 was allocated in financial year 21/22, with a further £79,000
this financial year. In order to provide for a meaningful programme of improvement
works targeted at the high priority sites, as well as a works package with is
attractive to what it is a limited supplier/contractor market, the funds have been
rolled together into a single package. Sites were given a priority rating based on
asset inspections and feedback form the Youth Forum, in compliance with the
Scottish Government’s grant requirements. The full list of prioritised sites was
reported to EDI in June and is available here. In this area the priority sites are
Ardrishaig KGV and Tarbert. .   
3.18 An update on this was recently provided in the weekly briefing [Edition 61 5th
August] which read: The recent tender process failed to generate any bids. We
requested feedback as to why there were no applications and we were advised
that the timescales for completion of work were too short. A request for more time
to complete was made and this is currently being assessed by our procurement
team. A further re-tender process will be looked at this month. 
3.19 A further update will be provided on this at the Committee meeting.   
Bridge Maintenance 
3.20 The Infrastructure Design team continue to carry out bridge inspections to all
approx 900 structures on a rolling programme across Argyll and Bute to ensure
they are safe and fit for purpose. This inspection regime identifies necessary
remedial works which are programmed for delivery. 
3.21 The team were also successful in a highly competitive bidding process for the
Scottish Government’s £32million Local Bridge Maintenance Fund, receiving a
funding award of £5,5million. The fund will be used to undertake proportionate
works on bridges in need of repair, identified through our inspection
programme/records. 
3.22 There are four schemes identified in this area, a £40,000 scheme at Archonnell
Bridge on the B840, which has an indicative siteworks start date of December
2022; a £477,000 scheme on Claonaig Bridge on the B839, which has an
indicative siteworks start date of June 2024; a £597,000 scheme at Glenegadale
on the A846, with an indicative start date of June 2023; and a £40,000 scheme at
Whitestone Bridge on the B842, which has an indicative start date of December
2022. More details on these schemes will follow as the projects develop. The

Page 5

indicative programme for this fund for the whole Council area was reported to EDI
in June and is available here. 
4.0 CONCLUSION 
4.1 This report provides a general update to local members on recent Roads and
Infrastructure activities. 
5.0 IMPLICATIONS 
5.1 Policy – various policies referred to within the body of the report 
5.2 Financial – none 
5.3  Legal – the Council has various statutory obligations which are the
responsibility of RIS and set out in various Acts, such as the Roads Scotland
Act 1984. The services provided are in line with our statutory obligations 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known 
5.5.2   Socio-economic Duty – none known 
5.5.3 Islands – none known 
5.6. Climate Change – none 
5.7  Risk – none known 
5.8  Customer Service - none 
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan 
Policy Lead for Roads and Transport
Councillor Andrew Kain 
August 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services; or Mark Calder, Project
Manager