ARGYLL AND BUTE COUNCIL                                         MID ARGYLL, KINTYRE
AND THE ISLANDS AREA
COMMITTEE     
ROADS AND INFRASTRUCTURE                  07  DECEMBER 2022
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 A Roads and Infrastructure standing report was a fixture on Area Committee
agendas throughout the life of the last Council. In the first two rounds of Area
Committee meetings in the new Council feedback was sought on the value of
these updates, and their format and frequency. Generally Members felt having a
standard item was beneficial and it was acknowledged that the Roads and
Infrastructure weekly briefings issued to all members each Friday afternoon
provide for the main sources of live information on current activities. On top of
these briefings there is a bank of resources on the new Member Zone system
which include the weekly briefings, subject specific briefings, ad hoc short
briefings on issues, relevant previous committee reports, operational service
procedures, legislation and Council policies. 
1.2 In the last Council the purpose of these reports was to provide an update on
service activities but since weekly briefings were introduced around 18 months
ago [at the time of writing this report we are on to briefing Edition 72] these have
largely superseded the original stated purpose of these reports. 
1.3 On the basis of the above a new format is proposed for these standing area
committee reports which removes duplication for Officers and rather links to
existing published information, with additional updates only in the body of the
reports if these are specifically requested/noted from previous meetings. The
report remains as a standing item and continues to provide the opportunity for
Officer engagement at the committee meetings. 
2.0 RECOMMENDATIONS 
It is recommended that the Area Committee: 
2.1 Note and consider the contents of this report, and provide feedback on the
proposed new format.

Page 2

3.0 DETAIL 
3.1 Roads and Infrastructure Services provides Members with weekly briefings on
topical service activities which are all available here.   
3.2 As part of the resources on the new Member Zone system there are various key
documents available in an online library here. 
3.3 The recent consultation on future options for Burnside Square had 569 responses
which provided following the £15million Campbeltown Flood Scheme provided
the following results: 
Flexible space 275 48%
Car park 51 9%
Events space  232 41%
Other  11 2% 
3.4 Officers met with South Kintyre members in Campbeltown on 8th November to
discuss next steps. Following that meeting the following design outline statement
is proposed for Burnside Square: 
We agreed to a general statement of intent for the space, which was:- 
Burnside Square is a flexible public events space, and when not being used for
events it is a public car park. 
3.5  In terms of specific features, we agreed to ask our designers to explore the
following options, while noting that we need to give due regard to any
technical/engineering necessities arising from the underground flood attenuation
tank. 
Possible features:
 Retain the existing car park access as an entrance only and add a new exit onto
Union Street, with the car park therefore operating on a one-way basis
 Remove the existing planters and do not replace them. This was on the basis that
space can then be maximised for community use. 
 Install an appropriate number of poles around the Square to facilitate community
decorative lighting and hanging baskets. Explore the possibility of electricity points
in or at some or all of these poles. POST MEETING NOTE – the existing amenity
heritage lighting columns around the square appear to be suitable for this
purpose. Subject to design checks these columns will be used for this purpose.
 Sensitively block off vehicular access to Harvey’s Lane and Cross Street
 Maximise the available width in the pedestrianised areas for the businesses on
those streets to have outdoor seating while still providing a pedestrian walkway –
this effectively provides similar width of pedestrianised area on both sides of the
square. 
 Install tie down points around the perimeter of the square for gazebos/stall for
events.

Page 3

 Have a surface which is aesthetically as near to like for like as is reasonably
practical
 Remove car parking from the centre of the car park – car parking spaces only
around the perimeter. This was on the basis that the pedestrianised areas would
be widened slightly, and also to allow the car park to work better/more safely.
Exact number of spaces this would allow for to be confirmed. Note the existing
arrangements is considered to be too tight for central parking, the widening of the
pedestrianised area reduces the central width further.
 Install specific disabled spaces at the Union Street side of the car park as an
appropriate proportion to the number of overall spaces. 
 Look to move the palm trees from the square to a local public site yet to be
confirmed – accepting that it is not possible to guarantee that the trees will survive
although reasonable endeavours will be made to preserve the trees.
 Offer the cherry trees to any organisation/local group who wishes to attempt to
replant, subject to the organisation/group organising transport and planting. 
In addition it should be noted that there will be the need to have a height restriction
barrier at the access points to ensure that no unauthorised heavy vehicles can
drive onto the square. We are investigating options for these to ensure they are
in keeping with the setting and that they can be opened/removed as necessary in
case any event organisers hosting events have high sided vans/trucks etc. 
3.6 The above noted design outline is not expected to have any budgetary implication
for the project – there is an existing pack of engineering drawings which formed
the basis of the tender and have been priced for and costed into the overall
budget. The above noted changes are superficial in design/budget terms but will
provide for an enhanced space for use of the community to support local events
while maintaining car parking options when not in use as an events space. 
4.0 CONCLUSION 
4.1 This report provides links to existing published information on service activities
and provides for the opportunity for Officer attendance and engagement at
committee meetings. 
5.0 IMPLICATIONS 
5.1 Policy – none 
5.2 Financial – none 
5.3  Legal – none 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known

Page 4

5.5.2   Socio-economic Duty – none known 
5.5.3 Islands – none known 
5.6. Climate Change – none 
5.7  Risk – none known 
5.8  Customer Service - none 
Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
November 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services; or Mark Calder, Project
Manager