ARGYLL AND BUTE COUNCIL                              MID ARGYLL, KINTYRE AND THE
ISLANDS AREA COMMITTEE                                                                                                         
ROADS AND INFRASTRUCTURE                                       6 DECEMBER 2023
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 A Roads and Infrastructure standing report was a fixture on Area Committee
agendas throughout the life of the last Council. In the first two rounds of Area
Committee meetings in the new Council feedback was sought on the value of
these updates, and their format and frequency. Generally Members felt having a
standard item was beneficial and it was acknowledged that the Roads and
Infrastructure weekly briefings issued to all members each Friday afternoon
provide for the main sources of live information on current activities. On top of
these briefings there is a bank of resources on the new Member Zone system
which include the weekly briefings, subject specific briefings, ad hoc short
briefings on issues, relevant previous committee reports, operational service
procedures, legislation and Council policies. 
1.2 In the last Council the purpose of these reports was to provide an update on
service activities but since weekly briefings were introduced around 18 months
ago (at the time of writing this report we are on to briefing Edition 121) these
have largely superseded the original stated purpose of these reports. 
1.3 On the basis of the above this new format has been agreed through the
December 2022 round of area committees for this standing item. This format
removes duplication for Officers and rather links to existing published
information, with additional updates only in the body of the reports if these are
specifically requested/noted from previous meetings. The report remains as a
standing item and continues to provide the opportunity for Officer engagement at
the committee meetings.   
2.0 RECOMMENDATIONS 
It is recommended that the Area Committee: 
2.1 Note and consider the contents of this report.

Page 2

3.0 DETAIL 
3.1 Roads and Infrastructure Services provides Members with weekly briefings on
topical service activities which are all available here.   
3.2 As part of the resources on the new Member Zone system there are various key
documents available in an online library here. 
3.3 There are also additional online resources covering the streetlighting, footway,
surface dressing and roads reconstruction programmes available on the website
here. 
Roads Capital Programme 
3.4 Officers met with Members of Mid Argyll, Kintyre and the Islands Area Committee
in October as part of our Roads Capital Programme engagement process. The
slides that formed the presentation have also been emailed to Members and
provide detailed information on the programme development process. Initial draft
schemes were presented for discussion and comments and suggestions from
Elected Members have been noted for consideration as we develop next year’s
programme of works. 
A816 Ardfern Landslip 
3.5 Works are ongoing following the Ardfern landslip which occurred on 6/7 October
2023 which include stabilising the hillside, clearing the A816 road of material and
building an emergency route. To date the following has taken place: 
 Formal agreement in place with Forest and Land Scotland, SEPA etc. to
open up a disused quarry to tip the landslip material. Approx. 15000 tonnes
of material have been taken from on and around the road and deposited
at the quarry. 
 Road corridor cleared, work continues to remove material which continues
to slump down the hill, including rocks up to and over 200 tonnes in weight.
 Archaeological and ecology assessments for the emergency route which
is on track to open before the A816 will be available. 
Elected Members continue to receive regular detailed updates on this and the
other sites which were affected during the heavy rainfall experienced on 6/7
October. A Member’s seminar has been arranged for 29 November 2023. 
4.0 CONCLUSION 
4.1 This report provides links to existing published information on service activities
and provides for the opportunity for Officer attendance and engagement at
committee meetings. 
5.0 IMPLICATIONS

Page 3

5.1 Policy – Roads and Infrastructure work to a number of policies across the range
of service areas 
5.2 Financial – revenue and capital budgets are in place to deliver projects and
cyclic work 
5.3  Legal – none known 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – where appropriate EqSEIAs will be
carried out to identify any implications 
5.5.2   Socio-economic Duty – where appropriate EqSEIAs will be carried out to
identify any implications 
5.5.3 Islands – where appropriate Island impacts assessments will be carried out to
identify any implications 
5.6. Climate Change – due regard will be given to climate change with a view to
minimising any climate change impact and these will be considered as and
when they arise 
5.7  Risk – risk managed through toolbox talks, safety briefings and where
appropriate risk registers – all of the above are monitored through the RIS
leadership and management teams 
5.8  Customer Service – none known 
Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads and Transport, Councillor Andrew Kain 
November 2023                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services