ARGYLL AND BUTE COUNCIL  Mid Argyll Kintyre and the Islands
DEVELOPMENT AND ECONOMIC
GROWTH 
28 February 2024 
LOCHGILPHEAD TO CRINAN CANAL ACTIVE TRAVEL ROUTE: CONCEPT
DESIGN AND FUTURE EXTERNAL FUNDING 
1.0 EXECUTIVE SUMMARY 
1.1. This report provides an update to Members on the progress made to date on the
Lochgilphead to Crinan Canal Active Travel Route, highlights the next steps and
seeks support for the continuation of the project from Members. 
1.2. A concept design has been produced for a preferred route alignment based on
the findings of a feasibility study and route options appraisal that was completed
in August 2023. 
1.3. A public consultation on the proposed concept design was held between 11th
and 28th September. The consultation received 99 responses, with 59% of
respondents supportive of the proposal. 
1.4. The Lochgilphead Community Council have confirmed that they fully support the
proposal. 
1.5. The preferred route alignment largely runs adjacent to the A83. Transport
Scotland have confirmed they are happy in principle, but will require to approve
the detailed design and technical design drawings before they can sign off on a
design. 
1.6. A short section of the proposed route is within the boundary of the Crinan Canal
which is a Scheduled Monument and managed by Scottish Canals. Scottish
Canals have indicated that they are supportive of the proposal. 
1.7. A short section of the preferred option runs over land that is in private
ownership. The landowners have been consulted but currently there is no legal
agreement in place with the landowners to allow for the use/acquisition of their
land to be used for the creation of the new route. 
1.8. The funding for the feasibility study, options appraisal and concept design has
come from Transport Scotland through the Sustrans administered Places for
Everyone programme (PFE) which is a challenge fund that requires designs to
adhere to strict design parameters in order for them to be considered by the
PFE funding application assessment panels. 
1.9. If members approve the progression of this project additional funding for the
developed and technical design stages will be required. At present the best

Page 2

route to access new funding for this project (and other active travel infrastructure
projects) would be through the Transport Scotland PFE programme. 
RECOMMENDATIONS 
It is recommended that the Mid Argyll Kintyre and the Islands members: 
• Welcome the progress made to date.
• Support the continuation of the project and the submission of a new PFE
funding application for design stages 3-4 (Developed & Technical
Design) to complete the design work required.

Page 3

ARGYLL AND BUTE COUNCIL  Mid Argyll Kintyre and the Islands
DEVELOPMENT AND ECONOMIC
GROWTH 
28 February 2024 
LOCHGILPHEAD TO CRINAN CANAL ACTIVE TRAVEL ROUTE: CONCEPT
DESIGN AND FUTURE EXTERNAL FUNDING 
2.0 INTRODUCTION 
2.1. This report provides an update to Members on the progress made to date on the
Lochgilphead to Crinan Canal Active Travel Route, highlights the next steps and
seeks support for the project from Members. 
3.0 RECOMMENDATIONS 
3.1  It is recommended that the Mid Argyll Kintyre and the Islands members: 
• Welcome the progress made to date.
• Support the continuation of the project and the submission of a new PFE
funding application for design stages 3-4 (Developed & Technical
Design) to complete the design work required. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. In 2023/24 to date, the Active Travel Team secured £2.56M external funding for
the development and delivery of a total of 22 projects across Argyll and Bute,
including the Lochgilphead to Crinan Canal Active Travel Route.   
4.3. Transport Scotland’s Places for Everyone (PFE) programme is structured
around 8 project stages with a competitive challenge fund, with the 32 local
authorities, 7 regional transport partnerships, two national parks and numerous
community groups across Scotland competing against each other to secure the
funding each project requires. 
4.4. A minimum of three new competitive funding submissions are required to
complete a project using PFE funding, with competitive applications required, as
a minimum, prior to Stage 0 (Strategic Definition), Stage 3 (Developed Design)
and Stage 5 (Construction).  The project stages are (0) Strategic Definition, (1)

Page 4

Preparation and Brief, (2) Concept Design), (3) Developed Design, (4) Technical
Design, (5) Construction, (6) Handover & Close Out and (7) In Use.                                           
4.5. Lochgilphead Front Green to Crinan Canal Design Stage 0-2 (work
completed to date) 
4.5.1. An active travel route linking the Lochgilphead Front Green with the Crinan
Canal was identified as a community aspiration through the 2016 Rethink the
Link Charrette. 
4.5.2. A preferred route was identified as part of a study carried out in 2020; however
due to changes in design standards (Cycling by Design 2021), concerns raised
by funders over estimated costs and changes to the funders requirements for
active travel projects, the feasibility study and options appraisal was revisited in
order to bring it in line with the new design principles and new design stage
deliverable outputs required by the funders. 
4.5.3. In 2022 the project was awarded PFE funding and Stantec were appointed as
the consultant design team to progress the project through the new PFE 0-2
design stages and produce a concept design that adhered to the principles of
Cycling by Design and that provided a route with as a high a level of service as
was practicably possible. 
4.5.4. The potential routes were split into several sections with each section having at
least 2 route options to be considered prior to a preferred option being identified. 
4.5.5. Through a series of workshops with key stakeholders, including Transport
Scotland, Scottish Canals, Argyll and Bute Council and community
organisations; the initial long list of options were scored against the Key
Principles in Cycling by Design (Safety, Coherence, Directness, Comfort,
Attractiveness and Adaptability) alongside the Deliverability and Maintainability
of each option. 
4.5.6. This initial appraisal recommended a preference for two sections of the route,
namely (1) for a shared use path between the Front Green and the car park next
to the Corran B&B and, (2) for the reinstatement of an old ramp from the A83 up
to the canal that is currently overgrown. However no clear preference could
identified for the section required to link these two sections. The options for this
missing section were: 
1. A causeway or bridge through the Corran Grazings.
2. An improved shared walking and cycling route to the south of the A83/A816
junction with full acquisition of the Corran B&B.
3. An improved shared walking and cycling route to the south of the A83/A816
junction with acquisition of some land that is within the Title of the Corran
B&B.
4. A new road bridge with shared footway.

Page 5

4.5.7. These options were assessed using the Active Mode Appraisal Toolkit (AMAT);
a tool published by the Department for Transport (England) for assessing the
overall benefits and costs of proposed walking and cycling interventions 
4.5.8. The AMAT appraisal identified that the preferred option for this section would be
to improve the shared walking and cycling route south of the A83/A816 junction
with acquisition of a short section of land that is within the Title of the Corran
B&B. Land acquisition is required due to the width of the footway between the
A83 and the Corran B&B currently being deemed too narrow to be considered
as acceptable for a PFE project. Cycling by Design requires a shared use path
with an anticipated level of use of less than 300 cyclist per hour (the lowest peak
flow threshold used in the document) to have an absolute minimum width of 2.5
metres and the footway width at this section is under 2 metres for an extended
length along a curve. Therefore in order to ensure the route provides as high a
level of service as is practicable the width of the existing footway needs to be
increased. Although the existing pedestrian bridge is also under 2.5m funders
have agreed in principle that this structure will not be required to be replaced
due to the short overall length and deliverability implications of replacing the
bridge.   
4.5.9. As the majority of the route runs adjacent to the A83 Trunk Road, Transport
Scotland are the Roads Authority responsible for this asset. Transport Scotland
have been involved in design workshops and although they cannot grant
consent to the design until further detail is developed they are supportive in
principle. 
4.5.10.A short section of the new route looks to reinstate an old ramp onto the Crinan
Canal. The Canal is a Scheduled Monument managed by Scottish Canals.
Scottish Canals have been involved in design workshops and are supportive in
principle. Scottish Canals have discussed the project with Historic Environment
Scotland and if the project is to proceed it would require the formal consent from
both these bodies. 
4.5.11.The owners of the Corran B&B have been approached and kept informed of the
project progress. They have raised concerns about how the project could
negatively affect them and the operation of their business. If the project is to
progress further investigatory technical survey work will be required to be carried
out to help inform future discussion with the owner of the B&B. 
4.5.12.A consultation on the concept design was held between 11th and 28th
September 2023. The consultation received 99 responses, with 59% of
respondents supportive of the preferred option. The comments that were
unsupportive were largely due to a desire to see a route through the Corran
Grazings which was estimated to cost over £5m. The Lochgilphead Community
Council have confirmed that they fully support the current proposal. 
4.6. Design Stage 3-4 
4.6.1. A PFE funding application has been submitted to allow the project to progress
onto design stages 3 and 4. This funding is a challenge fund open to all 32 local

Page 6

authorities and although the project has been funded for design stages 0-2 there
is no guarantee that the project will be awarded PFE funding for 2024/25 to
deliver design stages 3-4. It is expected that 2024/25 funding awards will be
confirmed in Quarter 1 2024/25. 
4.6.2. If the project is awarded additional funding for 2024/25 further discussion with
the owners of the Corran B&B will be a priority. 
4.6.3. If the project is not awarded 2024/25 PFE funding, Members have the options of
allocating Council funding or the project will require to be paused awaiting
funding or terminated. 
5.0 CONCLUSION 
5.1. A concept design for a new active travel route between the Lochgilphead Front
Green and the Crinan Canal has been produced for consultation. The results
from the consultation show that 59% of respondents were supportive of the
concept design. 
5.2. External funding from PFE has been sought for 2024/25 to progress the concept
design through the design stages 3-4. However, award of this funding is not
guaranteed. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design and land purchase will be funded by
external competitive funding applications. The Council
has not contributed any funding to design costs. 
There is strong evidence that people who are more
active, for example by walking or cycling, have
improved physical and mental health and are less
likely to require social care services in later life which
could result in a future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support any land purchase.
6.4. HR None.
6.5. Fairer Scotland
Duty:

Page 7

6.5.1 Equalities Completion of this project will provide enhanced
opportunities for all between Lochgilphead and the
Crinan Canal to travel more sustainably and actively
by walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route will improve access to essential services,
retail, leisure and employment opportunities for local
residents, with studies demonstrating those who
travelled actively had a higher monthly spend in local
businesses than those who travel via motorised
transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.
6.9. The Rights of the
Child (UNCRC)
Completion of this project will provide enhanced
facilities designed to be suitable for use by an
unaccompanied 12 year old. 
The route has been designed to be DDA compliant
and will provide a safe and accessible route for
children with disabilities 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Roads and Transport: Cllr Andrew Kain 
08 January 2024

Page 8

For further information contact:  Douglas Grierson,    
Sustainable Transport Coordinator    
Douglas.grierson@argyll-bute.gov.uk    
01546 604228 
The complete Feasibility and Options Appraisal report can be accessed via the
projects web page