Lochgilphead Town Centre to Joint Campus Active Travel Route: Developed Design and Future External Funding

Argyll and Bute Council · 5 March 2025
Back to Mid Argyll, Kintyre & the Islands Area Committee — 5 March 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  Mid Argyll Kintyre and the Islands
DEVELOPMENT AND ECONOMIC
GROWTH 
05 March 2025 
Lochgilphead Town Centre to Joint Campus Active Travel Route: Developed
Design and Future External Funding 
1.0 EXECUTIVE SUMMARY 
1.1. This report provides an update to Members on the progress made to date on the
Lochgilphead Town Centre to Joint Campus Active Travel Route and seeks
support from Members for the continuation of the project. 
1.2. A developed design (RIBA stage 3) has been produced and consulted on for an
active travel route linking Lochgilphead Front Green and Town Centre with the
Lochgilphead Joint Campus. A technical design (RIBA stage 4) is currently in
the process of being finalised. 
1.3. The design work to date has been fully funded through the Sustrans
administered Places for Everyone Programme. This programme is coming to an
end in 2025 and is to be replaced with Transport Scotland’s Active Travel
Infrastructure Fund. 
1.4. The design proposal has been progressed through the RIBA design stages 0-3
and has been subject to a series of consultations with key stakeholders and
members of the public. 
1.5. The stage 3 developed design is primarily for mixed traffic streets along Lorne
Street, Union Street, part of Manse Brae and part of Kilmory Road. Mixed traffic
streets promote the use of road space to be shared with cyclists and motor
vehicles through lining and signing and traffic calming measures that help raise
awareness and improve road safety. 
1.6. The traffic survey data obtained indicate that Cycling by Design would consider
a shared street design to provide a high level of service for the majority of the
route. The only exception to this is a short section of Lorne Street (between
Argyll Street and the Lorne Street car park entrance) where a higher number of
vehicle movements were recorded and as a result Cycling by Design would
consider this section to offer a medium level of service. 
1.7. The scheme also includes improved road crossing facilities (including a new
toucan crossing), additional double yellow lining for improved road safety on
Lorne Street and Union Street, new lining to demarcate on street parking bays
on Lorne Street and Union Street, footway and path widening, introducing blue/
green infrastructure and an improved accessibility link between Kilmory Road
and Whitegates Road.

Page 2

1.8. A public consultation on the developed design was held between 19th
September 2023 and 20th November 2023. Although well-advertised and
prompted the consultation only received 48 comments from 21 participants. 59%
of responses were positive. 
1.9. The Lochgilphead Community Council have stated that they are supportive the
proposal. 
1.10. A Stage 2 Road Safety Audit on the design has been completed and signed off
by Roads and Infrastructure Services subject to specifications for surfacing
materials, bollards and signage being agreed with local Roads Officers. This
agreement will be met before the conclusion of Stage 4 which is anticipated  to
be March 2025. 
1.11. The majority of the route is either along the adopted road corridor or within land
owned by Argyll and Bute Council and it is anticipated that the work can be
carried out through the Councils Permitted Development Rights; however for
certain aspects of the design (introduction of designating on street parking bays
and new double yellow lining) Traffic Regulation Order(s) (TRO) will be required. 
1.12. A short section of the route is on the National Forestry Estate and Scottish Land
and Forestry have not raised any objections to the proposal. 
1.13. The new Active Travel Delivery Fund is a competitive challenge fund open to all
Local Authorities, National Parks and Regional Transportation Partnerships in
Scotland. Although there is no confirmation of levels of funding for 2025/26
Transport Scotland have indicated that there will be £20 million available for this
financial year. 
1.14. The Active Travel Delivery Fund closes for new applications on 14th February
2025 and will not reopen for applications this financial year. 
1.15. As a TRO will not be required for the whole route a funding application for the
construction of the section of the route that does not require a TRO (the section
between the Joint Campus and Manse Brae) has been submitted for the
2025/26 ATIF application round. As part of the application assessment process
Transport Scotland are seeking assurance that projects have the support of the
local authorities relevant Committee. 
RECOMMENDATIONS 
1.16. It is recommended that the Mid Argyll Kintyre and the Islands members: 
1.16.1. Welcome the progress made to date. 
1.16.2. Support the continuation of the project and the submission of the
2025/26 Active Travel Infrastructure Fund funding application for the

Page 3

construction of the section of the route between the Joint Campus and
Manse Brae

Page 4

ARGYLL AND BUTE COUNCIL  Mid Argyll Kintyre and the Islands
DEVELOPMENT AND ECONOMIC
GROWTH 
05 March 2025 
Lochgilphead Town Centre to Joint Campus Active Travel Route: Developed
Design and Future External Funding 
2.0 INTRODUCTION 
2.1. This report provides an update to Members on the progress made to date on the
Lochgilphead Town Centre to Joint Campus Active Travel Route and seeks
Members support for the continuation of the project. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Mid Argyll Kintyre and the Islands Members: 
3.1.1. Welcome the progress made to date. 
3.1.2. Support the continuation of the project and the submission of the
2025/26 Active Travel Infrastructure Fund funding application for the
construction of the section of the route between the Joint Campus and
Manse Brae 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. Transport Scotland’s Active Travel Infrastructure Fund (ATIF) programme is a
competitive challenge fund, with the 32 local authorities, 7 regional transport
partnerships, and two national parks across Scotland competing against each
other to secure the funding each project requires. 
4.3. The ATIF programme replaces the Sustrans administered Places for Everyone
(PfE) programme as Transport Scotland’s flagship model to deliver active travel
projects in Scotland. ATIF funded projects are required to follow the same 8
stage process that was used for PfE.  These project stages are (0) Strategic
Definition, (1) Preparation and Brief, (2) Concept Design), (3) Developed
Design, (4) Technical Design, (5) Construction, (6) Handover & Close Out and
(7) In Use.

Page 5

4.4. Lochgilphead Town Centre to Joint Campus Stages 0-3 (work completed
to date) 
4.4.1. An active travel route linking the Lochgilphead Front Green and Town Centre
with the Joint Campus was identified as part of a wider community aspiration in
the 2016 Rethink the Link Charrette that identified the desire for safe cycling
infrastructure between pier Square in Ardrishaig and the Lochgilphead High
School. 
4.4.2. A route options appraisal and feasibility study (stage 0-1) was carried out in
2021 to identify a preferred route option to take onto concept design. Part of this
initial work included public consultation on all three route options. The three
route options were: 
• Option 1: Followed Lorne Street and Union Street before passing though
the former primary school site and linking into Kilmory Road. This option
was identified as the preferred route and formed the basis for the current
deign. 
• Option 2: followed the A83 road corridor before connecting into
Whitegates Road- this is the most direct route however it was discounted
due to the high volume of motor vehicles and existing constraints within
the road corridor that would not allow the required infrastructure to be
built without the demolition of buildings and realignment/redesign of the
A83/Whitegates Road mini roundabout. 
• Option 3: followed the coastline around Loch Gilp from the Front Green
and behind the existing housing to meet and cross the A83 before linking
into the existing path to the Joint Campus- this option was discounted
due to the very high cost- both capital and revenue. 
The options appraisal and feasibility consultation concluded in May 2021 and
allowed for work to commence on a concept design (stage 2) for the route. 
4.4.3. A consultation on the proposed concept design was held between 29th June and
27th August 2021. Due to Covid restrictions during this period the consultation
was limited to online consultation only. The consultation asked people to tell us
what they thought about the proposal and received 98 responses. Generally the
comments were positive; however there was a concern over the loss of available
on street parking along Union Street and to a lesser extent along Lorne Street. 
4.4.4. As part of the design process a 7 day parking survey was carried out between
28th June and 4th July 2021 between 05.30hrs- 1930hrs. This survey indicated
that the on street parking on both Lorne Street and Union Street did not reach its
maximum capacity.  The existing available parking space, excluding illegal
parking, was calculated as 58 spaces on Lorne Street and 74 spaces on Union
Street based on an available lengthwise distance of 300m and 397m
respectively. In addition both Lorne Street and Union Street each have 1
disabled parking bay. The survey found a peak level of occupancy of 38 legally
parked vehicles plus regular occupancy of the disabled bay on Lorne Street and
40 legally parked vehicles plus regular occupancy of the disabled bay on Union
Street.

Page 6

4.4.5. In late December 2021 the project was awarded PfE funding to progress with
the design through Stage 3 and 4. In 2022 Civic Engineers were appointed as
the consultant design team to progress the project through these design stages.
However prior to this appointment the design guidance- Cycling by Design- had
been updated  and a full review of the concept design was required to ensure
that it complied with the new design guidance 
4.4.6. An early design workshop between the design team and Argyll and Bute Council
Roads in Infrastructure Services Officers was held where it became apparent
the Roads Officers had a number of concerns about the concept design that
were not picked up during the previous consultation. This resulted in the design
team having to considerably rework the design to incorporate the comments and
advice from Roads and Infrastructure Services. 
4.4.7. Design workshops were held throughout 2022 and 2023 with Roads and
Infrastructure Officers to arrive at a design that they were content could be
presented for public consultation. The design and workshop meetings were also
informed by a series of additional surveys, including a new parking survey which
returned similar results to the first parking survey (peak occupancy Lorne Street
35 vehicles plus regular occupancy of 1 disabled bay and peak occupancy
Union Street 40 vehicles plus regular occupancy of 1 disabled bay), automatic
traffic counts, junction turning counts, none motorised user survey and swept
path analysis for a range of vehicle types including HGV’s and refuse vehicles. 
4.4.8. An additional risk to the project that was identified was the uncertainty over the
future use of the former Lochgilphead Primary School site and Whitegates Office
site. Regular meetings with the Councils Estates Team have been taking place
and the proposed active travel route through the former school site aims to
deliver a light touch improvement by widening and resurfacing the existing path
and resurfacing, lining and signing the existing road through the site. The
proposed intervention for Whitegates is to make the existing access ramp
between Whitegates Road and Kilmory Road more accessible and inclusive for
use, with a new section of path and retaining structure along the northern
boundary of this site. All the proposed work follows or is close to the perimeter of
the site to maximise any future development of the site. 
4.4.9. The developed design that went out to public consultation is primarily for mixed
traffic streets along Lorne Street, Union Street, part of Manse Brae and part of
Kilmory Road. Mixed traffic streets promote the use of road space to be shared
with cyclists and motor vehicles through lining and signing and traffic calming
measures that help raise awareness and improve road safety. The traffic survey
data obtained indicate that Cycling by Design would consider a shared street
design to provide a high level of service for the majority of the route. A high level
of service which is described as a facility that is suitable for most users.  The
only exception to this is a short section of Lorne Street (between Argyll Street
and the Lorne Street car park entrance) where a higher number of vehicle
movements were recorded in the base line survey and as a result Cycling by
Design would consider this section to offer a medium level of service which is

Page 7

described as a facility that may not be suitable for some users, particularly
novice users. 
4.4.10. The scheme also includes improved road crossing facilities (including a new
toucan crossing), additional double yellow lining for improved road safety on
Lorne Street and Union Street to prevent vehicles parking at or close to
junctions or locations where visibility splays could be impeded as well as to
provide areas of road space to allow for vehicles to pull in and pass one
another on Union Street, new lining to demarcate on street parking bays on
Lorne Street (39 plus 1 disabled bay) and Union Street (51 plus 2 disabled
bays), footway and path widening, an improved accessibility link between
Kilmory Road and Whitegates Road as noted in point 4.4.8 above and blue
green infrastructure in the form of rain gardens to provide sustainable urban
drainage systems that aid with street drainage. 
4.4.11. The public consultation on the developed design (RIBA Stage 3) was held
between 19th September 2023 and 20th November 2023. The public
consultation included a public drop in event held in the Lochgilphead Baptist
Church on the 28th September between 2pm and 7pm. Despite the event being
advertised through the Councils web page, by local stakeholders, posters and
a press release only 25 people attended the event. The majority of responses
to the proposal were positive. The only negative comments towards the design
came from 2 attendees who were concerned about the proposed changes to
Union Street. 
4.4.12. The design team also undertook two workshop events with secondary and
primary school pupils at the Joint Campus on the 28th September. The
workshops were attended by 31 pupils with pupils highlighting some of the
barriers they face to walking or cycling to school which included the weather,
laziness and the lack of provision of an attractive and safe route. One pupil
highlighted a concern over personal safety from passing through the former
school site after dark.   
4.4.13. A workshop was also held with 8 members (including 2 staff) of MS Argyll
Snowdrop Resource Centre who highlighted some the difficulties they face
navigating Lochgilphead, these were primarily to do with volume of road traffic,
on street parking creating blind spots for road crossing, distance from car park
to amenities. 
4.4.14.  Presentations on the design were also give to: Lochgilphead Community
Council; Forestry and Land Scotland; Mid Argyll Youth Development Services,
Fyne Futures; Argyll and Bute Council Sensory Impairment Officer and the
Project Engagement Group (which comprised of members of the community
who had expressed an interest in the project during the previous design stages
and consultation) 
4.4.15. Due to the poor turn out to the consultation drop in event a flier advertising the
consultation was mailed out to 3967 addresses with the PA30 and PA31
postcodes

Page 8

4.4.16. Despite all the promotional actives a total of 48 comments from 21 participants
were received to the online consultation. 59% of responses were positive with
respondents saying the proposals would encourage them to walk and cycle
more often 
4.4.17. Following the presentation to the Lochgilphead Community Council the
Community Council stated that they are supportive of the proposal. 
4.4.18. A Stage 2 Road Safety Audit on the design has been completed and signed off
by Roads and Infrastructure Services subject to specifications for surfacing
materials, bollards and signage being agreed with local Roads Officers. This
agreement will be met before the conclusion of Stage 4- anticipated in March
2025. 
4.4.19. The Road Safety Audit identified an issue with a crossing on Lorne Street and
in order to address this issue 1 parking bay on Lorne Street has had to be
removed from the design. This leaves 38 regular parking bays and 1 disabled
parking bay on Lorne Street. The highest peak occupancy recorder on Lorne
Street was from the 2021 survey that recorded 38 parked vehicles plus
occupancy of the disabled bay. The 2022 survey recorded a peak occupancy
of 35 parked vehicles plus occupancy of the disabled bay. 
4.4.20. The majority of the route is either along the adopted road corridor or within the
ownership of Argyll and Bute Council and it is anticipated that the work can be
carried out through the Councils Permitted Development Rights; however for
certain aspects of the design (introduction of designating on street parking
bays, additional disabled parking bay and new double yellow lining) Traffic
Regulation Order(s) (TRO) will be required. The TRO application will be made
once the specifications for surfacing materials, bollards and signage (noted in
the Stage 2 RSA) have been agreed with the local Roads Officers. 
4.4.21. A short section of the route is on the National Forestry Estate. Forestry and
Land Scotland have been briefed on the project and have not raised any
objections to the proposal. 
4.4.22. Part of the route incudes an uncontrolled crossing of the A83 Trunk Road.
Transport Scotland have been involved in the development of the design and
have not raised an objection to the proposal. 
4.4.23. The new Active Travel Delivery Fund is a competitive challenge fund open to
all Local Authorities, National Parks and Regional Transportation Partnerships
in Scotland. Although there is no confirmation of levels of funding for 2025/26
Transport Scotland have indicated that there will be £20 million available for
this financial year. 
4.4.24. The Active Travel Delivery Fund closes for new applications on 14th February
2025 and will not reopen for applications this financial year. 
4.4.25. As a TRO will not be required for the whole route a funding application for the
construction of the section of the route that does not require a TRO (the section

Page 9

between the Joint Campus and Manse Brae) has been submitted for the
2025/26 ATIF application round. As part of the application assessment process
Transport Scotland are seeking assurance that projects have the support of the
local authorities relevant Committee. 
5.0 CONCLUSION 
5.1. A developed design for a new active travel route between the Lochgilphead
Front Green/Town Centre and the Joint Campus was put out for public
consultation between the 19th September and 20th November 2023. The results
from the consultation show that 59% of respondents were supportive of the
developed design. However it is noted that the number of responses to this
consultation was low. 
5.2. Some of the negative comments received at consultation relate to the loss of
availability of on street parking. The two parking surveys that have been carried
out indicate that the design would provide sufficient on street parking for Lorne
Street (38 regular bays plus 1 disabled bay) and Union Street (51 regular bays
plus 2 disabled bays) to meet recorded demand. However the proposed change
in road layout and on street parking arrangements may affect the TRO process. 
5.3. A  Stage 2 Road Safety Audit has been carried out on the developed design.
The issues raised in the RSA have been addressed by the design team with
their responses either being accepted or accepted in principle subject to
technical design specifications by Roads and Infrastructure Services. The
technical specifications requested will be provided as part of the design stage 4.
Stage 4 will not be signed off until agreement has been reached with Roads and
Infrastructure Services 
5.4. The design for the section of the route through the former Lochgilphead Primary
School site and the Whitegates Office site mostly follows the existing paths and
road through these areas and is a light touch approach. Regular meetings with
the Councils Estates Team have been taking place and will continue to ensure
they are kept informed and up to date on this project. 
5.5. Following conclusion of Stage 4 all necessary permissions, including a TRO will
be sought. It is anticipated that this process will begin towards the end of March
2025. 
5.6. The Active Travel Infrastructure Fund deadline was the 14th February and a
funding application has been submitted for 2025/26 to progress the construction
of the section of the route between the Joint Campus and Manse Brae and
which does not require a TRO. However, the awarding of this funding is highly
competitive and cannot be guaranteed.

Page 10

6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Argyll and
Bute Local Outcomes Improvement Plan Outcome 1
and Outcome 3 and The Argyll and Bute Council Local
Development Plan 2 Policy 32. The project also aligns
with National Planning Framework 4 and National
Transport Strategy 2 and supports the objectives of
Transport Scotland’s Active Travel Framework
6.2. Financial The work will be funded by external competitive
funding applications. The Council has not contributed
any funding to design costs.  There is strong evidence
that people who are more active, for example by
walking or cycling, have been physical and mental
health and are less likely to require social care
services in later life which could result in a future
saving to the Council or HSCP.
6.3. Legal None
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide enhanced
opportunities for all between Lochgilphead and the
Crinan Canal to travel more sustainably and actively
by walking, wheeling and cycling.
The route has been designed to provide a safe and
accessible route for those with mobility aids including
wheelchairs and parents/guardians with a child’s pram
or buggy.
6.5.2 Socio-
economic Duty
The route will improve access to essential services,
retail, leisure and employment opportunities for local
residents, with studies demonstrating those who
travelled actively had a higher monthly spend in local
businesses than those who travel via motorised
transport.
The route will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a

Page 11

private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk Part of the scheme will require a Traffic Regulation
Order which is subject to public consultation. Part of
the route is on vacant land that is currently owned by
Argyll and Bute Council but could be sold in the future 
6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity: Councillor John Armour 
03 February 2025                                                  
For further information contact:   
Fergus Murray, Head of Development and Economic Growth 
fergus.murray@argyll-bute.gov.uk 
Douglas Grierson, Sustainable Transport Coordinator
Douglas.grierson@argyll-bute.gov.uk     
Please find the latest Stage 3 design drawings attached:
• 1695–CIVIC–XX–XX–D-C-00040
• 1695–CIVIC–XX–XX–D-C-00041
• 1695–CIVIC–XX–XX–D-C-00042
• 1695–CIVIC–XX–XX–D-C-00043 
Please note that these drawings are still in the process of being refined
through continued discussion with Local Roads Officers in terms of the on
street surfacing materials, street lining and street furniture to be used.