Page 1

Argyll and Bute Council
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 605522
DX 599700 LOCHGILPHEAD 
26 November 2025 
NOTICE OF MEETING 
A meeting of the MID ARGYLL, KINTYRE & THE ISLANDS AREA COMMITTEE will be held ON
A HYBRID BASIS IN THE COUNCIL CHAMBER, KILMORY, LOCHGILPHEAD AND BY
MICROSOFT TEAMS on WEDNESDAY, 3 DECEMBER 2025 at 10:30 AM, which you are
requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES FOR ABSENCE 
2. DECLARATIONS OF INTEREST 
3. MINUTE OF THE MID ARGYLL, KINTYRE AND THE ISLANDS AREA
COMMITTEE HELD ON 3 SEPTEMBER 2025 (Pages 5 - 8) 
4. PUBLIC QUESTION TIME 
5. SKILLS DEVELOPMENT SCOTLAND ANNUAL UPDATE (Pages 9 - 14)  
Report by Area Manager, Skills Development Scotland 
6. HEALTH & SOCIAL CARE PARTNERSHIP - PERFORMANCE REPORT FQ1
2025/26 (APRIL- JUNE) (Pages 15 - 30)  
Report by Senior Manager Performance and Improvement, Argyll and Bute Health
and Social Care Partnership 
7. ROADS AND INFRASTRUCTURE SERVICES UPDATE (Pages 31 - 34)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
8. ELECTRIC VEHICLE CHARGING STRATEGY (Pages 35 - 58)  
Presentation by Project Manager with responsibility for Roads and Infrastructure
Services 
Public Document Pack

Page 2

9. AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ2 2025/26
(Pages 59 - 92)  
Report by Executive Director with responsibility for Customer Support Services 
10. CHARITABLE TRUSTS, BEQUESTS AND TRUST FUNDS (Pages 93 - 100)  
Report by Executive Director with responsibility for Legal and Regulatory Support 
11. DRAFT MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMITTEE
WORKPLAN (Pages 101 - 104)  
For noting and updating 
12. NOTICE OF MOTION UNDER STANDING ORDER 13 
Carradale Harbour 
The Area Committee Notes:
• The strategically commercial and economic Local Government (LG) asset to
Kintyre, Argyll & Bute, and the wider Western seaboard of Scotland.
• That the Harbour supports and provides a haven to the fishing industry,
Aquaculture, and Inshore Waters leisure & training activities.
• That to maximise the potential benefits of the LG asset there is a consideration
to maintain, upgrade and enhance what is currently planned.
Officers are requested to bring forward a report to AC 
• That identifies potential strategic and economic benefits from investment in
and expansion of the LG harbour facilities and operations.
• At which time MAKI AC can consider making recommendations to the
Economic Development and Infrastructure Committee and Piers and Harbours
Authority. 
Proposed: Cllr Tommy Macpherson                       
Ward 01 - South Kintyre 
Seconded: Cllr Alastair Redman 
Ward 02 - Kintyre and the Islands 
REPORT FOR NOTING 
13. SAKURA CHERRY TREE PROJECT UPDATE (Pages 105 - 108)  
Report by Executive Director with responsibility for Legal and Regulatory Support 
Mid Argyll, Kintyre & the Islands Area Committee 
Councillor John Armour (Chair) Councillor Jan Brown
Councillor Garret Corner Councillor Anne Horn

Page 3

Councillor Jennifer Kean Councillor Tommy MacPherson
Councillor Dougie McFadzean (Vice-Chair)
Councillor Dougie Philand Councillor Alastair Redman   
Contact: Julieann Small, Democratic Services Assistant - 01546 604043

Page 4

This page is intentionally left blank

Page 5

MINUTES OF THE MEETING OF THE MID ARGYLL, KINTYRE & THE ISLANDS AREA
COMMITTEE HELD ON A HYBRID BASIS IN DUNAVERTY HALL, SOUTHEND AND BY
MICROSOFT TEAMS 
ON WEDNESDAY, 3 SEPTEMBER 2025 
Present: Councillor John Armour (Chair) 
Councillor Jan Brown
Councillor Garret Corner
Councillor Anne Horn
Councillor Jennifer Kean 
Councillor Tommy MacPherson
Councillor Dougie McFadzean
Councillor Alastair Redman 
Attending: Shona Barton, Governance Manager
Tom Murphy, Operations Manager
Suzanne Mason, Engagement and Communities Lead
David Hagerty, Community Development Officer
Seymour Adams, Chair, Cultural Heritage and Arts Assembly for the Argyll
and Isles (CHARTS) 
1. APOLOGIES FOR ABSENCE 
The Chair welcomed everyone to the meeting. 
Apologies for absence were intimated on behalf of Councillor Dougie Philand. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest intimated. 
3. MINUTE OF THE MID ARGYLL, KINTYRE AND THE ISLANDS AREA
COMMITTEE HELD ON 4 JUNE 2025 
The Minute of the meeting of the Mid Argyll, Kintyre and the Islands Area Committee, held
on 4 June 2025, was approved as a correct record. 
4. PUBLIC QUESTION TIME 
The Governance Manager advised that there had been no public questions
submitted in advance of the meeting. Having noted that there were members of the
public in attendance, the Chair invited them to submit any questions they may have. 
Jean Mary Knowles 
At the last meeting there were reports from different secondary schools and I wondered if
there were any exam results available from those secondary schools. 
The Governance Manager advised that a report went to the Community Services
Committee which detailed the SQA exam results and that she would provide the link to the
report to Ms Knowles following the meeting. 
Page 5 Agenda Item 3

Page 6

5. CHARTS (ARGYLL AND THE ISLES) 
The Committee gave consideration to a presentation by the Chair of the Cultural Heritage
and Arts Assembly (CHARTS) for Argyll and the Isles. The presentation included
information on CHARTS work and their key projects; the local impact; the Gaelic language
and culture; the work on the Argyll Collection project; the development and progress in
Campbeltown Museum; and the benefits of the continued support received from Argyll and
Bute Council. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. 
(Reference: Presentation by Chair, Cultural Heritage and Arts Assembly for the Argyll and
Isles, dated August 2025, submitted) 
6. ROADS AND INFRASTRUCTURE SERVICES UPDATE 
The Committee gave consideration to a report which provided links to the recent activities
of Roads and Infrastructure Services. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services, dated 11 August 2025, submitted) 
7. RECYCLING AND RECOVERY PERFORMANCE 
The Committee gave consideration to a report which provided details of the Council’s
recycling and landfill diversion performance, along with national policies, targets and
regulations which are likely to impact on future performance. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted the details as outlined in
the report and the national policy drivers that would likely impact over the coming years. 
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services, dated 3 September 2025, submitted) 
8. SUPPORTING COMMUNITIES FUND 2025/26 
Consideration was given to a report which detailed recommendations for the award of the
Council’s Supporting Communities Fund (SCF) for the 2025/26 round of funding that had
been made available for distribution by the Council to organisations in the Mid Argyll,
Kintyre and the Islands area.   
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 17 applications,
marked as ‘Award’ within Appendix 1 of the report, are awarded funding from the
Supporting Communities Fund totalling £22,500, as follows: 
Page 6

Page 7

Ref: Organisation name
Award /               
No Award 
Requested
Amount 
Recmnd
Award 
Cummulataive
Total
1 Bowmore Lunch Club Award  1,500.00£   1,500.00£   1,500.00£     
2 South Kintyre Development Trust Award  1,500.00£   1,500.00£   3,000.00£     
3 Tayinloan Youth Club Award  1,000.00£   1,000.00£   4,000.00£     
4 Islay Connections SCIO Award  1,500.00£   1,500.00£   5,500.00£     
5 Old Pals Club, Campbeltown, Argyll Award  1,200.00£   1,200.00£   6,700.00£     
6 Campbeltown Sea Cadets Unit 480 Award  1,500.00£   1,500.00£   8,200.00£     
7 Kintyre Link Club Award  1,500.00£   1,500.00£   9,700.00£     
8 Mid Argyll Community Enterprises Award  500.00£      500.00£      10,200.00£   
9 Friends of Castlehill Award  1,500.00£   1,500.00£   11,700.00£   
10 Mid Argyll Rugby Club Award  1,496.00£   1,496.00£   13,196.00£   
11 Kintyre Seasports Award  1,482.50£   1,482.50£   14,678.50£   
12 Jura Development Trust Award  1,500.00£   1,500.00£   16,178.50£   
13 Cairnbaan Community Trust Award  1,500.00£   1,500.00£   17,678.50£   
14 Ardrishaig Community Council Award  1,500.00£   1,500.00£   19,178.50£   
15 Mid Argyll Transport Volunteers Award  1,500.00£   1,500.00£   20,678.50£   
16 Campbeltown & District Juvenile Football Assoc. Award  1,500.00£   1,500.00£   22,178.50£   
17 Inveraray Carpet Bowls Club
Partial
Award  350.00£      321.50£      22,528.50£   
18 Kintyre Food Bank No Award  1,500.00£   24,028.50£   
19 Lochside Champions Community Group No Award  1,250.00£   25,278.50£   
20 Port Ellen FC Juniors No Award 1,500.00£   26,778.50£   
21 Islay and Jura Youth Wind Band No Award 1,500.00£   28,278.50£   
22 Kintyre Amateur Swimming Club No Award 1,500.00£   29,778.50£   
23 Multiple Sclerosis Centre, Mid Argyll No Award 1,500.00£   31,278.50£   
24 An Comunn Gaidhealach Meur Ìle No Award 1,500.00£   32,778.50£   
25 Live at the Loch (c/o Tarbert Enterprise Company)No Award 1,500.00£   34,278.50£   
26 Campbeltown Grammar School Parent Council No Award 1,500.00£   35,778.50£   
27 Islay Gaelic Choir No Award 1,500.00£   37,278.50£   
28 Jura Care Centre No Award 1,440.00£   38,718.50£   
29 Meadows Under Fives No Award 1,498.90£   40,217.40£   
30 West Kintyre Promotions CIC No Award 1,500.00£   41,717.40£   
31 Kilmory & Dunadd Camanachd No Award 1,493.50£   43,210.90£   
32 Campbeltown Kintyre Rugby Club No Award 1,500.00£   44,710.90£   
33 Islay Youth Football Club No Award 1,498.34£   46,209.24£   
34 Colonsay Book Festival No Award 1,500.00£   47,709.24£   
35 Mull of Kintyre 10km and Half Marathon No Award 1,500.00£   49,209.24£   
36 Greater Kilmeny Community Group No Award 1,500.00£   50,709.24£   
37 Heart of Argyll Wildlife Organisation No Award 628.00£      51,337.24£   
38 Islay Natural History Trust No Award 1,500.00£   52,837.24£   
39 Inspire Inveraray No Award 1,500.00£   54,337.24£   
40 The Community Forget Me Not Choir
CLD
Partnership 1,500.00£   55,837.24£   
Total 55,837.24£ 22,500.00£ 
(Reference: Report by Chief Executive, dated 15 August 2025, submitted) 
9. SUPPORTING COMMUNITIES FUND - MONITORING OF PROJECTS
FUNDED 2023/24 
Consideration was given to a report providing information on the impact and spend of
funding awarded to community projects from the Council’s Supporting Communities Fund
in 2023/24. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted:
Page 7

Page 8

1. the positive contribution of the Supporting Communities Fund as detailed in section 4
and within the table; and 
2. that Islay Community Council has requested an extension to spend their funds by
December 2025. 
(Reference: Report by Chief Executive, dated 22 August 2025, submitted) 
10. AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ1
2025/26 
The Committee gave consideration to the Area Performance Report for financial quarter 1
of 2025/26 (April to June 2025) which illustrated the agreed performance measures for
this period. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and
supporting commentary as presented. 
(Reference: Report by Executive Director with responsibility for Customer Support
Services, dated 12 August 2025, submitted) 
11. DRAFT MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMITTEE
WORKPLAN 
The Committee gave consideration to the Mid Argyll, Kintyre and the Islands Area
Committee workplan for future meetings. 
Decision 
The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the
workplan. 
(Reference: Mid Argyll, Kintyre and the Islands Area Committee Workplan, dated 3
September 2025, submitted) 
Page 8

Page 9

Skills Development Scotland 
Mid Argyll, Kintyre and the Islands Area Committee
Annual Update 
3 December 2025 
Page 9 Agenda Item 5

Page 10

1. Service Delivery in Mid Argyll, Kintyre and the Islands
1.1 School Service Offer 
Campbeltown Grammar, Islay High School, Lochgilphead Joint Campus and Tarbert Academy 
Our careers advisers work delivering career guidance to enable young people from S1-S6 to develop their
Career Management Skills via a range of group work and 1-1 coaching conversations. We work closely with
our partners within the school to identify young people who are considered most at risk of not making a
positive progression from school. Helping those young people to develop their career management skills and
move onto education, employment, or training when they leave school.  For more information click this link
What We Do - Scotland’s Career Service   
Update 
School Leaver Initial Destinations Follow Up
• Over the school holidays we currently contacting all school leavers Campbeltown Grammar, Islay
High School, Lochgilphead Joint Campus and Tarbert Academy (approx. 198) to ensure that they
have secured a positive destination post leaving school and offer support to any that haven’t. 
• These results will be published by the Scottish Government sometime in the new year.
• Please click here to see last year’s results. School leaver attainment and destinations - gov.scot 
1.2 Post School Service Offer
Our Next Steps service supports young people aged 16 – 18 (extended to 26 for care experienced young
people) who are unemployed, helping them to build up their career management skills and move on to and
sustain a range of options as appropriate. We also offer a service to any adult who wishes to develop their
career management and employability skills and move into employment or support a career change. 
Individuals can access help at our local centres at the following locations. 
Campbeltown, 40 Hall Street, PA28 6BU (based within JobCentre Plus). Please contact 01586 552795 for
an appointment. 
Islay, Islay High School, Flora Street, Bowmore, PA43 7JY. Please contact 01496 545 990 for an
appointment. 
We also can offer virtual and telephone support if required. 
2. PACE: Partnership Action for Continuing Employment (PACE) 
PACE is the Scottish Government’s initiative dedicated to responding to redundancy situations. Through
providing skills development and employability support, PACE aims to minimise the time individuals affected
by redundancy are out of work. PACE brings together 24 organisations, together with the Scottish
Government to provide free and impartial advice, guidance and support for individuals affected by
redundancy. Our PACE activity is co-ordinated by our Chair Pamela Little. 
Update
• In the current quarter of the financial year, we have had limited PACE activity. However, we have
offered and delivered PACE support to employees at Collies Haulage and where able to help support
all individuals effected into further employment. Please contact pacenationalteam@sds.co.uk for any
further information 
Page 10

Page 11

3.Participation Reports 
3.1 School Leaver Initial Destinations Follow Up
Initial school leaver destinations in Scotland refer to the first recorded activity of young people after leaving
school, such as entering higher education, further education, training, employment, or being unemployed.
• As noted above, we are currently contacting all school leavers (approx. 198) to ensure positive
outcomes and offer support as needed. 
• Results will be published by the Scottish Government in the new year. 
• Please click here to see last year’s results. School leaver attainment and destinations - gov.
scot 
3.2 Annual Participation Measure
The Annual Participation Measure (APM) reports on the education and employment activity of 16- to 19-
year-olds in Scotland. It is the source of the Scottish government's national performance indicator
“Percentage of young adults 16- to 19-year-olds participating in education, training or employment”. 
The APM method takes account of all status of 16- to 19-year-olds in Scotland over one calendar year from
the 1st of April to the 31st of March. We report on if they are participating, not participating and unconfirmed
is based on which status an individual spent to the greatest numbers of days within the year. 
See below the Annual Participation Measure from 2025 
Page 11

Page 12

For more information on the APM  please use this link to Annual Participation Measure 
4.Local Partnership Support
SDS local teams actively support the following partnerships:
• Developing the Young Workforce (DYW) – supporting employer events in schools
• Local Employability Partnership (LEP) – member
• Corporate Parent Board – supporting young people
• Community Learning Development (CLD) Partnership Board – member
• Community Justice Board – member
• Community Planning Partnership – member
•  
5. Skills Development Scotland - National Update
5.1 Skills Reform  
SDS continues to advocate for changes to the learning and skills system to deliver the best outcomes for
Scotland’s people and businesses.
Following the Scottish Government’s Independent Review of the Skills Delivery Landscape and the
Purpose and Principles on Post-school Education, Research and Skills, a consultation was held in Summer
2024. This informed an outline business case for simplifying the post-school funding landscape, including
proposals to move responsibility for apprenticeships and national training programmes to the Scottish
Funding Council (SFC).
Page 12

Page 13

The Tertiary Education and Training (Funding and Governance) (Scotland) Bill was introduced in February
2025 and is currently progressing through Parliament.
Subject to approval, the Bill is expected to become law in spring 2026, with changes coming into effect in
March 2027.
Until then, SDS will continue to deliver apprenticeships and national training programmes as usual.
5.2 Young People’s and Parents Research 
Our Programme of research with young people captures young people's perspectives on their career
journeys across from S1 through to the post school stages of education and career transitions. It also
provides evaluation evidence on the quality, value and benefits of our Career Information, Advice and
Guidance (CIAG) Services.  
• Pupil Voice Senior Phase (S4-S6). This research collected feedback from nearly 11,000 pupils in
2024, providing evaluation evidence on careers services and exploring broader themes related to
senior phase students' career journeys.   
• Young People’s Career Ambitions (1 year Post School). This research targets school leavers,
focusing on their career journeys a year after leaving school. The 2024 study engaged almost 3,000
participants, exploring influences, motivations, and post school experiences.  
• Pupil Voice (S1-S3), a new pilot will be launched in spring 2025. This project specifically focuses
on young people in S1-S3 and their career decision making process. 
• Parents and Carers in Scotland. In 2024 we gathered feedback from 4,000 parents and carers on
awareness and satisfaction with SDS services, information sources used, awareness and
perceptions of apprenticeships and confidence in having career conversations. 
Find Out More about Career Advice & Information Research - Click this link
6. Regional Skills Planning 
The latest Regional Skills Assessments (RSAs) for 2025 have been published and are now available on
the Skills Development Scotland (SDS) website. These reports provide a robust and consistent evidence
base to support partners in strategic skills investment planning. 
This year, the RSAs have been enhanced with:
• Region’s People Spotlight – Population trends using Census and NRS data, including equality
indicators.
• Granular Forecast Data – More detailed forecasts for total requirement, presented with an
intersection by both industry and occupation.
Following the success of last year’s publication, an up-to-date report on Scotland’s Labour Market
Drivers has been published to provide additional context. It offers a fresh overview of the key forces
shaping Scotland’s labour market outlook.
The RSA Summary Infographics continue to provide core measures down to local authority level in a
visual format, covering the economy and current and future demand in local areas across Scotland.  
Additional indicators have also been added to the Data Matrix, where data is available down to the local
authority level. Additional indicators include:
• Real-time employer demand - Information on job postings and top occupations.
• Detailed employment forecasts - By industry, occupation, and qualification.
Also now published are the latest Sectoral Skills Assessments (SSAs), including a new Digital
Practitioners Spotlight based on SDS research on the Digital economy.
Page 13

Page 14

7. Scottish Careers Week 10th – 14th November
Scottish Careers Week will take place from 10th to 14th November, delivered in partnership with a wide
range of organisations supporting informed career choices across Scotland.
8. Employer Support 
Skills Development Scotland works directly with employers, providing trusted advice to help invest
in skills, develop new talent, and grow businesses through inclusive recruitment and workforce
development.
• Free employer webinars are available on a range of themes.
• Skills for Growth is a free service for SMEs with 5–250 employees.
Find out more at our employer hub SDS Employer Hub or contacting us on 0800 783 6000 
9. Local contact
Susan MacRae  Area Manager  Argyll & Bute, Eilean Siar and Shetland 
susan.macrae@sds.co.uk 
10. Further information 
skillsdevelopmentscotland.co.uk - Corporate Website
myworldofwork.co.uk - for all your work, skills and learning needs
apprenticeships.scot - for all the latest on apprenticeships 
Page 14

Page 15

1   
Mid Argyll, Kintyre and the Islands Area Committee       
Date of Meeting: 3 December 2025 
Title of Report:  Health & Social Care Partnership - Performance Report – FQ1 2025/26 (April –
June) 
Presented by:    Kristin Gillies Head of Strategic Planning, Performance & Technology    
The Area Committee is asked to note and consider the: 
• Revised suite of 77 Key Performance Indicators within the Integrated Performance
Management Framework for 2025/26 
• Performance for FQ1 2025/26 (April – June 2025) 
• Delayed Discharge Sitrep as of 30 Jun 2025 (Appendix 1) 
• Latest performance against the National Health & Wellbeing Outcomes and
Ministerial Steering Group Integration Indicators (Appendix 2) 
EXECUTIVE SUMMARY 
This report details performance for the Financial Quarter (FQ) 1 2025/26 (April - June), the
performance outputs are taken from the Integrated Performance Management Framework (IPMF)
Reporting Dashboard with the focus on twelve key service areas, with a revised set of KPI being
implemented after annual review, ahead of the 2025/26 reporting year. 
Overall performance for FQ1 notes of 77 measures reported as on target (53%). The report details
performance against each of the service areas and the 77 supporting IPMF Key Performance
Indicators. Latest HSCP Activity Summary Dashboard and trajectory analysis across current
reporting year is included, as is the latest performance from the National Delayed Discharge Sitrep
and the National Health & Wellbeing Indicators performance. The use of the new performance
Dashboard within SharePoint is designed to offer a more focused approach to the access and
analysis of data, offering scope for self-service.   
2. RECOMENDATIONS
The committee are asked to note FQ1 25/26 performance which is scrutinised at Clinical and Care
Governance Committee and further reviewed by the IJB. 
3. DETAIL OF REPORT
The report details the HSCP (Health and Social Care Partnership) performance for FQ 1 2025/26
(April - June), highlighting key performance trends across the 77 KPIs (Key Performance Indicators).
Page 15 Agenda Item 6

Page 16

2
For 2025/26, the quarter 1 snapshot national update on Delayed Discharges (Appendix 1), alongside
the latest performance on the National Health and Wellbeing Outcomes Indicators (Appendix 2). 
4. RELEVANT DATA & INDICATORS 
4.1 FQ1 2025/26 (April – June) Performance Summary                                   
Overall performance for FQ1 notes that 77 KPI’s are scoring against target, with 41 (53%) reporting
as on-track. The KPI’s report performance against the target and include the target, actual and
variance and is a mix of both quantitative and qualitative indicators. The use of the green, amber
and red graphics within the Dashboard is used to give an overview of the HSCP’s total performance
for each of the twelve services and 77 KPI’s. The use of only green and red for the KPI’s is used to
focus delivery with regards to sustaining performance on or above target.   
4.2 Analysis of Key Performance  
This analysis identifies performance across the 12 service reporting categories within the Integrated
Performance Management Framework (IPMF). 
4.2.1 Children & Families
Across 5 KPIs, Children & Families and Justice performance notes 4 (80%) on track, with1 (20%)
off track, against the targets set for Q1 25/26. 
Performance on or above target: 
• Improve the percentage of Child Protection Register (CPR) cases that have an allocated
Social Worker met the 100% target this FQ1
• Children & Adolescent Mental Health Services (CAMHS) tier 3 seen within 18 weeks of
referral, 90% target was met in FQ1.
Page 16

Page 17

3
• Improve the number of teams that have delivered 85% or more of the Universal Health
Visiting Pathway (UHVP) met the target this quarter. 
• Health assessments started within 4 weeks of coming into care-exceeded the target of
96% (100%) 
Performance below target & areas for improvement: 
• Percentage of Justice Social Work reports submitted by 12 noon, 2 days before court
was below the target of 90%, reported at 80% this quarter. 
4.2.2 Strategy, planning, performance and digital
Performance across 11 Key Performance Indicators (KPIs) for Strategic Planning, Performance &
Technology Services shows 5 KPIs (45%) on track, with 6 KPIs (55%) reported as off track against
the targets set for FQ1 25/26.  
Performance on or above target: 
• Increase the number of new clients to Telecare services – exceeded the target of 200
(215).
• Increase the number of Telecare service reviews completed – exceeded the target of 85
(125).
• Increase the number of patients utilising ‘Near Me’ clinics – exceeded the target of 800
(972).
• Increase the utilisation of ‘Connect Me’ for blood pressure monitoring within primary
care – exceeded the target of 42 patients (124).
• Percentage of Transformation & Improvement projects on track – exceeded the target of
85% (100%). 
Performance below target & areas for improvement: 
• Increase in new referrals to Silvercloud – below the target of 70 (32).
• Waiting times for cancer appointments at the 31 and 62 day targets – above the target
of 0 breaches (7).
• Reduce new outpatient waiting times breaches >12 weeks – above the target of 46%
(47%).
• Reduce outpatient waiting list long waits >52 weeks – above the target of 0.0% (7.2%).
• HSCP FOI requests responded to within 20 working days – below the target of 100%
(94%).
• IT support requests resolved – below the target of 100% (34%).   
Scottish government has an acute focus on planned care, unscheduled care and CAMHS and this
is being addressed by a weekly high level huddle board wide with direct reporting to the minister
and sign off locally by management supporting an increased focus on booking and waiting list
management. 
4.2.3 Primary Care
Performance across 6 Key Performance Indicators (KPIs) for Primary Care shows 3 KPIs (50%) on
track, with 3 KPIs (50%) reported as off track against the targets set for FQ1 25/26.     
Performance on or above target: 
Page 17

Page 18

4
• 80% of children who received Fluoride Varnish treatment did not require referral for
further dental treatment – exceeded the target of 80% (84%).
• Vaccination delivery against National trends during autumn, winter and spring booster
programmes – met the target of 61% (Scotland wide percentage)
• Percentage of HSCP run GP practices enacting contingency measures – no practices
enacted contingency measures, actual 0 against a threshold of 14 
Performance below target & areas for improvement: 
• Percentage of planned activity carried out to deliver National Oral Health Improvement
Programmes against Service Plan – below the target of 100% (85%).
• Utilisation of HSCP Dental Clinic appointments – below the target of 75% (58%).
• Minimum 95% uptake for 6 in 1 vaccination in children by age 1 – below the WHO target
of 95% (94%). 
4.2.4 Public Health
Performance across 6 Key Performance Indicators (KPIs) for Public Health shows 1 KPIs (17%) on
track, with 5 KPIs (83%) reported as offtrack against the targets set for FQ1 25/26. 
Performance on or above target: 
• Mitigate health inequalities through increasing the number of referrals to community link
workers supported by “With You” ensuring health and wellbeing support is targeted to
areas of rural and socio-economic need. The target was set at 150, and we increased the
number of referrals to 174, exceeding the target by 24 (16%) above target. 
Performance below target & areas for improvement: 
• Increase number of successful quits, supported by NHS smoking cessation advisors or
jointly through shared care with Pharmacy, by people in the 40% most deprived areas in
Argyll and Bute, reporting undertaken a quarter in arrears – We set a target of 20, and we
achieved 14 (30%) below target.
• Report on the number of people in A&B attending training to deliver Community
Reinforcement and Family Training (CRAFT) to families – We set a target of 15 and the
actual reported in FQ1 was 0.
• Increase the number of people in Argyll and Bute attending training in the following areas,
Money Counts, Behaviour Change, Speakeasy, Mental Health and Suicide Prevention -
We set a target of 120 and the actual was 39, approximately 67.5% below target.
• Number of instances working with Scottish Government or National Agencies on National
Strategy and Policy Development. The target was set at 13, and we achieved 8, falling
short of the target by approximately 38.5%.
• Report on the number of engagements relating to planning with people with lived or
living experience of alcohol/or drugs – We set a target of 4, and we achieved 2
engagements, falling short of the target by 2 (50%). 
4.2.5 Finance 
Across 7 KPIs, Financial services performance notes 3 (43%) on track, with 4 (57%) off track
against the targets set for Q1 25/26.    
Performance on or above target:
Page 18

Page 19

5  
• Monitor Older People (OP) - Internal Residential Budget Spend % variance reported at
95% against 100% target
• Monitor Older People (OP) - External Residential Budget Spend % Variance reported at
95% against 100% target
• Monitor Older People (OP) - Homecare Budget Spend was noted at 92% against 100%
target 
Performance below target & areas for improvement: 
• Monitor Lorn & Islands Hospital overall budget is noted as off track and 7.9% over
budget at FQ1. 
• Monitor NHS saving recovery to ensure this remains on track. For Q1 the actual spend
is 35% of the annual budget, which suggests as the financial year progresses this may
go off track.
• Monitor Social Work savings recovery to ensure this remains on track. For Q1 the actual
spend is 49% of the annual budget, which suggests as the financial year progresses this
may go off track.
• Monitor the HSCP total budget to ensure this remains on track currently off track as at
quarter end by £2m (0.3%) 
4.2.6 Carers
Performance across 5 Key Performance Indicators (KPIs) for Carers shows 4 KPIs (80%) on track,
with 1 KPI (20%) reported as off track against the targets set for FQ1 25/26.  
Performance on or above target: 
• Increase the number of Adult Carer Support Plans completed across A&B Carers Centres
exceeded the target of 120 (127).   
• Increase the number of Unpaid Adult Carers supported across A&B Carers Centres
exceeded the target of 2700 (3107). 
• Increase the number of Unpaid Young Carers supported across A&B Carers Centres
exceeded the target of 783 (812).
• Increase the number of ACSP reviews completed by the various Carers Centres
exceeded the target of 1800 (1839). 
Performance below target & areas for improvement:  
  
• Increase the number of Young Carer Statements completed across A&B Carers Centres
below the target of 39 (29). 
4.2.7 Allied Health Professionals 
Performance across 5 Key Performance Indicators (KPIs) for Allied Health Professionals shows 1
KPIs (20%) on track, with 4 KPIs (80%) reported as off track against the targets set for FQ1 25/26. 
It should be acknowledged that nationally waiting time breaches are measured against a zero target
and it is a clear indicator of how many actual people are waiting. Local trajectory reporting allows
monitoring of progress and improvements to reduce the number of patients on waiting lists across
varied health specialties.
Page 19

Page 20

6   
Performance on or above target:   
• Increase the number of monthly AHP Outpatient Completed Waits exceeded the target of
945 (1017).
  
Performance below target & areas for improvement:   
• Reduce New Outpatient Referral waits breaching > 4 weeks for Musculoskeletal (MSK)
reported above the target of 0 (812).
• Reduce New Outpatient Referral waits breaching >12 week waits for AHP services
reported above the target of 0 (477).
• Reduce P1 and P2 Community Patient Referral waits breaching > 4 weeks for AHP
Services noted above the target of 0 (60).
• Reduce P3 and P4 Community Patient Referral waits breaching >12 week waits for AHP
services shows above the target of 0 (970). 
4.2.8 Delayed Discharges 
Performance across 6 Key Performance Indicators (KPIs) for Delayed Discharges shows 3 KPI
(50%) on track, with 3 KPIs (50%) reported as off track against the targets set for FQ1 25/26. 
It should be acknowledged nationally Delayed Discharges are measured against a zero target. Local
targets have been set to monitor progress and improvements to reduce the number of patients
showing as a Delayed Discharge.   
Performance on or above target: 
• The target to reduce the number of people delayed at monthly census point was 34, and
we achieved 32, exceeding the target by 2.
• The target to reduce the number of delays in hospital awaiting a care home placement
at monthly census point was 10, and we achieved 8, exceeding the target by 2.
• The target to reduce the number of people delayed with assessment code at monthly
census point was 10, and we had an actual of 7, exceeding the target by 3. 
Performance below target & areas for improvement: 
• The target to reduce the overall length of stay in hospital at monthly census point was
634, and our actual was 644, approximately 1.58% over the target.
• The target to reduce the number of people delayed in hospital with AWI code at monthly
census point was 4, and our actual was 5, just slightly missing the target by 1.
• The target to reduce the number of people delayed in hospital at monthly census point
due to care at home availability was 10, and our actual performance was 15, exceeding
the target by 50%. 
Page 20

Page 21

7
4.2.9 Adult Social Care 
Performance across 4 Key Performance Indicators (KPIs) for Adult Social Care shows 3 KPIs (75%)
on track, with 1 KPI (25%) reported as off track against the targets set for FQ1 25/26.   
Performance on or above target: 
• Increase the percentage of Older People who had their homecare monitoring review
completed within 6 months - Performance surpassed the target with an actual of 84%,
against a target of 60%. 
• Increase the occupancy rates across A&B Care Homes – We achieved 95%, exactly
matching the target.
• Reduce the number of hours of unmet need for care at home - The target was to reduce
hours to 500, and we achieved 417 hours, exceeding the reduction goal by
approximately 16.6%. 
Performance below target & areas for improvement: 
• Reduce unplanned admissions to A&B hospitals directly from a care home - The new
target set for this KPI was 18.  Our actual was 24, exceeding the target by 33%. 
4.2.10 Community Hospitals 
Performance across 5 Key Performance Indicators (KPIs) for Community Hospitals shows 5 KPIs
(100%) on track in FQ1 2025/26.  
Performance on or above target: 
• Reduce the rate of unplanned admissions to Community Hospitals for 65+ population -
The target was to reduce admissions to 450, and we achieved 449.
• Reduce the average length of stay for inpatients in A&B Community Hospitals – We
aimed to reduce the average LOS to 7.5 days and achieved 6.9, exceeding the target.
• A&E attendances meeting the 4 hrs wait target. The national target for attendances
meeting the 4 hours target is 95%, we achieved 96%.
• Maintain A&B Community Hospitals Bed occupancy rates below 80% target – The target
was to maintain bed occupancy below 80%, and actual occupancy was 61.8%.
• Reduce the number of falls being reported in a Community Hospital setting in A&B –
The target was to reduce falls to 38, and the actual number was 12.
  
Performance below target & areas for improvement: 
None   
4.2.11 Adults with Long Term Conditions / Adult Support & Protection / Alcohol Drugs
Partnership 
Performance across 8 Key Performance Indicators (KPIs) for Adults with Long Term Conditions
Services shows 3 KPIs (38%) on track, with 5 KPIs (62%) reported as off track against the targets
set for FQ1 25/26.   
It should be acknowledged that nationally waiting time breaches for New Mental Health Outpatients
(12 weeks) and Psychological Therapy (18 Weeks) are measured against a zero target. Local
Page 21

Page 22

8
targets have been set to monitor progress and improvements to reduce the number of patients on
waiting lists across varied health specialties 
Performance on or above target: 
• Reduce the number of people monthly waiting for psychological therapy services (>18
weeks) – exceeded the target of 175 (34).
• Mental Health urgent care referrals response timescales <2 hours – met the target of
90% (100%).
• Mental Health social circumstances report overdue – met the target of 33% (33%). 
Performance below target & areas for improvement: 
• Reduce the number of clients on the Dynamic Support Register with category
Amber/Red – above the target of 10 (18).
• Reduce the number of people waiting for a new Mental Health outpatient service (>12
weeks) – above the target of 390 (757).
• Increase the % of Adult Support Protection screening duty to inquire assessments
completed within 5 working days – below the target of 70% (40%).
• Increase the % of Adult Support Protection investigations completed within 15 working
days – below the target of 70% (32%).
• Drug & Alcohol completed waiting times from referral to first treatment (LDP) – below
the target of 90.0% (83.3%). 
4.2.12 Rural General Hospitals (Lorn & Island Hospital) 
Performance across 9 Key Performance Indicators (KPIs) for Rural General Hospitals (LIH) shows
6 KPIs (67%) on track, with 3 KPIs (33%) reported as off track against the targets set for FQ1 25/26. 
Performance on or above target: 
• Reduce the rate of unplanned admissions to LIH 65+ population. We aimed to reduce
unplanned admissions to 345. We achieved 315, approximately 9% under the target.
• Reduce the total number of unplanned bed days in LIH. We aimed to reduce the total
days to 3323 and successfully achieved 2810, 15.4% below the target.
• Maintain LIH Bed Occupancy Rates below 90% target. We set a target to maintain bed
occupancy below 90% and we maintained performance at 74.6%, 17.1% below the
target.
• Reduce the number of LIH A&E Attendances that result in an unplanned admission. We
set a target to reduce attendances to 19.2%, and we achieved 16.8%.
• Reduce the number of falls being reported in a hospital setting in LIH. We set a target to
reduce falls to 26, and only 7 were reported this quarter.
• Reduce the number of instances of tissue viability in Lorn & Islands Hospital.  We set a
target to reduce the number of instances to 4, with only 1 being reported this FQ. 
Performance below target & areas for improvement: 
• Reduce the Average Length of Stay for inpatients in LIH – Target is to reduce the
average LOS to 5 days and we reported 7 day this quarter.
Page 22

Page 23

9
• 95% of A&E attendances to meet the 4-hour wait target. This KPI has a national target
of 95% and we achieved 92% in FQ1. 
4.2.13 National Health & Wellbeing Outcome Indicators & Ministerial Steering Group
Integration Indicators 
The National Health and Wellbeing Outcomes provide a strategic framework for the planning and
delivery of health and social care services. This suite of outcomes serves to focus on improving the
experiences and quality of services for people using those services, carers, and their families. These
indicators form the basis of the annual reporting requirement for Health and Social Care
Partnerships across Scotland.   
The national indicators will be updated and reported within A&B HSCP’s Integrated Performance
Management Framework to provide the national performance position alongside the local service
Key Performance Indicators suite. 
The latest data in relation to 26 HWBOI and MSG Indicators reports 50% on track, with 13 on track
and 13 off track. An overview of A&B HSCP’s latest performance against the 26 measures is
reported in Appendix 1. It should be noted that reporting periods vary across the suite of national
indicator measures, with some measures reported quarterly affected by national reporting data lag. 
5. CONTRIBUTION TO STRATEGIC PRIORITIES
The monitoring and reporting against Key Performance Indicators using the Integrated Performance
Management Framework and Dashboard ensures the HSCP is able to deliver against key strategic
priorities. This in-turn is aligned with the Strategic Plan and key objectives. 
6. GOVERNANCE IMPLICATIONS
6.1 Financial Impact
Financial performance is evidenced within the IPMF Dashboard ensuring best value as well as
evidencing the impact and performance against organisational budget savings. 
6.2 Staff Governance
Key performance indicators within the IPMF ensure that staff governance requirements continue to
be progressed and developed include health and safety, wellbeing and new service redesign and
working practices. 
6.3 Care and Clinical Governance
Clinical Governance and patient safety remain at the core of prioritised service delivery against the  
new IPMF Dashboard and National Health & Wellbeing Outcomes Indicators. The new governance
structure supporting the IPMF ensures that the Clinical & Care Governance Committee remain
central to performance improvement. The development of the IPMF is focussed on moving away
from previous traditional styles of reporting to a fully collaborative approach with Head of Service
and Service Lead commentary. 
7. PROFESSIONAL ADVISORY 
Data used within the performance dashboard is fully accessible in SharePoint with data trends and
forecasting are identified to give wider strategic context. This provides the HSCP professional
advisors with self –service performance information to inform their role in maintaining professional
standards and outcomes.
Page 23

Page 24

10 
8. EQUALITY & DIVERSITY IMPLICATIONS
The Integrated Performance Management Framework captures relevant indictors used to inform the
HSCP E&D work.
8.1 PROTECTED CHARACTERISTICS
Performance detailed within this report acknowledges the rights of the Child (UNCRC), Islands.
Fairer Scotland, Socio-economic Duty, Equalities - protected characteristics.  
9. GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE 
Data use and sharing within this report and IPMF performance dashboard is covered within the
Argyll and Bute Council & NHS Highland Data Sharing Agreement 
10. RISK ASSESSMENT
Risks and mitigations associated with performance data sources and reporting are managed and
identified within the monthly Performance & Improvement Team- Work Plan. 
10.1 STRATEGIC, OPERATIONAL OR CLIMATE RISK
Performance reports are used by operational management to identify service delivery risk and to
inform mitigation action accordingly. 
11. PUBLIC & USER INVOLVEMENT & ENGAGEMENT
Performance reporting is available for the public via Argyll and Bute Council and NHS Highland
websites. The IPMF dashboard utilises SharePoint to support manager and staff access across the
HSCP. 
12. CONCLUSION 
The Integration Joint Board is asked to considerer and acknowledge FQ1 2025/26 (Apr - June)
performance as detailed in the IPMF Dashboard   
13. DIRECTIONS 
Directions
required to
Council, NHS
Board or
both.
Directions to: tick
No Directions required x
Argyll & Bute Council 
NHS Highland Health Board 
Argyll & Bute Council and NHS Highland Health Board 
14. PREVIOUS REVIEW OF THE REPORT 
Meeting  Title of report Date Output (if relevant)
Page 24

Page 25

11     
REPORT AUTHOR AND CONTACT 
Author Name: Douglas Hunter- Senior Manager Performance & Improvement
Email: douglas.hunter@argyll-bute.gov.uk
Page 25

Page 26

12 
Appendix 1 - Delayed Discharge Sitrep – 30th June 2025 
Page 26

Page 27

13 
Appendix 2 – HWBOI & MSG Integration Indicators. 
Core Suite of Integration Indicators 
HWBOI-Outcomes 
Data notes 55.5% (5 of 9) HWBOI Outcomes measures reporting as above the national Scotland Rate. It is worth noting that performance will be influenced and
vary in line with the total number of respondents participating in this voluntary survey. As such, caution should be noted with regards to previous comparison
and trends. Benchmarking performance against 7 comparator HSCPs is noted below. 
HWBOI – Outcomes - Benchmarking 
HWBOI- Performance Data 
Page 27

Page 28

14
Data notes 66.7% (6 of 9) HWBOI Performance measures reporting as above the national Scotland Rate. Note Indicators 17 and 19 are reported at FY 24/25
with measures 11, 12, 13, 14, 15, 16, 18 reported as at Calendar year 2024 as a proxy for 2024/25 due to the national data for 2024/25 being incomplete. This
is in line with guidance issued by Public Health Scotland which was communicated to all Health and Social Care Partnerships. Using more complete calendar
year data for 2024 should improve the consistency of reporting between Health and Social Care Partnerships. 
HWBOI- Performance Data – Benchmarking       
Page 28

Page 29

15
Ministerial Steering Group Indicators 
MSG Indicators 1.1, 1.2 and 2.1 are reported at Calendar Year 2024 as a proxy form 2024/25. This is in line with guidance issues by Public Health Scotland
which was communicated to all Health and Social Care Partnerships/ MSG Indicators data notes that all MSG measures have sustained higher activity or
have increased in the last reporting year. Activity around Emergency Admissions, Unplanned Bed Days, A&E attendances and Delayed Discharge Bed Days
all noted performance exceeding pre –Covid levels. This highlights the necessity to consider approaches to alleviate systems pressures around Urgent and
Unscheduled Care and expedite hospital flow, particularly around A&E Admissions and Delayed Discharges.
Ministerial Steering Group Indicators 2018/19 2019/20 2020/21 2021/22 2022/23  2023/24 2024/25
MSG 1.1 - Number of emergency admissions* CY 8,374 8,231 6,917 7,820 7,928 8,933  8,879
MSG 1.2 - Number of Admissions from A&E* CY 5,244 4,945 3,668 5,040 4,957 5,097  5,502
MSG 2.1 - Number of unplanned bed days acute
specialties* CY 65,794 64,008 53,390 67,255 77,094 77,882 80.655
MSG 2.2 - Number of unplanned bed days MH
specialties 13,747 13,204 11,208 9,049 9,212 11,575  11.380
MSG 3.1 - Number of A&E attendances 13,985 14,171 10,091 15,646 16,774 17,740  22,456
MSG 3.2 - % A&E attendances seen within 4 hours  93.4% 91.7% 93.1% 88.9% 83.9% 83.0%  83.0%
MSG 4.1 - Number of DD bed days occupied  9,530 7,863 5,354 7,742 11,929 12,757  14,042
MSG 5.1 - % of last six months of life by setting
community & hospital 90.0% 89.6 90.80% 90.80% 89.60% 89.40%  N/A
MSG 6.1 - % of 65+ population at Home (unsupported)  92.1% 92.1% 92.5% 92.6% 93.2% 93.4%  N/A 
Data notes 67% (6 of 9) HWBOI Outcomes measures reporting as above the national Scotland Rate. It is worth noting that performance will be influenced and vary in line with the total number of respondents
participating in this voluntary survey. As such, caution should be noted with regards to previous comparison and trends 
Page 29

Page 30

This page is intentionally left blank

Page 31

ARGYLL AND BUTE COUNCIL                                          MAKI AREA COMMITTEE                                                                                                         
ROADS AND INFRASTRUCTURE                    3 DECEMBER 2025
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 A Roads and Infrastructure standing report was a fixture on Area Committee
agendas throughout the life of the last Council. In the first two rounds of Area
Committee meetings in the new Council feedback was sought on the value of
these updates, and their format and frequency. Generally Members felt having a
standard item was beneficial and it was acknowledged that the Roads and
Infrastructure weekly briefings issued to all members each Friday afternoon
provide for the main sources of live information on current activities. On top of
these briefings there is a bank of resources on the new Member Zone system
which include the weekly briefings, subject specific briefings, ad hoc short
briefings on issues, relevant previous committee reports, operational service
procedures, legislation and Council policies. 
1.2 In the last Council the purpose of these reports was to provide an update on
service activities but since weekly briefings these have largely superseded the
original stated purpose of these reports. 
1.3 On the basis of the above this new format has been agreed through the
December 2022 round of area committees for this standing item. This format
removes duplication for Officers and rather links to existing published
information, with additional updates only in the body of the reports if these are
specifically requested/noted from previous meetings. The report remains as a
standing item and continues to provide the opportunity for Officer engagement at
the committee meetings.   
2.0 RECOMMENDATIONS 
It is recommended that the Area Committee: 
2.1 Note and consider the contents of this report. 
3.0 DETAIL 
3.1 Roads and Infrastructure Services provides Members with weekly briefings on
topical service activities which are all available here.   
Page 31 Agenda Item 7

Page 32

3.2 As part of the resources on the new Member Zone system there are various key
documents available in an online library here. 
3.3 There are also additional online resources covering the streetlighting, footway,
surface dressing and roads reconstruction programmes available on the website
here. 
4.0 CONCLUSION 
4.1 This report provides links to existing published information on service activities
and provides for the opportunity for officer attendance and engagement at
committee meetings. 
5.0 IMPLICATIONS 
5.1 Policy – Roads and Infrastructure work to a number of agreed policies across
the range of service areas. 
5.2 Financial – revenue and capital budgets are in place to deliver projects and
cyclic work. 
5.3  Legal – Roads and Infrastructure Services work to a number of different pieces
of legislation such as the Roads Scotland Act 1984 and the Environmental
Protection Act 1990. 
5.4  HR – none known. 
5.5  Customer Service – none known. 
5.6. Risk – risk managed through toolbox talks, safety briefings and where
appropriate risk registers – all of the above are monitored through the RIS
leadership and management teams. 
5.7  Climate Change - due regard will be given to climate change with a view to
minimising any climate change impact and these are considered as and when
they arise. 
5.8  Fairer Scotland Duty – none known. 
5.9  Equalities - protected characteristics – where appropriate EqSEIAs will be
carried out to identify any implications. 
5.10  Consumer Duty – where appropriate EqSEIAs will be carried out to identify any
implications. 
5.11    Islands – where appropriate Island impacts assessments will be carried out to
identify any implications. 
Page 32

Page 33

5.12    Children’s Rights and Wellbeing – none known. 
Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services, Councillor John
Armour 
30 October 2025 
For further information contact: 
Andy Summers, Head of Roads and Infrastructure Services 
andrew.summers@argyll-bute.gov.uk 
Mark Calder, Project Manager 
mark.calder@argyll-bute.gov.uk 
Page 33

Page 34

This page is intentionally left blank

Page 35

Electric Vehicle
Charging Strategy
MEMBER SEMINAR
20TH OCTOBER 2025
This Photo by Unknown Author is
licensed under CC BY-SA-NC
This Photo by Unknown Author is licensed
under CC BY
Page 35
Agenda Item
8

Page 36

Background
 2022 – Strategy approved: aim to fill geographic
gaps and achieve equitable coverage.
 2023–24 – Expansion plan and methodology
developed – 55 sites identified
 2024 – Committee reaffirmed direction while
awaiting EVIF funding.
Page 36

Page 37

Current expansion plan
 In 2022 the Council approved an EV
Charging Strategy based on two delivery
themes:
 Charging on the Move – ensuring drivers
can travel through Argyll confidently.
 Destination Charging – providing chargers
where people dwell.
 That approach assumed further funding
would follow
Page 37

Page 38

Funding secured
 We now have £1.033million
secured for the next phase – so
the key question is how best to
invest it?
 In Dec 2022 our 55-site plan
was estimated at £1.65million,
based on previous average
costs plus inflationary
adjustment
Page 38

Page 39

A hub-based approach
 The original 55-site plan (Dec 2022) costed at £1.65m can’t be
delivered in full with the £1.033m now secured.
 We therefore need to prioritise investment where it has the
greatest impact.
 We are therefore proposing a hub-based approach – clusters
of chargers in key towns and island centres – providing:
 Reliability: multiple chargers reduce the risk of faults or queues.
 Better use of funds: higher usage = better cost recovery and
maintenance value.
 Visitor and local benefit: located where people already spend
time and money.
 Platform for future growth: once hubs are established, we can
extend outwards to smaller communities and ferry points
(“spokes”
 This hub-first model does not remove the ‘Charging on the
Move’ theme — it remains central to ensuring through and
onward connectivity along all major corridors
Page 39

Page 40

Proposed hub methodology
Strategic principle: Build reliable, visible hubs first, then
expand to smaller “spokes” once the network backbone is
established, ensuring full route coverage across Argyll and
Bute. This also complements the existing network.
 Identify sites that deliver strategic coverage – locations
where people visit, shop and work
 Potential for high utilisation
 Represent value for money
 Access to local amenities
 Avoid duplicating private provision
 Resilience and cluster logic
Page 40

Page 41

Proposed hub methodology
 We have a proposed criteria for this based on population. The
hub (single-site) methodology is:
*when not near an existing large town
 We will add in an element of population swell through tourist
locations where they would therefore move up to the next
bracket:
 Population centres proposed for hubs reflect places where
visitors and residents visit, rather than domestic users charging
at home
Population Rapid Fast Total
10k plus 5 5 10
5k to 10k 3 3 6
2k to 5k* 2 2 4
Page 41

Page 42

Proposed hub methodology
Town/area Pop Tourist swell Hub/cluster
Helensburgh 13k N 5R; 5F
Oban 8.5k Y 5R; 5F
Dunoon 8.9k N 3R; 3F
Lochgilphead 2.3k N 2R; 2F
Campbeltown 4.5k N 2R; 2F
Islay – Bowmore 3k island Y 3R; 3F
Mull – Craignure 3k island Y 3R; 3F
Bute – Rothesay 6k island N 3R; 3F
Page 42

Page 43

Proposed hub methodology
To progress this we have asked our consultants to:
 Assess the current provision in each location
including non ABC operated publicly available
chargers. That assessment should consider as a
‘’hub’’ any chargers within a cluster area less than
one mile  from the hub site identified in the above
table
 Focus on new hubs/expansion of existing to be on a
single site
 Identify the number and type of chargers required
to meet the above hub targets, after accounting for
existing provision both Council and non-Council.
Page 43

Page 44

Proposed hub methodology
 Assuming hubs/clusters will be developed on
existing sites, base on following as the core
deliverability criteria on the basis we are trying to
assess if sites pass or fail:
 Proximity to existing electrical infrastructure;
 Compliance with accessibility standards;
 No flood risk
 Strong data connectivity
 To assess in binary terms whether the sites pass or fail
Page 44

Page 45

Proposed hub methodology
 Include usage information on existing chargers at
current sites.
 Determine total costs for any additional EVCs
required to meet the above requirement. Assume
mid range costs
 Assess scalable expansion options at each site
Page 45

Page 46

Proposed approach
 Total funding secured: £1.033 million
 £100k reserved for repairs and maintenance (de-
risking current network)
 £100k held as contingency for cost fluctuations.
 That leaves £833k for new delivery.
 Proposal:
 Deliver Phase 1 Hubs from this £833k.
 Once hub costs are known, apply the roads capital
percentage split to the remaining balance for Phase 2
(smaller “spoke” sites)
Page 46

Page 47

Proposed approach
Phase 1 – Strategic Hubs
 Priority delivery of key sites across Argyll and the islands.
 Exact costs dependent on DNO connection estimates.
 Focus on reliability, visibility and usage.
Phase 2 – Local delivery
 Remaining balance after hubs delivered.
 Split by the roads capital percentage to maintain equity:
 Bute & Cowal – 19.78%
 Helensburgh & Lomond – 10.67%
 Mid Argyll, Kintyre & Islay – 32.71%
 Oban, Lorn & the Isles – 36.84%
 Phase 2 decisions at local level (area committees)
Page 47

Page 48

Phase Two – local delivery
 Phase 2 delivery will focus on individual chargers
and smaller sites (‘spokes’) that maintain network
continuity and local access.
 These sites could be selected and prioritised by Area
Committees within their allocated share, to support
local decision-making and flexibility under the
strategic framework.
 Ensures alignment with the original thematic
principles and equitable access across rural routes
and communities.
Page 48

Page 49

Proposed next steps
 Finalise consultant outputs (deliverability-only).
 Confirm hub costs with DNO.
 Draft full delivery plan for EDI Committee (Dec
2025).
 Ongoing engagement with Members through area
committees.
Page 49

Page 50

Risks and dependencies
 Hub costs unknown – DNO connection and ground
conditions may vary widely.
 Private sector overlap – expansion by supermarkets,
forecourts, etc. must be tracked to avoid duplication.
 Maintenance load – the growing network is managed
by one officer; current resource may not be
sustainable.
 Tariff sustainability – need to balance affordability with
cost recovery.
 Back-office transition – migration to Scottish
Power/Fuuse underway; minor risk of disruption during
switchover.
Page 50

Page 51

Operational update
 37 Council-operated public chargers currently in
place across Argyll and Bute.
 New regional back-office contract through Scottish
Power (Fuuse platform):
 Improves automation and fault reporting.
 Allows dynamic tariffs and local control.
 Tariff remains £0.70/kWh – good balance between
recovery and affordability.
 Improved uptime under new maintenance
arrangements.
Page 51

Page 52

Cross-footway charging
 Growing number of residents requesting to charge from
home over public pavements.
 No national guidance from Transport Scotland.
 Local phased approach:
 Short-term: trial approved cable protectors.
 Medium-term: ducting pilot (2026).
 Long-term: formal policy and asset register.
 Working with disability groups to ensure accessibility
compliance
 This could be a potential source of modest future
income – in a similar way to drop kerbs
Page 52

Page 53

Discussion
 Is the hub-first, theme-led model the right direction?
 Are the proposed funding splits fair?
 Any concerns on rural coverage?
 What role should private providers play?
Page 53

Page 54

This page is intentionally left blank

Page 55

Classification: OFFICIAL#
AREA TOWN/VILLAGE EXISTING LOCATION COUNCIL
OWNED PROPOSED THEME PRIORITY COMMENTS
PIER, FERRY ROAD Y 1 x RAPID 1 1
To address a rapid charging network gap
between Campbeltown and Lochgilphead
[on the public road network for drivers]
TAYINLOAN FERRY FERMINAL Y 1 x RAPID 1 1 Rapid charger to be provided for cars in the
ferry queue as opposed to parked up.
TAYINLOAN FERRY FERMINAL Y 1 x FAST or
SLOW [TBC] 2 1
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
FERRY TERMINAL Y 1 x RAPID 1 2
Rapid charger to be provided for cars in the
ferry queue as opposed to parked up. As
part of ongoing works under the Marine
Asset Management Plan we are looking at
options for electricity upgrades for harbour
infrastructure which would include
capacity for EVC
FERRY TERMINAL Y 1 x FAST 2 2
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
CARRADALE SHORE ROAD CAR PARK Y 1 x RAPID 1 2 To address  a network gap in East Kintyre
CAMPBELTOWN ROAD CAR
PARK Y 1 x RAPID 1 1
To address an existing rapid charging
network gap between Campbeltown and
Lochgilphead. We have beneiftted from
45k of funding from SSE for use at this
location
1 x FAST CAMPBELTOWN ROAD CAR
PARK Y
Key
Chargers beyond economic life and removed from use
Chargers beyond economic life to be replaced via CCG to comply with new regulations
Sites expected to be delivered in 2025
Sites delivered since last update December 2022
Chargers beyond economic life and replaced as part of FASTER Project
TAYINLOAN
GIGHA
TARBERT
MID-ARGYLL,
KINTYRE AND
THE ISLANDS
Page 55

Page 56

Classification: OFFICIAL#
NEW QUAY CAR PARK y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-
street car parks. Divergence from the
'higher to lower' original criteria of car
parks on the basis of local geography.
1 x RAPID NEW QUAY CAR PARK y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
ARDRISHAIG CHALMERS ST No. 2 CAR PARK 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST
AND 1 x
RAPID
LORNE ST No. 1 CAR PARK Y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
2 x FAST MANSE BRAE CAR PARK Y
INVERARAY
1 x FAST
AND 1 x
RAPID
THE AVENUE Y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
COLONSAY COLONSAY AIRPORT Y 1 x FAST or
SLOW [TBC] 2 4
Island airport. Through enabling funding
secured from TS we are working with
colleagues in Strategic Transport to
explore options for power upgrades here
which would both serve the airport itself,
which currently has no mains power, as
well as provide for EVC.
BOWMORE
1 x RAPID
AND 1 x
FAST
SCHOOL STREET CAR PARK Y
FERRY TERMINAL Y 1 x RAPID 1 2 Rapid charger to be provided for cars in the
ferry queue as opposed to parked up.
FERRY TERMINAL Y 1 x FAST or
SLOW [TBC] 2 2
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
CRAIGHOUSE ISLAY COUNCIL CAR PARK 1 x FAST 2 3
Proposed instead of Feoilin ferry terminal
with a view to providig for the main service
centre, also noting that the ferry crossiNG
s relatively short and there is provision on
the Islay side
13
MID-ARGYLL,
KINTYRE AND
THE ISLANDS
CAMPBELTOWN
LOCHGILPHEAD
PORT ASKAIG
Page 56

Page 57

Classification: OFFICIAL#
ADDITIONAL CHARGERS DELIVERED THROUGH HITRANS FASTER
MID-ARGYLL,
KINTYRE AND
THE ISLANDS TARBERT 1 x RAPID FERRY TERMINAL
PROJECT AUTUMN/WINTER 2023
Page 57

Page 58

This page is intentionally left blank

Page 59

ARGYLL AND BUTE COUNCIL    MID ARGYLL, KINTYRE AND THE ISLANDS     
AREA   COMMITTEE                                                 
CUSTOMER SUPPORT SERVICES     3 DECEMBER 2025 
AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ2 2025/26 
1.0 EXECUTIVE SUMMARY 
Performance data is recorded and reported quarterly for each Council department as
well as for the Council as a whole. Each of the Council’s four administrative areas is
represented by an Area Committee. The performance information presented to these
committees is tailored to address topics of particular relevance and importance to the
respective area. 
Area committee are requested to note and consider the performance and supporting
commentary as presented. 
Page 59 Agenda Item 9

Page 60

ARGYLL AND BUTE COUNCIL  MID ARGYLL, KINTYRE AND THE
ISLANDS AREA COMMITTEE 
CUSTOMER SUPPORT SERVICES        3 DECEMBER 2025 
AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ2 2025-26 
2.0 INTRODUCTION 
2.1 This paper presents the Area Performance Report for Financial Quarter 2 2025/26
(July – September 2025) and illustrates the agreed performance measures. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that the Area Committee –
a) Notes and considers the performance and supporting commentary as
presented. 
4.0 DETAIL
4.1 This paper presents the Area Performance Report for Financial Quarter 2
2025/26 (July – September 2025) and illustrates the agreed performance measures.
4.2 The features of the Performance Report are as follows: -
 Indicators are grouped by Corporate Outcome.
 The data table for each indicator is colour coded to identify the level of
reporting.
o Area level measures are blue
o Council level measures are grey
o COI measures are white 
 Each indicator details the
o Target, Actual and Performance status (Green / Red / No Target) for
the current and four previous financial quarters.
o Commentary for the current financial quarter only.
o Narrative explaining the performance trend e.g. This indicator is
above Target and performance has improved since the last reporting
period.
Page 60

Page 61

o Where appropriate a Performance Trend Line has been added.
o The name of the Responsible Officer.
o Where possible performance is presented at both Area and Council
level. 
4.3 The commentary for each indicator helps ‘Tell Our Story’ and enables Elected
Members to put the performance data into perspective and understand if an issue
is local in nature or should be escalated up to a Strategic Committee. 
4.4 As part of our improvements to performance reporting and making best use of the
digital technology available to us, the information contained in this report is also
available in your online scorecard which can be accessed via the Members area
on The Hub. If support is required to navigate the online scorecard, please
contact lorna.gillies@argyll-bute.gov.uk
4.5 To improve the response to performance queries, it is requested that should there
be any queries that either the Responsible Person or Kay Owen are contacted.
This should enable some queries being resolved or clarified prior to the Area
Committee meeting and therefore being carried forward as Actions at a
subsequent meeting 
5.0 CONCLUSION
5.1 Area Committee are asked to note and consider the performance and
supporting commentary as presented. 
6.0 IMPLICATIONS 
6.1 Policy     All of the indicators in this report are based on 
agreed Council policy. 
6.2 Financial    All indicators with financial implications are actively     
managed through agreed budget monitoring 
processes. 
6.3 Legal All appropriate legal implications are complied
with. 
6.4 HR    All HR implications are actively managed 
through agreed Wellbeing and Management 
monitoring processes.
6.5 Customer Service   All activities with customer feedback or insight are     
rigorously monitored for improvement.
6.6 Risk    Without this information Elected Members are less     
informed of activities within their area 
Page 61

Page 62

6.7 Climate Change   The Council is committed to working towards net     
zero. 
6.8 Fairer Scotland Duty  None arising directly from this report. An IIA is not
required for performance reporting. 
6.9 Equalities -protected
characteristics  None arising directly from this report. All activities
monitored in this report comply with the council’s
equality policies and obligations. An IIA is not
required for performance reporting. 
6.10 Consumer Duty None arising directly from this report. An IIA is not
required for performance reporting. 
6.11 Island Communities None arising directly from this report. An IIA is not
required for performance reporting. 
6.12 Children’s Rights and 
Wellbeing  None arising directly from this report. An IIA is not
required for performance reporting. This report
highlights examples of how the Council is
committed to and working towards reducing child
poverty and improving outcomes for every child. 
Kirsty Flanagan 
Executive Director  
7th November 2025 
For further information contact:  
Jane Fowler 
Head of Customer Support Services 
APPENDICES 
Appendix 1 FQ2 2025/26 All Areas Performance Report 
Page 62

Page 63

#
Indicator Responsible Person Reported Page
COI - Maximise distribution of Scottish Welfare Fund Fergus Walker A&B only 3
COI - Percentage of clients satisfied that they are better able to deal with their financial problems following
our support and intervention Lee Roberts A&B only 4
Number of parking penalty notices issued Hugh O'Neill Area 5
Car parking income to date (cumulative) Hugh O'Neill Area 6 - 7
Number of dog fouling complaints Tom Murphy Area 8
COI - Increase the percentage of our care experienced young people that have the recommended additional
tracking and monitoring plans in place Louise Chisholm A&B only 9
COI - Provide quality meals within cost margins to all pupils Christine Boyle A&B only 10
Maximise the percentage of 16-19 year olds participating in education, training or employment Jennifer Crocket Area 11
2025/26 FQ2 Mid Argyll, Kintyre and Islay Performance Report
The information presented is a summary of the agreed measures.
Unless stated otherwise, performance is presented at both Area and Council-wide levels.
The measure shows the performance against target for the current previous three reporting periods with an explanation of performance trend.
Where appropriate a trend line has been added to illustrate movement in 'Actual' over the reporting period.
Corporate Outcome: People live active, healthier and happier lives
Corporate Outcome: People live in safer and stronger communities
Corporate Outcome: Children and young people have the best possible start
Corporate Outcome: Education, skills and training maximises opportunities for all
Page 63

Page 64

Classification: OFFICIAL#
Indicator Responsible Person Reported Page
Number of affordable social sector new builds completed per annum Kelly Ferns Area 12
Percentage of pre-planning application enquiries processed within 20 working days Peter Bain Area 13 - 14
Average number of weeks to determine householder planning applications Peter Bain Area 15 - 16
Number of empty properties Jonathan Welch Area 17
COI - Number of new homeless applicants who required temporary accommodation this period Morven Macintyre A&B only 18
COI - Maintain the percentage of local suppliers that benefit from the award of contracts via the
procurement portal Anne MacColl-Smith A&B only 19
COI - Increase the number of community benefits that are delivered through contracts we award locally Anne MacColl-Smith A&B only 20
Percentage of street lighting faults repaired within 10 days Tom Murphy Area 21
Number of waste collection complaints Tom Murphy Area 22
COI (part) - Percentage of waste recycled, composted and recovered Andy Summers Area 23 - 24
COI - Number of tonnes of waste sent to landfill Andy Summers A&B only 25
COI - LEAMS (Local Environment Audit and Management System) Tom Murphy Area 26 - 27
COI - Teacher sickness absence Jennifer Crocket (B&C and MAKI)
Wendy Brownlie (H&L and OLI) Area 28
COI - LGE staff (including non-Teacher) sickness absence Carolyn Cairns Area 29
COI - Increase the percentage of all self-service automated contacts Robert Miller A&B only 30
Corporate Outcome: We have an infrastructure that supports sustainable growth
Corporate Outcome: Making it happen
Corporate Outcome: Our economy is diverse and thriving
Page 64

Page 65

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 95.3% 123.0% 27.7% Green - Actual
exceeds Target
In FQ2 2025/26, we received a total of 1013 applications to the Scottish Welfare Fund, comprising 676 Crisis Grant
applications and 337 Community Care Grant applications.  We made 593 awards to the value of £281,810. 420 Crisis Grant
awards and 173 Community Care Grant awards, which is a 9% increase compared to the same period last year. Our
expenditure of £281,810 at the end of FQ2 is £52,668 above the profiled budget. We are continuing to support applications
from medium and high priorty cases but monitoring this closely.
Period Actual FQ1 Commentary
2024/25 FQ2 72.9%
2024/25 FQ3 79.7%
2024/25 FQ4 119.8%
2025/26 FQ1 119.0%
2025/26 FQ2 123.0%
Corporate Outcome - People live active, healthier and happier lives
COI - Maximise distribution of Scottish Welfare Fund
Responsible Person: Fergus Walker
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Actual trend line
In FQ1 2025/26, we received a total of 510 applications to the Scottish Welfare Fund, comprising 347 Crisis Grant applications
and 163 Community Care Grant applications. We made 312 awards in total to the value of £135,819. 227 Crisis Grant awards
and 85 Community Care Grant awards reflecting a 13% increase compared to the same period last year. Our allocated budget
from the Scottish Government for 2025/26 is £458,284. Our expenditure of £135,819 at the end of FQ1 is £21,249 above the
profiled budget for the quarter. This higher spend indicates the growing pressure on the fund and highlights the ongoing
importance of the Scottish Welfare Fund in providing vital support to individuals and families facing financial hardship. The
Council currently provides support for both medium and high priority cases under SWF and DHP. This is subject to ongoing
review, and should circumstances require a recommendation will be made to restrict support to high-priority cases only.
3
Page 65

Page 66

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 100% 100% 0% Green - Actual
meets Target
This is a voluntary survey with no obligation for clients to respond either in full or in part. It is also common for incomplete
returns to be received. In FQ2 2025/26, 14 survey forms were distributed to clients. 5 were returned. Of these 5 returns, 5
responded to the question relating to being better able to deal with their financial problems. Of these 5 respondents, 5
responded positively, whilst 0 responded negatively. Accordingly, 100% of clients that responded were positive about their
experience i.e. no negative comments or responses were reported.
Period Actual FQ1 Commentary
2024/25 FQ2 100%
2024/25 FQ3 100%
2024/25 FQ4 100%
2025/26 FQ1 100%
2025/26 FQ2 100%
Actual trend line
This is a voluntary survey with no obligation for clients to respond either in full or in part. It is also common for incomplete
returns to be received. In FQ1 2025/26, 7 survey forms were distributed to clients. 7 were returned. Of these 7 returns, 6
responded to the question relating to being better able to deal with their financial problems. Of these 6 respondents, 5
responded positively, whilst 0 responded negatively. Accordingly, 100% of clients that responded were positive about their
experience i.e. no negative comments or responses were reported.
Corporate Outcome - People live active, healthier and happier lives
COI - Percentage of clients satisfied that they are better able to deal with their financial problems following our support and intervention
Responsible Person: Lee Roberts
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 meets the target with no change in performance since the last reporting period.
4
Page 66

Page 67

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI No Target 123 N/A N/A
A substantial increase in Penalty Charge Notices compared to the same quarter of the previous financial year. This is largely
due to a warden being based within MAKI following the increase to the warden team (increased from 6 to 8 in March 2025). 
The increase has allowed a more regular focus within MAKI.  Another impact is the  introduction and enforcement of the
pavement parking prohibtions under Part VI of the Transport (Scotland) Act 2019.
Period Actual FQ1 Commentary
2024/25 FQ2 78
2024/25 FQ3 25
2024/25 FQ4 49
2025/26 FQ1 171
2025/26 FQ2 123
2025/26 FQ2 A&B No Target 2,090 N/A N/A
There is an approximate 10% variance in Penatly Charge Notcies compared to the same quarter of the previous financial year. 
The most likley cause of the reduction is the bedding in of the Luss Traffic Management Order and the associated reduction of
breaches, as visitor and local drivers become more familiar with the restrictions.
Period Actual FQ1 Commentary
2024/25 FQ2 2,302
2024/25 FQ3 968
2024/25 FQ4 1,253
2025/26 FQ1 2,536
2025/26 FQ2 2,090
This indicator for FQ2 shows the number of parking penalty notices has decreased since the last reporting period.
Actual trend line
Numbers tracking higher than previous FQ1.  Impacted by both the period of good weather and the introduction of the
pavement parking prohibitions.
This indicator for FQ2 shows the number of parking penalty notices has decreased since the last reporting period.
Actual trend line
Numbers higher than previous FQ1, there is now a warden based in MAKI and impacted by the enforcement of the pavement
parking prohibitions.
Corporate Outcome - People live in safer and stronger communities
Number of parking penalty notices issued
Responsible Person: Hugh O'Neill
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
5
Page 67

Page 68

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI £60,506 £60,678 £172 Green - Actual
exceeds Target On target and up from same quarter in 2024/25. 
Period Target Actual FQ1 Commentary
2024/25 FQ2 £56,242 £49,027
2024/25 FQ3 £71,792 £72,739
2024/25 FQ4 £71,942 £71,637
2025/26 FQ1 £25,325 £25,842
2025/26 FQ2 £60,506 £60,678
£5,961
£11,964
£15,834
£1,078
£0
£34,837
Income Collected During FQ2
Fisher Row, Inveraray
The Avenue, Inveraray
Front Street and Toilets, Inveraray
Lorne Street, Lochgilphead
MAKI
Total
This indicator for FQ2 shows the cumulative amount of income has exceeded the cumulative target.
Actual trend line
There is no trend as this data is
cumulative as of FQ1 each financial year.
Despite target being rasied compared to previous FQ1, target has been met.
Corporate Outcome - People live in safer and stronger communities
Car parking income to date (cumulative)
Responsible Person: Hugh O'Neill
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
6
Page 68

Page 69

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B £681,962 £675,793 -£6,169 Red - Actual
below Target Less than 1% variance in income.  Supports the current target having been set correctly.
Period Target Actual FQ1 Commentary
2024/25 FQ2 £594,132 £639,207
2024/25 FQ3 £832,042 £887,707
2024/25 FQ4 £963,049 £1,011,360
2025/26 FQ1 £309,143 £309,660
2025/26 FQ2 £681,962 £675,793
This indicator for FQ2 shows the cumulative amount of income is lower than the cumulative target.
Actual trend line
There is no trend as this data is
cumulative as of FQ1 each financial year.
Despite target being rasied compared to previous FQ1, target has been met (over 100% achieved).
Car parking income to date (cumulative)
Corporate Outcome - People live in safer and stronger communities
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
Responsible Person: Hugh O'Neill
7
Page 69

Page 70

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI No Target 17 N/A N/A There were 17 dog fouling complaints received this quarter for the MAKI area, Isle of Islay 0, Kintyre 6 and Mid Argyll 11
Period Actual FQ1 Commentary
2024/25 FQ2 12
2024/25 FQ3 26
2024/25 FQ4 31
2025/26 FQ1 20
2025/26 FQ2 17
2025/26 FQ2 A&B No Target 36 N/A N/A
The total number of dog fouling complaints received this quarter was 36.  There were no dog fouling fines issued over July,
August and September, it is difficult to issue fines as the Wardens have to act on information given or witness it.  As always
when time allows the Warden service will continue to monitor and patrol.
Period Actual FQ1 Commentary
2024/25 FQ2 33
2024/25 FQ3 65
2024/25 FQ4 75
2025/26 FQ1 44
2025/26 FQ2 36
This indicator for...
Actual trend line
The number of dog fouling complaints have dropped significantly this quarter compared to last. The Warden service will
continue to monitor and patrol when time allows.
This indicator for FQ2 shows the number of dog fouling complaints has decreased since the last reporting period.
Actual trend line
There has been a drop in the number of dog fouling complaints this month for the MAKI area, with 20 complaints received,
with Islay receiving 4, Kintyre 11 and Mid Argyll 5.
Corporate Outcome - People live in safer and stronger communities
Number of dog fouling complaints
Responsible Person: Tom Murphy
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
8
Page 70

Page 71

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 100% 100% 0% Green - Actual
meets Target
Each care experienced child and young person (CECYP) enrolled in an authority school continues to have tracking and
monitoring in place via our education management system, known as Seemis.  Data collected includes attendance, exclusions,
progress and attainment and wellbeing information. The Virtual School adds an additional layer of scrutiny to this process
through a series of attainment meets and partnership working, helping to ensure our CECYP have the supports required. Our
bespoke care experience application is now live and supports the care Experience Education Team access real time
information.   We continue to work with partner agencies and other local authorities to support our CECYP hosted out with
Argyll and Bute.
Period Actual FQ1 Commentary
2024/25 FQ2 100%
2024/25 FQ3 100%
2024/25 FQ4 100%
2025/26 FQ1 100%
2025/26 FQ2 100%
Actual trend line
Each care experienced child and young person (CECYP) enrolled in an authority school has tracking and monitoring in place via
our education management system, known as Seemis. Data collected includes attendance, exclusions, progress and
attainment and wellbeing information. The Virtual School adds an additional layer of scrutiny to this process through a series
of attainment meets and partnership working, helping to ensure our CECYP have the supports required. Our bespoke care
experience application testing phase will begin in the new academic year. We continue to work with partner agencies and
other local authorities to support our CECYP hosted out with Argyll and Bute.
Corporate Outcome - Children and young people have the best possible start
COI - Increase the percentage of our care experienced young people that have the recommended additional tracking and monitoring plans in place
Responsible Person: Louise Lawson
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 meets the target with no change in performance since the last reporting period.
9
Page 71

Page 72

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B +/-5.00% -4% -2% Green - Actual
exceeds Target
We will continue to monitor schools not achieving the +/- 5% target
B&C 0.81%, H&L -4.63%, MAKI -8.05%, OLI -3.35%
Period Actual FQ1 Commentary
2024/25 FQ2 -1.37%
2024/25 FQ3 0.14%
2024/25 FQ4 -2.25%
2025/26 FQ1 3.17%
2025/26 FQ2 -3.50%
COI - Provide quality meals within cost margins to all pupils
Responsible Person: Christine Boyle
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 within the +/-5.00% variance however performance has decreased since the last reporting period.
Actual trend line
We will continue to monitor schools not achieving the +/-5% target.
B&C 5.18%, H&L 3.04%, MAKI -1.67, OLI 7.57%
Corporate Outcome - Children and young people have the best possible start
10
Page 72

Page 73

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 94.00% 94.60% 0.60% Green - Actual
exceeds Target
As of 7th October 2025 the participation figure (16–19-year-olds in employment, training or education) in Mid-Argyll, Kintyre
and Islay was 754 young people, which equates to 94.60%. This is 0.6% above the target and 0.1% above the annual Argyll and
Bute participation figure of 94.5% which was released by Skills Development Scotland at the end of August 2025. The
participation figure of 94.60% for FQ2 of 2025/26 is a decrease of 0.79% on the participation figure for FQ1 of 2025/26, and
represents a decrease of 2.03% on the FQ2 figure from 2024/25.
Period Actual FQ1 Commentary
2024/25 FQ2 96.63%
2024/25 FQ3 95.20%
2024/25 FQ4 94.60%
2025/26 FQ1 95.39%
2025/26 FQ2 94.60%
2025/26 FQ2 A&B 94.00% 93.70% -0.30% Red - Actual
below Target
As of 7th October 2025 the participation figure (16–19-year-olds in employment, training or education) across the whole of
Argyll and Bute was 3126 young people, which equates to 93.70%. This is 0.3% below the target and 0.8% below the annual
Argyll and Bute participation figure of 94.5% which was released by Skills Development Scotland at the end of August 2025.
The participation figure of 93.70% for FQ2 of 2025/26 is a decrease of 1.01% on the participation figure for FQ1 of 2025/26,
and represents a decrease of 2.1% on the equivalent FQ1 figure from 2024/25.
Period Actual FQ1 Commentary
2024/25 FQ2 95.80%
2024/25 FQ3 94.19%
2024/25 FQ4 93.50%
2025/26 FQ1 94.71%
2025/26 FQ2 93.70%
Actual trend line
As of 2nd July 2025 the participation figure (16–19-year-olds in employment, training or education) across the whole of Argyll
and Bute was 4175 young people, which equates to 94.71%. This is 0.71% above the target and 0.41% above the annual Argyll
and Bute participation figure of 94.3% which was released by Skills Development Scotland at the end of August 2024. The
participation figure of 94.71% for FQ1 of 2025/26 is an increase of 1.21% on the participation figure for FQ4 of 2024/25, and
represents an decrease of 0.28% on the equivalent FQ1 figure from 2024/25.
This indicator for FQ2 is lower than the target and performance has decreased since the last reporting period.
Actual trend line
As of 2nd July 2025 the participation figure (16–19-year-olds in employment, training or education) in Mid-Argyll, Kintyre and
Islay was 994 young people, which equates to 95.39%. This is 1.39% above the target and 1.09% above the annual Argyll and
Bute participation figure of 94.3% which was released by Skills Development Scotland at the end of August 2024. The
participation figure of 95.39% for FQ1 of 2025/26 is an increase of 0.79% on the participation figure for FQ4 of 2024/25, and
represents an decrease of 1.25% on the FQ1 figure from 2024/25.
This indicator for FQ2 exceeds the target however performance has decreased since the last reporting period.
Corporate Outcome - Our economy is diverse and thriving
Maximise the percentage of 16-19 year olds participating in education, training or employment
Responsible Person: Jennifer Crocket
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
11
Page 73

Page 74

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 0 0 0 Green - Actual
meets Target No completions in FQ2
Period Actual FQ1 Commentary
2024/25 FQ2 20
2024/25 FQ3 6
2024/25 FQ4 0
2025/26 FQ1 0
2025/26 FQ2 0
2025/26 FQ2 A&B 0 0 0 Green - Actual
meets Target No completions in FQ2
Period Actual FQ1 Commentary
2024/25 FQ2 26
2024/25 FQ3 6
2024/25 FQ4 9
2025/26 FQ1 0
2025/26 FQ2 0
This indicator for FQ2 meets the target with no change in performance since the last reporting period.
Actual trend line
No completions in FQ1. There are some projects on site to complete later in year.
This indicator for FQ2 meets the target with no change in performance since the last reporting period.
Actual trend line
No completions FQ1.
Number of affordable social sector new builds completed per annum
Responsible Person: Kelly Ferns
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
Corporate Outcome - Our economy is diverse and thriving
12
Page 74

Page 75

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 75.0% 53.3% -21.7% Red - Actual
below Target
Performance across the Development Management Service is still being recovered and impacted upon by the management of
a significant backlog of casework. Overall output and performance across the service is improving as staff resource issues have
been resolved. However, timeliness measures continue to be adversely impacted through the prioritisation of older statutory
'legacy' casework for determination. The target for the handling of pre-application enquiries has been set to 30 days although
this change has not yet been reflected in the format of corporate reporting. During FQ2, 15 pre-applications were responded
to within Mid Argyll, Kintyre and the Islands. 8 responses (53%) were issued within 20 days; 8 responses (53%) were issued
within the revised target of 30 days. It is acknowledged that performance is still significantly below target on this measure but
is expected to improve as casework pressure on available staff resource from 'legacy' items decreases over time.
Period Actual FQ1 Commentary
2024/25 FQ2 35.9%
2024/25 FQ3 48.7%
2024/25 FQ4 55.2%
2025/26 FQ1 50.0%
2025/26 FQ2 53.3%
Actual trend line
Performance across the Development Management Service is still being recovered and impacted upon by the management of
a significant backlog of casework. Overall output and performance across the service is improving as staff resource issues have
been resolved. However, timeliness measures continue to be adversely impacted through the prioritisation of older statutory
'legacy' casework for determination. The target for the handling of pre-application enquiries has been set to 30 days although
this change has not yet been reflected in the format of corporate reporting. During FQ1 40 pre-applications were responded
to within Mid Argyll, Kintyre and the Islands. 20 responses (50%) were issued within 20 days; 22 responses (55%) were issued
within the revised target of 30 days. It is acknowledged that performance is still significantly below target on this measure but
is expected to improve as casework pressure on available staff resource from 'legacy' items decreases over time.
This indicator for FQ2 is lower than the target however performance has increased since the last reporting period.
Corporate Outcome - Our economy is diverse and thriving
Percentage of pre-planning application enquiries processed within 20 working days
Responsible Person: Peter Bain
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
13
Page 75

Page 76

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 75.0% 59.0% -16.0% Red - Actual
below Target
Performance across the Development Management Service is still being recovered and impacted upon by the management of
a significant backlog of casework. Overall output and performance across the service is improving as staff resource issues have
been resolved. However, timeliness measures continue to be adversely impacted through the prioritisation of older statutory
'legacy' casework for determination. The target for the handling of pre-application enquiries has been set to 30 days although
this change has not yet been reflected in the format of corporate reporting. During FQ2, 100 pre-applications were responded
to across Argyll and Bute. 59 responses (59%) were issued within 20 days; 65 responses (65%) were issued within the revised
target of 30 days.
Period Actual FQ1 Commentary
2024/25 FQ2 49.2%
2024/25 FQ3 48.3%
2024/25 FQ4 58.5%
2025/26 FQ1 63.5%
2025/26 FQ2 59.0%
Actual trend line
Performance across the Development Management Service is still being recovered and impacted upon by the management of
a significant backlog of casework. Overall output and performance across the service is improving as staff resource issues have
been resolved. However, timeliness measures continue to be adversely impacted through the prioritisation of older statutory
'legacy' casework for determination. The target for the handling of pre-application enquiries has been set to 30 days although
this change has not yet been reflected in the format of corporate reporting. During FQ1 137 pre-applications were responded
to across Argyll and Bute. 87 responses (63.5%) were issued within 20 days; 93 responses (67.9%) were issued within the
revised target of 30 days.
This indicator for FQ2 is lower than the target and performance has decreased since the last reporting period.
Corporate Outcome - Our economy is diverse and thriving
Percentage of pre-planning application enquiries processed within 20 working days
Responsible Person: Peter Bain
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
14
Page 76

Page 77

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 8.0 11.4 3.4 Red - Actual
exceeds Target
Performance across the Development Management Service has been impacted by a significant backlog of casework. Whilst
issues relating to staff resource availability have been resolved and output has significantly improved it is highlighted that
KPI's measuring average time taken remain adversely affected by the resolution of increasing volumes of 'legacy' casework.
The Council's target for 'householder' applications has been revised to 10 weeks although this is not yet reflected in the
format of corporate reports. By FQ2 only a handful of 'householder' 'legacy' items remained, this has resulted in a general
improvement across this particular performance measure. During FQ2, 10 'householder' applications were determined in Mid
Argyll, Kintyre and the Islands, none of which were 'legacy' items.
Period Actual FQ1 Commentary
2024/25 FQ2 21.6
2024/25 FQ3 27.0
2024/25 FQ4 27.3
2025/26 FQ1 17.4
2025/26 FQ2 11.4
This indicator for FQ2 exceeds the target however performance has increased since the last reporting period.
Actual trend line
Performance across the Development Management Service has been impacted by a significant backlog of casework. Whilst
issues relating to staff resource availability have been resolved and output has significantly improved it is highlighted that
KPI's measuring average time taken remain adversely affected by the resolution of increasing volumes of 'legacy' casework.
The Council's target for 'householder' applications has been revised to 10 weeks although this is not yet reflected in the
format of corporate reports. During FQ1 only a handful of 'householder' 'legacy' items remained, this has resulted in a general
improvement across this particular performance measure. During FQ1 12 'householder' applications were determined in Mid
Argyll, Kintyre and the Islands including 2 'legacy' items and is reflected in the significant improvement in performance
reported for this period. Excluding 'legacy' items, the remaining 10 applications were determined in an average time of 9.0
weeks.
Corporate Outcome - Our economy is diverse and thriving
Average number of weeks to determine householder planning applications
Responsible Person: Peter Bain
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
15
Page 77

Page 78

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 8.0 7.9 -0.1 Green - Actual
below Target
Performance across the Development Management Service has been impacted by a significant backlog of casework. Whilst
issues relating to staff resource availability have been resolved and output has significantly improved it is highlighted that
KPI's measuring average time taken remain adversely affected by the resolution of increasing volumes of 'legacy' casework.
The Council's target for 'householder' applications has been revised to 10 weeks although this is not yet reflected in the
format of corporate reports. By FQ2 only a handful of 'householder' 'legacy' items remained, this has resulted in a general
improvement across this particular performance measure. During FQ2 66 'householder' applications were determined across
Argyll and Bute including 3 'legacy' items and is reflected in the significant improvement in performance reported for this
period. Excluding 'legacy' items, the remaining 59 applications were determined within an average time of 8.1 weeks.
Period Actual FQ1 Commentary
2024/25 FQ2 26.1
2024/25 FQ3 15.9
2024/25 FQ4 14.2
2025/26 FQ1 10.4
2025/26 FQ2 7.9
Corporate Outcome - Our economy is diverse and thriving
Average number of weeks to determine householder planning applications
Responsible Person: Peter Bain
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
This indicator for FQ2 is lower than the target however performance has increased since the last reporting period.
Actual trend line
Performance across the Development Management Service has been impacted by a significant backlog of casework. Whilst
issues relating to staff resource availability have been resolved and output has significantly improved it is highlighted that
KPI's measuring average time taken remain adversely affected by the resolution of increasing volumes of 'legacy' casework.
The Council's target for 'householder' applications has been revised to 10 weeks although this is not yet reflected in the
format of corporate reports. During FQ1 only a handful of 'householder' 'legacy' items remained, this has resulted in a general
improvement across this particular performance measure. During FQ1 62 'householder' applications were determined across
Argyll and Bute including 3 'legacy' items and is reflected in the significant improvement in performance reported for this
period. Excluding 'legacy' items, the remaining 59 applications were determined within an average time of 8.1 weeks.
16
Page 78

Page 79

Period Area Baseline Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 104 105 1 Red - Actual
exceeds Baseline
The empty rate is currently 4.11% in MAKI. In the past quarter, we have seen a slight increase in the number of properties
claiming empty property relief. The increase is evidenced in Lochgilphead. To date, the empty business property officer has
assisted 2 grant-aided projects that are fully claimed with 2 businesses now trading from the properties. We have a further 4
properties which are subject of live projects in progress, plus 6-7 projects at enquiry-application stage. There is positive
momentum across MAKI however, projects are slow to advance for a variety of reasons, ie: owner capacity, trades availability
or complexity due to size/type of property, consents or state of repair.
Period Actual FQ1 Commentary
2024/25 FQ2 -
2024/25 FQ3 -
2024/25 FQ4 -
2025/26 FQ1 105
2025/26 FQ2 105
2025/26 FQ2 A&B 277 267 -10 Green - Actual
below Baseline
The empty rate is currently 3.27%, which is down from 3.38% in the previous quarter. We have seen a decline in the number
of properties claiming empty property relief, and the empty business property grant scheme, plus the extended property
relief have both proven useful in supporting owners or incoming tenants. The support is warmly welcomed by the private
sector, as the trading environment is challenging, so the financial support to help de-risk business start-up, expansion and
alternative usage is proving a positive intervention.
Period Actual FQ1 Commentary
2024/25 FQ2 -
2024/25 FQ3 -
2024/25 FQ4 -
2025/26 FQ1 276
2025/26 FQ2 267
This indicator for FQ2 shows the cumulative number of empty properties is lower than the baseline.
Actual trend line
A&Bs 'empty' vacancy rate is currently 3.37%. Although the measure against baseline is positive, this % does represent a
slightly higher figure (0.5%) versus historic analysis. The suite of empty business property policy changes implemented by the
council are positive and the market is responding to the new extended property relief and the business grant scheme. The role
of town centres is multi-faceted so they are impacted by many externalities. These can be an acute in rural economies already
facing challenges with depopulation, declining workforce, accessibility and macro-economic factors. Ongoing work is required
to diagnose the issues currently affecting each of our town centres, and provide a framework of approaches/interventions to
support their revival.
Corporate Outcome - Our economy is diverse and thriving
Number of empty properties
Responsible Person: Jonathan Welch
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
This indicator for FQ2 shows the cumulative number of empty properties has exceeded the baseline.
Actual trend line
MAKI's 'empty' vacancy rate is 4.11%. Since the Empty Business Property Grant Scheme was approved in June 2025, 4 x Empty
Business Property Grants have been approved. 2 projects in Campbeltown, 1 in Lochgilphead and 1 in Ardrishaig, for an
accumulative value of £60,711.09. We have numerous live enquiries for properties in Lochgilphead, with others in Tarbert,
Campbeltown and Bowmore. Please note: MAKI figures are skewed somewhat by a single property which has 20 entries in the
valuation roll. Work is ongoing to explore methods to monitor 'demand' in our town centres as that data is vital to
regeneration and socio-economic development.
17
Page 79

Page 80

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B No Target 31 N/A N/A
During FQ2, the housing service took 125 homeless applications and provided temporary accommodation for 31 new
homeless households.
B&C: Out of 38 Homeless Applications, 13 new households went in to temporary accommodation (10 x Serviced
Accommodation, 1 x Bed & Breakfast, 2 x Registered Social Landlord).
H&L: Out of 31 Applications, 6 new households went in to temporary accommodation (3 x Serviced Accommodation, 1 x Bed
& Breakfast, 1 x Private Sector Lease, 1 x Registered Social Landlord).
MAKI: Out of 36 Homeless Applications, 8 new households went in to temporary accommodation (5 x Private Sector Lease, 3 x
Serviced Accommodation).
OLI: Out of 19 Homeless Applications, 4 new households went in to temporary accommodation (4 x Supported
Accommodation).
There was also one Homeless Application taken from someone outside of Argyll and Bute Council area.
Period Actual FQ1 Commentary
2024/25 FQ2 40
2024/25 FQ3 27
2024/25 FQ4 30
2025/26 FQ1 27
2025/26 FQ2 31
Actual trend line
During FQ1, the housing service took 110 homeless applications and provided temporary accommodation for 27 new
homeless households.
B&C: Out of 26 Homeless Applications, 8 new households went in to temporary accommodation (4 x Serviced
Accommodation, 1 x Bed & Breakfast, 2 x Registered Social Landlord, 1 Private Sector Lease).
H&L: Out of 36 Applications, 8 new households went in to temporary accommodation (3 x Serviced Accommodation, 4 x Bed
& Breakfast, 1 x Private Sector Lease).
MAKI: Out of 31 Homeless Applications, 5 new households went in to temporary accommodation (3 x Private Sector Lease, 1 x
Serviced Accommodation 1 x Supported Accommodation).
OLI: Out of 17 Homeless Applications, 6 new households went in to temporary accommodation (5 x Supported
Accommodation, 1 x Serviced Accommodation).
Please note:
•  The Registered Social Landlord and Private Rented Sector properties are leased by the Council and sub-let to homeless households as temporary accommodation.
•  Serviced Accommodation is available in Cowal and Helensburgh and is for single people providing an en-suite bedroom and shared kitchen facilities.
• Supported accommodation is provided in Lorn by Blue Triangle Housing Association.
•  Emergency accommodation may on occasion be provided out with the location of the original presentation due to the pressure on the availability of temporary accommodation
Corporate Outcome - Our economy is diverse and thriving
COI - Number of new homeless applicants who required temporary accommodation this period
Responsible Person: Morven Macintyre
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 shows the number of applicants has increased since the last reporting period.
18
Page 80

Page 81

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 20.0% 0.0% Not Known, due to staff resource and sickness absense data has not been collected.
Period Actual FQ1 Commentary
2024/25 FQ2 10.5%
2024/25 FQ3 23.6%
2024/25 FQ4 15.2%
2025/26 FQ1 0.0%
2025/26 FQ2
COI - Maintain the percentage of local suppliers that benefit from the award of contracts via the procurement portal
Responsible Person: Anne MacColl-Smith
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for...
Actual trend line
FQ1 data expected from Spikes Cavell (Scottish Government data base) in mid September.
Corporate Outcome - Our economy is diverse and thriving
19
Page 81

Page 82

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B No Target 14 N/A N/A 14 achieved community benefits reported to Procurement Commercial & Contract Management Team for FQ2
Period Actual FQ1 Commentary
2024/25 FQ2 31
2024/25 FQ3 -
2024/25 FQ4 44
2025/26 FQ1 0
2025/26 FQ2 14
Actual trend line
The number of achieved community benefits during FQ1 was 37.
Corporate Outcome - Our economy is diverse and thriving
COI - Increase the number of community benefits that are delivered through contracts we award locally
Responsible Person: Anne MacColl-Smith
This indicator is a Corporate Outcome Indicator that is reported in FQ2 and FQ4. The performance presented is Council-wide only.
This indicator for FQ2 shows the number of community benefits has decreased since the last reporting period.
20
Page 82

Page 83

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI 75% 100% 25% Green - Actual
exceeds Target This quarter saw fewer faults reported, coinciding with the summer season and an overall improvement in performance.
Period Actual FQ1 Commentary
2024/25 FQ2 94%
2024/25 FQ3 95%
2024/25 FQ4 92%
2025/26 FQ1 93%
2025/26 FQ2 100%
2025/26 FQ2 A&B 75% 95% 20% Green - Actual
exceeds Target A relatively quiet quarter, with 40 faults reported and only 2 exceeding the required repair timescales.
Period Actual FQ1 Commentary
2024/25 FQ2 97%
2024/25 FQ3 92%
2024/25 FQ4 92%
2025/26 FQ1 90%
2025/26 FQ2 95%
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Actual trend line
Performace has improved, however we are still requiring some contractor assistance especially in the Helensburgh area, some
requiring Scottish Powers attendance along with the support of civil contractors. We hope to have these works carried out
prior to the clocks changing.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Actual trend line
Performance has been good as it is the lighter months and works can be inspected and fixed in a timely manner. Works can
also be planned around contractual works which also helps with the timescales of attendance.
Corporate Outcome - We have an infrastructure that supports sustainable growth
Percentage of street lighting faults repaired within 10 days
Responsible Person: Tom Murphy
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
21
Page 83

Page 84

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI No Target 9 N/A N/A MAKI received a total of 9 waste collection complaints in FQ2, broken down, Mid Argyll 1, Isle of Islay 3, Isle of Jura 2 and
Kintyre 3
Period Actual FQ1 Commentary
2024/25 FQ2 4
2024/25 FQ3 0
2024/25 FQ4 1
2025/26 FQ1 7
2025/26 FQ2 9
2025/26 FQ2 A&B No Target 36 N/A N/A
A total of 36 waste collection complaints were received for the Argyll and Bute area in FQ2.  The Helensburgh and Lomond
area remains the highest with 14 complaints, however as reported last quarter the Helensburgh and Lomond area service
12,437 properties and broken down over the quarter this equates to residual 49,748, reclycling 74,622, food waste 149,244
and glass 37,311 giving a total of 310,925 bins collected.  Therefore overall this is a very good level of service.
Period Actual FQ1 Commentary
2024/25 FQ2 26
2024/25 FQ3 36
2024/25 FQ4 31
2025/26 FQ1 34
2025/26 FQ2 36
This indicator for FQ2 shows the number of waste collection complaints has increased since the last reporting period.
Actual trend line
A total of 34 waste collection complaints were received this quarter for the whole of Argyll and Bute. The Isles of Mull and
Bute received no waste collection complaints this quarter which shows the waste teams on the islands are delivering a high
level of service.  In the Helensburgh and Lomond area there are 12,437 properties from which refuse is collected, quarterly
this equates to residual 49,748, recycling 74,622, food waste 149,244 and glass 37,311 giving a total of 310,925 bins collected
per quarter.  The number of complaints made as a percentage of the bins collected equates to 0.0067%.
Actual trend line
Mid Argyll received 3 waste collection complaints this quarter and the Isle of Islay received 4, a total of 7 complaints.
This indicator for FQ2 shows the number of waste collection complaints has increased since the last reporting period.
Corporate Outcome - We have an infrastructure that supports sustainable growth
Number of waste collection complaints
Responsible Person: Tom Murphy
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
22
Page 84

Page 85

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 45.0% 63.2% 18.2% Green - Actual
exceeds Target
63.2% combined recycling, composting and recovery (39.6% recycling and composting plus 23.6% recovery). Recovery figure
for FQ2 is down slightly from previous quarters due to commencement by Biffa (formerly Renewi) of the conversion of
mechanical biological treatment (MBT) plants to Waste Transfer Stations (WTS) at the 3 main sites. Once complete, this will
provide the capability for the residual general waste to be transferred from 1st January to the central belt for refuse derived
fuel (RDF/energy from waste (EfW) to ensure landfill ban compliance.
Period Actual FQ1 Commentary
2024/25 FQ2 70.5%
2024/25 FQ3 65.4%
2024/25 FQ4 63.2%
2025/26 FQ1 66.6%
2025/26 FQ2 63.2%
2025/26 FQ2 Renewi No Target 48.9% N/A N/A
48.9% combined recycling,composting and recovery (35.9% recycling and composting plus 13% recovery). Recovery figure for
FQ2 is down slightly from previous quarters due to commencement by Biffa (formerly Renewi) of the conversion of
mechanical biological treatment (MBT) plants to Waste Transfer Stations (WTS) at 3 sites in order to ensure residual general
waste can be transferred to the central belt for from 1st January 2026 to ensure compliance with the municipal waste landfill
ban.
Period Actual FQ1 Commentary
2024/25 FQ2 61.3%
2024/25 FQ3 52.4%
2024/25 FQ4 46.8%
2025/26 FQ1 51.5%
2025/26 FQ2 48.9%
Actual trend line
51.5% recycling,composting and recovery (34.6% recycling and composting plus 16.9% recovery). Recycling and composting
are slighter higher than previous quarter mainly due to the increased levels of green garden waste sent for composting .
Actual trend line
66.6% recycling,composting and recovery (39.3% recycling and composting plus 27.3% recovery). Recovery percentage is high
mainly due to Helensburgh and Lomond residual waste going for refuse derived fuel (RDF)/energy from waste (EFW).
Recycling and composting are slighter higher than previous quarter mainly due to increased levels of green garden waste sent
for composting.
This indicator for FQ2 shows the percentage of waste recycled has decreased since the last reporting period.
Corporate Outcome - We have an infrastructure that supports sustainable growth
COI - Percentage of waste recycled, composted and recovered
Responsible Person: Andy Summers
This indicator is reported quarterly. The performance presented is by Council-wide service provision.
This indicator for FQ2 exceeds the target however performance has decreased since the last reporting period.
23
Page 85

Page 86

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 Islands No Target 40.1% N/A N/A
40.1% combined recycling,composting and recovery (27.1% recycling and composting plus 13% recovery). Recycling figure for
FQ2 is down slightly from previous quarters due to some delays in receiving tonnage information before the Q2 input cut-off
date from a couple of contractors handling some of the recycling materials. The late tonnage information will be entered in
the next quarter.
Period Actual FQ1 Commentary
2024/25 FQ2 51.8%
2024/25 FQ3 44.2%
2024/25 FQ4 49.2%
2025/26 FQ1 52.5%
2025/26 FQ2 40.1%
2025/26 FQ2 H&L No Target 100.0% N/A N/A
100% combined recycling,composting and recovery (51.3% recycling and composting plus 48.7% recovery). Residual general
waste from Helensburgh and Lomond area is already compliant with the municipal waste landfill ban as it currently goes for
refuse derived fuel (RDF)/energy from waste (EfW). Recycling and composting during the quarter exceeded 50% mainly due to
high levels of green garden waste being sent for onward composting from the Blackhill Recycling Centre (Helensburgh).
Period Actual FQ1 Commentary
2024/25 FQ2 100.0%
2024/25 FQ3 100.0%
2024/25 FQ4 100.0%
2025/26 FQ1 100.0%
2025/26 FQ2 100.0%
Actual trend line
100% recycling,composting and recovery (46.9% recycling and composting plus 53.1% recovery). Recovery percentage is high
mainly due to Helensburgh and Lomond residual waste going for refuse derived fuel (RDF)/energy from waste (EFW).
Recycling and composting slighter higher than previous quarter mainly due to increased levels of green garden waste sent for
composting.
Actual trend line
52.5% recycling,composting and recovery (42.5% recycling and composting plus 10.0% recovery). Recycling and composting
are slighter higher than previous quarter mainly due to the increased levels of green garden waste sent for composting .
This indicator for FQ2 shows the percentage of waste recycled has remained the same since the last reporting period.
This indicator for FQ2 shows the percentage of waste recycled has decreased since the last reporting period.
Corporate Outcome - We have an infrastructure that supports sustainable growth
COI - Percentage of waste recycled, composted and recovered
Responsible Person: Andy Summers
This indicator is reported quarterly. The performance presented is by Council-wide service provision.
24
Page 86

Page 87

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 5,550 3,625 -1,925 Green - Actual
below Target
Within target mainly due to the residual waste from Helensburgh and Lomond already being landfill ban compliant. PPP area
landfill is up from the previous few quarters due to commencement by Biffa (formerly Renewi) of the conversion of
mechanical biological treatment (MBT) plants to Waste Transfer Stations (WTS) at the 3 main sites. Once works are complete,
this will provide the capability for the residual general waste to be transferred from 1st January to the central belt for refuse
derived fuel (RDF/energy from waste (EfW) to ensure landfill ban compliance.
Period Target Actual FQ1 Commentary
2024/25 FQ2 5,550 3,225
2024/25 FQ3 5,100 2,846
2024/25 FQ4 5,000 3,103
2025/26 FQ1 5,850 3,267
2025/26 FQ2 5,550 3,625
Corporate Outcome - We have an infrastructure that supports sustainable growth
COI - Number of tonnes of waste sent to landfill
Responsible Person: Andy Summers
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 is lower than the target (lowest is best).
Actual trend line
Well within landfill target mainly due to Helensburgh and Lomond residual general waste going for refuse derived fuel
(RDF)/energy from waste (EFW).
25
Page 87

Page 88

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 Mid Argyll 73 87 14 Green - Actual
exceeds Target Mid Argyll has a street cleanliness figure of 87 in FQ2.
Period Actual FQ1 Commentary
2024/25 FQ2 84
2024/25 FQ3 82
2024/25 FQ4 77
2025/26 FQ1 81
2025/26 FQ2 87
2025/26 FQ2 Kintyre 73 87 14 Green - Actual
exceeds Target Kintyre has a street cleanliness figure of 87 in FQ2.
Period Actual FQ1 Commentary
2024/25 FQ2 79
2024/25 FQ3 85
2024/25 FQ4 80
2025/26 FQ1 80
2025/26 FQ2 87
Actual trend line
The Kintyre area has a street cleanliness figure of 80 this quarter , which exceeds the actual target.
Actual trend line
Mid Argyll have a street cleanliness figure of 81 this quarter, which exceeds the actual target.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Corporate Outcome - We have an infrastructure that supports sustainable growth
COI - LEAMS (Local Environment Audit and Management System)
Responsible Person: Tom Murphy
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
26
Page 88

Page 89

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 Islay 73 83 10 Green - Actual
exceeds Target The street cleanliness score for the Isle of Islay in FQ2 is 83 .
Period Actual FQ1 Commentary
2024/25 FQ2 88
2024/25 FQ3 79
2024/25 FQ4 81
2025/26 FQ1 81
2025/26 FQ2 83
2025/26 FQ2 A&B 73 86 13 Green - Actual
exceeds Target
For FQ2 a street cleanliness score of 86 has been achieved excelling the target of 73.  This reflects well on the teams in the
areas who continue to provide a good level of service and again shows very little litter visible on the streets and/or open
spaced checked.
Period Actual FQ1 Commentary
2024/25 FQ2 85
2024/25 FQ3 84
2024/25 FQ4 83
2025/26 FQ1 84
2025/26 FQ2 86
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
Actual trend line
A street cleanliness score of 84 has been achieved for the whole of Argyll and Bute this quarter, which shows the street
cleanliness remains high on both the mainland and Islands. These figures show very little litter visible on the streets and or
open spaces checked. This high score reflects well on the teams who are providing a good service, by ensuring they work
efficiently and effectively to keep the areas clean.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Corporate Outcome - We have an infrastructure that supports sustainable growth
COI - LEAMS (Local Environment Audit and Management System)
Responsible Person: Tom Murphy
Actual trend line
The Isle of Islay has a street cleanliness score of 81  this quarter, which exceeds the actual target. 
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
27
Page 89

Page 90

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI No Target 2.00 N/A N/A
Working days lost due to sickness have decreased this quarter, likely influenced by the school holidays during this period.
However, levels remain higher than the same quarter last year, so continued focus and support for managers will be
important to sustain improvement.
Period Actual FQ1 Commentary
2024/25 FQ2 1.46
2024/25 FQ3 1.92
2024/25 FQ4 2.91
2025/26 FQ1 2.47
2025/26 FQ2 2.00
2025/26 FQ2 A&B No Target 1.75 N/A N/A Overall absence has decreased this quarter, which may be partly attributed to the scheduled school holidays during this
period. We continue to monitor absence closely and implement targeted interventions aimed at further improvement.
Period Actual FQ1 Commentary
2024/25 FQ2 1.77
2024/25 FQ3 2.89
2024/25 FQ4 3.23
2025/26 FQ1 2.13
2025/26 FQ2 1.75
This indicator for FQ2 shows the number of sickness absence days has decreased since the last reporting period.
Actual trend line
Slight increase from last quarter and from the same quarter, last year. The HR&OD team continue to monitor absence, with
targeted work aiming to improve this. They are also preparing to review the Supporting Attendance at Work procedures in
the next 12 months.
This indicator for FQ2 shows the number of sickness absence days has decreased since the last reporting period.
Actual trend line
Slight increase from last quarter and significant increase based on the data recorded in the same quarter last year.
Corporate Outcome - Making it happen
COI - Teacher sickness absence
Responsible Person: Jennifer Crocket (B&C and MAKI) / Wendy Brownlie (H&L and OLI)
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
28
Page 90

Page 91

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 MAKI No Target 4.25 N/A N/A
Working days lost due to sickness have increased this quarter, with levels remaining higher than the same quarter last year
and indicates a continuing upward trend. A further focus will be given to understanding the underlying drivers and supporting
managers to manage absence effectively.
Period Actual FQ1 Commentary
2024/25 FQ2 3.34
2024/25 FQ3 4.25
2024/25 FQ4 4.28
2025/26 FQ1 3.68
2025/26 FQ2 4.25
2025/26 FQ2 A&B No Target 4.06 N/A N/A
Overall, sickness absence performance this quarter has been mixed, with some areas showing positive reductions in working
days lost, while others have seen a slight increase or remained in line with the same period last year. This suggests that while
some progress is being made, absence patterns continue to vary across services. Targeted support, focused management
engagement and ongoing monitoring will remain key to sustaining improvement and addressing areas of higher absence.
Period Actual FQ1 Commentary
2024/25 FQ2 3.43
2024/25 FQ3 4.40
2024/25 FQ4 4.66
2025/26 FQ1 3.82
2025/26 FQ2 4.06
This indicator for FQ2 shows the number of sickness absence days has increased since the last reporting period.
Actual trend line
Reduction in working days lost this quarter. The figure has followed smilar levels from the same quarter, last year.
This indicator for FQ2 shows the number of sickness absence days has increased since the last reporting period.
Corporate Outcome - Making it happen
COI - LGE staff (including non-Teacher) sickness absence
Responsible Person: Carolyn Cairns
This indicator is reported quarterly. The performance presented is at area level and Council-wide.
Actual trend line
Slight reduction overall. However, there is still an increase from the same quarter last year.  The HR&OD team continue to
monitor absence, with targeted work aiming to improve this. They are also preparing to review the Supporting Attendance at
Work procedures in the next 12 months.
29
Page 91

Page 92

Period Area Target Actual Variance Status FQ2 Commentary
2025/26 FQ2 A&B 70.0% 78.4% 8.4% Green - Actual
exceeds Target
In FQ2 2025/26 there were 37,268 customer transactions dealt with by Customer Service Agents (21.6%) and
135,337 were automated/self-service transactions (78.4%) so the 70.0% target was substantially bettered. This
was an improvement on than the same quarter of 2024/25, where 72.7% of transactions were handled through
automation/self-service.
Period Actual FQ1 Commentary
2024/25 FQ2 72.7%
2024/25 FQ3 82.7%
2024/25 FQ4 74.8%
2025/26 FQ1 76.1%
2025/26 FQ2 78.4%
Corporate Outcome - Making it happen
COI - Increase the percentage of all self-service automated contacts
Responsible Person: Robert Miller
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only.
This indicator for FQ2 exceeds the target and performance has increased since the last reporting period.
Actual trend line
In FQ1 2025/26 there were 40,513 customer transactions dealt with by Customer Service Agents (23.9%) and 129,292 were
automated/self-service transactions (76.1%) so the 70.0% target was substantially bettered. This was also better than the
same quarter of 2024/25, where 71.7% of transactions were handled through automation/self-service.
30
Page 92

Page 93

CHARITABLE TRUSTS, BEQUESTS AND TRUST FUNDS 
1.0 EXECUTIVE SUMMARY 
1.1 The Mid Argyll, Kintyre and the Islands Area Committee are Trustees for a
number of Charitable Trusts, Bequests and Trust Funds. Historically a report has
been brought to the Area Committee on an annual basis with recommendations
for distribution. 
1.2 While officers continually seek to simplify and update processes where possible to
ensure ongoing compliance with the original terms of the bequests and to reduce
the administrative burden of the management and distribution, there remains a
number of challenges. A number of the charitable funds were established many
years ago, and as a consequence of changes in society over time the intended
beneficiaries of the bequests are no longer easily identified. 
1.3 This report provides details of a number of the Trusts and Bequests that remain
active in the Mid Argyll, Kintyre and the Islands Area and seeks agreement from
Members on proposed distribution methods. 
2.0 RECOMMENDATIONS
2.1  The Mid Argyll, Kintyre and the Islands Area Committee are asked to:
1. consider the financial position of the Charitable Trusts, Bequests and
Trust Funds as of August 2025; 
2. agree that the Hutcheon Memorial Trust and May Paterson Trust prizes
be limited to £30; and 
3. agree that all other charities and trust funds, that have historically been
awarded to Council Departments and Allied partners, are awarded on
the basis outlined in paragraph 5.4 and defined within appendix 1. 
ARGYLL AND BUTE COUNCIL MID ARGYLL, KINTYRE AND THE
ISLANDS AREA COMMITTEE 
LEGAL & REGULATORY SUPPORT 3 December 2025
Page 93 Agenda Item 10

Page 94

CHARITABLE TRUSTS, BEQUESTS AND TRUST FUNDS 
3.0  INTRODUCTION
3.1 The Mid Argyll, Kintyre and the Islands Area Committee are Trustees of 19
Charitable Trusts, Bequests and Trust Funds with an estimated unrestricted
balance of around £138K.  This report provides information on proposals in
relation to the ongoing management of these funds and seeks agreement on
distribution proposals.
4.0  RECOMMENDATIONS
4.1 The Mid Argyll, Kintyre and the Islands Area Committee are asked to:
1. consider the financial position of the Charitable Trusts, Bequests and
Trust Funds as of August 2025; 
2. agree that the Hutcheon Memorial Trust and May Paterson Trust prizes
be limited to £30; and 
3. agree that all other charities and trust funds, that have historically been
awarded to Council Departments and Allied partners, are awarded on
the basis outlined in paragraph 5.4 and defined within appendix 1. 
5.0  BACKGROUND & DISTRIBUTION ARRANGEMENTS
5.1 Historically reports are prepared and submitted to Area Committees outlining the
status of each of the funds, proposed distribution method(s) and the amounts
available. 
5.2 Of the 19 funds for which the Area Committee are trustees many have
historically been awarded to Council Departments and allied partners (for
example Roads and Amenity Services). 
5.3 In December 2021 the Area Committee agreed to place a moratorium on the
distribution of monies from 6 funds as they had no/limited funds available for
distribution. This approach has served to lessen the administrative burden and
will allow interest to be accumulated to ensure maximum community benefit at a
ARGYLL AND BUTE COUNCIL MID ARGYLL, KINTYRE AND THE
ISLANDS AREA COMMITTEE 
LEGAL & REGULATORY SUPPORT 3 December 2025
Page 94

Page 95

later date. One of those funds, specifically Kilkerran Cemetery, has performed
well over the last 24 months and will be considered for reactivation in 2026. 
5.4 In order to provide a level of consistency to the process for those
Bequests/Trusts which are transferred to Council Departments or allied partners
it is proposed that to allow for maximum benefit from the resources available,
those Funds will be allocated on a basis of the interest from the previous
financial year plus 1/20th of the unrestricted funds. This approach being the
recommendation of Financial Officers as a means for members to meet their
fiscal responsibilities as trustees, specifically that the funds are maintained over
the longer term and not exhausted.
5.5 The exemption to this rule is the funds which relate to a school prizes, the
Hutcheon Memorial Trust and the May Paterson Trust. It is suggested the level
of each prize be £30 this is in line with those awarded in other areas. This will
be paid by Finance on receipt of confirmation of the recipient from the school.
The Hutcheon Memorial Trust is awarded to the pupil that displays general
excellence within the subject of mathematics, while the May Paterson Trust is
awarded to the pupil that displays general excellence within business studies.
5.6 Should the Area Committee approve this approach over £6k will be available to
council departments and allied partners this financial year. Of which around
£4.8k is awarded to Live Argyll via the Library Endowment and Campbelltown
New Books funds. 
5.7 A small number of funds, five, have bespoke distribution methods which are
undertaken by Legal and Regulatory Support, this process will continue.
Officers will continue to advertise and monitor the expenditure from these
funds, should expenditure not provide a community benefit Officers will explore
what action can be taken.  
5.8 Following agreement by the Area Committee officers engaged with suitable
organisations to apply for support from the Macalister Mortification and The Fisher
Bequest. In June 2025 the Area Committee agreed to award to award £3850 from
the Macalister Mortification to A'Chleit Hall and £348 from the Fisher Bequest to
Westlochfyneside Foodshare with moratoriums being placed on these funds
thereafter. End of project monitoring reports will be submitted to the Area
Committee in due course 
6.0 CONCLUSION
6.1 This report has outlined the current position in terms of financial and distribution
arrangements of the funds/bequests held in trust by the Area Committees. On
approving the recommendations they will provide a clear community benefit
while meeting our obligation of ensuring transparent and effective governance.
7.0 IMPLICATIONS
7.1  Policy - None. 
7.2  Financial - None.
Page 95

Page 96

7.3  Legal - Area Committees, as Trustees, must ensure that the distribution
arrangements comply with the terms of the funds/bequests, failure to do so would
result in the Council being liable. 
7.4  HR - To proceed with reorganisation, in terms of section 10 or 11 of the Law Reform
(Miscellaneous Provisions) (Scotland) Act 1990 would require the allocation of
Officer time. 
7.5 Customer Service 
7.6  Risk - None 
7.7  Climate Change – None 
7.8  Fairer Scotland Duty – None 
7.9  Equalities - protected characteristics – None 
7.10  Consumer Duty – None 
7.11  Island Communities – None 
7.12  Children’s Rights and Wellbeing – None 
Douglas Hendry
Executive Director with responsibility for Legal & Regulatory Support 
November 2025 
Policy Lead - Councillor Mark Irvine 
Appendix 1 – Distribution Arrangements for Trust Funds and Bequests.
For further information contact: Stuart McLean, Committee Manager, 01436 658717,
stuart.mclean@argyll-bute.gov.uk               
Page 96

Page 97

#
TRUST NAME CHARITABLE PURPOSE DISTRIBUTION ARRANGEMENTS Capital
(Restricted Funds)
Income during
2024-25
Accumulated
Funds for
Distribution
1/20th of
unrestricted
Maximum proposed
award - 2025
MAY PATERSON TRUST
Prize for business
studies in Campbeltown
Grammar
Paid to the Campbeltown Grammar School. 250.00 24.00 267.00 n/a 30.00
HUTCHEON MEMORIAL
TRUST 
Prize for mathematics in
Campbeltown Grammar
Paid to the Campbeltown Grammar School. 104.00 15.00 209.00 n/a 30.00
CAMPBELTOWN NEW
BOOKS
Interest to go to the
provision of new books
in the library.
Paid to Live Argyll on confirmation that the funds have been
used for the provision of new books in the library. 2,000.00 238.00 3,117.00                155.85 393.85
A T ROSS BEQUEST
To be applied to
Ardfenaig Home,
Ardrishaig
Paid to Social Work (IJB) on confirmation that the funds
have been applied to Ardfenaig Home, Ardrishaig. 6,286.00 435.00 2,947.00                147.35 582.35
CLACHAN CEMETERY
TRUST
Upkeep of cemetry,
Clachan.
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
5,281.00 470.00 4,027.00                201.35 671.35
LIBRARY ENDOWMENT
FUND
Upkeep of reading room
Campbeltown
Paid to Live Argyll on confirmation that the funds have been
used for the upkeep of reading room Campbeltown. 5,000.00 2,375.00                40,885.00              2,044.25 4,419.25
GEORGE MELVILLE
DUNCAN BEQUEST
For the benefit of the
poor of the Burgh in the
form of gifts of fuel,
clothing and foodstuffs
during the winter
months.
Combine income of George Melville Duncan Bequest and
David Andrew Greenlees Trust and invite applications
annually for a sum to be determined.  Vouchers are to be
redeemed in local shop particiapating in the scheme.
17,000.00 3,289.00                48,970.00              n/a n/a
D A GREENLEES TRUST
For the Poor of
Campbeltown and the
Workhouse Hospital
there.
Combine income of George Melville Duncan Bequest and
David Andrew Greenlees Trust and invite applications
annually for a sum to be determined.  Vouchers are to be
redeemed in local shop particiapating in the scheme.
8,702.00 1,358.84                18,640.00              n/a n/a
CAMPBELL BEQUEST
For the benefit of the
poor of the Parish of
Kildalton and Oa
Combine income of McNeill Bequest and invite applications
quarterly. Distribution arrangements confirmed in March
2024.
50.00 152.00 3,188.00                n/a n/a
Council Departments and Allied Partners.
Bespoke arrangements in place.
Appendix 1
Page 97

Page 98

#
TRUST NAME CHARITABLE PURPOSE DISTRIBUTION ARRANGEMENTS Capital
(Restricted Funds)
Income during
2024-25
Accumulated
Funds for
Distribution
1/20th of
unrestricted
Maximum proposed
award - 2025
MCNEILL BEQUEST
For the benefit of the
poor of the Parish of
Kildalton and Oa
Combine income of Campbell Bequest and invite
applications quarterly. Distribution arrangements
confirmed in March 2024.
100.00 220.00 4,220.00                n/a n/a
KINTYRE YOUTH FUND To assist the youth of
kintyre Advise schools and youth groups of funds and invite bids. 21,195.00 1,174.00                3,736.00                n/a n/a
LATIMER MCINNES
TRUST
Upkeep of family lair
Kilchousland
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
183.00 8.00 31.00 n/a n/a
MACALISTER TRUST Upkeep of graves
Tarbert Cemetery
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
70.00 8.00 100.00 n/a n/a
KILMORY
LOCHGILPHEAD
CHURCHYARD
For the upkeep of
Kilmory Churchyard and
'any benefit from the
Fund, should the Trust
lapse, being extended to
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
148.00 8.00 19.00 n/a n/a
KILMARTIN NEW BURIAL
GROUND BEQUEST
Upkeep of new burial
ground
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
300.00 2.00 8.00 n/a n/a
KILMARTIN WAR
MEMORIAL FUND Upkeep of memorial
Transfer to Roads and Amenity Services annually when it is
confirmed that maintenance is being carried out on the war
memorial and use funds to offset costs of maintenance.
38.00 2.00 8.00 n/a n/a
KILKERRAN CEMETERY Upkeep of lairs,
Kilkerran.
Transfer to Roads and Amenity Services annually when it is
confirmed that the cemetery is being maintained. If no work
is being undertaken do not make the transfer until such
time as work is to be carried out.
6,025.00 279.00 717.00 n/a n/a
FISHER BEQUEST For the poor of Inverary Awarded to Westlochfyneside Foodshare  June 2025. 50.00 21.00 41.27 n/a n/a
Moratorium in situ
Page 98

Page 99

#
TRUST NAME CHARITABLE PURPOSE DISTRIBUTION ARRANGEMENTS Capital
(Restricted Funds)
Income during
2024-25
Accumulated
Funds for
Distribution
1/20th of
unrestricted
Maximum proposed
award - 2025
MACALLISTER
MORTIFICATION
To be invested in
heritable security for
the poor of the parish'
Killean & Kilchenzie. 
Awarded to A'Chleit Hall June 2025. 1,100.00 244.00 248.05 n/a n/a
Page 99

Page 100

This page is intentionally left blank

Page 101

Mid Argyll, Kintyre and the Islands Workplan 2025 – 26 
Committee
Date
Report Description Lead Service and contact
officer
Regularity of
occurrence/consideration
Date for Reports
to Committee
Services
Additional
Comment
December 2025
3 December
2025
Area Committee
Quarterly
Performance Reports
– FQ2 2025/26
Customer Support 
Services –
Claire McAllister
Quarterly Report 7 November 2025 
3 December
2025
Health & Social Care
Partnership -
Performance Report
– FQ1 2025/26 (April
– June)
Argyll and Bute Health
and Social Care
Partnership –
Charlotte Craig 
Bi-Annual Report 7 November 2025 
3 December
2025
Charities and Trust
Funds
Legal and Regulatory
Support –
Stuart McLean 
Annual Report 7 November 2025 
3 December
2025
Roads and
Infrastructure
Services Update
Roads and Infrastructure
Services – 
Mark Calder
Quarterly Report 7 November 2025 
3 December
2025
Electric Vehicle
Charging Strategy
Roads and Infrastructure
Services – 
Mark Calder
As Required 7 November 2025 
3 December
2025
Skills Development
Scotland Update
Skills Development
Scotland –
Susan MacRae
Annual Report 7 November 2025 Annual
report
usually in
September,
moved to
December
for 2025.
3 December
2025
Sakura Cherry Tree
Project Update
Legal and Regulatory
Support –
As Required 7 November 2025 
Page 101
Agenda Item
11

Page 102

Mid Argyll, Kintyre and the Islands Workplan 2025 – 26 
Committee
Date
Report Description Lead Service and contact
officer
Regularity of
occurrence/consideration
Date for Reports
to Committee
Services
Additional
Comment
Aileen McNicol
March 2026     
4 March 2026 Transport Scotland
Update
Transport Scotland –
Ian Woodcock
Annual Report 5 February 2026 
4 March 2026 Scottish Water
Update
Scottish Water –
Linzie Gowans
Annual Report 5 February 2026 
4 March 2026 Argyll Community
Housing Association
(ACHA) Update
Argyll Community
Housing Association
(ACHA) –
Michelle Mundie
Annual Report 5 February 2026 
4 March 2026 Area Performance
Report FQ3 2025/26
Customer Support 
Services –
Claire McAllister 
Quarterly Report 5 February 2026 
4 March 2026 Roads and
Infrastructure
Services Update
Roads and Infrastructure
Services – 
Mark Calder
Quarterly Report 5 February 2026 
4 March 2026 Housing Services
Activity Update –
Strategic Housing
Investment Plan
(SHIP) – Annual
Update
Development and
Economic Growth –
Douglas Whyte 
Annual Report 5 February 2026 
4 March 2026 2025/26 Active Travel
Progress Report
Development and
Economic Growth –
Colin Young
Annual Report 5 February 2026 
4 March 2026 Primary Area
Attainment Report:
Mid Argyll, Kintyre
and the Islands
Education –
Brendan Docherty 
Annual Report 5 February 2026 
Page 102

Page 103

Mid Argyll, Kintyre and the Islands Workplan 2025 – 26 
Committee
Date
Report Description Lead Service and contact
officer
Regularity of
occurrence/consideration
Date for Reports
to Committee
Services
Additional
Comment
4 March 2026 Campbell and McNeil
Bequest Award
Recommendations
Legal and Regulatory
Support –
Stuart McLean
Quarterly Report (if
required) 
5 February 2026 
June 2026     
3 June 2026 Islay High School
Report
Education –
Brendan Docherty
Annual Report 7 May 2026 
3 June 2026 Tarbert Academy
Report
Education –
Brendan Docherty
Annual Report 7 May 2026 
3 June 2026 Campbeltown
Grammar School
Report
Education –
Brendan Docherty
Annual Report 7 May 2026 
3 June 2026 Lochgilphead High
School Report
Education –
Brendan Docherty
Annual Report 7 May 2026 
3 June 2026 Roads and
Infrastructure
Services Update
Roads and Infrastructure
Services – 
Mark Calder
Quarterly Report 7 May 2026 
3 June 2026 Area Performance
Report FQ4 2025/26
Customer Support 
Services –
Claire McAllister 
Quarterly Report 7 May 2026 
3 June 2026 Argyll and Bute
Health and Social
Care Partnership
Performance Report
Argyll and Bute Health
and Social Care
Partnership –
Charlotte Craig
Bi-Annual Report 7 May 2026 
3 June 2026 Area Committee
Meetings – 2026-
2027
Legal and Regulatory
Support –
Shona Barton
Annual Report 7 May 2026 
Future Items     
Kilkerran
Cemetery
Hugh O’Neill    
Page 103

Page 104

Mid Argyll, Kintyre and the Islands Workplan 2025 – 26 
Page 104

Page 105

ARGYLL AND BUTE COUNCIL                          MID ARGYLL, KINTYRE AND 
THE ISLANDS AREA COMMITTEE 
SAKURA CHERRY TREE PROJECT UPDATE    3rd DECEMBER 2025                       
SAKURA CHERRY TREE PROJECT UPDATE 
1.0  INTRODUCTION 
1.1  In April 2024 the Lord-Lieutenant of Argyll and Bute contacted the Executive
Director with responsibility for Legal and Regulatory Support to explore the
possibility of working in partnership to secure a number of flowering cherry
trees, to be planted across Argyll and Bute, through the Sakura Cherry Tree
Project.      
1.2  The project was established in 2016 in recognition of decades of friendship
between the United Kingdom and Japan and to further strengthen
relationships between the two countries. Flowering cherry tree saplings are
provided to communities free of charge for planting in public spaces where
everyone can enjoy them.   
1.3  This report provides an update on progress in relation to this partnership
project between the Lieutenancy of Argyll and Bute and the Council.       
2.0  RECOMMENDATIONS 
It is recommended that the Area Committee: 
2.1     Note the contents of this report.      
3.0  DETAIL 
3.1  In April 2024 the Sakura Cherry Tree Project made contact with the Lieutenancy
of Argyll and Bute with the offer of free flowering cherry trees to be planted
locally. Trees reserved in April 2024 would be available for delivery from
November 2025. 
Page 105 Agenda Item 13

Page 106

3.2  The Sakura Cherry Tree Project was established in 2016 in recognition of
decades of friendship between the United Kingdom and Japan and to further
strengthen relationships between the two countries. Flowering cherry tree
saplings are provided for planting in public spaces where everyone can enjoy
them. These offers are traditionally made through local Lieutenancies. The
project had an initial target of 1,000 trees across the United Kingdom, but this
has expanded with 8,000 trees having been planted since its inception. 
3.3  The trees are provided completely free of charge, with the only request being
that they are planted in easily accessible locations where they can be enjoyed
by as many people as possible, such as parks, playgrounds, community land,
schools or other public spaces. They have an expected life span of around thirty
years. 
3.4 Upon receipt of the offer, the Lord-Lieutenant of Argyll and Bute contacted the
Executive Director with responsibility for Legal and Regulatory Support, who is
also the Clerk to the Lieutenancy, to explore scope for working in partnership
with the council to reserve trees for delivery in November 2025. 
3.5 The Executive Director made contact with the Council’s Amenity Services team
who agreed that they would be willing to assist in the distribution and planting
of the trees following delivery and in line with the specialist guidance provided. 
3.6 Subsequently, the Executive Director contacted all Elected Members seeking
their views on possible locations for planting trees in their local communities.
Ideas had to be submitted in line with the Project’s deadline of 30th April 2024,
so that trees could be reserved to meet the November 2025 delivery target. 
3.7 A number of Elected Members responded to the request and, after liaising with
local residents, provided a range of suggestions where flowering cherry trees
could be planted locally for the enjoyment and benefit of the community. The
Mid Argyll, Kintyre and the Islands locations contributed are listed at Appendix
1. These suggestions were passed to the Lord-Lieutenant who made contact
with the Sakura Cherry Tree Project to accept the offer on behalf of Argyll and
Bute.   
3.8 The Lieutenancy has now received word from the Project that trees are due for
delivery to premises in Lochgilphead during November. Following receipt of the
trees, colleagues in Amenity Services will assist with the distribution and
planting of the trees, adhering to the planting guidance provided, over the
course of the coming months. Updates will be provided to local Elected
Members by email to notify them of upcoming arrangements, when finalised,
for their ward. 
Page 106

Page 107

4.0  CONCLUSION 
4.1  This report provides an update for Elected Members on the next stage of Argyll
and Bute’s Sakura Cherry Tree Project, following their contributions in terms of
possible planting locations and the advice of a delivery timeframe for the trees. 
5.0  IMPLICATIONS 
5.1  Policy – none known.    
5.2  Financial – costs will be met within existing budgets. 
5.3   Legal – planting will be carried out in line with any relevant requirements.    
5.4   HR – none known. 
5.5   Customer Service – none known but the planting project offers an opportunity   
to secure additional amenities for local communities.    
5.6.  Risk – risks will be managed through existing and established Amenity Services
procedures for activities of this nature.    
5.7   Climate Change – none known. 
5.8   Fairer Scotland Duty – none known. 
5.9   Equalities - protected characteristics – where and if appropriate EqSEIAs will
be carried out to identify any implications. 
5.10   Consumer Duty – where and if appropriate EqSEIAs will be carried out to
identify any implications. 
5.11    Islands – where and if appropriate island impacts assessments will be carried
out to identify any implications. 
5.12    Children’s Rights and Wellbeing – none known. 
Executive Director with responsibility for Legal and Regulatory Support,
Douglas Hendry 
7th November 2025 
For further information contact:    
Aileen McNicol, Leadership Support and Member Services Manager, telephone 01546
604014 or email aileen.mcnicol@argyll-bute.gov.uk  
Page 107

Page 108

Appendix 1 – Elected Member Contributions – Potential Planting Locations in Mid
Argyll, Kintyre and the Islands   
Mid Argyll, Kintyre and the Islands   
Green lawn space at Aqualibrium 
Linda McCartney Garden at Burnett Building (single tree)   
Page 108