Democracy Spraffa

MAKI Expansion List

Argyll and Bute Council · 3 December 2025
Back to Mid Argyll, Kintyre & the Islands Area Committee — 3 December 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Classification: OFFICIAL#
AREA TOWN/VILLAGE EXISTING LOCATION COUNCIL
OWNED PROPOSED THEME PRIORITY COMMENTS
PIER, FERRY ROAD Y 1 x RAPID 1 1
To address a rapid charging network gap
between Campbeltown and Lochgilphead
[on the public road network for drivers]
TAYINLOAN FERRY FERMINAL Y 1 x RAPID 1 1 Rapid charger to be provided for cars in the
ferry queue as opposed to parked up.
TAYINLOAN FERRY FERMINAL Y 1 x FAST or
SLOW [TBC] 2 1
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
FERRY TERMINAL Y 1 x RAPID 1 2
Rapid charger to be provided for cars in the
ferry queue as opposed to parked up. As
part of ongoing works under the Marine
Asset Management Plan we are looking at
options for electricity upgrades for harbour
infrastructure which would include
capacity for EVC
FERRY TERMINAL Y 1 x FAST 2 2
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
CARRADALE SHORE ROAD CAR PARK Y 1 x RAPID 1 2 To address  a network gap in East Kintyre
CAMPBELTOWN ROAD CAR
PARK Y 1 x RAPID 1 1
To address an existing rapid charging
network gap between Campbeltown and
Lochgilphead. We have beneiftted from
45k of funding from SSE for use at this
location
1 x FAST CAMPBELTOWN ROAD CAR
PARK Y
Key
Chargers beyond economic life and removed from use
Chargers beyond economic life to be replaced via CCG to comply with new regulations
Sites expected to be delivered in 2025
Sites delivered since last update December 2022
Chargers beyond economic life and replaced as part of FASTER Project
TAYINLOAN
GIGHA
TARBERT
MID-ARGYLL,
KINTYRE AND
THE ISLANDS

Page 2

Classification: OFFICIAL#
NEW QUAY CAR PARK y 1 x FAST 2 2
Population of 2,000 to 5,000 - 25% off-
street car parks. Divergence from the
'higher to lower' original criteria of car
parks on the basis of local geography.
1 x RAPID NEW QUAY CAR PARK y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
ARDRISHAIG CHALMERS ST No. 2 CAR PARK 1 x FAST 2 1 Population 1,000 to 2,000 - one car park.
2 x FAST
AND 1 x
RAPID
LORNE ST No. 1 CAR PARK Y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
2 x FAST MANSE BRAE CAR PARK Y
INVERARAY
1 x FAST
AND 1 x
RAPID
THE AVENUE Y
Rapid charger beyond economic life and to
be replaced via CCG to comply with new
regulations
COLONSAY COLONSAY AIRPORT Y 1 x FAST or
SLOW [TBC] 2 4
Island airport. Through enabling funding
secured from TS we are working with
colleagues in Strategic Transport to
explore options for power upgrades here
which would both serve the airport itself,
which currently has no mains power, as
well as provide for EVC.
BOWMORE
1 x RAPID
AND 1 x
FAST
SCHOOL STREET CAR PARK Y
FERRY TERMINAL Y 1 x RAPID 1 2 Rapid charger to be provided for cars in the
ferry queue as opposed to parked up.
FERRY TERMINAL Y 1 x FAST or
SLOW [TBC] 2 2
Second charger at this site to provide for
those ferry passengers who wouldleave
their car.
CRAIGHOUSE ISLAY COUNCIL CAR PARK 1 x FAST 2 3
Proposed instead of Feoilin ferry terminal
with a view to providig for the main service
centre, also noting that the ferry crossiNG
s relatively short and there is provision on
the Islay side
13
MID-ARGYLL,
KINTYRE AND
THE ISLANDS
CAMPBELTOWN
LOCHGILPHEAD
PORT ASKAIG

Page 3

Classification: OFFICIAL#
ADDITIONAL CHARGERS DELIVERED THROUGH HITRANS FASTER
MID-ARGYLL,
KINTYRE AND
THE ISLANDS TARBERT 1 x RAPID FERRY TERMINAL
PROJECT AUTUMN/WINTER 2023