ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
14 June 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 17 March 2022 in relation to
the delivery of a dedicated, high quality walking and cycle route linking
Helensburgh, Cardross and Dumbarton. 
1.2. Officers are working with WSP to get a programme in place to complete the
design process to the final technical design stage. 
1.3. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive challenge funding, committing
appropriate match funding and securing access to private land for the route. 
1.4. The Council’s Active Travel Team (1.3 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing external highly competitive
challenge funds. 
RECOMMENDATIONS 
1.5. It is recommended that the Helensburgh and Lomond members: 
i. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process.

Page 2

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
14 June 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 17 March 2022 in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh, Cardross
and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
i. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process. 
4.0 DETAIL 
Finances 
4.1. Design (Colgrain to Cardross & Cardross to Dumbarton).  Funding for the
design development has been confirmed from the Transport Scotland Places for
Everyone programme, administered by Sustrans.  This is a highly competitive
challenge fund which requires projects to closely comply with the ever evolving
design requirements set by Sustrans as administrators of the funding. 
4.2. Construction (Cardross Rail Station to Geilston Burn).  Costs for the final
works in Cardross Park to complete the section linking Cardross Rail Station to
the Geilston Burn have been paid to the Council’s Roads and Infrastructure
Service. These costs were secured from Strathclyde Partnership for Transport
(SPT) Capital Programme and the Scottish Government’s Cycling, Walking and
Safer Routes fund. 
4.3. The Council’s Active Travel Team (1.3 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing external challenge funds.

Page 3

Design 
4.4. Transport Scotland’s Places for Everyone funding programme, administered by
Sustrans, is structured around 8 project stages with gateways which require
approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use. 
4.5. Developed design (stage 3) work for the outstanding section of the route linking
Colgrain to Geilston Burn, Cardross and Ferry Road, Cardross to Dumbarton
has been paused by WSP.  Officers are working with WSP to confirm a
programme to complete the developed design, including considering the
outcomes of the community engagement prior to progressing the necessary
design work. 
4.6. Technical Design (stage 4) engineering investigation and design finalization is
planned to be progressed following completion of the develop design stage. 
Officers are working with WSP to confirm a programme to complete the
technical design stage.  Once completed, the Developed Design and Technical
Design will complete the design stages required prior to land acquisition and
construction. 
4.7. Landowner engagement.  As instructed, WSP have sought engagement with
all identified landowners affected by the route to gain their input to the design
development.  Landowner comments have been considered and, where
appropriate incorporated, within the developed designs. 
4.8. Helensburgh Town.  An application for funding was submitted on 08 November
2021 to Transport Scotland’s Places for Everyone fund, administered by
Sustrans, for funding to undertake a high quality community engagement to
identify demand for and a potential route(s) of the Cyclepath from the western
edge of Helensburgh into the centre of the town.  Disappointingly, despite
Sustrans Officers stating they expected to provide a quick decision on the
application; since submission no decision on the funding request has been
made and no timescale for providing a decision has been provided by Sustrans. 
Due to the entire reliance of this project on external funding it is not possible to
commence work on this important section of the route until a funding decision is
received. 
Construction: Cardross Station to Geilston Burn 
4.9. The section of route linking Cardross Station to Cardross Park opened in
December 2021 and is already being well used by the community.   
4.10. The permanent pedestrian and cycle bridge over the Geilston Burn was installed
on 29 October 2021.  Following this, the Council’s Roads Operations team
continue to work to progress with the final surfacing, signs and lines for the
whole route linking Cardross Station to the Geilston Burn.  It is now expected

Page 4

this work will be completed by summer 2022, to fit within the available delivery
capacity. 
Programme 
4.11. Appendix 1 provides an the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.12. Appendix 2 provides an update on commercial discussions with the design
contractor and the current position on land negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following detailed design work and as and when land purchases have been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive challenge funding, committing
appropriate match funding and securing access to private land for the route. 
6.0 IMPLICATIONS 
6.1  Policy - Completion of this project will support the Council’s SOA outcomes 2:
We have infrastructure that supports sustainable growth and 5: People live
active, healthier and independent lives. The project also supports
achievement of the Scottish Government’s objectives set out in the Cycling
Action Plan for Scotland (CAPS) and Let’s Get Scotland Walking - The
National Walking Strategy. 
6.2  Financial - The design, construction and land purchase will be funded by
external grant funding applications. The Council has not contributed any
funding to design or capital costs.  There is evidence to indicate that people
who are more active, for example by walking or cycling, are less likely to
require social care services in later life which could result in a future saving to
the Council or HSCP although the value of this would be difficult to quantify. 
6.3  Legal – Continued input will be required from Legal Services to support
contractual agreements and land purchase including a CPO should this be
deemed necessary.

Page 5

6.4  HR – None. 
6.5  Fairer Scotland Duty 
6.5.1  Equalities - Completion of this project will provide opportunities for all in the
Helensburgh – Cardross – Dumbarton corridor to travel more sustainably and
actively by walking, wheeling and cycling. 
6.5.2  Socio-economic Duty – The route has been designed to be DDA compliant
and will provide a safe and accessible route for those with mobility aids
including wheelchairs and parents/guardians with a child’s pram or buggy. 
6.5.3  Islands – there are no adverse impacts.   
6.6  Climate Change – Active Travel is the least carbon intensive mode of travel. 
Providing the opportunity for residents and visitors to consider an alternative to
having to use a private car to travel between these communities will help lower
Argyll and Bute’s carbon footprint. 
6.7  Risk – There is a reputational risk to the Council if the project is not completed
within a reasonable timeframe. 
6.8  Customer Service – None.   
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Economy and Rural Growth: Councillor Robin Currie   
19 May 2022                                                  
For further information contact:  
Colin Young, Strategic Transportation Delivery Officer
Colin.Young@argyll-bute.gov.uk / Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]