Democracy Spraffa

Agenda reports pack

Argyll and Bute Council · 20 September 2022
Back to Helensburgh & Lomond Area Committee — 20 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Argyll and Bute Council 
Comhairle Earra-Ghàidheal Agus Bhòid 
Executive Director:  Douglas Hendry 
Kilmory, Lochgilphead, PA31 8RT
Tel:  01546 602127  Fax:  01546 604435
DX 599700 LOCHGILPHEAD
12 September 2022 
NOTICE OF MEETING 
A meeting of the HELENSBURGH & LOMOND AREA COMMITTEE will be held in the
HELENSBURGH AND LOMOND CIVIC CENTRE on TUESDAY, 20 SEPTEMBER 2022 at 9:30
AM, which you are requested to attend. 
Douglas Hendry
Executive Director 
BUSINESS 
1. APOLOGIES 
2. DECLARATIONS OF INTEREST 
3. MINUTE OF THE MEETING OF THE HELENSBURGH AND LOMOND AREA
COMMITTEE, HELD ON 14 JUNE 2022 (Pages 3 - 8) 
4. PUBLIC QUESTION TIME 
5. POLICE SCOTLAND UPDATE (Pages 9 - 10)  
Update from Inspector Andrew Barron, Police Scotland 
6. AREA PERFORMANCE REPORT - FQ1 2022/23 (Pages 11 - 52)  
Report by Executive Director with responsibility for Customer Support Services 
7. ROADS AND INFRASTRUCTURE SERVICES UPDATE (Pages 53 - 58)  
Report by Executive Director with responsibility for Roads and Infrastructure Services 
8. RECYCLING AND RECOVERY PERFORMANCE (Pages 59 - 66)  
Report by Executive Director with responsibility for Roads and Amenity Services 
9. HELENSBURGH WATERFRONT DEVELOPMENT (HWD) - PROJECT POSITION
UPDATE (Pages 67 - 84)  
Report by Executive Director with responsibility for Commercial Services 
10. REFERRAL FROM THE AUDIT AND SCRUTINY COMMITTEE - COMMUNITY
ASSET TRANSFER REVIEW (Pages 85 - 102)  
Extract of Minute of Audit and Scrutiny Committee held on 23 June 2022 and report
Public Document Pack

Page 2

by Chair of the Community Asset Transfer Scrutiny Panel 
REPORTS FOR NOTING 
11. HELENSBURGH AND LOMOND AREA COMMITTEE WORKPLAN (Pages 103 -
108) 
EXEMPT REPORT FOR DECISION 
12. HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
(a) Report by Executive Director with responsibility for Development and
Economic Growth (Pages 109 - 116)  
(b) Appendix 1 (Pages 117 - 118)
E1  (c) Appendix 2 (Pages 119 - 122)
,
The Committee will be asked to pass a resolution in terms of Section 50(A)(4) of the Local
Government (Scotland) Act 1973 to exclude the public for items of business with an “E” on the
grounds that it is likely to involve the disclosure of exempt information as defined in the
appropriate paragraphs of Part 1 of Schedule 7a to the Local Government (Scotland) Act 1973. 
The appropriate paragraph is:- 
E1 
Paragraph 6 
Information relating to the financial or business affairs of any particular person (other than the
authority). 
Helensburgh & Lomond Area Committee 
Councillor Math Campbell-Sturgess Councillor Maurice Corry
Councillor Graham Hardie Councillor Fiona Howard
Councillor Mark Irvine Councillor Paul Donald Kennedy
Councillor Ian MacQuire Councillor Gary Mulvaney (Vice-Chair)
Councillor Iain Paterson Councillor Gemma Penfold (Chair)   
Shona Barton, Committee Manager 
Contact: Lynsey Innis, Senior Committee Assistant - 01546 604338

Page 3

MINUTES of MEETING of HELENSBURGH & LOMOND AREA COMMITTEE held in the
MARRIAGE ROOM, HELENSBURGH & LOMOND CIVIC CENTRE 
on TUESDAY, 14 JUNE 2022 
Present: Councillor Gemma Penfold (Chair) 
Councillor Math Campbell-Sturgess
Councillor Maurice Corry
Councillor Graham Hardie
Councillor Fiona Howard 
Councillor Mark Irvine
Councillor Paul Kennedy
Councillor Gary Mulvaney
Councillor Ian MacQuire
Attending: Shona Barton, Committee Manager
Inspector Roddy MacNeill, Police Scotland
Charlotte Craig, Business Improvement Manager, Argyll and Bute HSCP
Simone McAdam, Education Manager
Mark Calder, Project Manager 
Colin Young, Senior Transport Delivery Officer 
The Chair welcomed everyone to the meeting, giving a special welcome to the newly
elected members. 
1. APOLOGIES 
An apology for absence was intimated from Councillor Iain Paterson. 
2. DECLARATIONS OF INTEREST 
Councillor MacQuire declared a non-financial interest in item 9 (Appointment to Outside
Bodies – Dunbritton Housing Association) of these minutes on the basis that his relative
was the Chair of Dunbritton Housing Association.  He advised that the interest was
insignificant in terms of the request to appoint a member on behalf of the Area Committee
and he remained in the meeting when the matter was determined. 
3. MINUTE OF THE MEETING OF THE HELENSBURGH AND LOMOND AREA
COMMITTEE, HELD ON 17 MARCH 2022 
The Minutes of the meeting of the Helensburgh and Lomond Area Committee meeting of
17 March 2022 were approved as a correct record. 
4. PUBLIC QUESTION TIME 
The Committee Manager read out a question from Sarah Davies, Helensburgh Resident
and Helensburgh Community Councillor, regarding Lighting in Colquhoun Square.   
“Can it please be explained why it has taken six months from the first report of problems,
an upheld official complaint and numerous phone calls to get the lights repaired in
Colquhoun Square  (All those who answered my numerous calls were, efficient, polite and
helpful I thank them for that) Are the lights now fully operational? 
Page 3 Agenda Item 3

Page 4

Why at no time were the reported faults logged on the website as reported, as other
lighting faults are? 
Can we please be assured that this problem will not occur again. Functional Street
Lighting is a matter of Health and Safety particularly for women, girls, the elderly and the
vulnerable.” 
Mark Calder, Project Manager responded by advising that the lighting was not currently
operational.  This was as a result of the columns being non-standard construction,
requiring specialist parts.  He advised that the ordering had been impacted by a review of
suppliers to ensure continued best value.  The parts have been ordered but due to the
specialist nature there was no timescale for their delivery. 
With regard to the upheld complaint, Mark explained that the complaint was in regard to
the flow of information rather than the fault.  This had been due to the operational and
customer facing case management systems being misaligned due to a glitch.  Regarding
the website, he advised that the complaint had been logged, was in the system, and was
being actioned. 
In terms of assurances that there would be no further issues, Mark commented that it was
not possible to assure that there would never be another fault but that changes in the
management and reporting system should reassure that service requests are robustly and
appropriately managed.  Mark advised that he was in correspondence with the author of
the question and that he would update the person directly when more was known about
the delivery timescales. 
Councillor MacQuire commented that to his knowledge 14 of the 22 lights had now been
fixed. 
5. POLICE SCOTLAND UPDATE 
The Committee considered an update by Inspector MacNeill which included the
appointment of a new Chief Inspector, Samantha Glasgow; Operation Balaton (the multi-
agency approach to ensure effective policing due to summer tourism); joint patrols with
Argyll and Bute Council and National Park Wardens; support for community events such
as discos and a Midnight football league; speeding and crime figures; and DBI (Distress
Brief Intervention) which training is ongoing to ensure those in distress can be assisted to
get the right care of partner organisations. 
Decision 
The Chair, on behalf of the Committee, thanked Inspector MacNeill for his attendance and
informative update. 
(Reference:  Undated Report by Inspector MacNeill, submitted) 
6. INTEGRATION JOINT BOARD PERFORMANCE REPORT (MAY 2022) 
A report providing the Committee with an update on the impact on service performance
and the progress made with regard to remobilising health and social care services in
Argyll and Bute up to 31 March 2022 was considered. 
Page 4

Page 5

Decision 
The Helensburgh and Lomond Area Committee: 
1. considered the HSCP performance progress presented to the IJB on 25 May
regarding remobilisation of activity in line with NHS Highland performance target for
2021/22 agreed with Scottish Government to 70%-80% of 2019/20 activity as at
November 2021;
2. considered Waiting Times Performance and a further reduction in Consultant and
Nurse Led Outpatient breaches greater than 12 weeks;
3. noted performance with regards to both Argyll and Bute and Greater Glasgow and
Clyde current Treatment Time Guarantee for Inpatient/Day Case Waiting List and
activity; and
4. noted Scottish Government’s advice on timescales for the publication of 2021/22
Annual Performance Report (APR). 
(Reference:  Report by Head of Strategic Planning, Performance and Technology, Argyll
and Bute HSCP dated 7 June 2022, submitted) 
7. PRIMARY SCHOOL REPORT 2021-22 - HELENSBURGH AND LOMOND AREA 
A report providing a range of key information about school provision in the Helensburgh
and Lomond area during the school session August 2021 to June 2022 along with the
National collection of attainment and achievement data from June 2021 was considered.  
Decision  
The Helensburgh and Lomond Area Committee considered and noted the contents of the
report.  
(Reference: Report by Executive Director with responsibility for Education, dated 7 June
2022, submitted) 
8. ROADS AND INFRASTRUCTURE SERVICES UPDATE 
A report providing a general update on key activities of the Service over recent months
and highlighting works being undertaken which were of relevance to the Helensburgh and
Lomond area was considered.  
For the benefit of the new Members of the Committee, the Project Manager also gave an
overview of the extensive remit, scope and responsibilities of the Service and the wide
range of work and strategic projects currently being undertaken across the whole Council
area.  
Decision  
The Helensburgh and Lomond Area Committee noted and considered the contents of the
report.  
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services dated May 2022, submitted) 
Page 5

Page 6

9. APPOINTMENTS TO OUTSIDE ORGANISATIONS 
A report asking the Committee to consider making appointments to a number of local
bodies/organisations within the Helensburgh and Lomond area was considered.  The
Committee Manager also advised that an additional request to appoint a substantive
representative to the Glasgow Airport Consultative Committee had been received since
the agenda had been issued and invited the Committee to also consider making an
appointment to that group.  
Decision  
The Helensburgh and Lomond Area Committee agreed to make the following
appointments: 
Organisation Elected Member(s) 
Cardross Trust  Councillor Kennedy
Dunbritton Housing Association Councillor Mulvaney 
Helensburgh and Lomond Area
Community Planning Group
Councillors Irvine (Ward 9), Howard
(Ward 10) and Penfold (Ward 11)
Helensburgh and Lomond Locality
Planning Group
Councillor Hardie
Gourock, Dunoon and Kilcreggan
Harbour Reference Group
Councillor Irvine was proposed by
Councillor Howard, seconded by
Councillor MacQuire.  Councillor
Corry was proposed by Councillor
Mulvaney, seconded by Councillor
Hardie.  The amendment to appoint
Councillor Corry was carried by 5
votes to 4 and the Committee
agreed to appoint Councillor Corry to
the Group. 
Dunbartonshire Educational Trust Councillor Campbell-Sturgess
Glasgow Airport Consultative
Committee
Councillor Paterson subject to
confirmation of acceptance of the
appointment. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 24 May 2022, submitted) 
10. REQUEST FOR FINANCIAL ASSISTANCE - HELENSBURGH AND DISTRICT
TWINNING ASSOCIATION 
A report providing information on a request from the Helensburgh and District Twinning
Association for financial assistance to help with a visit to Thouars in 2023 and a visit to
Helensburgh by residents from Thouars in 2024 was considered. 
Page 6

Page 7

Decision 
The Helensburgh and Lomond Area Committee agreed to award the sum of £833 from the
Helensburgh and Lomond Area Twinning Budget for 2022/23 to Helensburgh and District
Twinning Association. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 25 June 2022, submitted) 
11. AREA SCORECARD FQ4 2021-22 
A paper presenting the Area Scorecard for Financial Quarter 4 2021/22 (January to March
2022) which illustrated the agreed performance measures was considered.  
Decision  
The Helensburgh and Lomond Area Committee:  
1.    noted and considered the performance and supporting commentary as presented; 
2.    noted that upon receipt of the Quarterly Performance Report the Committee should
contact either the Responsible Named Officer or the Performance Improvement Officer
with any queries; 
3.    noted that work was ongoing and that Members should respond to the Performance
Improvement Officer with requests or comments regarding the layout and format of the
Performance Report; and 
4.    noted the proposal to include the additional Corporate Outcome Indicators within the
quarterly Area Committee report.  
(Reference: Report by Executive Director with responsibility for Customer Support
Services dated 9 May 2022, submitted) 
12. HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
A report updating Members on the progress made since the previous report to the
Helensburgh and Lomond Area Committee on 17 March 2022 in relation to the delivery of
a dedicated, high quality walking and cycle route linking Helensburgh, Cardross and
Dumbarton was considered. 
Decision 
The Helensburgh and Lomond Area Committee the continued efforts of Officers to engage
with WSP Design Consultants to confirm the programme to complete the design process. 
(Reference: Report by Executive Director with responsibility for Strategic Transport dated
19 May 2022, submitted) 
13. HELENSBURGH AND LOMOND AREA COMMITTEE WORKPLAN 
The Helensburgh and Lomond Area Committee Workplan was before Members for
information.   
Page 7

Page 8

Decision  
The Helensburgh and Lomond Area Committee noted the contents of the Workplan.  
(Reference: Helensburgh and Lomond Area Committee Workplan dated 14 June 2022,
submitted) 
Page 8

Page 9

OFFICIAL 
OFFICIAL
Area Committee Report for September 2022 
Police Scotland
Inspector Andy Barron
Helensburgh & Lomond Area 
Temporary change in personnel within the area with Police Inspector Andy Barron covering for
Inspector Roddy MacNeill for a period. 
The Youth Engagement Officer for the area PC Mark Toner is now dedicated solely to the
Helensburgh and Lomond area as an additional post for this work has been created for Dunoon and
Cowal. This additional capacity will allow us focus on re-establishing previously successful Police
Scotland Youth Volunteer Groups and to work more closely with Care Experienced Young people to
deliver on our responsibilities as a corporate parent. We are looking at opportunities to learn from
Glasgow’s implementation of the ‘Respect’ Programme and options to utilise our Youth Engagement
Officers to deliver against the outcomes and provide support and reduce harms for Care Experienced
Young People.
Adverts are being run at present for officers to apply for a Community Policing Team for the area.
Development in terms of remit for this proposed department is ongoing and action plans have been
drawn up to tackle anti-social behaviour, drug misuse and violence in hot spot areas and increased
high visibility patrols in these areas is hoped will increase public confidence and build relationships
with local communities.
The four new probationary officers have commenced deployment from Helensburgh Police Office
spread across the various shifts. 
Building, facilities and vehicle fleet are all in operational order. The office will take receipt of a new
marked police vehicle mid September. 
I am engaging regularly with the ASB group and the co-ordinator. 
Multi-agency meetings continue as part of Operation Balaton. This is the operation to ensure we
provide the most effective policing model to deal with the large increase in footfall across the area
during the summer months. 
Chief Inspector Glasgow and Inspector Barron have met with the Chair of the Luss Estates and
members of the Luss Community Council regarding disorder related concerned in relation to the
good weather periods. 
The joint patrols with the NP Rangers on Loch Lomond take place where resourcing allows to ensure
loch users are acting responsibly, safely and in line with the park by-laws. Also allows for a police
presence on the islands during the course of the shift. Very worthwhile given the substantial
increase in the use of both powered and non-powered craft on the water.
Police Scotland, Royal Navy Police and Ministry of Defence Police have established joint patrols of
Helensburgh Town Centre on weekends to promote the safety and wellbeing of members of the
public and prevent criminality taking place or escalating.  The patrols are also being utilised to work
Page 9 Agenda Item 5

Page 10

OFFICIAL 
OFFICIAL
with licensed premises, including staff and managers promoting the responsible sale of alcohol. The
overall objective is to adopt a collaborative approach to provide a safe recreational environment,
maximising public safety and reduce anti-social behaviour and disorder.
We are working closely with the Drug and alcohol Partnership to look at ways to better support
families affected by Drugs Deaths in the Community. We are meeting with our partners from NHS
and We are With You to establish how Police Scotland can play an effective role locally in prevention
and support and are scheduled to attend a number of local groups to establish greater working
relationships and actively try and reduce the stigma of addiction.
PC Toner had been continuing with Live Argyll, MDP and SFRS in carrying out the weekly midnight
football league at Hermitage Academy from June to August to help keep youths occupied and to
provide an opportunity to engage with those attending in an informal setting.       
Attention is being given to speeding whenever possible. Members of the public and local councillors
regularly suggest areas of concern and where resources can be allocated, the most appropriate
areas are identified. Power issue remains and causing a delay to the operational functionality of the
speed camera in Cardross. Work continues to have this rectified. 
Training has commenced for selected officers in Distress Brief Intervention (DBI). As noted in the
June report this allows for front line services such as ourselves, to provide another level of support
and care to distressed members of the public and for us to refer them on to qualified staff from
partner organisations that can provide the help quickly and properly. 
Page 10

Page 11

1 
ARGYLL AND BUTE COUNCIL HELENSBURGH AND
LOMOND AREA COMMITTEE 
CUSTOMER SUPPORT SERVICES   13 SEPTEMBER 2022 
AREA PERFORMANCE REPORT – FQ1 2022/23 
1 Background 
1.1 This paper presents the Area Performance Report for Financial Quarter 1 2022/23
(April to June 2022) and illustrates the agreed performance measures. 
1.2 As previously agreed the 14 quarterly Corporate Outcome Indicators (COIs) are
now reported to all Area Committees on a quarterly basis, and are now included in
the Performance Reports. 
The features of the Performance Report are as follows:- 
 The Report mirrors the information as presented on the Scorecard.
 The Report is effectively ‘owned’ by the appropriate Area Committee.
 Indicators are grouped by Corporate Outcome.
 The data table for each indicator is coded to identify the level of reporting.
o Area level measures are blue
o Council level measures are grey
o COI measures are white 
 Each indicator details 
o The Target, Actual and Performance status (Green / Red / No Target)
for the current and three previous financial quarters.
o Commentary for the current financial quarter only.
o Narrative explaining the performance trend e.g. This indicator is above
Target and performance has improved since the last reporting period.
o The name of the responsible officer.
o Where possible performance is presented at both Area and Council
level. 
It should be noted that Pyramid remains live and all measures can be navigated
as usual through the front screen. If support to navigate Pyramid is required please
email pyramid@argyll-bute.gov.uk 
1.3 The commentary for each indicator helps ‘Tell Our Story’ and enables Elected
Members to put the performance data into perspective and understand if an issue is
local in nature or should be escalated up to a Strategic Committee.   
1.4 To improve the response to performance queries, it is requested that either the
Responsible Named Officer or Sonya Thomas are contacted once the Quarterly
Performance Report is received with any queries. This should enable some
Page 11 Agenda Item 6

Page 12

2 
queries being resolved or clarified prior to the Area Committee meeting, and
therefore being carried forward as Actions at a subsequent meeting. 
2 Recommendations 
2.1 It is recommended that the Area Committee – 
a) Notes and considers the performance and supporting commentary as
presented. 
b) Upon receipt of the Quarterly Performance Report the Area Committee
contact either the Responsible Named Officer or Sonya Thomas with any
queries. 
c) Note that work is ongoing and to respond to Sonya Thomas with requests
or comments regarding the layout and format of the Performance Report
and Scorecard. 
3.0 IMPLICATIONS 
3.1 Policy: None
3.2 Financial: None
3.3 Legal: None
3.4 HR: None
3.5 Fairer Scotland Duty: No impact assessment required for this report. 
3.5.1 Equalities: None. If requested the Area Committee Performance Report
can be supplied in a different format.
3.5.2 Socio-economic Duty: None
3.5.3 Islands: None 
3.6 Climate Change: None
3.7 Risk: None
3.8 Customer Service: None 
Kirsty Flanagan, Executive Director with responsibility for Customer Support
Services 
Jane Fowler
Head of Customer Support Services
25 July 2022 
For further information, please contact:
Sonya Thomas
Organisation Development Officer - Performance and Improvement
Page 12

Page 13

3 
Customer Support Services
01546 604454 
Appendix 1: FQ1 2022/23 H&L Performance Report 
Page 13

Page 14

Appendix 1
Page 1 
Helensburgh and Lomond
FQ1 2022/23 Overall Performance Summary 
The information presented is a summary of the measures in the Scorecard that is available on Pyramid. 
The measures show the performance against target for the current and previous three reporting periods with an explanation of performance trend. 
The data table for each indicator is colour coded to identify the level of reporting: 
 Area level measures are blue.
 Council level measures are grey.
 Corporate Outcome Indicators (COIs) are white. 
Page 14

Page 15

Appendix 1
Page 2 
Index of Measures 
Corporate Outcome No.1 – People live active healthier independent lives
COI – Maximise distribution of Scottish Welfare Fund
COI – Percentage of clients satisfied that they are better able to deal with their financial problems following our support and
intervention 
Corporate Outcome No.2 – People live in safer and stronger communities
Number of parking penalty notices issued
Car parking income to date
Dog fouling – total number of complaints 
Corporate Outcome No.3 – Children and young people have the best possible start
COI – Increase the percentage of our care experienced young people that have the recommended additional tracking and
monitoring plans in place
COI – Provide quality meals within cost margins to all pupils 
Corporate Outcome No.4 – Education, skills and training maximises opportunities for all
Maintain the percentage of 16-19 year olds participating in education, training or employment 
Corporate Outcome No. 5 – Our economy is diverse and thriving
Number of affordable social sector new builds completed per annum
Percentage of pre-application enquiries processed within 20 working days
Householder planning applications – average number of weeks to determine
COI – The number of new homeless applicants who required temporary accommodation this period
COI – Maintain the percentage of local suppliers that benefit from the awards of contracts via the procurement portal
COI – Increase the number of community benefits that are delivered through contracts we award locally 
Page 15

Page 16

Appendix 1
Page 3 
Corporate Outcome No.6 – We have an infrastructure that supports sustainable growth
Street lighting – percentage of faults repaired within 10 days
Total number of complaints regarding waste collection
COI – Percentage of waste recycled, composted and recovered
Shanks – Percentage of waste that is recycled, composted and recovered
Islands – Percentage of waste recycled, composted and recovered
H&L – Percentage of waste recycled, composted and recovered
COI – The number of tonnes of waste sent to landfill
LEAMS (Local Environment Audit and Management System) 
Make It Happen
Teacher sickness absence
LGE staff (non-teacher) sickness absence
COI – Increase the percentage of all self-service and automated contacts Page 16

Page 17

Appendix 1
Page 4 
Helensburgh and Lomond
Corporate Outcome No.1 – People live active, healthier and independent lives 
COI – Maximise distribution of Scottish Welfare Fund
Responsible person: Fergus Walker 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is below target and performance has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 95.3% 134.5% Green
FQ3 2021/22 95.3% 130.0% Green
FQ4 2021/22 95.3% 120.7% Green
FQ1 2022/23 95.3% 87.5% Red 
FQ1 Comment
We have currently spent £102,039 of our 2022/23 allocation of £458,338 which is less than our monthly profile amount however as the cost-of-living pressures
continue we expect this figure to increase as the year progresses. 
Page 17

Page 18

Appendix 1
Page 5 
Helensburgh and Lomond
Corporate Outcome No.1 – People live active, healthier and independent lives 
COI – Percentage of clients satisfied that they are better able to deal with their financial problems following our support and
intervention
Responsible person: Lee Roberts 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator has met the target with no change in performance since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 100% 100% Green
FQ3 2021/22 100% 100% Green
FQ4 2021/22 100% 100% Green
FQ1 2022/23 100% 100% Green 
FQ1 Comment
There were no Debt Arrangement Schemes set up in this quarter. All of the clients provided with a Personal Debt Recovery Action Plan were satisfied. Out of 8
surveys issued 5 were returned showing 100% of clients satisfied. Four of the 5 survey returns had comments showing their appreciation of the service and how it
had helped them. 
Page 18

Page 19

Appendix 1
Page 6 
Helensburgh and Lomond
Corporate Outcome No.2 – People live in safer and stronger communities 
Number of parking penalty notices issued – Helensburgh and Lomond
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
The indicator for FQ1 shows the number of parking penalty notices has significantly increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 1,241 No target
FQ3 2021/22 No target 769 No target
FQ4 2021/22 No target 760 No target
FQ1 2022/23 No target 1,411 No target 
FQ1 Comment
Luss village issues remain same with drivers unaware of restrictions and receiving Penalty Charges. Arrochar car park full to capacity on good weather. Wardens
from other areas assisting in enforcing Lomond area. 
Number of parking penalty notices issued – Argyll and Bute
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of parking penalty notices has significantly increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 1,583 No target
FQ3 2021/22 No target 973 No target
FQ4 2021/22 No target 1,188 No target
FQ1 2022/23 No target 2,043 No target 
Page 19

Page 20

Appendix 1
Page 7 
FQ1 Comment
ABC areas are returning to pre-Covid levels. Lomondside is especially busy on good weather weekends. 
Page 20

Page 21

Appendix 1
Page 8 
Helensburgh and Lomond
Corporate Outcome No.2 – People live in safer and stronger communities 
Car parking income to date – Helensburgh and Lomond
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the amount of income collected has exceeded the target. 
Reporting Period Target Actual Status
FQ2 2021/22 £114,206 £179,755 Green
FQ3 2021/22 £148,442 £224,101 Green
FQ4 2021/22 £181,503 £239,840 Green
FQ1 2022/23 £42,168 £60,908 Green 
FQ1 Comment
Helensburgh, Luss and Lomond areas have experienced larger than normal visitors over the first quarter. This is in part due to good weather and the easy
commute from the Glasgow area. 
Income collected in FQ4 and FQ1. 
Car Park Location FQ4 Actual FQ1 Actual
Arrochar £1,782 £16,712
Luss, Lomond £9,031 £31,979
Sinclair Street, Helensburgh £0 £1,410
Maitland Street, Helensburgh £24 £33
Pier, Helensburgh £4,206 £10,751
H&L £695 £23 
Page 21

Page 22

Appendix 1
Page 9 
Car parking income to date – Argyll and Bute
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the amount of income collected is significantly lower than the target. 
Reporting Period Target Actual Status
FQ2 2021/22 £507,833 £491,275 Red
FQ3 2021/22 £660,069 £699,363 Green
FQ4 2021/22 £807,078 £801,606 Red
FQ1 2022/23 £250,264 £165,678 Red 
FQ1 Comment
Bute and Cowal and Oban, Lorn and the Isles appear to still be affected whereby visitor numbers are still well down compared to pre-Covid. It is hoped in the
second quarter that visitor numbers will increase however this again is dependent on good weather. We have not seen a return to predicted numbers for camper
vans and motor homes. 
Page 22

Page 23

Appendix 1
Page 10 
Helensburgh and Lomond
Corporate Outcome No.2 – People live in safer and stronger communities 
Dog fouling – total number of complaints – Helensburgh and Lomond
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of dog fouling complaints has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 9 No target
FQ3 2021/22 No target 9 No target
FQ4 2021/22 No target 18 No target
FQ1 2022/23 No target 13 No target 
FQ1 Comment
The number of dog fouling complaints received this quarter for the Helensburgh/Lomond area is down on last quarter, this could be down to the increased patrols
by the Warden and the erection of new signs. 
Dog fouling – total number of complaints – Argyll and Bute
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of dog fouling complaints has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 46 No target
FQ3 2021/22 No target 60 No target
FQ4 2021/22 No target 81 No target
FQ 2022/23 No target 61 No target 
Page 23

Page 24

Appendix 1
Page 11 
FQ1 Comment
Although the number of dog fouling complaints has reduced this quarter it still remains high.  The warden service will continue to patrol and monitor as well as
engage with all parties in an attempt to explain and education on the issues of dog fouling. 
Page 24

Page 25

Appendix 1
Page 12 
Helensburgh and Lomond
Corporate Outcome No.3 – Children and young people have the best possible start 
COI – Increase the percentage of our care experienced young people that have the recommended additional tracking and monitoring
plans in place
Responsible person: Louise Lawson 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is on track with no change in performance since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 100% 100% Green
FQ3 2021/22 100% 100% Green
FQ4 2021/22 100% 100% Green
FQ1 2022/23 100% 100% Green 
FQ1 Comment
There is individual tracking and monitoring in place on SEEMIS in schools for care experienced children and young people. In addition to this, the Principal Teacher
for care experienced children and young people monitors the information in SEEMIS and has subsequent conversations with staff in schools to ensure care
experienced children and young people are receiving all the support they need to achieve and that the staff in school have the right strategies in place to help the
child remain engaged with their education attainment and achievement. Often the care experienced health and wellbeing officers are used to provide extra
support for the child and the family. 
Page 25

Page 26

Appendix 1
Page 13 
Helensburgh and Lomond
Corporate Outcome No.3 – Children and young people have the best possible start 
COI – Provide quality meals with cost margins to all pupils
Responsible person: Jayne Jones 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is below target however performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 5.00% -3.81% Green
FQ3 2021/22 5.00% -0.62% Green
FQ4 2021/22 5.00% -4.00% Green
FQ1 2022/23 5.00% 3.77% Green 
FQ1 Comment
The food cost percentage for the whole area showed a variance of 3.77%. We will continue to review the food cost percentage for those schools above and below
the 5% variance target. 
Page 26

Page 27

Appendix 1
Page 14 
Helensburgh and Lomond
Corporate Outcome No.4 – Education, skills and training maximises opportunities for all 
Maximise the percentage of 16-19 years olds participating in education, training or employment – Helensburgh and Lomond
Responsible person: Simon Easton 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is below target however performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 94.00% 93.88% Red
FQ3 2021/22 94.00% 91.98% Red
FQ4 2021/22 94.00% 92.79% Red
FQ1 2022/23 94.00% 92.88% Red 
FQ1 Comment
As has been the case in all areas of the authority, a reduction in participation was seen in Helensburgh and Lomond in the latter half of 2021, which can in some
measure be attributed to the effect of the Covid-19 pandemic on opportunities for young people, and its effect on resilience and wellbeing. Some recovery has
been seen in 2022. The appointment and work of the Developing the Young Workforce (DYW) Co-ordinator for the Helensburgh area are leading to improved links
between schools and employers, which have already led to more young people successfully entering employment post-school.  It is expected that the increase in
participation will continue as further work and interventions are put in place, by DYW, Education and Community Learning and Development, to support young
people into positive destinations. 
EDU107_04-Maintain the percentage of 16-19 years olds in Argyll and Bute participating in education, training or employment services
– Argyll and Bute
Responsible person: Simon Easton 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 has met the target and performance has improved since the last reporting period. 
Page 27

Page 28

Appendix 1
Page 15 
Reporting Period Target Actual Status
FQ2 2021/22 94.00% 94.29% Green
FQ3 2021/22 94.00% 93.17% Red
FQ4 2021/22 94.00% 93.80% Red
FQ1 2022/23 94.00% 94.00% Green 
FQ1 Comment
Across the authority, a reduction in participation was seen in the latter half of 2021, which can be in some measure attributed to the effect of the Covid-19
pandemic on opportunities for young people, and its effect on resilience and wellbeing. Nonetheless, authority participation levels have once again matched the
target level of 94%.  Some recovery has been seen in 2022. The appointment and work of the Developing the Young Workforce (DYW) Co-ordinators for all areas of
the authority are leading to improved links between schools and employers, which have already led to more young people successfully entering employment post-
school.  It is expected that the increase in participation will continue as further work and interventions are put in place, by DYW, Education and Community
Learning and Development, to support young people into positive destinations. 
Page 28

Page 29

Appendix 1
Page 16 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
Number of affordable social sector new builds completed per annum – Helensburgh and Lomond
Responsible person: Allan Brandie 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of completions has remained the same since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 0 0 Green
FQ3 2021/22 0 0 Green
FQ4 2021/22 0 0 Green
FQ1 2022/23 0 0 Green 
FQ1 Comment
There were no affordable housing completions in the Bute and Cowal area during Quarter 1 of 2022/23. 
DEG103_01-Number of affordable social sector new builds completed per annum – Argyll and Bute
Responsible person: Alan Brandie 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 has met the target however performance has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 19 19 Green
FQ3 2021/22 23 23 Green
FQ4 2021/22 45 45 Green
FQ1 2022/23 36 36 Green 
Page 29

Page 30

Appendix 1
Page 17 
FQ1 Comment
During Quarter 1, LINK completed 18 units at Dunbeg Phase 3 (all social rent, includes 2 wheelchair and 2 amenity units): 8 x 1bed, 4 x 2bed, 5 x 3bed, 1 x 4bed. In
Mid Argyll, Kintyre and Islay – West Highland Housing Association completed 8 units at Imeraval Phase 3, Islay: (6 social rent and 2 NSSE; includes 2 amenity units).
ACHA completed 10 units at Inveraray: (all social rent; includes 2 wheelchair units and 2 other suitable specialist units) 4x1bed, 4x2bed, 2x3bed. 
Page 30

Page 31

Appendix 1
Page 18 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
Percentage of pre-planning application enquiries processed within 20 working days – Helensburgh and Lomond
Responsible person: Peter Bain 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is below target however performance has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 75.0% 87.5% Green
FQ3 2021/22 75.0% 70.0% Red
FQ4 2021/22 75.0% 41.4% Red
FQ1 2022/23 75.0% 45.5% Red 
FQ1 Comment
The H&L team processed 45.5% of their pre-applications within the 20 working day target in FQ1, a 4% improvement on last quarter. 
It is advised that the Development Management team covering Bute, Cowal, Helensburgh and Lomond have been operating shorthanded for extended periods
since Summer 2020. The team operated from August 2020 to Feb 2021 with a vacant post and have operated since March 2022 until end Sept 2022 with a vacancy
in the Dunoon office (mitigated by p/t cover from an external contractor during July/August to ensure critical service delivery is maintained). During this period it is
also noted that teams based in both Oban and Mid Argyll have also operated for extended periods with vacancies which has negated the opportunity to redeploy
resources to provide cover for gaps at local level. 
The Council has experienced difficulty in recruiting suitably qualified professional planning officers during this period. This is not an issue which is unique to Argyll
and Bute but is a wider issue impacting other local authorities nationally. 
The Covid pandemic has given rise to a backlog of planning casework which has been exacerbated by a significant upsurge in the submission of applications for
determination over a time period where the Council has been understaffed and unable to recruit. Planning officers across the DM Service have been working
under considerable caseload pressure for an extended period of time and this has impacted adversely upon performance in the handling of planning applications,
responding to pre-application enquiries, and reduced the capacity available to deliver on enforcement. 
Page 31

Page 32

Appendix 1
Page 19 
The DM Service is actively seeking to recruit and advertises positions in national publications, has opened up professional positions to suitably qualified associated
professions (subject to relevant planning experience) and also as graduate opportunities’ it has also engaged with Heads of Planning Scotland and the Royal Town
Planning Institute in their efforts to address the longer-term availability of planning professionals. 
Percentage of pre-planning application enquiries processed within 20 working days – Argyll and Bute
Responsible person: Peter Bain 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is below target however performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 75.0% 65.5% Red
FQ3 2021/22 75.0% 61.7% Red
FQ4 2021/22 75.0% 56.3% Red
FQ1 2022/23 75.0% 60.5% Red 
FQ1 Comment
The Development Management Team continues to operate with reduced resource. As new officers settle in, the Service are concentrating resource on working
through planning applications which is a regulatory function. 
Page 32

Page 33

Appendix 1
Page 20 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
Householder planning applications – average number of weeks to determine – Helensburgh and Lomond
Responsible person: Peter Bain 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 has not met the target however performance has increased significantly since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 8.0 weeks 9.5 weeks Red
FQ3 2021/22 8.0 weeks 15.6 weeks Red
FQ4 2021/22 8.0 weeks 17.1 weeks Red
FQ1 2022/23 8.0 weeks 9.8 weeks Red 
FQ1 Comment
This measure only relates to planning applications received for alterations to existing premises.
The average of 9.8 weeks to determine householder applications is above the target of 8, however it is a significant improvement on last quarter’s figure of 17.1. 
Householder planning applications – average number of weeks to determine – Argyll and Bute
Responsible person: Peter Bain 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 has not met the target however performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 8.0 weeks 9.7 weeks Red
FQ3 2021/22 8.0 weeks 11.8 weeks Red
FQ4 2021/22 8.0 weeks 13.8 weeks Red
FQ1 2022/23 8.0 weeks 12.4 weeks Red 
Page 33

Page 34

Appendix 1
Page 21 
FQ1 Comment
This measure only relates to planning applications received for alterations for existing premises.
The Development Management Team continues to operate with reduced resource. The headline performance figure of an average of 12.4 weeks to determine
these applications shows an improvement from last quarter’s figure of 13.8. 
Benchmarking FY 2019/20, 2020/21 and 2021/22
This is one of several measures where the Development Management Service is benchmarked against The Scottish Government and "Rural 9" average
performance. 
Changes made by The Scottish Government in reporting cycles, have necessitated changes to the way we input benchmarking figures in Pyramid: 
(1) The annual benchmark figure, when published in July each year will be used to retrospectively update every FQ for that FY (applied to FY 2019/20 and FY
2020/21).
(2) This will be projected forward throughout the four FQ's of the next FY* (as has been standard practice in Development Management for over a decade
now). 
* projected benchmark figures are necessary to populate the field in Scorecard, due to the fact that information is now only published by The Scottish Government
twice a year. 
Page 34

Page 35

Appendix 1
Page 22 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
COI – The number of new homeless applicants who required temporary accommodation this period
Responsible person: Flora Lamont 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 shows the number of applicants has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 42 No target
FQ3 2021/22 No target 28 No target
FQ4 2021/22 No target 37 No target
FQ1 2022/23 No target 32 No target 
FQ1 Comment
During FQ1 – The Housing Service provided temporary accommodation to 32 new homeless households. 
Bute and Cowal – 13
Helensburgh and Lomond – 7
Oban, Lorn and the Isles – 10
Mid Argyll, Kintyre and Islay – 2 
Page 35

Page 36

Appendix 1
Page 23 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
COI – Maintain the percentage of local suppliers that benefit from the awards of contracts via the procurement portal
Responsible person: Anne MacColl-Smith 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is below target and performance has decreased slightly since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 20.0 25.8 Green
FQ3 2021/22 20.0 39.4 Green
FQ4 2021/22 20.0 13.5 Red
FQ1 2022/23 20.0 13.2 Red 
FQ1 Comment
13.2% – slight decrease from the previous quarter, again due to the nature of the contracts. However, of the 6 bids made by local contractors, 5 were awarded the
contract (83.3%) with a total value of over £92k. A summary of all contracts awarded in FQ1 is available on Pyramid. The PCCMT continue to support local
suppliers by providing useful information on the Council’s website, i.e. pre-recorded webinars on how to bid for Council contracts, hints and tips for tendering as
well as our contract plan, details of upcoming supplier development events and our category officer’s contact details all of which enable local suppliers to be able
to bid for our contracts. 
Page 36

Page 37

Appendix 1
Page 24 
Helensburgh and Lomond
Corporate Outcome No.5 – Our economy is diverse and thriving 
COI – Increase the number of community benefits that are delivered through contracts we award locally
Responsible person: Anne MacColl-Smith 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ4 shows the number of community benefits has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 15 No target
FQ3 2021/22 No target - No target
FQ4 2021/22 No target 40 No target
FQ1 2022/23 No target - No target 
FQ4 Comment
This indicator is reported in FQ2 and FQ4.
PCCMT has been working closely with their suppliers to deliver additional social, economic and environmental value and achieved 40 community benefits through
Contract Management, Contract Awards and the Request List from 1st October 2021 to 31st March 2022. Further detail is available on Pyramid. 
Page 37

Page 38

Appendix 1
Page 25 
Helensburgh and Lomond
Corporate Outcome No.6 – We have infrastructure that supports sustainable growth 
Street lighting – percentage of faults repaired within 10 days – Helensburgh and Lomond
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is below target however performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 75% 29% Red
FQ3 2021/22 75% 80% Green
FQ4 2021/22 75% 12% Red
FQ1 2022/23 75% 22% Red 
FQ1 Comment
The number of reported faults has reduced in FQ1, as weather conditions improved slightly and lighter nights reduced the lighting up time period. The total
number of instructions completed in the quarter was 50, of which 11 were completed in 10 days or less, giving an efficiency of 22%. The FQ1 21/22 figure is logged
as 15% therefore there is a marginal improvement in performance. Response times continue to be affected by operator absences, geography and delays in the
supply chain. 
RIS113_05-The percentage of street lighting faults are completed within 10 working days – Argyll and Bute
Responsible person: Hugh O’Neill 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is below target however performance has improved slightly since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 75% 31% Red
FQ3 2021/22 75% 59% Red
FQ4 2021/22 75% 28% Red
Page 38

Page 39

Appendix 1
Page 26 
Reporting Period Target Actual Status
FQ1 2022/23 75% 29% Red 
FQ1 Comment
A total of 116 individual lighting fault instructions were started and completed within the quarter which is approximately one third of that completed in the
previous period. However only 34 of these were done in 10 days or less, giving the overall efficiency of 29%. Completion of works continue to be hampered by 
operatives’ absences, including Covid and the continued extended delivery periods for materials associated with this and the effects of Brexit. Specialist electrical
and lighting equipment suppliers being European based or further, in the main. 
Page 39

Page 40

Appendix 1
Page 27 
Helensburgh and Lomond
Corporate Outcome No.6 – We have infrastructure that supports sustainable growth 
Total number of complaints regarding waste collection – Helensburgh and Lomond
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of waste collection complaints has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 0 No target
FQ3 2021/22 No target 0 No target
FQ4 2021/22 No target 29 No target
FQ1 2022/23 No target 32 No target 
FQ1 Comment
There were 32 waste collection complaints received for the 1st quarter, this could be down to operational and staffing issues over the months of April, May and
June, hopefully this number will reduce in the next quarter. Given the number of collections relating to domestic waste, co mingle collections, glass recycling
collections and food waste recycling collections this is still a good level of service. 
Total number of complaints regarding waste collection – Argyll and Bute
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of waste collection complaints has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 0 No target
FQ3 2021/22 No target 0 No target
FQ4 2021/22 No target 40 No target
FQ1 2022/23 No target 58 No target
Page 40

Page 41

Appendix 1
Page 28 
FQ1 Comment
The number of waste collection complaints has risen again this month and again especially in the Helensburgh/Lomond area. There have been a number of
operational and staffing difficulties over these 3 months, however discussions will take place with the local delivery teams in an attempt to reduce the number of
complaints. 
Page 41

Page 42

Appendix 1
Page 29 
Helensburgh and Lomond
Corporate Outcome No.6 – We have infrastructure that supports sustainable growth 
COI – Percentage of waste recycled, composted and recovered
Responsible person: John Blake 
This indicator is reported quarterly. Performance is presented by Council-wide service provision. 
This indicator for FQ1 is above target and performance has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 45.0% 50.5% Green
FQ3 2021/22 45.0% 50.6% Green
FQ4 2021/22 45.0% 48.3% Green
FQ1 2022/23 45.0% 52.1% Green 
FQ1 Comment
52.1% recycling/composting and recovery (39.3% recycling/composting plus 12.8% recovery). Recycling and composting rate slightly higher than normal mainly
due to high tonnage of green garden waste sent to composting sites during the quarter. 
Shanks – Percentage of waste recycled, composted and recovered
Responsible person: John Blake 
This indicator is reported quarterly. Performance is presented by Council-wide service provision. 
This indicator for FQ1 shows the percentage of waste has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 52.8% No target
FQ3 2021/22 No target 53.1% No target
FQ4 2021/22 No target 49.7% No target
FQ1 2022/23 No target 54.4% No target 
Page 42

Page 43

Appendix 1
Page 30 
FQ1 Comment
54.4% recycling/composting and recovery (37.5% recycling/composting plus 16.9% recovery). Recycling and composting rate slightly higher than normal mainly
due to high tonnage of green garden waste sent to composting sites during the quarter. 
Islands – Percentage of waste recycled, composted and recovered
Responsible person: John Blake 
This indicator is reported quarterly. Performance is presented by Council-wide service provision. 
This indicator for FQ1 shows the percentage of waste has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 37.2% No target
FQ3 2021/22 No target 39.0% No target
FQ4 2021/22 No target 38.4% No target
FQ1 2022/23 No target 33.3% No target 
FQ1 Comment
33.3% recycling/composting and recovery (32.1% recycling/composting plus 1.2% recovery). Recycling and composting rate similar to Q1 in previous year. 
H&L – Percentage of waste recycled, composted and recovered
Responsible person: John Blake 
This indicator is reported quarterly. Performance is presented by Council-wide service provision. 
This indicator for FQ1 shows the percentage of waste has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 51.2% No target
FQ3 2021/22 No target 49.5% No target
FQ4 2021/22 No target 48.9% No target
FQ1 2022/23 No target 53.6% No target 
Page 43

Page 44

Appendix 1
Page 31 
FQ1 Comment
53.6% recycling/composting and recovery (45.8% recycling/composting plus 7.8% recovery). Recycling and composting rate slightly higher than normal mainly due
to high tonnage of green garden waste sent to composting sites during the quarter. 
Page 44

Page 45

Appendix 1
Page 32 
Helensburgh and Lomond
Corporate Outcome No.6 – We have infrastructure that supports sustainable growth 
COI – The number of tonnes of waste sent to landfill
Responsible person: John Blake 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is below target (lowest is best) and performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 5,550 4,800 Green
FQ3 2021/22 5,100 4,550 Green
FQ4 2021/22 5,000 4,252 Green
FQ1 2022/23 5,850 4,546 Green 
FQ1 Comment
Tonnes of biodegradable waste sent to landfill was less than same quarter in previous financial year. Recycling and composting rate slightly higher than normal
mainly due to high tonnage of green garden waste sent to composting sites during the quarter. 
Page 45

Page 46

Appendix 1
Page 33 
Helensburgh and Lomond
Corporate Outcome No.6 – We have infrastructure that supports sustainable growth 
LEAMS (Local Environment Audit and Management System) – Helensburgh and Lomond
(Monthly data combined to show quarterly average)
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is above target and performance has improved significantly since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 73 77 Green
FQ3 2021/22 73 86 Green
FQ4 2021/22 73 56 Red
FQ1 2022/23 73 86 Green 
FQ1 Comment
The standard of street cleanliness within the Helensburgh and Lomond area remains high this quarter, with April 84, May 86 and June 88. 
LEAMS (Local Environment Audit and Management System) – Argyll and Bute
(Monthly data combined to show quarterly average)
Responsible person: Tom Murphy 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 is above target and performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 73 81 Green
FQ3 2021/22 73 78 Green
FQ4 2021/22 73 79 Green
Page 46

Page 47

Appendix 1
Page 34 
Reporting Period Target Actual Status
FQ 2022/23 73 85 Green 
FQ1 Comment
The department continues to deliver a high standard of street cleanliness across the whole area. This is a great achievement. The service uses the annual report
from Keep Scotland Beautiful and monthly inspections to assess the date and make appropriate alterations to work schedules to ensure that the level of
performance is maintained. 
Page 47

Page 48

Appendix 1
Page 35 
Helensburgh and Lomond
Making It Happen 
Teacher sickness absence – Helensburgh and Lomond
Responsible person: Simon Easton 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of sickness absence days has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 0.83 days No target
FQ3 2021/22 No target 1.31 days No target
FQ4 2021/22 No target 1.71 days No target
FQ1 2022/23 No target 1.81 days No target 
FQ1 Comment
Absence levels have increased from the last quarter which bucks the seasonal trend where we usually see a decrease in absence levels from Q4 to Q1 but this is
common in two other areas this year. In comparison the same quarter last year there has been a reduction in absence which is different to all other areas. 
Teacher sickness absence – Argyll and Bute
Responsible person: Simon Easton 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of sickness absence days has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 0.89 days No target
FQ3 2021/22 No target 1.60 days No target
FQ4 2021/22 No target 1.77 days No target
FQ1 2022/23 No target 1.79 days No target 
Page 48

Page 49

Appendix 1
Page 36 
FQ1 Comment
Absence levels have stayed almost the same in comparison to the last quarter which is different to the usual seasonal trend where they normally increase in Q4
and reduce in Q1. Against the same quarter last year there has been a slight increase - an increase was expected due to the reduction in Covid restrictions.
Page 49

Page 50

Appendix 1
Page 37 
Helensburgh and Lomond
Making It Happen 
LGE staff (non-teacher) sickness absence – Helensburgh and Lomond
Responsible person: Carolyn Cairns 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of sickness absence days has decreased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 3.01 days No target
FQ3 2021/22 No target 3.45 days No target
FQ4 2021/22 No target 4.21 days No target
FQ1 2022/23 No target 4.17 days No target 
FQ1 Comment
Absence levels have remained almost the same between last quarter and this quarter which bucks a seasonal trend which usually sees higher levels in Q4 than Q1.
There is a decrease on the same quarter last year which is different to all other areas who have seen an increase. 
LGE staff (non-teacher) sickness absence – Argyll and Bute
Responsible person: Carolyn Cairns 
This indicator is reported quarterly. Performance is presented for both Area and Council-wide levels. 
This indicator for FQ1 shows the number of sickness absence days has increased since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 No target 3.16 days No target
FQ3 2021/22 No target 3.49 days No target
FQ4 2021/22 No target 3.42 days No target
FQ1 2022/23 No target 3.57 days No target 
Page 50

Page 51

Appendix 1
Page 38 
FQ1 Comment
There has been a small increase in the absence against last quarter. Against the same quarter last year again there has been a small increase. This was not
unexpected due to the reduction in Covid restrictions. 
Page 51

Page 52

Appendix 1
Page 39 
Helensburgh and Lomond
Making It Happen 
COI – Increase the percentage of all self-service automated contacts
Responsible person: Robert Miller 
This indicator is a Corporate Outcome Indicator that is reported quarterly. The performance presented is Council-wide only. 
This indicator for FQ1 is above target and performance has improved since the last reporting period. 
Reporting Period Target Actual Status
FQ2 2021/22 70.0% 73.7% Green
FQ3 2021/22 70.0% 72.2% Green
FQ4 2021/22 70.0% 73.1% Green
FQ1 2022/23 70.0% 79.4% Green 
FQ1 Comment 
In FQ1 there were 39,166 transactions dealt with by customer service agents (20.8%) and 150,535 automated or self-service transaction (79.4%) so the 70% target
was well exceeded. There was a significant increase of Governance & Law automated interactions due to the recent council elections: FQ1 2021/22 2022/23
Mediated 37,224 39,166 Automated 99,398 150,535. 
Page 52

Page 53

ARGYLL AND BUTE COUNCIL                                             HELENSBURGH AND                                                                                                       
LOMOND AREA 
COMMITTEE                                                                                                 
ROADS AND INFRASTRUCTURE                 20 SEPTEMBER 2022
SERVICES                     
ROADS AND INFRASTRUCTURE SERVICES UPDATE 
1.0 INTRODUCTION 
1.1 This report format and frequency for these reports were agreed as part of the
previous Council. The purpose of the report is to provide a general update on
key activities of the Service over recent months and to enable a discussion on
key, high level topics and projects. As part of developing future committee
structure and workplans the purpose and effectiveness of this standing item
should be reviewed. 
1.2 As part of the normal course of business we provide all members with regular
weekly briefings on topical projects and ongoing service delivery. We have been
doing this weekly for over 60 editions now and these prove to be a useful tool for
regular service updates. They are all available as part of the wider resource
portal on the Member Zone system which also includes specific topic briefing
sheets and key policy documents. We are also in the process of developing a
seminar programme on specific topics which we are hoping to make as
interactive as possible with various site visits.     
2.0 RECOMMENDATIONS 
2.1 It is recommended that the Area Committee note and consider the contents of this
report and its purpose/value as a standing item on the agenda given that all the
information contained is otherwise accessible.   
3.0 DETAIL 
COVID Absence/Resource Availability 
3.1 For the period of the previous report two reports in March then June absence
rates as a result of self-isolation requirements remained high in the case of the
former report and tapered down more in line with pre-COVID trends in the latter
report. This remains largely the case, and absence levels continue to be in line
with pre-COVID trends, although there do remain a few isolated absences
attributed to COVID, the overwhelming percentage of absences are non-COVID
Page 53 Agenda Item 7

Page 54

related 
3.2 A more pressing issue in terms of resource availability is around recruitment
particularly for manual roles in our Operations team. We are finding that we are
having to go out three or four times for some posts, and even then we continue
to have some long-term unfilled vacancies. At the time of writing this report
there are 18 vacant posts which we are trying to recruit to in our Operations
team. Even in the posts we are successfully recruiting to, we are finding that
we have far fewer applicants than we would have done for similar posts
previously. 
Capital Roads Reconstruction Programme 
3.3 The focus of the roads reconstruction programme is to recover the network
through the delivery of a mix of carriageway resurfacing schemes,
patching/surface dressing and in-situ road surface recycling, which follow the
principles set out within the Roads Asset Management Plan. 
3.4 The Council capital allocation for the HL area is £999.340, and the scheme list is
available on the Council website here. As well as the programme itself, the online
resources include financial values and short explanations of engineering
methods/solutions.   
3.5  Overall progress with the programme has been excellent and works remain on
schedule. As well as the full programme [link above] which is updated monthly,
we provide weekly updates on schemes via our weekly briefing. At the time of
writing this report 14 of the 20 individual schemes in Helensburgh and Lomond
have been completed. 
Winter Maintenance  
3.6 The annual winter policy update has been reported to and agreed at the recent
EDI meeting.  The policy is largely unchanged from previous years and forms the
basis of the delivery of our winter maintenance activities over winter 22/23.   
3.7 A key aspect of the winter service is the provision of public information on what
we do and why we do it. There is a range of online resources available on the
Council website here. 
Play park funding 
3.8 Funding of £76,000 was allocated in financial year 21/22, with a further £79,000
this financial year. In order to provide for a meaningful programme of improvement
works targeted at the high priority sites, as well as a works package with is
attractive to what it is a limited supplier/contractor market, the funds have been
rolled together into a single package. Sites were given a priority rating based on
asset inspections and feedback form the Youth Forum, in compliance with the
Scottish Government’s grant requirements. The full list of prioritised sites was
Page 54

Page 55

reported to EDI in June and is available here. In this area the priority sites are
Bendarroch and Arrochar.   
3.9 An update on this was recently provided in the weekly briefing [Edition 61 5th
August] which read: The recent tender process failed to generate any bids. We
requested feedback as to why there were no applications and we were advised
that the timescales for completion of work were too short. A request for more time
to complete was made and this is currently being assessed by our procurement
team. A further re-tender process will be looked at this month. 
3.10 A report will go to EDI in December on the fund, future year funding and
consultation plans. 
Luss Traffic Order 
3.11 We provided a short update on this in our weekly briefing Edition 64 [26 August]
which read: The public hearing for the Proposed Order was held on Tuesday 23rd
August, at the Loch Lomond Arms Hotel, Luss. The Reporter gave an overview
of the proposed Traffic Regulation Order and summarised the overall objections
submitted before moving on to allow both the attending objectors to speak to their
specific objections.  The Reporter allowed questions and statements to be heard
from the attendees and although there was not a great number, the points made
were relevant to the proceedings.  At the close of the hearing, the Reporter has
allowed the Council a two week period to provide supporting information. The
Reporter also proposes to allow a further two week period for the objectors to
submit comment on the Councils supporting information and draft modifications.  
The Reporter will then complete his report, with any recommendations, and
submit to the Council in due course.  Upon review, Officers will submit the report
to the Helensburgh and Lomond Area Committee for considerationAll the
documentation on the proposed Order, along with information on all Traffic
Orders, is available on the Council website here. 
Faslane Cemetery Project 
3.12 A short update on this project was provided in the previous area committee report
in June, and in our weekly briefing Edition 62 [12th August] we provided the
following update: We have been working with the local community council and the
MoD to progress a scheme to upgrade Faslane Cemetery. The MoD provided
labour to clear out some overgrown shrubbery and tidy up the cemetery grounds.
The community council fundraised and had a local blacksmith create brand new
gates to our specification. They also cleaned the stonework around the
entranceway. We widened the vehicular access into the cemetery and upgraded
the car park. Overall the project has seen a welcome improvement to the
cemetery with contributions from all involved. We will shortly be arranging a small
event to mark the project and more information on this will follow. 
Page 55

Page 56

3.13 At the time of writing the above event has not yet been arranged but it is expected
it will have been by the time of the committee meeting and a verbal update can
be provided at the meeting. 
4.0 CONCLUSION 
4.1 This report provides a general update to local members on recent Roads and
Infrastructure activities. 
5.0 IMPLICATIONS 
5.1 Policy – various policies referred to within the body of the report 
5.2 Financial – none 
5.3  Legal – the Council has various statutory obligations which are the
responsibility of RIS and set out in various Acts, such as the Roads Scotland
Act 1984. The services provided are in line with our statutory obligations 
5.4  HR – none known 
5.5  Fairer Scotland Duty: 
5.5.1   Equalities - protected characteristics – none known 
5.5.2   Socio-economic Duty – none known 
5.5.3 Islands – none known 
5.6. Climate Change – none 
5.7  Risk – none known 
5.8  Customer Service - none 
Page 56

Page 57

Executive Director with responsibility for Roads and Infrastructure Services
Kirsty Flanagan 
Policy Lead for Roads and Transport
Councillor Andrew Kain 
August 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services; or Mark Calder, Project
Manager 
Page 57

Page 58

This page is intentionally left blank

Page 59

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND
LOMOND AREA
COMMITTEE 
ROADS AND INFRASTRUCTURE
SERVICES 
20 SEPTEMBER 2022 
RECYCLING AND RECOVERY PERFORMANCE 
1.0 EXECUTIVE SUMMARY 
1.1 Argyll and Bute Council is both a waste collection and waste disposal authority. 
1.2 Waste disposal is dealt with by 3 separate models across the council as follows: 
 Island sites e.g. on Mull and Islay where landfill sites are operated directly
by the council;
 Helensburgh and Lomond area where waste is disposed of at sites outside
of Argyll and Bute;
 A 25 year (2001 – 2026) Waste PPP contract which covers the rest of Argyll
and Bute. 
1.3 Waste figures for all four administrative areas have been summarised within
this report. Due to the way the reporting is carried out it is not possible to
accurately break down the information on an area by area basis for all data. 
1.4 National policy decisions, guidance and regulations e.g. relating to the
Biodegradable Municipal Waste landfill ban will have a significant impact on future
recycling, composting and recovery performance. 
1.5 It is recommended that Members note and give consideration to the details as
outlined in this report and the national policy drivers that will likely impact over the
coming years.
Page 59 Agenda Item 8

Page 60

ARGYLL AND BUTE COUNCIL  BUTE AND COWAL
AREA COMMITTEE 
ROADS AND INFRASTRUCTURE
SERVICES 
SEPTEMBER 2022 
RECYCLING AND RECOVERY PERFORMANCE 
2.0 INTRODUCTION 
2.1 Argyll and Bute Council is both a waste collection and waste disposal authority.
Recycling, composting and recovery (i.e. other landfill diversion) statistics are
reported quarterly within the council’s performance system Pyramid. Statutory
returns to SEPA e.g. licensed site tonnage, landfill tax and waste data flow vary
from quarterly to annual. 
2.2 This report provides details on the council’s recycling and landfill diversion
performance along with national policy, targets and regulations which are likely to
impact on future performance. 
3.0 RECOMMENDATIONS 
3.1 It is recommended that Members note and give consideration to the details as
outlined in this report and the national policy drivers that will likely impact over the
coming years. 
4.0 DETAILS 
4.1 The council’s waste strategy was approved by the Environment, Development
and Infrastructure Committee in September 2019. Whilst this strategy will emerge
in line with government guidance, regulation legislation, and contractual
requirements the Strategy is predicated on the model shown in Figure 1 below.
Page 60

Page 61

4.2 Argyll and Bute Council operate a performance management system
‘Pyramid’. Quarterly recycling/composting, recovery and landfill
percentages are included – split between the Islands landfill sites, Waste
Management PPP and Helensburgh/Lomond areas. These details
include: 
 percentage of waste recycled and composted;
 percentage of waste recovered e.g. other landfill diversion;
 combined percentage of waste recycled, composted and recovered;
 percentage of waste to landfill;
 tonnes of biodegradable municipal waste to landfill. 
Percentages Summary of Landfill, Recycling, Composting and
Recovery 2019, 2020 and 2021 
2019 2020 2021 
Argyll & Bute
wide
% of waste recycled, composted and
recovered
48.4% 43.7% 49.3%
% waste recycled and composted 35.4% 27.8% 36.2%
% waste recovered 13.0% 15.9% 13.0%
% waste landfilled 51.6% 56.3% 50.7%
Tonnes of municipal waste to
landfill
29,48
8
29,26
1
29,87
5
Waste PPP % of waste recycled, composted
and recovered 
46.6% 45.1% 50.6%
Page 61

Page 62

% waste recycled and composted 28.5% 23.6% 33.0% 
% waste recovered 18.1% 21.5% 17.6% 
% waste landfilled 53.4% 54.9% 49.4%     
Helensburgh &
Lomond
% of waste recycled, composted and
recovered
53.0% 43.9% 50.8% 
% waste recycled and composted 45.3% 34.6% 42.7% 
% waste recovered 7.8% 9.3% 8.1% 
% waste landfilled 47.0% 56.1% 49.2%     
Islands
% of waste recycled, composted and
recovered
44.4% 33.8% 36.3% 
% waste recycled and composted 44.4% 31.7% 34.8% 
% waste recovered 0.0% 2.1% 1.5% 
% waste landfilled 55.6% 66.2% 63.7%     
4.3 Some points to note are as follows: 
 There was a drop in recycling performance in 2020 due to Council
kerbside recycling services being suspended and recycling/civic
amenity sites were closed during the early months of the first COVID
lockdown. In 2021, all recycling services returned to normal
throughout the year which is reflected in the increase in recycling
rates compared to 2020. 
 During these first 3 months of the pandemic in 2020, Recycling/civic
amenity sites, which were required to close Scotland wide. The site
were re-opened in early June 2020. There were no closures in 2021
which contributed to an increase in recycling compared to 2020. 
 The combined recycled, composted and recovery rate has
increased from 43.7% in 2020 to 49.3% in 2021. This is mainly due to
the reasons described above. 
 The combined recycling, composting and recovery rate in 2019 was
48.4%. The 2021 combined rate of 49.3% would indicate that our
Page 62

Page 63

overall recycling and landfill diversion rates in 2021 returned to pre-
covid levels. There are some disposal area differences when
comparing 2019 and 2021, e.g. most of the glass collected in the
Helensburgh/Lomond and the PPP areas is serviced by a dedicated
glass collection vehicle and staffing based in Helensburgh.
Depending on collection volumes and routes, the vehicle will
sometimes discharge the glass at PPP sites and on other occasions
at the Helensburgh site which varies the location where the glass is
registered as being recycled. In 2021, there was significantly more
glass discharged for recycling at the PPP sites (and subsequently
less at the Helensburgh site) compared to 2019 levels.  In the
Islands disposal area, there was a drop in recycling from 2021
compared to 2019, this is mainly due to a large reduction in wood
delivered for recycling at our Mull and Islay facilities. 
 The recovery in the Waste PPP area is carried out by Renewi
through residual waste mechanical biological treatment plants
based at their waste facilities near Oban, Dunoon and
Lochgilphead. 
 The recovery in the Helensburgh and Lomond area is mainly carried
out by Barr Environmental at their Auchencarroch waste facility, near
Alexandria. 
 There was an increase of circa 13% in overall municipal solid waste
tonnages in 2021 compared to 2020. Tonnages in 2020 were much
lower than normal mainly due to the sharp reduction in visitors and
the closure of many commercial premises during the first lockdown
in 2020.However, it is noteworthy that the 2021 tonnages were still
higher by circa 3% compared to 2019.The overall tonnage increase
in 2021 is likely due to the high number of staycation visitors during
the year plus some new housing developments have come on
stream e.g. Dunbeg (Oban). 
 The overall percentage waste to landfill in 2021 (50.7%) was lower
than 2020 (56.3%) again mainly due to the suspension of most
recycling services for circa 3 months during the first lockdown in
2020. 
 The tonnage of municipal waste to landfill in 2021 (i.e. 29,875
tonnes) was slightly more than in 2020 (i.e. 29,261 tonnes).This
was mainly due to the overall tonnage drop in 2020 plus the 2021
tonnage increase as previously described. 
 Recycling and composting is mainly from recycling collections, bring
sites and segregated wastes from recycling/civic amenity sites.
Recovery is predominantly moisture and process loss/use and/or
compost like output from mixed waste treatment plants operated by
the council’s Waste PPP partner and other waste contractors. 
 SEPA published annual recycling data for local authorities focuses
mainly on recycling and composting from households.
Page 63

Page 64

Landfill Ban 
4.4 The Waste (Scotland) Regulations were introduced by the Scottish
Government in 2012 and they included a landfill ban of biodegradable
waste from 2021. 
4.5 The landfill ban planned for 2021 has since been rescheduled by the
Scottish Government until 2025. This delay was welcomed by the Council
and gives more time for alternative solutions and funding to be sought. An
update report on the Waste PPP/Landfill Ban can be found at the
September 2022 Environment, Development and Infrastructure
Committee. 
Deposit Return Scheme 
4.6 The Scottish Government in 2019 set out a planned implementation date
of April 2021 for a national deposit return scheme (DRS) for drinks
containers including PET plastic drinks bottles, drinks cans and glass
bottles. During the COVID-19 outbreak the implementation date was
delayed by the Scottish Government until July 2022 and then
subsequently until August 2023.Circularity Scotland have since been
appointed by The Scottish Government to administer and operate the
scheme throughout Scotland. 
4.7 The DRS scheme may result in an overall Scotland wide increase in
recycling including other environmental benefits e.g. current non-
recyclers may use the scheme plus there should be less littering of such
items. The scheme may however, see a reduction in Council recycling
performance if items such as glass drinks bottles are no longer handled
by Council glass collections albeit they should still be recycled in future
via the DRS scheme. The DRS scheme aims to capture 70% of such
items during the first year of implementation then rising to 90% in future
years. Much will depend on how the scheme is implemented by the
Scottish Government and Scheme Administrator in the coming years and
public participation in the scheme. 
Scottish Government Circular Economy Proposals 
4.8 During the summer of 2022, The Scottish Government published its
Circular Economy proposals which included 31 existing and proposed
new measures up to and beyond 2025.These included existing measures
such as the 2025 landfill ban and the DRS scheme as previously
mentioned. There were also a number of new proposals which will likely
impact on future recycling and recovery rates. Further details on these
Scottish Government proposals will be reported at future ED&I
Committees as they progress. Some of the main proposals are as follows: 
 The Incineration Review recommendations will be actioned by the
Scottish Government;
 The rural food waste exemption will be reviewed by the end of
2022;
Page 64

Page 65

 Garden waste collections may become mandatory in 2023;
 Textiles collections may be made mandatory in 2025;
 Hazardous household waste collections may be made mandatory in
2025;
 The Household Recycling Charter may be made mandatory in
future;
 Statutory Recycling Targets may be placed on individual Councils in
future. 
5.0 CONCLUSION 
5.1 Steady progress was made on recycling and composting performance
during 2021 after being affected during the early months of the pandemic
in 2020. Since council kerbside services returned and recycling/civic
amenity sites re-opened in June 2020, more normal recycling levels have
returned throughout 2021. National Policy drivers such as the ban on
biodegradable waste to landfill, the Scottish Deposit Return Scheme and
the circular economy proposals will have significant implications for future
recycling, composting and recovery performance. 
6.0 IMPLICATIONS 
6.1  Policy - National policies and regulations will likely impact on future
recycling, composting and recovery performance. The council’s policy is
to reduce landfill. 
6.2  Financial -  The 2025 ban on biodegradable waste to landfill will have
financial implications. An update report can be found in the September
2022 Environment, Development and Infrastructure Committee. 
6.3  The landfill ban (delayed until 31st December 2025) is a legal requirement
under the Waste (Scotland) Regulations 2012. Other legal requirements
may result following The Scottish Government Circular Economy
proposals. 
6.4  HR – None.   
6.5  Equalities – None.   
6.6  Risk - Risks to the council on the landfill ban and any other future
statutory requirements are mainly financial. A national deposit scheme
for drinks containers will hopefully have an overall environmental benefit,
although it may impact negatively on council recycling rates. 
6.7  Customer – None at present.   
Executive Director with Responsibility for Roads and Infrastructure
Services: Kirsty Flanagan 
Page 65

Page 66

Head of Roads and Infrastructure Services: Jim Smith 
Policy Lead for Climate Change and Environment Services: Councillor
Ross Moreland 
For further information contact: John Blake – Fleet, Waste & Transport
Manager 
Page 66

Page 67

Page 1 of 8
1. EXECUTIVE SUMMARY
1.1. The purpose of the report is to provide the Helensburgh & Lomond Area
Committee with a project position update as 9 months has elapsed since the last
update was presented in December 2021 and to confirm that we have now
issued the Certificate of Practical Completion for Phase 1 of Helensburgh
Waterfront Development and the new Helensburgh Leisure Centre was handed
over by Heron Bros Friday 29th July 2022 and fully opened to the public on 3
September 2022.
1.2. The Project Management Team would like to take this opportunity to thank
everyone involved for all their hard work in helping us to achieve this significant
milestone. It has been a long and difficult journey, with the back drop of a global
pandemic as well as many other issues to overcome. Everyone has played their
part and gone above and beyond in many cases to ensure this project was
delivered to the highest of standards and to original timescales. The progress
achieved in the face of considerable challenge is a testament to the power of
partnership and professionalism It is all the more impressive given all the back
office staff behind the Waterfront Development are working remotely to deliver
the project.
1.3. Since Contract Award, the Helensburgh Waterfront Development was awarded
£100,000 grant funding from SportScotland, January 2021, which has been
used by the project to support existing plans including adding the movable floor
to the studio pool which will be ideal for beginner swimming lessons and
providing more inclusive access.
1.4. Heron Bros Ltd commenced works on site on the 31 August 2020 and we are
currently 107 weeks into the 119 week construction programme. 
1.5. Whilst the project has made significant progress to date, given that it’s being
delivered in the midst of a global pandemic, the Project Management Team
recognise that issues of a commercial nature will likely emerge given the size
and scale of this complex major capital project.
1.6. RECOMMENDATIONS
The Helensburgh & Lomond Area Committee is invited to:
1.7. Note and consider the contents of this Report
ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area
Committee
Commercial Services 20 September 2022
Helensburgh Waterfront Development (HWD) – Project Position Update
Page 67 Agenda Item 9

Page 68

Page 2 of 8
2. INTRODUCTION
2.1. The Helensburgh Waterfront Development Project is all about creating a vibrant
and attractive waterfront for the town. The main feature of the project will be a
new leisure facility incorporating a swimming pool, with associated parking and
public realm works to meet the needs of the local community.  At the same time
the flood defences will be increased to address current and future flooding issues
on the site.  The new leisure facility will be run on behalf of the Council by
LiveArgyll.
2.2. The principal aims and objectives for the project are to:
• Develop Helensburgh as a great place to live, work and visit, by delivering
a new state-of-the-art leisure facility and swimming pool which meets the
needs of the Helensburgh and Lomond community
• Add to what has been achieved through other projects such as CHORD
and Hermitage Park regeneration, which have created an attractive,
vibrant and contemporary town Centre that is attracting residents,
businesses and visitors to the area.
• Encourage additional private sector investment in the waterfront area and
town centre
• Through the steps above, support the Helensburgh and Lomond economy
with increased opportunities for existing and new businesses
2.3. The purpose of the report is to provide the Helensburgh & Lomond Area
Committee with a project position update as 9 months has elapsed since the last
update was presented in December 2021 and to confirm that we have now
issued the Certificate of Practical Completion for Phase 1 of Helensburgh
Waterfront Development and the new Helensburgh Leisure Centre was handed
over by Heron Bros Friday 29th July 2022 and fully opened by LiveArgyll to the
public on 3 September 2022.
2.4. We would like to take this opportunity to thank everyone involved for all their
hard work in helping us to achieve this significant milestone. It has been a long
and difficult journey, with the back drop of a global pandemic as well as many
other issues to overcome. Everyone has played their part and gone above and
beyond in many cases to ensure this project was delivered to the highest of
standards and to original timescales. The progress achieved in the face of
considerable challenge is a testament to the power of partnership and
professionalism It is all the more impressive given all the back office staff
behind the Waterfront Development are working remotely to deliver the
project.
ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area
Committee
Commercial Services 20 September 2022
Helensburgh Waterfront Development (HWD) – Project Position Update
Page 68

Page 69

Page 3 of 8
2.5. Since Contract Award, the Helensburgh Waterfront Development was awarded
£100,000 grant funding from SportScotland, January 2021, which has been
used by the project to support existing plans including adding the movable floor
to the studio pool which will be ideal for beginner swimming lessons and
providing more inclusive access.
Budget
2.6. The current budget of £22,367,314, includes £5million awarded from the UK
Government Libor Fund, as well as forecast funds arising from the future retail
development.
2.7. In January 2021 the Helensburgh Waterfront Development was awarded
£100,000 grant funding from SportScotland. This additional grant funding will be
used to support existing plans; including adding the movable floor to the studio
pool, Pool Pods and Changing Places toilet facilities/
Programme
2.8. HBL commenced works on site on the 31 August 2020 and we are currently 107
weeks into the 119 week programme.
2.9. Table 2.7 Project Programme and Milestone
Description Duration Start Date End Date
Construction: Stage 1 - Flood Defences
and Stage 2 - Leisure Building 500 days 31-Aug-20 29-Jul-22
Construction: Staff Migration to New
Leisure Building and Familiarisation 21 days 8 – Aug -22 3 -Sept-22
Construction: Stage 3 - Demolition of
Existing Pool and Completion of Car
Parking and Landscaping
136 days 12-Aug-22 06-Feb-23
Construction: Defects Rectification
Period 260 days 07-Feb-23 07-Feb-24
Construction: Contract Close Out 20 days 07- Feb-24 07 -Mar-24
2.10. Currently onsite the following Phase 2 activities (Construction Stage 3 –
Demolition of Existing Pool and Completion of Car Parking and Landscaping)
are progressing at a pace: Demolition of Existing Old Swimming Pool Building
commenced on the 5th September, and is due to conclude in the coming
weeks; mass stone fill to former car park; granite paving to emerging public
realm steps; public realm granite paving and surfacing works; construction of
remaining section of car park, and to new cycle lane adjacent to West Clyde
Street.
2.11. Whilst the project has made significant progress to date during the past 107
weeks, it’s being delivered in the midst of a global pandemic, currently it
remains on programme and within budget. However the Project Management
Page 69

Page 70

Page 4 of 8 
Team recognise that issues of a commercial nature will likely emerge given
the size and scale of this complex major capital project, and we continue to
work closely with all parties to mitigate and minimise the potential impact of
these upon the delivery of the works.
Helensburgh Masonry Pier Resurfacing and Lighting Improvement Works 
2.12. Helensburgh Masonry Pier will receive a £345,000 makeover to help improve
the appearance and add to the overall improvements works at the waterfront.
The works, funded by Crown Estates and the Scottish Government’s Place
Based Investment Programme include resurfacing the masonry section of the
pier and replacing lighting. Works commenced onsite on 11 July, 2022 with the
pier closed to the public for the duration of the works.  Pedestrian access to the
Public Toilets will maintained during these works. 
2.13. Heron Bros Ltd are delivering the works in keeping with landscaping already
carried out as part of the waterfront development. Once complete the surface
will match the quality and finishes of the waterfront development project, and
enhance views looking out from the swimming pool and gym. The works are
taking place during the summer, as relatively dry weather is required for the type
of materials used for resurfacing. As funding is only available for a set time, there
is a small window of opportunity to complete the improvements. 
2.14. Completion of the pier resurfacing will coincide with the opening of the new
leisure centre and swimming pool as part of the wider waterfront development.
Considerate Constructor Scheme (CCS)
2.15. Well done to the Heron Bros Site Team for once again achieving a rating of
‘Excellent’ (42 out of 45) in a recent audit conducted by the Considerate
Constructors Scheme (CCS), a not-for-profit, independent organisation founded
to raise standards in the construction industry. Construction sites, companies
and suppliers voluntarily register with the scheme and agree to abide by the code
of considerate practice, designed to encourage best practice beyond statutory
requirements. https://www.ccscheme.org.uk/ 
3. Risk
3.1. The Anticipated Final Cost for the Project includes a construction contingency
allowance, as well as a fully itemised and costed Risk Register, which is being
managed by the Project Team. The Project Risk Register has been updated to
include the potential risk of long term working under some form of COVID-19
restrictions having an impact upon site productivity.
3.2. The value of the Construction Contract, at Award Stage was £19,971,918.51.
Given the health and economic impacts since the award, the Anticipated Final
Cost for the Contract and therefore the project is likely to increase. We are
working with Heron Bros Ltd to ensure that any claims for Extensions of Time,
and/or Loss and Expense, are properly and fully substantiated and assessed in
accordance with the requirements of the Contract. This work stream is on-
Page 70

Page 71

Page 5 of 8
going and its’ outcome will be reported to the relevant committees of the
Council in due course.
4. CONCLUSION
4.1. The Helensburgh Waterfront Development project is a complex, multi-             
disciplinary project that includes a number of: design and construction
interfaces; statutory approvals; construction logistics; and utility diversion and
upgrading requirements
4.2. It has been a long and difficult journey, with the back drop of a global pandemic
as well as many other issues to overcome. The progress achieved in the face
of considerable challenge is a testament to the power of partnership and
professionalism It is all the more impressive given all the back office staff
behind the Waterfront Development are working remotely to deliver the
project.
5. IMPLICATIONS
5.1 Policy The delivery of this project fits with, as appropriate,
the Council’s Corporate Plan, Single Outcome
Agreement, Economic Development Action Plan
and approved Local Development Plan key actions
and policy for safeguarding our built heritage and
town Centre regeneration.
5.2 Financial The current budget of £22,367,314, includes
£5million awarded from the UK Government Libor
Fund, as well as forecast funds arising from the
future retail development. The £100,000 grant
funding from SportScotland will be used by the
project to support existing plans including adding
the movable floor to the studio pool which will be
ideal for beginner swimming lessons and providing
more inclusive access.
5.3 Legal Legal Services will provide support as and when
required.
5.4 HR The HWD Project Manager continues to project
manage the project on a day to day basis, supported
by colleagues from other departments of the
Council.
5.5 Fairer Scotland Duty: Access to the facilities, once constructed, will be
covered by either the A&BC Car Parking
Management Strategy and/or the Live Argyll
Operational Business Model for the new Leisure
Building.  The relevant officers in each organisation
will be responsible for undertaking the necessary
Page 71

Page 72

Page 6 of 8
EqSEIA for these.
5.6      Equalities – protected    
characteristics
The detailed proposals for the HWD Project have
been designed in accordance with the requirements
of the Equalities Act (2010) legislation at the
forefront, including, as far as practical, the removal
of physical barriers preventing access to facilities or
services.
5.7 Socio-economic Duty Access to the facilities, once constructed, will be
covered by either the A&BC Car Parking
Management Strategy and/or the Live Argyll
Operational Business Model for the new Leisure
Building.  The relevant officers in each organisation
will be responsible for undertaking the necessary
EqSEIA for these.
5.8 Islands
5.9      Climate Change
Not Applicable
Flood defence works designed and constructed to
take account UK Climate Change Predictions, latest
being UKCP18, and are also  designed and
constructed in such a way that they can be extended
should UK Climate Change Predictions of the future
make this necessary. The new Leisure Building in
terms of reducing carbon emissions, has an energy
efficient Gas fired Combined Heat and Power (CHP)
system installed, which can return excess electrical
power generation to the National Grid. 
5.10. Risk The Anticipated Final Cost for the Project includes a
construction contingency allowance, as well as a
fully itemised and costed Risk Register, which is
being managed by the Project Team. The Project
Risk Register has been updated to include the
potential risk of working under some form of COVID-
19 restrictions is likely to have an impact upon site
productivity.
5.11  Customer Service Legal Services will provide support as and when
required.
Douglas Hendry, Executive Director with responsibility for Commercial Services
Cllr Gary Mulvaney, Policy Lead for Finance and Commercial Services
31 August 2022
For further information contact: Andrew Collins, Helensburgh Waterfront
Development Project Manager Tel: 01436 657633  
Page 72

Page 73

Page 7 of 8
Appendix A
Helensburgh Waterfront Development - Progress Photographs
Page 73

Page 74

This page is intentionally left blank

Page 75

Appendix A 
Helensburgh Waterfront Development - Progress Photographs 
Page 75

Page 76

Page 76

Page 77

Page 77

Page 78

Page 78

Page 79

Page 79

Page 80

Page 80

Page 81

Page 81

Page 82

Page 82

Page 83

Page 83

Page 84

This page is intentionally left blank

Page 85

ARGYLL & BUTE COUNCIL  HELENSBURGH AND LOMOND
AREA COMMITTEE 
LEGAL AND REGULATORY SUPPORT  20 SEPTEMBER 2022 
EXTRACT OF MINUTE OF AUDIT AND SCRUTINY COMMITTEE HELD ON 23 JUNE
2022 
12. COMMUNITY ASSET TRANSFER SCRUTINY REVIEW 
The Committee gave consideration to a report presenting the findings of the
Community Asset Transfer Scrutiny Review, which was carried out as per the 2021/22
scrutiny plan.   The report identified ‘a perception that the Council’s current asset
transfer process is complex and does not fully support community empowerment to
allow community groups to progress transfer request without significant support’.   
Discussion was had in relation to the opportunity this afforded to expose the
opportunities of Community Asset Transfer to a wider audience, with it being noted
that delegated authority for Asset Transfers lies with the Policy and Resources
Committee.   
Decision 
The Audit and Scrutiny Committee:- 
1. Agreed the draft Community Asset Transfer Scrutiny Report; and 
2. Agreed that the Community Asset Transfer Scrutiny Report be presented to the
Council’s 4 Area Committees in the first instance, for information and to
facilitate promotion to community groups to consider, noting that any
recommendations arising would require to be referred to the Policy and
Resources Committee for consideration.   
(Reference:  Report by Chair of the Community Asset Transfer Scrutiny Panel, dated
23 June 2022, submitted)   
Page 85 Agenda Item 10

Page 86

This page is intentionally left blank

Page 87

ARGYLL AND BUTE COUNCIL AUDIT AND SCRUTINY COMMITTEE
FINANCIAL SERVICES 23 JUNE 2022
COMMUNITY ASSET TRANSFER SCRUTINY REVIEW
1. SUMMARY
1.1 The Community Asset Transfer scrutiny review was carried out as per the
2021/22 scrutiny plan agreed by the Audit and Scrutiny Committee at their
development session on the 27 April 2021.
1.2 The Community Asset Transfer scrutiny panel comprised of Mr Martin
Caldwell (Chair), Councillor Trail and Councillor McGrigor with support
provided by internal audit officers.
1.3 The Community Asset Transfer process was chosen for inclusion in our
scrutiny priorities for 2021/22 as a result of findings from the Council’s Best
Value Assurance Review conducted by Audit Scotland in May 2020.  The
report identified ‘a perception that the Council’s current asset transfer process
is complex and does not fully support community empowerment to allow
community groups to progress transfer request without significant support’.
2. RECOMMENDATIONS
2.1 Committee to agree the Draft Community Asset Transfer Scrutiny Report.
2.2 Committee to agree the most appropriate committee or other Council group for
the Community Asset Transfer scrutiny report to be presented to for
consideration.
3. DETAIL
3.1 The agreed objectives of the scrutiny review were to:
• ensure the council’s guidance is consistent with legislation and national
guidance
• ensure the Council’s process is supportive to community transfer bodies
• ensure there is adequate engagement with community groups to assess
feedback
• ensure that the action plan from Audit Scotland’s Best Value Assurance
Report is being progressed.
3.2 Throughout this review two panel meetings were held to gather evidence.
Page 87

Page 88

• Panel one – Council’s Social Enterprise Development Officer and the
Estates and Property Development Manager 
• Panel two – representative from Audit Scotland comprising of the Audit
Director and two Senior Audit Managers 
3.3 We would like to extend our appreciation for the cooperation and assistance
received from all witnesses invited to provide evidence over the course of the
review. 
3.4 Based on the information obtained over the course of the review the panel has
identified eight findings specific to this review. These are detailed in the report
attached as appendix 1. 
3.5 The report has been discussed with the officers and panel members involved in
the review to confirm accuracy and it is now for the Committee to decide
whether to approve the report and, if so, to agree the most appropriate
committee or other Council group for the Community Asset Transfer scrutiny
report to be presented to for consideration. 
4.  CONCLUSION 
4.1 Committee is requested to agree the attached report and agree the most
appropriate Committee or other Council group for the report to be presented to
for consideration. 
5. IMPLICATIONS 
5.1 Policy - None
5.2 Financial -None
5.3 Legal -None
5.4 HR - None
5.5 Fairer Scotland Duty - None
5.5.1 Equalities – None
5.5.2 Socio-Economic Duty – None
5.5.3 Islands Duty – None
5.6      Climate Change – None 
5.7 Risk – None
5.8 Customer Service - None 
Martin Caldwell
Chair of the Community Asset Transfer Scrutiny Panel
23 June 2022  
For further information please contact: 
Moira Weatherstone, Interim Chief Internal Auditor, 01546 604146 
Appendices:
Appendix 1 – Draft Community Asset Transfer Scrutiny Report 
Page 88

Page 89

Argyll and Bute Council
Scrutiny Report
March 2022
DRAFT 
Community Asset Transfer
Page 89

Page 90

2 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
Contents 
1. Executive Summary .............................................................................................................. 3
Introduction................................................................................................................................. 3
Objectives.................................................................................................................................... 3
Background.................................................................................................................................. 3
Scrutiny Initiation Briefing – 13 August 2021 ................................................................................. 4
2. Scrutiny Meetings ................................................................................................................. 5
Scrutiny Meeting One – Council Officers – 05 October 2021 .......................................................... 5
Scrutiny Meeting Two – Audit Scotland – 18 November 2021 ........................................................ 9
3. Overall Conclusion and Findings .......................................................................................... 11 
Contact Details 
Chair: Martin Caldwell (Chair of Audit and Scrutiny Committee)
Interim Chief Internal Auditor: Moira Weatherstone (moira.weatherstone@argyll-bute.gov.uk)
www.argyll-bute.gov.uk
Page 90

Page 91

3 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
1. Executive Summary
Introduction
1. As part of Argyll and Bute Council’s (the Council) 2021/22 scrutiny plan, approved by the Audit &
Scrutiny Committee (the Committee) in June 2021, we have undertaken a scrutiny review of the
Council’s Community Asset Transfer process. 
2. Throughout this report references to ‘the Panel’ refers to the chair of the Committee and two
Committee members who conducted this review. They were:
 Martin Caldwell (Panel Chair)
 Councillor Trail 
 Councillor McGrigor 
3. The Panel was supported by council officers and relevant external parties who gave willingly of
their time to help deliver the review. We would like to extend our appreciation for the
cooperation and assistance received from all witnesses invited to provide evidence over the
course of the review.
Objectives
4. The agreed objectives of the scrutiny review were to:
 ensure the Council’s guidance is consistent with legislation and national guidance
 ensure the Council’s process is supportive to community transfer bodies
 ensure there is adequate engagement with community groups to assess feedback
 ensure that the action plan from Audit Scotland’s Best Value Assurance Report is being
progressed.
Background
5. The Council’s Best Value (BV) report issued by the Accounts Commission in May 2020 stated that
community focus groups highlighted that:
There is ‘a perception that the Council’s current asset transfer process is complex and does not
fully support community empowerment to allow community groups to progress transfer
requests without significant support.’
and recommended that:
‘The council should work with communities and community groups to understand and address
their concerns in respect of the current asset transfer arrangements.’
In response to the BV report the Council have implemented a BV Action Plan with one of the
actions being to ‘Review and simplify the community asset transfer process’.
6. Part 5 of the Community Empowerment (Scotland) Act 2015 (The Act), sets out the key rights
and duties for community transfer bodies and relevant authorities and provides a framework for
the asset transfer process.
7. Historically, asset transfer was only available for land or buildings which a public authority has
decided to dispose of, and has decided is suitable for community use.  The Act puts more power
Page 91

Page 92

4 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
in the hands of communities by allowing them to request whatever publicly held property they
believe will be most suitable to deliver their objectives.  Therefore community transfer bodies
who meet the qualifying criterial can make applications to relevant authorities to acquire land
and property which is not listed for sale.
8. The Act requires each relevant authority to establish, maintain and make available a register of
land which it owns or leases to the best of its knowledge and belief.  This register is available to
view within an area of the Council’s website dedicated to community asset transfers along with
links to other relevant guidance and tools.
9. The Council has developed an “expression of interest” process which seeks to resolve
community requests as simply as possible out with the statutory Asset Transfer process and runs
parallel with the Asset Transfer process.   This process assists community transfer bodies wishing
to investigate the possibility of developing a full asset transfer request or other alternative
means of managing community assets.  A transfer request can be for ownership, lease or other
rights.
10. As at 30 June 2021, the Council reported to Scottish Government that it had received 70
expressions of interest since January 2017.  Of these:
 14 are active
 53 have been resolved or withdrawn
 3 developed into asset transfer requests, one of which was successful and two refused. 
11. The Council’s Social Enterprise Development Officer is the single point of contact to provide
assistance to community transfer bodies.  There is an internal process guide to ensure consistent
evaluation of expressions of interest and asset transfer requests received.
12. The Council’s Asset Transfer Group consists of representatives across various council services. 
The group meets monthly to review progress with expressions of interest and asset transfer
requests, review the Best Value Assurance Report action plan and the published asset register
and consider any other relevant business.
13. The Community Asset Transfer process was approved for inclusion in our scrutiny plan for
2021/22 at the meeting of the Council’s Audit and Scrutiny Committee on 15 June 2021.  
Scrutiny Initiation Briefing – 13 August 2021
14. In August 2021 scrutiny officers circulated a briefing paper to the Panel which provided
background on the community asset transfer process.  The Panel met to agree the scope and
identify invitees to give evidence at a series of meetings.   
15. The agreed scope was to consider whether the community asset transfer process:
 complies with relevant legislation and guidance
 supports community transfer bodies through the expression of interest and asset
transfer process
 uses feedback from community transfer bodies to inform improvement actions that will
address the findings of the Best Value Report. 
16. The Panel agreed that they should meet with appropriate representatives of the groups set out
in Exhibit 1.   
Page 92

Page 93

5 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
Exhibit 1 – Scrutiny Meetings
Group Key Areas for Discussion
Council
Officer(s)
 Council compliance with legislation and national guidance.
 How the expression of interest pre-application stage assists
community transfer bodies prepare for a full asset transfer request.
 How an asset transfer request is assessed.
 How representation at review panels is decided.
 Whether feedback from community groups is used to inform
improvement actions.
 Progress in addressing the action plan from the Audit Scotland Best
Value Assurance Report.
Audit
Scotland
(author of
Best Value
Assurance
Report) 
 Whether guidance published by the Council is considered compliant
with statutory requirements.
 Whether community transfer bodies can easily access information
and support from Council officers.
 Whether sufficient feedback had been sought from community
transfer bodies to inform the Best Value Assurance Report.
 What specific areas/issues were highlighted as being complex through
feedback received from community transfer bodies.
2. Scrutiny Meetings 
Scrutiny Meeting One – Council Officers – 05 October 2021
17. The first scrutiny meeting consisted of the Council’s Social Enterprise Development Officer, who
is the single point of contact for community groups and supports the Community Asset Transfer
request process and the Estates and Property Development Manager who deals with any
property related matters for the Council and chairs the Asset Transfer Group.  The key messages
reflecting the views of the Council officers who attended, from this meeting are set out in Exhibit
2.
Exhibit 2 – Scrutiny Meeting 1 – Council Officers - Key Messages 
Theme  Detail 
Scottish
Government
and Council
Guidance 
Scottish Government provides two guidance notes, the “Community
Empowerment (Scotland) Act 2015: community transfer bodies’ guidance”
and a 16 page summary guide both of which have been written with
communities in mind.  Council officers have selected key sections from this
guidance to further simplify and publish on the Council’s website for public
use.  General feedback from events and talks is that the webpages are very
helpful.  However, Audit Scotland stated in the Best Value report that
“feedback from Community Groups highlights a perception that the
Council’s current Asset Transfer process is complex and does not fully
support community empowerment”. 
The Council’s Legal Services have been fully involved throughout the
community asset transfer process development and there is a high level of
confidence that the Council fully complies with Scottish Government
guidance and legislation. 
Page 93

Page 94

6 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
The Council’s website contains all of the statutory elements that are
required to be published, including additional links to further guidance and
resources.  
There is information exchange with other Councils, this enables learning
from each other and evaluation of how the process is managed at other
Councils whilst meeting the statutory requirements.  The legislation is still
relatively new and Council processes are evolving. 
An Asset Transfer Request must be in writing but it is not necessary to use
the form provided by the Council.  Community transfer bodies are
encouraged to use the expression of interest process, this allows the
Council to provide support and information on what may be the best
approach to meet the communities need. 
The value of assets involved tend to be low and there has not been a
request close to the State Aid barrier to date, there is unlikely to be any
significant impact following the change to Subsidy Control which currently
has a threshold of approximately £335,000 over the current and two
previous years.   
Expression of
Interest (EOI)
The EOI process is not a requirement of the Act but is a recommendation in
the Scottish Government Guidelines, many other Councils offer similar
support.  It is not a pre-application stage to a formal asset transfer request
(ATR), it is an option groups can choose to use to investigate their idea
further without necessarily requiring a formal ATR as other solutions to
address their needs are often identified thus negating the need to submit a
formal ATR.   
Every EOI is different, some are easy to quantify but some are vague in
terms of their request or identified outcome, however the Council tries to
help groups find a solution or clarify what outcome the community is
looking for.  The EOI process guides the groups towards the best way to
achieve their objectives without necessarily resulting in a formal ATR.  In
addition the process helps groups understand the full extent of their
interest and the associated operational requirements should they wish to
progress.  If what a group is suggesting seems unrealistic they receive
feedback and suggestions for improvement, this allows the group to make a
more informed decision of whether they wish to proceed, seek alternative
solutions or withdraw from the process.   
EOI forms gather initial high level information. Part of the assessment
process looks at ongoing capacity within the group and resilience to
continue to manage or develop services with the asset for the benefit for
the wider community.   
EOIs are not rejected, the final decision is made by the group on whether to
take the request forward, however, a positive outcome is supported
wherever possible. It can be difficult to measure whether an EOI remains
active or not as groups are often slow to respond and therefore unsure if
they have decided whether to continue or not.   
Page 94

Page 95

7 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
The annual Scottish Government return identifies how many EOIs have
been received, how many have progressed to full ATR and how many have
resulted in an alternative positive outcome.  These statistics show that very
few EOIs progress to formal ATR, however this is not necessarily a negative
result as positive outcomes are often achieved by other means.  At present
the Council do not capture information in relation to the final outcome
where a full ATR is not achieved.   
General support and information regarding funding opportunities is offered
to any group qualifying as a community transfer body (CTB).  Groups that
do not qualify as a CTB are also supported although they would not be
entitled to use the formal legislation.  Groups are also directed to other
Council services such as Business Gateway and partner agencies such as
Just Enterprise for further/specialist advice and support. 
The Council does not provide financial support to groups to progress their
EOI or ATR, however they do facilitate a joint valuation of the property
concerned.  Officers will advise of other funding sources and available
assistance e.g. Business gateway will with the preparation of a business
plan. 
Asset Transfer
Request
Community Asset Transfer information provided on the Council’s webpage
is based on the legislation to ensure compliance with the Act.   
The Community Empowerment Act is about empowering communities
voices to be heard, their requests listened to and considered.   It does not
provide a guarantee that a request will be approved but it does give them
certain rights to be heard and not dismissed. 
Community groups can submit a request for assets which are currently in
use by the Council, there is no requirement for the asset to be identified as
being a surplus asset, however, this could possibly make their request a bit
more challenging. 
An ATR can be submitted at any time by a CTB and it is their decision
whether or not to take forward.  Council Officers will provide support and
advice in order to ensure that any ATR application submitted by a CTB is as
strong as possible to provide the best chance of succeeding. If the CTB can
then alleviate some of the concerns at the outset this gives them a stronger
more robust ATR going forward.   
Formal ATRs are concluded when a decision has been reached or an appeal
has been heard.  If unsuccessful, officers will continue to engage with the
groups to find an alternative positive outcome for their request.   
Financial and Legal Services are represented on the Asset Transfer Group
(ATG).  They will assess their relevant areas within the application and if
required will request further information depending on the scale of the
asset the CTB are looking to take over.  An updated matrix is used for
evaluation of all ATRs. 
Page 95

Page 96

8 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
Review Panels Members of the Policy and Resources Committee are responsible for
determining how to run review panels. A review panel can be a complete
review, an open public meeting or review of additional information
provided by council officers or the CTB.   The ATG will provide an asset re-
evaluation report to help guide decision making. 
Each case is reviewed and considered on its individual merit rather than
taking a consistent approach.   
Both review panels held were conducted as a desk-top exercise with
additional information presented, there was no representative from the
CTBs present at either review panel. 
Feedback From
Community
Groups
There has been no customer survey for ATR or EOI’s undertaken to date,
however, feedback received at courses or events for communities has been
positive.   
Some changes have been identified and these are reviewed by the legal
team prior to publishing to ensure ongoing compliance with the Act. 
Specific changes are being made following the BV3 comments to aid
community engagement and understanding. 
Officers have attended and contributed at training, events and
consultations organised by Community Ownership and Support Service
(COSS, a subsidiary branch of the Development Trust Association that is
funded directly from Scottish Government to support communities and LAs
in delivering asset transfers).  Council officers also review websites of other
Councils to benchmark our information provision and processes with other
Local authorities, we have similar processes to others but also do some
things that others don’t. 
Officers attended a national event for local authorities to review the
process and feed into a review of the Act, a similar event is planned for
community groups to get wider feedback.  It is thought that a paper will be
produced at the end of the current parliament covering any required
updates or changes to the Act. 
Best Value
Assurance
Report Action
Plan and
Progress
Positive feedback has been received from groups regarding the information
available on the Council’s website.  The web pages have been updated in
light of the BV3 report with a focus on the EOI pages to simplify the
language used and remove some of the technical information, replacing it
with links to provide further information or clarity as required.   This is a
recent change and there has been no feedback to date. 
The EOI is a supportive tool for groups to use that enables them to decide
whether they wish to proceed to a full ATR or not.  The panel meeting has
provided a very different view to what is recorded in the Audit Scotland BV3
report. 
Promotion of
Asset Transfers
The BV3 report requires the Council to promote asset transfers, this has
been taken on board. One specific area that the Council has focussed on is
Page 96

Page 97

9 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
that they are actively looking at ways to try and promote toilets that are at
risk of closure and how groups can work in partnership with the Council to
take responsibility for this asset. Similar opportunities will start to appear
on the Council’s webpages as they arise. 
Surplus Assets are marketed commercially by the Estates service to obtain
best value for them.  The details are published on the Council’s website to
allow community groups the opportunity to view and form their proposals
should they wish to apply for an ATR.  However, the focus of the Act is on
the community need rather than the property.
Other relevant
information
Legislation requires officers to respond within a fixed period of time, if
there were more than 2 or 3 ATRs in a year the service would struggle to
resource this.  Around one third of the Social Enterprise Officer’s time is
spent on EOIs and supporting groups to progress enquiries.   
The Council provide limited time monitoring completed ATR’s as all
responsibility is transferred with the asset.  If another option is taken
forward using a joint approach, the Council can provide guidance and
support to the group.
Scrutiny Meeting Two – Audit Scotland – 18 November 2021
18. The second scrutiny meeting consisted of representatives from Audit Scotland, this included the
Audit Director and two Senior Audit Managers.  The key messages from this meeting, reflecting
the views of Audit Scotland, are set out in Exhibit 3. 
Exhibit 3 – Scrutiny Meeting 2 – Audit Scotland - Key Messages 
Theme  Detail 
Scottish
Government
Guidance
Observations made by the panel regarding the complexity of government
guidance are well made, however, this is often the nature of guidance
documents.  Unfortunately, community groups often do not have the
capacity or time to deal with complex guidance. 
The Government return could include more information regarding
positive outcomes that have not resulted in a full community asset
transfer.   
Argyll and Bute
Council
Guidance and
Procedures
The BV3 report recognised that there is guidance in place but that it may
be over burdensome and could be streamlined.   
The Council has taken Audit Scotland’s comments on board and is
engaging with communities to make the whole process more straight
forward.  The Council aims to simplify the guidelines for community
groups by either slimming down the guidance further, changing it or
producing something that runs alongside it to make it easier for people to
work with. 
The guidance has to be provided for transparency reasons but this can be
off-putting for community groups.   Incorporating the guidance into the
process and early engagement between the Council and community
groups is therefore of utmost importance.  This helps to establish what
the community group are looking to achieve and then progress the
Page 97

Page 98

10 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
requirement in meaningful segments using the officer’s technical
expertise to support the group through the process. 
Feedback from
Community
Groups used to
inform Argyll
and Bute
Council’s Best
Value
Assurance
Report
The BV3 report was cleared with SMT to agree factual accuracy prior to
publishing.   
One of the elements of the BV3 report was to look at how the Council
engages with the community, how active it is in promoting community
engagement and what the perceptions are from the community in terms
of the level of engagement.  It was not intended to look specifically at
community asset transfers.   
There was no survey used as part of the BV3 audit, the work involved
meeting with a number of community groups or their representatives
drawn from across Argyll and Bute area with a mix of island and mainland
based groups to gain an understanding of how they perceived community
engagement.  There is no definitive data available to share with the
Council. 
One of the themes to emerge was that of mixed feelings regarding the
Community Asset Transfer process and this was documented in the
report as a perception as the asset transfer process had not been audited. 
The purpose of the report content was to reflect back to the Council for
consideration on how to move forward and better understand why the
community groups were of this opinion. 
Audit Scotland acknowledged that there may be an element of bias in the
perception depending on the results of applications or enquiries made by
the groups that were consulted.   
As well as the feedback from communities there is corroborative
feedback from some of the elected members where they were aware of
communities enabled to engage with the Council and take forward
community asset transfers. 
Audit Scotland did not look at the Council’s website in any great detail
when preparing the BV3 report. 
The website is due to promote assets for community participation in 2022
on a trial basis as part of the improvement actions. 
It would be beneficial to request feedback from community groups on
how clear and easy it is to access and navigate the website to make it as
user-friendly as possible and achieve a positive outcome.   
It would also be beneficial to indicate that a community asset transfer is
not the only option and there are other solutions that may be more
appropriate.  Some solutions may involve further partnership working
between community groups where more than one community group is
interested in a property e.g. library within a café. 
Page 98

Page 99

11 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
Other
observations/
comments
Audit Scotland acknowledged that not all applications for community
asset transfers come to fruition and that was fundamental,
demonstrating the complexity of the process and also because
community asset transfer is not necessarily the best outcome as a better
solution might present itself as noted above in the Scottish Government
guidance detail of Exhibit 3.   
The Council should reflect on the support provided to community groups
considering community asset transfer and establish whether they are
comfortable with the level provided and whether it is considered to be a
partnership approach or client and customer relationship dealt with at
arms-length.   
The Council could benefit from discussing and comparing processes with
Glasgow City Council in terms of how they have set up their processes,
their arrangements and their team to deal with not just community asset
transfers but more about finding the right solution and working with
community groups in terms of some of the challenges.  
3. Overall Conclusion and Findings 
19. Based on the information obtained over the course of the review the Panel has concluded that:
 the Community Asset Transfer process is compliant with statutory requirements
 the process enables opportunity for engagement with community transfer bodies
 the process is supportive to community transfer bodies and communities 
20. The review has identified eight findings which have been discussed with management. These,
and the management responses, are detailed in Exhibit 4.
Exhibit 4 – Findings
No. Recommendations Management Response
1 The legislation is still relatively new and
processes are evolving.  Some variations in
processes exist between Councils due to
interpretation of the legislation. 
Information exchange takes place with
other Councils for learning and evaluation
purposes however Audit Scotland suggests
communicating directly with Glasgow City
Council to learn from some of the
challenges they have overcome.
COSS have established a Quarterly Forum
“RA Quarterly Group” which
representatives of the Asset Transfer
Group plan to attend. This will give the
opportunity to learn from other councils
and discuss how others resolve any issues.
Next meeting 7th March 2022. 
2 The annual Scottish Government return
identifies how many EOIs have been
received and how many asset transfers
have been received.  These statistics show
that very few EOIs progress to formal ATR,
however this is not necessarily a negative
result as positive outcomes are often
achieved by other means.  There is no
Data is collected on numbers with notes of
resolution.  Work is ongoing to develop
quarterly highlight reports that give
further detail of outcomes. The follow up
outcomes of assets previously transferred
will be added on a periodic basis to the
quarterly reporting.
Page 99

Page 100

12 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
No. Recommendations Management Response
data capture of all outcomes and the
degree of resolution achieved, therefore,
a method or format should be created to
identify the outcomes secured.
3 An EOI is not a pre-application stage to a
formal asset transfer request (ATR), it is an
option that groups can choose to explore
their idea further without necessarily
requiring a formal ATR.  Other solutions
often present themselves that will address
the needs of the group thus negating the
need to submit a formal ATR.   The
information provided on EOI does not
make this explicit on the website.
Actions have been taken to clarify the
processes and the options available.  We
have clarified our descriptions of the
processes and try to be consistent in our
use of language when discussing /
describing the processes on offer. 
4 Review panels were held for two rejected
ATRs, these were conducted as a desk-top
exercise with additional information
presented to support the appeal.  There
was no representative from the CTBs
present at either review panel.  The
option of a default presence of CTBs
should be investigated.
Currently this is a decision that sits with
the Policy and Resources sub group.  They
decide on the format of the review and
can request participation from the group if
this was considered to assist with the
process.
5 No customer surveys have been
undertaken to date, however, feedback is
received when attending courses and
events and this has been positive.  More
in-depth feedback from community
groups should be considered, it may be
useful to approach COSS to obtain advice
on how to structure such feedback.
The Communities and Partnership Team
(CPT) have been working with COSS to
deliver some introductory training
courses.  The Scottish Government and
COSS have been undertaking community
consultation. We will review the feedback
from this and then consider what further
consultation is needed and add this to the
CPT training programs.
6 The Council is actively looking at ways to
promote asset transfers, toilet facilities in
particular with other opportunities to
follow as they arise.
This action is being developed and with
the approval of the Asset Transfer Group
will be implemented in 22/23. 
7 The BV3 report recognised that Council
guidance is in place but that it may be
over burdensome and could be
streamlined as community groups often
do not have the capacity, time or
capability to deal with complex guidance. 
Audit Scotland did not review the
Council’s website in any great detail
during their review, however, the web
pages have been updated as a result of
the BV3 report with a focus to simplify the
EOI pages, and there has been no
feedback to date. 
Action noted and will be raised at 
COSS events along with regular catch up
meetings with COSS representatives. 
Page 100

Page 101

13 
Argyll and Bute Council – Scrutiny Report – Community Asset Transfer 2021/22
No. Recommendations Management Response
The Council’s guidance is based on
complex guidance issued by Scottish
Government and therefore may deter
groups from applying.  Council officers
should consider raising the issue with the
COSS group with a view to submitting a
collective request to Scottish Government
to review and potentially simplify the
guidance.
8 It would be beneficial to indicate that a
community asset transfer is not the only
opportunity available to CTBs as there are
other solutions that may be more
appropriate.  Some solutions may involve
further partnership working between CTBs
where more than one CTB is interested in
a property e.g. library within a café.  This
type of solution should be added to the
information available on the Council’s
website.
This information has been added to the
website.  We will continue to monitor and
look for ways to highlight further
opportunities as we develop these
resources. 
Page 101

Page 102

This page is intentionally left blank

Page 103

Helensburgh and Lomond Workplan 2022 – 23 
Committee
Date
Report Description Lead Service and contact officer Regularity of
occurrence/consideration
Date for
Reports to
Committee
Services
Additional
Comment
13th September 2022
13th
September
2022
Quarterly
Performance
Scorecard FQ1
22/23
Jane Fowler/Sonya Thomas
Performance and Improvement
Quarterly Report  
13th
September
2022
Roads and
Infrastructure
Services Update
Jim Smith
Roads and Infrastructure
Services
Quarterly Report  
13th
September
2022
Annual Recycling
Performance Report
Jim Smith
Roads and Infrastructure
Services
Annual Report  
13th
September
2022
Police Scotland
Update
Inspector Roderick MacNeill
Police Scotland 
Quarterly Report  
13th
September
2022
Helensburgh,
Cardross and
Dumbarton
Cyclepath Update
Colin Young
Development and Economic
Growth 
Regular Report  
13th
September
2022
Major Projects
Update 
Bi-Annual Update  
13th
September
2022
Referral from Audit
and
Scrutiny(Community
Asset Transfer)
Committee Services One off report  
13th December 2022
Page 103
Agenda Item
11

Page 104

Helensburgh and Lomond Workplan 2022 – 23 
Committee
Date
Report Description Lead Service and contact officer Regularity of
occurrence/consideration
Date for
Reports to
Committee
Services
Additional
Comment
13th 
December
2022
Hermitage
Academy Report 
Douglas Morgan
Acting Head Teacher
Annual Report  
13th 
December
2022
Quarterly
Performance
Scorecard FQ2
21/22
Jane Fowler/Sonya Thomas
Performance and Improvement
Quarterly Report  
13th 
December
2022
HSCP Bi-Annual
Update Report
Charlotte Craig/Fiona Davies
Argyll and Bute Health and
Social Care Partnership
Bi-Annual Report  
13th 
December
2022
Charities and Trust
Funds
Shona Barton
Legal and Regulatory Support 
Annual Report  
13th 
December
2022
Roads and
Infrastructure
Services Update
Jim Smith
Roads and Infrastructure
Services
Quarterly Report  
13th 
December
2022
Police Scotland
Update
Inspector Roderick MacNeill
Police Scotland 
Quarterly Report  
13th 
December
2022
Commercial
Services Property
Update
David Allan
Development and Economic
Growth
Quarterly Report  
13th 
December
2022
Helensburgh
Conservation Area
Regeneration
Scheme (CARS)
Dianne Richardson
Development and Economic
Growth
Update Report  
Page 104

Page 105

Helensburgh and Lomond Workplan 2022 – 23 
Committee
Date
Report Description Lead Service and contact officer Regularity of
occurrence/consideration
Date for
Reports to
Committee
Services
Additional
Comment
13th 
December
2022
Helensburgh,
Cardross and
Dumbarton
Cyclepath Update
Colin Young
Development and Economic
Growth 
Regular Report  
14th March 2023
14th  March
2023
Supporting
Communities Fund
Applications 
Kirsty Moyes/Becky Hothersall
Chief Executive
Annual Report  
14th  March
2023
Quarterly
Performance
Scorecard FQ3
22/23
Jane Fowler/Sonya Thomas
Performance and Improvement
Quarterly Report  
14th  March
2023
Roads and
Infrastructure
Services Update
Jim Smith
Roads and Infrastructure
Services
Regular Report  To include
Roads Capital
Plan, Roads
and Amenities
Revenue Work
Plan
(Programmed),
Grass Cutting
Schedule and
Post Winter
Update
14th  March
2023
Strategic Housing
investment plan
(SHIP)
Douglas Whyte
Development and Economic
Growth
Annual Report  
Page 105

Page 106

Helensburgh and Lomond Workplan 2022 – 23 
Committee
Date
Report Description Lead Service and contact officer Regularity of
occurrence/consideration
Date for
Reports to
Committee
Services
Additional
Comment
14th  March
2023
Police Scotland
Update
Inspector Roderick MacNeill
Police Scotland 
Quarterly Report  
14th  March
2023
Commercial
Services Property
Update
David Allan
Development and Economic
Growth
Quarterly Report  
14th  March
2023
Helensburgh,
Cardross and
Dumbarton
Cyclepath Update
Colin Young
Development and Economic
Growth 
Regular Report  
14th  March
2023
Major Projects
Update 
Bi-Annual Update  
Future Items
June 2023  Supporting
Communities Fund
– End of Project
Monitoring Report
2021/22
Kirsty Moyes/Rona Gold
Chief Executive
Regular Report   
Hermitage
Academy –
Curriculum Review
Louise Connor
Education
Update on progress   
Helensburgh
Shopfronts
Andrew Collins
Development and Economic
Growth
Update Report  
Page 106

Page 107

Helensburgh and Lomond Workplan 2022 – 23 
Committee
Date
Report Description Lead Service and contact officer Regularity of
occurrence/consideration
Date for
Reports to
Committee
Services
Additional
Comment 
Parking in
Helensburgh
Hugh O’Neill
Roads and Infrastructure
Services   
Helensburgh
Waterfront
Development
Andrew Collins/John Gordon
Commercial Services
Updates on Progress   
Helensburgh
Conservation Area
Regeneration
Scheme (CARS)
Dianne Richardson
Development and Economic
Growth
Updates on Progress   
Page 107

Page 108

This page is intentionally left blank

Page 109

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee 
DEVELOPMENT AND ECONOMIC
GROWTH 
20 September 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 14 June 2022 in relation to
the delivery of a dedicated, high quality walking and cycle route linking
Helensburgh, Cardross and Dumbarton. 
1.2. Officers are working with WSP to agree an updated work plan and programme
to progress the design process to the technical design stage.  WSP have
indicated an estimated timescale of 20 weeks to complete their work once an
updated work plan is agreed. 
1.3. Phase 3, linking Helensburgh Town Centre to the existing section of cyclepath
adjacent to Morrison’s Supermarket, has received 22/23 funding from the highly
competitive Transport Scotland’s Places for Everyone Programme challenge
fund to undertake community engagement, route identification and concept
design (PFE stages 0 – 2). 
RECOMMENDATIONS 
1.4. It is recommended that the Helensburgh and Lomond members: 
1.4.1. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process for
Phases 1 & 2, Helensburgh to Cardross and Cardross to Dumbarton. 
1.4.2. Welcome the securing of funding from the highly competitive Places for
Everyone Programme for initial design development of Phase 3,
Helensburgh Town. 
1.4.3. Instruct Officers in future to provide an annual update report on the
Helensburgh – Cardross – Dumbarton Cyclepath project in line with the
annual nature of the external funding used to develop and deliver this
project. 
Page 109 Agenda Item 12a

Page 110

1.4.4. Instruct Officers to provide update reports additional to the annual update
report to the Committee by exception when a significant development
which members should be aware of occurs. 
Page 110

Page 111

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
20 September 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 14 June 2022 in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh, Cardross
and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process for
Phases 1 & 2, Helensburgh to Cardross and Cardross to Dumbarton. 
3.1.2. Welcome the securing of funding from the highly competitive Places for
Everyone Programme for initial design development of Phase 3,
Helensburgh Town. 
3.1.3. Instruct Officers in future to provide an annual update report on the
Helensburgh – Cardross – Dumbarton Cyclepath project in line with the
annual nature of the external funding used to develop and deliver this
project. 
3.1.4. Instruct Officers to provide update reports additional to the annual update
report to the Committee by exception when a significant development
which members should be aware of occurs. 
4.0 DETAIL 
Finances 
4.1. Design (Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton). 
Funding for the design development has been confirmed from the Transport
Scotland Places for Everyone programme, administered by Sustrans.  The
Places for Everyone programme, funded by the Scottish Government/Transport
Scotland, is a highly competitive challenge fund which requires projects to
Page 111

Page 112

closely comply with the ever evolving design requirements set by Sustrans as
administrators of the funding. 
4.2. Design (Phase 3 Helensburgh Town).  Funding has been secured from the
highly competitive challenge fund Places for Everyone programme, which
administered by Sustrans.  This funding will be used to engage an external
design consultant to lead on community engagement, preferred route
identification and concept design.  The Places for Everyone programme, funded
by the Scottish Government/Transport Scotland, is a highly competitive
challenge fund which requires projects to closely comply with the ever evolving
design requirements set by Sustrans as administrators of the funding. 
4.3. Construction (Cardross Rail Station to Geilston Burn).  Costs for the final
works in Cardross Park to complete the section linking Cardross Rail Station to
the Geilston Burn have been paid to the Council’s Roads and Infrastructure
Service. These costs were secured from Strathclyde Partnership for Transport
(SPT) Capital Programme and the Scottish Government’s Cycling, Walking and
Safer Routes fund. 
4.4. The Council’s Active Travel Team (1.3 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
Design 
4.5. Transport Scotland’s Places for Everyone funding programme, administered by
Sustrans, is structured around 8 project stages with gateways which require
approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use. 
4.6. Phase 1 & 2 Developed design (stage 3) work for the outstanding section of
the route linking Colgrain to Geilston Burn, Cardross and Ferry Road, Cardross
to Dumbarton has been paused by WSP.  Officers are working with WSP to
confirm a programme to complete the developed design, including considering
the outcomes of the community engagement prior to progressing the
necessary design work. 
4.7. Phase 1 & 2 Technical Design (stage 4) engineering investigation and design
finalization is planned to be progressed following completion of the develop
design stage.  Officers are working with WSP to confirm a programme to
complete the technical design stage.  Once completed, the Developed Design
and Technical Design will complete the design stages required prior to land
acquisition and construction. 
Page 112

Page 113

4.8. Phase 1 & 2 Landowner engagement.  As instructed, WSP have sought
engagement with all identified landowners affected by the route to gain their
input to the design development.  Landowner comments have been considered
and, where appropriate incorporated, within the developed designs. 
4.9. Phase 3 (Helensburgh Town) Concept Design (stage 0 – 2) will commence
on completion of the procurement exercise required to appoint a design
consultant.  This is for the initial design stages and will include community
engagement, identification of a preferred route and concept design.  Due to the
entire reliance of this project on external funding it has not been possible to
commence procurement or work on this important section of the route until a
funding decision was received. 
Construction (stage 5): Cardross Station to Geilston Burn 
4.10. The section of route linking Cardross Station to Cardross Park opened in
December 2021 and is already being well used by the community.   
4.11. Confirmation is awaited from the Council’s Roads Operations team as to when
the final surfacing, signs and lines for the whole route linking Cardross Station to
the Geilston Burn will be completed.  This will require to fit within the available
delivery capacity and existing workload of the Roads Operations team. 
Programme 
4.12. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.13. Appendix 2 provides an update on commercial discussions with the design
contractor and the current position on land negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following detailed design work and as and when land purchases have been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive challenge funding, committing
appropriate match funding and securing access to private land for the route.
Page 113

Page 114

6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external grant funding applications. The
Council has not contributed any funding to design or
capital costs.  There is evidence to indicate that people
who are more active, for example by walking or
cycling, are less likely to require social care services in
later life which could result in a future saving to the
Council or HSCP although the value of this would be
difficult to quantify.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
6.5.2 Socio-
economic Duty
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
Page 114

Page 115

6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
17 August 2022                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]
Page 115

Page 116

This page is intentionally left blank

Page 117

Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme 
Activity
2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2
Q
3
Q
4
Q
1
Q
2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Funding Applications                                                                
Phase 1: Helensburgh to Cardross                                    
Route Design: Helensburgh to Cardross                                                               
Land Purchase Negotiations: Helensburgh to Cardross                                                               
CPO Process (if required):                                                                
- Provide CPO recommendation to H&L Area Committee                                        
- Develop CPO                                                               
- Gain Full Council approval for CPO                                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                                
- CPO Process                                                                
Construction: Helensburgh to Cardross                                                                
Construction of Helensburgh to Cardross Phase 1
(Cardross Station to Geilston Burn)                                                                
Construction of Helensburgh to Cardross Phase 2
(assuming negotiated acquisition)                                                                
Construction of Helensburgh to Cardross Phase 3
(assuming Compulsory Purchase Order required)                                                                
Construction of Helensburgh to Cardross Phase 4
(assuming Compulsory Purchase Order required)                                                                
Phase 2: Cardross to Dumbarton                                    
Route Design: Cardross to Dumbarton                                                                
Land Purchase Negotiations: Cardross to Dumbarton                                                                
CPO Process (if required):                                                                
- Provide CPO recommendation to H&L Area Committee                                        
- Develop CPO                                                                
- Gain Full Council approval for CPO                                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                                
- CPO Process                                                                
Construction: Cardross to Dumbarton                                                                
Construction of Cardross to Dumbarton Phase 1
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 2
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 3
(assuming Compulsory Purchase Order required)                                                                
Construction of Cardross to Dumbarton Phase 4
(assuming Compulsory Purchase Order required)                                                                
Helensburgh: Hermitage Academy to Town Centre                                    
Community Consultation & Route Identification                                    
Route Design                                    
Land Access Negotiations                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 1                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 2                                                                 
Colour Key (Responsibilities / Lead): 
Green: Strategic Transportation 
Blue: Road Service 
Orange: Estates Service 
Red: Legal 
Purple: External to Council (e.g. Scottish Government)
Page 117
Agenda Item
12b

Page 118

This page is intentionally left blank

Page 119

Document is Restricted
Page 119 Agenda Item 12cNOT FOR PUBLICATION by virtue of paragraph(s) 6
of Schedule 7A of the Local Government(Scotland) Act 1973

Page 120

This page is intentionally left blank