ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee 
DEVELOPMENT AND ECONOMIC
GROWTH 
20 September 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 14 June 2022 in relation to
the delivery of a dedicated, high quality walking and cycle route linking
Helensburgh, Cardross and Dumbarton. 
1.2. Officers are working with WSP to agree an updated work plan and programme
to progress the design process to the technical design stage.  WSP have
indicated an estimated timescale of 20 weeks to complete their work once an
updated work plan is agreed. 
1.3. Phase 3, linking Helensburgh Town Centre to the existing section of cyclepath
adjacent to Morrison’s Supermarket, has received 22/23 funding from the highly
competitive Transport Scotland’s Places for Everyone Programme challenge
fund to undertake community engagement, route identification and concept
design (PFE stages 0 – 2). 
RECOMMENDATIONS 
1.4. It is recommended that the Helensburgh and Lomond members: 
1.4.1. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process for
Phases 1 & 2, Helensburgh to Cardross and Cardross to Dumbarton. 
1.4.2. Welcome the securing of funding from the highly competitive Places for
Everyone Programme for initial design development of Phase 3,
Helensburgh Town. 
1.4.3. Instruct Officers in future to provide an annual update report on the
Helensburgh – Cardross – Dumbarton Cyclepath project in line with the
annual nature of the external funding used to develop and deliver this
project.

Page 2

1.4.4. Instruct Officers to provide update reports additional to the annual update
report to the Committee by exception when a significant development
which members should be aware of occurs.

Page 3

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
20 September 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 14 June 2022 in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh, Cardross
and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Note the continued efforts of Officers to engage with WSP Design
Consultants to confirm the programme to complete the design process for
Phases 1 & 2, Helensburgh to Cardross and Cardross to Dumbarton. 
3.1.2. Welcome the securing of funding from the highly competitive Places for
Everyone Programme for initial design development of Phase 3,
Helensburgh Town. 
3.1.3. Instruct Officers in future to provide an annual update report on the
Helensburgh – Cardross – Dumbarton Cyclepath project in line with the
annual nature of the external funding used to develop and deliver this
project. 
3.1.4. Instruct Officers to provide update reports additional to the annual update
report to the Committee by exception when a significant development
which members should be aware of occurs. 
4.0 DETAIL 
Finances 
4.1. Design (Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton). 
Funding for the design development has been confirmed from the Transport
Scotland Places for Everyone programme, administered by Sustrans.  The
Places for Everyone programme, funded by the Scottish Government/Transport
Scotland, is a highly competitive challenge fund which requires projects to

Page 4

closely comply with the ever evolving design requirements set by Sustrans as
administrators of the funding. 
4.2. Design (Phase 3 Helensburgh Town).  Funding has been secured from the
highly competitive challenge fund Places for Everyone programme, which
administered by Sustrans.  This funding will be used to engage an external
design consultant to lead on community engagement, preferred route
identification and concept design.  The Places for Everyone programme, funded
by the Scottish Government/Transport Scotland, is a highly competitive
challenge fund which requires projects to closely comply with the ever evolving
design requirements set by Sustrans as administrators of the funding. 
4.3. Construction (Cardross Rail Station to Geilston Burn).  Costs for the final
works in Cardross Park to complete the section linking Cardross Rail Station to
the Geilston Burn have been paid to the Council’s Roads and Infrastructure
Service. These costs were secured from Strathclyde Partnership for Transport
(SPT) Capital Programme and the Scottish Government’s Cycling, Walking and
Safer Routes fund. 
4.4. The Council’s Active Travel Team (1.3 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
Design 
4.5. Transport Scotland’s Places for Everyone funding programme, administered by
Sustrans, is structured around 8 project stages with gateways which require
approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use. 
4.6. Phase 1 & 2 Developed design (stage 3) work for the outstanding section of
the route linking Colgrain to Geilston Burn, Cardross and Ferry Road, Cardross
to Dumbarton has been paused by WSP.  Officers are working with WSP to
confirm a programme to complete the developed design, including considering
the outcomes of the community engagement prior to progressing the
necessary design work. 
4.7. Phase 1 & 2 Technical Design (stage 4) engineering investigation and design
finalization is planned to be progressed following completion of the develop
design stage.  Officers are working with WSP to confirm a programme to
complete the technical design stage.  Once completed, the Developed Design
and Technical Design will complete the design stages required prior to land
acquisition and construction.

Page 5

4.8. Phase 1 & 2 Landowner engagement.  As instructed, WSP have sought
engagement with all identified landowners affected by the route to gain their
input to the design development.  Landowner comments have been considered
and, where appropriate incorporated, within the developed designs. 
4.9. Phase 3 (Helensburgh Town) Concept Design (stage 0 – 2) will commence
on completion of the procurement exercise required to appoint a design
consultant.  This is for the initial design stages and will include community
engagement, identification of a preferred route and concept design.  Due to the
entire reliance of this project on external funding it has not been possible to
commence procurement or work on this important section of the route until a
funding decision was received. 
Construction (stage 5): Cardross Station to Geilston Burn 
4.10. The section of route linking Cardross Station to Cardross Park opened in
December 2021 and is already being well used by the community.   
4.11. Confirmation is awaited from the Council’s Roads Operations team as to when
the final surfacing, signs and lines for the whole route linking Cardross Station to
the Geilston Burn will be completed.  This will require to fit within the available
delivery capacity and existing workload of the Roads Operations team. 
Programme 
4.12. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.13. Appendix 2 provides an update on commercial discussions with the design
contractor and the current position on land negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following detailed design work and as and when land purchases have been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive challenge funding, committing
appropriate match funding and securing access to private land for the route.

Page 6

6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external grant funding applications. The
Council has not contributed any funding to design or
capital costs.  There is evidence to indicate that people
who are more active, for example by walking or
cycling, are less likely to require social care services in
later life which could result in a future saving to the
Council or HSCP although the value of this would be
difficult to quantify.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
6.5.2 Socio-
economic Duty
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.

Page 7

6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
17 August 2022                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]