ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee 
DEVELOPMENT AND ECONOMIC
GROWTH 
13 December 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 20 September 2022 in
relation to the delivery of a dedicated, high quality walking and cycle route
linking Helensburgh, Cardross and Dumbarton. 
1.2. Officers have agreed with WSP that their work package will be finished no later
than 31 March 2023.  This provides a confirmed date by which WSP will
complete contracted work and helps to clarify the timescale to progress this
important project.  At time of writing, Officers are working to agree an updated
work plan and programme with WSP to enable their work to be completed by
the end of the financial year. 
1.3. Subsequent to WSP’s work, some further elements will require to be undertaken
during summer 2023 to complete the design package required for construction. 
This includes ecology surveys which can only be undertaken during summer
months and a quality review of the design work undertaken by WSP. 
RECOMMENDATIONS 
1.4. It is recommended that the Helensburgh and Lomond members: 
1.4.1. Welcome the agreement with WSP that their work package will be
completed no later than 31 March 2023. 
1.4.2. Note that some elements of work will require to be completed separately
during summer 2023 to finalise the full package required for construction.

Page 2

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee 
DEVELOPMENT AND ECONOMIC
GROWTH 
13 December 2022 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 20 September 2022 in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh, Cardross
and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome the agreement with WSP that their work package will be
completed no later than 31 March 2023. 
3.1.2. Note that some elements of work will require to be completed separately
during summer 2023 to finalise the full package required for construction. 
4.0 DETAIL 
Finances 
4.1. Design (Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton). 
Funding for the design development has been secured from the Transport
Scotland Places for Everyone programme, administered by Sustrans.  The
Places for Everyone programme, funded by the Scottish Government, is a highly
competitive challenge fund which requires projects to closely comply with the
ever evolving design requirements set by Sustrans as administrators of the
funding. 
4.2. Design (Phase 3 Helensburgh Town).  Funding has been secured from
Transport Scotland’s highly competitive challenge fund Places for Everyone
programme, which administered by Sustrans.  This funding will be used to
engage an external design consultant to lead on community engagement,
preferred route identification and concept design.  The Places for Everyone
programme, funded by the Scottish Government/Transport Scotland, is a highly
competitive challenge fund which requires projects to closely comply with the

Page 3

ever evolving design requirements set by Sustrans as administrators of the
funding. 
4.3. Construction (Cardross Rail Station to Geilston Burn).  Costs for the final
works in Cardross Park to complete the section linking Cardross Rail Station to
the Geilston Burn have been paid to the Council’s Roads and Infrastructure
Service. These costs were secured from Strathclyde Partnership for Transport
(SPT) Capital Programme and the Scottish Government’s Cycling, Walking and
Safer Routes fund. 
4.4. The Council’s Active Travel Team (2 FTE) is part of the Strategic Transport Team
within the Development and Economic Growth Service.  No Council funding is
currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
Design 
4.5. Transport Scotland’s Places for Everyone funding programme, administered by
Sustrans, is structured around 8 project stages with gateways which require
approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use. 
4.6. Phase 1 & 2 Developed design (stage 3) work for the outstanding section of
the route linking Colgrain to Geilston Burn, Cardross and Ferry Road, Cardross
to Dumbarton is due to be recommenced by WSP.  A programme for completion
of the design stage is awaited from WSP, which will plan for their work to be
completed by 31 March 2023. 
4.7. Phase 1 & 2 Technical Design (stage 4) engineering investigation and design
finalization is planned to be progressed following completion of the develop
design stage.  Officers are working with WSP to confirm a programme to
complete their work on the technical design by 31 March 2023.  Subsequent to
completion of WSPs work, some further elements will require to be undertaken
during summer 2023 to complete the design package required for construction. 
This includes ecology surveys which can only be undertaken during summer
months and a quality review of the design work undertaken by WSP. 
4.8. Phase 3 (Helensburgh Town) Concept Design (stage 0 – 2) will commence
on completion of the procurement exercise required to appoint a design
consultant.  This is for the initial design stages and will include community
engagement, identification of a preferred route and concept design.   
Construction (stage 5): Cardross Station to Geilston Burn 
4.9. The section of route linking Cardross Station to Cardross Park opened in
December 2021 and is being well used by the community.

Page 4

4.10. The Council’s Roads Operations team are working to complete the work in the
Cardross Park including fencing, bollards and signage by end-November,
dependent on supply of materials.  This will complete work on the Cardross Park
side of the Geilston Burn.  To protect the public, the bridge over the Geilston
Burn will be fenced off until access is agreed to further land on the west side of
the Burn to construct the path through to an accessible destination. 
Programme 
4.11. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.12. Appendix 2 provides an update on commercial discussions with the design
contractor and the current position on land negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following detailed design work and as and when land purchases have been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive challenge funding, committing
appropriate match funding and securing access to private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external grant funding applications. The
Council has not contributed any funding to design or

Page 5

capital costs.  There is evidence to indicate that people
who are more active, for example by walking or
cycling, are less likely to require social care services in
later life which could result in a future saving to the
Council or HSCP although the value of this would be
difficult to quantify.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
6.5.2 Socio-
economic Duty
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
09 November 2022                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk

Page 6

Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]