ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
14 March 2023 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 13 December 2022 in relation
to the delivery of a dedicated, high quality walking and cycle route linking
Helensburgh, Cardross and Dumbarton. 
1.2. Officers have approved five (5) change requests from WSP, resulting in a cost
increase of £28,538.97, taking the total cost of WSPs work to £253,427.96. This
additional cost can be accommodated within the secured external funding. 
1.3. WSP have recommenced their work package and have confirmed their work will
be finished no later than 31 March 2023. 
1.4. Subsequent to WSPs work, Officers are working to identify further elements
which will require to be undertaken during summer 2023 to complete the design
package required for construction.  This includes ground investigation (GI)
surveys, ecology surveys which can only be undertaken during summer months,
a quality review of the design work undertaken by WSP and submission of
planning application and related statutory permissions. 
1.5. Following completion of the full design package, the Council’s Estates Team will
lead the land acquisition process with landowners in order to secure the land
necessary to construct the designed route. 
1.6. While funding has been secured to complete the design stages of the project;
based on current funding models, to pay for construction of the route further
competitive applications will be required to a range of programmes including the
Strathclyde Partnership for Transport (SPT) Capital Programme and the
Transport Scotland Places for Everyone (PFE) Programme, administered by
Sustrans.  The PFE Programme requires a minimum of 30% of total
construction costs are secured from other, non-Transport Scotland derived,
sources. 
1.7. Officers are currently tendering for a design consultancy to identify the preferred
route linking the existing cyclepath at Morrisons Supermarket/Hermitage
Academy to Helensburgh Town Centre and the new section of segregated
cycleway under construction at Helensburgh Waterfront, and to develop the
preferred route to concept design stage.  It is expected this work will commence

Page 2

in May 2023 and be completed in financial year 2023/24.  This work is being
funded via a successful competitive application to Transport Scotland’s PFE
Programme. 
RECOMMENDATIONS 
1.8. It is recommended that the Helensburgh and Lomond members: 
1.8.1. Note the agreement of five change requests from WSP at an additional
cost of £28,538.97, taking the total cost of WSPs work to £253,427.96. 
This additional cost is covered by externally secured funding. 
1.8.2. Welcome the progress made by WSP towards completing their work
package by 31 March 2023. 
1.8.3. Note that some elements of work will require to be completed separately
during summer 2023 to finalise the full package required for construction. 
1.8.4. Note the current tender exercise for a design consultant to commence
work on the section of route linking Morrisons Supermarket to
Helensburgh Town Centre/Waterfront.

Page 3

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
14 March 2023 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 13 December 2022 in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh, Cardross
and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Note the agreement of five change requests from WSP at an additional
cost of £28,538.97, taking the total cost of WSPs work to £253,427.96. 
This additional cost is covered by externally secured funding. 
3.1.2. Welcome the progress made by WSP towards completing their work
package by 31 March 2023. 
3.1.3. Note that some elements of work will require to be completed separately
during summer 2023 to finalise the full package required for construction. 
3.1.4. Note the current tender exercise for a design consultant to commence
work on the section of route linking Morrisons Supermarket to
Helensburgh Town Centre/Waterfront. 
4.0 DETAIL 
Finances 
4.1. Design (Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton).  
Officers have approved five (5) change requests from WSP, resulting in a cost
increase of £28,538.97, taking the total cost of WSPs work to £253,427.96. This
additional cost can be accommodated within the externally secured funding for
this work.  Funding for the design development has been secured from the
Strathclyde Partnership for Transport (SPT) Capital Programme and Transport
Scotland’s Places for Everyone (PFE) programme.  The Transport Scotland
PFE programme, funded by the Scottish Government, is a highly competitive

Page 4

challenge fund which requires projects to closely comply with the ever evolving
design requirements set by the paid administrators of the funding, Sustrans. 
4.2. Design (Phase 3 Helensburgh Town).  Officers are currently tendering for a
design consultancy to identify the preferred route linking Morrisons
Supermarket/Hermitage Academy to Helensburgh Town Centre and the new
section of segregated cycleway under construction at Helensburgh Waterfront,
and to develop the preferred route to concept design stage.  It is expected this
work will commence in May 2023 and be completed in financial year 2023/24. 
This work is being funded via a successful competitive application to the
Transport Scotland PFE Programme.  Funding has been secured from the SPT
Capital Programme and Transport Scotland’s highly competitive challenge fund
PFE programme.  This funding will be used to engage an external design
consultant to lead on community engagement, preferred route identification and
concept design.  Future stages of work will be subject to Officers successfully
securing future competitive challenge funding. 
4.3. Construction (Cardross Rail Station to Geilston Burn).  Costs for the final
works in Cardross Park to complete the section linking Cardross Rail Station to
the Geilston Burn have been paid to the Council’s Roads and Infrastructure
Service. These costs were secured from the SPT Capital Programme and the
Scottish Government’s Cycling, Walking and Safer Routes (CWSR) fund. 
4.4. Match Funding. Transport Scotland’s Places for Everyone programme,
administered by Sustrans, requires a minimum of 30% of total construction cost
is secured by the Council from alternative, non-Transport Scotland derived,
sources.  As this requirements placed upon the project by the Places for
Everyone funding criteria and additional demands of Sustrans PFE Officers
around elements of the design result in a high-quality, expensive to construct,
design the 30% construction match funding requirement is forecast to be in
excess of £2M. 
4.5. The Council’s Active Travel Team (1.7 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
Design 
4.6. Transport Scotland’s Places for Everyone funding programme, administered by
Sustrans, is structured around 8 project stages with a competitive challenge
fund submission for the next stage(s) of funding which require approval from the
Sustrans Project Board at the end of Stage 2 (Concept Design) and Stage 4
(Technical Design) to progress to the next stage.  The project stages are (0)
Strategic Definition, (1) Preparation and Brief, (2) Concept Design), (3)
Developed Design, (4) Technical Design, (5) Construction, (6) Handover &
Close Out and (7) In Use.

Page 5

4.7. Phase 1 & 2 Technical Design (stage 4) engineering design has been
commenced by WSP in line with their programme to complete their work on
the design by 31 March 2023.  This work package includes further landowner
engagement with regard to design detail.  Subsequent to WSPs work further
elements which will require to be undertaken during summer 2023 to complete
the design package required for construction.  This includes ground investigation
(GI) surveys, ecology surveys which can only be undertaken during summer
months, a quality review of the design work undertaken by WSP and submission
of planning application and related statutory permissions.   
4.8. Phase 3 (Helensburgh Town) Concept Design (stage 0 – 2) will commence
on completion of the procurement exercise required to appoint a design
consultant.  This is for the initial design stages of route identification and concept
design, and will include significant community engagement to ensure the route
links the most appropriate locations and best serve community needs.   
Construction (stage 5): Cardross Station to Geilston Burn 
4.9. The Council’s Roads Operations team have completed work in the Cardross
Park including fencing, bollards and signage.  This completes work on the
Cardross Park side of the Geilston Burn.  To protect the public, the bridge over
the Geilston Burn has been fenced off until access is agreed to further land on
the west side of the Burn to construct the path through to an accessible
destination. 
Programme 
4.10. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following completion of design work and as and when land acquisition has been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive external challenge funding,
committing appropriate match funding and securing access to private land for
the route.

Page 6

6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
The Council has not contributed any funding to design
or capital costs.  There is strong evidence that people
who are more active, for example by walking or
cycling, have been physical and mental health and are
less likely to require social care services in later life
which could result in a future saving to the Council or
HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
6.5.2 Socio-
economic Duty
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.

Page 7

6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
13 February 2023                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme