ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
13 June 2023 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 14 March 2023 in relation to
the delivery of a dedicated, high quality walking and cycle path linking
Helensburgh, Cardross and Dumbarton.  The delivery of this path is a stated
Council Priority. 
1.2. Officers have approved one (1) change request from WSP, resulting in a cost
increase of £6,479.51 taking the total cost of WSPs work to £259,907.47. This
additional cost can be accommodated within the secured external funding from
Transport Scotland’s Places for Everyone (PFE) Programme, administered by
Sustrans, and Strathclyde Partnership for Transport’s (SPT) Capital Programme. 
1.3. WSP did not complete their work package by the previously agreed deadline of
31 March 2023.  WSP have submitted an updated programme and, subject to
agreement, now expect to complete their work for end-July 2023.  This
timescale is dependent on securing landowner agreement to enable survey
access and on continued positive engagement with other key stakeholders. 
1.4. In March 2023, WSP sent land access requests for the purpose of non-invasive
ecology surveys to the 15 affected landowners.  Of these, 7 have agreed to
allow access, 3 rejected the request but asked for direct contact from the
Council, 3 rejected the request for access, and, at time of writing, WSP were
unable to reach 2 landowners.  The primary reasons for rejection of access
appear to be around a loss of trust in WSP and the wider design process,
exacerbated by the delay in providing feedback to landowners following initial
meetings caused by the nearly 18 month pause in work by WSP.  One
landowner stating they opposed the selected route alignment and any
proposals to cross their land, while another stated that the path crossing their
land was not part of their revised business plan.  The responses clearly
indicate the need for the design team and the wider project to seek to rebuild
trust with landowners if we are to progress this project in a cooperative
approach. 
1.5. Subsequent to WSPs work, Officers are working to identify further elements
which will require to be undertaken following completion of WSPs work to
complete the design package required for construction.  This includes ground
investigation (GI) surveys, ecology surveys which can only be undertaken during

Page 2

summer months, a quality review of the design work undertaken by WSP and
submission of planning application and related statutory permissions. 
1.6. Following completion of the full design package, the Council’s Estates Team will
lead the land acquisition process with landowners in order to secure the land
necessary to construct the designed route. 
1.7. Officers are working to award a contract to a design contractor by end-June to
identify the preferred route linking the existing cyclepath at Morrisons
Supermarket / Hermitage Academy to Helensburgh Town Centre and the new
section of segregated cycleway under construction at Helensburgh Waterfront,
and to develop the preferred route to concept design stage.  The outline
programme for this work forecasts completion of design stages 0-2 (Feasibility,
Route Alignment and Concept Design) by the end of 2023/24.  This work is
being funded via successful competitive applications to SPT’s Capital
Programme and Transport Scotland’s PFE Programme. 
1.8. While funding has been secured to complete the design stages of the project;
based on current funding models, to pay for construction of the route further
competitive applications will be required to a range of programmes including the
SPT Capital Programme and the Transport Scotland PFE Programme.  The
PFE Programme requires a minimum of 30% of total construction costs are
secured from non-Transport Scotland derived sources. 
RECOMMENDATIONS 
1.9. It is recommended that the Helensburgh and Lomond members: 
1.9.1. Note the agreement of one change requests from WSP at an additional cost of
£6,479.51, taking the total cost of WSPs work to £259,907.47.  This additional
cost is covered by externally secured funding. 
1.9.2. Note amended completion date submitted by WSP of end-July 2023.   
1.9.3. Note that some elements of work will require to be completed separately
following completion of WSPs work to finalise the full package required for
construction. 
1.9.4. Welcome the progress towards the award of contract for the section of route
linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town
Centre/Waterfront, and development of this to Concept Design stage.

Page 3

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
13 June 2023 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 14 March 2023 in relation to the delivery of a
dedicated, high quality walking and cycle path linking Helensburgh, Cardross
and Dumbarton.  The delivery of this path is a stated Council Priority. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Note the agreement of one change requests from WSP at an additional cost of
£6,479.51, taking the total cost of WSPs work to £259,907.47.  This additional
cost is covered by externally secured funding. 
3.1.2. Note amended completion date submitted by WSP of end-July 2023.   
3.1.3. Note that some elements of work will require to be completed separately
following completion of WSPs work to finalise the full package required for
construction. 
3.1.4. Welcome the progress towards the award of contract for the section of route
linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town
Centre/Waterfront, and development of this to Concept Design stage. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team (1.7 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
4.2. In 2022/23, the Active Travel Team secured £3.03M external funding for the
development and delivery of a total of 32 projects across Argyll and Bute, including
the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 22 separate
competitive funding applications, to 8 separate funds.

Page 4

Match Funding 
4.3. Transport Scotland’s Places for Everyone (PFE) programme, administered by
Sustrans, requires a minimum of 30% of total construction cost is secured by the
Council from alternative, non-Transport Scotland derived, sources.  As the
requirements placed upon the project by the Places for Everyone funding criteria
and additional demands of Sustrans PFE Officers around elements of the design
result in a premium design, and therefore expensive to construct,  the 30%
construction match funding requirement is forecast to be in excess of £2M. 
Phasing construction over a number of financial years will enable maximization of
suitable external match funding, however this will result in a longer construction
programme.  Accelerating the construction programme will require additional
match funding to be secured, from internal and/or external sources, which could
prove challenging. 
Design 
4.4. Transport Scotland’s PFE programme is structured around 8 project stages with
a competitive challenge fund submission for the next stage(s) of funding which
require approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use.   
4.5. Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton   
4.5.1. Officers have approved one (1) change request from WSP, resulting in a cost
increase of £6,479.51, taking the total cost of WSPs work to £259,907.47. This
additional cost is for completion of design for the signals proposed at the
junction of Ferry Road/A814, Cardross and can be accommodated within the
externally secured funding for this work.   
4.5.2. WSP did not complete their work package by the previously agreed deadline of
31 March 2023, with Ecological Appraisal, Technical Designs and Monitoring &
Evaluation Plans outstanding.  WSP have stated this was due to longer than
forecast timescales for Network Rail, Scottish Water and landowners to respond
to enquiries.  Officers had previously identified that WSPs timescales for
expecting responses from external organisations and individuals were extremely
optimistic as part of a challenging programme they had set out.  WSP have
submitted an updated programme and, subject to Officer agreement, now
expect to complete their work for end-July 2023.  This timescale is dependent on
securing landowner agreement to enable survey access and on positive
continued engagement with other key stakeholders. 
4.5.3. Land access requests for the purpose of non-invasive ecology surveys were
sent by WSP in March 2023 to the 15 affected landowners.  Of these, 7 have
agreed to allow access, 3 rejected the request but asked for direct contact
from the Council, 3 rejected the request for access, and, at time of writing,

Page 5

WSP were unable to reach 2 landowners.  The primary reasons for rejection
of access appear to be around a loss of trust in WSP and the wider design
process, exacerbated by the delay in providing feedback to landowners
following initial meetings caused by the nearly 18 month pause in work by
WSP.  One landowner stating they opposed the selected route alignment and
any proposals to cross their land, while another stated that the path crossing
their land was not part of their revised business plan.  From the responses
received, there is a clear need for the design team and the wider project to
seek to rebuild trust with landowners if we are to progress this project in a
cooperative manner. 
4.5.4. Due to the nature of ecological investigations, it is necessary for these to cover a
wider area than the land directly occupied by the path.  As such, 4 of the
landowners contacted do not have land which the path will require to pass over. 
4.5.5. Subsequent to completion by WSP of their work package further elements will
require to be undertaken to complete the design package required for
construction.  This includes ground investigation (GI) surveys, ecology surveys
which can only be undertaken during summer months, a quality review of the
design work undertaken by WSP and submission of planning application and
related statutory permissions.   
4.5.6. Funding for the design development has been secured from the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s
PFE programme.  The Transport Scotland PFE programme, funded by the
Scottish Government, is a highly competitive challenge fund which requires
projects to closely comply with the ever evolving design requirements set by the
paid administrators of the funding, Sustrans. 
4.6. Phase 3 Helensburgh Town 
4.6.1. Officers are working to award a contract to a design contractor by end-June to
identify the preferred route linking the existing cyclepath at Morrisons
Supermarket / Hermitage Academy to Helensburgh Town Centre and the new
section of segregated cycleway at Helensburgh Waterfront, and to develop the
preferred route to concept design stage.  The outline programme for this work
forecasts completion of design stages 0-2 (Initial Business Case, Feasibility &
Route Alignment and Concept Design) by the end of 2023/24.  This work will
include community engagement to ensure the route links the most appropriate
locations and best serves community needs.   
4.6.2. This work is being funded via a successful competitive application to the highly
competitive Transport Scotland PFE Programme and to the SPT Capital
Programme.  Future stages of work will be subject to Officers successfully
securing future competitive challenge funding. 
Construction (stage 5) 
4.7. Cardross Rail Station to Geilston Burn

Page 6

4.7.1. Cardross Rail Station to Geilston Burn.  The Council’s Roads and Infrastructure
Service have completed installation of most elements of the cyclepath through
Cardross Park, with only a small amount of fencing still to be installed. This work
has been funded by the SPT Capital Programme and the Scottish Government’s
Cycling, Walking and Safer Routes (CWSR) fund. 
4.7.2. To protect the public, the bridge over the Geilston Burn has been fenced off until
access is agreed to further land on the west side of the Burn to construct the
path through to an accessible destination. 
Maintenance 
4.8. Consideration requires to be given the maintenance of the cyclepath, including
sections of route already in place.  At present, the Council does not receive any
funding for the maintenance of cyclepaths and none of the current external
funding sources for active travel include maintenance as an eligible cost.  This
anomaly has been repeatedly raised by Officers with Transport Scotland Officials
and it is widely acknowledged to be inconsistent with the Scottish Government’s
commitments regarding capital funding for active travel projects. 
4.9. The Roads and Infrastructure Service are the single service within the Council
which possesses infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths, however it is acknowledged
these teams are already at capacity delivering the Roads and Infrastructure
Service commitments. The Roads and Infrastructure Service has previously
stated they will not adopt sections of cyclepath remote from the public road. 
Programme 
4.10. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.11. Appendix 2 provides an update with regard to the current position on landowner
negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following completion of design work and as and when land acquisition has been
concluded.

Page 7

5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on securing highly competitive external challenge funding,
committing appropriate match funding and securing access to private land for
the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
The Council has not contributed any funding to design
or capital costs.  There is strong evidence that people
who are more active, for example by walking or
cycling, have been physical and mental health and are
less likely to require social care services in later life
which could result in a future saving to the Council or
HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment

Page 8

opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
27 April 2023                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]