ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
12 SEPTEMBER 2023 
HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 13 June 2023 in relation to
the delivery of a dedicated, high quality walking and cycle path linking
Helensburgh, Cardross and Dumbarton.  The delivery of this path is a stated
Council Priority. 
1.2. Officers have approved one (1) change request from WSP, resulting in a cost
increase of £5,285.53 taking the total cost of WSPs work to £265,913.00. This
additional cost can be accommodated within the secured external funding from
Transport Scotland’s Places for Everyone (PFE) Programme, administered by
Sustrans, and Strathclyde Partnership for Transport’s (SPT) Capital Programme. 
1.3. WSP continue to work on securing landowner agreement to enable
environmental survey access and on continued engagement with other key
stakeholders to secure support for the designs.  Since the previous update,
Officers have secured agreement to the surveys with one landowner, Officers
and WSP have met on-site with one landowner and Officers have been in
dialogue with the land agents for two other landowners. 
1.4. A contract has been awarded to Civic Engineers for £99,333.00 to identify the
preferred route linking the existing cyclepath at Morrisons Supermarket /
Hermitage Academy to Helensburgh Town Centre and the new section of
segregated cycleway under construction at Helensburgh Waterfront, and to
develop the preferred route to concept design stage.  The outline programme for
this work forecasts completion of design stages 0-2 (Feasibility, Route
Alignment and Concept Design) by the end of 2023/24.  This work is being
funded via successful competitive applications to SPT’s Capital Programme and
Transport Scotland’s PFE Programme. 
1.5. While funding has been secured to complete the design stages of the project;
based on current funding models, to pay for construction of the route further
competitive applications will be required to a range of programmes including the
SPT Capital Programme and the Transport Scotland PFE Programme.  The
PFE Programme requires a minimum of 30% of total construction costs are
secured from non-Transport Scotland derived sources.  The future maintenance
of the route also needs to be considered as currently no specific funding is
received by the Council for maintenance of walking/cycling paths.

Page 2

RECOMMENDATIONS 
1.6. It is recommended that the Helensburgh and Lomond members: 
1.6.1. Welcome the award of contract to Civic Engineers for £99,333.00 for the
identification of a route linking Morrisons Supermarket/Hermitage Academy to
Helensburgh Town Centre/Waterfront, and development of this to Concept
Design stage. 
1.6.2. Note the agreement of one (1) change requests from WSP at an additional cost
of £5,285.53, taking the total cost of WSPs work to £265,913.00.  This additional
cost is covered by externally secured funding. 
1.6.3. Note the continued efforts by WSP and Officers to engage with landowners. 
1.6.4. Note the high-level options for land acquisition laid out in this report. 
1.6.5. Approve Officers to contact colleagues in Highland Council to understand their
experience of Land Reform (Scotland) Act 2003 Section 22 Orders. 
1.6.6. Approve Officers to engage with Scottish Government civil servants to identify
the current requirements for a Compulsory Purchase Order.  For clarity, this
exploratory engagement would not include submission of any Compulsory
Purchase Order, which would require approval of full Council and/or the
appropriate Committee prior to submission. 
1.6.7. Give consideration to the need to secure 30% match funding of the cost of
construction from non-Transport Scotland sources. 
1.6.8. Give consideration to identifying how future maintenance of the path will be
funded and undertaken, given the current situation where no path specific
maintenance funding is provided to the Council.

Page 3

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
12 SEPTEMBER 2023 
HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 13 June 2023 in relation to the delivery of a
dedicated, high quality walking and cycle path linking Helensburgh, Cardross
and Dumbarton.  The delivery of this path is a stated Council Priority. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome the award of contract to Civic Engineers for £99,333.00 for the
identification of a route linking Morrisons Supermarket/Hermitage Academy to
Helensburgh Town Centre/Waterfront, and development of this to Concept
Design stage. 
3.1.2. Note the agreement of one (1) change requests from WSP at an additional cost
of £5,285.53, taking the total cost of WSPs work to £265,913.00.  This additional
cost is covered by externally secured funding. 
3.1.3. Note the continued efforts by WSP and Officers to engage with landowners. 
3.1.4. Note the high-level options for land acquisition laid out in this report. 
3.1.5. Approve Officers to contact colleagues in Highland Council to understand their
experience of Land Reform (Scotland) Act 2003 Section 22 Orders. 
3.1.6. Approve Officers to engage with Scottish Government civil servants to identify
the current requirements for a Compulsory Purchase Order.  For clarity, this
exploratory engagement would not include submission of any Compulsory
Purchase Order, which would require approval of full Council and/or the
appropriate Committee prior to submission. 
3.1.7. Give consideration to the need to secure 30% match funding of the cost of
construction from non-Transport Scotland sources.

Page 4

3.1.8. Give consideration to identifying how future maintenance of the path will be
funded and undertaken, given the current situation where no path specific
maintenance funding is provided to the Council. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team (1.7 FTE) is part of the Strategic Transport
Team within the Development and Economic Growth Service.  No Council funding
is currently received by the Active Travel Team. All project costs, including internal
staff costs, have to be funded via successfully securing highly competitive external
challenge funds. 
4.2. In 2022/23, the Active Travel Team secured £3.03M external funding for the
development and delivery of a total of 32 projects across Argyll and Bute, including
the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 22 separate
competitive funding applications, to 8 separate funds. 
Match Funding 
4.3. Transport Scotland’s Places for Everyone (PFE) programme, administered by
Sustrans, requires a minimum of 30% of total construction cost is secured by the
Council from alternative, non-Transport Scotland derived, sources.  As the
requirements placed upon the project by the Places for Everyone funding criteria
and additional demands of Sustrans PFE Officers around elements of the design
result in a premium design, and therefore expensive to construct,  the 30%
construction match funding requirement is forecast to be in excess of £2M. 
Phasing construction over a number of financial years will enable maximization of
suitable external match funding, however this will result in a longer construction
programme.  Accelerating the construction programme will require additional
match funding to be secured, from internal and/or external sources, which could
prove challenging. 
4.4. At present no construction match funding has been specifically identified and/or
secured.  While SPT Capital Fund is eligible as match, depending on the
timescale for construction and the other demands for SPT Capital Funding it is
considered that alternative sources of match funding should be sought, including
consideration if any internal Council funds should be allocated to delivery of this
Council Priority. 
Design 
4.5. Transport Scotland’s PFE programme is structured around 8 project stages with
a competitive challenge fund submission for the next stage(s) of funding which
require approval from the Sustrans Project Board at the end of Stage 2 (Concept
Design) and Stage 4 (Technical Design) to progress to the next stage.  The
project stages are (0) Strategic Definition, (1) Preparation and Brief, (2) Concept
Design), (3) Developed Design, (4) Technical Design, (5) Construction, (6)
Handover & Close Out and (7) In Use. 
4.6. Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton

Page 5

4.6.1. Officers have approved one (1) change request from WSP, resulting in a cost
increase of £5,285.53 taking the total cost of WSPs work to £265,913.00. This
additional cost is for additional hydrology work associated with understanding
the impact of drainage in Network Rail’s ownership related to the rail line on the
drainage proposed for the cyclepath and can be accommodated within the
externally secured funding for this work. 
4.6.2. WSP are now working to complete their work packages by end of 2023.  This
timescale includes some contingency to enable continued engagement with
landowners to ensure their comments on the designs are gathered and seek to
maximise the number of landowners who agree to allow the necessary ecology
surveys.  However, to complete the work within this revised timescale is still
dependent on positive and responsive engagement from landowners, utilities
networks and key stakeholders. 
4.6.3. In relation to the land access requests for Ecology Surveys, since the last
update report Officers have engaged with 4 landowners and secured agreement
from one landowner.  Therefore, at time of writing 8 landowners have agreed, 3
continue to be engaged, 3 have rejected request for access and one landowner
continues to be unresponsive. 
4.6.4. Funding for the design development has been secured from the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s
PFE programme.  The Transport Scotland PFE programme, funded by the
Scottish Government, is a highly competitive challenge fund which requires
projects to closely comply with the ever evolving design requirements set by the
paid administrators of the funding, Sustrans. 
4.7. Phase 3 Helensburgh Town 
4.7.1. A contract has been awarded to Civic Engineers for £99,333.00 to identify the
preferred route linking the existing cyclepath at Morrisons Supermarket /
Hermitage Academy to Helensburgh Town Centre and the new section of
segregated cycleway at Helensburgh Waterfront, and to develop the preferred
route to concept design stage.  The outline programme for this work forecasts
completion of design stages 0-2 (Initial Business Case, Feasibility & Route
Alignment and Concept Design) by the end of 2023/24.  This work includes
community engagement to ensure the route links the most appropriate locations
and best serves community needs.   
4.7.2. This work is being funded via a successful competitive application to the highly
competitive Transport Scotland PFE Programme and to the SPT Capital
Programme.  Future stages of work will be subject to Officers successfully
securing future external competitive challenge funding and/or allocation of
Council funding. 
Construction (stage 5) 
4.8. Cardross Rail Station to Geilston Burn

Page 6

4.8.1. Cardross Rail Station to Geilston Burn.  The Council’s Roads and Infrastructure
Service have completed installation of most elements of the cyclepath through
Cardross Park, with only a small amount of fencing still to be installed. This work
has been funded by the SPT Capital Programme and the Scottish Government’s
Cycling, Walking and Safer Routes (CWSR) fund. 
4.8.2. To protect the public, the bridge over the Geilston Burn has been fenced off until
access is agreed to further land on the west side of the Burn to construct the
path through to an accessible destination. 
Maintenance 
4.9. Consideration requires to be given the maintenance of the cyclepath, including
sections of route already in place.  At present, the Council does not receive any
funding for the maintenance of cyclepaths and none of the current external
funding sources for active travel include maintenance as an eligible cost.  This
anomaly has been repeatedly raised by Officers with Transport Scotland Officials
and it is widely acknowledged to be inconsistent with the Scottish Government’s
commitments regarding capital funding for active travel projects. 
4.10. The Roads and Infrastructure Service are the single service within the Council
which possesses infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths, however it is acknowledged
these teams are already at capacity delivering the Roads and Infrastructure
Service commitments. The Roads and Infrastructure Service has previously
stated they do not plan to adopt sections of cyclepath remote from the public road.   
4.11. At present no internal or external funding is available for maintenance of
cyclepaths, including the Helensburgh – Cardross – Dumbarton Cyclepath.  To
maximise the benefits of new walking and cycling routes, including the
Helensburgh – Cardross – Dumbarton Cyclepath these require to be maintained. 
While the construction standards set by the Council’s Active Travel Team seek to
minimise future maintenance costs, e.g. by requiring 120 year design life for
structures, regular vegetation cutback and, ideally, winter maintenance are
required to allow year round use. 
Land Access / Acquisition 
4.12. A key requirement of the delivery of this path is securing access to the necessary
land for the construction, maintenance and operation of the path.  As instructed
by the Committee, an outline of the identified potential options for securing access
to the necessary land are laid out in table 1 below.  It should be noted that until
completion of all design work the exact land requirements will be subject to
change.

Page 7

Table 1: Options for Land Access / Acquisition
Option Process Timescale Advantages Disadvantages
Negotiation  Negotiation
with each
landowner/lan
downers
appointed
agent to
secure
voluntary
agreement on
acquisition of
necessary
land.
 Indeterminate,
dependent on
continued
goodwill and
determination
to make
progress.
 Most
collaborative
approach,
therefore
most likely to
ensure
continued
landowner
support.
 Timescale depends
on continued
landowner goodwill.
 If unable to agree
land acquisition
then alternative
option will require to
be commenced.
 Dependent on no
title issues which
prevent the
landowner granting
a valid title in favour
of the Council
(including obtaining
the consent of any
lenders with a
security over the
land).
 Any relevant
Lenders may be
reluctant to consent
to the Path
Agreement without
full assessment of
effect on value of
their security.
Section 21
Path
Agreement
 Land Reform
(Scotland) Act
2003, Section
21 
 The Council
may enter an
agreement
with the
landowner for
the
delineation,
creation and
maintenance
of a path
within the
landowner’s
land.
Therefore,
each required
agreement will
be subject to
negotiation
with each
landowner /
 Indeterminate,
dependent on
continued
goodwill and
determination
to make
progress.
 Collaborative
approach,
therefore
most likely to
ensure
continued
landowner
support.
 Section 21
provides a
structure for
negotiated
land access.
 Timescale depends
on continued
landowner goodwill.
 If unable to agree
land acquisition
then alternative
option will require to
be commenced.
 Dependent on no
title issues which
prevent the
landowner granting
a valid title in favour
of the Council
(including obtaining
the consent of any
lenders with a
security over the
land).
 Any relevant
Lenders may be
reluctant to consent
to the Path
Agreement without
full assessment of

Page 8

landowners
appointed
agent to
secure
voluntary
agreement.
effect on value of
their security.
Section 22
Path Order
 Land Reform
(Scotland) Act
2003
 Only where it
is
impracticable
for the Council
to enter into a
Path
Agreement
may the
Council make
a Path Order.
 6 months – 2+
years,
depending on if
any objections
lodged and
time taken by
legal process.
 If successful,
would
secure
access to
the
necessary
land.
 All land required
must be identified in
full prior to
commencing
process.
 Unable to amend
land required once
process
commenced.
 If secured, the Path
Order cannot be
amended.
Compulsory
Purchase
Order
 Land Reform
(Scotland) Act
2003 or
another
enabling act.
 6 months – 2+
years,
depending on if
any objections
lodged and
time taken by
legal process.
 If successful,
would
secure
access to
the
necessary
land.
 Permissible
to continue
negotiation
with
landowners
and any land
which is
successfully
acquired by
negotiation
could be
removed
from CPO
during
process.
 All land required
must be identified in
full prior to
commencing
process.
 Once process
commenced can
remove land from
process but not
add.
 Could be most
costly option, in
view of requirement
to advertise in local
and national
newspapers at
various stages in
the process and
also if hearing or
public local enquiry
should be required
by the Scottish
Ministers.
 Compensation paid
usually will be
market value of
land to be acquired
and any other
permitted losses. 
4.13. Negotiation; this approach to acquisition requires goodwill and willingness on the
part of both parties.  As there is no legal framework or set process for negotiation
and progress is based on the willingness of both parties, it is not possible to set a
specific timescale for land acquisition by negotiation.  Should a landowner decide
not to engage with a request for negotiation, or to withdraw from negotiation right

Page 9

up to the point of final transfer of the land, then another route to acquisition would
require to be sought. 
4.14. Section 21 Path Agreement; based on the negotiated approach but seeks to
secure the ability to construct/maintain the path over the landowners ground
voluntarily without full acquisition of the land.  If the land has and loan(s), e.g. a
mortgage, secured against the land the lender is likely to wish to assess how this
agreement would impact on the value of the land and likely require to be a
signatory to the agreement which could create additional cost and delay. As a
negotiation based approach, it is not possible to set a specific timescale for
securing agreement to a Section 21 Path Agreement.   
4.15. Section 22 Path Order; is an option available if it is impractical to secure a
Section 21 Path Agreement and requires the Council to consider the rights and
interests of the landowner as well as those of the public wishing to use the route
prior to deciding if a Section 22 Path Order is an appropriate approach.  Should it
be determined a Section 22 Path Order is an appropriate approach and
authorised by the full Council and/or the appropriate Committee, a submission
required to be lodged with the Scottish Government.  Should any objections be
submitted to the proposed Order, a Scottish Government Reporter will examine
the submission and objection(s) and make a recommendation to the Scottish
Government as to if the Order should be granted or not.  If the land has and
loan(s), e.g. a mortgage, secured against the land the lender is likely to wish to
assess how this agreement would impact on the value of the land and likely
require to be a signatory to the agreement which could create additional cost and
delay.  It is understood the Section 22 Path Order process can take from around
6 months if no objections are submitted, to in excess of 2 years where sustained
objections are submitted and a hearing is required; although Officers are aware
of only 3 such Orders having been granted two of which are in Highland Council
area. Given the external scrutiny, the submission of a request for a Section 22
Path order does not guarantee that it will be granted. 
4.16. As the Council has not previously sought to promote a Section 22 Path Order,
Officers believe a body of experience in relation to this has been built up in
Highland Council, who have had 2, out of a total of 3 in Scotland, Section 22 Path
Order approved by the Scottish Government. Seeking to understand Highland
Council’s experience with Section 22 Path Orders may provide a more detailed
understanding of the process. 
4.17. Compulsory Purchase Order (CPO) requires the Council to consider the rights
and interests of the landowner as well as those of the public wishing to use the
route prior to deciding if a CPO is an appropriate approach.  Should it be decided
a CPO may be an appropriate approach it requires approval of full Council and/or
the appropriate Committee prior to submission of application for an Order to
Scottish Government.  Prior to submission, a CPO requires all land to be clearly
identified and a clear justification why the public benefit from allowing the
acquisition of private outweighs the landowner’s right to their land.  This bar is
specifically set high to help protect the right of landowners to their property.  Given
the external scrutiny, the submission of a CPO does not guarantee that it will be
granted.

Page 10

4.18. Landowners have the opportunity to submit an objection to a CPO, which will be
taken into consideration by the Scottish Government Reporter in reaching their
recommendation.  Due to the potential for a hearing or public local enquiry and
requirement to advertise in local and national newspapers at various stages in
process a CPO can be a costly approach.  It is understood the CPO process can
take from around 6 months if no objections are submitted, to in excess of 2 years
where sustained objections are submitted and a hearing is required.  Should a
CPO be successful it would set a value to be paid for the land, based on market
value of the land and any permitted losses to the landowner, and the Council
would have a specific time period in which to make payment to the landowner(s)
and take possession of the land for its intended purpose. 
4.19. As the Council does not regularly promote CPOs and, to Officers knowledge, no
CPO has been promoted to date for an active travel route; it is understood that
Officers can seek guidance from Scottish Government civil servants on the
detailed process for the submission and determination of a CPO.  While seeking
this advice has no bearing on the decision make in relation to a CPO, it would
provide a more detailed understanding of the process in relation to an active travel
route. 
4.20. It is understood by Legal Services that the Scottish Government may take into
consideration that route based infrastructure, e.g. a road, requires the successful
acquisition of every section of land along the route for the delivery of the
infrastructure.  As a cyclepath is a piece of route based infrastructure, Officers
also require to establish if this will be taken into consideration in determining any
CPO submission. 
4.21. Table 2 outlines the options for future access/ownership models in relation to the
land the cyclepath will require to cross. 
Table 2: Future access / ownership models
Model Benefits Disbenefits
Path
Agreement
 No direct cost for land, albeit
landowner may seek
accommodation works
 Landowner retains ownership
 Only for set time period, will require further
agreements to retain in longer term.
 Landowner retains ownership and,
depending on conditions of agreement,
may have ability to limit path use and/or
terminate agreement.
Lease  Landowner retains ownership  Requires to be secured via negotiation
with landowner.
 Usually requires a payment to be made,
either capitalised or on annual basis.
 Only for set time period – likely to require
future payments to retain in longer term.
 Landowner retains ownership and,
depending on conditions of lease, may
have ability to limit path use and/or
terminate lease.

Page 11

Section 21  No direct cost for land, albeit
landowner may seek
accommodation works
 Landowner retains ownership
 Permanent
 Requires to be secured via negotiation
with landowner.
Section 22  No direct cost for land, albeit
landowner may seek
accommodation works
 Landowner retains ownership
 Permanent
 Legal process required which can take 6
months to 2+ years.
Servitude  Permanent  Requires to be secured via negotiation
with landowner.
 Usually requires a capitalised payment to
be made.
Purchase  Permanent  May require to be secured via negotiation
with landowner (voluntary purchase).
 Alternatively, a legal process may be
required (compulsory purchase), which
can take 6 months to 2+ years.
 Usually requires a capitalised payment to
be made. 
4.22. Path Agreement is a voluntary agreement to allow the construction, maintenance
and use of a path/cyclepath across the landowner’s land.  Path Agreements do
not result in any payment to the landowner.  A Path Agreement must include a
termination date, although this can be many decades in the future, as it cannot be
an agreement in perpetuity.  Most Path Agreements also include one or more
severance clauses that enable one or either party to terminate the agreement if
circumstances change. 
4.23. Lease is a voluntary agreement between the Council and the landowner to allow
the consultation, maintenance and use of a path/cyclepath and involves either a
single capitalised or regular, e.g. annual, payments for the agreement.  A Lease
must include a termination date, although this can be many decades in the future,
as it cannot be an agreement in perpetuity.  Most Leases also include one or more
severance clauses that enable one or either party to terminate the agreement if
circumstances change. 
4.24. Section 21 Path Agreement is a voluntary agreement to allow the construction,
maintenance and use of a path/cyclepath across the landowner’s land.  Section
21 Path Agreements do not result in any payment to the landowner.  A Section
21 Path Agreement cannot be revoked without a legal process. 
4.25. Section 22 Path Order is a compulsory process which enables the construction,
maintenance and use of a path/cyclepath across the landowner’s land.  Section
22 Path Orders do not result in any payment to the landowner.  A Section 22 Path
Order cannot be revoked without a legal process. 
4.26. Servitude is a legal right in perpetuity to access or cross land belonging to another
and recorded in title deeds.  In the case of a path, this could include the rights to
access, construct, maintain and/or utilise a path across another landowner’s land.

Page 12

A single capitalised payment may be made to secure a new servitude and, expect
in very specific circumstances, a servitude cannot be revoked without agreement
of both parties and/or a legal process. 
4.27. Purchase can be voluntary, e.g. by negotiation, or compulsory, e.g. following a
successful Compulsory Purchase Order.  Purchase is the permanent transfer of
land title from one landowner to another, in this case it would be from the private
landowner(s) to the Council, for which a single capitalised payment is usually
made. 
Programme 
4.28. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
4.29. Appendix 2 provides an update with regard to the current position on landowner
negotiations. [EXEMPT] 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the construction of further sections of the cycleway
following completion of design work and as and when land acquisition has been
concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on completing the design work, securing highly competitive external
challenge funding, committing appropriate match funding and securing access to
private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.

Page 13

6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
The Council has not contributed any funding to design
or capital costs.  There is strong evidence that people
who are more active, for example by walking or
cycling, have been physical and mental health and are
less likely to require social care services in later life
which could result in a future saving to the Council or
HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment
opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.

Page 14

6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None. 
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain 
28 August 2023                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Update on Land Negotiations for Helensburgh, Cardross and
Dumbarton Cyclepath [EXEMPT]