Page 1

Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme 
Activity
2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30
Q
1
Q
2
Q
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Funding Applications                                                        
Phase 1: Helensburgh to Cardross                                    
Route Design: Helensburgh to Cardross                                                        
Land Purchase Negotiations: Helensburgh to Cardross                                                        
CPO Process (if required):                                                        
- Provide CPO recommendation to H&L Area Committee                                        
- Develop CPO                                                       
- Gain Full Council approval for CPO                                                        
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                        
- CPO Process                                                        
Construction: Helensburgh to Cardross                                                        
Construction of Helensburgh to Cardross Phase 1
(Cardross Station to Geilston Burn)                                                        
Construction of Helensburgh to Cardross Phase 2
(assuming negotiated acquisition)                                                        
Construction of Helensburgh to Cardross Phase 3
(assuming Compulsory Purchase Order required)                                                        
Construction of Helensburgh to Cardross Phase 4
(assuming Compulsory Purchase Order required)                                                        
Phase 2: Cardross to Dumbarton                                    
Route Design: Cardross to Dumbarton                                                        
Land Purchase Negotiations: Cardross to Dumbarton                                                        
CPO Process (if required):                                                        
- Provide CPO recommendation to H&L Area Committee                                        
- Develop CPO                                                        
- Gain Full Council approval for CPO                                                        
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                        
- CPO Process                                                        
Construction: Cardross to Dumbarton                                                        
Construction of Cardross to Dumbarton Phase 1
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 2
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 3
(assuming Compulsory Purchase Order required)                                                        
Construction of Cardross to Dumbarton Phase 4
(assuming Compulsory Purchase Order required)                                                        
Helensburgh: Hermitage Academy to Town Centre                                    
Community Consultation & Route Identification                                    
Route Design                                    
Land Access Negotiations                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 1                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 2                                                         
Colour Key (Responsibilities / Lead): 
Green: Strategic Transportation 
Blue: Road Service 
Orange: Estates Service 
Red: Legal 
Purple: External to Council (e.g. Scottish Government)