20240312 HL Area Committee Cardross Cyclepath Update Report - Appendix 1 Programme of Work
Argyll and Bute Council · 12 March 2024
Back to Helensburgh & Lomond Area Committee — 12 March 2024 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme Activity 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 Q 1 Q 2 Q 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Funding Applications Phase 1: Helensburgh to Cardross Route Design: Helensburgh to Cardross Land Purchase Negotiations: Helensburgh to Cardross CPO Process (if required): - Provide CPO recommendation to H&L Area Committee - Develop CPO - Gain Full Council approval for CPO - Advertise CPO - Lodge CPO with Scottish Government - CPO Process Construction: Helensburgh to Cardross Construction of Helensburgh to Cardross Phase 1 (Cardross Station to Geilston Burn) Construction of Helensburgh to Cardross Phase 2 (assuming negotiated acquisition) Construction of Helensburgh to Cardross Phase 3 (assuming Compulsory Purchase Order required) Construction of Helensburgh to Cardross Phase 4 (assuming Compulsory Purchase Order required) Phase 2: Cardross to Dumbarton Route Design: Cardross to Dumbarton Land Purchase Negotiations: Cardross to Dumbarton CPO Process (if required): - Provide CPO recommendation to H&L Area Committee - Develop CPO - Gain Full Council approval for CPO - Advertise CPO - Lodge CPO with Scottish Government - CPO Process Construction: Cardross to Dumbarton Construction of Cardross to Dumbarton Phase 1 (assuming negotiated acquisition) Construction of Cardross to Dumbarton Phase 2 (assuming negotiated acquisition) Construction of Cardross to Dumbarton Phase 3 (assuming Compulsory Purchase Order required) Construction of Cardross to Dumbarton Phase 4 (assuming Compulsory Purchase Order required) Helensburgh: Hermitage Academy to Town Centre Community Consultation & Route Identification Route Design Land Access Negotiations Construction of route from Hermitage Academy to Helensburgh Town Centre Phase 1 Construction of route from Hermitage Academy to Helensburgh Town Centre Phase 2 Colour Key (Responsibilities / Lead): Green: Strategic Transportation Blue: Road Service Orange: Estates Service Red: Legal Purple: External to Council (e.g. Scottish Government)