ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
12 March 2024 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 12 December 2023 in relation
to the delivery of a dedicated, high quality walking and cycle path linking
Helensburgh, Cardross and Dumbarton.  The delivery of this path is a stated
Council Priority. 
1.2. Within Helensburgh Town (Phase 3), community engagement was undertaken
between 01 to 29 February 2024 to support identification of key locations to be
served and potential routes for the cycleway within the built up area of
Helensburgh.  An in-person drop-in session was held at the Market in
Colquhoun Sq on Sat 24 Feb for members of the public who wished to speak to
the design team face-to-face.  The design team also visited local schools to
speak to school pupils about the cycleway. 
1.3. WSP has agreed that 15 March 2024 will be the final termination date of their
current design contract for Phase 1 (Colgrain – Cardross) and Phase 2
(Cardross – Dumbarton).  At time of writing, Officers are working with WSP to
support them to complete as many of the contracted deliverables as is
reasonably achievable. 
1.4. Following 15 March, Officers will review the deliverables from WSP to (a) identify
any omissions or area requiring further work; and, (b) determine the best course
of action to continue to progress the design package to a final, deliverable stage. 
1.5. The Council can seek a Compulsory Purchase Order (CPO) for the proposed
route and is only in a position to do so once that route is fully defined. Once
the Council resolves to obtain a CPO, permission for that must ultimately be
authorised by Scottish Ministers.  If a CPO is authorised then the Council
must pay appropriate compensation. 
1.6. Where landowners are willing to agree on the acquisition and compensation
the CPO process can happen fairly quickly. Where a landowner(s) contest an
acquisition or CPO the process can take up to two or more years depending
on the complexity and whether and how the CPO is disputed by one or more
parties.

Page 2

1.7. The applications guidance for the new Transport Scotland Active Travel
Infrastructure Fund (ATIF) for construction projects states that all projects will
require some element of match funding.  However, the guidance does not specify
a minimum match funding percentage.    While the lack of a specific match funding
value to plan against is unhelpful, Officers understand that there is not an
expectation from Transport Scotland that match funding would exceed the 30%
required by the now terminated PFE Construction challenge fund.  Based this, it
is recommended Members plan based on the cyclepath requiring construction
match funding not exceeding £2M.  At present no construction match funding has
secured. 
1.8. As part of the final technical design, Sustrans PFE staff have requested a written
maintenance plan and confirmation of how this will be funded and delivered.  As
such, members require to decide how the future maintenance of the cyclepath,
including sections of route already in place, will be delivered.  At present, the
Council does not receive any funding for the maintenance of cyclepaths. 
1.9. The Roads and Infrastructure Service includes infrastructure maintenance teams
appropriately trained and qualified to undertake maintenance of cyclepaths.
However, it is acknowledged these teams are already near capacity delivering the
Roads and Infrastructure Service commitments, and the Roads and Infrastructure
Service has previously stated they do not wish to adopt sections of cyclepath
remote from the public road. 
1.10. Members may wish to consider if there is a role for local community group
volunteers to support the routine maintenance of the cyclepath, for example
annual vegetation maintenance.  Similar maintenance work is undertaken by
community groups for cyclepaths in other locations. 
RECOMMENDATIONS 
1.11. It is recommended that the Helensburgh and Lomond members: 
1.11.1.Welcome the community engagement to support the identification of a preferred
route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town
Centre/Waterfront. 
1.11.2.Instruct Officers to progress with review of deliverables received from WSP,
identification of outstanding requirements and to progress with securing these
deliverables including sourcing funding for these as appropriate. 
1.11.3.Consider the guidance from Legal Services in relation to CPO process and
timescales. 
1.11.4.Instruct Officers to submit a report to Council requesting approval for
development and submission of a CPO for all land required to construct and
maintain the preferred route alignment for the whole of Stage 1 (Colgrain to
Cardross) and Stage 2 (Cardross to Dumbarton) of the Helensburgh – Cardross 
Dumbarton Cyclepath.

Page 3

1.11.5.Consider how they can secure of match funding towards land acquisition and
construction of this priority project, including from internal Council sources. 
1.11.6.Consider future maintenance options for the cyclepath, including if there is a role
for community group volunteers.

Page 4

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
12 March 2024 
Helensburgh, Cardross and Dumbarton Cyclepath Update 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 12 December 2023 in relation to the delivery of a
dedicated, high quality walking and cycle path linking Helensburgh, Cardross
and Dumbarton.  The delivery of this path is a stated Council Priority. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome the community engagement to support the identification of a preferred
route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town
Centre/Waterfront. 
3.1.2. Instruct Officers to progress with review of deliverables received from WSP,
identification of outstanding requirements and to progress with securing these
deliverables including sourcing funding for these as appropriate. 
3.1.3. Consider the guidance from Legal Services in relation to CPO process and
timescales. 
3.1.4. Instruct Officers to submit a report to Council requesting approval for
development and submission of a CPO for all land required to construct and
maintain the preferred route alignment for the whole of Stage 1 (Colgrain to
Cardross) and Stage 2 (Cardross to Dumbarton) of the Helensburgh – Cardross 
Dumbarton Cyclepath. 
3.1.5. Consider how they can secure of match funding towards land acquisition and
construction of this priority project, including from internal Council sources. 
3.1.6. Consider future maintenance options for the cyclepath, including if there is a role
for community group volunteers. 
4.0 DETAIL

Page 5

4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. In 2023/24, to date the Active Travel Team secured £2.56M external funding for
the development and delivery of a total of 22 projects across Argyll and Bute,
including the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 18
separate competitive funding applications, to 5 separate funds. 
Funding 
4.3. Transport Scotland’s Places for Everyone (PFE) programme is the primary
external active travel design funding available in Scotland.  It is structured
around 8 project stages with a competitive challenge fund, with the 32 local
authorities, 7 regional transport partnerships, two national parks and numerous
community groups across Scotland competing against each other to secure the
funding each project requires. 
4.4. As of 2024/25, the construction element of the funding has been taken into a
separate competitive fund, Transport Scotland’s Active Travel Infrastructure
Fund (ATIF). ATIF still requires a separate competitive application to be
submitted but is, currently, only open for applications once a year.  All projects
submitted to ATIF must be ready in all respects to commence construction,
including having any legal or regulatory approvals required in place. 
4.5. A minimum of three new competitive funding submissions are required to
complete a project using external funding, with competitive applications required,
as a minimum, to PFE prior to Stage 0 (Strategic Definition) and Stage 3
(Developed Design) and to the new Transport Scotland ATIF prior to Stage 5
(Construction).  The project stages are (0) Strategic Definition, (1) Preparation
and Brief, (2) Concept Design), (3) Developed Design, (4) Technical Design, (5)
Construction, (6) Handover & Close Out, and (7) In Use. 
4.6. As briefed in the separate Active Travel Update Paper to this Committee,
Transport Scotland have informed local authorities that they plan to significantly
alter the model used to distribute active travel funding over the next 2 years.  It is
Officers understanding that the changes will result in some of the active travel
funding being included within the Council’s block grant allocation from Scottish
Government, with the remainder administered in the form of competitive
challenge funds primarily by Transport Scotland.  Officers also understand that
further funding changes in the later stages of the 2 year transition period will
favour those local authorities who choose to commit their active travel block
grant allocation in full to appropriate active travel projects. 
Match Funding 
4.7. The applications guidance for the new Transport Scotland Active Travel
Infrastructure Fund (ATIF) for construction ready projects states that all projects

Page 6

submitted for construction funding will require some element of match funding. 
However, the guidance does not specify a minimum match funding percentage. 
Rather it states that the ATIF team will engage during the assessment process
to determine the requirements for match funding. 
4.8. While the lack of a specific match funding value to plan against is unhelpful,
Officers understand that there is not an expectation from Transport Scotland that
match funding would exceed the 30% required by the now terminated PFE
Construction challenge fund.  Based on not exceeding the 30% value, it is
recommended Members plan based on the cyclepath requiring construction
match funding not exceeding £2M. 
4.9. Phasing construction over a number of financial years will enable maximisation of
suitable external match funding, however this will result in a longer construction
programme.  Accelerating the construction programme will require additional
match funding to be secured, from internal and/or external sources, which could
prove challenging given the current economic climate. 
4.10. At present no construction match funding has secured.  It is likely to be beneficial
to the project if sources of construction match funding could be secured at an early
stage, including consideration of any internal Council funds which could be
allocated to the delivery of this Council Priority. 
Maintenance 
4.11. Sustrans have requested a written maintenance plan and confirmation of how this
will be funded and delivered as a deliverable during the Stage 3 (Developed) and
Stage 4 (Technical) design process.  As such, members require to decide how
the future maintenance of the cyclepath, including sections of route already in
place, will be delivered.  At present, the Council does not receive any funding for
the maintenance of cyclepaths and none of the current external funding sources
secured through competitive bidding for active travel include maintenance as an
eligible cost.  This anomaly has been repeatedly raised by Officers with Transport
Scotland Officials and it is recognised to be inconsistent with the Scottish
Government’s commitments regarding capital funding for active travel projects. 
4.12. The Roads and Infrastructure Service are the single service within the Council
which includes infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths. However, it is acknowledged
these teams are already near capacity delivering the Roads and Infrastructure
Service commitments. The Roads and Infrastructure Service has previously
stated they do not wish to adopt sections of cyclepath remote from the public road. 
4.13. Members may wish to consider if there is a role for local community group
volunteers to support the routine maintenance of the cyclepath.  While unlikely to
be skilled or qualified for the less frequent ‘heavier’ technical maintenance of
drainage or path surfacing, community groups may be able and willing to assist
with the more routine elements of maintenance, for example annual vegetation
maintenance.  Similar maintenance work is undertaken by community groups for
cyclepaths in other locations.

Page 7

Design 
Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton 
4.14. WSP has agreed that 15 March 2024 will be the final termination date of their
current design contract for Phase 1 (Colgrain – Cardross) and Phase 2
(Cardross – Dumbarton).  WSP have provide an outline list of design outputs
which they don’t expect to deliver by 15 March.  As such, consideration will
require to be given as to how these design outputs can best be delivered to
enable the project to complete all required design stages. 
4.15. WSP have informed Officers that they don’t expect to complete the following
design outputs within the remaining time of their commission:
• Ground Investigation
• Habitats Regulation Appraisal
• Planning Application
• Utility C4
• Drainage Design
• Flood Risk Assessment
• Land valuation
• Archaeological Assessment 
4.16. It is also acknowledged that the scaling back of WSPs design outputs prior to
the termination date of their contract on 15 March 2024 will result in a hiatus in
relation to providing information requested by landowners including, for
example, detailed drainage designs.  Officers will be writing to affected
landowner to inform them of the termination of WSP as the design contractor
and that, once a new design team are in place, they will be in touch with
landowners to progress the discussions. 
4.17. While the design work has, to date, been funded by jointly by the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s
PFE programme, the decision to de-fund the SPT Capital Programme in 24/25
results in the project being fully reliant on securing 24/25 PFE funding or internal
Council funding in order to complete the outstanding design requirements. 
Phase 3 Helensburgh Town 
4.18. An online community engagement was held between 1 to 29 February 2024 to
help identify a preferred route linking the existing cyclepath at Morrisons
Supermarket / Hermitage Academy to Helensburgh Town Centre and the new
section of segregated cycleway at Helensburgh Waterfront, and to identify the
most appropriate locations in Helensburgh which the route should seek to serve
to best meet community needs.  An in-person event was held at the
Helensburgh Market on Saturday 24 February with Civic Engineers design team
and Council Officers in attendance. 
4.19. While the design work has, to date, been funded by jointly by the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s

Page 8

PFE programme, the decision to de-fund the SPT Capital Programme in 24/25
results in the project being fully reliant on securing 24/25 PFE funding or internal
Council funding in order to complete the outstanding design requirements. 
Construction (stage 5) 
Cardross Rail Station to Geilston Burn 
4.20. Cardross Rail Station to Geilston Burn.  The Council’s Roads and Infrastructure
Service have completed installation of most elements of the cyclepath through
Cardross Park, with only a small amount of fencing still to be installed. 
4.21. With the changes to the active travel funding model for 24/25 onwards, it is
expected that the costs for the remaining fencing work will require to be covered
from, as yet to be identified, internal Council budgets. 
4.22. To protect the public, the bridge over the Geilston Burn has been fenced off until
access is agreed to further land on the west side of the Burn to construct the
path through to an accessible destination. 
Land Acquisition 
4.23. The Council can seek a Compulsory Purchase Order (CPO) for the proposed
route and is only in a position to do so once that route is fully defined. Once
the Council resolves to obtain a CPO, permission for that must ultimately be
authorised by Scottish Ministers. Thus, the Council cannot unilaterally utilise
their compulsory purchase powers. If a CPO is authorised then the Council
must pay appropriate compensation, but it can take both legal and physical
possession of the property before agreement on the amount of compensation
to be paid is reached or determined by the Lands Tribunal where this is
disputed. Possession can only be obtained if:
• The compulsory purchase is confirmed (i.e. approved) by Ministers;
• Any legal challenge to the compulsory purchase has been exhausted;
and
• The Council has served formal notices taking ownership or access.
• There are limited grounds on which an objection to a CPO can be made.
If objections are made then it is for Scottish Ministers to determine
whether to hold an inquiry before an independent reporter. In the event
that the order is subsequently confirmed by Scottish Ministers then there
is a six week period within which the validity of the order may be
challenged in the Court of Session. 
4.24. The whole CPO process can happen fairly quickly, where there are parties
willing to agree on the acquisition and compensation. In this case the Council
is dealing with a number of landowners (12 in total) and the Service is aware
of some who have already indicated their intention to contest any acquisition
or CPO. In that case the matter can take up to two or more years depending
on the complexity and whether and how the matter is disputed by one or more
parties.

Page 9

4.25. Once a CPO is made then it must be used within a limited time, usually three
years, otherwise it will expire. 
Risk 
4.26. Risk refers to events which have not yet happened but which could impact on
the project if they were to happen.  A risk can be negative or positive to the
project.  Risks are identified through the lifetime of the project and, where
possible, mitigation is planned to minimise negative impacts or maximise
positive impacts.  As risks evolve relatively slowly through the lifetime of a
project, it is not expect that the tables below will alter significantly within the
current stage of work. 
4.27. Project risks relate to risks which could affect the overall project.  Table 1
provides the top 5 identified project risks and planned mitigation 
Table 1: Selected Project Risks
Risk Risk Description Risk Level Mitigation
Land
acquisition
Inability to secure
agreement for land required
within an acceptable
timescale and cost.
High 1. Engagement with landowners to
gain acceptance of design.
2. Use of Council’s Estates Team to
lead land acquisition.
3. Consideration of option of a CPO.
Funding Inability to secure necessary
funding to pay of either (a)
design work; and/or, (b)
construction costs.
Medium 1. Close engagement with external
funders to ensure project meets
their funding requirements.
2. Officers continue to explore
potential alternative funding
sources.
3. Early engagement with Members
to identify potential sources of
construction match funding.
Programme Inability to meet challenging
programme timeline.
Medium 1. Regular review of programme.
2. Work with key stakeholders to
understand programme drivers
and barriers.
3. Establish realistic timescales for
each package of work.
Community
support
Loss of community support
for the project.
Low 1. Consult the community on key
design decisions as appropriate.
2. Seek to deliver project which
meets community’s key
requirements.
3. Keep community informed via
project updates at appropriate
times, including publicly available
quarterly committee reports.
Funder
requirements
Failure to meet external
funder requirements,
thereby losing funding.
Low 1. Engage with funders to fully
understand their requirements.
2. Ensure project outcomes/outputs
meet funders’ requirements.
3. Review funding options regularly to
ensure funding sought/secured is
most appropriate to the project.

Page 10

4.28. Design risk refers to risk that the design fail to meet the required standards
and/or design conditions imposed by external factors, for example
environmental requirements. Design risks, if allowed to occur, can become
issues which may mean the project design has to be changed, which can
cause delays and cost increases. Defects or failures in the design can also
result in an increase in future maintenance costs.  Table 1 provides the top 5
identified design risks and planned mitigation. 
Table 2: Selected Design Risks
Risk Risk Description Risk Level Mitigation
Ground
Conditions
Lack of Ground
Investigation (GI) limits
understanding of the
ground conditions the
route will be constructed
over.
High 1. Design route to be as robust as
practicable.
2. Undertake Ground Investigation
works at earliest practicable date.
Ecological
Impacts
Working adjacent to the
Inner Clyde SSSI and
RAMSAR site results in
additional ecological
requirements which the
designs must meet. 
High 1. Engage with regulators, e.g.
NatureScot, at early stage in design.
2. Undertake comprehensive
ecological surveys to inform design.
3. Develop full Habitat Regulations
Appraisal to ensure ecological
requirements taken into account in
design.
Drainage Constructed at the foot of
the slope, the design will
require to cater for all run-
off and drainage from the
slopes above, while
satisfying regulatory
requirements.
Medium 1. Develop drainage designs through
design process.
2. Engage with regulators, e.g. SEPA,
at early stage in design.
3. Engage with landowners, as
repository of knowledge of existing
conditions, during design
development.
Flood Risk The route is close to and,
in locations, within areas
identified as at risk from 1
in 200 year flood events.
Medium 1. Develop flood risk assessment at
early stage in design process to
identify key areas of risk.
2. Keep flood risk assessment under
review through design process.
3. Design of cyclepath to take account
of flood risk where appropriate.
Proximity to
railway
The majority of the route is
in proximity to the live
railway and requires to
ensure the designs do not
negatively impact on the
railway.
Medium 1. Early engagement with Network Rail
to understand their safety and
operational requirements.
2. Seek to agree ‘standard’ approach
to mitigating safety and operation
requirements which can be applied
to all or most of route.
3. Review of designs to ensure railway
safety and operational risk is
mitigated appropriately. 
Programme 
4.29. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre.

Page 11

5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the design and construction of further sections of the
cycleway as and when land acquisition has been concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on completing the design work, securing highly competitive external
challenge funding, committing appropriate match funding and securing access to
private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
External funding is not currently available to cover
maintenance costs.  To date, the Council has not
contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to
require social care services in later life which could
result in a future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton

Page 12

corridor to travel more sustainably and actively by
walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment
opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.
6.9. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates even stronger
support for the delivery of the Helensburgh – Cardross
– Dumbarton Cyclepath from younger members of the
community than the already high overall level of
community support. Wider engagement with school
pupils indicates that the vast majority of pupils strongly
support the provision of new active travel
infrastructure, even where it would adversely impact
other modes of transport.

Page 13

Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead: Cllr Andrew Kain 
07 February 2024                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme