Downing Renewable Developments: Installation of Battery Energy Storage System (Bess) and Associated Infrastructure: Land West of Taynuilt Substation, Taynuilt (Ref: 24/02083/Pp)

Argyll and Bute Council · 18 June 2025
Back to Planning, Protective Services and Licensing Committee — 18 June 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
Argyll and Bute Council
Development & Economic Growth   
Planning Application Report and Report of Handling as required by Schedule 2 of the
Town and Country Planning (Development Management Procedure) (Scotland)
Regulations 2013 relative to applications for Planning Permission or Planning
Permission in Principle 
Reference No: 24/02083/PP
Planning Hierarchy: Major Application
Applicant: Downing Renewable Developments
Proposal: Installation of battery energy storage system (BESS) and associated
infrastructure
Site Address:  Land West Of Taynuilt Substation, Taynuilt  
DECISION ROUTE 
☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997 
☒Committee - Local Government Scotland Act 1973 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission 
• Formation of substation compound 
• Installation of Battery Energy Storage Units (within containers) to not exceed
49.9Mw export capacity
• Installation of on-site substation
• Installation of inverters
• Installation of water tank
• Erection of fences (weld and palisade) and entrance gate
• Installation of welfare facility container
• Installation of CCTV and lighting
• Installation of other incidental plant and machinery
• Formation of access   
(ii) Other specified operations
• Landscaping
• Installation of underground cabling
• Installation of drainage infrastructure 
(B) RECOMMENDATION: 
It is recommended that Planning Permission be approved subject to conditions for the
reasons detailed in this report. 
(C) CONSULTATIONS:   
A&B Environmental Health: (Dated 16.01.25, 03.03.25 & 12.05.25): No objection

Page 2

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
A&B Flooding and Drainage: (Dated 24.12.24). No objection  
A&B Biodiversity Officer : (Dated 29.06.25) No objection. 
NatureScot (Dated 23.05.25) No Objection – Appropriate Assessment required in
respect of Loch Etive Woods Special Area of Conservation.
Scottish Fire and Rescue (Dated 9.1.25) No Objection (Draft advice from National Fire
Chiefs Council provided). 
Trunk Road Authority (Dated 17.12.24): No objection subject to conditions.
Taynuilt CC Dated (02.04.25) : Objection based upon
• Environmental Impacts
• Undesirable Precedent
• Noise
• Fire Risk
• Inadequate drainage and containment
• Substandard Site Access
• Impact on Surrounding Infrastructure
Oban Community Council : (Dated 30.01.25)  Objection/Concerns 
Proposals do not appear to conform to draft guidance form Scottish Fire and Rescue
Service. Recognising BESS systems in Scotland are still in their infancy, a more
detailed and comprehensive risk analysis covering construction, operation and
decommissioning of the facility should be provided as a single document to the Local
Authority before permission is granted
SSEN Electricity Networks: (Dated 31.12.24) No Objection. Request access
condition/control and informative related to existing substation access.
Network Rail : No response 
(D) HISTORY:  
24/00287/PAN:  Installation of 49.9Mw Battery Energy Storage System
23/02451/SCREEN: Installation of 49.9Mw Battery Energy Storage System. (No EIA
required). 
(E) PUBLICITY:  Yes :  Reg 20  Press Notice. Expired 09.01.25   
(F) REPRESENTATIONS:  Yes 
The application at time of writing has received 135 Objections, 1 submission in Support and 4
Representations. A full list of these is contained at Appendix B of this Report.  All third-party
submissions are published in full on the planning application file and are available to view via
the Public Access section of the Council’s website under the application reference number. 
(i) Summary of matters in Submission of Support
• Proposal should be fully supported if we want to have a greener future
• Battery Energy Storage an essential part of green energy delivery
• Site selection process supports the choice of the current site 
(ii) Summary of matters raised in Representations 
•   If project is to proceed should comply with National Fire Chiefs Council guidance
• Scottish Fire and Rescue Service advice should also be followed by scheme
• Local concerns should be acknowledged but electricity is a fundamental requirement
and sustainable energy generation is the way forward.

Page 3

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
• Local weather topography wind direction and land use are all pertinent considerations
to risks from such proposals, but other large roadside BESS schemes are being
developed in Scotland. 
• Road and rail links are already not infrequently blocked on occasions by accidents,
weather and land movements.
• Acknowledge the decision-making process by applicant through site selection report
• Biodiversity net gain planting should be expanded over the whole site except the
compound, this would also assist in containing noise and minimising visual disturbance.
• Site has been considered to reduce its impact. There are limited opportunities to mitigate
certain risks of development
• Noise evaluation and proposed actions are not robust
• BESS technology is in its infancy and technology is advancing 
(iii) Summary of Objections raised:
• Development will detract from quality of landscape and visual amenity of the area.
• There are no acceptable solutions to decommissioning, operation and maintenance,
decommissioning and emergency event planning provided in support of the application
• The application does not give details of the specification of the battery technology that
will actually be installed at the site.
• Battery storage should be installed beside windfarms and not villages
• Applicant has not provided satisfactory reassurances on what would happen if the
company that owned/leased the site went bankrupt and who would be responsible for
the upkeep/safe mothballing of site.
• Proposals would cause unacceptable noise impact on residents
• No information on historic flooding has been provided by applicant
• The risks associated with the proposal outweigh the benefits of the proposal
• The Scottish Fire and Rescue Service should review the detailed design of the facility
before it is constructed to make sure it can meet required safety standards at time of
construction as these are evolving.  Updated 2025 advice from the National Association
of Fire Chiefs is expected.
• Proposed lighting would be detrimental to a dark sky area at night
• The developer has failed to provide sufficient information to address low frequency noise
impact on residents and surrounding properties 
Officer Comment: The objections as set out above are considered as material planning
considerations and these matters are addressed in the Officer report. However, the
following matters do not relate directly to planning considerations and are therefore not
considered to carry any substantive weight  in the determination of the proposals as set out
below; 
• There is a fire risk and health and safety issue due to toxic gasses released in the event
of a fire
• No risk analysis of the proposals has been provided
• Leakage of water from the site used on any fire would allow pollutants into the water
environment causing environmental harm. Similarly, a battery leakage would also harm
the general and water environment
• Proposal will have economic and wellbeing impacts on adjoining properties
• A fire would require the closure of the A85 and railway line
• Concerned not enough water in onsite water tank to deal with a fire
• Concerned not enough fire engines and firemen to deal with industrial scale fire
• Use of the land for BESS contrary to Crofting Legislation
• Will do little for village but make profits for shareholders

Page 4

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
• Local Area already makes more than its fair contribution to climate emergency from
Windfarms, Cruachan Pump Hydro etc. Taynuilt substation runs off Cruachan pumped
storage so why is battery storage required when Cruachan is already the storage.
• Proposals contrary to Article 2 of the Human Rights Act 1998.
• Guarantees wanted that scheme will not impact on insurance premiums of adjoining
houses
• Lithium used in the batteries is extremely hazardous to the environment Battery
Leakage would cause unacceptable pollution to River Awe, Loch Awe and flora and
fauna. More environmentally acceptable battery technologies are available and should
be used such as Vanadium redox flow batteries.
• Development should commit to community gain financial payment i.e. per MW Hr or a
percentage of profits made.
• The sector is not well regulated and there is a need for more planning and
environmental guidance
• Two fires in Taynuilt have been beyond the capabilities of local fire service in recent
years.
• Carbon footprint of the manufacturing of the equipment makes timescale for net zero
to be some 30 yrs operation. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Impact
Assessment Report:
☐Yes ☒No 
(ii) An Appropriate Assessment
under the Conservation (Natural
Habitats) Regulations 1994:   
See Appendix C of this report
☒Yes ☐No 
(iii) A Design or Design/Access
statement:   
☒Yes ☐No 
(iv) Sustainability Checklists (with reference to the requirements of LDP2
Policy 04) 
TN06 Sustainability Checklist
TN07 Sustainable Buildings
Checklist
☒Yes ☐No
☐Yes ☒No  
(v) A report on the impact of the
proposed development e.g. Retail
impact, transport impact, noise
impact, flood risk, drainage
impact etc:  
☒Yes ☐No 
• Battery Energy Storage
Technical Statement
• Construction Traffic
Management Plan
• Economic Benefit Statement
• Site Selection Report
• Flood Risk Assessment and
Drainage Strategy
• Heritage Statement
• Landscape and Visual Appraisal

Page 5

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
• Noise Impact Assessment
• PAC Report
• Planning Design and Access
Statement
• Ecological Appraisal
• Environmental Site Assessment 
Following initial submissions, the
applicants have submitted further
supporting information as set out below: 
• Updated Noise Impact
Assessment Information dated
14.04.25 
• Response to matters raised in
objections dated 19.02.25 
• Updated Ecology Report/Otter
Survey dated 15.04.25 
• Further Supporting submission on
case and alterations made to
address concerns dated 25.04.25 
• Revised Site Layout Plan 
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   ☐Yes ☒No 
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30, 31
or 32:  ☐Yes ☒No 
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application. 
(i)  List of all Development Plan Policy considerations taken into account in
assessment of the application. 
National Planning Framework 4 (Adopted 13th February 2023) 
Part 2 – National Planning Policy 
Sustainable Places
NPF4 Policy 1 – Tackling the Climate and Nature Crises
NPF4 Policy 3 – Biodiversity

Page 6

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
NPF4 Policy 4 – Natural Places  
NPF4 Policy 7 – Historic Assets and Places
NPF4 Policy 11 – Energy 
Liveable Places
NPF4 Policy 23 – Health and Safety (Criteria e - Noise) 
Productive Places
NPF4 Policy 25 – Community Wealth Building
NPF4 Policy 29 – Rural Development 
Argyll and Bute Local Development Plan 2 (Adopted 2024) 
Spatial and Settlement Strategy
Policy 02 – Outwith Settlement Areas 
High Quality Places
Policy 08 – Sustainable Siting
Policy 10 – Design – All Development
Policy 14 – Bad Neighbour Development 
Policy 15 – Protection, Conservation and Enhancement of Our Historic Environment 
Diverse and Sustainable Economy
Policy 30 – The Sustainable Growth of Renewables 
Connected Places
Policy 35 - – Design of New and Existing, Public Roads and Private Access Regimes
Policy 37 – Development Utilising an Existing Private Access or Existing Private        
Road
Policy 39 – Construction Standards for Private Access 
Sustainable Communities
Policy 55 – Flooding
Policy 59 - Water Quality and the Environment
Policy 61 – Sustainable Urban Drainage Systems (SUDS)
Policy 62 – Drainage Impact Assessments 
High Quality Environment
Policy 73 – Development Impact on Habitats, Species and Biodiversity.
Policy 74 – Development Impact on Sites of International Importance 
Local Development Plan 2 Schedules 
(ii)  List of all other material planning considerations taken into account in the
assessment of the application, having due regard to Annex A of Circular
3/2013. 
• Scottish Energy Strategy: The future of energy in Scotland (“the Energy
Strategy”) Draft Scottish Energy Strategy and Just Transition Plan 2023
• Scottish Government Climate Change Plan
• Draft National Fire Chiefs Council Guidance (in respect of access, water tank
design/size and site layout/design matters only)
•  Bat Conservation Trust publication “Bats and Artificial Lighting in the UK'
Guidance Note GN 08 / 23”

Page 7

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
• SEPA’s guidance - Battery Energy Storage Systems | Scottish Environment
Protection Agency (SEPA) 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental Impact
Assessment:  ☒Yes A negative screening opinion has been issued ref.:
24/00674/SCREEN.    
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  ☒Yes   
PAC Report Submitted with application. Report states main issues identified through
Community Consultation exercise are reported as set out below by topic Full information
can be found at Section 5 of the PAC report: 
• Name of development
• Safety of batteries, including fire risk; 
• Road Safety; 
• Noise levels; 
• Community benefit
• Visual impact; 
• Proximity to residential Dwellings 
(M) Does the Council have an interest in the site:  ☐Yes ☒No 
(N) Requirement for a pre-determination hearing: ☐Yes ☒No 
Although the application has attracted 135 letters of objection, it is considered that Members
have sufficient information within the report and supporting documentation on public access to
enable them to determine this application and properly evaluate the application against the
statutory planning framework having regard to any other material planning considerations.
Many of the objections submitted relate to fire safety and other pollution control matters which
are controlled through other legislation and regulation, not through the planning system. Those
concerns which are material planning considerations are considered to have been adequately
addressed in the Officer report. It is therefore not considered by Officers’ that a pre-
determination Hearing would add value to the determination process. 
(O)(i) Key Constraints/Designations Affected by the Development: 
(O)(ii) Soils
Agricultural Land Classification:  Class  4.2 Grazing Land
Peatland/Carbon Rich Soils
Classification:
☐Class 1
☐Class 2
☐Class 3
☒N/A Class 4
Peat Depth Classification:  N/A

Page 8

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Does the development relate to croft
land?
☐Yes ☒No
Would the development restrict
access to croft or better quality
agricultural land?
☐Yes ☒No ☐N/A
Would the development result in
fragmentation of croft / better quality
agricultural land?
☐Yes ☒No ☐N/A 
(O)(iii) Woodland  
Will the proposal result in loss of
trees/woodland?
(If yes, detail in summary
assessment)
☐Yes
☒No
Existing periphery trees to be protected and retained.
Does the proposal include any
replacement or compensatory
planting?
☒Yes Landscaping Mitigation Plan 
☐No details to be secured by condition
☐N/A  
(O)(iv) Land Status / LDP Settlement Strategy
Status of Land within the Application  ☐Brownfield
☐Brownfield Reclaimed by Nature
☒Greenfield 
ABC LDP2 Settlement Strategy
(tick all relevant boxes) 
☐Settlement Area
☒Countryside Area (Lorn and Inner
Isles)
☐Remote Countryside Area
☐Helensburgh & Lomond Greenbelt
ABC LDP2 Allocations/PDAs/AFAs etc: 
N/A 
(P) Summary assessment and summary of determining issues and material
considerations 
The proposal is for essential energy infrastructure which contributes to addressing the Climate
emergency and the objectives of NPF4 Policy 1. It must be acknowledged in the decision-
making process that there is strong policy support for such proposals, it is  important that the
policy support for such proposals is also considered as set out in LDP2 Policy 30 and NPF 4
Policy 11 in coming to a planning decision in this case. 
Officers consider that the site location is acceptable and subject to;  
• Enhanced landscape/biodiversity planting,
• A condition to safeguard residential amenity from noise, 
• An appropriate plan and financial mechanism for decommissioning/ restoration being
secured and 
• The access and site layout requirements of the Scottish Fire and Rescue Service to be
approved before construction begins.

Page 9

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Officers are therefore of the opinion that subject to the imposition of appropriate conditions that
the BESS proposal is in accordance with the policies of the development plan as set out in this
report, and no reason to warrant refusal of the application has been identified.   
(Q) Is the proposal consistent with the Development Plan: ☒Yes ☐No 
(R) Reasons why Planning Permission or Planning Permission in Principle Should be
Refused: N/A 
(S) Reasoned justification for a departure to the provisions of the Development Plan:
NA 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland: ☐
Yes ☒No 
Author of Report: David Moore Date: 29.05.2025 
Reviewing Officer: Sandra Davies Date: 03.06.2025 
Fergus Murray
Head of Development & Economic Growth

Page 10

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 24/02083/PP 
Standard Condition on Soil Management During Construction 
Additional Conditions 
1. PP - Approved Details & Standard Notes: Non-EIA Development 
The development shall be implemented in accordance with the details specified on
the application form dated 19.11.24, supporting information and, the approved
drawings listed in the table below unless the prior written approval of the planning
authority is obtained for an amendment to the approved details under Section 64 of
the Town and Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Existing Location Plan 1:1250 C 20.11.24
Existing Site Plan 1:500 C 20.11.24
Proposed Location Plan 1:1250 C 20.11.24
Indicative Layout Drawing 1:1250 D 14.04.25
Equipment Storage Container
Details
1:25 A 02.12.24
Equipment Drawing Layout 1:125 A 02.12.24
Supplementary Location Plan 1:10,000  02.12.24
Switchgear Building (1 of 2) GCS0015-1 7 02.12.24
Switchgear Building (2 of 2) GCS0015-2 7 02.12.24
BESS Container, Spares
Container and Switchgear Details
1:25 A 09.12.24
Welfare Facilities Container 1:25 A 09.12.24
Inverter Details 1:25 A 09.12.24
Water Storage Tank Details 1:50 A 09.12.24
Weld Mesh Fencing Details 1:25 A 09.12.24
Palisade Fence Details 1:25 A 09.12.24
Temporary Construction
Compound Layout
1:50 A 09.12.24
Miscellaneous Equipment Details A1 A 09.12.24 
Reason: For the purpose of clarity, to ensure that the development is implemented
in accordance with the approved details. 
2. Time Limit of the permission 
The Commencement of the Development shall be no later than five years from date
of this consent. 
Reason: To ensure that the development is commenced within a reasonable period
and having regard to the delivery time uncertainties of other necessary grid
infrastructure upgrades outside the control of the applicant.  
3. Landscaping, Biodiversity and Tree Protection 
(1) Notwithstanding the submitted details, prior to the commencement of
Development a Landscaping and Biodiversity Enhancement Plan shall be submitted

Page 11

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
for the written approval of the Planning Authority in accordance with the
requirements of NPF 4 Policy 3. 
(2) The scheme shall comprise a planting and tree maintenance and retention plan
and schedule which shall include details of: 
i) Existing and proposed ground levels in relation to an identified fixed datum; 
ii) a scheme for the retention and safeguarding of existing boundary trees during
construction. The scheme shall comprise: 
• A programme of measures for the protection of existing trees during
construction works which shall include fencing at least one metre beyond the
canopy spread of each tree in accordance with BS 5837:2012 “Trees in
Relation to Construction”. 
• Tree protection measures shall be implemented for the full duration of
construction works in accordance with the duly approved scheme. No trees
shall be lopped, topped or felled other than in accordance with the details of
the approved scheme unless otherwise approved in writing by the Planning
Authority. 
iii)  All existing landscaping features and vegetation to be retained; 
iv) Proposed soft and hard landscaping works including the location, species and 
size of every tree/shrub to be planted; 
v) A programme for the timing, method of implementation, completion and 
subsequent on-going maintenance. 
vi) A biodiversity net gain evaluation of the proposals 
All of the hard and soft landscaping works shall be carried out in accordance with
the approved scheme unless as otherwise may approved in writing by the Planning
Authority. 
(3) That all works included in any scheme of landscaping and planting should be
completed in accordance with the details of said plan and an agreed phasing and
implementation timetable. 
(4) Within 5 years following the completion of the development of any trees, shrubs,
or areas of grass which die, are removed, damaged or become diseased shall be
replaced within the following year with others of a similar size and species.
Thereafter details of a maintenance programme shall be provided for the future
management of the landscaping to ensure its long-term retention and health. 
Reason: To ensure appropriate landscape integration and biodiversity enhancement
are achieved. 
4. Drainage 
(1) All drainage works shall be carried out in accordance with the details submitted
within the submitted Flood Risk Assessment and Surface Water Drainage Strategy
Document, dated Nov 2024 or as may otherwise be agreed in writing by the Planning
Authority in consultation with its drainage and flooding advisor.

Page 12

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
(2) Any proposed watercourse crossings that are added or upgraded should be 
designed to convey the 1 in 200 year plus climate change (46% allowance) flood
event unless otherwise be agreed in writing by the Planning Authority in consultation
with its drainage and flooding advisor, or otherwise not decrease the existing
channel capacity. 
Reason: To ensure necessary standards are achieved and the proposals are
implemented in accordance with the submitted and approved details. 
5. Details of the BESS Technology to be used 
1) There shall be no Commencement of the Development unless and until details of
the storage technology and approved layout to be implemented, including final
details of access, site layout and water supply for emergency services, have been
submitted to and approved in writing by the Planning Authority in consultation with
the Scottish Fire and Protection Service. The storage technology details and
infrastructure, including the battery storage units to be deployed, shall be consistent
in scale and appearance with the submitted application parameters. 
(2) Thereafter, the Development shall be installed and maintained in accordance
with the approved details, unless otherwise agreed in writing by the Planning
Authority in consultation with the Scottish Fire and Rescue Service. 
Reason: In the interests of protecting the environment and visual amenity. 
6. Archaeology 
No development shall take place within the development site as outlined red in the
approved plan until the developer has secured the implementation of a programme
of archaeological works in accordance with a scheme of investigation which has
been submitted by the applicant, agreed by the West of Scotland Archaeological
Service, and approved by the Planning Authority. Thereafter the developer shall
ensure that the programme of archaeological works is fully implemented and that all
recording and recovery of Archaeological resources within the development site is
undertaken to the satisfaction of the Planning Authority in agreement with the West
of Scotland Archaeological Service. 
Reason: To safeguard archaeological Interests 
7. Trunk Road Access Arrangements 
a) Prior to the Commencement of development, the existing access on the A85
Trunk Road shall be upgraded and necessary visibility splays to be provided in  
accordance with drawing No. Fig 3.1 Dated 25/09/24 within the Construction Traffic
Management Plan, to the satisfaction of the Planning Authority in consultation with
Transport Scotland unless as otherwise may be agreed by Transport Scotland. 
b) There shall be no drainage connections to the trunk road drainage systems.  
Reasons: To ensure compliance with access standards and layout requirements in
the interests of Traffic Safety on the Trunk Road Network and to ensure the trunk
road drainage network is not impacted by the development. 
8. Construction Traffic Management Plan

Page 13

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Prior to the commencement of development, a finalised Construction Traffic Plan
shall be submitted to the Planning Authority for its approval in consultation with
Transport Scotland. The development shall thereafter be undertaken in accordance
with the details contained within the approved Construction Traffic Management
Plan unless as otherwise agreed in writing by the Planning Authority in consultation
withTransport Scotland. 
Reason: To ensure that the construction of the development does not unacceptably
interfere with the continued effective and safe operation of the Trunk Road and other
essential adjacent SSEN electricity grid infrastructure. 
9. Secondary Access Operational Use Agreement 
Prior to the commencement of development, the applicant shall provide to the
Planning Authority evidence of any required written agreement of Scottish and
Southern Energy Networks (or any necessary legal easement) related to the 
proposed use of the existing substation access associated with the construction or
operation of the approved Battery Energy Storage System. 
Reason: To ensure that the construction or operation of the development does not
unacceptably interfere with the continued effective and safe servicing and operation
of adjacent essential electricity grid infrastructure. 
10. Site Decommissioning, Restoration and Aftercare 
(1) The Development will disconnect from the grid and cease to import or export
electricity no later than the date falling forty years from the date of final
commissioning. The total period for decommissioning and restoration of the
site in accordance with this condition shall not exceed forty-two years from
the date of final commissioning without prior written approval of the Planning
Authority. 
(2) No Development shall commence until a decommissioning, restoration and
aftercare plan (including costings) have been submitted to and approved in
writing by the Planning Authority. 
(3) The detailed decommissioning, restoration and aftercare plan, shall provide
detailed proposals for the removal of the Development, the treatment of
ground surfaces, the management and timing of the works and environment
management provisions which shall include: 
a. a site waste management plan (dealing with all aspects of waste produced
during the decommissioning, restoration and aftercare phases); to include
the items listed in the CEMP site waste plan; 
b. details of the formation of the construction compound, welfare facilities, any
areas of hardstanding, turning areas, internal access tracks, car parking,
material stockpiles, oil storage, lighting columns, and any construction
compound boundary fencing; 
c. a dust management plan; 
d. details of measures to be taken to prevent loose or deleterious material being
deposited on the road network including wheel cleaning and lorry sheeting

Page 14

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
facilities, and measures to clean the site entrances and the adjacent local
road network; 
e. a pollution prevention and control method statement, including arrangements
for the storage and management of oil and fuel on the site; 
f. soil restoration; 
g. a surface water and groundwater management and treatment plan, including
details of the separation of clean and dirty water drains 
h.  any sewage disposal and treatment; 
i. temporary site illumination; 
j. the construction of any temporary access into the site and the creation and
maintenance of associated visibility splays; 
k. details of any watercourse crossings; 
l. a species protection plan based on surveys for protected species (including
birds) carried out no longer than 18 months prior to submission of the plan; 
m. traffic management plan; 
n. timetable for decommissioning and restoration which period shall not exceed
two years unless otherwise agreed in writing by the Planning Authority; 
o. Restoration Layout Plan showing the indicative final restored layout including
agricultural grade land, and which shall include restoration of the topography
which existed prior to the commencement of the development unless otherwise
agreed with the Planning Authority; and 
p. The Development shall be decommissioned, the site restored, and aftercare
thereafter undertaken in accordance with the approved detailed
decommissioning, restoration and aftercare plan, unless otherwise agreed in
writing in advance with the Planning Authority. 
Reason: To ensure the decommissioning and removal of the development in an
appropriate and environmentally acceptable manner and the restoration and
aftercare of the site, in the interests of safety, amenity and environmental protection 
11. Financial Guarantee 
(1) There shall be no commencement of development until a bond or other form of
financial guarantee in terms which secures the cost of performance of all
decommissioning, restoration and aftercare obligations referred to in condition 10
has been submitted to and approved in writing by the Planning Authority. 
(2) The value of the financial guarantee shall be agreed between the Company and
the Planning Authority or, failing agreement, determined (on application by either
party) by a suitably qualified independent professional as being sufficient to meet
the costs of all decommissioning, restoration and aftercare obligations referred to in
condition 10.

Page 15

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
(3) The financial guarantee shall be maintained in favour of the Planning Authority
until the completion of all decommissioning, restoration and aftercare obligations
referred to in condition 10. 
(4) The value of the financial guarantee shall be reviewed by agreement between
the Company and the Planning Authority or, failing agreement, determined (on
application by either party) by a suitably qualified independent professional not less
than every five years to ensure sufficient funds to secure restoration are provided,
and at the time of the approval of the detailed decommissioning. 
(5) The value of the financial guarantee shall be increased or decreased to take
account of any variation in costs of compliance with decommissioning, restoration
and aftercare obligations referred to in condition 10 as reflected in CPI index pricing
and best practice prevailing at the time of each review, or utilising such an alternative
indexing mechanism,  with the written agreement of the Planning Authority. 
(6) The costs of all necessary qualified and independent advice to establish and
review the value of the financial mechanism shall be borne by the applicant/operator
of the BESS scheme, or landowner, whatever party has control over the site at the
relevant date or as otherwise may be agreed in writing by the Planning Authority. 
Reason: to ensure that there are sufficient funds to secure performance of the
decommissioning, restoration and aftercare conditions attached to this planning
permission in the event of default by the Company. 
12. Construction Environmental Management Plan 
(1) There shall be no Commencement of Development unless and until a
Construction Environmental Management Plan (CEMP) has been submitted to and
approved in writing by the Planning Authority. The CEMP shall include (but not be
limited to) provisions in respect of: 
a) mitigation measures for potential dust, noise, and vibration impacts on nearby
properties; 
b) waste management, pollution control and mitigation; 
c) surface water management; 
d) procedures for monitoring compliance and dealing with any breaches of the
approved management plan; 
e) Updated pre-commencement ecological surveys and details of any necessary
Species Protection Plans which to be approved in consultation with NatureScot.. 
(2) The measures set out within the approved CEMP shall thereafter be
implemented in full. 
Reason: To ensure that all construction operations are carried out in a manner that
minimises their impact on road safety, amenity and the environment. 
13. Abnormal Loads 
(1) Prior to commencement of deliveries to site, the proposed route for any abnormal
loads on the trunk road network must be submitted to and approved by the Planning
Authority, in consultation with Transport Scotland as the trunk roads authority.

Page 16

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
(2) Prior to the movement of any abnormal load, any accommodation measures
required on the trunk road network, including the removal of street furniture, junction
widening, and traffic management must be approved and implemented to the
satisfaction of the Planning Authority, in consultation with Transport Scotland. 
(3) Prior to the movement of any components and/or construction materials, any
additional signing or temporary traffic control measures deemed necessary on the
trunk road network due to the size or length of any loads being transported must be
undertaken by a recognised QA traffic management consultant, to be approved by
Transport Scotland. 
Reason: To ensure that the transportation of any components/materials will not have
any detrimental effect on the road and structures along the route or road safety and
the free flow of traffic on the trunk road network. 
14 Noise limit at nearest residential properties 
The development hereby permitted shall operate in accordance with the predicted
and permitted noise level outputs as set out in the submitted Noise Impact
Assessment (Dated 31 March 2025) Revision 1, as agreed by The Council’s
Environmental Health Officer by consultation response dated 12.05.25. 
The development shall at all times operate within the noise limits as set out in the
approved Noise Impact Assessment. 
Following the development becoming fully operational, an additional noise survey
shall be undertaken by the applicant, at their expense, to demonstrate to the
satisfaction of the Planning Authority, in consultation with Environmental Health
Officers, that the development, as constructed, is operating within the permitted
noise levels. 
Should the maximum permitted noise levels be exceeded at any time, the
development shall immediately cease operation, and mitigation measures to
address the situation shall be submitted to, approved in writing in consultation with
Environmental Protection Officers, and thereafter implemented, prior to the
development resuming operations. 
Reason:  In the interests of residential amenity 
.
15. Construction Hours 
All construction work associated with the development must be carried out and all
audible construction activities shall be limited to: Monday to Friday 7.00am to
7.00pm in the summer and 7:30am to 5:00pm in the winter. 
On Saturdays, the working hours shall be limited to 07:00am to 5:00pm in the
summer and 7:30am to 5:00pm in the winter with no construction work taking place
on a Sunday or on public holidays. 
Reason: In the interests of local amenity. 
16. External Lighting 
Prior to commencement of development full details of any external lighting to be
used within the site shall be submitted to and approved in writing by the Planning

Page 17

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Authority. Such details shall include the location, type, angle of direction and wattage
of each light which shall be so positioned and angled to prevent any glare or light
spillage outwith the site boundary. Towards either residential properties or the Trunk
Road. 
External lighting should be designed to be automated to power on only upon
detection of movement within the site (calibrated to allow for wildlife movements)
and switched off at all other times unless required for works/maintenance of an
essential nature taking place on the site. 
The lighting should also be designed to be in accordance with the advice set out
within the Bats and Artificial Lighting in the UK' Guidance Note GN 08 / 23 to ensure
no unacceptable impacts on bats occurs during the normal operation of the facility. 
No external lighting shall be installed or operated except in accordance with the duly
approved scheme. 
Reason: In order to avoid light pollution and in the interest of amenity, road safety
and protected species interests. 
18. Public and Private Water Supply Protection Plan 
(1) No development shall commence until a Public and Private Water Supply
Protection Plan, has been submitted to and approved in writing by the Planning
Authority in consultation with SEPA. 
(2) The Company shall demonstrate within the Public and Private Water Supply
Protection Plan that the wholesomeness and sufficiency of all private water supplies
in the vicinity of the development shall not be compromised by the proposed
development. 
(3) If during, or on completion of the works, surrounding private water supplies are
affected or deemed to have become unsuitable, as a result of the consented
development, it shall be the responsibility of the operator and/or landowner to ensure
that any damage to the said water supplies is rectified and addressed within 24
hours to ensure that the water supplies to the properties meet at least the standards
which were in place prior to works of this permission being implemented. 
(4) Thereafter the development shall be carried out in accordance with the approved
Public and Private Water Supply Protection Plan . 
Reason: In the interests of public health, to safeguard water supplies and provide
mitigation measures should there be any impacts on drinking water supplies arising
from the construction, operation, maintenance or decommissioning of the
Development. 
19.  Workers Accommodation Strategy 
Prior to the commencement of development, a strategy for housing incoming
construction workers shall be submitted to and approved in writing by the Planning
Authority. Thereafter the development shall be carried out in accordance with the
approved details.

Page 18

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Reason: To address potential adverse socio-economic effects and ensure the
proposals do not adversely impact upon the operation of the local housing market
having regard to the declared Argyll and Bute housing emergency. 
20. Reinstatement of Construction Compound 
Within six months of the Battery Energy Storage Scheme becoming fully operational,
all temporary site offices, containers, construction materials, machinery and
equipment shall be removed, and the compounds/laydown area if outside the BESS
platform area shall be fully restored in accordance with a scheme detailing
vegetation replacement techniques and timing, which shall be submitted to and
approved in advance by the Planning Authority. 
Reason: In order to secure appropriate reinstatement of those areas that may be
disturbed by construction in the interests of amenity. 
21 No development shall commence if the existing ecological survey information in
relation to the site is over 18 months old. In this event updated ecological surveys
shall be undertaken and any required species protection plans shall be submitted to
the Planning Authority for written approval in consultation with NatureScot before the
commencement of development. 
Reason: In order to protect biodiversity and protected species interests. 
ADDITIONAL NOTES TO APPLICANT 
Transport Scotland: 
The applicant should note that the granting of Planning Permission does not carry
with it the right to carry out works within the trunk road boundary and that
permissions must be granted by Transport Scotland Roads Directorate. Where any
works are required to the trunk road, contact details are provided on Transport
Scotland’s response to the Planning Authority which is available on the Council’s
Planning Portal.  
Trunk Road modification works shall, in all respects comply with the Design Manual
for Roads and Bridges and the Specification for Highway Works published by
HMSO. The developer shall issue a certificate to that effect, signed by the design
organisation.  
The road works which are required due will require a Road Safety Audit as specified
by the design Manual for Roads and Bridges  
Any Trunk Road works will necessitate a Minute of Agreement with the Trunk Road
Authority prior to commencement.  
In respect of the design and suitability of water pollution control measures, you are
advised to contact SEPA to ensure that the design and operation of proposed
safeguards proposed for the BESS are in accordance with relevant legislative and/or
regulatory requirements.

Page 19

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
COMMITTEE REPORT
APPENDIX A – RELATIVE TO APPLICATION NUMBER:  REF: 24/02083/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
1. Settlement Strategy 
1.1. The application site is situated within an area of countryside on land to the immediate
west of Taynuilt Substation, to the south of the A85 trunk road, on the outskirts of Taynuilt
totalling approximately 2 hectares. The A85 road, to the north and west of the field site
boundary, runs from Oban to Perth which serves the locality and leads to the A82 road
towards Glasgow and Stirling. 
1.2. To the east lies the Taynuilt Substation (operated by SSEN) which is enclosed by mixed
woodland and plantation. The broader surrounding area is characterised by agricultural
land and consists of several residential properties towards the south. The boundary with
the A85 has linear tree screening along much of the boundary, with sporadic and limited
gaps in this boundary tree screening where views of the proposed substation would be
possible from the road. There are no footways at this location. 
1.3. LDP 2 Policy 2 requires that development proposals in the Countryside must: 
demonstrate that there will be no unacceptable adverse effects (either individually or
cumulatively) on natural heritage resources, built and/or cultural heritage resources, and
landscape and visual amenity. Where a major development is proposed, or for any
development where there is preliminary evidence that there may be such adverse effects
(and where a formal environmental impact assessment is not required), a landscape and
visual impact assessment, natural heritage assessment, or built and/or cultural heritage
assessment may be required. In circumstances where there is otherwise evidence of a
risk to the environment (for example flood risk or environmental pollution) other
assessments may be required. The need for any such assessments would be determined
at the development management stage, generally through pre-planning application
processes 
1.4. Policy 02 A which is applicable to Countryside Areas states: 
Policy 02 – Outwith Settlement Areas continued A – Countryside Areas Within the
Countryside Areas there is a presumption in favour of sustainable development where
this is of an appropriate scale, design, siting and use for its countryside location, as
detailed in the relevant subject policies 
1.5. Officers have had regard to the submitted alternative site evaluation report and consider
that co-locating the proposed BESS facility in close proximity to the existing substation it
will connect to is an appropriate approach given the characteristics of the site. 
1.6. In this instance Officers are content that the proposal represents new grid infrastructure
which will support the transition to net-zero and can be considered as acceptable
sustainable development at this countryside location. More detailed evaluation of
landscape, biodiversity, heritage and other matters referenced in policy 02 which must

Page 20

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
also be complied with to accord with the requirements of LDP2 Policy 02 are set out within
appropriate subject headings within this report. 
2. Location, Nature and Design of Proposed Development 
2.1. The site occupies part of a single field enclosure located to the immediate west of the
SSEN Taynuilt Substation. The application site extends to approximately 2 hectares and
comprises rough grassland and is of low agricultural value. The village of Taynuilt itself is
situated approximately 1.9km west of the site. 
2.2. The A85 road, north of the site boundary, runs from Oban to Perth. To the east lies the
Taynuilt Substation which is enclosed by mixed woodland and plantation. The broader
surrounding area is characterised by agricultural land and consists of several crofts
towards the south. 
2.3. The application site is undulating, however in general terms the landform can be
described as rising southwards from the A85. Elevations range from lows of
approximately 25m AOD (near the roadside at the substation) to highs of approximately
35m AOD (near the southern boundary). There is a knoll towards the southwestern extent
of the application site. 
2.4. Along the roadside of the A85, post-and-wire fencing and a structural woodland strip
(primarily comprising deciduous species) defines the boundary of the application site.
Scattered mature individual trees are also present in the application site, with further
scattered trees and copses located near the southern boundary. The site is crossed by
two tributary watercourses. 
2.5. The purpose of the proposed development seeks to install a Battery Energy Storage
System (BESS) which would provide standby, emergency electricity for National Grid in
times of high electricity demand or when renewable energy projects are unable to fulfil
demand. 
2.6. The main elements of the development are as follows: 
• 22 x battery energy storage container units; (reduced from 26)
• 11 x Inverter stations; (reduced from 13)
• 1x Switchgear Container; 
• 1x Spares Container; 
• 1x Customer Substation; 
• Underground cabling connecting each BESS container with the switchgear and
substation; 
• 2.4m Welded Mesh Fencing 
• Water Tank; 
• Access Tracks 
• Hardstanding 
• Access Gate 
• Parking 
• Temporary Construction Compound; and 
• Perimeter lighting and CCTV. 
2.7. The applicants clarify that “The site layout is highlighted on the Indicative Layout (ref:
Indicative Layout Drawing), however it should be noted that the layout is indicative and
subject to procurement of the most appropriate infrastructure and technology at the time
of construction”.

Page 21

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
2.8. This appears to be a common approach relating BESS applications where evolving
technology is reflected in a reluctance of the applicant to wish to specify exactly what
technical plant or equipment will finally be installed.  Officers have had regard to this
approach, and have  therefore proposed conditions to ensure that any subsequent details
provided, accord with the terms of this permission in respect of the scale and general
appearance of any future equipment details. This will ensure that the Planning Authority
remains in control of what is built and that the evaluation within this report in in respect of
the  scale, layout , appearance, and noise generating characteristics of the operation of
the equipment is defined by the details permitted to be installed under the terms of this
planning permission. 
2.9. The battery containers and ancillary equipment would be painted in a muted green colour
to be agreed with the Local Planning Authority. The development would be secured by a
2.4 metre high mesh welded security fence, with the western and southern boundary
being a 3.0m wooden acoustic fence. 
2.10. Additional landscaping details in the form of tree and shrub planting has been proposed
by the applicant to both assist assimilation of the development into the landscape and to
ensure a biodiversity net gain will be delivered. Officers will provide further commentary
on these matters in evaluating the potential Landscape Impacts and biodiversity
enhancement requirements related to the development. 
3.  Landscape and Visual Impact Assessment and Biodiversity Net Gain 
3.1. As has been set out at Section 1 of this report, the application seeks to locate a BESS
facility on a site within a countryside location. The development will therefore require to
address the policies which apply to such development in their entirety. 
3.2. LDP 2 Policy 02 clarifies, inter alia, that applications : 
will also be required to demonstrate that there will be no unacceptable adverse effects
(either individually or cumulatively) on natural heritage resources, built and/or cultural
heritage resources, and landscape and visual amenity... 
3.3.  LDP 2 Policy 04 which relates to sustainable development requires that; 
In preparing new development proposals, developers should seek to demonstrate the
following sustainable development principles, which the planning authority will also use in
deciding whether or not to grant planning permission... 
i) Respect the landscape character of an area and the setting and character of
settlements; 
3.4.  LDP 2 Policy 08 in respect of sustainable siting states 
Each of the following will apply when assessing any proposal for development...... 
• The development should integrate into the landscape or existing built form to minimise
detrimental effects on the environment. Particularly careful attention should be given to
hilltop, skyline or ridge locations, where development will only be acceptable if such a
location cannot be avoided and any significant adverse landscape and visual effects are
clearly outweighed by social, environmental or economic benefits of community wide
importance arising from the development proposal, and have been sufficiently mitigated

Page 22

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
through an environmental impact assessment or landscape and visual impact
assessment.
.
3.5. LDP 2 Policy 10, which sets out the design principles applicable to all development,
requires that; 
The design of any development must: 
• Demonstrate an understanding of and appropriate response to the proposed
development site and wider context including consideration of character and, where
applicable, urban grain. 
3.6. A Landscape Masterplan (ref: P23-2297_EN_08_B) has been submitted with the
application. Existing trees and shrubs along the A85 trunk road are proposed to be
retained as far as is practicable, with additional mixed native tree and shrub species
introduced to provide improved year-round screening which would mitigate any potential
impacts further. 
3.7. The applicants have clarified by submission that additional screening has been included
to reduce visual impacts to receptors to the south of the proposed development. The site
boundary for the application allows for all development associated with the proposed
development, including connection to the grid and landscaping features to be provided
within the red line site boundary. 
3.8. A Landscape and Visual Impact Appraisal (LVIA) has been submitted to accompany the
application. In summary this document concludes that although greater local landscape
impacts will occur during construction , the applicant submits that at the operational stage
of the development , when proposed landscaping is also factored into the evaluation,
minimal landscape impact will occur. Officers, having reviewed the documentation are in
agreement with its methodology and findings that no significant adverse landscape
impacts will occur in respect of the proposals. 
3.9. Officers consider that the location where the BESS scheme as proposed is in conformity
with policy advice in respect of minimising landscape impacts and maximising landscape
integration.  Given the well contained nature of the site from public views of significance,
and the fact that further mitigation is possible through a carefully designed landscaping
strategy to ensure more trees/screening and biodiversity focussed landscaping are
provided, officers are content that the proposals can acceptably integrate into the
landscape at this point. 
3.10. The red line site boundary leaves ample land for substantial biodiversity net gain
focussed structural shrub/tree planting to be provided, further containing the site and
minimising its potential impact on the landscape and amenity of the area in general.
Although some additional scattered tree/copse planting is currently proposed, Officers do
not consider that this is sufficient to meet both landscape integration requirements or
biodiversity enhancement requirements. A condition requiring improved and more
substantial tree/landscape planting around the BESS site is therefore proposed. 
3.11. There are a number of residential properties located within the area immediately
surrounding the application site. The submitted Zone of Theoretical Visibility concludes
that that there is a very limited number from which potential visibility of the proposed
development would arise: at Fairy Hill Croft, Plot 2 Deerview, and Land at Croft 4.
Although the right to a view is not a material planning consideration, officers do consider
that any impacts on the amenity of residential properties should in so far as is practicable
be minimised. The need for additional and more substantial planting related to both

Page 23

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
landscape integration and biodiversity enhancement will also reduce impacts on views of
the development from residential properties located south and above the application site. 
3.12. Officers consider there will be landscaping opportunities to assist in reducing any on
views/amenity impacts from residential properties located in the general vicinity of the
proposed site and officers are content that having regard to the LVIA evaluation, the
requirement by suspensive condition for additional biodiversity focussed tree
planting/landscaping will ensure that no unacceptable impacts on residential amenities
will occur.  
3.13. That the proposals will co-locate in the landscape with existing SSEN grid
infrastructure is also considered to be a material consideration in favour of the proposed
site as the containment of such infrastructure offers more potential to both effectively
integrate the proposals into the landscape with the development not appearing out of
character with its immediate environs before landscaping planting will mature. 
3.14. The proposals, subject to the imposition of appropriate conditions to require additional
biodiversity net gain compliant landscaping are therefore considered to be in accordance
with LDP 2 Policies 02, 04, 08, 10 and 73 objectives and also NPF 4 Policy 3 and Policy
4 requirements. 
3.15. NPF 4 and LDP 2 Energy Policy Evaluation   
3.16. The role of Battery Energy Storage Schemes as part of achieving net zero ambitions is
sometimes questioned by objectors as the generation of electricity from batteries is not in
itself a renewable source of energy. The Scottish Ministers have made clear in numerous
decisions that they regard BESS Development as essential infrastructure related at
addressing the climate emergency and achieving net zero targets. The proposed
Development, through provision of energy storage, adds flexibility and resilience
necessary to maintain secure and reliable supplies of energy to homes and businesses
as our energy transition takes place. It is the view of officers that the proposed
Development is supported by the Draft Scottish Energy Strategy and Just Transition Plan
2023 and that there is strong wider policy support from the Scottish Government for
battery storage as a vital component of energy policy ambitions. 
3.17. The proposal is considered to be essential energy infrastructure which contributes to
addressing the Climate Emergency and the objectives of NPF4 Policy 1. It must be
acknowledged in the decision-making process that there is strong National policy support
for such proposals. It is therefore recommended that Members, in coming to a planning
decision in this instance, consider the strong policy support for such proposals set out in
LDP2 Policy 30 and NPF 4 Policy 11. LDP 2 policy 30 states; 
The Council will support renewable energy developments where these are consistent with
the principles of sustainable development and it can be adequately demonstrated that
there would be no unacceptable environmental effects, whether individual or cumulative,
on local communities, natural and historic environments, landscape character and visual
amenity, and that the proposals would be compatible with adjacent land uses….In
assessing any application the Council will additionally have regard to the opportunities for
energy storage, local energy networks, and long term environmental management of the
site. 
3.18. NPF 4 Policy 11 clarifies that:

Page 24

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
a) Development proposals for all forms of renewable, low-carbon and zero emissions
technologies will be supported. These include: 
iii. energy storage, such as battery storage and pumped storage hydro; 
3.19. Notwithstanding these energy policies and other policy advice which strongly support the
approval of the current BESS proposal, there are also specific locational and site-specific
planning policy issues which require to be satisfactorily addressed as set out in other
policies within LDP 2 and NPF4 and as referenced in this report. 
4. Noise and Amenity 
4.1. Objections have been lodged on the potential for the operation of the BESS to have an
unacceptable impact on the amenity of residential properties nearest to the scheme through 
the generation of noise. This is a matter of legitimate concern, and a considerable amount
of discussion has taken place between Environmental Health Officers (EHO) and the
applicants in respect of this matter. 
4.2. In their initial consultation response of 16.01.25 EHO expressed concerns that the
development, as then proposed, could cause unacceptable noise disturbance to residential
amenity due to the report underestimating the actual noise output characteristics of the
development when considered against the background noise levels of the locality. The
conclusion was that the proposals as they were then proposed could not be recommended
for approval. 
4.3.  Following this response a meeting was held and the scheme was amended to remove two
pairs of battery units and their associated inverters and the layout of the scheme revised.
These revised proposals were supported by an updated Noise Impact Report. The
proposals have been redesigned to reduce the number of battery units (26 down to 22) and
the number of inverter stations has been reduced from 13 to 11. 
4.4. The EHO is now content that the revised proposals are acceptable and that the noise
characteristics predicted will not have an unacceptable impact of residential properties. In
order to ensure this, a condition requiring that the development, as constructed, will operate
within the agreed noise limits is proposed. This will ensure the actual noise levels conform
to the predicted noise levels in the updated noise impact report reflecting the amended
design. 
4.5. For the reasons set out above it is considered that subject to the imposition of appropriate
conditions to safeguard residential amenities the proposal is acceptable and in compliance
with the general objectives of LDP 2 Policy 04(h) and LDP 2 Policy 14. 
5. Network, Parking and Associated Transport Matters. 
5.1. Access for the construction and operational phases of the development is proposed via a
new priority access junction from the A85 trunk road on the northern site boundary, located
approximately 82 metres to the west of the existing access serving Taynuilt Substation.
This access is the preferential access point and is subject to formal and final agreement
with Transport Scotland. A track to link the BESS site and the adjacent substation is also
proposed as a secondary access during the operational phase of the development. 
5.2. All emergency vehicles and/or HGVs (required should a large part need replacing on an
ad-hoc basis for example) will access the site via the A85 site access, however regular
maintenance vehicles undertaken by 4x4 type vehicles will have the option of accessing
the site via the A85 and/or the substation access. The planning application boundary has

Page 25

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
been extended to provide the optionality of an alternative off the existing highway utilising
the existing Taynuilt Substation access, however the preferred option would be having a
permanent access junction from the A85. 
5.3. As this access is directly onto the A85 Trunk Road, the appropriate roads consultee for the
application is Transport Scotland and not the Area Roads Engineer.  The applicants have
confirmed by submission at paragraph 3.20 of the Construction Traffic Management Plan
that the proposed access onto the A85 is agreed in principle with Transport Scotland as
part of pre-application discussions. 
5.4. Transport Scotland in their consultation response dated 17.12.24 have raised no objections
to the proposals subject to the imposition of conditions to secure sight lines and a safe
access, entry point being created to the trunk road that will not undermine safety. A
suspensive condition to ensure that a finalised Construction Traffic Management Plan is
approved by Transport Scotland is therefore proposed. 
5.5. Officers have proposed conditions in accordance with the requirements of Transport
Scotland and therefore the proposals are considered to accord with the road safety
objectives of LDP 2 Policies 35, 37 and 39. Additional informatives, as requested by
Transport Scotland, will be placed upon any grant of Planning Permission. 
6. Other Key Policy Matters 
6.1 Flooding and Drainage 
The Council’s Flooding advisor has raised no objection to the proposals and has
recommended no objection subject to the imposition of a condition. This condition has been
proposed. 
An existing mains water supply is routed along the edge of the trunk road in the vicinity of
the site. A suspensive condition is therefore proposed to ensure that no public or private
water supplies are adversely impacted during the construction of the site or through its
operation. 
The applicants have proposed a containment method to ensure no water run off which could
damage the environment would occur in the event of a fire. The control of the quality of any
runoff water from the site is a matter covered by other legislative regimes and administered
by SEPA. Such matters are therefore not a material planning application in determining the
current proposals. 
The proposals are therefore considered to be in compliance with the requirements of the
LDP 2 Policies 55,59,61 and 62. 
6.3 Economic Benefits and Workers Housing Strategy Requirements 
The policy framework against which proposals for energy development proposals must be
evaluated also includes the following policy matters: 
NPF 4 Policy 11(c) states that: 
“Development proposals will only be supported where they maximise net economic
impact, including local and community socio-economic benefits such as employment,
associated business and supply chain opportunities.” 
Policy 25(a) of the NPF4 states:

Page 26

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
“Development proposals which contribute to local or regional community wealth
building strategies and are consistent with local economic priorities will be supported.
This could include for example improving community resilience and reducing
inequalities; increasing spending within communities; ensuring the use of local supply
chains and services; local job creation; supporting community led proposals,
including creation of new local firms and enabling community led ownership of
buildings and assets.” 
LDP 2 Policy 30 requires energy related proposals to be assessed against a number of
criteria , including: 
Net economic impact, including local and community socio-economic benefits such as
employment, associated business and supply chain opportunities.” 
The applicants have submitted an economic benefits statement dated November 24 as part
of their application submissions. Officers accept that there will be net economic benefits
associated with the construction of the BESS facility as set out in this report. It is specifically
noted that longer term benefits are anticipated to be created as 
The applicant summarises the envisaged Economic Benefits as set out below; 
• Construction phase employment: The Proposed Development will provide
investment of around £50million and could support up to 90 temporary jobs, both
direct jobs on-site and in the wider supply chain, during the 12-month construction
period. 
• Contribution of construction phase to economic output: The gross value added
(GVA) generated by jobs supported during the construction phase could be up to
£5.8million. 
• Operational benefits: It is estimated that the Proposed Development will support up
to five full-time equivalent jobs (FTE) in Argyll and Bute and the wider economy once
it is operational. The GVA associated with these jobs is estimated to be £7million
(present value) over the 40-year operational life span of the scheme. 
• Energy Security: The Proposed Development can provide back-up energy in case
of a power outage in Argyll. 
Officers consider that the matters set out above are satisfactory to address the policy
requirements of this particular proposal. 
In accordance with normal requirements for development which could attract construction
workers to rural areas and impact on the functioning of the local housing market, Officers
consider that a condition requiring the submission of a workers housing strategy should be
imposed upon any grant of planning permission to ensure that matters related to the
declared housing emergency are adequately addressed in respect of the proposal and to
ensure workers coming into the area do not unacceptably impact the local communities
access to housing. 
It is therefore considered that the proposals are in compliance with LDP 2 Policy 30 and
NPF 4 Policy 11(c) and Policy 25 (a) requirements to ensure that developments do not
have an adverse impact on the local community interests and/or adverse socio-economic
impacts associated with the declared housing emergency.

Page 27

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
6.4 Restoration Bond and Site Restoration Plan (to include waste management and
disposal plan for any potentially contaminating materials) 
It is an important and material planning consideration that a mechanism to ensure the
decommissioning of the site and its restoration are adequately addressed in considering
this planning application. Indeed, concerns on these matters were properly raised by
objectors to the scheme in their submissions. 
Officers have therefore proposed suspensive planning conditions requiring a site
decommissioning plan and a confirmed financial mechanism to safeguard the communities
interests as part of the suite of conditions, and also the requirement for a detailed
decommissioning Environmental Management Plan. 
6.5 Cultural Heritage 
The applicants have submitted a heritage statement in respect of these matters as part of
the application submission package. Both WoSAS and Officers are in agreement that there
will be no adverse impact on any heritage assets associated with the development of the
current proposals. 
The proposals are therefore considered to be in accordance with the requirements of NPF
4 Policy 7 and LDP 2 Policy 15. 
6.6 Ecology/Protected Species 
The applicants as part of their supporting information have provided an Ecological
Appraisal of the site, which includes a Phase 1 Habitat Survey and also information
relating to potential Bat Roosts in the existing trees and potential impacts on any
European Protected Species. This survey was updated at the request of the Councils
Biodiversity Officer and a new survey was submitted on 15.04.25. 
The submissions confirm that the submitted appraisal follows the Guidelines for
Preliminary Ecological Appraisal and the Guidelines for Ecological Report Writing (CIEEM
2017a; 2017b),and is in line with the British Standard BS42020:2013 ‘Biodiversity – Code
of practice for planning and development’. It is based on information from a desk study, 
and an Extended Phase 1 Habitat Survey. 
Having regard to the main findings of the updated report, there are no identified protected
species on the site, however there may be limited opportunity for bat roosts in some of
the larger trees on site. In respect of the surveys for Otters there are no identified Holts
on the application site although there are signs that Otters may utilise the watercourse 
Both NatureScot and the Councils biodiversity officer are content with the proposals
subject to the imposition of appropriate conditions to secure biodiversity net gain through
increased landscape/tree planting. The proposals are therefore considered to be in
accordance with the requirements of NPF4 Policies 3 and 4 and LDP 2 Policy 73. 
Members are requested to note that an Appropriate Assessment (AA) has been carried
out at the request of NatureScot in respect of potential adverse impacts on Loch Etive
Woods Special Area of Conservation. The required AA has been provided at appendix C
to this report. Officers can identify no reason to depart from the opinion of NatureScot that
based on the information provided, our conclusion is that the Proposal will not adversely
affect the integrity of the site.

Page 28

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Officers note the request by NatureScot for a 10m vegetation gap around the proposal.
This is a matter that can be addressed as part of approving the required landscaping and
biodiversity enhancement scheme as required by  other conditions. 
The proposals are therefore considered to be in accordance with  LDP 2 Policy 74 of  and
NPF 4 Policy 4.   
6.7 Conclusion. 
The proposal is for essential energy infrastructure which contributes to addressing the
Climate emergency and the objectives of NPF4 Policy 1, it must be acknowledged in the
decision-making process that there is strong policy support for such proposals as set out
in LDP2 Policy 30 and NPF 4 Policy 11 in coming to a Planning decision in this case. 
Officers consider that the site location is acceptable and subject to;  
• Enhanced landscape/biodiversity planting,
• Condition(s) to safeguard residential amenity from noise, 
• An appropriate financial mechanism for decommissioning/ restoration being secured
and 
• The requirements of the Scottish Fire and Rescue Service to be accommodated before
construction begins,   
that the BESS facility is in accordance with the policies of the development plan as set
out in this report, and no reason to warrant refusal of the application has been identified.

Page 29

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Appendix B – Objections and representations at 30.05.25 
Representations in relation to 24/02083/PP 
Objection 
1. A Wright 25 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
2. Ailie Robertson 3 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
3. AJ Day Flat 0/6 212 Newlands Road Glasgow G44 4EY 
4. Alan Johnstone Floodigarry 2 Otter Creek Taynuilt  PA35 1HP 
5. Alan Porte Ardbrae Taynuilt Argyll And Bute PA35 1HP 
6. Alan Provan Tigh Ruadh Taynuilt Argyll And Bute PA35 1HP 
7. Alan Ross Hawthorn Bank  Otter Creek  Taynuilt PA35 1HP 
8. Alec Cameron 5 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
9. Alison Boyce 44 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
10. Alison Pringle Polvernie  Taynuilt PA35 1JH  
11. Allister Butler Lichen Burn Otter Creek Taynuilt PA35 1HP 
12. Alva Lundmark 1 Millar Place Stirling FK8 1UX  
13. Amy Boyce 4 Cruachan Cottages Taynuilt Argyll And Bute PA35 1JG 
14. Andrew Drummond 18 Achnafearna Taynuilt Argyll And Bute PA35 1JP 
15. Andrew Parker PA35 1HP    
16. Anne Archer Sealladh Briagha Gallanach Road Oban Argyll And Bute 
17. Arthur Houston 15 Aldersyde Taynuilt Argyll And Bute PA35 1AG 
18. Audrey Paterson Traigh Neannda 7 Aldersyde Taynuilt Argyll And Bute 
19. Benjamin Scheschkewitz     
20. Birgit Dorries     
21. Brian Pennock Otter Creek Taynuilt Argyll PA35 1HP 
22. C Godliman 15 Achlonan  Taynuilt Argyll PA35 1JJ 
23. Candy Drummond 18 Achnafearna Taynuilt Argyll And Bute PA35 1JP 
24. Carol Thomson Brander View Bridge Of Awe Argyll And Bute PA35 1HT 
25. Caroline Moran 35 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
26. Catherine MacMillan Cluan Beag Taynuilt Argyll And Bute PA35 1JN 
27. Cecilia Keenan 36 Cruachan Cottages Taynuilt Argyll And Bute PA35 1JG 
28. Clare Gilbert Heather Cottage Taynuilt  PA35 1HP  
29. Colin Evans 29 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
30. Colin Winter Shellachan Kilchrenan Argyll And Bute PA35 1HD 
31. Craig Macmillan Sanaigmhor Achlonan Taynuilt Argyll And Bute 
32. Dan Mulqueen Brochroy Farmhouse Taynuilt Argyll And Bute PA35 1JQ 
33. Daniel Day 1 Millar Place Stirling FK8 1UX  
34. Daphne MacCallum No Address Provided    
35. David Currie Cara Glen Lonan Taynuilt  
36. David Paterson Traigh Neannda 7 Aldersyde Taynuilt Argyll And Bute 
37. David Pratt 1 Old School Bank  Taynuilt Argyll PA35 1JE 
38. David Wellburn Cearnag 6 Otter Creek Taynuilt PA35 1HP 
39. Dee Pennock Otter Creek  Taynuilt Argyll PA35 1HP 
40. Deirdre Pennock 8 Otter Creek Taynuilt Argyll PA35 1HP 
41. Derek Worth 26 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
42. Donald Harrison     
43. Donalda Henderson Tigh-Na-Fuaran Airds Taynuilt Argyll And Bute 
44. Douglas Bell     
45. Dr Aileen Porte Ardbrae Taynuilt Argyll And Bute PA35 1HP 
46. Duncan Blyth Carnoch Taynuilt Argyll And Bute PA35 1HP 
47. Elaine Boyce 28 Aldersyde Taynuilt Argyll And Bute PA35 1AG 
48. Emily Reid Burnside Croft Ichrachan  Taynuilt Argyll

Page 30

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
49. Evelyn Greig Tigh Fuaran Kirkton Taynuilt Argyll And Bute 
50. Fabian Henning Am Ziegeleischiag 4B 14641 Wustermark Germany  
51. Fiona Evans 29 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
52. Fiona Jarvie 1 & 2 The Cottages Ichrachan Taynuilt Argyll And Bute PA35 1HP 
53. Flora Anderson 42 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
54. Flora Winter Shellachan Kilchrenan Argyll And Bute PA35 1HD 
55. Geoffrey Russell The Cottage In The Woods Taynuilt Argyll And Bute PA35 1HZ 
56. Gordon Nicol 9 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
57. Heather Shaw 5 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
58. Heather Shephard 29 Aldersyde Taynuilt PA35 1AG  
59. Hilary Currie Cara Glen Lonan Taynuilt  
60. Hugh Campbell Achanlochan Farm Taynuilt Argyll And Bute PA35 1JW 
61. Hugh Longbottom Sandbank Airds Bay Argyll And Bute PA35 1JR 
62. Iain D MacKintosh 3 Kirkton  Taynuilt Argyll  
63. Ian Johnstone 14 St Oran's Place  Connel PA37 1AD  
64. Isabel Blyth Carnoch Taynuilt Argyll And Bute PA35 1HP 
65. J Bennett Dun Aluin Kilchrenan Argyll And Bute PA35 1HG 
66. J Campbell Inverawe Barn Inverawe Argyll And Bute PA35 1HU 
67. J D MacKintosh Kirkton  Taynuilt  Argyll PA35 1JD 
68. J Godliman 15 Achlonan  Taynuilt Argyll PA35 1JJ 
69. J Horne 17 Achnafearna Taynuilt Argyll And Bute PA35 1JP 
70. Jack James Reid Burnside Croft Ichrachan  Taynuilt Argyll 
71. Jamie Gibson 1 Chestnut Court Taynuilt Argyll And Bute PA35 1JZ
72. James MacMillan Cluan Beag Taynuilt Argyll And Bute PA35 1JN
73. Janet Frew 20 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
74. Janette MacMillan 21 Cruachan Cottages Taynuilt Argyll And Bute PA35 1JG 
75. Janice Harrison     
76. Janine Johnston 5 Polfearn House Taynuilt Argyll And Bute PA35 1JQ 
77. John Boyce 44 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
78. John Day Fairy Hill Croft  Taynuilt Argyll PA35 1HP 
79. Jonathan Brown Edgebrook House 13 East Fettes Avenue Edinburgh EH4 1DN 
80. Joy MacWhannell 6 Cruachan Cottage Taynuilt Argyll PA35 1JS 
81. Joyce Cameron 26 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
82. June Currie Roselea Taynuilt Argyll And Bute PA35 1JE 
83. Karen MacMillan 7 Otter Creek Taynuilt  Argyll PA35 1HP 
84. Karen Smurthwaite Struthan Cottage TAYNUILT PA35 1HY  
85. Katherine Blyth Carnoch Taynuilt Argyll And Bute PA35 1HP 
86. Kathryn Pennock 8 Otter Creek  Taynuilt  Argyll PA35 1HP 
87. Kathy Longbottom Sandbank Airds Bay Argyll And Bute PA35 1JR 
88. Keith MacMillan 21 Cruachan Cottages Taynuilt Argyll And Bute PA35 1JG 
89. Kieran Swan The Bothie Airds Bay Argyll And Bute PA35 1JR 
90. L A Crossley 4 Lochandhu Taynuilt Argyll And Bute PA35 1JL 
91. Linsey Johnstone Floodigarry  2 Otter Creek Taynuilt PA35 1HP 
92. Lisa Crossley New York Dalavich Argyll And Bute PA35 1HL
93. Liz Ross 10 Otter Creek Taynuilt Argyll And Bute PA35 1HP   
94. Luna Martin     
95. Lynne Meldrum Dunfraoch  Taynuilt PA35 1JE  
96. Lynne Russell The Cottage In The Woods Taynuilt Argyll And Bute PA35 1HZ 
97. M C Wells 9 Brochroy Crofts Taynuilt Argyll And Bute PA35 1JQ 
98. Magaret Butler Lichen Burn Otter Creek Taynuilt  PA35 1HP 
99. Mary Nicolson Caladh-Reidh Airds Taynuilt Argyll And Bute 
100. Mary Scott Nantrigg Taynuilt Argyll PA35 1JQ 
101. Matthew Davey Ardtalla 6 Brochroy Crofts Taynuilt Argyll And Bute 
102. Michael Smurthwaite Struthan Cottage TAYNUILT PA35 1HY  
103. Michael Thorley Little Paddock  East Road  East Mersea Essex

Page 31

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
104. Morag Griffiths Woodend Cottage Kirkton Taynuilt Argyll And Bute 
105. Mr MacDonald 1 Aldersyde  Taynuilt Argyll PA35 1AG 
106. Mr Provan Tigh Ruadh  Taynuilt   
107. Mrs MacDonald 1 Aldersyde Taynuilt  Argyll PA35 1AG
108. Stefan Jaretzke 3 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
109. Vanessa Anderson West Manse Taynuilt Argyll And Bute PA35 1JW 
110. Paula Baker 7 Otter Creek Taynuilt Argyll PA35 1HP 
111. Paul Smith Dean Cottage Airds Taynuilt Argyll And Bute   
112. Peter Henderson Tigh-Na-Fuaran Airds Taynuilt Argyll And Bute 
113. Provan Tigh Ruadh  Taynuilt   
114. R A Morrison Flat 0/6  212 Newlands Road Glasgow G44 4EY 
115. R Horne 17 Achnafearna Taynuilt Argyll And Bute PA35 1JP 
116. R Wright 25 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
117. Rosie Hughes 3 Cruachan Terrace Taynuilt Argyll And Bute PA35 1JX 
118. Sally Nicol 9 Otter Creek Taynuilt Argyll And Bute PA35 1HP 
119. Sarah Thorley Little Paddock  East Road East Mersea Essex  
120. Sarah Wellburn Cearnag 6 Otter Creek Taynuilt PA35 1HP 
121. Sharon Reid Ichrachan Cottage Taynuilt Argyll And Bute PA35 1HP 
122. Sheena McIntyre 7 Cruachan Cottages Taynuilt Argyll And Bute PA35 1JG 
123. Shirley Bell     
124. Stephen MacIntyre Head Of Environment  Mowi Scotland   
125. Susan Jarvie 1 & 2 The Cottages Ichrachan Taynuilt Argyll And Bute PA35
1HP 
126. Susan Lindsay 8 Achlonan Taynuilt Argyll And Bute PA35 1JJ 
127. Susan MacPhail The Bothie Airds Bay Argyll And Bute PA35 1JR 
128. Thomas Dolan 4 Brochroy Crofts Taynuilt Argyll And Bute PA35 1JQ 
129. Tom McLellan Manish Taynuilt Argyll And Bute PA35 1JQ 
130. Undine Achilles-Day Fairy Hill Croft Taynuilt Argyll PA35 1HP 
131. Valerie MacFarlane Tigh Na Barsh Taynuilt Argyll PA35 1JQ 
132. Vanessa Henning Am Ziegeleischiag 4B 14641 Wustermark Germany  
133. W Lewis Mo-Dhaichaidh Airds Taynuilt Argyll And Bute 
134. Wendy Campbell Field House Airds Bay Argyll And Bute PA35 1JR 
135. Wilfried Dorries     
Support 
1. John Bee Bar Glas Taynuilt Argyll And Bute PA35 1HY 
Representation 
1. Sam Bristow Nant Bank Croft Taynuilt Argyll And Bute PA35 1HP 
2. James Andrews Springbank  Taynuilt   
3. Maria Andrews Springbank  Taynuilt   
4. Ian Reid 2 Firgrove Ardconnel Road Oban Argyll And Bute

Page 32

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
Appendix C – HABITATS REGULATIONS ‘APPROPRIATE ASSESSMENT’
Loch Etive Woods Special Area of Conservation (SAC) (Biological) : Appropriate
Assessment by Argyll and Bute Council under Regulations 9A and 11-15 of The
Conservation (Natural Habitats, &c.) Regulations 1994 as amended by the Conservation
(Natural Habitats, &c.) Amendment (Scotland) Regulations 2011 
Loch Etive Woods Special Area of Conservation (SAC) (Biological)
Site Code: UK0012750
Site Area: 2,642.60 Ha
NatureScot Opinion on the need for an Appropriate Assessment 
NatureScot have taken the view that this Proposal is likely to have a significant effect on the
woodland features of the SAC. 
In circumstances where European Protected Species could be subject to significant effects as
a consequence of development proposals the competent authority, in considering whether
development should be consented, is required to undertake an ‘appropriate assessment’ to
inform its decision-making process, on the basis that where unacceptable effects are
identified, or in cases of ‘reasonable scientific doubt’, then permission ought not to be granted. 
An ‘appropriate assessment’ is required to be undertaken in cases where any plan or project
which:   
(a)  Either alone or in combination with other plans or projects would be likely to have a          
significant effect on a European site designated for nature conservation; and   
(b)  Is not directly connected with the management of the site.
Consequently, Argyll and Bute Council, as Competent Authority, is required to carry out an
Appropriate Assessment in view of the site’s conservation objectives for its qualifying interest.
SPA Qualifying Interests
1) Woodland 
Key factors affecting the qualifying features Mixed woodland on base-rich soils associated
with rocky slopes.  This habitat typically occurs in association with base-rich rocks in the steep-
sided immature river valleys and is found on nutrient-rich soils that often accumulate in the
shady micro-climates towards the bases of slopes and ravines. Such forests are not extensive
but fragmentary stands that then grade into other woodland types on level valley floors or
slopes above are widespread. 
Some good examples of this habitat occur in the deeply-incised rocky gorges associated with
Glen Nant and in the nearby Coille Leitire, with the habitat also found at Ard Trilleachan, Barran
Dubh, Clais Dhearg, Kennacraig to Esragan Burn and Bonawe to Cadderlie. The habitat at
Glen Nant supports notable bryophyte and lichen communities. These sites are representative
of the habitat type in western Scotland and comprise stands of ash woodland with a hazel
understorey and a rich field layer of tall herbs and woodland grasses on base-rich soils
characteristic of the habitat. 
Key management issues include grazing levels and problematic native and non-native
species. The woodland is considered to be in a favourable declining condition at this site due

Page 33

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL
to grazing levels and the associated lack of regeneration, which in turn has affected the
woodland structure. 
2) Otter 
Otter require continued proximity to unpolluted open water either freshwater or coastal.
There should be a plentiful food supply and features for providing shelter for both resting and
breeding. They are wide ranging and normally occur at low densities. The feature is in
favourable condition at Loch Etive Woods SAC. Previous population declines in otters in
Scotland were primarily due to pollution and persecution. 
Characteristics of the Development
The proposal relates to the provision of a Battery Energy Storage Scheme (BESS)  located
approximately 1km from the boundary with the SAC. The site is separated from the SAC by
both fields and residential properties and curtilages. The construction and normal operational
characteristic of the BESS scheme will have no direct or cross boundary impacts upon the
SAC however NatureScot raised concerns that there may be a risk of fire which could affect
the SAC. The ecological survey submitted with the application did however indicate the
presence of Otters using the application site, which is both a European Protected Species and
a Qualifying Interest of the SAC and therefore potential impact upon movement routes through
the site required to be considered.
Assessment 
The assessment considers the impact of the proposals on the qualifying species within the
designated area and has regard to the applicant’s submitted information in support of the
planning application, and to consultation advice provided by NatureScot. 
NatureScot in their response indicated that they considered that there may be a risk of fire
spreading from the Proposal to the SAC. However, they note that the Applicant has outlined
a number of fire safety measures in their application which will be suitable to minimise this
risk. Additionally, the habitat between the Proposal and the designated site will likely limit the
spread of fire in that direction. 
Notwithstanding this advice they advised that a 10m vegetation gap is implemented around
the proposal to help prevent any fire from spreading beyond the edge of the development. 
With regards to the otter Qualifying Interest of the SAC, their advice is that it is unlikely that
the proposal will have a significant effect, either directly or indirectly. An appropriate
assessment in respect of Otters and potential impacts is therefore not required. This is
because, although suitable otter habitat exists at the site, the area of development is small
compared to the rest of the SAC, and the surveys have shown that there is no evidence of
otter using the site at present. 
Recommended Mitigation to be Secured by Planning Condition
Comments received from NatureScot in respect of the requested 10m “fire break” around the
development are able to be secured as part of consideration of the landscaping details which
are required by proposed condition 03. 
NatureScot have also requested further pre-start ecological surveys be undertaken. Proposed
condition 12 in respect of the CEMP includes a requirement for pre-commencement surveys,
and if required Species Protection Plans to be subject to consultation and approval by
NatureScot.

Page 34

LDP2 format template March 4th 2024
Report of Handling Template for PPSL and Delegated Planning Applications – Updated 10.11.2023 
Classification: OFFICIAL 
Conclusion
The potential impacts of the development in relation to the qualifying species within the SPA
designation have been considered in the light of the above and it has been concluded that
with identified mitigation measures in place through the imposition of appropriate planning
conditions that the impacts arising from the construction, operation and decommissioning of
the development as proposed, will not with identified mitigation in place,  have a significant
impact upon qualifying interests, and accordingly there is no reason to withhold permission on
European nature conservation grounds.