Democracy Spraffa

Helensburgh, Cardross and Dumbarton Cyclepath Update

Argyll and Bute Council · 11 June 2024
Back to Helensburgh & Lomond Area Committee — 11 June 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 JUNE 2024 
HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
the Helensburgh and Lomond Area Committee on 12 March 2024 in relation to
the delivery of a dedicated, high quality walking and cycle path linking
Helensburgh, Cardross and Dumbarton.  The delivery of this path is a stated
Council Priority. 
1.2. Officers are reviewing the large amount of data provided by WSP following
termination of their contract in March 2024 for Phase 1 (Colgrain – Cardross)
and Phase 2 (Cardross – Dumbarton).  This is necessary to identify the
outstanding items of work which require to be completed to deliver a robust
design package and to satisfy funder requirements. 
1.3. The Feasibility report for Helensburgh Town Centre East (Phase 3) is currently
in draft form with funders for comment. 
1.4. 2024/25 funding applications have been submitted to Transport Scotland’s
Places for Everyone (PFE) programme to enable design work to continue. 
RECOMMENDATIONS 
1.5. It is recommended that the Helensburgh and Lomond members: 
1.5.1. Instruct Officers, subject to securing external funding, to seek a new design
team to continue development of Phase 1 and Phase 2 designs to complete
Developed Design and Technical Design stages. 
1.5.2. Support progression of the project to full Technical Design, as required by the
external funder.

Page 2

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
11 JUNE 2024 
HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the Helensburgh and
Lomond Area Committee on 12 March 2024 in relation to the delivery of a
dedicated, high quality walking and cycle path linking Helensburgh, Cardross
and Dumbarton.  The delivery of this path is a stated Council Priority. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Instruct Officers, subject to securing external funding, to seek a new design
team to continue development of Phase 1 and Phase 2 designs to complete
Developed Design and Technical Design stages. 
3.1.2. Support progression of the project to full Technical Design, as required by the
external funder. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. In 2023/24 the Active Travel Team secured £2.56M external funding for the
development and delivery of a total of 22 projects across Argyll and Bute, including
the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 18 separate
competitive funding applications, to 5 separate funds. 
Funding 
4.3. Transport Scotland’s Places for Everyone (PFE) programme is the primary
external active travel design funding available in Scotland.  It is structured
around 8 project stages with a competitive challenge fund, with the 32 local

Page 3

authorities, 7 regional transport partnerships, two national parks and numerous
community groups across Scotland competing against each other to secure the
funding each project requires. 
4.4. As of 2024/25, the construction element of the funding has been taken into a
separate competitive fund, Transport Scotland’s Active Travel Infrastructure
Fund (ATIF). ATIF still requires a separate competitive application to be
submitted but is, currently, only open for applications once a year.  All projects
submitted to ATIF must be ready in all respects to commence construction,
including having any legal or regulatory approvals required in place. 
4.5. A minimum of three new competitive funding submissions are required to
complete a project using external funding, with competitive applications required,
as a minimum, to PFE prior to Stage 0 (Strategic Definition) and Stage 3
(Developed Design) and to the new Transport Scotland ATIF prior to Stage 5
(Construction).  The project stages are (0) Strategic Definition, (1) Preparation
and Brief, (2) Concept Design, (3) Developed Design, (4) Technical Design, (5)
Construction, (6) Handover & Close Out, and (7) In Use. 
4.6. While the design work has, to date, been funded by jointly by the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s
PFE programme, the decision to de-fund the SPT Capital Programme in 24/25
results in the project being fully reliant on securing 24/25 PFE funding or internal
Council funding in order to continue work to complete the outstanding design
requirements. 
Match Funding 
4.7. The applications guidance for the new Transport Scotland Active Travel
Infrastructure Fund (ATIF) for construction ready projects states that all projects
submitted for construction funding will require some element of match funding. 
However, the guidance does not specify a minimum match funding percentage. 
Rather it states that the ATIF team will engage during the assessment process
to determine the requirements for match funding. 
4.8. While the lack of a specific match funding value to plan against is unhelpful,
Officers understand that there is not an expectation from Transport Scotland that
match funding would exceed the 30% required by the now terminated PFE
Construction challenge fund.  Based on not exceeding the 30% value, it is
recommended Members plan based on the cyclepath requiring construction
match funding not exceeding £2M. 
4.9. Phasing construction over a number of financial years will enable maximisation of
suitable external match funding, however this will result in a longer construction
programme.  Accelerating the construction programme will require additional
match funding to be secured, from internal and/or external sources, which could
prove challenging given the current economic climate. 
4.10. At present no construction match funding has secured.  It is likely to be beneficial
to the project if sources of construction match funding could be secured at an early

Page 4

stage, including consideration of any internal Council funds which could be
allocated to the delivery of this Council Priority. 
Maintenance 
4.11. Sustrans have requested a written maintenance plan and confirmation of how this
will be funded and delivered as a deliverable during the remaining design process. 
As such, members require to decide how the future maintenance of the cyclepath,
including sections of route already in place, will be delivered.  At present, the
Council does not receive any funding for the maintenance of cyclepaths and none
of the current external funding sources secured through competitive bidding for
active travel include maintenance as an eligible cost.  This anomaly has been
repeatedly raised by Officers with Transport Scotland Officials and it is recognised
to be inconsistent with the Scottish Government’s commitments regarding capital
funding for active travel projects. 
4.12. The Roads and Infrastructure Service are the single service within the Council
which includes infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths. However, it is acknowledged
these teams are already near capacity delivering the Roads and Infrastructure
Service commitments. The Roads and Infrastructure Service has previously
stated they do not wish to adopt sections of cyclepath remote from the public road. 
4.13. Members may wish to consider if there is a role for other organisations and/or
local community group volunteers to support the routine maintenance of the
cyclepath.  While unlikely to be skilled or qualified for the less frequent ‘heavier’
technical maintenance of drainage or path surfacing, other groups may be able
and willing to assist with the more routine elements of maintenance, for example
cutting back vegetation / mowing the grass.  Similar maintenance work is
undertaken by community groups for cyclepaths in other locations. 
Design 
Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton 
4.14. Following termination of WSP’s contract in March 2024, Officers have been
reviewing the significant amount of data provided by WSP to identify the
outstanding items of work which require to be completed to deliver a robust
design package and to satisfy funder requirements. 
4.15. To date, Officers have identified a number of required deliverables which were
not completed by WSP prior to termination of their commission:
• Ground Investigation
• Habitats Regulation Appraisal
• Planning Approval
• Utility Identification
• Drainage Design
• Flood Risk Assessment
• Land valuation
• Archaeological Assessment

Page 5

• Site clearance drawings
• Bill of Quantities
• Pre-construction information pack
• Delivery Plan
• Contractor procurement strategy*
• Monitoring and Evaluation Plan*
• Behaviour Change Plan*
• Community Engagement Plan*
• Business Case*
• Cycle by Design Review*
• Maintenance Plan*
*These are requirements introduced by the external funder after the contract
was awarded to WSP in 2021. 
4.16. Officers have applied for 24/25 funding from Transport Scotland’s Places for
Everyone Programme to enable this work to continue to completion of Concept
Design (Stage 2) in 2024/25.  A decision in regard to 2024/25 funding is
expected in late summer 2024. 
Phase 3 Helensburgh Town 
4.17. The Feasibility report for Helensburgh Town Centre East (Phase 3) is currently
in draft form and has been provided to the Transport Scotland Places for
Everyone team at Sustrans for comment, as required by their funding
agreement. 
4.18. Officers have applied for 24/25 funding from Transport Scotland’s Places for
Everyone Programme to enable this work to continue to completion of Concept
Design (Stage 2) in 2024/25.  A decision in regard to 2024/25 funding is
expected in late summer 2024. 
Construction (stage 5) 
Cardross Rail Station to Geilston Burn 
4.19. Cardross Rail Station to Geilston Burn.  The Council’s Roads and Infrastructure
Service have completed installation of most elements of the cyclepath through
Cardross Park, with only a small amount of fencing still to be installed. 
4.20. With the changes to the active travel funding model for 24/25 onwards, it is
expected that the costs for the remaining fencing work will require to be covered
from, as yet to be identified, internal Council budgets. 
4.21. To protect the public, the bridge over the Geilston Burn has been fenced off until
access is agreed to further land on the west side of the Burn to construct the
path through to an accessible destination.

Page 6

Land Acquisition 
4.22. The delay in award of 2024/25 funding and the review of WSPs design outputs
will result in a hiatus in relation to providing information requested by landowners
including, for example, detailed drainage designs.  Officers will be writing to
affected landowner to inform them of the termination of WSP as the design
contractor and that, once a new design team are in place, they will be in touch
with landowners to progress the discussions. 
4.23. Officers continue to engage with colleagues in Legal Services to seek to
progress approval from Council to develop a CPO for the remaining sections
of this important route. 
Risk 
4.24. Risk refers to events which have not yet happened but which could impact on
the project if they were to happen.  A risk can be negative or positive to the
project.  Risks are identified through the lifetime of the project and, where
possible, mitigation is planned to minimise negative impacts or maximise
positive impacts.  As risks evolve relatively slowly through the lifetime of a
project, it is not expect that the tables below will alter significantly within the
current stage of work. 
4.25. Project risks relate to risks which could affect the overall project.  Table 1
provides the top 5 identified project risks and planned mitigation. 
Table 1: Selected Project Risks
Risk Risk Description Risk Level Mitigation
Land
acquisition
Inability to secure
agreement for land required
within an acceptable
timescale and cost.
High 1. Engagement with landowners to
gain acceptance of design.
2. Use of Council’s Estates Team to
lead land acquisition.
3. Consideration of option of a CPO.
Funding Inability to secure necessary
funding to pay of either (a)
design work; and/or, (b)
construction costs.
Medium 1. Close engagement with external
funders to ensure project meets
their funding requirements.
2. Officers continue to explore
potential alternative funding
sources.
3. Early engagement with Members
to identify potential sources of
construction match funding.
Programme Inability to meet challenging
programme timeline.
High 1. Regular review of programme.
2. Work with key stakeholders to
understand programme drivers
and barriers.
3. Establish realistic timescales for
each package of work.
Community
support
Loss of community support
for the project.
Low 1. Consult the community on key
design decisions as appropriate.
2. Seek to deliver project which
meets community’s key
requirements.
3. Keep community informed via
project updates at appropriate

Page 7

times, including publicly available
quarterly committee reports.
Funder
requirements
Failure to meet external
funder requirements,
thereby losing funding.
Medium 1. Engage with funders to fully
understand their requirements.
2. Ensure project outcomes/outputs
meet funders’ requirements.
3. Review funding options regularly to
ensure funding sought/secured is
most appropriate to the project. 
4.26. Design risk refers to risk that the design fail to meet the required standards
and/or design conditions imposed by external factors, for example
environmental requirements. Design risks, if allowed to occur, can become
issues which may mean the project design has to be changed, which can
cause delays and cost increases. Defects or failures in the design can also
result in an increase in future maintenance costs.  Table 2 provides the top 5
identified design risks and planned mitigation. 
Table 2: Selected Design Risks
Risk Risk Description Risk Level Mitigation
Ground
Conditions
Lack of Ground
Investigation (GI) limits
understanding of the
ground conditions the
route will be constructed
over.
High 1. Design route to be as robust as
practicable.
2. Undertake Ground Investigation
works at earliest practicable date.
Ecological
Impacts
Working adjacent to the
Inner Clyde SSSI and
RAMSAR site results in
additional ecological
requirements which the
designs must meet. 
High 1. Engage with regulators, e.g.
NatureScot, at early stage in design.
2. Undertake comprehensive
ecological surveys to inform design.
3. Develop full Habitat Regulations
Appraisal to ensure ecological
requirements taken into account in
design.
Drainage Constructed at the foot of
the slope, the design will
require to cater for all run-
off and drainage from the
slopes above, while
satisfying regulatory
requirements.
Medium 1. Develop drainage designs through
design process.
2. Engage with regulators, e.g. SEPA,
at early stage in design.
3. Engage with landowners, as
repository of knowledge of existing
conditions, during design
development.
Flood Risk The route is close to and,
in locations, within areas
identified as at risk from 1
in 200 year flood events.
Medium 1. Develop flood risk assessment at
early stage in design process to
identify key areas of risk.
2. Keep flood risk assessment under
review through design process.
3. Design of cyclepath to take account
of flood risk where appropriate.
Proximity to
railway
The majority of the route is
in proximity to the live
railway and requires to
ensure the designs do not
negatively impact on the
railway.
Medium 1. Early engagement with Network Rail
to understand their safety and
operational requirements.
2. Seek to agree ‘standard’ approach
to mitigating safety and operation
requirements which can be applied
to all or most of route.

Page 8

3. Review of designs to ensure railway
safety and operational risk is
mitigated appropriately. 
Programme 
4.27. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the design and construction of further sections of the
cycleway as and when land acquisition has been concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on completing the design work, securing highly competitive external
challenge funding, committing appropriate match funding and securing access to
private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
External funding is not currently available to cover
maintenance costs.  To date, the Council has not
contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to
require social care services in later life which could
result in a future saving to the Council or HSCP.

Page 9

6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton
corridor to travel more sustainably and actively by
walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment
opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.

Page 10

6.9. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates even stronger
support for the delivery of the Helensburgh – Cardross
– Dumbarton Cyclepath from younger members of the
community than the already high overall level of
community support. Wider engagement with school
pupils indicates that the vast majority of pupils strongly
support the provision of new active travel
infrastructure, even where it would adversely impact
other modes of transport.   
Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Head of Development and Economic Growth: Fergus Murray 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
17 May 2024                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme