Democracy Spraffa

MINUTE OF THE MEETING OF THE HELENSBURGH AND LOMOND AREA COMMITTEE, HELD ON 11 June 2024

Argyll and Bute Council · 10 September 2024
Back to Helensburgh & Lomond Area Committee — 10 September 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

MINUTES OF THE MEETING OF THE HELENSBURGH & LOMOND AREA COMMITTEE HELD
ON A HYBRID BASIS IN THE PILLAR HALL, VICTORIA HALLS, HELENSBURGH AND BY
MICROSOFT TEAMS 
ON TUESDAY, 11 JUNE 2024 
Present: Councillor Mark Irvine (Chair) 
Councillor Math Campbell-Sturgess
Councillor Maurice Corry
Councillor Fiona Howard
Councillor Paul Donald Kennedy 
Councillor Ian MacQuire
Councillor Gary Mulvaney
Councillor Gemma Penfold 
Attending: Stuart McLean, Committee Manager 
Claire Kennedy, Depute Head Teacher, Hermitage Academy
Mhairi Stewart, Depute Head Teacher, Hermitage Academy
Rona Gold, Communities & Partnership Manager
Kirsty McLuckie, Community Development Officer
Mark Calder, Project Manager
Arlene Cullum, Senior Development Officer
Colin Young, Strategic Transportation Delivery Officer
Charlotte Craig, Business Improvement Manager, HSCP
Inspector Bart Simonis, Police Scotland 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Graham Hardie and Iain Paterson. 
2. DECLARATIONS OF INTEREST 
Councillor Math Campbell-Sturgess declared a non-financial interest in relation to item 11
of the agenda (Supporting Communities Fund 2024/25) as a family member attends Route
81. He advised that he would leave the room and take no part in the consideration of this
item of business. 
3. MINUTE OF THE MEETING OF THE HELENSBURGH AND LOMOND AREA
COMMITTEE, HELD ON 12 MARCH 2024 
The Minute of the meeting of the Helensburgh and Lomond Area Committee, held on 12
March 2024 was approved as a correct record. 
4. PUBLIC QUESTION TIME 
Having noted that there were members of the public in attendance, the Chair invited them
to submit any questions they may have.     
Sarah Davies, Helensburgh Community Council
Why is the Helensburgh Waterfront Development not on the Agenda today?
At the last meeting a decision was taken, in private, to choose two preferred bidders and
since then we have heard nothing. We had expected the decision to be discussed at the

Page 2

next Policy and Resources Committee but once again it was not on the agenda. Why was
that?
We had heard that this Committee would be holding a Business Day to discuss the bids
further, has this happened? If not, when will it happen, who will be involved and how will
any decisions be reported to Helensburgh residents.
Following the decision to move forward without the Helensburgh Community Council’s bid,
we wrote to all Argyll and Bute Councillors expressing our serious concerns with the
process. We believe community views have been excluded from the process and the
overall selection of bids is based on a flawed process and weak evidence. We are
concerned this will lead to a large retail development on the waterfront site, against the
wishes of the community and harmful to existing and fragile retail in our town. 
This letter was sent to all Argyll and Bute Councillors, the Leader and Chief Executive of
the Council our local MSP’s and Mp’s. We have since then had replies and discussions
with our local MSP and MP. 
We have had acknowledgements from some Argyll and Bute Councillors, but not a single
response from any of you our local councillors who sit on this Committee that made that
decision. 
We have received a response from an officer, Ross McLaughlin Head of Commercial
Services informing us that the Community Council will be further consulted once the
selection has been made and the proposal moves to planning. In our view this is too late.
What will now be the process for the final selection of a bidder for the Waterfront?
When and how will the community be informed or involved in any of the decisions or
discussions about the development of this prime and valued site in our town?
How and when will this committee engage with the community about their plans? 
The Chair advised that an Area Committee Business Day was scheduled for 26 June for
Members and Officers to discuss the Helensburgh Waterfront Development further and
that a report regarding the project would be considered at a future meeting of the Policy
and Resources Committee. 
Angela Anderson, Plastic Free Helensburgh
Question 1
Plastic Free Helensburgh have seen an increased amount of litter around Helensburgh
Pier and beach area, as a consequence of the better weather and longer evenings.
However, we are concerned that it has been reported that Argyll and Bute Council
consider the increase of litter and vandalism due to the opening of the Skatepark and in
Plastic Free Helensburgh’s opinion even though both happened around same time we do
not consider them linked. Can you agree that these are not linked as suggested in the
report?
Councillor Campbell-Sturgess agreed that it would be impossible to link the litter and
vandalism with the opening of the Skatepark.

Page 3

The Project Manager advised that there was no intention to cast dispersion on anyone in
the Roads and Infrastructure weekly update to Members and that it was simply to highlight
the increase of vandalism and littering in that area.
Question 2
This is the third quarterly meeting I have brought up the issue of drainage and flooding
which continues to be an issue in the locality, especially due to the increased rainfall in the
last week.
Plastic Free Helensburgh are keen to work with the Council on these issues and would
like to have a campaign locally to ensure the community are looking after the drainage
system but we feel we cannot do this in an enabling way without support from the Council.
I have been told that the drains are classed as ‘not blocked’ if there is no standing water
on them, which doesn’t help when the town is built on a hill.
Can the Committee ensure this issue will be looked into?
The Chair advised that there is a significant amount of ongoing work looking into drainage
and that further discussions on this matter would take place at the Roads and
Infrastructure Services Update item. 
Councillor MacQuire advised that clarification is needed on when drains are being cleared
as he had received mixed communications from the Roads Department.
Lindsey Young, Cyclepath Action Group
I would like the Committee to consider the outstanding work undertaken WSP which is
listed in the Helensburgh, Cardross and Dumbarton Cyclepath update report. A lot of this
work can only be done in the summer months, consequently if it is not done within the
next 2 or 3 months it won’t be able to be done until next year, meaning another year to
wait. Can the Committee ensure that these studies are completed this summer?
The Chair advised that he would raise Ms Young’s comments to the Project Lead at the
agenda item. 
5. POLICE SCOTLAND UPDATE 
Consideration was given to an update which provided information on the ongoing work of
the Service and information on crime statistics; engagement with housing providers and
Argyll & Bute ASB to target anti-social behaviour among individuals and properties;
support to reduce the impact of acquisitive crime; continuing to support and improve
awareness to front-line officers to ensure they are equipped and trained to provide a victim
centred approach; road safety work and youth engagement activities. 
Decision 
The Helensburgh and Lomond Area Committee considered and noted the information
provided in the report. 
(Reference: Report by Inspector Bart Simonis, Police Scotland, dated June 2024,
submitted)

Page 4

6. ARGYLL AND BUTE COUNCIL SECONDARY SCHOOL ATTAINMENT
REPORTS 
(a) Hermitage Academy 
The Committee heard from Ms Kennedy and Ms Stewart, Depute Head Teachers
at Hermitage Academy, who spoke to the school report which had been provided
to Members. The report included information on S3 ACEL attainment in literacy
and numeracy; the pass rates of national qualifications; and data from Insight
Scotland. Information in relation to wider achievement qualifications; equity and
attainment; and Pupil Equity Funding was also provided. 
Decision 
The Helensburgh and Lomond Area Committee noted and considered the contents
of the report and information provided. 
(Reference: Report by Executive Director with responsibility for Education, dated
June 2024, submitted) 
7. AREA PERFORMANCE REPORT - FQ4 2023/24 
The Committee gave consideration to the Area Performance Report for financial quarter 4
of 2023/24 (January to March 2024) which illustrated the agreed performance measures
for this period. 
Decision 
The Helensburgh and Lomond Area Committee noted and considered the performance
and supporting commentary as presented; 
(Reference: Report by Executive Director with responsibility for Customer Support
Services, dated 15 May 2024, submitted) 
Having noted the officers in attendance, the Chair advised that it was his intention to vary
the order of business to take the following agenda items out of sequence. The order in
which they are minuted, is the order in which discussion took place. 
8. ROADS AND INFRASTRUCTURE SERVICES UPDATE 
The Committee gave consideration to a report which provided links to the recent activities
of Roads and Infrastructure Services. 
Decision 
The Helensburgh and Lomond Area Committee: 
1. considered and noted the contents of the report; and 
2. agreed that a Business Day be held to explore flooding related issues within the
Helensburgh and Lomond Area with relevant stakeholders invited to attend and
contribute.

Page 5

(Reference: Report by Executive Director with responsibility for Roads and Infrastructure
Services, dated May 2024, submitted) 
9. ARGYLL AND BUTE HEALTH AND SOCIAL CARE PARTNERSHIP
PERFORMANCE REPORTS - FQ3 AND FQ4 2023/24 
Consideration was given to the Health and Social Care Partnership Performance Reports
for financial quarter 3 and 4 of 2023/24. 
Decision 
The Helensburgh and Lomond Area Committee considered and noted the Performance
Reports for financial quarter 3 and 4 of 2023/24. 
(Reference: Report by Head of Strategic Planning, Performance and Technology, Argyll
and Bute Health and Social Care Partnership, dated June 2024, submitted) 
10. HELENSBURGH OUTDOOR MUSEUM - ARTS STRATEGY UPDATE JUNE
2024 
The Committee gave consideration to a report providing background to the Helensburgh
Outdoor Museum, its governance and funds. The report also invited Elected Members to
take up the Chair and Vice Chair roles of the Design Panel as well as seeking approval for
a change to the Terms of Reference. 
Decision 
The Helensburgh and Lomond Area Committee: 
1. agreed that the Chair and Vice Chair of the Area Committee be invited to fill the
positions of Chair and Vice Chair of the Design Panel; and 
2. approved the change to the Terms of Reference to allow the Design Panel to approve
variation to funding amounts of approved applications that do not amount to more than
the 50% of the total project costs. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth, dated 30 April 2024, submitted) 
11. SUPPORTING COMMUNITIES FUND 2024/25 
Consideration was given to a report which detailed recommendations for the award of the
Council’s Supporting Communities Fund (SCF) for the 2024/25 round of funding that had
been made available for distribution by Council to organisations in the Helensburgh and
Lomond area. 
Decision  
The Helensburgh and Lomond Area Committee agreed that the 17 applications, marked
as ‘Award’ and ‘Partial Award’ within Appendix 1 of the report, are awarded funding from
the Supporting Communities Fund Budget totalling £31,175.50, as follows:

Page 6

Ref Applicant Recommendation Amount
Requested
Recommended
Award 2024/25
1 Cove Park Award £2,500.00 £2,500.00
2 Fun First Award £2,500.00 £2,500.00
3 Route 81 Youth Project Award £2,500.00 £2,500.00
4 Helensburgh Community
Woodlands Group Award £2,500.00 £2,500.00
5 Argyll & Bute Citizens Advice
Bureau - HL Award £2,300.00 £2,300.00
6 Garelochhead Senior Citizens Award £800.00 £800.00
7 Gibson Hall Award £2,500.00 £2,500.00
8 Arrochar & Tarbet Community
Development Trust Award £2,500.00 £2,500.00
9 Gareloch Riding for the
Disabled Association Award £2,092.00 £2,092.00
10 Garelochhead Station Trust Award £1,200.00 £1,200.00
11
The Edible Garden at Rhu Hall
– Rhu and Shandon Community
Education Centre
Award £950.00 £950.00
12 Live Music Now Scotland Award £614.40 £614.40
13 Peninsula Choir Award £2,021.00 £2,021.00
14 Rosneath Community Garden Award £1,018.00 £1,018.00
15 Cove and Kilcreggan
Community Council Award £2,200.00 £2,200.00
16 Plastic Free Helensburgh Award £980.00 £980.00
17 Friends of Loch Lomond & The
Trossachs Partial award £2,500.00 £2,000.10
18 Peaton Pealers No award £2,500.00 £0.00
19 Grey Matters No award £2,250.00 £0.00
20 Helensburgh Heritage Trust No award £1,500.00 £0.00
21 Helensburgh Amateur Athletics
Club No award £2,000.00 £0.00
22 Woodlandwise Forest School
CIC No award £2,500.00 £0.00
23 Helensburgh Gaelic Group No award £2,500.00 £0.00 
(Reference: Report by Chief Executive, dated 11 June 2024, submitted) 
12. REQUEST FOR FINANCIAL ASSISTANCE FROM HELENSBURGH AND
DISTRICT TWINNING ASSOCIATION 
A report providing information on a request from the Helensburgh and District Twinning
Association for financial assistance to help assist with the costs of hosting visitors from
Thouars in 2025 was considered. 
Decision 
The Helensburgh and Lomond Area Committee agreed to award the sum of £625 from the
Helensburgh and Lomond Area Twinning Budget for 2024/25 to Helensburgh and District
Twinning Association.

Page 7

(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated May 2024, submitted) 
13. APPOINTMENTS TO OUTSIDE ORGANISATIONS 
A report asking the Committee to consider making appointments to a number of local
bodies/organisations within the Helensburgh and Lomond area was considered. 
Decision 
The Committee agreed to make the following appointments: 
Organisation Elected Member 
Cardross Trust  Councillor Paul Kennedy
Dunbritton Housing Association Councillor Iain Paterson was
proposed by Councillor Mark Irvine,
seconded by Councillor Fiona
Howard.   
Councillor Gary Mulvaney was
proposed by Councillor Gemma
Penfold, seconded by Councillor
Maurice Corry.   
The motion to appoint Councillor Iain
Paterson was carried by 5 votes to 3
and the Committee agreed to
appoint Councillor Iain Paterson to
the position. 
Helensburgh and 
Lomond Locality Planning Group
Councillor Fiona Howard
Gourock, Dunoon and 
Kilcreggan Harbour 
Reference Group
Councillor Mark Irvine
Dunbartonshire Educational Trust Councillor Fiona Howard 
Glasgow Airport 
Consultative Committee
Councillor Graham Hardie - subject
to confirmation of acceptance of the
appointment. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 13 May 2024, submitted) 
14. DRAFT HELENSBURGH AND LOMOND AREA COMMITTEE WORKPLAN 
The Helensburgh and Lomond Area Committee workplan was before members for
information. 
Decision

Page 8

The Helensburgh and Lomond Committee noted the contents of the workplan. 
(Reference: Helensburgh and Lomond Area Committee workplan, dated 11 June 2024) 
Having noted members intentions to raise questions that would likely involve the
disclosure of exempt information as defined in Paragraph 9 of Part 1 of Schedule 7A
to the Local Government (Scotland) Act 1973 the Chair moved and the Area
Committee agreed to the exclusion of the press and public in terms of Section
50(A)(4) of the Local Government (Scotland) Act 1973. 
15. HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE 
Consideration was given to a report updating Members on the progress made since the
Helensburgh and Lomond Area Committee on 12 March 2024 in relation to the delivery of
a dedicated, high quality walking and cycle route linking Helensburgh, Cardross and
Dumbarton. 
Decision 
The Helensburgh and Lomond Area Committee: 
1. instructed Officers, subject to securing external funding, to seek a new design team to
continue development of Phase 1 and Phase 2 designs to complete Developed Design
and Technical Design stages; and 
2. supported progression of the project to full Technical Design, as required by the
external funder. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth, dated 17 May 2024, submitted)