Rosneath, Phase 2 Marina to ‘Y’ Junction at Castle Caravan Park
Stage 1&2 Combined, Options Feasibility Report
DATE:  February 2024  REF:  501047 VERSION:  Draft v3

Page 2

MARK RINKUS                                   
Managing Director                                   
Mark.rinkus@connectedtp.com                 
Click the icons to view our website and LinkedIn                   +44 7515834101 
Contents
1 OUTLINE BUSINESS CASE ................................................................................... 1
2 OPTIONS DEVELOPMENT AND APPRAISAL ....................................................... 17
3 DEVELOPING THE CONCEPTS ........................................................................... 33
4 DESIGN PROCESS QUALITY AND INNOVATION ............................................... 37
5 PROJECT DELIVERABILITY AND DESIGN COLLABORATION ............................ 46
APPENDIX A – NETWORK AND UTILITIES ................................................................. 43
APPENDIX B – SOCIAL AND EQUALITY IMPACT ASSESSMENT (SEQIA) ................... 45
APPENDIX C – STAGE 1 ROAD SAFETY AUDIT AND DESIGNERS’ RESPONSE ............ 46
APPENDIX D – PRELIMINARY ECOLOGICAL APPRAISAL (PEA) ................................ 47
APPENDIX E – DESIGNERS RISK REGISTER .............................................................. 48
APPENDIX F – PRE-APPLICATION PLANNING RESPONSE ......................................... 49

Page 3

1 | P a g e
www.connectedtp.com 
1 OUTLINE BUSINESS CASE
1.1 Introduction and Study Overview
Rosneath supports a community of around 1,2601 people who live within the
settlement of Rosneath / Clynder. The village is located 3.8km away from the
village of Kilcreggan (population 1,320) which of located on the western coast of
the peninsula.  The villages, whilst near to each other form part of the circular
route around the peninsula starting and ending at Garelochhead, linked by the
B833.  The route is a popular visitor destination due to the scenic views of the
coast.  
During 2018, the Rosneath to Marina section of the Active Travel route was
constructed by Argyll and Bute Council (ABC). The route provided a 2.5m wide
surfaced shared use cycle footway connecting Rosneath village and the
associated footway/service infrastructure to the yacht marina and small industrial
/ employment units located on the southern outskirts of the village.  This is Phase
2 of the route which would extend the route from the Marina around Camsail Bay
to the ‘Y’ junction formed on the B833.  The junction is of strategic importance as
it provides road access to the Castle Bay tip of the peninsula and the Rosneath
Castle Caravan Park.  Due to resourcing and funding issues, the concepts
developed for the phase 2 route were not shared with the community.  The
publication of an updated active travel route design standard in 2021 necessitated 
1 National Records of Scotland (15 August 2013). "Appendix 2: Population and
households on Scotland's Inhabited Islands" (PDF). Statistical Bulletin: 2011
a revisit of the original route options.  Following identification of further funding,
this project seeks to reinvestigate the original route concepts and through
working with the local community, develop the concepts and identify a preferred
concept that can support a bid for future funding and detailed design.  
Notwithstanding, a future Phase 3 of the route will be required to complete the
route by connecting the ‘Y’ junction to Rosneath Castle Caravan Park and
therefore enabling access by visitors and residents to travel between both places
by travel modes other than private car.
This Outline Business Case (OBC) seeks to provide a ‘snapshot’ of the phase 2
project in context to the local area, setting out a baseline from which future
monitoring and evaluation can be referenced.
This report should be considered in conjunction with the Stage 1 Community
Feedback and Monitoring and Evaluation Report; reported separately. 
Census: First Results on Population and Household Estimates for Scotland Release
1C (Part Two) (PDF) (Report). SG/2013/126. Retrieved 14 August 2020.

Page 4

2 | P a g e
www.connectedtp.com 
1.2 Study Location Plan
The Proposed Study Area Is Shown In The Following Figure 
2 A project which enables travel behaviour change.
1.3 Recent Study History
Whilst the phase 1 route was supported by a funding bid, no details of the route
business case or route design are available. Only PDF copies of the original 3
concept options for phase 2 have been provided by ABC.
1.4 Project Alignment with National and Local Strategy / Policy 
As an active travel enabler2, this project seeks to support the connection of 20-
minute neighbourhoods3, linking people and place whilst enabling the movement
of people of all ages and abilities.  The project will seek to reduce car
dependency, reducing car dominant short journey trips whilst promoting the
benefits of healthier walking and cycling in undertaking everyday journeys by
these sustainable travel modes.
The project will also likely directly contribute to safety and resilience objectives
through the creation of a safe walking and cycling route.
The project is therefore directly and indirectly aligned with national, regional and
local policy and aligned with the strategy objectives of Argyll and Bute Council
(ABC).  
The following strategies and policies are considered relevant to this study:
• The Scottish Government’s National Performance Framework
• Scottish Government Infrastructure Investment Plan
3 https://www.sustrans.org.uk/our-blog/get-active/2020/in-your-community/what-is-a-20-minute-
neighbourhood

Page 5

3 | P a g e
www.connectedtp.com 
• Active Scotland Outcomes
• Physical Activity Implementation Plan – A More Active Scotland
• Scottish Government Creating Places
• Preventing Obesity in Scotland
• The National Walking Strategy
• The Cycling Action Plan for Scotland (CAPS)
• The Climate Change Plan
• The Road Safety Framework; and
• The National Transport Strategy (NTS)
A figure summarising the Scottish Governments journey towards reducing car
dependency for single occupancy trips is presented below. 
4 National Records of Scotland (15 August 2013). "Appendix 2: Population and
households on Scotland's Inhabited Islands" (PDF). Statistical Bulletin: 2011
Census: First Results on Population and Household Estimates for Scotland Release
1C (Part Two) (PDF) (Report). SG/2013/126. Retrieved 14 August 2020.
1.5 Population and Demographic Assessment
Rosneath currently has a population of 1,2604 residents based on the 2021
census. The population has overall has been falling slowly since 2001,
summarised in the following table.
Year Rosneath Population
2001 1,400
2011 1,324
2021 1,260
The population is evenly split between males and females and slightly weighted
towards ages 40 years old and upwards.  The peninsula has more 70-year-old
people than under 16-year-olds.5 
5 https://www.nrscotland.gov.uk/files//statistics/scap/figures-maps/scap-figure-
18.pdf
The National Picture

Page 6

4 | P a g e
www.connectedtp.com 
The peninsula is challenged with migration as a number of younger adults will
leave the area pre-30’s to pursue employment and careers before returning in
later life.
SIMD Assessment
To understand Rosneath’s social challenges, the Scottish Index of Multiple
Deprivation (SIMD) area statistics for 2022 were examined.  The results indicate
that Rosneath is ranked low overall at 1,814 out of 6,976 places, with income,
Crime, Employment, Health and Housing ranking low ranking at 3 out of 10. 
Crime surprisingly scored more favourably at 6 out of 10. Geography and Access
are also notable challenges. 
1.6 Rural Deprivation 
6 The Scottish Rural Policy Centre (SRUC) published a report entitled ‘Rural
Scotland in Focus’
In recent years there has been a greater understanding of the impacts of
transport poverty; where people lack access to services or work and the
contributions that a lack of affordable transport options creates.    
It is important to consider the aspect of rural inequalities, which creates
challenges to living that are different from communities within larger urban
areas6. In reviewing employment in rural areas, the SRUC report highlights a
significantly larger percentage of those in part-time or smaller contract jobs, often
with lower hourly rates or salaries than counterparts in urban population centres.
Many rural areas have become increasingly reliant on the tourism industry, as a
result, many jobs are seasonal and in demand, reducing the overall hours or
contracts available over the year. 
Fuel Poverty Living outside larger urban areas is likely to increase the costs of
goods overall – primarily due to the cost of the supply chain network required.
This can be seen in the cost of fuel with a predominant market of independent
providers, unable to offer the prices of larger national outlets. This issue raises a
secondary cost to local residents, with rural communities relying more on private
transport, and often having to travel further for services. Ultimately, for residents
of communities such as those in Rosneath and Islay, more fuel is required to
travel for day-to-day work and leisure.  SIMD Extract for Rosneath

Page 7

5 | P a g e
www.connectedtp.com 
A report on the Minimum Income Standard for Remote Rural Scotland and
research on the Minimum Income Standard for Scotland highlights that the cost
of food and consumable goods are between 10-50% higher in rural areas, whilst
clothing and household goods are between 30-50% higher than in urban areas.
These estimates do not consider the impact of living in the most remote locations
where the costs associated with the movement of goods and services can be
even more disproportionate.
The cycling organisation Sustrans through their own research have identified
three key areas which can assist in addressing transport poverty.  These are:
• People-centred transport planning;
• Provision of quality accessible, frequent and affordable public transport
service; and
• Development of a transport network that supports the movement of
people to places irrespective of user’s social status.
Whilst these options may not address the inequalities of rural transport
challenges; improving accessibility and access for goods and services, through
sustainable travel modes will provide the community with improved travel choices
better aligned with the National Transport Policy.  In time, these measures have
the potential to reduce car dependency for short journey trips whilst contributing
to people’s health and wellbeing through increasing daily physical activity.  The
reprioritisation of our streets, away from the private car, combined with the
reallocation of road space to support sustainable travel, landscaping, ecological
and placemaking will improve the social and environmental experience of the
area.
Transport and access within Rosneath can be concluded to be a core
consideration in helping to manage the challenges of rural social deprivation.
1.7 Understanding Place
Rosneath Village
Rosneath forms is the main service centre for the peninsula.  The coastal village
is located along the B833 road which passes through the village and extends
around the peninsula.  Few properties actually front the road with the Phase 2
project located on the southeastern outskirts of the village within an area with no
frontage properties.
Rosneath supports access to several everyday community services:
• The Rosneath Co-op, supplying most everyday essentials;
• Local butchers and bakers;
• Rosneath Primary School;
• Community Library; and
• Churches, supporting all aspects of community activity. 
Kilcreggan and Clynder
Kilcreggan is a small coastal village located to the south west of Rosneath on the
coast on the peninsulas opposite coast.  The settlement is located around 3.8km
away via the B833. Kilcreggan has a history dating back to the 19th century and

Page 8

6 | P a g e
www.connectedtp.com 
was originally a popular destination for holidaymakers from Glasgow. The
settlement includes access to Gourock via a ferry across the Clyde and a number
of everyday services including a Cost Cutter supermarket.  The village has strong
links with Rosneath and Clynder with residents of the villages’ active between
settlements.
The village is known for its scenic beauty, with views across the Clyde to the
picturesque town of Gourock. Kilcreggan is also notable for its Victorian pier,
which was once a crucial transportation link for steamships connecting the area
with other parts of the Clyde and beyond.
Infrastructure
The B833 is formed as a bi-directional traffic route c.7m wide linking
Garelochhead around the peninsula.  The road's is adopted and maintained by
ABC with a total length of c.26km. 
In general, the carriageway is formed with unbound edges incorporating hard
strips in some location. The carriageway surface blends into the adjacent verge. 
The route wynds through coastal topography with surface water drained via
ditches provided adjacent to the carriageway.  From the in-land side of the road,
the drainage ditches are culverted under the road and discharged directly into the
sea.  There is no provision for the storage or treatment of road water runoff. In
most locations, the embankment of the road is steep and unsuitable to pass
oncoming vehicles.  In most instances, such as on and near bends, opposing
vehicles are required to slow down to pass.
The road pavement, in most locations, is in generally good condition with many
locations showing evidence of recent resurfacing.
Within the extent of the rural villages dotted along the B833 footways and street
lighting is provided, typically to an outdated standard with the pavement less
than 1.5m wide. 
The road is subject to a de-restricted speed limit along length with 30mph speed
limits provided within the village extents.  Vehicle speeds do however vary by
location.
Pedestrian and cyclist activity occurs on the carriageway with pedestrians and
cyclists giving way to oncoming vehicles.  In some locations, this requires cyclists
to dismount noting the adjacent verge can be steep, narrow and unstable
underfoot. 
With no street lights, for most of the route, the movement of pedestrians and
cyclists is restricted to occur within the hours of daylight or more likely during the
summer period.
Parking and Access
As relevant to this study, a single public car parking lay-by is provided at Camsail
Bay supporting visitors who wish to stop, park and inspect the views of the bay.

Page 9

7 | P a g e
www.connectedtp.com 
There are no parking restrictions within the peninsula.  Within the villages, for a
number of residents, parking on-street along their property frontage is required.  
There is no provision for publicly accessible electric vehicle charging points in
Rosneath. 
Tourism, Visitors and Local Economy
The peninsula is understood to be a popular visitor destination attracting visitors
from a wide geographical area.  Peak visitor season is understood to be between
May and September with visitors arriving by either the Gourock ferry to
Kilcreggan or via the B833 from Garelochhead.  Visitors drive or cycling the route.
Few visitors are understood to be associate with visiting Rosneath directly but will
pass through the village either touring the area or to access services.  The
community travel between Rosneath and the adjacent Kilcreggan, with the
Rosneath Castle Caravan Park located between both.  
1) Faslane Naval Base
The Faslane Naval Base is located to the northeast on the other side of Gareloch
and is of significant economic importance to the local community and the wider
region. The base provides employment opportunities for many people, including
both military personnel and civilian staff. The influx of personnel and their
families contributes to the local economy through housing, education, and various
other services.
The base's operations also stimulate economic activity in the surrounding areas,
as local businesses provide goods and services to support the needs of the naval
personnel. Additionally, infrastructure development and maintenance at the base
generate contracts for local companies, further contributing to the regional
economy.
The strategic importance of Faslane as a naval base plays a role in sustaining
economic activity in the local community through employment, business
transactions, and associated services. 
2) Rosneath Castle Caravan Park
Rosneath Castle Caravan Park offers a range of caravan and camping facilities for
tourists and visitors. The park provides static caravans for rent or sale, as well as
spaces for individuals bringing their own caravans or tents. 
Camsail Bay parking lay-by

Page 10

8 | P a g e
www.connectedtp.com 
Given its name, Rosneath Castle Caravan Park overlooks Castle Bay , and visitors
have the opportunity to enjoy the scenery and take part in the recreational
activities offered along the coast. The park provides a family-friendly environment
with recreational facilities, playgrounds, and some limited on-site facilities. 
The park also has the only licensed bar in Rosneath, its proximity supports a
strong relationship with visitors to the park travelling to access facilities within
Rosneath.  Given the scenic beauty of Camsail Bay, the walking and cycling
demand between these places is understood to be strong.
The park is subject to continual expansion with 40 new bays recently formed
(2023) to support visitors travelling by motorhomes.  In addition to generating
additional pedestrian and cyclist traffic along the B833 between the Rosneath and
the park, the ongoing expansion will also likely increase the traffic flow along the
B833 route and encourage a greater number of larger vehicles to visit.  This will
likely be to the detriment of pedestrians and cyclists using the route in the
absence of a Phase 2 path being provided.
3) Rosneath Marina
The Rosneath Marina is subject to a ‘live’ planning application to redevelop the
site to provide c.175 luxury new houses (09/01089/DET).  Whilst the application
has been approved by ABC in 2019, the detail relating to the proposed
infrastructure and operation is yet to be determined.  
The development is proposed to be accessed through a number of changes to the
existing road geometry.  These include:
• Minor widening of the carriageway along the Marina frontage to include
provision for a vehicular right-turn stacking lane;
• Extension of the 2.5m wide constructed phase 1 active travel path along
the Marina frontage to a point around mid-way along Camsail Bay.  The
proposed path will however only be 2m wide with a 0.5m wide verge;
• Reduction of the B833 speed limit from 60mph to 40mph limit from the
midpoint along Camsail bay extended into Rosneath.  This includes
vehicle speed management measures consisting of signage and rumble
strips.
Utilities and Known Constraints
To understand the utilities within the area, a search of utility apparatus within the
study area was undertaken.  These are summarised as follows:
Water supply 
Scottish water GIS plan has indicated a 90mmm HPPE pipe below / verge of the
B833 road along the extent of the route. Consideration should be taken for any
works undertaken within the vicinity of the pipe work in line with Scottish water
guidance.  The apparatus plan is shown in Appendix A.
Electricity
Line search before you dig has indicated multiple HV mains cables in the vicinity
of the project route. These are slung alongside the breakwater. Consideration

Page 11

9 | P a g e
www.connectedtp.com 
should be taken for any works undertaken within the vicinity of the cables In
line with SSE guidance. The apparatus plan is shown in Appendix A.
Foul/Surface Water
Scottish water GIS plan has indicated a water main is present along the B833. 
The apparatus plan is shown in Appendix A.
Communications
No apparatus found. The apparatus plan is shown in Appendix A. 
Gas
No apparatus found. 
Flood Risk
An extract of the SEPA flood risk for the project area is included in Appendix A. 
The extract confirms that the project route is at risk to tidal flooding from a
1:200-year event.
Landownership and Rights of Access
Landownership within study area consists of 10 private land owners whose land
interests flank the B833 road corridor.  All private owned land is undeveloped and
consists of vegetation and a former quarry.  The land is overall estimated to be of
low commercial value. 
The road and 2m of grass verge between the high-water line and opposing tree
line are owned and maintained by ABC.  There are 10 landowners fronting the Study Area

Page 12

10 | P a g e
www.connectedtp.com 
1.8 Understanding Travel Behaviour
The majority of pedestrian activity is located along the B833 within the
settlements of Rosneath but it understood that the trips by the community along
Camsail Bay towards the Castle Caravan Park are currently undertaken.  Walking
between the park and Rosneath village centre takes around 30 minutes or 2.2km.  
As a coastal route, travel mode decision are impacted by weather including
storms and, in some places, tidal surges (Camsail Bay).  
The current lack of coherent walking and cycling infrastructure combined with the
narrow road, perception of high vehicle speeds and the width of large vehicle are
noted by the community to be barriers to travel along the route. 
School Travel
Rosneath Primary School is located on the eastern edge of Rosneath (furthest
from the project area). In support of this project a Hands-up Survey (HuS) was
undertaken during November 2023 to understand how the community’s younger
member’s travel.  The results of the survey show the that pupil’s dependency on
travel by walking (50%) and car (40%).  Around 10% of the surveyed children
cycle to school.
The school engagement has confirmed that a number of the villages younger
members do own bikes and do regularly walk or cycle along the route.  The
school’s remote location relative to the study area is however unlikely to be a key
indicator of suppressed active travel demand. 
Public Transport
Bus services around the peninsula are operated by Garelochhead Coaches who
provide public transportation services in various regions of Scotland. They offer a
schedule of bus services connecting the various villages around the peninsula.
It is understood that the service is currently subsidised through HITRANS.
1.9 Baseline Data
To support this project, a number of data sources were commissioned to provide
a snapshot of people and traffic volumes speeds and movements during 2023.  
The surveys consisted of 3 Automatic Traffic Counters (ATCS) installed for a 7-
day period along the route.  The counters recorded all vehicle movements
including speeds by direction continuously.  Following consultation with the
project steering group, the counters were located at the following strategic
locations:
• ‘Y’ junction near Castle Caravan Park;
Travel Mode Morning Trip Afternoon Trip
Walk 19 20
Cycle 1 1
Bus 0 0
Scooter 0 0
Car 14 14

Page 13

11 | P a g e
www.connectedtp.com 
• Adjacent to the yacht marina; and
• In the middle of Camsail Bay.
In addition to the ATC’s a number of Non-Motorised Users (NMU) surveys were
also undertaken during the same period.  The NMU survey was located at the
busiest locations along the route corridor. 
ATC Results
The results of the surveys indicate that the typical traffic volumes along the
corridor are around 1,592 vehicles per day, roughly split at 800 vehicles per day
in both the northbound and southbound travel directions.  
The corresponding 85% vehicle speed is 44mph and is likely to be a result of the
narrow road route, built-up features of the village and the presence of people.
Traffic composition at this location is 90% cars or light vans with 10% classed as
medium weight and no Heavier Goods Vehicles (HGVs).
The traffic volumes are again around 1740 vehicles per day, roughly split at 900
vehicles per day in both the northbound and southbound direction indicating that
vehicular trips observed within the ‘Y’ junction near Castle Caravan Park continue
along this route. The corresponding 85% vehicle speeds are slightly increased
relative to the ‘Y’ junction near Castle Caravan Park at 41mph with southbound
speeds similar to northbound. 
Traffic composition at this location is 88% cars or light vans with 12% classed as
medium weight and no Heavier Goods Vehicles (HGVs).
Traffic data sets have been supplied separately. 
NMU’s
The NMU surveys were located near the ‘Y’ junction supporting access to Castle
Caravan Park.  The survey captured all pedestrian and cyclist numbers by travel
direction within a 24hr day 00:00 to 00:00 over 5 weekdays and 2 weekend days. 
Traffic Analysis, Speed, Volume and NMU Analysis

Page 14

12 | P a g e
www.connectedtp.com 
The results of the surveys indicated that over the 7 surveyed days the typical
daily pedestrian flow was 8 people (4 per direction).  Most days no cyclists were
recorded although one day saw a total of 9 cyclists.  
Road Safety 
A review of the road safety records using the Crashmap website7 indicates that
over the last 5 years between 2018 and 2022, there have been no recorded road
safety incidents within the study area that have involved personal injury. 
This doesn’t mean that no accidents have occurred as it is possible that more
recent incidents have not yet been published.   
7 https://www.crashmap.co.uk/Search 
Current Travel Patterns
The 2011 census data for Rosneath was examined to understand current travel
behaviours and travel patterns within the peninsula.  However, no data was
available.   
Rosneath Accident History 2018 - 2022

Page 15

13 | P a g e
www.connectedtp.com 
It is noted that more rural locations are more likely be more dependent on private
car use when compared with the Scottish average.  Travel mode preference in
Rosneath is anticipated to reflect this trend.
Understanding Roseneath’s Demographics
The Rosneath population profile is aligned with the Scottish average (2011 census
data) for the age group 0–16-year-olds. There is then a significant drop in 16-29-
year-olds as young people migrate away from the community, however, it levels
back out with the Scottish average for 30-44 as many people return to the area in
their adult years.  The figures remain level for 45-59 year olds but are
significantly higher for 60-74 year olds. 
Where do People Currently Cycle?
Cyclist demand around the peninsula is understood to be ‘healthy’ with cyclists’
day tripping from Glasgow to cycle the peninsula circuit.
A number of circular walk and cycle routes have been published.  These routes
are in the majority off-road although cycling around the B833 is noted to be
popular.
Cycling in Rosneath is popular, although the number of people cycling within the
project route is understood to be comparably low.  The route between the ‘Y’
junction near Castle Caravan Park and Rosneath is c.1.2km in length and is
comfortable to walk or cycle during pleasant weather.  Anecdotal evidence
provided by the community indicates that the project route is popular with
tourists and is used to cycle/walk whilst exploring the area.    
Tourists will visit the peninsula by car and tour. This results in a number of tourist
vehicles also driving along the project route.
To assist in understanding existing cycle and walking use on the island the Strava
fitness app was examined.  The app records users cycling and walking activities
by location and can be a useful indicator of walking and cycling activity.
An extract as appropriate for Rosneath is provided as follows with Blue colours
showing locations of greater walking and cycling intensity, 
Rosneath Cycling Activity from Strava
Project Extent

Page 16

14 | P a g e
www.connectedtp.com 
Forecasting User Group Demand
It is not possible to forecast with certainty the likely future walking, cycling and
wheeling demand for the project.  With reference to the views reported within
the Community Feedback Report, the community consists of 1,260 people.  Of
these, 56% regularly visit Castle Caravan Park (more than twice a week) and
11% visit every day. Only 6% of the surveyed indicated they currently regularly
travel the project route every day.   with 82% indicating the provision of the
route would encourage them to walk or cycle.  Using these percentages, it is
estimated that the project route will support around 34 journeys regularly per
week or an average of 4 journeys per day.
Allowing for a similar level of tourist trips during the peak seasons of the year,
the project may support a weekly total usage of around 74 trips per week or 8
trips per day.
This estimate is noted to be around double the current surveyed daily cyclists’
numbers recorded. 
1.10 Connecting Rosneath
The project aims to provide a high-quality walking and cycling facility which will
improve travel link options with the ‘Y’ junction near Castle Caravan Park.  
The inclusion of public realm works will improve the local amenity reducing
dependency on car use, creating of spaces to stop and dwell and enjoy the
scenery, wildlife and views.
The project has the potential to address the safety-related challenges associated
with travelling along the single track B833, better supporting the movement of
people to place through supporting travel mode choice.
The project will align with the National Roads Development Guidance (NRDG)
Hierarchy of Users, creating an inclusive and accessible space prioritising the
movement of people. 
National Road Users Hierarchy

Page 17

15 | P a g e
www.connectedtp.com 
1.11 Health and Wellbeing
Being more physically active can benefit everyone and can reduce the chances of
developing preventable conditions such as diabetes and heart disease. Active
travel as promoted by this project route will encourage individuals to be more
physically active as part of their daily routine by incorporating physical activity
into everyday tasks.  This reduces the need to find extra time, money or
motivation for exercise. 
The route could also offer savings to travel by saving on fuel, and vehicle running
costs. Making short journeys using active travel helps to reduce the number of
vehicles on the road and improves local air quality and environmental amenities.
Investment in active travel can also deliver economic benefits. Active travel is
affordable and delivers value for money in achieving health, transport and wider
policy objectives. 
Studies on the economic benefits of walking and cycling interventions revealed an
average return of £13 for every £1 invested and in the UK, returns as high as £19
for every £1 invested.

Page 18

16 | P a g e
www.connectedtp.com

Page 19

17 | P a g e
www.connectedtp.com 
2 OPTIONS DEVELOPMENT AND APPRAISAL
2.1 Investigating the Network
Following a community engagement process during November 2023, the design
team worked with the steering group and community to revamp the 3 original
concept routes developed by ABC.  A fourth option was subsequently added to
ensure that all route corridor options had been considered.
The appraisal was developed in stages including the following key milestones:
• A constraints plan was developed to capture all known geographic,
ecological and physical considerations within the identified route
corridors.  Following engagement with the Registry of Scotland (ROS) a
land ownership register was produced to accompany a land ownership
plan.  Additional research identified protected environmental areas and
other ecological constraints including protected woodland.  A suite of
data collection surveys was commissioned, including traffic and ecological
surveys and the results were consolidated and considered.
• The 3 original ABC concept options were added to the constraints plan
along with the fourth design team generated option.
• A site visit was undertaken by the design team in October to review the
most obvious technical challenges of developing a route through the
project area.  
• Details of known committed developments relevant to the area were
identified through consultation with ABC planning portal.  Post
investigation, these potential developments / changes were transcribed
onto the constraints and options plans.  
A key development relevant to the design is the planning approved
housing development to be located adjacent to Camsail Bay within the
former yacht marina. 
The extent of the road changes will have a significant impact on the
project active travel route as the intervention includes around 50% of the
active travel route corridor into Camsail Bay.  The extent of the
development related change is shown as follows noting the proposed
footway (blue) will extend through the Camsail Bay parking lay-by. 
Marina Related Roads Improvement

Page 20

18 | P a g e
www.connectedtp.com 
• Utilising the design team experience in conjunction with the guidance
provided within Cycle by Design 2021, the route corridor options were
investigated.  
The four route options considered are summarised as follows and graphically
overleaf. 
Option Route Description
1 Shared use path on coastal side with new sea defences. 
2 Realign road to include path on coastal side.   
3 Shared use path on inland side of existing road.   
4 Remote path through quarry / Forrest.

Page 21

19 | P a g e
www.connectedtp.com 
4 Route Options were Initially Considered

Page 22

20 | P a g e
www.connectedtp.com 
2.2 Route Summary Descriptions
Each of the route options are described in greater detail as follows.
Option 1: Shared use path Coastal with new Sea Wall Defence
Route
Length
481m
Route
Description
The route continues along the seaside verge. The route utilises
and upgrades the existing path. It will require the retaining wall
to be realigned and will extend beyond the high-water springs
line. The path is proposed to be a 2.5m shared use path, a 1m
buffer and a 0.25m offset from the proposed parapet.
Key 
Challenges
• The existing sea defence is a heritage item and whilst not
listed is an example of Victorian construction.
• Interaction with the coastal entity beyond the mean high
water spring line.
• Additional land take.
• Culverts to be extended.
• Structure required.
• Import additional fill materials.
• Interact and change the flooding extents.
• Passes through sections of verge which may have 
protected plant species.
• Likely also have the highest cost to construct due to
impact on sea defences.
• Does little to address concerns of higher vehicle speeds
or narrow road width.
• No natural surveillance / no community interaction.
• Would require minimalist design standard due to land
requirements into bay. 
Key
Opport’ies
• Opportunity to form new sea defence to address coastal
flooding risk.
• Coherent and consistent standard.
• Can be segregated from the road.  Safer for non-
motorised users.
• Route is flat and level. 
• Would not require more extensive sub-base formation to
allow access by 7.5 tonne maintenance vehicles. 
• The route alignment would not prevent ABC from
adopting the asset to support future maintenance.  
• Separation of tourist traffic and reduction on demand for
limited road space.
• Limited impact on parking.
• The route alignment would not prevent ABC from
adopting the asset to support future maintenance.  
• Avoids impact on protected woodlands.
• Most coherent route option which avoids the needs for
users to cross the B833. 
Option 2: Road Re-Alignment with Path on Coast Side
Route
Length
501m
Route
Description
This route option would seek to realign the existing B833 on the
inland side of the road (western) edge of the B833.
Key  • Users would need to cross the B833 multiple times.

Page 23

21 | P a g e
www.connectedtp.com 
Challenges • Impact on protected woodlands.
• Largest impact on land required.
• Requires changes to the road drainage system (possibly
provision of).
• No mitigation of future flood risk.
• Impact on verge protected plants.
Key
Opport’ies
• Can be segregated from the road.  Safer for non-
motorised users. 
• Would not require more extensive sub-base formation to
allow access by 7.5 tonne maintenance vehicles. 
• The route alignment would not prevent ABC from
adopting the asset to support future maintenance.  
• Separation of tourist traffic and reduction on demand for
limited road space.
• Limited impact on parking.
• Route is flat and level. 
• Avoids the need to alter sea defences  
Option 3: Landside Verge with Path on inland side
Route
Length
497m
Route
Description
Similar to Option 2, the facility would be formed on the inland
side of the existing B833 with no change to the road alignment.
Key 
Challenges
• Users would need to cross the B833 multiple times.
• Less coherent or consistent standard.
• Avoids impact on protected woodlands.
• Small impact on land required.
• Requires changes to the road drainage system (possibly
provision of).
• No mitigation of future flood risk.
• Impact on verge plants.
Key
Opport’ies
• Can be segregated from the road.  Safer for non-
motorised users. 
• Would not require more extensive sub-base formation to
allow access by 7.5 tonne maintenance vehicles. 
• The route alignment would not prevent ABC from
adopting the asset to support future maintenance.  
• Separation of tourist traffic and reduction on demand for
limited road space.
• Limited impact on parking.
• Route is flat and level. 
• Avoids the need to alter sea defences 
Option 4: Remote Track Path through Quarry
Route
Length
572m
Route
Description
This route represents an alternative option to direct users away
from the B833.  The route would pass through the quarry site
and woodland before rejoining the B833 near the Y junction.
Key 
Challenges
• Users would need to cross the B833 multiple times.
• Coherent and consistent standard.

Page 24

22 | P a g e
www.connectedtp.com 
• Impact on protected woodlands. Noting the presence of
two listed trees of significance.
• Largest impact on future value of land due to severance
of land parcels.
• No mitigation of future flood risk.
• Impact on verge plants.
• Would require more extensive sub-base formation to
allow access by 7.5 tonne maintenance vehicles. 
• The route alignment would prevent ABC from adopting
the asset to support future maintenance.  
• Would need a community maintenance model to be
established.
• More limited natural surveillance so perception of safety
impacts on some users.
• Some challenging gradients.
• Least direct.
• Users will misses out on sea / bay views.
Key
Opport’ies
• Can be segregated from the road.  Safer for non-
motorised users. 
• Separation of tourist traffic.
• No impact on parking.
• Avoids the need to alter sea defences. 
2.3 Considering an Appropriate Route Design Standard
The route design standard was subjected to a review using Transport Scotland’s
Cycling by Design 2021 guidance.  Noting the results of the vehicle traffic /
speeds, number of potential NMU that the route standard must be for a shared
use facility.  A minimum width of 3m segregated from the B833 via a 1m
wide verge has been identified by the design team to reflect a minimum
standard of appropriate provision.  
Consideration of a 2m wide unsegregated route was considered and discounted
on the ground of road user safety risk.  The substandard option could be
accommodated whilst avoiding need for major support works.
The route must also consider appropriate coastal protection requiring a minimum
of 0.5m segregation from the coast edge and or provision of a protective barrier
to a height of 1m where the route is formed adjacent to the coastal edge.
A key influence on the route standard is vehicle speed.  The proposed Marina
Development will have a direct impact on the B833 speed limit through
introduction of a 40mph speed limit, mid-way along the project route.  
Whilst the change to speed limit is subject to a separate public / statutory
process and is therefore not guaranteed.  It is generally accepted that for the
road design to be given design approval (RCC) the speed limit reduction would be
pre-concluded requirement.  It is therefore appropriate to assume that the Marina
access design will introduce a 40mph speed limit at a mid-point along Camsail
Bay.

Page 25

23 | P a g e
www.connectedtp.com 
2.4 Considering Technical Design Constraints
To assist in understanding the extend of land required to accommodate the 4
options considered.  The proposed minimum design standard of a route formed
on both the inland and seaward side of the B833 was sketched alongside the
existing road at a point where the existing route corridor is most constrained.
An allowance has been made for the extent of public adopted road (assumes 2m
or up to the nearest boundary).
A review of the cross sections indicates that if the route was formed on the
seaward side, the maximum width of additional land required would be 2m. 
Should the route be formed on the inland side, the land required would increase
to 4m.  This is land in addition to the extent of public adopted verge.
Obviously, the cross sections do not consider the off-road route option 4 which
would be formed independently of the road. 
The cross sections were plotted onto a OS tile plan of the route corridor and the
plan examined to determine the extent of the route to which each cross section
would apply.
The plan was overmarked to shade the extents of the route where land would be
requried to accomidate each respective options.  Using the plan the following land
requirements have been calcualted:
• Coastal: 192sqm
• Inland: 1,168sqm  Route Cross Sections Comparison

Page 26

24 | P a g e
www.connectedtp.com 
Extent of Land Required

Page 27

25 | P a g e
www.connectedtp.com 
Preliminary Flood Risk Assessment 
The site has been reviewed for potential sources of flooding in accordance with
The Argyll & Bute Council Supplementary Guidance on Flood Risk. These are
outlined below along with a qualitive assessment of the risk they post to the
route. 
• Fluvial Flooding: The SEPA Indicative Flood Map shows that the
location of the site is not within the area of fluvial flood risk. 
• Pluvial flooding: The SEPA Indicative Flood Map shows that the
location of the site is within the area of high pluvial flood risk. 
• Costal Flooding: The SEPA Indicative Flood Map shows that the location
of the site is within the area of high coastal flood risk.
To summarise, the site is considered at risk of flooding and further investigation
is deemed necessary into the flood risk of any proposed routes.
Landownership Meetings
Initial meetings were attempted both Face to Face and by MS Teams with the key
landowners that would with certainty be impacted by the 4 route corridor options.
Each landowner was contacted first by phone, then by email and finally by letter
with the extract from the Registry of Scotland (ROS) included.
Where landowners responded, the conversations were conducted at a ‘high level’
and aimed primarily to understand landowner support for each of the 4 options. 
A summary of the key points to each meeting is noted as follows:
• Plot 1 & 2.  No Impact 
• Plot 3, Marina Owner / Developer. The developer / owner of the site
is in principle supportive of the concept design and will reserve a 1.5m
wide land strip within their site to the rear of their frontage footway.
• Plot 4, 5 and 6, No Response 
• Plot 7,  ABC above the High Water Line and Marine Licence below. 
• Plot 8,  No Impact
• Plot 9,  ABC above the High Water Line and Marine Licence below.
• Plot 10,  No Impact
Community Feedback
Reference is drawn to the results of the extensive community and stakeholder
feedback reported within the Community Feedback Report.  A summary of the
community’s feedback as route concerns and aspirations are summarised as
follows.
Concerns relating to the use of the existing road route
• A perception of high road traffic speeds along Camsail Bay.
• Walking or cycling along the bay is unsafe as no continuous footway is
provided.
• A lack of street lighting discourages use of the path in the evening or
winter.

Page 28

26 | P a g e
www.connectedtp.com 
• Perception that buses (and larger vehicles) are too wide to fit within the
narrow road space.
• Visibility of cyclist and pedestrians along the route is poor.
• Utility and services such as a new water main are located within the road. 
These will influence the options.
• Development of Rosneath Caravan Park will increase the number of and
type of larger vehicles such as caravans and campervans accessing the
area.
• General lack of route connection to Kilcreggan and the Rosneath to
Kilcreggan circular walking and cycling trail.
Aspirations for the future design
• Preferred route widening on coastal side.
• Reduce the severity of the road bend.
• Reduce the roads speed limit.
• Include lighting.
Stakeholder Feedback
Reference is drawn to the results of the extensive community and stakeholder
feedback reported within the Community Feedback Report.  
A summary of the stakeholder feedback received is summarised as follows.

Page 29

27 | P a g e
www.connectedtp.com 
ABC Roads • Off-road options will not likely be adopted by the council.
• Off-road route options will require more substantive construction and therefore introduce greater capital expenditure.
• Any coastal works will require the formation of a new coastal sea defence constructed to an appropriate height.  The
space behind the sea defence being backfilled. 
• Preference to maintain capital investment from developer of plot 3 and support their path construction with our design
seeking to modify accordingly.
ABC Marine Operations Contacted as part of Pre-application process
ABC Fleet Public Transport No Issue
ABC Outdoor Access No Issue
ABC Planning Noting the routes proximity to the coast, any intervention impacting above the High-Water line would be the responsibility of
ABC planning to determine.  Consultees to the process would include ABC Roads, Marine Operations, the DIO and SEPA.  Any
interventions impacting below the High-Water Line would trigger a separate statutory process requiring application for a Marine
License. As an ABC project, it is understood that no pre-application fee would be required.
ABC Youth Services No Issue
ABC Community Development
Team
No Issue
ABC Economic Development No Issue
SEPA Contacted as part of Pre-application process
Scottish Water No Issue
SSE No Issue
DIO (Faslane) Not contacted.  Recommended via a pre application process

Page 30

28 | P a g e
www.connectedtp.com 
2.5 Route Appraisal Against Cycling by Desing (CbD) 2021 
The route corridors were subjected to a review using the Sustrans route
assessment criteria in combination with Cycling by Design 2021.  The routes were
scored ranging between 1 – 3 with 1 reflecting a ‘high level’ of service and 3 a
‘low level’ of service. The assessment was undertaken by the design team as a
workshop discussion to allow each route option and assessment criterion to be
discussed and scored.
The criteria considered in the assessment included:
• Indicative Cost;
• Deliverability;
• Accessibility;
• Local Need;
• Coherence;
• Directness;
• Comfort;
• Attractiveness; and
• Adaptability.
The resulting assessment identified that a number of the routes, unsurprisingly
would need further investigation to determine an appropriate standard of design
provision.  This assessment would require to be undertaken in conjunction with a
detailed review of how each section of the route is currently utilised by the
community.
No consideration of the relative weighting of the evaluation criteria has been
undertaken.

Page 31

29 | P a g e
www.connectedtp.com 
Route /
Option
Length
(m)
Proposed Intervention
Structures
Required 
1 High level of Service
2 Medium level of Service
3 Low level of Service
Costs
Deliverability
Accessibility
Local Need
Safety
Cohesiveness
Directness
Com
fort
Attractiveness
Adaptability
Total
Option 1  481 Coastal Widening Sea Defences
+ Culvert
Extended
3 3 1 1 2 1 1 1 1 1 15
Option 2  501 Road Realignment and widening Culvert
Extended 3 3 1 1 2 1 1 2 2 1 17
Option 3  497 Inland route provision on existing
road
Culvert
Extended 1 2 3 1 2 1 2 2 2 1 17
Option 4 572 Remote path through Quarry None required 2 3 3 1 3 2 3 2 3 1 23

Page 32

30 | P a g e
www.connectedtp.com 
With reference to the above table, option 1 (coastal widening) is marginally
better aligned with the CbD criterion with options 2 and, inland road realignments
a close second.
2.6 Initial Route Appraisal Considering Landownership 
Each of the options has been appraised against the corresponding landownership
requirements and considering the initial land ownership feedback received.  The
results of the appraisal are summarised in the following table. 
With reference to the above table, any of the inland route options (options 2,3
and 4) will require the support of plots 4, 5 and 6.  Only option 1 requires the
approvals of plot 7 and 9, both of which would be subject to pre-planning
application inquiry.
2.7 Route Appraisal Against Stage 1 Community Feeback 
Each of the options has been appraised against the feedback received from the
community. The same scoring system was used ranging between 1 – 3 with 1
reflecting alignment with community expectations and 3 indicating a potential
design conflict   The results of the comparison are shown in the following table.
All criterion has again been given an equal weighting. 
Route
Option
Plot 3
(Marina)
Plot 4,5 and 6
(inland side)
Plot 7
(seaward)
Plot 9
(seaward)
1 Supportive No Response Unknown Unknown
2 Supportive No Response Unknown Unknown
3 Supportive No Response Unknown Unknown
4 Supportive No Response Unknown Unknown
Route Option
Appraisal Against Stage 1 Community Feedback
Coastal widening of the route is the most preferred option.
A
route managing the speeds on the road 
Options to reduce the severity of the road bend preferred.
Off-road route through the quarry is popular
Minimise road crossings required
Promote scenery
Physical separation of the route from
the road is preferred
Improve Visibility of Users
Lighting is preferred.
A
road-based route is preferred
Total
1 1 2 3 3 1 1 1 1 2 1 16
2 3 1 1 3 1 2 1 2 2 1 16
3 3 2 3 3 3 2 1 2 2 1 22
4 3 3 3 1 3 3 1 3 3 3 26

Page 33

31 | P a g e
www.connectedtp.com 
With reference to the above table, options 1 and 2 (coastal and road realignment)
are best aligned with the aspirations of the community.
2.8 Considering Those with Protected Characteristics
An appraisal of the project has been undertaken using ABC Social and Equality
Impact Appraisal template (SEQiA). The results of the assessment are included in
Appendix B.
Taking cognisance of the appraisals summarised previously it is noted that all
options would be provided to achieve a Cycle by Design ‘High standard’ of
provision.  Once a preferred route alignment has been determined the design
should consider best practice to maximise the routes accessibility for all user
groups and abilities. 
2.9 Route Appraisal Summary 
Evaluating the four route options, it is clear that there are two main themes: path
on either the ‘seaward’ or the ‘in-land’ side. Further exploring these options, it is
clear that both options will require either land take or statutory approval to go
beyond the council-adopted extent. 
The ‘seaward’ option highlights that the path will extend into the coastal
boundary, beyond the spring high water line, by at least 2m which excludes the
space required for a sea defence wall which could either be a retaining wall or a
rock armour solution. The sea defence wall will have to be structurally designed
and the existing wall will have to be demolished. The total length of new wall
required is 192m. This route will require statutory approvals from SEPA and the
Maritime Agency. The route has the potential to impact the flooding extent as it is
in the area of coastal flooding and therefore additional flood risk assessment is
recommended. 
The ‘in-land’ options will extend beyond the council adopted area by at least 4m
which means that additional land take is required. Landowners will have to agree
to land take which is one of the main risks for this route. This route will also
require two road crossings which will require a transport assessment and
decrease the directness of the route. The existing boundary wall will have to be
demolished and rebuilt. 
Taking cognisance of the appraisals it is noted that both options 1 and 2, which
would be most likely to achieve a Cycle by Design ‘High Level of design provision’
are the most supported options.   Both align well with the feedback from the
community and the initial feedback from the stakeholders consulted through the
process.
However, both options are dependent upon separate and unrelated approvals
relating to planning and landowner agreements.  Until these requirements are
understood, it is not possible to identify a preferred route option.
At this stage, it is recommended that the coastal route (option 1) is subject to a
pre-planning application to determine the likely planning deliverability.  
For option 2 (and all other options, further investigation to identify the
landowners involved should also be progressed.

Page 34

32 | P a g e
www.connectedtp.com  DEVELOPING THE CONCEPTS

Page 35

33 | P a g e
www.connectedtp.com 
3 DEVELOPING THE CONCEPTS
3.1 Developing the Options
Following approval to progress by ABC, Option 1 (sea defence and coastal
widening) and Option 2 (inland widening and road realignment) route options
were further developed by the design team with greater focus being applied to
the standard and appropriateness of intervention.  A key ambition of the
developed design process is to identify a preferred single alignment option for
consideration at the next design stage.
Both options are considered to be in principle deliverable but both are note to be
reliant upon differing constraints with option 1 dependent upon third party land
and option 2 on the ability to navigate statutory process.  It was agreed within
the design team that both options should be developed further and reevaluated
as part of the stage 2 project programme.
Option 1 – New Sea defence with Path Formed on Coastal Side.
This option was subject to a more detailed desktop structural investigation and
noted that 192m of the route would need to be widened into the coast by 2m.
The package includes:
• A replacement stone faced concrete or dyke stone sea defence around
200m long and 3m high which will partially connect with the existing
verge and gabions. The protection barrier to pedestrian cyclists will be
formed as an extension of the wall. The wall would be formed on a
concrete ring beam and backfilled with inert material to form a new
carriageway level.  The wall will include weep vents at carriageway level
to allow any water from coastal flooding to return to the sea. The wall
will include sufficient height above carriageway to provide pedestrian and
cyclist protection.
• Inert backfill material likely to be well compacted granular fill (type 2 or
type 1 x or type 3).  Road surface provided as a bound bitumen surface
and tar stitched to existing wearing course.
• Introduction of a formalised road drainage system for all areas where the
road is being augmented. This should include improvements to the
western extent where surface water ponding in known to freeze in the
winter and result in cars skidding.
• Improvement to existing public transport infrastructure including the
upgrading and provision of new shelters on both eastbound and
westbound sides of the road.  The shelters will be formed on hard
standing and connected via dropped kerb crossing.  The eastbound stop
will be located away from its current location adjacent to a field access to
reduce conflict and improve crossing visibility.
• Integration with the proposed Marina infrastructure.  This will include
widening of the newly formed path from the tie in point with the existing
path west through the new marina access and along the coastal side of
the route. From the end of the marina works the path will be continued

Page 36

34 | P a g e
www.connectedtp.com 
toward the ‘Y’ junction utilising the space provided through the provision
of the new sea defence.
• The Marina development will also promote a 40mph speed limit extending
between Rosneath to a point just beyond the Marina access.  The
promotion of the speed limit change will remain the responsibility of the
Marina development.
• No street lighting is proposed.
Option 2 – Inland Road Realignment with Path formed on Coastal Side
• This option includes the majority of option 1 with the main difference
relating to the formation of the new path.  This option will utilise the
existing verge located within the inland side of the road and realign the
road inland to provide sufficient space to accommodate a new path on
the coastal side.
• The route will require the purchase of some third-party land on the inland
side of the route. The existing sea defence will be heightened to provide
pedestrian and cyclist protection through the addition of a parapet fence
although an option to heighten the sea defence through a dyke wall
construction could be considered subject to the necessary checks of the
existing walls structural stability.
Constructing and Maintaining the Concepts
A key challenge of remote rural scheme design is ensuring the robustness and
low maintenance obligations.  To support this, aim a series of workshops were
held with Argyll and Bute Network Management Representative.  In advance of
each workshop a concept option plan was shared.  The key points of each
workshop are summarised as follows.
Argyll and Bute Network Management (Workshop 2)
• ABC would adopt and maintain either of option 1 and 2 as both can be
accessed from the existing carriageway.
• The design is dependent upon the successful conclusion of a Traffic Road
Regulation Order (TTRO) which will be promoted by ABC in support of a
speed limit change from 60mph to 40mph in support of the Marina
Development access.
• Road drainage should be formalised as part of the design.
• As the surface area of the carriageway is increasing, the untreated
surface wate run off discharging into the sea will likely increase.  Options
to mitigate should be considered at the next design stage.
• The design and form of the sea defence will be subject to further
consideration.
• The coastal route would need a cofferdam construction method to
manage the impact of tide.  The construction costs are therefore likely to
be between 7 to 10 times greater than option, inland road widening.
Based on the feedback received, the concept design plans were revised to
address the above noted points.

Page 37

35 | P a g e
www.connectedtp.com 
3.2 Maintaining Parking and Access to Public Transport
Neither design option is forecast to have an impact on local parking. Both designs
include enhanced provision and access to the bus stops located within the
scheme. The proposed scheme includes the provision of bus shelters, seating,
pole and flag with an area of hardstanding provides on the eastbound side.  The
design also include provision of dropped kerbs to better support the crossing
options for those with mobility challenges.
Both designs will result in the loss of the visitor parking bay located near the
midpoint of the route.
3.3 Route Safety Audit and Designers Response
The emerging concept design were submitted to Drummond Black Ltd who
undertook a Stage 1 Road Safety Audit during February 2024. The results of the
audit are summarised as follows along with the designer’s response. All points
have been fully actioned.  
Details of the audit are reported separately in Appendix C.
3.4 Landowner Agreement
Further attempts by letter have been made to contact the primary landowner
associated with Option 2 – inland widening.  No response has been received.  It
is therefore recommended that should this option be progressed further that ABC
consider the use of Compulsory Purchase powers (CPO).
There is no private land purchase associated with Option 1 – New Sea defence.
It is noted that the adjacent Marina developer has agreed to support either
concept design with both designs reliant upon delivery of the road scheme
currently awaiting Roads Construction Consent (RCC).  An agreement indicates
their design will make reservation of a 2m strip of land within their ownership to
the rear of their proposed new path. This agreement should be formalised as
soon as possible.
3.5 Results of Pre-Application Development Screening
Further to conclusion of the pre-development application screening process with
ABC (Incident: 240103-000174). The results do not indicate any notable
challenges to the development of Option 1 – sea defence and coastal widening in
relation to statutory process.
A fully summary of the Pre-App feedback is included in Appendix F.
3.6 Developing the Route Cross Sections
Narro Associates have developed a number of route cross sections for each of the
options.  These are shown as follows.

Page 38

36 | P a g e
www.connectedtp.com 
3.7 Considering Construction Phasing
Due to the overall route length and complexity the identified route options will be
constructed as a single delivery project. 
3.8 Weighted Route Appraisal Against Cycling by Desing (CbD) 2021 
Both options were again subjected to a review using the Sustrans route
assessment criteria in combination with Cycling by Design 2021 (CBD) using the
same assessment criterion. 
Recognising that not all evaluation criterion will have the same level of
significance, both options were subjected to a further assessment against CBD,
this time including the use of criterion weighting. The key changes resulting from
the design team workshop include:
• Additional criterion added to the matrix separate land purchase challenges
from deliverability noting that many scheme can be excellent concepts but do
not progress to construction due to land purchase challenges.
• Clarification that ‘Safety’ is subjective viewpoint of end user and not an
evaluation against a design standard as all options must be safe in relation to
design standards to be suitable for consideration. 
• Resilience and Environmental criterion were added to capture the
environmental sensitivity of both options noting that one options will have a
greater environmental impact than the other.

Page 39

37 | P a g e
www.connectedtp.com 
• Noting that both options provide broadly similar scores across most of the
criterion, the main differentiation is in each options capital cost and
deliverability. The criterion weighting used was adjusted to keep the
comparative weighting between performance related criterion whilst an
adjustment was made to place greater emphasis on deliverability and capital
cost of both options.
• The options descriptions were corrected to avoid risk of misleading reviewer
noting that confusion could result with the options being similar.
Each criterion was given a weighted index ranging from 1 to 10 with 1 reflecting
lower priority and 10 a maximum.  The weighting of each value was debated by
the design team during a progress meeting workshop and the relative comparison
of criterion weighting was debated and finally agreed.
The results including criterion weighting are shown in the following table.

Page 40

32 | P a g e
www.connectedtp.com 
Route /
Option
Length
(m)
Proposed
Intervention
Structures Required
(Y/N)
1 High level of Service
2 Medium level of Service
3 Low level of Service
Capital Costs
Deliverability Construction
Deliverability Land and Stakeholders
Maintainability
Route Directness
End User Safety 
Perception
Route Cohesiveness
Vehicular Impact
Route Comfort
Route Attractiveness
Resiliance and Environment
Adaptability
Total
W
eighted
Total
Option 1 – Sea
defence and
Coastal
Widening
481 Coastal widening Sea Defences + Culvert Extended 3 3 2 3 3 3 3 3 3 3 2 2 33 136
Option 2 –
Inland Widening
and Road
Realignment
501 Inland realignment and
widening
Culvert Extended 1 1 2 1 3 3 3 3 3 3 3 3 29 95

Page 41

33 | P a g e
www.connectedtp.com 
3.9 Route Appraisal Against Stage 2 Community Feeback 
Both options have been appraised against the feedback received from the
community as part of the stage 2 assessment. The same scoring system was
used ranging between 1 – 3 with 1 reflecting alignment with community
expectations and 3 indicating a potential design conflict   The results of the
comparison are shown in the following table. 
With reference to the above table, option 2 – Inland Widening and Road
Realignment is best aligned with the aspirations of the community.
3.10 Considering Those with Protected Characteristics
An appraisal of the project has again been undertaken using ABC Social and
Equality Impact Appraisal template (SEQiA). The results of the assessment are
included in Appendix C.
Route
Option
Appraisal Against Stage 2 Community Feedback
Inland realignment of the route is the most preferred option.
Improved Speed Limits 
Improvement to Bend at Junction
Reduce Flooding
More Street Signs
Safe W
alking Route
Improved Street Lighting
Cycle Lanes
Total
1 3 1 2 3 1 1 1 1 13
2 1 1 1 3 1 1 1 1 10

Page 42

34 | P a g e
www.connectedtp.com 
Taking cognisance of the appraisals summarised previously it is noted that all
options would be provided to achieve a Cycle by Design ‘High standard’ of
provision.  Once a preferred route alignment has been determined the design
should consider best practice to maximise the routes accessibility for all user
groups and abilities. 
3.11 Forecast Construction Costs Estimates
An initial assessment of the capital cost of constructing each of option 2 is set out
in the following table.  Due to a lack of landowner response, the land costs
associated with option 2 - inland widening have been initially sought via a District
Valuer (DV) assessment.  However, the land in question is noted to be
undeveloped verge and of low value.  As an alternative, the design team have
determined a land value capped at £25,000 exc VAT. Additional costs are also
included within the following estimates to support a Compulsory Purchase Order
(CPO) by Argyll and Bute Council.
A summary of budgeted scheme costs is set out in the following table.

Page 43

35 | P a g e
www.connectedtp.com 
3.12 Recommendations and Next Steps
Following consideration of the material provided within this assessment, it is
recommended that option 2 – widening inland with a new shared use walking
cycle path formed on the coastal side is promoted.
It is noted that both options will provide a similar level of end users service with
the primary difference between options relating to the construction cost and
deliverability of the options.
Option 2 should be progressed to detailed design with a primary focus on
investigating the necessary land purchase agreement of Compulsory Purchase
process.
It is recommended that all necessary land requirements are progressed via a
legal agreement ASAP.

Page 44

36 | P a g e
www.connectedtp.com 
DESIGN PROCESS QUALITY AND INNOVATION

Page 45

37 | P a g e
www.connectedtp.com 
4 DESIGN PROCESS QUALITY AND
INNOVATION
4.1 Outline Design Process
The project will be developed to align with the Placed for Everyone (PfE) design
development programme.
4.2 Design Guidance and Quality
A wide range of design guidance and standards have been used to develop the
project proposals.  The core documents include: 
• Designing Streets;
• Cycling by Design (2021);
• The National Roads Development Guide (NRDG); and
• Inclusive Mobility (2021).
The detailed design process will use these standards and include:
• Design Manual for Roads and Bridges (DMRB);
• Traffic Signs and Regulations and General Directions (TSRDG);
• Local Transport Notes (LTN); and
• Traffic Advisory Leaflets (TAL).
These references represent the core design guidance however other documents
such as Sustrans Design Guidance Documents and other examples of best
practice have also been considered.

Page 46

38 | P a g e
www.connectedtp.com 
4.3 Considering Wider Area Improvements
The concept design process will include a number of key considerations in
support of the emerging network. These include:
• Improvement to accessibility, walking and cycling links between people
and place;
• Developing a signage and wayfinding strategy;
• Promoting cycle-friendly intervention;
• Introducing a Travel behaviour change programme; and
• Providing cycle parking and storage measures.
4.4 Considering Streetscape and Landscape Improvements
The Rosneath route on its own will not create an environment which will support
the movement of people, create place and encourage community ownership. 
Rosneath is a remote peninsular community which relies heavily on the use of
motorised travel to support the movement of the community.  
To support lasting change to travel behaviours the design process must include
placemaking potential giving priority to maximising the communities’ assets and
access to public transport as well as the opportunity to walk and cycle. 
4.5 Planting, Drainage and Local Environment
Within the proximity of any areas where there would be works such as seating,
way finders, and shared surfaces, planting of native species will enhance the
environmental improvements.  
Not only will planting create an attractive setting but it will also be encouraging
and increasing biodiversity. Salt-tolerant species can be used for foraging and can
be educational.  The changing seasons are marked with the advent of spring with
blossom flowers followed by autumn leaf colour changes. 
For example, groupings of trees of the same species at either end of the village
would act as a visual landmark, or scented shrubs around seating areas would
improve the visitor experience. 
The sea view from the village and beach must be retained, but the clever
positioning of planting can be used to frame and enhance the visitor’s experience.

Page 47

39 | P a g e
www.connectedtp.com 
4.6 Developing Streetscape
Sensitively designed rural street furniture and public art, can be incorporated as
part of the concept design process and is aimed at enriching the experience of
everyday journeys and visits to the area.  
Whilst keeping in mind the Coastal environment; seating, opportunities for
incidental play, way-finders would be appropriate.
As a rural area with limited street lighting, the lighting design must be done very
sensitively. Lighting can become a design feature in its own right, by marking at
ground level or by enhancing seating areas by incorporating lighting into the
structures. 
Paving materials will avoid any garish colours and patterns which would be more
associated with an urban area and kerbs are to be avoided; again, as they are
not in keeping with the style of the road. The linear nature of the site naturally
establishes a physical connection through the site which can be punctuated with
environmental improvements such as seating areas and viewpoints. 
Examples of Bike Stands Combined with Seating
Examples of Bike Stands

Page 48

40 | P a g e
www.connectedtp.com 
Examples of Rural Signage
Examples of Micro Asphalt Bound Path
Examples of Resin Bound Path

Page 49

41 | P a g e
www.connectedtp.com 
Examples of Rural Seating Solutions

Page 50

42 | P a g e
www.connectedtp.com 
Bins and Adding Colour

Page 51

43 | P a g e
www.connectedtp.com 
Examples of Rural Route Lighting Solutions

Page 52

44 | P a g e
www.connectedtp.com 
Designing for Equality and Accessibility
The proposed Active Travel network must support access by all user’ groups that
includes accessibility by all ages and abilities.  As the route corridor design
progresses, consideration must be given to ensuring that the network remains
safe and inviting to everyone.  This includes how those more vulnerable in our
society will be supported by the design.
The design is supported by a Social and Equalities Impact Assessment (SEQiA)
which is included in Appendix B.
4.7 Flood Prevention
With a changing climate, the importance of designing with flood risk in mind is
paramount.  The SEPA flood risk maps indicate that much of the road route will
be at high risk of coastal flooding in the near future.  A summary of the flood risk
map is presented in Appendix A alongside the ABC Flood Teams pre consultation
response. The response does not highlight any design considerations other than
the future design should consider.
“The small, unnamed watercourse flows underneath
Rosneath Road marginally below the foot of the site. No
information has been supplied regarding culvert
modification within the site, however, if any
modifications are to be made, the capacity of the existing
must remain the same, or ideally be resized to facilitate
the equivalent of a 0.5% AP plus climate change (200
year plus climate change) flood event.”
4.8 Traffic Modelling
No traffic modelling is considered necessary at this stage of the concept
development. 
4.9 Preliminary Ecological Appraisal (PEA)
A Preliminary Ecological Appraisal has been undertaken for the existing route
corridor.  The PEA is included in Appendix D.

Page 53

45 | P a g e
www.connectedtp.com  PROJECT DELIVERABILITY AND DESIGN COLLABORATION

Page 54

46 | P a g e
www.connectedtp.com 
5 PROJECT DELIVERABILITY AND DESIGN
COLLABORATION
5.1 Landownership
The project route is predominately located within council-owned or adopted
lands.  There are however sections of the route where third-party land ownership
may be required.  In these instances, attempts to contact the landowner have
been made and initial feedback has been sought.  
Frontage landowners will need to be consulted at the next stage of the design
development or pursual of a Compulsory Purchase Orders (CPO).
5.2 Designer Risk Register
Similar to the Project Risk Register, the Designer Risk Register provides a
summary of the risks and risk management associated with the technical delivery
of the design.  The Designer Risk Register is provided in Appendix E.
5.3 Project Budget Forecast
It is recommended that the following project cost allowances are considered to
support development of the design to the next stages.
• Detailed Design - £40,000
• Technical Design - £40,000

Page 55

47 | P a g e
www.connectedtp.com  APPENDICES

Page 56

43 | P a g e
www.connectedtp.com 
APPENDIX A – NETWORK AND UTILITIES

Page 57

44 | P a g e
www.connectedtp.com

Page 58

45 | P a g e
www.connectedtp.com 
APPENDIX B – SOCIAL AND EQUALITY IMPACT ASSESSMENT (SEQIA)
See separate Excel File

Page 59

46 | P a g e
www.connectedtp.com 
APPENDIX C – STAGE 1 ROAD SAFETY AUDIT AND DESIGNERS’ RESPONSE
See separate File

Page 60

47 | P a g e
www.connectedtp.com 
APPENDIX D – PRELIMINARY ECOLOGICAL APPRAISAL (PEA)
See separate File

Page 61

48 | P a g e
www.connectedtp.com 
APPENDIX E – DESIGNERS RISK REGISTER
See separate File

Page 62

49 | P a g e
www.connectedtp.com 