Democracy Spraffa

Rosneath Cyclepath Update

Argyll and Bute Council · 10 December 2024
Back to Helensburgh & Lomond Area Committee — 10 December 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
10 DECEMBER 2024 
ROSNEATH CYCLEPATH UPDATE 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates members on the progress made in relation to the Rosneath
to Castle Caravan Park junction cyclepath. 
1.2. Officers have completed a land access agreement with ACHA to allow
construction of the section of path between Argyll Road and the Clachan Burn. 
Officers have also secured £259,950 funding in 24/25 for the construction of the
section of the route between Argyll Road and the Clachan Burn.  This section of
path will be completed by spring 2025. 
1.3. Officers secured funding from SPT in 23/24 to commission feasibility and
concept design work on phase 2 of the route linking the end of the first phase at
the builder’s merchants around Camsail Bay to the Castle Caravan Park
junction. 
1.4. The initial feasibility and options appraisal examined 4 options for the route
around Camsail Bay, with a community consultation open for 2 weeks in
November 2023. The associated community event attracting 32 attendees, with
the same materials available on the study consultation website.  The design
team also visited Rosneath Primary School.  A total of 80 survey responses
were received which represents 7% of the local population.  82% of survey
respondents believed that the provision of a route would encourage them to
walk and cycle. 
1.5. Respondents were also asked for their aspirations of what the concept design
should take account of.  The main topics were: lower speed limit, good
maintenance, tarmac path, minimise road crossings, provision of a cycle lane,
preserve the scenery, improve accessibility and improve safety. 
1.6. A concept design was developed based on the community and stakeholder
feedback and presented to the community for comment in February 2024.  It
was launched with a community event on 06 Feb, with a total of 16 people
attending.  Again all consultation materials were made available online.  A
total of 60 survey responses were received.  Of the two options presented at
concept design, 78% of respondents indicated a preference of minor
realignment of the road inland to provide space for a path on the seaward
side.  73% of respondents also stated that the options presented resolved

Page 2

most or all of their concerns in regard to walking or cycling between Rosneath
and Castle Caravan Park. 
RECOMMENDATIONS 
1.7. It is recommended that the Helensburgh and Lomond members: 
1.7.1. Welcome the securing of land agreements and funding to enable construction of
section of the route within Rosneath in 24/25. 
1.7.2. Support the preferred option identified for Phase 2 of the route around Camsail
Bay. 
1.7.3. Instruct Officers, subject to securing external funding, to complete development
of designs for Phase 2 through Developed Design and Technical Design stages. 
1.7.4. Instruct Officers to submit a further paper to members on completion of the
Technical Design.

Page 3

ARGYLL AND BUTE COUNCIL  HELENSBURGH AND LOMOND AREA
COMMITTEE 
DEVELOPMENT AND ECONOMIC
GROWTH 
10 DECEMBER 2024 
ROSNEATH CYCLEPATH UPDATE 
2.0 INTRODUCTION 
2.1. This report updates Members of the progress made since the previous quarterly
report to the Helensburgh and Lomond Area Committee in relation to the
delivery of a dedicated, high quality walking and cycle path linking Helensburgh,
Cardross and Dumbarton.  The delivery of this path is a stated Council Priority. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome the securing of land agreements and funding to enable construction of
section of the route within Rosneath in 24/25. 
3.1.2. Support the preferred option identified for Phase 2 of the route around Camsail
Bay. 
3.1.3. Instruct Officers, subject to securing external funding, to complete development
of designs for Phase 2 through Developed Design and Technical Design stages. 
3.1.4. Instruct Officers to submit a further paper to members on completion of the
Technical Design. 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds. 
4.2. In 2023/24 the Active Travel Team secured £2.56M external funding for the
development and delivery of a total of 22 projects across Argyll and Bute, including
the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 18 separate
competitive funding applications, to 5 separate funds.

Page 4

Rosneath Town Section 
4.3. Since design work on the 350m section of the route linking Argyll Road to the
Clachan Burn was completed in 2021, Officers have been engaging with ACHA
as the landowner of the large grass area between Argyll Road and Ferry Road. 
This engagement resulted in a path agreement being signed between ACHA
and the council in September 2024 which permits the council to construct and
maintain a path across ACHAs land. 
4.4. Officers submitted a funding application to Transport Scotland’s Tier 2 Active
Travel fund in late 2023 for 24/25 for funding to enable the construction of the
section of the route between Argyll Road and the Clachan Burn.  While the
announcement of this funding was delayed due to the Scottish Government
spending moratorium, fortuitously the funding award was confirmed on 11
November 2024. 
4.5. The funding award for £259,950 in 24/25 will enable the construction of the
section of the route between Argyll Road and the Clachan Burn.  This section of
path will be constructed by the council’s roads and infrastructure service and will
be completed by spring 2025. 
Phase 2: Camsail Bay Section 
4.6. Officers secured funding from SPT in 23/24 to commission feasibility and
concept design work on phase 2 of the route linking the end of the first phase at
the builder’s merchants around Camsail Bay to the Castle Caravan Park
junction. 
4.7. The initial feasibility and options appraisal examined 4 options for the route
around Camsail Bay, with a community consultation open for 2 weeks in
November 2023. The associated community event attracting 32 attendees, with
the same materials available on the study consultation website.  The design
team also visited Rosneath Primary School.  A total of 80 survey responses
were received which represents 7% of the local population.  82% of survey
respondents believed that the provision of a route would encourage them to
walk and cycle. 
4.8. Respondents were also asked for their aspirations of what the concept design
should take account of.  The main topics were: lower speed limit, good
maintenance, tarmac path, minimise road crossings, provision of a cycle lane,
preserve the scenery, improve accessibility and improve safety. 
4.9. A concept design was developed based on the community and stakeholder
feedback and presented to the community for comment in a 2 week
consultation on February 2024.  The consultation was promoted via local
press, social media, 1000 leaflets distributed with the community magazine,
and a pop up event in the local Coop.  It was launched with another
community event on 06 Feb, with a total of 16 people attending.  Again all
consultation materials were made available online.  A total of 60 survey
responses were received.  This is in line with other projects where community

Page 5

engagement reduces following the initial consultation when the community are
broadly supportive or ambivalent about the project.  Of the two options
presented at concept design, 78% of respondents indicated a preference of
minor realignment of the road inland to provide space for a path on the
seaward side.  73% of respondents also stated that the options presented
resolved most or all of their concerns in regard to walking or cycling between
Rosneath and Castle Caravan Park. 
5.0 CONCLUSION 
5.1. Completion of the Rosneath Cyclepath will provide an accessible walking and
cycle route linking Rosneath to the Castle Caravan Park junction.  This route will
provide improved opportunities for local residents and visitors to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint.. 
5.2. The delivery of the Rosneath Cyclepath is dependent on completing the design
work, securing highly competitive external challenge funding, committing
appropriate match funding and securing access to private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
SOA outcomes 2: We have infrastructure that supports
sustainable growth and 5: People live active, healthier
and independent lives. The project also supports
achievement of the Scottish Government’s objectives
set out in the Cycling Action Plan for Scotland (CAPS)
and Let’s Get Scotland Walking - The National
Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
External funding is not currently available to cover
maintenance costs.  To date, the Council has not
contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to
require social care services in later life which could
result in a future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty:

Page 6

6.5.1 Equalities Completion of this project will provide opportunities for
local residents and visitors to travel more sustainably
and actively by walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment
opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.
6.9. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates even stronger
support for the delivery walking and cycling
infrastructure from younger members of the
community than the already high overall level of
community support. Wider engagement with school
pupils indicates that the vast majority of pupils strongly
support the provision of new active travel
infrastructure, even where it would adversely impact
other modes of transport.

Page 7

Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Head of Development and Economic Growth: Fergus Murray 
Policy Lead for Roads, Transport and Amenity Services: Councillor John Armour 
11 November 2024                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk   
Tel: 01546 604275 
Appendix 1: Options Feasibility Report
Appendix 2: Community Engagement Report