Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme 
Activity
2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Funding Applications                                                
Phase 1: Helensburgh to Cardross                                    
Route Design: Helensburgh to Cardross                                                
Land Purchase Negotiations: Helensburgh to Cardross                                                
CPO Process (if required):                                                
- Provide CPO recommendation to Council                                    
- Develop CPO                                                
- Gain Full Council approval for CPO                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                
- CPO Process                                                
Construction: Helensburgh to Cardross                                                
Construction of Helensburgh to Cardross Phase 1
(Cardross Station to Geilston Burn)                                                
Construction of Helensburgh to Cardross Phase 2
(assuming negotiated acquisition)                                                
Construction of Helensburgh to Cardross Phase 3
(assuming Compulsory Purchase Order required)                                                
Construction of Helensburgh to Cardross Phase 4
(assuming Compulsory Purchase Order required)                                                
Phase 2: Cardross to Dumbarton                                    
Route Design: Cardross to Dumbarton                                                
Land Purchase Negotiations: Cardross to Dumbarton                                                
CPO Process (if required):                                                
- Provide CPO recommendation to Council                                    
- Develop CPO                                                
- Gain Full Council approval for CPO                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                
- CPO Process                                                
Construction: Cardross to Dumbarton                                                
Construction of Cardross to Dumbarton Phase 1
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 2
(assuming negotiated acquisition)                                    
Construction of Cardross to Dumbarton Phase 3
(assuming Compulsory Purchase Order required)                                                
Construction of Cardross to Dumbarton Phase 4
(assuming Compulsory Purchase Order required)                                                
Helensburgh: Hermitage Academy to Town Centre                                    
Community Consultation & Route Identification                                    
Route Design         
Land Access Negotiations (if required)                                   
Redetermination Order(s) / Traffic Regulation Order(s)                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 1                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Phase 2                                                 
Colour Key (Responsibilities / Lead): 
Green: Strategic Transportation (Development and Economic Growth) 
Blue: Road and Infrastructure Service 
Orange: Estates Service 
Red: Legal 
Purple: External to Council (e.g. Scottish Government)
Negotiated
access
Negotiated
access
If no private
land required
If no private land
required