ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
11 March 2025 
Helensburgh, Cardross and Dumbarton Cyclepath Progress Report 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
this Committee on 10 September 2024 in relation to the delivery of a high
quality walking and cycle route linking Helensburgh, Cardross and Dumbarton. 
1.2. Phase 1 & 2: Officers worked with Procurement colleagues undertake a
procurement exercise for a new design team to complete the Developed Design
(Stage 3) and Technical Design (Stage 4) covering Phase 1 (Colgrain –
Cardross) and Phase 2 (Cardross – Dumbarton).  This is necessary to complete
the outstanding items of work which are required to deliver a robust design
package and to satisfy funder requirements. 
1.3. Phase 1 & 2: Following a competitive open tender process via Public Contracts
Scotland, the preferred tenderer was identified as Connected Transport
Planning (CTP).  Due to funding restrictions, a contract was awarded to CTP
covering February and March 2025 to enable initial progress on continuing the
Developed design stage to be made.  Subject to securing appropriate funding,
the procurement has been structured to allow a contract to be directly award to
CTP for 2025/26 to continue the Developed and Technical design stages. 
1.4. Phase 3: Civic Engineers (CE) have continued to developed the Concept
Design for Phase 3 of the project as part of the Helensburgh Town Centre East
(Helensburgh in Motion) project.  It is programmed that the Concept Design
work will be completed by late March 2025 in line with the funders requirements. 
1.5. Phase 3: A community consultation was held between 23 November 2024 to 05
January 2025.  Information material and the survey were available on-line via
the Council’s website for the 6-week period, with posters and flyers distributed to
local shops, library and churches.  The consultation was also promoted via
appropriate social media channels.  Two in-person events were held, at the
Hermitage Academy Christmas Fair on 23 November and at the Helensburgh
and Lomond Civic Centre on 16 December.  Officers and the design team also
attended the Helensburgh Community Council meeting on 28 November 2024. 
1.6. The consultation received a total of 185 responses; with 59% (105) not feeling
safe travelling actively on the A814 at present; 85% (154) believing that
improvements to the area would make people more likely to walk, wheel or
cycle; 79% (143) requested improved cycling infrastructure, 61% (11) more or
safer crossing points and 49% (89) traffic calming measures.

Page 2

1.7. In 2024/25 Officers secured a total of £150,000 from Transport Scotland’s
Places for Everyone (PFE) programme, administered by Sustrans, to enable
progress to be made in relation to all phases of the design. 
1.8. Internally, Officers continue to seek guidance from Legal Services on the use of
the Council’s statutory powers to enforce access to private land for the
necessary surveys (e.g. ecology or ground investigation) where landowner
permission is not forthcoming.  Officers also continue to seek engagement with
colleagues in Legal Services to seek to progress approval from Council to
develop a CPO for the remaining sections of this important route. 
RECOMMENDATIONS 
1.9. It is recommended that the Helensburgh and Lomond members: 
1.9.1. Welcome, subject to securing external funding, the appointment a new design
team to complete development of Phase 1 and Phase 2 designs through
Developed Design and Technical Design stages. 
1.9.2. Instruct Officers, subject to securing external funding, to appoint a design team
to complete development of Phase 3 designs through Developed Design and
Technical Design stages. 
1.9.3. Instruct Legal Services to utilise the Council’s statutory powers as necessary to
enforce access to private land for surveys required as part of the design process
where landowner permission is not forthcoming. 
1.9.4. Work to identify potential sources of construction match funding, estimated to
require a minimum of £3M to complete the route. 
1.9.5. Instruct Roads and Infrastructure Service to adopt all sections of the
Helensburgh – Cardross – Dumbarton Cyclepath once constructed including
those not contiguous with an adopted road, and maintain as part of the Council
Roads Asset Management Plan (RAMP).

Page 3

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
11 March 2025 
Helensburgh, Cardross and Dumbarton Cyclepath Progress Report 
2.0 INTRODUCTION 
2.1. This report updates Members on the progress made since the previous report to
this Committee on 10 September 2024 in relation to the delivery of a high
quality walking and cycle route linking Helensburgh, Cardross and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome, subject to securing external funding, the appointment a new design
team to complete development of Phase 1 and Phase 2 designs through
Developed Design and Technical Design stages. 
3.1.2. Instruct Officers, subject to securing external funding, to appoint a design team
to complete development of Phase 3 designs through Developed Design and
Technical Design stages. 
3.1.3. Instruct Legal Services to utilise the Council’s statutory powers as necessary to
enforce access to private land for surveys required as part of the design process
where landowner permission is not forthcoming. 
3.1.4. Work to identify potential sources of construction match funding, estimated to
require a minimum of £3M to complete the route. 
3.1.5. Instruct Roads and Infrastructure Service to adopt all sections of the
Helensburgh – Cardross – Dumbarton Cyclepath once constructed including
those not contiguous with an adopted road, and maintain as part of the Council
Roads Asset Management Plan (RAMP). 
4.0 DETAIL 
4.1. The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is
part of the Strategic Transport Team within the Development and Economic
Growth Service.  No Council funding is currently received by the Active Travel
Team. All project costs, including internal staff costs, have to be funded via
successfully securing highly competitive external challenge funds.

Page 4

4.2. In 2023/24 the Active Travel Team secured £1.4M external funding for the
development and delivery of a total of 16 projects across Argyll and Bute, including
the Helensburgh – Cardross – Dumbarton Cyclepath.  This required 19 separate
competitive funding applications to 6 separate funds. 
Funding 
4.3. Transport Scotland’s Places for Everyone (PFE) programme has been the
primary external active travel design funding in Scotland for over a decade.  It is
structured around 8 project stages with a competitive challenge fund, with the 32
local authorities, 7 regional transport partnerships, two national parks and
numerous community groups across Scotland competing against each other to
secure the funding each project requires. It has been announced that the PFE
Programme will by wound down with a final closure date of December 2025. 
4.4. Transport Scotland have informed Officers that, as of 25/26, the funding model
for active travel will change.  The primary change will be the reallocation of the
significant funding previously disbursed via third-sector organisations (such as
Sustrans with Places for Everyone fund) to a single Transport Scotland
controlled Active Travel Infrastructure Fund Tier 2 fund.  The new fund will
remain as a competitive challenge fund and is expected to be significantly
oversubscribed due to the number of high value projects being progressed
across Scotland and will therefore be highly competitive.   
4.5. Transport Scotland have confirmed that ATIF Tier 2 funding will continue to
follow the same 8–stage design and delivery process as the previous PFE
Programme.  The project stages are (0) Strategic Definition, (1) Preparation and
Brief, (2) Concept Design), (3) Developed Design, (4) Technical Design, (5)
Construction, (6) Handover & Close Out, and (7) In Use. 
4.6. While the design work has, to date, been funded by jointly by the Strathclyde
Partnership for Transport (SPT) Capital Programme and Transport Scotland’s
PFE programme, the decision to de-fund the SPT Capital Programme in 24/25
results in the project being fully reliant on securing 24/25 PFE funding or internal
Council funding in order to continue work to complete the outstanding design
requirements. 
4.7. In 24/25, Officers secured £150,000 from the PFE Programme to continue
design work in relation to all 3 phases of the Helensburgh – Cardross –
Dumbarton Cyclepath project. 
4.8. Officers have applied to Transport Scotland’s 25/25 ATIF Tier 2 fund to enable
design work to continue to complete Developed and Technical design for all
sections of the project.  Transport Scotland have stated they aim to confirm
25/26 funding awards by April 2025, subject to funding.

Page 5

Match Funding 
4.9. The 25/26 application guidance for the new Transport Scotland Active Travel
Infrastructure Fund Tier 2 for construction ready projects states that all projects
submitted for construction funding will require to provide match funding for a
minimum of 30% of the 25/26 construction cost from non-Transport Scotland
derived sources. 
4.10. While full construction costs are still to be determined, based on similar projects
elsewhere it is recommended Members identify construction match funding of at
least £3M to complete the cyclepath. 
4.11. Phasing construction over a number of financial years will reduce the level of
match funding the Council must secure each financial year, however this will result
in a longer construction programme.  Accelerating the construction programme
will require additional match funding to be secured, from internal and/or external
sources, which could prove challenging given the current economic climate. 
4.12. At present no construction match funding has been secured.  It is likely to be
beneficial to the project if sources of construction match funding could be secured
at an early stage, including consideration of any internal Council funds which
could be allocated to the delivery of this priority project. 
Design 
Phase 1 Colgrain to Cardross & Phase 2 Cardross to Dumbarton 
4.13. Phase 1 & 2: Officers worked with Procurement colleagues undertake a
procurement exercise for a new design team to complete the Developed Design
(Stage 3) and Technical Design (Stage 4) covering Phase 1 (Colgrain –
Cardross) and Phase 2 (Cardross – Dumbarton).  This is necessary to complete
the outstanding items of work which are required to deliver a robust design
package and to satisfy funder requirements. 
4.14. Phase 1 & 2: Following a competitive open tender process via Public Contracts
Scotland, the preferred tenderer was identified as Connected Transport
Planning (CTP).  Due to funding restrictions, a contract was awarded to CTP for
February and March 2025 to enable initial progress on continuing the Developed
design stage to be made.  Subject to securing appropriate funding, the
procurement has been structured to allow a contract to be directly award to CTP
for 2025/26 to continue the Developed and Technical design stages. 
Land Access 
4.15. A key element of the outstanding design deliverables are on-site survey work,
including Ecological surveys and Ground Investigation (GI) surveys.  When
previously contacted, a number of landowners were willing to give permission for
the necessary surveys.  However, a significant minority of landowners declined
to give permission.  While it is planned that all landowners will be re-contacted
by the new CTP design team, it may be necessary for the Council to use its

Page 6

statutory powers to require landowners who do not voluntarily provide the
access required for surveys. 
4.16. At time of writing, Officers continue to continue to seek guidance from Legal
Services on the use of the Council’s statutory powers to enforce access to
private land for the necessary surveys where landowner permission is not
forthcoming. 
Phase 3 Helensburgh Town 
4.17. Phase 3: Civic Engineers (CE) have continued to developed the Concept
Design for Phase 3 of the project as part of the Helensburgh Town Centre East
(Helensburgh in Motion) project.  It is programmed that the Concept Design
work will be completed by late March 2025 in line with the funders requirements. 
4.18. A community consultation was held between 23 November 2024 to 05 January
2025.  Information material and the survey were available on-line via the
Council’s website for the 6-week period, with posters and flyers distributed to
local shops, library and churches.  The consultation was also promoted via
appropriate social media channels.  Two in-person events were held, at the
Hermitage Academy Christmas Fair on 23 November and at the Helensburgh
and Lomond Civic Centre on 16 December.  Officers and the design team also
attended the Helensburgh Community Council meeting on 28 November 2024. 
The consultation received a total of 185 responses. 
4.19. Key results are presented below. 
Daily, 30%
Several time a
week, 43%
Once a week,
11%
Rarely, 7%
Once a month,
6% Never, 3%
How often would you engage with the identified
route?
Daily
Several time a
week
Once a week
Rarely
Once a month
Never

Page 7

Yes
85%
No
10%
Unsure
5%
Do you believe improvements to this area will
make people more likely to walk, wheel, cycle
etc?
Yes
No
Unsure
Improved cycling
infrastructure
24%
Traffic calming
measures
15%
More rest areas /
seating
9%
Wayfinding /
signage
10%
More, or safer
crossing points
19%
Bicycle parking or
storage
11%
More, or
improved drop
kerbs
10%
I don't think this route needs anything
Improvements Required
Improved cycling infrastructure Traffic calming measures
More rest areas / seating Wayfinding / signage
More, or safer crossing points Bicycle parking or storage
More, or improved drop kerbs I don't think this route needs anything

Page 8

Land Acquisition 
4.20. The delay in award of 2024/25 funding and the requirement to tender for a new
design team to complete the design resulted in a hiatus in relation to providing
information requested by landowners including, for example, detailed drainage
designs.  Officers have written to affected landowner to inform them of the
appointment of CTP as the design team. 
4.21. Officers continue to engage with colleagues in Legal Services to seek them to
commence the necessary documentation to develop a CPO for approval from
Council for the remaining sections of this important route. 
Construction (stage 5) 
Cardross Rail Station to Geilston Burn 
4.22. Cardross Rail Station to Geilston Burn.  The Council’s Roads and Infrastructure
Service have completed installation of most elements of the cyclepath through
Cardross Park, with only a small amount of fencing still to be installed. 
4.23. With the changes to the active travel funding model for 24/25 onwards, it is
expected that the costs for the remaining fencing work will require to be covered
from, as yet to be identified, internal Council budgets. 
4.24. To protect the public, the bridge over the Geilston Burn has been fenced off until
access is agreed to further land on the west side of the Burn to construct the
path through to an accessible destination. 
Yes
26%
No
59%
Unsure
15%
Do you feel safe when engaging in active travel
on the identified route at present?
Yes
No
Unsure

Page 9

Risk 
4.25. Risk refers to events which have not yet happened but which could impact on
the project if they were to happen.  A risk can be negative or positive to the
project.  Risks are identified through the lifetime of the project and, where
possible, mitigation is planned to minimise negative impacts or maximise
positive impacts.  As risks evolve relatively slowly through the lifetime of a
project, it is not expect that the tables below will alter significantly within the
current stage of work. 
4.26. Project risks relate to risks which could affect the overall project.  Table 1
provides the top 5 identified project risks and planned mitigation. 
Table 1: Selected Project Risks
Risk Risk Description Risk Level Mitigation
Land
acquisition
Inability to secure
agreement for land required
within an acceptable
timescale and cost.
High 1. Engagement with landowners to
gain acceptance of design.
2. Use of Council’s Estates Team to
lead land acquisition.
3. Consideration of option of a CPO.
Funding Inability to secure necessary
funding to pay of either (a)
design work; and/or, (b)
construction costs.
Medium 1. Close engagement with external
funders to ensure project meets
their funding requirements.
2. Officers continue to explore
potential alternative funding
sources.
3. Early engagement with Members
to identify potential sources of
construction match funding.
Programme Inability to meet challenging
programme timeline.
High 1. Regular review of programme.
2. Work with key stakeholders to
understand programme drivers
and barriers.
3. Establish realistic timescales for
each package of work.
Community
support
Loss of community support
for the project.
Low 1. Consult the community on key
design decisions as appropriate.
2. Seek to deliver project which
meets community’s key
requirements.
3. Keep community informed via
project updates at appropriate
times, including publicly available
quarterly committee reports.
Funder
requirements
Failure to meet external
funder requirements,
thereby losing funding.
Medium 1. Engage with funders to fully
understand their requirements.
2. Ensure project outcomes/outputs
meet funders’ requirements.
3. Review funding options regularly to
ensure funding sought/secured is
most appropriate to the project. 
4.27. Design risk refers to risk that the design fail to meet the required standards
and/or design conditions imposed by external factors, for example
environmental requirements. Design risks, if allowed to occur, can become
issues which may mean the project design has to be changed, which can

Page 10

cause delays and cost increases. Defects or failures in the design can also
result in an increase in future maintenance costs.  Table 1 provides the top 5
identified design risks and planned mitigation. 
Table 2: Selected Design Risks
Risk Risk Description Risk Level Mitigation
Ground
Conditions
Lack of Ground
Investigation (GI) limits
understanding of the
ground conditions the
route will be constructed
over.
High 1. Design route to be as robust as
practicable.
2. Undertake Ground Investigation
works at earliest practicable date.
Ecological
Impacts
Working adjacent to the
Inner Clyde SSSI and
RAMSAR site results in
additional ecological
requirements which the
designs must meet. 
High 1. Engage with regulators, e.g.
NatureScot, at early stage in design.
2. Undertake comprehensive
ecological surveys to inform design.
3. Develop full Habitat Regulations
Appraisal to ensure ecological
requirements taken into account in
design.
Drainage Constructed at the foot of
the slope, the design will
require to cater for all run-
off and drainage from the
slopes above, while
satisfying regulatory
requirements.
Medium 1. Develop drainage designs through
design process.
2. Engage with regulators, e.g. SEPA,
at early stage in design.
3. Engage with landowners, as
repository of knowledge of existing
conditions, during design
development.
Flood Risk The route is close to and,
in locations, within areas
identified as at risk from 1
in 200 year flood events.
Medium 1. Develop flood risk assessment at
early stage in design process to
identify key areas of risk.
2. Keep flood risk assessment under
review through design process.
3. Design of cyclepath to take account
of flood risk where appropriate.
Proximity to
railway
The majority of the route is
in proximity to the live
railway and requires to
ensure the designs do not
negatively impact on the
railway.
Medium 1. Early engagement with Network Rail
to understand their safety and
operational requirements.
2. Seek to agree ‘standard’ approach
to mitigating safety and operation
requirements which can be applied
to all or most of route.
3. Review of designs to ensure railway
safety and operational risk is
mitigated appropriately. 
Landowner Engagement 
4.28. Landowner searches for Phase 1 (Moss Road, Colgrain to Cardross) have
identified the land is held by 5 landowners.  The preferred route for Phase 2 (Ferry
Road, Cardross to Dumbarton) has a total of 6 landowners identified on it. 
4.29. Previous discussions with landowners has confirmed they wish to provide the
least land practical to deliver the path.  As such, progression of land acquisition
requires designs to be finalised in order to firmly identify the necessary land.  Once
the design process has been completed, the Council’s Estates Team will require
to be engaged to progress land acquisition.

Page 11

4.30. Engagement with landowners along the route are driven by progress with design
work which has resulted in an irregular pattern of landowner contact.  It is
understood that, particularly over the long timeline this project has been in
development, irregular contact can result in uncertainty around the Council’s
intentions and likelihood of the project progressing.  It is intended that, with the
appointment of the CTP to complete the design work, more regular contact with
landowners will be attained as the design is progressed and, once the design is
completed, with the Council’s Estates Team in order to seek a negotiated land
acquisition. 
Maintenance 
4.31. It is a requirement of the external funders that a written maintenance plan
including confirmation of how this will be funded and delivered is developed as
part of the design process.  As such, Members require to decide how the future
maintenance of the cyclepath, including sections of route already in place, will be
delivered.  At present, the Council does not receive any funding for the
maintenance of cyclepaths and none of the current external funding sources
secured through competitive bidding for active travel include maintenance as an
eligible cost.  This anomaly has been repeatedly raised by Officers with Transport
Scotland Officials and it is recognised to be inconsistent with the Scottish
Government’s commitments regarding capital funding for active travel projects. 
4.32. Officers have suggested routine maintenance of the cyclepath as a potential role
for local community group volunteers, for example cutting back vegetation /
mowing the grass.  Similar maintenance work is undertaken by community groups
for cyclepaths in other locations.  However, this suggestion has, to date, not been
positively received by the community.  As such, Members require to consider
alternative options for the long-term maintenance of the path. 
4.33. The Roads and Infrastructure Service are the single service within the Council
which includes infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths. While it is acknowledged these
teams are already near capacity delivering the Roads and Infrastructure Service
commitments and that the Roads and Infrastructure Service has previously stated
they do not wish to adopt sections of cyclepath remote from the public road, as
the only service within the Council with the appropriate teams to maintain a
cyclepath, it is recommended that Members instruct Roads and Infrastructure
Service to adopt every section of the cyclepath as it is constructed including those
sections remote from the public road. 
Programme 
4.34. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre.

Page 12

5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking
Helensburgh, Cardross and Dumbarton.  This route will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor to travel more
sustainably and actively by walking and cycling.  This will provide a safe
alternative to having to use a private car to travel between these communities
and help lower Argyll and Bute’s carbon footprint. Funding for these works has
been secured from our key active travel partners with further bids being
developed to enable the design and construction of further sections of the
cycleway as and when land acquisition has been concluded. 
5.2. The delivery of the Helensburgh – Cardross – Dumbarton Cyclepath is
dependent on completing the design work, securing highly competitive external
challenge funding, committing appropriate match funding and securing access to
private land for the route. 
6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
Outcomes Improvement Plan outcomes 1: Transport
Infrastructure and 3: Community Wellbeing. The
project also supports achievement of the Scottish
Government’s objectives set out in the Cycling Action
Plan for Scotland (CAPS) and Let’s Get Scotland
Walking - The National Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
External funding is not currently available to cover
maintenance costs.  To date, the Council has not
contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to
require social care services in later life which could
result in a future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase
including a CPO should this be deemed necessary.
6.4. HR None.
6.5. Fairer Scotland
Duty: 
6.5.1 Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton

Page 13

corridor to travel more sustainably and actively by
walking, wheeling and cycling.
The route has been designed to be DDA compliant
and will provide a safe and accessible route for those
with mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.5.2 Socio-
economic Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel,
which are lower cost than alternative modes of
transport.  The route will also improve access to
essential services, retail, leisure and employment
opportunities for residents living along the route, with
studies demonstrating those who travelled actively had
a higher monthly spend in local businesses than those
who travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.5.3 Islands There are no adverse impacts.
6.6. Climate Change  Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will
help lower Argyll and Bute’s carbon footprint.
6.7. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.8. Customer
Services  
None.
6.9. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates even stronger
support for the delivery of the Helensburgh – Cardross
– Dumbarton Cyclepath from younger members of the
community than the already high overall level of
community support. Wider engagement with school
pupils indicates that the vast majority of pupils strongly
support the provision of new active travel
infrastructure, even where it would adversely impact
other modes of transport.

Page 14

Executive Director with the responsibility for Development and Economic
Growth: Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity, Councillor John Armour 
03 February 2025                                                  
For further information contact:   
Fergus Murray, Head of Development and Economic Growth 
Fergus.murray@argyll-bute.gov.uk 
Colin Young, Strategic Transportation Delivery Officer
Colin.Young@argyll-bute.gov.uk     
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme