ARGYLL AND BUTE COUNCIL   HELENSBURGH & LOMOND AREA 
COMMITTEE
COMMERCIAL SERVICES 10 JUNE 2025 
CHORD-HELENSBURGH: SURPLUS FUNDS, COMET PLINTH 
1. EXECUTIVE SUMMARY 
This report provides members with updated and costed proposals for the manufacture
of a lit plinth to display a resin encapsulated model of the PS ‘Comet,’ and which will
subsequently be housed and put on permanent public display in Helensburgh town
centre. In addition, it provides further information in respect of the remaining models of
PS ‘Comet.’
In December 2016, following the successful completion of the CHORD – Helensburgh
project, the Area Committee took the decision to allocate the ‘surplus’ funds to take
forward additional works which were complimentary to the CHORD proposals. This
included funding to develop a lit and resin encapsulated model of the PS ‘Comet’ which
would be mounted on a suitable plinth for public display, as well as consideration as to
how the remaining models of the PS ‘Comet’ might be used going forward. The Area
Committee allocated £3,500 towards the ‘Comet Plinth’ and £1,000 towards the ‘Flotilla
of Comets’ as they became known.
The report provides a breakdown of the updated cost plan of £5,291.53 (excluding VAT)
for the ‘Comet Plinth’.
RECOMMENDATIONS 
The Area Committee is asked to: 
1. Consider and note the contents of the Report, 
2. Approve the allocation of up to £5,291.53 (excluding VAT) towards the cost of
creating the ‘Comet Plinth’, and 
3. Approve that the balance of the Surplus Funds budget be transferred to the
Outdoor museum Budget upon conclusion of the Comet Plinth works

Page 2

ARGYLL AND BUTE COUNCIL   HELENSBURGH & LOMOND AREA 
COMMITTEE
COMMERCIAL SERVICES 10 JUNE 2025 
CHORD-HELENSBURGH: SURPLUS FUNDS, COMET PLINTH 
2. INTRODUCTION 
2.1 Following the completion of the CHORD – Helensburgh works there was surplus
capital funding of £653,119 which was allocated in October 2016 to a programme of
complimentary works, primarily pavement and carriageway improvements to be taken
forward by Roads and Infrastructure Services.
2.2 In addition, there were works and funding associated with the concept of the
Outdoor Museum, and this included specific funding allocations for the ‘Comet Plinth’
and the ‘Flotilla of Comets’ with the Area Committee allocating £3,500 and £1,000,
respectively.
2.3 As of 1 December 2024, there remained a total of £24,879.81 in the Surplus
Funds budget, including the £4,500 allocated to the Comets. At its meeting on 10
December 2024 the Area Committee allocated up to £21k towards the removal of
stainless-steel bins from 
2.4 The report provides members with the updated cost plan for the fabrication of
the ‘Comet Plinth’ at a cost of £5,291.53 (excluding VAT) and further information in
respect of the remaining models of the Comet.
3 RECOMMENDATIONS
The Area Committee is asked to:
3.1 Consider and note the contents of the Report, 
3.2 Approve the allocation of up to £5,291.53 (excluding VAT) towards the
cost of creating the ‘Comet Plinth’, and 
3.3 Approve that the balance of the Surplus Funds budget be transferred to
the Outdoor museum Budget upon conclusion of the Comet Plinth works
4 DETAIL
4.1 During the CHORD Project the existing lamp posts in Colquhoun Square were
replaced, and the models of the PS Comet that adorned them were disposed of. Several

Page 3

of these models were subsequently rescued by the arts organisation WAVEparticle,
which had been instrumental in the creation the Helensburgh Outdoor Museum. 
Fig.1 Comet model on the top of the original lamppost in Colquhoun Square
4.2 The model in the best condition was selected to be encapsulated within acrylic
resin so that it could subsequently be mounted on a plinth, incorporating lighting and
controls, and put on permanent public display. The original intention was that the plinth
would be on display in the open air e.g. in Colquhoun Square, however, concerns around
the acrylic resins exposure to environmental conditions, which cause the resin to go
opaque over time, has led to the conclusion that it would be better to house the plinth
within a publicly accessible building in Helensburgh Town Centre e.g. Helensburgh and
Lomond Civic Centre. 
Fig. 2 Comet model encapsulated in acrylic
4.3 We have worked with WAVEparticle to update the cost plan in line with this
revised proposal for internal display, and consequently can advise a cost of £5,291.53
(excluding VAT), which is broken down as follows:

Page 4

4.4 This would provide a quality display/presentation platform for the encapsulated
model of the Comet, and which could be housed in a publicly accessible building in
Helensburgh town centre. The lighting controls mean that assorted colour and intensity
settings can be achieved resulting in the ability to set different ‘moods/atmospheres’ for
the model. WAVEparticle will also develop a plaque or similar to be mounted on the
cabinet, providing background information on the PS Comet. It also provides flexibility
for the display to be temporarily relocated to other buildings within the Council area, e.g.
in support of maritime themed events.
4.5 Discussions with colleagues in Roads and Infrastructure Services have confirmed
a revised cost estimate for them to replace the stainless-steel bins in the town centre,
and that this can now be achieved for a cost of £17,000, as compared to the £21,000
allocated by the Area Committee in December 2024. Allowing for the cost of replacing
the silver bins, plus the cost of completing the Comet Plinth, a total of £22,291.53 to
deliver both, leaving a balance in the Surplus Funds Budget of £2,588.28.
4.6 There will then remain seven more models of the Comet a use for which is still to
be determined/identified. We would therefore recommend that these are held in storage
by the Council and made available when a suitable and sympathetic use is identified for
them in the future. The balance of the surplus funds (a minimum of £2,588.28) could be
transferred to the Outdoor Museum budget upon completion of the Comet Plinth works.
5 CONCLUSION
5.1 The Surplus Funds works provided an opportunity to extend the benefits of the
original Helensburgh CHORD Works, and the completion of the Comet Plinth will bring
these works to a conclusion.
Acrylic Encapsulated Coment Plinth incl Stand
Project Management
1. Wave particle @ 2-days £545.96
£1,091.92
Metal Casing/Stand for Encapsulated Comet
2. Metal Casing 710mm x 370mm x 470mm incl. drawer and security
lock to hold lightbox £2,039.85
3. Powder coating - matt black £239.98
4. Fixings £179.99
£2,459.81
Encapsulated Comet 700mm x 350mm x 450mm (existing)
5. Preparation for public display £60.00
6. Sandblasted base £299.98
7. Acrylic polished/buffed £359.97
£719.95
Lighing and Controls
8. Bespoke LED lightbox 700mm x  350mm x 120mm £538.80 Addlux Quote AB15-Q1
9. 2x blade LRI Units 663mm long £0.00
10. DMS RGB Controller (optional) £0.00
11. Timer clock (optional) £0.00
£538.80
Transport
12. delivery to installation site £359.97
£359.97
subtotal £4,810.48
Contingency @ 10% £481.05 £5,291.53
VAT @ 20% £1,058.31
£1,058.31
subtotal £6,349.83
Cost Plan                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           
Jan-25

Page 5

6 IMPLICATIONS
6.1 Policy – The original CHORD Programme fitted to the Council’s Corporate Plan,
Single Outcome Agreement and approved Development Plan policy for town centre
regeneration.
6.2 Financial – Allocation of £5,291.53 from the remaining CHORD - Helensburgh
surplus funds, and transfer of any residual balance to the Helensburgh Outdoor
Museum Budget upon completion.
6.3  Legal – no implications
6.4  HR – no implications
6.5  Fairer Scotland Duty: 
6.5.1 Equalities - protected characteristics – no implications 
6.5.2 Socio-economic Duty – no implications 
6.5.3 Islands – no implications
6.6 Climate Change the lighting system operates using energy efficient LED’s
reducing power consumption
6.7 Risk – Cost Plan includes 10% Contingency Allowance
6.8  Customer Service – no implications 
Douglas Hendry
Executive Director with responsibility for Commercial Services
Cllr Ross Moreland
Policy Lead for Financial and Commercial Services 
7 March 2025                                                  
For further information contact: John Gordon, PPMS Programme Manager, Tel:
01369 708457 or Mobile: 07901 516 106