Argyll and Bute Council
Development and Economic Growth   
This report is an Update to Members on responses sent to the Scottish Government’s
Energy Consents Unit (ECU) on the Section 36 Consultations for the following
applications; 
1) Killearn Wind Farm 
Reference Nos: 24/01541/S36 /ECU 00004927 
Applicant: Renewable Energy Systems Ltd (RES) 
Proposals: Development comprising 9 wind turbines up to 180 metres tip height (each
generating around 6.6MW) and associated infrastructure 
And 
2) Balliemeanoch Pump Storage Hydro 
Reference Nos : 24/01324/S36 / ECU00003444 
Applicant:  Intelligent Land Investments (ILI)(Consultation from Scottish Government) 
Proposals: Construct a PSH scheme located close to Lochan Airigh. It is approximately 4.4
km to the south of the village of Portsonachan and 9 km northwest of the town of Inveraray.
Subject to further design studies it is anticipated that the proposed Development will have an
installed electrical generation capacity of up to 1,500 megawatts (MW) and a storage capacity
of approximately 45,000 megawatt hours (MWh).
_________________________________________________________________________  
1.0 INTRODUCTION 
The purpose of this report is to update Members of the submission of two holding objections
to the Scottish Government Energy Consents Unit in relation to the above referenced S36
consultations.
As a point of procedural clarification, these require to be lodged as an objection to the ECU
as there is no formal process to allow a “holding objection” even although this is in reality what
is intended. It is the intention of Officers to report these applications to Members at a future
date when sufficient information has been provided, necessary consultation responses
provided (external and internal), and time allowed to produce a report making a properly
informed and balanced recommendation to Members.
This would also be the case in the event that the ECU determine to pass the cases over to the
DPEA.
2.0 DETAIL
Applications made for developments with an electricity generating capacity of more that 50MW
are considered under s36 of the Electricity Act 1989.  The Council is not the decision maker
in these circumstances and is a consultee in its capacity as Planning Authority.
Where a s36 consent is issued, Scottish Ministers can direct that planning permission be
deemed to be granted.  Deemed planning permission has broadly the same effect as a normal

Page 2

planning permission in that it can be subject to conditions, capable of variation and enforced
by the Planning Authority.
These large-scale energy developments which are covered by the Electricity Act will normally
be supported by an Environmental Impact Assessment.  In these circumstances, the ECU give
the Council four months to consider these proposals.  In reaching a view on these
consultations, the Planning Authority undertake internal consultations and assess the
proposals against the policies of the Development Plan.  
The Development Plan which currently comprises NPF4 and LDP2 contains policies on a wide
range of topics.  In many cases, the assessment of these policies requires input from statutory
consultees with expert knowledge but as these are s36 applications, it is the ECU that
undertakes the consultations.  The Planning Authority uses the advice contained within these
consultation responses to inform an assessment on whether the proposal would comply with
Development Plan policies.  Officers consider this is essential in order to undertake a proper
assessment of the proposal and reach a view on its acceptability.  This is because, as noted
earlier, a s36 consultation could eventually result in a deemed planning application which the
Planning Authority would need to manage in the same way as a normal planning application
including the discharge of conditions and enforcement.
While the ECU will consider these issues under the Electricity Act 1989, they are not assessing
the proposals against Development Plan policy. It is understood that they will rely largely on
the Planning Authority responsible for this issue.
It is the aim of officers to ensure that any S36 reports presented to Members have been fully
considered with all outstanding matters fully and properly considered in preparing a report
and providing a recommendation to Members.
The ECU has advised that requests for extensions of more than an additional 4 months,
beyond the period already provided for in the regulations, will only be granted in exceptional
circumstances. Officers have been advised that extensions requested for the reasons listed
below on their own, will not be considered ‘exceptional’:
• Consideration of Additional Information or other clarifications
• Availability of Planning Committees
• Consideration of other Consultee Responses
• Resourcing Issues
• Technical Expertise 
If the Council do not respond within the timescale set by the ECU, the Council loses the right
to require a public inquiry to be held should it choose to object to the proposal.  In order to
ensure that this right is not lost, officers are of the view that holding objections require to be
submitted to the ECU prior to the deadline for response.
3.0 OUTSTANDING AND UNRESOLVED MATTERS
In relation to these two s36 consultations, the following matters are still outstanding and
unresolved:
1) Killearn Wind Farm (Holding Objection Submitted 21 May 2025) 
• Unresolved objection from National Air Traffic Services
• Requirement to secure consultation advice from the West of Scotland Archaeology
Service.

Page 3

• Requirement to secure visualisation packs for Councillors in advance of committee. 
2) Balliemeanoch Pump Storage Hydro
The applicants submitted further Environmental Information on 22 May 2025 in response to
Objections and concerns received to the initial submissions. At time of writing there have been
no further external consultee responses placed on the ECU website. Currently therefore the
following matters are outstanding and require to be resolved/considered further before a
competent committee report advising Members can be written and presented to PPSL;
• Unresolved objection from NatureScot 
• Unresolved objection from SEPA
• Unresolved objection from Dawnfresh
• Unresolved objection from SSE
• Unresolved objection from Argyll Fisheries Trust
• Unresolved objection from RSPB
• Unresolved objection from Glenorchy and Innishail Community Council 
In this instance the reason for submitting this holding objection was that the Council was
unable to undertake a proper assessment of the proposal and make a fully informed and
competent decision within the previously agreed extended timescale of 28.06.25.  
4.0 RECOMMENDATION
It is recommended that Members note: 
• The submission of these two holding objections to the Energy Consents Unit to
safeguard the Council’s position.
• That Officers will present a report to PPSL at a future date on each of these S36
applications for their views, as and when it is competent to do so. 
Author of Report: David Moore   Date: 04.08.2025
Reviewing Officer:  Sandra Davies  Date: 06.08.2025 
Fergus Murray 
Head of Development and Economic Growth