Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme 
Activity
2024/25 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2032/33
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Funding Applications                                                
Phase 1: Helensburgh to Cardross                                    
Route Design: Helensburgh to Cardross                                                
Land Purchase Negotiations: Helensburgh to Cardross                                                
CPO Process (if required):                                                
- Provide CPO recommendation to Council                                    
- Develop CPO                                                
- Gain Full Council approval for CPO                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                
- CPO Process                                                
Construction: Helensburgh to Cardross                                                
Construction of Helensburgh to Cardross Section 1                                                
Construction of Helensburgh to Cardross Section 2                                                
Construction of Helensburgh to Cardross Section 3                                                
Construction of Helensburgh to Cardross Section 4                                                
Phase 2: Cardross to Dumbarton                                    
Route Design: Cardross to Dumbarton                                                
Land Purchase Negotiations: Cardross to Dumbarton                                                
CPO Process (if required):                                                
- Provide CPO recommendation to Council                                    
- Develop CPO                                                
- Gain Full Council approval for CPO                                                
- Advertise CPO                                    
- Lodge CPO with Scottish Government                                                
- CPO Process                                                
Construction: Cardross to Dumbarton                                                
Construction of Cardross to Dumbarton Section 1                                    
Construction of Cardross to Dumbarton Section 2                                    
Construction of Cardross to Dumbarton Section 3                                                
Construction of Cardross to Dumbarton Section 4                                                
Helensburgh: Hermitage Academy to Town Centre                                    
Community Consultation & Route Identification                                    
Route Design                                    
Land Access Negotiations (if required)                                    
Redetermination Order(s) / Traffic Regulation Order(s)                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Section 1                                    
Construction of route from Hermitage Academy to Helensburgh Town
Centre Section 2                                                 
Colour Key (Responsibilities / Lead): 
Green: Strategic Transportation (Development and Economic Growth) 
Blue: Road and Infrastructure Service 
Orange: Estates Service 
Red: Legal 
Purple: External to Council (e.g. Scottish Government)
Negotiated
access
If no private
land required
If no private land
required
Negotiated
access
Negotiated
access
Negotiated
access
Negotiated
access
Negotiated
access
Negotiated
access
Negotiated
access