ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
09 December 2025 
Helensburgh, Cardross and Dumbarton Cyclepath Progress Report 
1.0 EXECUTIVE SUMMARY 
1.1. This report updates Members on the progress made since the previous report to
this Committee on 09 September 2025 in relation to the delivery of a high-quality
walking and cycle route linking Helensburgh, Cardross and Dumbarton. 
1.2. Surveys: initial topographical and ecological surveys have been completed.
Winter birds surveys necessary due to the proximity of the project to the Inner
Clyde SSSI are ongoing and are forecast to be completed by spring 2026. 
1.3. Phase 1: The design consultants, Connected Transport Planning (CTP), are
undertaking a deliverability review re-considering both the route adjacent to the
inland side of the railway line and a route adjacent to the A814 road. This
deliverability review considers a range of relevant factors including construction
works, drainage, land take, maintainability, landowner support and ecology. The
team are working towards concluding the deliverability review of Phase 1 route
options this calendar year. At time of writing, the review indicates that a route
following the southern (seaward) side of the A814 would be more deliverable
compared to a route following the inland side of the railway as well as offering
additional benefits for future maintainability and personal safety perspectives.
Therefore, at the time of writing the emerging preferred route for phase 1 is
adjacent to the A814. 
1.4. As part of the deliverability review of Phase 1, Officers and consultancy staff
working collaboratively have continued to meet with landowners to seek their
support for a single route. All landowners have provisionally stated support for a
route following the A814 subject to localized design considerations. It is expected
that having landowner support for a single route will enable faster development
and delivery of the route and is a consideration in the route deliverability review
process. 
1.5. Phase 2: Following the deliverability review of the section of the route linking
Cardross and Dumbarton, some amendments have been made to the concept
design. The most significant amendment identified is to improve the design for the
Ferry Road/Craigend Road/A814 junction. Realignment of Craigend Road
improves the sightlines and access for the farms located on the private Craigend
Road and has enabled the design for the junction of Ferry Road/A814 to be
revised, with an updated design for a signalised pedestrian crossing in lieu of the
previously promoted signalised junction. This updated design for Ferry

Page 2

Road/A814 is forecast to be fully accommodated within the road corridor,
therefore there is no requirement for any space from residential gardens. The
design reduces the visual impact compared to the previous proposal to fully
signalise the junction of Ferry Road/Craigend Road/A814. The changes are also
forecast to improve visibility for drivers exiting from Ferry Road. 
1.6. Landowners on the Phase 2 section linking Cardross and Dumbarton have
agreed in principle to an outline design. The consultant’s civil engineering team
are now detailing the outline design up to developed design stage, suitable for
future public engagement planned for spring/summer 2026. 
1.7. The engineering team are working to define the ground investigation surveys
required to enable the full engineering design, and will be engaging with relevant
landowners to seek their agreement to undertake these surveys in the coming
weeks. It is anticipated that surveys could be completed early in the new year,
subject to securing landowner agreement. 
1.8. Phase 3: Officers are working to tender for a new design team to progress the
designs for Phase 3 linking Helensburgh Waterfront to Morrison’s Supermarket
from the current concept stage through developed and technical stages, subject
to securing funding in future financial years. 
1.9. Funding: Officers have continued engagement with colleagues in Transport
Scotland and now expect to receive a funding offer for 25/26 in early December.
Transport Scotland have confirmed that this funding offer can be backdated to
cover costs incurred across the full financial year 25/26. Transport Scotland has
also commenced the funding application process for 26/27, as active travel
funding is only awarded for a single financial year at a time. 
RECOMMENDATIONS 
1.10. It is recommended that the Helensburgh and Lomond members: 
1.10.1.Welcome the continued positive engagement of landowners. 
1.10.2.Support the updated layout for the junction of A814 / Ferry Road / Craigend Road. 
1.10.3.Instruct Officers to progress the Phase 1 route on basis of the one which is
identified as the most deliverable following conclusion of the deliverability review. 
1.10.4.Support efforts of Officers, subject to receiving suitable tender returns, to seek to
appoint a design team to complete development of Phase 3 designs through
Developed Design and Technical Design stages.

Page 3

ARGYLL AND BUTE COUNCIL  Helensburgh and Lomond Area
Committee
DEVELOPMENT AND ECONOMIC
GROWTH 
09 December 2025 
Helensburgh, Cardross and Dumbarton Cyclepath Progress Report 
2.0 INTRODUCTION 
2.1. This report updates Members on the progress made since the previous report to
this Committee on 09 September 2025 in relation to the delivery of a high-quality
walking and cycle route linking Helensburgh, Cardross and Dumbarton. 
2.2. Full details of the project, including previous progress is available in the project
update reports previously presented to this Committee. 
3.0 RECOMMENDATIONS 
3.1. It is recommended that the Helensburgh and Lomond members: 
3.1.1. Welcome the continued positive engagement of landowners. 
3.1.2. Support the updated layout for the junction of A814 / Ferry Road / Craigend Road. 
3.1.3. Instruct Officers to progress the Phase 1 route on basis of the one which is
identified as the most deliverable following conclusion of the deliverability review. 
3.1.4. Support efforts of Officers, subject to receiving suitable tender returns, to seek to
appoint a design team to complete development of Phase 3 designs through
Developed Design and Technical Design stages. 
4.0 DETAIL 
Funding 
4.1. Officers have continued engagement with colleagues in Transport Scotland and
now expect to receive a funding offer for 25/26 in early December. Transport
Scotland have confirmed that this funding offer can be backdated to cover costs
incurred across the full financial year 25/26. 
4.2. Transport Scotland have commenced the funding application process for 26/27,
as ATIF funding is only awarded for a single financial year. It is understood that
previous applications will require to be updated and will be reconsidered against
all other projects applied for in 26/27, but a new full application form will not require
to be completed as most of the information will not have changed. 
Landowner Engagement

Page 4

4.3. Landowner investigation for Phase 1 (Moss Road, Colgrain to Cardross) has
identified the land is held by 5 landowners. Phase 2 (Ferry Road, Cardross to
Dumbarton) has a total of 6 landowners identified. 
4.4. Phase 1: Officers and staff from the design consultants have continued to meet
with landowners on Phase 1 of the route between Cardross and Helensburgh
individually and as a group to seek landowner support for a single, deliverable
route. All landowners have provisionally stated support for a route following the
A814, subject to localized design considerations. It is expected that having
landowner support for a single route will enable faster development and delivery
of the route and is a consideration in the route deliverability review process. 
4.5. Phase 2: Following some amendments to the concept design, landowners on the
Phase 2 section linking Cardross and Dumbarton have agreed in principle to the
outline design. 
4.6. It is planned to continue dialogue with landowners as designs are developed to
capture landowner views within the design development process. 
Design 
Phase 1 Colgrain to Cardross 
4.7. Following securing the agreement of landowners, the initial non-invasive ecology
and topographical surveys have been completed. Winter birds surveys are
programmed to continue until spring 2026. 
4.8. As a number of changes have occurred since the current preferred route
alignment was selected in 2019, a deliverability review re-considering the route
adjacent to the inland side of the railway line and a route adjacent to the A814
road is being undertaken by the design consultants, Connected Transport
Planning (CTP). The purpose of this review is to identify the most deliverable
alignment, considering a range of relevant factors including construction works,
drainage, land take, maintainability, landowner support and ecology. The team
are working towards concluding the deliverability review of Phase 1 route options
this calendar year. At time of writing, the review indicates that a route following
the southern (seaward) side of the A814 would be more deliverable compared to
a route following the inland side of the railway. Both routes are forecast to provide
a similar level of end-user benefits with the road route offering additional
advantages in terms of natural surveillance and user safety. Therefore, at the time
of writing the emerging preferred route for phase 1 is adjacent to the A814. 
4.9. As part of the deliverability review of Phase 1, Officers and consultancy staff
working collaboratively have continued to meet with landowners to seek their
support for a single route. All landowners have provisionally stated support for a
route following the A814. It is expected that having full landowner support for a
single route will ultimately enable faster development and delivery of the route by
avoiding compulsory purchase. Landowner support is therefore a consideration
in the route deliverability review process.

Page 5

4.10. Following conclusion of the deliverability review, and any decision required on
route alignment to be developed, to continue to make progress with this project;
it is proposed that the consultant’s civil engineering team should progress to
developing designs for the route identified as the most deliverable up to developed
design stage, suitable for future public engagement in spring/summer 2026. 
4.11. The engineering team should also define the ground investigation surveys
required to enable the full engineering design and commence engagement with
relevant landowners to seek their agreement to undertake these surveys early in
2026. 
Phase 2 Cardross to Dumbarton 
4.12. Following securing the agreement of landowners, the initial non-invasive ecology
and topographical surveys have been completed. Winter birds surveys are
programmed to continue until spring 2026. 
4.13. The Ferry Road/Craigend Road/A814 junction design has been recast to realign
Craigend Road thereby improving the sightlines and access for the farms located
on the private Craigend Road. This has enabled the design for the junction of
Ferry Road/A814 to be revised with an updated design for a signalised pedestrian
crossing. This updated design can be fully accommodated within the road
corridor, therefore there is no requirement for any space from private gardens,
and reduces the visual impact compared to the previous proposal to fully signalise
the junction of Ferry Road/Craigend Road/A814 while improving sightlines for
drivers existing Ferry Road.  The concept general arrangement drawing for the
revised design is included as Appendix 2. 
4.14. The consultant’s civil engineering team are now detailing the outline designs up
to developed design stage, suitable for future public engagement in
spring/summer 2026. 
4.15. The engineering team are also working to define the ground investigation surveys
required to enable the full engineering design and will be engaging with relevant
landowners to seek their agreement to undertake these surveys in the coming
weeks. It is anticipated that phase 2 ground investigation surveys could be
completed early in the new year, subject to securing landowner agreement. 
Phase 3 Helensburgh Town 
4.16. Officers are working to tender for a new design team to progress the designs for
Phase 3 from the current concept stage through developed and technical stages,
subject to securing funding in future financial years. 
Land Acquisition 
4.17. Previous discussions with landowners have confirmed they wish to provide the
least land practical to deliver the path. As such, progression of land acquisition
requires designs to be further developed to firmly identify the necessary land.

Page 6

Once the design process has been completed, the Council’s Estates Team will
require to engage with landowners in a timely manner to progress land acquisition. 
Construction 
Cardross Rail Station to Geilston Burn 
4.18. Cardross Rail Station to Geilston Burn. The Council’s Roads and Infrastructure
Service have completed most elements of the cyclepath through Cardross Park,
with only a small amount of fencing still to be installed. It is expected that the costs
for the remaining fencing work will require to be covered from a yet to be identified
internal Council budget. 
4.19. To protect the public, the bridge over the Geilston Burn will remain fenced off until
access is agreed to land on the west side of the Burn to construct the path through
to an accessible destination. 
Maintenance 
4.20. It is a requirement of the external funders that a written maintenance plan
including confirmation of how this will be funded and delivered is developed as
part of the design process. At present, the Council does not receive any funding
for the maintenance of cyclepaths and none of the current external funding
sources secured through competitive bidding for active travel include
maintenance as an eligible cost. This anomaly has been repeatedly raised by
Officers with Transport Scotland Officials and it is recognised to be inconsistent
with the Scottish Government’s commitments regarding capital funding for active
travel projects. 
4.21. The Roads and Infrastructure Service are the single service within the Council
which includes infrastructure maintenance teams appropriately trained and
qualified to undertake maintenance of cyclepaths. The Traffic and Development
Officer for Helensburgh and Lomond is a member of the officer project group for
the cyclepath and is providing input from Roads and Infrastructure Service on the
designs to ensure these meet Roads and Infrastructure Service requirements for
adoption. 
Programme 
4.22. Appendix 1 provides the current programme of the key stages and forecast
timescales for each section of the Phase 1: Helensburgh to Cardross section of
the Cyclepath; Phase 2: Cardross to Dumbarton; and, Phase 3: Helensburgh:
Hermitage Academy to Town Centre. 
Risk 
4.23. Risk refers to events which have not yet happened but which could impact on the
project if they were to happen. A risk can be negative or positive to the project.
Risks are identified through the lifetime of the project and, where possible,
mitigation is planned to minimise negative impacts or maximise positive impacts.

Page 7

As risks evolve relatively slowly through the lifetime of a project, it is not expect
that the tables below will alter significantly within the current stage of work. 
4.24. Project risks relate to risks which could affect the overall project. Table 1 provides
the top 5 identified project risks and planned mitigation. 
Table: Selected Project Risks
Risk Risk Description Risk Impact Mitigation
Land access Inability to secure
agreement for temporary
access to land required to
undertake surveys.
High 1. Positively engage with landowners
to seek voluntary access
agreements.
2. Consideration of Council’s
statutory powers if necessary.
Land
acquisition
Inability to secure
agreement for land required
within an acceptable
timescale and cost.
High 1. Engagement with landowners to
gain acceptance of design.
2. Use of Council’s Estates Team to
lead land acquisition.
3. Consideration of option of a CPO.
Programme Inability to meet challenging
programme timeline.
High 1. Regular review of programme.
2. Work with key stakeholders to
understand programme drivers
and barriers.
3. Establish realistic timescales for
each package of work.
Funding Inability to secure necessary
funding to pay of either (a)
design work; and/or, (b)
construction costs.
Medium 1. Engagement with external
funder(s) to ensure project meets
their design and funding
requirements.
2. Review funding options regularly to
ensure funding sought/secured is
most appropriate to the project.
3. Early engagement with Members
to identify potential sources of
construction match funding.
Community
support
Loss of community support
for the project.
Low 1. Consult community on key design
decisions at appropriate time.
2. Seek to deliver project which
meets community’s key
requirements.
3. Keep community informed via
project updates at appropriate
times, including area committee
reports. 
4.25. Design risk refers to risk that the design fail to meet the required standards
and/or design conditions imposed by external factors, for example
environmental requirements. Design risks, if allowed to occur, can become
issues which may mean the project design has to be changed, which can cause
delays and cost increases. Defects or failures in the design can also result in
an increase in future maintenance costs.  Table 1 provides the top 5 identified
design risks and planned mitigation. 
Table 2: Selected Design Risks
Risk Risk Description Risk Impact Mitigation
Ecological
Impacts
Working adjacent to the
Inner Clyde SSSI and
RAMSAR site results in
High 1. Engage with regulators, e.g.
NatureScot, at early stage in design.

Page 8

additional ecological
requirements which the
designs must meet. 
2. Undertake comprehensive
ecological surveys to inform design.
3. Develop full Habitat Regulations
Appraisal to ensure ecological
requirements taken into account in
design.
Proximity to
railway
The majority of the route is
in proximity to the live
railway and requires to
ensure the designs do not
negatively impact on the
railway.
High 1. Early engagement with Network Rail
to understand their safety and
operational requirements.
2. Seek to agree ‘standard’ approach
to mitigating safety and operation
requirements which can be applied
to all or most of route.
3. Review of designs to ensure railway
safety and operational risk is
mitigated appropriately.
Ground
Conditions
Lack of Ground
Investigation (GI) limits
understanding of the
ground conditions the
route will be constructed
over.
High 1. Design route to be as robust as
practicable.
2. Undertake Ground Investigation
works at earliest practicable date.
Drainage The design will require to
cater for run-off and
drainage, while satisfying
regulatory requirements.
Medium 1. Develop drainage designs through
design process.
2. Engage with regulators, e.g. SEPA,
at early stage in design.
3. Engage with landowners, as
repository of knowledge of existing
conditions, during design
development.
Flood Risk The route is close to and,
in locations, within areas
identified as at risk from 1
in 200 year flood events.
Medium 1. Develop flood risk assessment at
early stage in design process to
identify key areas of risk.
2. Keep flood risk assessment under
review through design process.
3. Design of cyclepath to take account
of flood risk where appropriate. 
5.0 CONCLUSION 
5.1. Completion of the Helensburgh, Cardross and Dumbarton Cyclepath will provide
a dedicated, high quality, accessible walking and cycle route linking Helensburgh,
Cardross and Dumbarton. This route will provide opportunities for all in the
Helensburgh – Cardross – Dumbarton corridor to travel more sustainably and
actively by walking and cycling. This will provide a safe alternative to having to
use a private car to travel between these communities and help lower Argyll and
Bute’s carbon footprint. Funding for these works has been secured from our key
active travel partners with further bids being developed to enable the design and
construction of further sections of the cycleway as and when land acquisition has
been concluded. 
5.2. The delivery of the Helensburgh, Cardross and Dumbarton Cyclepath is
dependent on completing the design work, securing highly competitive external
challenge funding, committing appropriate match funding and securing access to
private land for the route.

Page 9

6.0 IMPLICATIONS 
6.1. Policy Completion of this project will support the Council’s
Outcomes Improvement Plan outcomes 1: Transport
Infrastructure and 3: Community Wellbeing. The project
also supports achievement of the Scottish
Government’s objectives set out in the Cycling Action
Plan for Scotland (CAPS) and Let’s Get Scotland
Walking - The National Walking Strategy.
6.2. Financial The design, construction and land purchase will be
funded by external competitive funding applications.
External funding is not currently available to cover
maintenance costs.  To date, the Council has not
contributed any funding to design or capital costs.  
There is strong evidence that people who are more
active, for example by walking or cycling, have been
physical and mental health and are less likely to require
social care services in later life which could result in a
future saving to the Council or HSCP.
6.3. Legal Continued input will be required from Legal Services to
support contractual agreements and land purchase.
6.4. HR None.
6.5. Customer Service None.
6.6. Risk There is a reputational risk to the Council if the project
is not completed within a reasonable timeframe.
6.7. Climate Change Active Travel is the least carbon intensive mode of
travel.  Providing the opportunity for residents and
visitors to consider an alternative to having to use a
private car to travel between these communities will help
lower Argyll and Bute’s carbon footprint.
6.8. Fairer Scotland
Duty
The route, once completed, will offer residents and
visitors the opportunity to choose to travel actively,
which is lower cost than alternative modes of transport. 
The route will also improve access to essential services,
retail, leisure and employment opportunities for
residents living along the route, thereby increasing
opportunities to reduce socio-economic disadvantage.
6.9. Equalities Completion of this project will provide opportunities for
all in the Helensburgh – Cardross – Dumbarton corridor
to travel more sustainably and actively by walking,
wheeling and cycling.
The route has been designed to be DDA compliant and
will provide a safe and accessible route for those with

Page 10

mobility aids including wheelchairs and
parents/guardians with a child’s pram or buggy.
6.10. Socio-economic
Duty
The route, once completed, will offer residents the
opportunity to choose to travel using active travel, which
are lower cost than alternative modes of transport.  The
route will also improve access to essential services,
retail, leisure and employment opportunities for
residents living along the route, with studies
demonstrating those who travelled actively had a higher
monthly spend in local businesses than those who
travel via motorised transport.
The path will also offer opportunities for individuals to
travel for leisure, again encouraging spend in local
businesses along and connected by the route.
6.11. Islands
Communities
There are no adverse impacts.
6.12. The Rights of the
Child (UNCRC)
Active travel is the most accessible mode of travel to
young people, as it does not have any minimum age
limits, does not require any form of licence, is free to
use and is not tied to any fixed timetable.
All new active travel infrastructure is designed to be
utilised by an unaccompanied 12 year old.
Engagement feedback demonstrates even stronger
support for the delivery of the Helensburgh – Cardross
– Dumbarton Cyclepath from younger members of the
community than the already high overall level of
community support. Wider engagement with school
pupils indicates that the vast majority of pupils strongly
support the provision of new active travel infrastructure,
even where it would adversely impact other modes of
transport.   
Kirsty Flanagan
Executive Director with the responsibility for Development and Economic
Growth 
Policy Lead: Cllr John Armour 
28 November 2025                                                  
For further information contact:  Colin Young   
Strategic Transportation Delivery Officer   
Colin.Young@argyll-bute.gov.uk

Page 11

APPENDICES 
Appendix 1: Helensburgh, Cardross & Dumbarton Cyclepath Programme
Appendix 2: Revised Concept General Arrangement Drawing for Junction of A814 /
Ferry Road / Craigend Road.