Page 1

ARGYLL AND BUTE COUNCIL                      ENVIRONMENT, DEVELOPMENT AND   
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             2 JUNE 2022
SERVICES                     
ROADS AND INFRASTRUCTURE PROJECTS – COUNCIL FUNDED 
1.0 EXECUTIVE SUMMARY 
1.1 This report provides Members with an update on schemes being taken forward
by the Roads and Infrastructure Service which are substantially funded by budget
allocations from the Council, as opposed to the other projects report on the
agenda which provides detail on projects being taken forward with the benefit of
external funding. 
RECOMMENDATIONS 
It is recommended that Members of the Environment, Development and
Infrastructure Committee: 
i. Endorse the overall programme of council funded projects being taken
forward by Roads and Infrastructure Services. 
ii. Note that a programme of street lighting column replacements will be
brought to the Environment, Development and Infrastructure Committee in
September 2022.

Page 2

ARGYLL AND BUTE COUNCIL                      ENVIRONMENT, DEVELOPMENT AND   
INFRASTRUCTURE COMMITTEE 
ROADS AND INFRASTRUCTURE                             2 JUNE 2022
SERVICES                     
ROADS AND INFRASTRUCTURE PROJECTS – COUNCIL FUNDED 
2.0 INTRODUCTION 
2.1  The report set out below provides Members of the Environment, Development
and Infrastructure Committee with information on the projects and schemes being
taken forward by the Roads and Infrastructure Service, funded by the Council. 
3.0  RECOMMENDATIONS 
It is recommended that Members of the Environment, Development and
Infrastructure Committee: 
i. Endorse the overall programme of council funded projects being taken
forward by Roads and Infrastructure Services. 
ii. Note that a programme of street lighting column replacements will be
brought to the Environment, Development and Infrastructure Committee in
September 2022. 
4.0 DETAIL 
4.1 COUNCIL FUNDED PROJECT SUCCESSES 2021/22 
Project
name
Investment Comments
Roads
reconstruction
programme
£10million  2021/22 Improvements to the road network,
supporting the local economy, tourism etc. 
More than 140 separate schemes across Argyll
and Bute
Footway and
active travel
routes
£500,000 Improvements to footways across the area
Modernised
parking
payment 
£200,000 Providing chip and pin options as well as cash

Page 3

We now have 64 parking terminals which offer
multi payment options.
Glengorm
landfill cell
and waste
transfer
station
£1million New cell at the landfill site on Mull and
conversion of existing building to transfer
station. 
Securing the future efficiency of general waste
collections on Mull up to the landfill ban in 2025,
and providing efficient method to take material
off the island for onward processing. 
4.2 ONGOING PROJECTS  
Project name Investment Comments
Roads
reconstruction
programme
£8million  2022/23 programme Improvements to the road
network, supporting the local economy, tourism
etc.   
Specific detail on this year’s programme is a
separate item on this committee agenda. 
Footway and
active travel
routes 
£500,000 Programme being developed which will be
reported to the September ED&I Committee. 
Route
optimisation
£100,000+ Project to use technology to provide efficiencies
in vehicle routing and customer
information/feedback on bin collections, with a
view to expanding later to other works
programming like gully cleaning, asset
inspections etc. A procurement process is
currently underway for this project with tender
returns being assessed at the time of writing this
report.
Public
conveniences
£100,000 Scheme to install charging infrastructure at
high-use PCs to help offset the cost of providing
PCs, which are non-statutory. 
Tender returns expected 20 May – will provide
verbal update at meeting.
Bute sea wall Circa
£1million
Sea wall was damaged in storms December
2021. 
The team had to act immediately to put a
temporary solution in place to protect the public
road, utilities and nearby houses. 
This scheme will see a total replacement to
modern design standards. Ongoing work
seeking permissions and consents for the
permanent works which will be tendered.

Page 4

Lochgilphead
depot
rationalisation
TBC Following the Oban model to reduce operating
costs and open up land for development. 
This project is currently in the design and
costing stage. 
LED project Circa.
£4million
Final 1,000 LED replacements (total stock
c14,000). 
This will complete the LED replacement
programme which was paused as a result of
COVID. 
Replacing all streetlights with energy efficient
LEDs means a huge reduction in costs and
carbon footprint. 
Residual funds within the LED budget will be
utilised for column and cable replacement.
Streetlighting
column
replacement
£300,000 At the budget meeting on 24 February 2022, the
Council allocated £300k to deliver a programme
of street lighting column replacement and
improvement across Argyll and Bute, prioritised
based on condition, with funding for at least 260
lighting columns. 
A works programme is being developed which
will cover the residual funding from the LED
project and this £300k column replacement fund
which will be reported to the September ED&I
Committee. These works will be prioritised
based on asset condition and need.
Sign
replacements
£200,000 At the Council meeting on 24 June 2021, the
Council allocated £200k to replace street litter
bins and key road signage. This was intended to
help reduce future budget pressures for
replacements of bins and signs and would also
help to enhance the streetscape and general
appearance of the area by refreshing the street
furniture. 
This funding has focused on replacing signage
assets based on condition and road hierarchy,
with a focus on directional and speed signage
(and where required the posts supporting
signs). 
We have been able to replace signs which were
faded and rusted, work which we would not
otherwise have been able to do through existing
budgets.

Page 5

Costs vary according to the size of signs and
what other infrastructure is required 
The available funding has provided for a
package of nearly 500 new signs across the
Council area. 
The programme of installations is progressing
will in the western areas (OLI and MAKI), and
signs are on order for the eastern areas (BC
and HL). 
Note that in line with Council policy and
directional or place name signs will be dual
language with English and Gaelic. 
Public bin
replacements
£100,000 At the budget meeting on 24 February 2022, the
Council allocated £100k for a litter bin
replacement programme and infrastructure,
providing new/better bins across the area where
required due to condition/need and with a focus
on town centres and prominent locations, to
support cleaner communities.   
The bin programme will focus on bin
replacements and where possible combining
multiple bins to improve the street scape, with a
view to supporting and managing
staycation/increased visitor numbers. 
Where possible the replacement bins will be
240L wheel bins contained in a ‘street cabinet’
similar to those installed in Oban town centre.
These are better bins which increase capacity
for some of the older bins and ease loading
where wheeled bin can be contained within the
street cabinets (which look more attractive and
are not susceptible to blowing around in a storm
unlike empty wheeled bins). 
Funding spilt evenly across the four
administrative areas. At market prices available
in February this had been assumed to provide
49 bins per area (196 across Argyll and Bute). 
Recently we have seen prices increases across
a whole range of sectors – the current estimate
is that the £100k budget will now provide a total
of 156 bins in total. This is a reduction on the

Page 6

numbers estimated in February when the
budget was allocated.
Marine
Projects 
Over
£10million
funded
through
agreed
Marine Asset
Management
Plan
Various on-going projects which will be reported
to the Harbour Board in detailed update on the
asset management plan. 
5.0 CONCLUSION 
5.1 The Roads and Infrastructure Service is engaged in a range of council funded
schemes which will support and maintain key infrastructure and develop and
support service delivery, all of which contributes to the sustainable economic
growth and success of the region. 
6.0 IMPLICATIONS 
6.1 Policy – projects are being taken forward to align with key policies like the Local
Outcome Improvement Plan and the Roads Asset Management Plan 
6.2 Financial – from existing and allocated budgets 
6.3  Legal – the Council has statutory duties to maintain infrastructure set out in
various legislation like the Roads Scotland Act 1984 
6.4  HR – none known 
6.5  Fairer Scotland Duty: 
6.5.1   Equalities - protected characteristics – none known
6.5.2   Socio-economic Duty – none known
6.5.3 Islands – none known 
6.6 Climate Change – a number of these schemes, particularly the LED project,
contribute to the Council’s climate change objectives 
6.7  Risk – none known 
6.8  Customer Service - none 
Executive Director with responsibility for Roads and Infrastructure Services:
Kirsty Flanagan 
Policy Lead for Roads and Transport: Councillor Andrew Kain

Page 7

Policy Lead for Climate Change and Environment Services: Councillor Ross
Moreland 
24 May 2022                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services