Roads Capital Reconstruction Programme 202223 Update Appendix 1
Argyll and Bute Council · 2 June 2022
Back to Environment, Development and Infrastructure Committee — 2 June 2022 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
Roads Reconstruction Capital Programme £2,621,610 £2,972,850 AREA COMMITTEE PAPERS £1,406,200 £999,340 £8,000,000 MID-ARGYLL , KINTYRE and ISLANDS £2,621,610 Area Budget allocated Mid ARGYLL A819 Electric Cottage - Widening and re- alignmant PH1 & PH2 (CARRY OVER) £100,000 Wall repairs and site clearance only £46k - 2021-22 ( await access ) £100,000 District Total carry over 2021-22 A816 Cairnbaan Corner £30,000 Pre SD & Surface Dress U71 Park Road Ardrishaig £16,000 Pre SD & Surface Dress U54 Glenfyne Ardrishaig £16,000 Pre SD & Surface Dress UC20/21 Kilmartin School Loop £33,000 Pre SD & Surface Dress B8025 A816 Junt. - Cross roads £70,000 Pre SD & Surface Dress ROADS RECONSTRUCTION PROGRAMME 2022-23 MID-ARGYLL , KINTYRE and ISLANDS Programme 2022-23 Provisional £8.0M Scheme List 2022/23 - from Scheme Manager RCI & Strategic Schemes Additional Schemes from "Future Years". OBAN , LORN and the ISLES Programme 2022-23 BUTE and COWAL Programme 2022-23 Ver. 1 - 8th December 2021 ( Budget £5.0M provisional) Ver 2a - e Dec - Feb (Budget £5.0M plus £2M prov. ) Ver. 3a - d - 28th February 2022 ( Carry over £969K separate with Original Budget £4.378M + £2.653 Additional) HELENSBURGH and LOMOND Programme 2022-23 ANNUAL ALLOCATION Appendix 1
Page 2
A816 Barrichbeyan Bends £150,000 Widen, Regulate & overlay (potential = STTS co funding £150k ) A819 Electric Cottage - Widening and re- alignmant PH2 (Balance funding) £50,000 Earthworks and carrigeway widening £50k plus £100k carryover = STTS £150K tbc B8024 A83 JCT - Achabraid £52,869 Geogrid & Overlay (poss. STTS Bid) + £200k SSE Full Scheme Possible £750k plus U Class Inveraray Housing Scheme £30,000 Inlay U18 Drimvore - Crinan Ferry £110,000 Structural Overlay / Patching B8025 Gallachoille £45,000 Pre SD Patching 2023 C38 Barmalloch £50,000 Structural Overlay / Patching C65 Inveraray Pier Carpark £35,000 Inlay C67 Lorne Street £31,402 Inlay £719,271 District Total 2022-23 Budget KINTYRE B8001 Claonaig Ferry - Stabilisation of slope - (CARRY OVER) £342,000 Design to be finalised £342,000 District Total carry over 2021-22 B8024 Glenralloch Ph 2 £71,000 Geogrid & Overlay (poss. STTS Bid additional £165k tbc ) - Clachan Village Loop £96,000 Pre SD & Surface Dress - Saddell £12,000 Pre SD & Surface Dress - New Peninver Housing Scheme £8,000 Pre SD & Surface Dress - Southend £59,000 Pre SD & Surface Dress U17 Gobbagrennan £100,000 Pre SD Patching B842 Southend £50,000 Overlay B843 Drumlemble £51,869 Structural Overlay / Patching U17 Gobbagrennan £90,000 Pre SD Patching U10 Glenbreckrie £70,000 Structural Overlay / Patching U18 Tangy £40,000 Structural Overlay / Patching U17 Calton Hill £50,000 inlay B843 Drumlemble ( ph2) £21,402 Drainage improvements
Page 3
£719,271 District Total 2022-23 Budget ISLANDS A846 East Lodge - Bridgend £125,000 Pre SD & Surface Dress A846 Jura Three Arch Bridge to Leargybreck £50,000 Pre SD Patching B8016 North of Laggan Bridge - Strengthening £210,442 Suspended Road over peat base formation A846 Bridgend £40,000 Inlay A847 Blue Houses - Mart Bridgend £36,000 Structural Patching & Drainage C17 Oa Road - Cragabus £74,626 Regulate & Overlay B8016 High Road - North of Glenegedale £89,000 Regulate + Overlay U45 Port Wemyss £40,000 Regulate + Overlay U27 & U54 Mansfield £76,000 Inlay £741,068 District Total 2022-23 Budget OBAN , LORN and the ISLES £2,972,850 Area Budget allocated LORN - Pulpit Rock - Oban - Inlay after S.L. (CARRY OVER) £40,000 £40,000 District Total carry over 2021-22 C29 Inverinan - Kilchrennan £50,000 Surface Dressing (Pre SD completed 2020-2021) - South Shian Roads £150,000 Surface Dressing (Pre SD completed 2020-2021) A816 Blaran £150,000 Embankment strengthening, C/W widening & overlay (STTS Bid) A816 Kilininver £100,000 Strengthening & overlay (STTS Bid) B845 Inveresragan £42,765 Regulate + Overlay C29 Loch Avich Narrachan £120,000 Strengthening & overlay C63 / C28 Bridge of Orchy £100,000 Regulate + Overlay ROADS RECONSTRUCTION PROGRAMME 2022-23
Page 4
U37 Salachail £30,000 Regulate + Overlay Connell Village PH2 £40,000 Inlay U27 Airds Bay £20,000 Inlay U57 Ulva Road £20,000 Inlay U98 Villa Road £20,000 Inlay B845 Blarcreen - Bonawe £70,000 Regulate + Overlay A816 Soroba Road - Argyll Sq £50,000 Inlay U25 Muasdale Rd £40,000 Regulate + Overlay U63 Monument Hill £30,000 Regulate + Overlay U15 Duncraggin Road £30,000 Inlay U56 Kerrera £80,000 Regulate + Overlay U98 Balindoe £20,000 Regulate + Overlay A819 Claddich Jct £80,000 Widening & Overlay - North Shian Roads £110,702 Regulate + Overlay £1,353,467 District Total 2022-23 Budget ISLES C68 Breadalbane Street - Tobermory - Wall (CARRY OVER) £414,000 Design and land access delay B8072 Coll , Cranaig Junction-Sorisdale (CARRY OVER) £58,000 Ferry and Weather logistic delays £472,000 District Total carry over 2021-22 A848 Tobermory - Gulan Dubh £150,000 Surface Dressing B8073 Burg - Kilninian £61,000 Regulate & overlay C46 Glenbellart £126,000 Regulate & overlay - Tiree various locations. £100,000 Regulate & overlay B8035 Tiroran £55,000 Regulate & overlay C48 Carsaig £70,000 Regulate & overlay U14 Grasspoint £50,000 Regulate & overlay U6 Croig £24,000 Regulate & overlay - Tobermory Village £53,535 Inlay C47 Glengorm £40,000 Regulate & overlay B8073 Calgary £40,000 Regulate & overlay B8035 Knock £50,000 Regulate & overlay
Page 5
B8073 Ulva - Torloisk £100,000 Regulate & overlay A849 /A848 Craignure - Tobermory £87,848 Pre S/D for 2023-24 B8071/2/3 Coll Roads ph 2 (with C/O) £100,000 Regulate & overlay £1,107,383 District Total 2022-23 Budget BUTE and COWAL £1,406,200 Area Budget allocated BUTE A866 Rhubodach - Port Bannatyne £60,000 Surface Dressing U4 Ardmory Road £20,000 Inlay A866 Ambrismore - Ardscalpsie £150,000 Regulate + Overlay UC24 Crichton Road (Ardencraig Road - Albany Road) £32,680 Inlay UC05 Clate Point - Kildavanan £90,000 Regulate + Overlay C1 Bruchaig Road £50,000 Regulate + Overlay B878 Russell Street £19,180 Inlay £421,860 District Total 2022-23 Budget COWAL A815 Whistlefield - Invernoaden £170,000 Pre SD & Surface Dressing A886 Leanach - Stabilisation of Slope £400,000 Slope Stabilisation and Carrigeway repairs UC19 Coustoun Road Colintraive £42,920 Regulate + Overlay A8003 Glen Caladh - Bennien Mor £130,000 Edge strengthening & overlay ( poss STTS bid ) B839 Pole Farm - Inveronich £60,000 Regulate + Overlay C60 Argyll Road - Argyll Street - Park Road £50,000 Inlay U22 Mill Cottage - Lower Camquart £45,000 Regulate + Overlay U56 Kyles View Colintraive £15,000 Inlay B828 Glen Mor £31,420 Regulate + Overlay B8042 Victoria Road £40,000 Inlay ROADS RECONSTRUCTION PROGRAMME 2022-23
Page 6
£984,340 District Total 2022-23 Budget HELENSBURGH and LOMOND £999,340 Area Budget allocated U197 Machrie Drive -Helensburgh ( CARRY OVER) £15,000 Delay awaiting utility upgrade £15,000 District Total carry over 2021-22 U012 Ardencaple Drive £40,000 Pre SD & Surface Dressing U191 Loch Drive £40,000 Pre SD & Surface Dressing U Roads Garelochead £110,000 Pre SD & Surface Dressing A814 Cardross - Westerhill £80,000 Inlay A818 Luss Road £90,000 Inlay A814 Glen Douglas JCT - Arrochar £34,920 Culvert Upgrade & Ditching Phase1 B833 Rockville £75,000 Regulate & Overlay U157 James Street Helensburgh £50,000 Inlay U320 William Street Helensburgh £30,000 Inlay U282 Sutherland Street £23,000 Inlay - Tarbet Roads £40,000 Inlay U118 Fraser Avenue £25,000 Inlay B833 Mambeg £100,000 Regulate & Overlay U247 School Road Kilcreagan (Barbour - Shore Road) £100,000 Inlay B872 Whistlefield Road Garelochhead (Viewpoint - Smiddy) £96,420 Inlay U149 Ardmore £50,000 Overlay £984,340 District Total 2022-23 Budget ROADS RECONSTRUCTION PROGRAMME 2022-23 Helensburgh & Lomond